Jump to content

ji20874

Members
  • Posts

    3,745
  • Joined

  • Last visited

Posts posted by ji20874

  1. The original poster needs to read the clause at FAR 52.244-2.  The paragraphs that discuss when consent is needed are (b), (c)(1), (c)(2), and (d).

    Para. (b) and para. (d) are inapplicable here.

    We can’t tell whether (c)(1) or (c)(2) applies because we don’t the answer to the questions that retreaded asked.  

    But I think the answer to the question that was asked is NO, because consent to subcontract is never required for a modification that merely takes an existing subcontract from below the SAT to above the SAT.  If consent is required, it will be because—

    • (A) the modification is bilateral*; and 
    • (B) the modification itself is reached by para. (c)(1) or (c)(2) of the clause.

    *A bilateral modification is a contract, as contract is defined in FAR subpart 2.1 and used in 52.244-2.

  2. 4 minutes ago, bob7947 said:

    Should there be a point where we decide that he/she is nonresponsive to our request for information and close the topic?  Should there be some time period in which we ask questions and then provide the OP with a deadline to respond to our questions?

    Maybe.  That will require heavier moderation than in the past.  If so, the time period should probably be measured in days rather than hours.  Sometimes, someone will make a very useful comment on a thread that has been inactive for weeks or months — I would hate to lose that.

    I think original posters don’t respond to questions for several reasons, including—

    1.  They already have an answer;

    2.  They don’t understand or see the relevance of the question;

    3.  They might perceive the question as a challenge or a trap;

    4.  They want to keep things vague because they don’t want the thread being identified with them;

    5.  They don’t want to take sides or get involved in a spat;

    6.  They’re afraid to show a lack of knowledge; or

    7.  The questioner is coming on too strongly.  

  3. Wifcon threads are like water cooler discussions -- someone shares something, and someone else offers a thought -- it's called conversation.  Sometimes the thoughts are right on, and sometimes they aren't but they cause the original poster to think. 

    • OP:  I have a headache.
    • R:  It's probably the new fluorescent lighting.
    • OP:  No, I don't think so.  I was on vacation last week in the outdoors, and had it then, too.
    • R:  Oh, maybe you have allergies.
    • OP:  Maybe.  If I still have the headache tomorrow, I'll go to the clinic.
    • R:  Best wishes.

    "R" shared some thoughts, and maybe those thoughts caused "OP" to reflect and explore.  If another respondent "R2" wants to get involved and share some thoughts that support or differ from "R", that's also welcome -- maybe "R2" offers a similar or a different opinion.  Either way, "OP" can take what he hears from all respondents and make a better informed decision, or at least be a little better prepared for further discussions within his or her own office.  It would be sad if "R2" hollered at "R," castigated "R" for providing a diagnosis without a medical degree, and tried to bully "R" out of the discussion thread.

  4. Well, you could do both (attach to invoice and put in the shipping box), or you could ask the contracting officer.  Or, you could read the appropriate clause of the contract and do what it says.  For example, if your contract includes the clause at FAR 52.246-15, Certificate of Conformance, paragraphs (a) and (b) provide instructions.

  5. Record the facts in CPARS.

    Did the contract constitute a bailment?  Reduce the contract price to reflect the value of the lost property.  

    Reduce the contract price to reflect the contractor's unsuccessful performance.  

    You don't need a pre-determined calculation method.  The contracting officer can pick what he or she thinks is a reasonable reduction -- if the contractor doesn't like the reduction, it can file a claim to get a different reduction.

    Send a cure notice and be ready to terminate for default or cause.

    Start a suspension or debarment action.

    These are just some possibilities in no particular order for you to consider.  For sure, read the contract.

  6. I think ibn battuta (pbuh) is making this too hard.  I don't want to stir his ire, but I really don't think a discussion of voluntary versus gratuitous services is needed for this situation.  I haven't read the contract and I haven't read the offeror's notice under para. (i)(2) of the contract clause at FAR 52.214-1 with its Alt. I, but the submitter said the contractor intended to complete its contract obligations within the ceiling price.  If that's what the contractor said in its notice, and its promise was unambiguous, I think we can rely on it.  The contractor is not being asked to do any additional services -- the services it will do are already promised under the contract.  The contractor wants to complete rather than letting the contract die or face a termination for convenience (a real possibility if it insisted on more money).  The contract does not say the contractor must stop work when it reaches the ceiling price; rather, it says the contractor "...shall not be obligated to continue performance..."  I think the offeror can choose to continue performance, if it wants to.

    So I see the notice (if it unambiguously makes the promise) as the contractor's pledge that it will complete its contract obligations without charging the Government beyond the ceiling price, and a waiver of its privilege of stopping work.  If the contractor incurs costs in excess of the ceiling price, the clause does not say the Government must stop the work; rather, it simply says that the Government will not be obligated to pay any amount in excess of the ceiling price.  I am in favor or reading the contract, and doing what the contract says.

    The submitter said the ceiling price is in the low 10 digits and the overrun might be in the six digits -- an overrun of $100,000 (six digits) on a a ceiling price of $10,000,000 (ten digits) is one percent.  Big deal.  I would not call these gratuitous services.  There is no anti-deficiency act problem.  There is no freebie.  The contractor is simply fulfilling its contractual duties. 

    If the contractor's notice is wishy-washy, you might want to ask for its firm promise to perform all of its contract obligations within the ceiling price.

    At least, that's my perspective, offered to the original submitter.

  7. I wouldn’t.

    Ideally, you would have obligated only funds for the option quantities you exercised, and not for any option quantities you didn’t exercise.  In such a case, your question would be moot.

    Based only on what I read in the original posting, I would think that your deobligation mod should be a unilateral administrative mod.

  8. If the offeror invoices for the ceiling price, and can validate it that it has worked all the hours it charges, then that is what the Government pays.

    You accept the services because they are required by the contract.  They are required services, not voluntary services.

    You did not contract for a certain number of hours — you contracted for a job with a ceiling price, and you agreed to pay contractor invoices monthly or bi-weekly provided the hours were actually worked up to the ceiling price.  If the contractor charges 100 hours to your contract, you pay for 100 hours.  If the contractor charges an additional 10 hours somewhere else or declares it a loss, what do you care?  Pay the 100 hours and give the contractor an Exceptional CPARS rating.  If the contractor invoices for 100 hours, you cannot pay for 110 hours.

  9. A contractor exceeds the ceiling price at its own risk.

    A contractor who fails to give the Government the notice it promised to give before approaching the ceiling price robs the Government of the opportunity or space to make a decision on finding more money or curtailing the work — by keeping silent and continuing to incur costs, and then seeking reimbursement for those costs, the contractor robs the Government.  The boards and courts have strictly enforced the notice requirement and refused payment to contractors for these reasons.

    You failed in your contractual commitment to give timely notice of the impending overrun.  You have no entitlement.  The Government’s CPARS report (if your contract is eligible for CPARS) should reflect your failure to comply with the contract and your cost overrun.

    This would be my starting point if I were the contracting officer.

  10. Re:  Rule of Two.  Please remember that the rule of two is wholly inapplicable to procurements under FAR subpart 8.4 using federal supply schedules and FAR 16.505(b) ordering against multiple-award IDIQ contracts.  So please do not push for set-asides based on the rule of two in these circumstances — in both circumstances, the FAR leaves it entirely to the contracting officer’s discretion and you will want to respect that discretion.  [Note: This assumes the parent multiple-award contracts do not have rule of two language in their ordering instructions — this is permitted, but in my experience very few contracts contain such language.]

  11. On 1/23/2020 at 10:25 AM, aordway said:

    Let's say I have a firm-fixed-price contract to buy 5  t-shirts for $100 total. After delivery of the 5 t-shirts, the contractor invoices for $90, and indicates that they have submitted their final invoice and will not be invoicing for the remaining $10 (it seems illogical that they would not bill for the full price they are owed, but this seems to happen frequently nonetheless). By the contractor stating they only want to be paid $90 instead of $100, it seems like we have a supplemental agreement for the contract.  Not only do we have $10 excess funds obligated to the contract, but the contract price has changed from $100 to $90. If we skip doing a deobligation mod on the contract to remove that $10, that also means we are not adjusting the price in the contract to the new agreed upon $90. Therefore the Government has created a back alley agreement with the contractor on a new contract price, but has not officially recognized that new agreement via an official contract document. The contract stating a firm-fixed-price of $100 is not accurate to what is occurring in the real world.

    What is the necessity for modifying the contract price in this situation? Must it be done so that the contract document's stated price matches what the Contractor has agreed to accept as final payment? 

    FACT ONE:  The contract price is $100.

    FACT TWO:  The contractor invoiced for $90.

    Fact Two does not change Fact One.  Or, in other words, Fact One is not changed by Fact Two.

    You most assuredly do not have a supplemental agreement to change the price.  There is no new agreement.

    You can simply close out the contract file and deobligate the excess funds IAW FAR subpart 4.8 (or let your agency’s <$1,000 automated process do the deobligation).

    The contract price was and still is $100.  The contractor invoiced for less than that.  Treat it like a discount.  This has been happening for many years and was easily handled with human finance specialists.  Do you do a supplemental agreement when your paying office takes a prompt payment discount?  No.

    That said, your agency’s automated systems might be too dimwitted to recognize this reality.  If your agency’s automated systems require a mod to change the price (so that the obligated amount = price = paid amount), you can do a unilateral administrative close-out modification with a note that the CLIN 001 price is changed from $100 to $90 to reflect the contractor’s invoiced amount, and that the likelihood of the contractor seeking the deobligated amount is essentially zero, so the modification (1) is done solely to make the automated systems happy; and (2) does not change any of the rights or obligations of the parties.  I have done these mods.  Since they are unilateral administrative close-out mods, the contractor never sees them.

    Think about this is a cost-reimbursement setting.  If CLIN 001 has an estimated cost of $90 and a fixed fee of $10 (for a price of $100) and the contractor completes the work at $85 cost, do you do a mod to lower the estimated cost by supplemental agreement?  No.  The agreed estimated cost was and still is $90 — you pay the contractor $95 ($85 cost + $10 fixed fee) and you unilaterally and administratively deobligate the excess funds.

     

  12. ibn battuta,

    Hmmm, a few days ago, you refused to discuss definitions.  I'm glad you're more open now.  Below are some quotes from GAO bid protest decisions where GAO uses the word "subjective."  I think my use the word is the same as the GAO's.  I hope these are helpful to you in your continuous learning...

    • The determination of the relative merits of proposals is the responsibility of the agency that solicited them, and requires weighing competing subjective considerations and exercising sound discretion...
    • For the most part, the evaluative conclusions to which Price Waterhouse objects are precisely the type of subjective judgments reserved to contracting officials, not our Office...
    • The evaluation of past performance, by its very nature, is subjective...
    • The protester primarily challenges the differences in the findings between the SSEB and SSAC and contends that the SSA should have adopted the findings of the SSEB with regard to the evaluation of its proposal, rather than the SSAC’s evaluation, which the protester argued was “subjective” and unreasonable.
    • Finally, the solicitation advised offerors that the agency intended to make the source selection decision without conducting discussions and noted that the best value evaluation is, in and of itself, a subjective assessment by the Government.”
    • When conducting a best-value tradeoff analysis . . . an agency may not simply rely on the assigned adjectival ratings to determine which proposal offers the best value because evaluation scores–whether they are numerical scores, colors, or adjectival ratings–are merely guides to intelligent decision-making and often reflect the disparate, subjective judgments of the evaluators...

    GAO testimony before a House subcommittee...

    • Procuring agencies are obligated to conduct proposal evaluations in accordance with the evaluation scheme set forth in the solicitation. Such proposal evaluation judgments are by their nature often subjective; nevertheless, the exercise of these judgments in the evaluation of proposals must be reasonable and must bear a rational relationship to the announced criteria upon which the successful competitor is to be selected...
  13. On 1/17/2020 at 8:35 PM, formerfed said:

    Might an evaluators confidence rating be an example of what you’re talking about?  I can see that subjectivity plays into assessing how well an offeror understands the requirement, the degree of soundness in a technical approach, and the likelihood of success.  

    Yes.  Really, most of our evaluations and selections are more subjective than objective, and I am okay with that.  A point scheme may seem objective (85 is better than 75, right?), but it might be just a veneer.  If a company got 40 out of 50 points for factor one, 30 out of 30 points for factor two, and 15 out of 20 points for factor three, for a total of 85 points, well, assigning 40 instead of 38 or 42 was probably a subjective process in the first place.   Truly objective evaluations and selections can be done, but I think most major acquisitions are really subjective (even if there is an objective veneer).  Really, I don’t like veneers — I much prefer honesty, so I am okay with admitting that there is real subjectivity in our evaluation and selection processes.  Subjectivity is not inherently bad — it can be professional, legitimate, honorable, and so forth.  Subjectivity is a positive value that acquisition professionals bring to the table.  

  14. 1 hour ago, Guardian said:

    ...we are proposing to apply an immediate comparative analysis in both phases one and two...

    That’s fine.  The process may become cumbersome with too many offers or factors, but there is no defined cut-off.  I hope it works for you.

    I wouldn’t try to use numerical points — just subjective comparative assessments with a tradeoff inherent in the process.  But that’s me.

  15. Don,

    Of my numbered statements 1. through 5. reflecting my thought process, which do you judge as untrue?

    Earlier in this thread, I asked you a question and you haven’t answered it yet.  Will you answer it now?

    T   F   FAR 16.505(b)(1) repeatedly uses the word “notice” and never uses the word “solicitation” to describe a fair opportunity announcement.

    And one more?  It also has been asked, but you haven’t answered it yet.

    Y     N     In your own practice, do you insert the Bankruptcy clause in every fair opportunity notice exceeding the SAT (even though the clause is already included in the parent contract and will be applicable to the order regardless of whether or not you insert the clause in the notice)?

    You err in providing the reason that I will have not answered your question.  You really shouldn’t put words in my mouth.  Your question has a flawed premise, and answering your question with a simple yes or no (as you demanded) would not provide for an honest discussion.  

    But please answer my questions above — that actually will help us have an honest discussion.

    If you tell me which of the five statements is offending you, and why, I am hopeful that I can resolve your concern and assuage your animus.

    If you answer TRUE to the FAR text question, I am hopeful we will have found common ground.  If you answer FALSE to that question, we will be miles apart.

    If you answer YES to the bankruptcy clause question, we will have a difference of opinion — you do what you need to do in your practice, and me in mine.  If you answer NO, I will be glad you aren’t wasting ink and paper but it will seem inconsistent with your insistence that a notice is a solicitation.

×
×
  • Create New...