why are there no payment clauses in my GSA schedule


Recommended Posts

I am relying on the contracts clauses link on my schedule on GSA elibrary. 52.232-37 is the only payments clause listed. In times past, 52.212-4 was in GSA contracts. It is not in this contract,

I am reading 52.232-37 to mean that the ordering agency must include payment provisions in the task order. There are no FAR or agency clauses on payments included in the task order. There is a general statement that invoices may be presented monthly, in arrears.

My issue is whether partial payments for ODCs are permitted by the contract, or if ODCs must be delivered and accepted before being invoiced. The ODCs are bundled into one very large CLIN, with a unit of measure called "LT," which I take to mean "Lot," as it can't mean liter in the context. This would require contractor to finance all of the ODCs on the contract for one full year before invoicing, it seems? So contractor would like to request some kind of provision for partial payment, which I suppose means requesting partial payments

Link to comment
Share on other sites

If the task order hasn’t been issued, suggest contacting the applicable ordering agency…

Same thing if it has already been issued.

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...