Contractor's total allowable cost is going to exceed the target cost on our CPIF contract. How do we adjust the contract value without changing the target cost to comply with the limitation of cost and funds clauses for obligation purposes? Right now our contract value is the target cost. Target cost cannot be increased without an equitable adjustment.