|
NCI argues that the Army improperly based its IGCE on
Lockheed’s performance of the incumbent contract. In this
regard, the protester argues that the agency viewed Lockheed’s
proposed technical approach as the “baseline” for the
government’s requirements, and that all other offerors were
penalized for deviating from that baseline.
We review challenges to government estimates for
reasonableness. See Division Laundry and Cleaners, Inc.,
B-311242, May 19, 2008, 2008 CPD ¶ 97 at 3; OMNI Gov’t Servs.,
LP, B-297240.2 et al., Mar. 22, 2006, 2006 CPD ¶ 56 at 3. A
protester’s mere disagreement with an agency’s basis for
developing an IGCE provides no basis to sustain a protest.
As discussed above, the IGCE consisted of the Army’s estimate
that the task order would require 70 FTEs, at a cost of $27
million. AR, Tab 20, attach. 3, Price Evaluation Report, at 2.
The agency states that it based the IGCE on two sources of
information that described the work currently being performed
at Fort Benning under the incumbent contract: (1) the C4IM
services list, which was included in the RTOR, and (2) the
table of distribution and allowances (TDA) for the [Army’s
Network Enterprise Center] NEC. Supp. CO Statement at 2-3.
A C4IM is a list of the services provided
to agency IT users on a particular installation that an NEC is
expected to provide. Id. at 3. The CO states that the C4IM
list for Fort Benning was consulted to determine a baseline
for the services required under the task order. Id. The C4IM
list was then compared to the historical workload requirements
for the Fort Benning NEC--under the incumbent contract--to
develop the IGCE. Id.
The TDA is a list detailing the
organizational structure and personnel available for a
particular non-tactical Army unit. Id. The CO states that the
TDA showed that there 146 FTE positions available at Fort
Benning for IT support, 38 of which were assigned to other NEC
contracts, leaving a total of 108 available personnel. From
this figure, the agency subtracted an additional 38 government
civilian employees assigned to work at the NEC, resulting in a
total of 70 FTEs for a contractor to provide. Id. The Army
then compared that C4IM data to the TDA data, and concluded
that 70 FTEs was an appropriate level of staffing for the task
order. Id.
The record here thus shows that the
agency consulted information concerning the level of services
required at the Ft. Benning NEC, as well as the level of
effort provided under the incumbent contract by Lockheed. The
record does not show, as the protester contends, that the
agency simply adopted the technical approach used by Lockheed
under the incumbent contract as the “baseline” for the IGCE.
In any event, the protester provides no
support for its contention that an agency’s IGCE may not rely
on data from an incumbent’s performance of the predecessor
contract. The sole support cited by the NCI for its argument
is our decision in Aegis Defence Services, Ltd., B-403226 et
al., Oct. 1, 2010, 2010 CPD ¶ 238, where we held that a CO
could reasonably ignore an IGCE for purposes of conducting a
price realism analysis of the awardee, based on his
determination that the IGCE relied on data from the incumbent
contract. In that decision, however, we noted that the CO was
concerned that the incumbent contract and IGCE were based on a
completely different technical and cost approach than that
used by the awardee (third country national personnel as
compared to expatriate personnel). Id. at 7. For this reason,
we concluded that the CO could reasonably disregard the IGCE
as irrelevant for purposes of a price realism analysis. Id.
The Aegis Defense Services not stand for the opposite position
advanced by the protester--that a CO is prohibited from
considering an IGCE based on the incumbent’s performance.
On this record, we find no basis to conclude that the Army’s
IGCE was unreasonable, or that it could not be relied upon in
evaluating offerors’ proposals. (NCI
Information Systems, Inc., B-405589, November 23, 2011)
(pdf)
Vizada asserts that the agency failed to conduct a proper price
realism analysis and that Stratos' price was unrealistically
low.
Where, as here, a fixed-price contract is to be awarded, a
solicitation may provide for the use of a price realism analysis
to measure an offeror's understanding of the requirements or to
assess the risk inherent in a proposal. Puglia Eng'g of
California, Inc., B-297413 et al., Jan. 20, 2006, 2006 CPD para.
33 at 6. As our Office has repeatedly held, the depth of an
agency's price realism analysis is a matter within the agency's
discretion. Navistar Def., LLC; BAE Sys., Tactical Vehicle Sys.
LP, B-401865 et al., Dec. 14, 2009, 2009 CPD para. 258 at 17. In
reviewing protests challenging price realism evaluations, our
focus is whether the agency's review was reasonable and
consistent with the terms of the solicitation. Grove Resource
Solutions, Inc., B-296228, B‑296228.2, July 1, 2005, 2005 CPD
para. 133 at 5. As a general matter, it is unobjectionable for
an offeror to submit a below-cost proposal for a fixed-price
contract, since fixed-price contracts generally are not subject
to adjustment during performance, and the contractor, not the
agency, bears the financial risk of cost overruns. Crown Title
Corp., B-298426, Sept. 21, 2006, 2006 CPD para. 145 at 6.
The RFP stated that offerors' fixed-priced proposals would be
evaluated for price realism to determine if there were proposals
that were unrealistic in terms of overall price or reflective of
an inherent lack of management and/or technical competence or
comprehension of the requirements. RFP at 27. In accordance with
the RFP, the agency's price realism analysis started with a
comparison of all offerors' prices to the IGCE. The analysis
revealed that all of the offered prices were significantly less
than the IGCE of $9,838,303. Upon further review of the
proposals, the agency determined that the difference in price
between the IGCE and the offered prices was due to the IGCE's
inclusion of costs for providing dedicated staff for the NOC to
monitor network systems 24 hours a day, 7 days a week; the cost
for dedicated monitoring was not proposed by the offerors. This
resulted in an over-estimation by the IGCE of the costs by
approximately $4.12 million. When the over-estimation was
accounted for, Stratos' low-priced proposal was within 23
percent of the IGCE. Agency Report, Tab 4, Award Memorandum, at
4-5.
Because Stratos' price was significantly lower than the prices
in the other proposals, an additional review of Stratos' price
proposal was undertaken to ascertain if it was unrealistically
low. Based on the agency's review, it appeared that the price
difference resulted from Stratos providing [REDACTED] price for
the contract line item (CLIN) for the NOC. To be certain Stratos
intended [REDACTED] price, and to insure Stratos understood the
requirement, the agency requested that Stratos confirm that it
intended to propose [REDACTED] for this line item. Stratos
confirmed its price of [REDACTED] for the CLIN and indicated its
intent to perform at the offered price. Based on Stratos'
response, the agency concluded that the price was realistic, and
reflected an exercise of business judgment, rather than a lack
of competence, or a lack of understanding the RFP requirements.
Based upon our review of the record, we find that the agency's
analysis of Stratos' price was reasonable and consistent with
the terms of the solicitation. Contrary to Vizada's claims, the
RFP did not require an in-depth CLIN-by-CLIN analysis to the
IGCE or a CLIN-by-CLIN comparison among the offered prices. To
the extent that Vizada believes that Stratos cannot perform the
contract at its proposed price, Vizada's disagreement with the
agency's judgment provides no basis to sustain the protest. See
Team BOS/Naples--Gemmo S.p.A./DelJen, B-298865.3, Dec. 28, 2007,
2008 CPD para. 11 at 14. (Vizada
Inc., B-405251; B-405251.2; B-405251.3, October 5, 2011)
(pdf)
Cost Realism Analysis
The record shows that the Army found that Systek proposed too
few labor hours to perform sample tasks 1 and 2. The Army
evaluators thus made several significant adjustments to Systek's
proposed labor hours, which the cost evaluation team utilized to
calculate the most probable cost of Systek's proposal. Systek
questions the propriety of these labor hour adjustments and the
resulting most probable cost adjustments. Systek argues that the
adjustments were inappropriate and undocumented, and
fundamentally changed its technical approach by allocating a
greater percentage of hours to less qualified employees than
offered in Systek's task order response. Systek also argues that
the agency's reliance on the IGCE in making the most probable
cost adjustments was irrational and represented unequal
treatment because it did not reasonably consider Systek's
technical approach and was not used in evaluating the task order
responses of the other offerors, even though their proposed
staffing widely diverged from the IGCE.
When an agency evaluates proposals for the award of a
cost-reimbursement contract, an offeror's proposed estimated
cost of contract performance is not considered controlling
since, regardless of the costs proposed by the offeror, the
government is bound to pay the contractor its actual and
allowable costs. Metro Mach. Corp., B-295744, B-295744.2, Apr.
21, 2005, 2005 CPD para. 112 at 9; Hanford Envtl. Health Found.,
B-292858.2, B-292858.5, Apr. 7, 2004, 2004 CPD para. 164 at 9.
Consequently, a cost realism analysis must be performed by the
agency to determine the extent to which an offeror's proposed
costs represent what the contract costs are likely to be under
the offeror's technical approach, assuming reasonable economy
and efficiency. Federal Acquisition Regulation (FAR) sections
15.305(a)(1), 15.404-1(d)(1), (2); The Futures Group Int'l,
B‑281274.2, Mar. 3, 1999, 2000 CPD para. 147 at 3.
A cost realism analysis is the process of independently
reviewing and evaluating specific elements of each offeror's
cost estimate to determine whether the estimated proposed cost
elements are realistic for the work to be performed, reflect a
clear understanding of the requirements, and are consistent with
the unique methods of performance and materials described in the
offeror's proposal. FAR sect. 15.404-1(d)(1); Advanced Comms.
Sys., Inc., B-283650 et al., Dec. 16, 1999, 2000 CPD para. 3 at
5. An offeror's proposed costs should be adjusted when
appropriate based on the results of the cost realism analysis.
FAR sect. 15.404-1(d)(2)(ii). Our review of an agency's cost
realism evaluation is limited to determining whether the cost
analysis is reasonably based and not arbitrary. Jacobs COGEMA,
LLC, B-290125.2, B-290125.3, Dec. 18, 2002, 2003 CPD para. 16 at
26.
For sample task 1, offerors were required to develop an
engineering package as part of an effort to engineer, furnish,
install, and test (EFI&T) for a Major Headquarters Command,
Control, Communications, Computers, and intelligence/information
technology relocation project in Germany. The project involved
performing site surveys, and included developing the following
products: the facility wiring and design criteria, a system
design plan, an engineering installation plan, a system
acceptance test plan, and an installation schedule. Although
Systek was rated acceptable technically for this sample task,
and was found to have proposed an adequate labor skill mix for
the task, the evaluators found that Systek had proposed a low
level of hours for completing the detailed engineering and
design related requirements of site surveys, system design plan,
detailed engineering, system acceptance test plan and
installation schedule. The agency therefore found a weakness in
Systek's proposal, and made three significant adjustments to
Systek's proposed labor hours: the facility wiring and design
criteria work was adjusted from 1,852 proposed labor hours to
4,042 labor hours; the detailed engineering work was adjusted
from 916 proposed labor hours to 4,228 labor hours; and the
system acceptance test plan work was adjusted from 702 proposed
labor hours to 2,534 labor hours. AR, Tab 13a, Final Evaluation
Report for Systek, at 4-6; Hearing exh. A.
For sample task 2, offerors were required to develop an
engineering package as part of an EFI&T effort for a new
communication system in Afghanistan to provide wideband digital
connectivity to deployed users in that area of operation. This
system was to consist of two parts: (1) a fixed strategic
satellite communication (SATCOM) system and (2) a new core
backbone network. Again, the evaluators found the task order
response technically acceptable, albeit with a minimally
feasible approach, but with a realistic labor mix. However, the
evaluators found that Systek's response contained the
significant weakness of proposing significantly low hours for
completing three SATCOM system related requirements. As a
result, Systek's proposed labor hours for detailed engineering
were adjusted from 1,000 proposed labor hours to 2,592 labor
hours; SATCOM installation was adjusted from 2,790 proposed
labor hours to 11,250 labor hours; and SATCOM engineering
validation (EV)/acceptance testing (AT) was adjusted from 1,215
proposed labor hours to 5,500 labor hours. AR, Tab 13a, Final
Evaluation Report for Systek, at 6-9; Hearing exh. A.
Here, because the agency report, including contemporaneous
evaluation documentation, did not completely explain the
agency's rationale for making significant adjustments to
Systek's proposed labor hours, our Office conducted a hearing in
this matter. While we generally give little weight to
reevaluations prepared in the heat of the adversarial process,
post-protest explanations that provide a detailed rationale for
contemporaneous conclusions--and as is the case here, simply
fill in previously unrecorded details--will generally be
considered in our review of the rationality of selection
decisions, so long as those explanations are credible and
consistent with the contemporaneous record. Remington Arms Co.,
Inc., B-297374, B-297374.2, Jan. 12, 2006, 2006 CPD para. 32 at
12. As discussed below, based on the contemporaneous record and
credible hearing testimony consistent with the record, we find
the agency's evaluation of the task order responses and cost
realism to be reasonable.
To explain the process that the Army utilized to evaluate the
realism of the offerors' proposed labor hours, including
Systek's, the Army produced five witnesses at the hearing: the
contracting officer, a member of the source selection advisory
council (SSAC), the chair of the sample task evaluation team, a
member of the sample task evaluation team, and a member of the
cost team. The record evidences that the agency witnesses,
particularly those who were responsible for developing the
sample tasks and IGCE and for evaluating the proposals' labor
mixes and labor hours, possessed extensive knowledge and
experience with estimating hours to perform the work required by
the sample task. For example, the SSAC member, who developed the
sample tasks, is a technical director for ISEC, has a degree in
electrical engineering, has worked with ISEC since 1985, and has
been a lead engineer on three major Army moves (in Germany,
Panama, and Puerto Rico). Tr. at 77-79. In addition, the chair
of the sample task evaluation team, who also helped develop the
sample task, is an integration systems engineer with a degree in
electronics engineering; has been a project engineer on SATCOM
installations; has personally performed several installations;
and has overseen, managed and directed personnel doing
installations. Tr. at 87, 105-06, 120-21.
In evaluating Systek's proposal, including the specific labor
hour adjustments made to its proposal, the Army considered
Systek's narrative technical approach, BOE, WBS, project
schedule, and skill mix. See Tr. at 35-36, 113. The witnesses
attributed the significant labor hour adjustments that were made
to Systek's proposal primarily to the lack of detail that the
evaluators found in Systek's responses to these two sample
tasks. See Tr. at 46-50, 80-81, 121‑22, 220. The agency
witnesses testified that while Systek's proposal focused more on
what it would do to meet the sample task requirements, the
agency also sought information about how the offeror would
perform the agency's sample tasks. See Tr. at 80-81, 218-19. The
witnesses testified that this lack of detail increased the
Army's reliance on the IGCE, and that adjustments to Systek's
proposal based on the hours in the IGCE were only made when
there was a lack of sufficient detail in the sample task
responses, such that there was no basis to conclude that an
offer was inconsistent with the approach encompassed in the
"government solution," as set forth in the IGCE. See Tr. at
46-50, 80-81, 113-14, 121‑22, 220. For example, the chair of the
sample team testified "if the contractor or offeror . . .
parroted back what [the contractor document requirements lists]
stated . . . and really didn't give us anything more than that,
we assumed that to be the government solution, and that's when
we would, you know, start using the IGCE as a baseline or
starting point to make adjustments." Tr. at 114.
The Army explains that contrary to the protester's arguments,
these adjustments did not introduce any new labor categories or
significantly alter the distribution of hours per labor
category, and therefore the agency did not change fundamentally
Systek's technical approach or labor mix. An example to
illustrate this point involved the Army's significant adjustment
to Systek's proposed 2,790 labor hours for SATCOM installation
under task order 2, where the chair testified that the proposal
lacked detail for work that the IGCE estimated at 15,000 labor
hours. See Tr. at 113-114, 123. The chair explained that the RFP
required the offeror to describe its approach to conducting each
installation task. See RFP Sample Task 2 at 4; Tr. at 117-20.
The chair also testified that although Systek's response met the
sample task requirements for the SATCOM installation, it did not
include much explanation of how it derived its specific number
of labor hours. Tr. at 121-22. Moreover, in determining that
Systek's proposed labor hours for this work were unrealistically
low, the evaluators specifically considered Systek's labor mix
for this work, which was primarily based on technicians on site,
rather than engineers. Tr. at 127-28. The chair stated that
while 15,000 hours was quite a bit more than 2,790 hours, the
agency did not simply mechanically adjust Systek's hours for
this requirement up to the IGCE level because the agency
understood that its estimate was a conservative estimate for the
work. The chair testified that given that Systek's proposal
reflected a minimally detailed approach, the agency concluded
that 11,250 hours was the right number. The chair explained that
the agency reached this conclusion based on its ISEC experience
and historical data, and the narrative in Systek's proposal,
which did not set out an approach different from what the agency
anticipated in the IGCE. See Tr. at 137-38; Hearing exh. A
By contrast, the chair explained (and our review of the record,
including the proposals, confirms) that the other offerors' (GDIT's,
SAIC's, and NCI's) approaches were more detailed, and gave the
evaluators more confidence that these offerors knew with greater
precision what might be involved in sending a team to
Afghanistan to perform the tasks. See Tr. at 132. Thus, the
evaluators concluded that the proposals of GDIT, SAIC, and NCI
presented less risk. Further, the contracting officer testified
that the evaluators found that the details in these proposals
indicated greater efficiencies and a higher level of
understanding, which gave the agency greater confidence that the
work could be performed with fewer labor hours than the IGCE.
Tr. at 49-50. As an example, the chair discussed the details
included in SAIC's proposal for the Task 2 SATCOM installation,
including the specific training and experience of the personnel
who will perform the installation; the chair also testified that
this level of detail was absent from Systek's proposal. Tr. at
134.
Another example discussed at the hearing was the agency's
adjustment to Sytek's proposed hours for SATCOM EV/AT from 1,215
labor hours to 5,500 labor hours. The IGCE for this requirement
was 6,300 labor hours. Here again, the chair convincingly
explained how Systek's proposal contained minimal detail and did
not offer anything different from the government's approach as
reflected in the IGCE; this conclusion led to the agency's
upward adjustment to Systek's proposed labor hours. See Tr. at
142-45. The chair also explained that the Army did not adjust
the proposal up to the full 6,300 labor hours because the IGCE
included some technical writers and draftspeople that did not
appear relevant to Systek's proposed approach here. See Tr. at
147. While Systek argues that the Army's evaluation did not
account for its use of higher-level technicians, the Army found
that Systek's approach also included lower-level technicians,
which would impact the efficiency at which Systek would be able
to perform the tests; in sum, the Army did not find Systek's low
proposed labor hours to be realistic. See Tr. at 147-49.
On the other hand, the chair testified that NCI, which had
proposed [DELETED] labor hours, was only adjusted up to
[DELETED] labor hours because its proposal included more detail
and offered more [DELETED]. Tr. at 150-53. The chair further
testified that the agency did not adjust SAIC's estimate of
[DELETED] labor hours because the proposal included [DELETED],
and an [DELETED]. See Tr. at 156-58. The chair also testified
that GDIT's estimate of [DELETED] labor hours was accepted
because its proposal was detailed and included [DELETED] for the
requirement. Tr. at 158.
We have reviewed the totality of the agency record, including
contemporaneous documents supporting the labor hour adjustments,
and the testimony of the Army explaining the contemporaneous
evaluation of the proposals, for each labor hour adjustment made
to Systek's proposal. Based on our review, we find that the Army
has reasonably explained the basis for the adjustments made to
Systek's proposed labor hours consistent with the
contemporaneous record. As noted in the testimony above, our
review supports the agency's view that Systek's proposal did not
provide as sufficient a level of detail in response to the
sample tasks as the other offerors, which resulted in a weakness
and a significant weakness being assigned to Systek's proposal,
and the significant adjustments to its proposed labor hours. The
record also shows that the agency, when it made its most
probable cost adjustments, considered Systek's labor mix and
reasonably distributed the added hours across labor categories
included in the task order response. Thus, we see no basis to
find unreasonable the agency's upward adjustments to determine
Systek's most probable cost or the agency's failure to make
similar adjustments to the awardees' proposed costs.
For the record, however, there is one error in the agency's most
probable cost evaluation. In this regard, the agency noted that
Systek had proposed 5,504 labor hours for core backbone network
installation, which was part of task order 2, and that this work
was not within the scope of the requirement. No downward
adjustments were made to Sytek's proposed costs to reflect this
error, but the evaluators assigned a weakness because they
viewed this error as evidence that Systek did not fully
understand the scope of the sample task. The assignment of a
weakness in this case was clearly warranted. However, we think
the agency erred in not eliminating these costs from Systek's
proposal in determining its most probable cost.
As noted above, the purpose of a cost realism analysis is to
determine the extent to which an offeror's proposed costs
represent what the contract costs are likely to be under the
offeror's technical approach. The end product of an agency's
cost realism analysis should be a total evaluated cost of what
the government realistically expects to pay for the offeror's
proposal effort, as it is the agency's evaluated cost and not
the offeror's proposed cost that must be the basis of the source
selection determination. FAR sect. 15.404-1(d)(2)(i). Thus, it
was improper for the Army to include the costs of work that the
government would not receive as part of the task requirement.
See FAR sect. 15.404-1(d)(2)(ii) ("The probable cost is
determined by adusting each offeror's proposed cost . . . to
reflect any additions or reductions in cost elements to
realistic levels based on the results of the cost realism
analysis" (emphasis supplied)); Priority One Servs., Inc.,
B-288836, B-288836.2, Dec. 17, 2001, 2002 CPD para. 79 at 3-4
(protest sustained where agency concludes that protester
misunderstood the requirements for other direct costs; most
probable cost should have been reduced to reflect agency's
judgment as to costs actually to be incurred); Kellogg Brown &
Root Servs., Inc., B-298694 et al., Nov. 16, 2006, 2006 CPD para.
160 at 5-8 (agency properly made downward adjustment to
protester's probable cost where indirect cost rates were
overstated).
Nevertheless, this error provides no basis to sustain the
protest. In this regard, the protester states the total impact
of this error accounted for an additional evaluated cost of
$21,510,737 to its proposal. Protester's Comments at 23. Thus,
even taking into account this error, Systek's lower-rated
proposal would still have the highest evaluated cost of the four
competitive range offerors. Under the circumstances, we do not
think Systek was prejudiced by this error and we will not
disturb the award decision. See Alsalam Aircraft Co.,
B-401298.4, Jan. 8, 2010, 2010 CPD para. 23 at 9-10. (Systems
Technologies, Inc., B-404985; B-404985.2, July 20, 2011)
(pdf)
Labor Rates
MPRI challenges the agency's cost realism analysis, which
resulted in an upward adjustment in its proposed labor rates.
When an agency evaluates proposals for the award of a
cost-reimbursement contract, an offeror's proposed costs are not
considered controlling because, regardless of the costs
proposed, the government is bound to pay all actual, allowable
costs. Federal Acquisition Regulation (FAR) sections
15.305(a)(1); 15.404-1(d). Consequently, an agency must perform
a cost realism analysis to determine the extent to which an
offeror's proposed costs represent what the contract should
cost, assuming reasonable economy and efficiency. FAR sect.
15.404‑1(d)(2); Information Ventures, Inc., B-297276.2 et al.,
Mar. 1, 2006, 2006 CPD para. 45 at 7; Hanford Envtl. Health
Found., B-292858.2, B-292858.5, Apr. 7, 2004, 2004 CPD para. 164
at 8-9. An agency's cost realism analysis requires the exercise
of informed judgment, and we will review this judgment only to
see that it was reasonable. Information Ventures, Inc., supra;
Hanford Envtl. Health Found., supra. While a realism analysis
need not achieve scientific certainty, the methodology employed
must provide some measure of confidence that the agency's
conclusions about the most probable costs under an offeror's
proposal are reasonable and realistic. Information Ventures,
Inc., supra; see Metro Mach. Corp., B-295744; B‑295744.2, Apr.
21, 2005, 2005 CPD para. 112 at 10-11. Here, we find that the
Army's cost realism analysis was not reasonable, and that it
resulted in an excessive upward adjustment to MPRI's proposed
labor rates.
The record shows that the agency initially reviewed offerors'
proposed labor rates for discrepant rates by comparing them to a
range of rates for each position calculated based on one
standard deviation (OSD) from the average of the five offerors'
proposed rates for the position. The agency then further
reviewed the rates based on the circumstances of each offeror,
adjusting some, but not all, of the rates outside the range, as
well as some, but not all, of the rates within the range.
(Table deleted because
the redactions made it useless)
As shown by the chart,
MPRI's proposed labor rates for [REDACTED] of the labor
categories ([REDACTED]) were lower than the OSD range the agency
considered realistic, accounting for [REDACTED] of 275 required
staff as specified in the SOW. MPRI attributed the rate
reduction--on average approximately [REDACTED] percent as
compared to its incumbent contract--to "updating salaries based
on the current market conditions." MPRI Cost Proposal at IV-3.
Based on its realism analysis, the agency determined that the
reduction was not justified and adjusted MPRI's rates for all
five labor categories upward to the rates under MPRI's current
Afghanistan mentoring contract. This actually left three of the
five resulting rates higher than the OSD range.
Likewise, notwithstanding that all of DynCorp's proposed rates
were within the OSD range, the Army adjusted the rates for all
five categories--four upward and one downward--to the levels
under DynCorp's MNSTC-I contract (for mentoring of Iraq security
forces), which the agency determined to be similar "in customer,
scope, and function to the CSTC‑A effort." Cost Realism and
Price Analysis Report at 7. While LGS's proposed labor rates for
[REDACTED] labor categories were above the OSD range, all were
accepted without modification for purposes of the cost realism
evaluation on the basis that "LGS's hourly wages are competitive
and are held to be sufficient." Id. at 8. As for Offeror B, "[n]o
exceptions were taken to the rates proposed by [Offeror B]. In
its common labor categories, all rates are well within the
standard deviation range." Id. at 14. Finally, although four of
Offeror A's five proposed rates fell within the OSD range, its
rates were adjusted upward to the levels under MPRI's current
contract based on the indication in its proposal that Offeror A
"expect[ed] to recruit most, if not all, incumbents, because we
will offer to match their current compensation if higher than
proposed." Id. at 4.
MPRI asserts that the agency unreasonably failed to consider
whether MPRI could achieve its proposed rates, and that the
adjustment unreasonably increased MPRI's rates above the OSD
range and the rates calculated for other offerors.
As an initial matter, we find the agency's rejection of MPRI's
proposed labor rates as unsupported to be reasonable. An offeror
has the burden of submitting an adequately written proposal, and
it runs the risk that its proposal will be evaluated unfavorably
when it fails to do so. Recon Optical, Inc., B-310436,
B-310436.2, Dec. 27, 2007, 2008 CPD para. 10 at 6. MPRI's
proposal generally attributed the [REDACTED]% reduction in its
incumbent labor rates to "current market conditions," MPRI Cost
Proposal at IV-3, but included no information regarding current
market conditions. Further, MPRI's proposed rates not only were
significantly lower than its current rates for the same work,
but also were significantly lower (by a weighted average of
approximately [REDACTED]%) than the rates under DynCorp's MSNTC-I
contract (which, as noted, the agency considered to be similar
to the current requirement). Finally, MPRI's proposed rates were
lower than the average of all offerors' proposed rates for
[REDACTED] labor categories; lower than the OSD range for
[REDACTED] labor categories, accounting for [REDACTED] of 275
required staff; lower than all of the other proposed rates for
the [REDACTED] labor categories; and lower than [REDACTED] of
the other proposed rates for [REDACTED].
While we find that the agency reasonably rejected MPRI's
proposed labor rates as unrealistc, we agree with MPRI that the
extent of the resulting upward adjustment in the rates was
unreasonable. In this regard, we review an agency's conclusions
about the most probable costs under an offeror's proposal in
view of the cost information reasonably available to the agency
at the time of its evaluation. Information Ventures, Inc.,
supra; see Metro Mach. Corp., supra. In increasing MPRI's labor
rates to the level under its current contract, thereby rejecting
any reduction, the agency's realism evaluation assumed rates for
MPRI that were higher than the average proposed rate for each of
the labor categories; higher than the OSD range for three of the
five labor categories; higher than the rates proposed by any
offeror for three of the labor categories; and higher than the
rates proposed by three of the other offerors for the remaining
two categories. The adjusted rates for MPRI also were higher
than the rates for three of the five labor categories under
DynCorp's similar MSNTC-I contract, which rates DynCorp itself
proposed to reduce for this procurement. In some instances, the
adjustment left MPRI's rates significantly higher than these
other reference points; for example, for the mentor category
(128 of 275 required staff), the adjusted rate for MPRI was
$[REDACTED], while DynCorp's proposed rate was $[REDACTED] and
its MNSTC-I contract rate was $[REDACTED], the average proposed
rate was $31.49, and the OSD range was $28.51-$34.46.
The significance of these reference points in determining the
realism of MPRI's evaluated rates is highlighted by testimony at
the hearing conducted by our Office in this matter, indicating
that the SSA and the agency cost analyst performed no analysis
of trends in compensation for foreign nationals in Afghanistan
and, indeed, were unaware of the rates currently being paid
(including those under DynCorp's civilian police mentoring
contract) in Afghanistan other than those under MPRI's incumbent
contract. Transcript (Tr.) at 78-82, 94, 494-96, 508. In this
regard, when asked what the most probable labor rates would be
for foreign nationals in Afghanistan, the cost analyst responded
that "competition generally dictates what a reasonable price
is," that the "market rates" were determined by competition, and
that the average of the rates proposed by the five offerors thus
represented "a reasonable starting point." Tr. at 514-16,
558-60. The cost analyst then went on to state that MPRI's
current contract rates did not represent "the market rates." Tr.
at 513. Further, testimony by the chairman of the SSEB (a senior
mentor in Afghanistan)--that the offerors were expecting to draw
their staff from "a limited number of people, some [of whom] are
already doing the same work in Afghanistan, some [of whom] were
doing the same work in Iraq . . . ," Tr. at 579-80,
587-88--suggests that there would be no reason to expect widely
disparate rates among offerors, since they all are drawing from
the same pool of potential employees. We conclude that the
record does not support the magnitude of the upward adjustments
to MPRI's proposed labor rates, and that the cost evaluation
therefore was unreasonable.
MPRI also challenges the downgrading of its technical proposal
under the capability factor based on the cost evaluation
conclusions. Again, the Army determined that MPRI had "grossly
underestimated" its labor costs such that a "direct labor cost
growth of approximately [REDACTED]% would occur" as MPRI was
forced to increase its labor compensation to the levels under
its current contract, with the result that MPRI would experience
"high turnover, a lack of qualified personnel, and/or be forced
to work with personnel of lesser quality than those proposed."
SSD at 8. We agree that the technical evaluation was flawed.
While it may be that any reduction in compensation would lead to
some additional turnover, it is reasonable to assume that the
degree to which MPRI's rates were deemed inadequate determined
the extent to which its proposal was downgraded under the
capability factor. Thus, since we have found that the inadequacy
of MPRI's rates was unreasonably exaggerated in the
evaluation--as reflected in the excessive increase in MPRI's
proposed rates--we also find that the downgrading of MPRI's
technical proposal based on the same flawed cost evaluation
results likewise was unreasonable.
We will sustain a protest based on our finding of an evaluation
deficiency only where the protester demonstrates a reasonable
possibility that it was competitively prejudiced, that is, that,
but for the agency's actions, it would have had a substantial
chance of receiving the award. Parmatic Filter Corp.,
B-285288.3, B-285288.4, Mar. 30, 2001, 2001 CPD para. 71 at 11;
see Statistica, Inc. v. Christopher, 102 F.3d 1577, 1581 (Fed.
Cir. 1996).
The parties have offered alternative methodologies for
ascertaining the extent to which MPRI was prejudiced by the
agency's unreasonable cost evaluation. The agency and DynCorp
suggest that any new adjusted rates should be based on the
average of the proposed rates for each labor category. The
agency and DynCorp go on to assert that, if such an approach
were adopted, DynCorp's evaluated rates--which were based on its
MNSTC-I contract rates, which DynCorp indicated in its proposal
were excessive for this procurement--likewise should be
adjusted. According to the agency and DynCorp, this approach
would increase MPRI's evaluated cost advantage by less than
$[REDACTED] million--from approximately $36.4 million ($212.7
million for MPRI versus $249.1 million for DynCorp) to
approximately $[REDACTED] million ($[REDACTED] million for MPRI
versus $[REDACTED] million for DynCorp), Joint Agency/DynCorp
Comments, May 24, 2010, at 4-5--and would not have a material
impact on the evaluation or source selection.
MPRI, on the other hand, asserts that the extent of prejudice is
best captured by a calculation based on accepting MPRI's
proposed rates for senior mentor and trainer--since they fell
within the OSD range--and adjusting the rates for the remaining
three categories upward to the low end of the OSD range. MPRI
notes, in this latter regard, that the proposed rates for LGS's
subcontractors that fell outside the OSD range were adjusted to
the low end of the range. MPRI further asserts that there is no
basis for adjusting DynCorp's evaluated rates, since there has
been no showing that it was unreasonable for the agency to rely
on DynCorp's MNSTC-I contract rates rather than its lower
proposed rates (for four of the labor categories). MPRI
calculates that this approach--based on a revised evaluated cost
of $[REDACTED] million for MPRI, and DynCorp's originally
evaluated $249.1 million--would increase its cost advantage to
approximately $[REDACTED] million. MPRI Comments, May 24, 2010,
at 4-11.
Here, only by accepting the agency's material reevaluation of
the cost proposals and declining to accord any weight to the
protester's alternative methodology could we conclude that there
was no substantial probability of prejudice. However, while in
reviewing protests we will take into account post-protest
explanations that provide a detailed rationale for
contemporaneous conclusions, we generally give little or no
weight to reevaluations and judgments prepared in the heat of
the adversarial process. Navistar Defense, LLC; BAE Sys.,
Tactical Vehicle Sys. LP, B‑401865 et al., Dec. 14, 2009, 2009
CPD para. 258 at 6; Boeing Sikorsky Aircraft Support,
B-277263.2, B‑277263.3, Sept. 29, 1997, 97-2 CPD para. 91 at 15.
There is no basis for according any significant weight to the
agency's reevaluation here, given the possibility and the
appearance that the agency may have selected its alternative
methodology to ensure no material impact on the original
evaluation results. In any case, the agency's position fails to
take into account our finding that the flaws in the cost
evaluation resulted in an unreasonable evaluation of MPRI's
technical proposal. Accordingly, we conclude that MPRI was
prejudiced by the agency's actions and sustain the protest on
this basis. (MPRI, Division of
L-3 Services, Inc.; LINC Government Services, B-402548;
B-402548.2; B-402548.3; B-402548.4; B-402548.5; B-402548.6, June
4, 2010) (pdf)
ERC challenges the agency's cost realism
analysis of both ASRI's and ERC's proposal and maintains that
the MPC adjustments were unreasonable.
When an agency evaluates a proposal for the award of a
cost-reimbursement contract, an offeror's proposed estimated
costs are not dispositive because, regardless of the costs
proposed, the government is bound to pay the contractor its
actual and allowable costs. Federal Acquisition Regulation (FAR)
sections 15.305(a)(1); 15.404-1(d); Tidewater Constr. Corp.,
B-278360, Jan. 20, 1998, 98-1 CPD para. 103 at 4. Consequently,
the agency must perform a cost realism analysis to determine the
extent to which an offeror's proposed costs are realistic for
the work to be performed. FAR sect. 15.404-1(d)(1). An agency is
not required to conduct an in-depth cost analysis, see FAR sect.
15.404‑1(c), or to verify each and every item in assessing cost
realism; rather, the evaluation requires the exercise of
informed judgment by the contracting agency. Cascade Gen., Inc.,
B-283872, Jan. 18, 2000, 2000 CPD para. 14 at 8. Further, an
agency's cost realism analysis need not achieve scientific
certainty; rather, the methodology employed must be reasonably
adequate and provide some measure of confidence that the rates
proposed are reasonable and realistic in view of other cost
information available to the agency as of the time of its
evaluation. See SGT, Inc., B‑294722.4, July 28, 2005, 2005 CPD
para. 151 at 7; Metro Mach. Corp., B‑295744, B-295744.2, Apr.
21, 2005 CPD para. 112 at 10-11. Because the contracting agency
is in the best position to make this determination, we review an
agency's judgment in this area only to see that the agency' cost
realism evaluation was reasonably based and not arbitrary.
Hanford Envtl. Health Found., B‑292858.2, B‑292858.5, Apr. 7,
2004, 2004 CPD para. 164 at 10.
ASRI's Evaluated MPC
ERC contends that the cost realism analysis of ASRI's proposed
costs was unreasonable. ERC argues that ASRI deviated
significantly from the composite labor rates set forth in the
RFP and that ASRI failed to substantiate its deviations. Protest
at 3-7; Supplemental Protest and Comments at 9-13. ERC further
argues that the agency's application of an attrition rate to
ASRI's labor costs was not reasonable and deviated from the
requirements of the RFP. Comments at 21-23. As discussed below,
the protester's arguments provide no basis to sustain the
protest.
With regard to ERC's assertion that ASRI deviated from the
composite rates, we note that the composite rates provided in
the RFP were "[f]or information purposes only," and offerors
were permitted to deviate from these rates with adequate
justification. RFP at 105, 112. The agency reports that both ERC
and ASRI deviated from the historical average pay rates for
several labor categories. AR at 4. The agency explains that ASRI
deviated by proposing lower rates for 6 of the 30 non‑management
labor categories. AR at 5; Contracting Officer Statement at 8.
ASRI explained that its labor rates were developed using the
historical average pay rates provided in the RFP and actual
rates of current ASRI employees in each labor category. AR, Tab
J, ASRI Cost Proposal, at 18. ASRI also documented that it
[DELETED] to fill positions for this effort. Id. at 26. ASRI
offered several justifications for its lower labor rates, to
include: high unemployment and layoffs will result in lower wage
rates; good benefits will result in a willingness to forego wage
increases; and promotions from within the organization will
allow ASRI to fill vacated positions with less senior people at
lower wages. Id. at 27-28.
Both DCAA and the agency found ASRI's rates to be reasonable,
given that 5 of the 6 rates that deviated downward from the
RFP‑provided rates were based on the hourly rates of current
ASRI employees working under very similar conditions. (The 6th
rate was adjusted downward based on a local wage survey.) AR,
Tab K, DCAA Audit Report for ASRI, at 7; see also AR at 5.
Moreover, the record shows that the cost evaluation did result
in certain upward adjustments to ASRI's rates to reflect the
average actual direct labor rates for the labor categories where
incumbent employees were performing. AR, Tab K, DCAA Audit
Report for ASRI, at 7; Contracting Officer's Statement at 9.
Based on this record, we find no basis to conclude that the
agency's evaluation of ASRI's labor rates was unreasonable.
With regard to attrition rate, the record shows that ASRI
proposed an attrition rate of [DELETED] percent for all five
performance periods, and DCAA applied a lower rate of [DELETED]
percent to the first period only. AR, Tab K, DCAA Audit Report
for ASRI, at 8. DCAA based its lower rate on ASRI's experience
in performing a contract similar in scope to this requirement.
The agency adopted DCAA's recommendation in this area, which
resulted in a downward reduction of approximately [DELETED], or
[DELETED] of a percent, in ASRI's MPC. AR, Tab I, MPC Analysis
of ASRI's Proposal, at 2; Supplemental AR at 3. If this
attrition rate were not applied, the difference in MPCs between
ERC's and ASRI's proposals would be [DELETED], rather than
[DELETED]. Supplemental AR at 3. Given the small impact
attributable to the application of an attrition rate on ASRI's
MPC, the protester has not shown that it was prejudiced, even if
the application of the attrition rate was in error. See
Armorworks Enters., LLC, B-400394.3, Mar. 31, 2009, 2009 CPD
para. 79 at 3.
ERC's Cost Evaluation
ERC also argues that the agency unreasonably increased its
fringe rates in the MPC analysis. Specifically, ERC contends
that the adjustments were based on an inappropriate application
of linear regression analysis. Protest at 7-8; Supplemental
Protest and Comments at 16-19.
The upward adjustments of ERC's fringe rates were due to DCAA
recommendations. In this regard, DCAA questioned ERC's proposed
fringe rates because they were inconsistent with the firm's
established practices. When questioned about this disparity, ERC
responded that "its proposed method for allocating fringe costs
is not necessarily how it will be accounting for them." AR, Tab
P, DCAA Audit Report of ERC, at 9. DCAA therefore projected
ERC's fringe rates for 2009 using a linear regression analysis,
based on historical data from 2005 to 2008 of the actual fringe
rates incurred by ERC on a contract of similar scope to the
requirement here. This resulted in an upward adjustment to ERC's
proposed fringe rates of between .3 and 1.1 percent for each of
the ordering periods. Id.
The agency explains that, when there is a good correlation
between historical pools and bases (as is the case here), linear
regression is a better predictor of future overhead rates than
new contract specific rates with no historical bases. According
to the agency, linear regression is one of the techniques most
commonly used to quantify the relationship between indirect cost
rate bases and pools over time. Contracting Officer's Statement
at 11.
ERC does not disagree with this premise, but argues that the use
of linear regression here was not appropriate because the agency
provided, as part of the RFP, "a proportion of future hours . .
. that differed significantly from the historical experience of
ERC as the incumbent contractor." Supplemental Protest and
Comments at 18. Consequently, it is ERC's position that the
increase in the RFP‑mandated hours has the effect of lowering
its fringe rates. Id. at 16.
The protester has not shown that DCAA's use of the linear
regression technique was unreasonable here. Since ERC failed to
provide DCAA with an adequate explanation for proposing fringe
rates that were different from what it was currently using, DCAA
reasonably used an evaluation technique that relied on ERC's
actual performance to determine ERC's fringe rates--a technique
that all parties agree is a good predictor of overhead rates
when there is a good correlation between historical pools and
bases. Id. at 18; Contracting Officer's Statement at 11. Given
that the RFP advised offerors that rates would be examined by
DCAA, and given that DCAA's analysis of ERC's fringe rates was
reasonable, we have no basis to question the agency's following
of DCAA's recommendation to upwardly adjust ERC's fringe costs
in the MPC evaluation. See Systems Research Corp., B-237008,
Jan. 25, 1990, 90-1 CPD para. 106 at 5 (agency reasonably may
rely on DCAA's rate checks in connection with a cost realism
analysis). (ERC, Inc.,
B-404721; B-404721.2, April 19, 2011) (pdf)
New Analytic Strategies argues that the
solicitation did not provide for a price realism evaluation, and
that the agency's evaluation of the protester's proposed price
for realism was thus inconsistent with the solicitation's terms.
The protester also argues that, in any event, its proposed price
was realistic, and the agency's determination to the contrary
was unreasonable.
Before awarding a fixed-price contract, an agency is required to
determine whether the price offered is fair and reasonable.
Federal Acquisition Regulation (FAR) sect. 15.402(a). An
agency's concern in making this determination in a fixed-price
environment is primarily whether the offered prices are too
high, as opposed to too low, because it is the contractor and
not the government that bears the risk that an offeror's low
price will not be adequate to meet the costs of performance.
Sterling Servs., Inc., B-291625, B-291626, Jan. 14, 2003, 2003
CPD para. 26 at 3. An agency may, in its discretion, provide for
a price realism analysis for the purpose of assessing whether an
offeror's price is so low as to evince a lack of understanding
of the contract requirements or for assessing risk inherent in
an offeror's approach. METAG Insaat Ticaret A.S., B‑401844, Dec.
4, 2009, 2010 CPD para. 86 at 6. However, offerors competing for
award of a fixed-price contract must be given reasonable notice
that a business decision to submit a low-priced proposal will be
considered as reflecting on their understanding or risk
associated with their proposal. Milani Constr. LLC, B-401942,
Dec. 22, 2009, 2010 CPD para. 87 at 5-6; CSE Constr.,
B-291268.2, Dec. 16, 2002, 2002 CPD para. 207 at 4-5. Where a
solicitation for a fixed-price contract omits a provision for
realism but requests detailed cost or pricing information, we
have found that an agency may properly consider whether an
unreasonably low price poses proposal risk if the solicitation,
in either the technical or price factors, provides for the
evaluation of an offeror's understanding of the requirements.
See METAG Insaat Ticaret A.S., supra; SEEMA, Inc., B-277988,
Dec. 18, 1997, 98-1 CPD para. 12 at 5. Conversely, where the
solicitation lacks either a technical or price evaluation factor
that provides for the offerors' understanding of the
requirements, and the solicitation also does not require
detailed cost or pricing information, then the agency may not
consider whether unreasonably low prices pose proposal risk.
Milani Constr., Inc., supra.; CSE Constr., supra.
The RFP's price proposal preparation instructions provided in
relevant part as follows:
For each proposed labor
category, the offeror shall indicate the unit price (hourly
rate) for labor being proposed. The price proposal shall be
based on the direct labor rates and shall address all other
direct costs related to the work being proposed, broken out by
cost element. . . . The price proposal shall identify all labor
categories, the number of hours for each labor category, and any
materials or supplies to be used in performing the requirement.
. . . The offeror should clearly identify in the proposal the
overhead and [general and administrative] rate, if applicable,
to the travel costs and [other direct costs] under the time and
material [contract line item numbers].
RFP at 67. With regard to
the evaluation of proposals under the price factor, the
solicitation provided as follows:
Proposed costs for the
contract will be evaluated to determine whether they are
reasonable for the conduct of the proposed contract, reflect a
clear understanding of the requirements, and are consistent with
the methods of performance described in the offeror's quotation.
The overall evaluated price based on the proposal for the
contract will be used to develop the relative price rankings of
the proposals.
RFP at 69.
Thus, the RFP required that price proposals include price
information as well as considerable direct and indirect cost
information. The solicitation also provided that the proposals
would be evaluated under the price factor for understanding and
consistency with the offeror's proposed approach to contract
performance. Accordingly, the RFP provided adequate notice to
the offerors that low prices could be considered as reflecting
on their understanding or risk associated with their proposals.
See METAG Insaat Ticaret A.S., supra.
In evaluating price proposals, the agency analyzed "the proposed
labor mix and skill associated with the provided labor rates and
fixed unit prices . . . to determine if the prices proposed"
were "reasonable and realistic for the type of work proposed."
AR, Tab 5, Procurement Summary/Source Selection Memorandum, at
5. In doing so, the agency calculated a blended labor rate for
each offeror, and compared each offeror's blended labor rate to
the blended rates of the other offerors and the agency's
independent government cost estimate (IGCE). Id. at 6-7. The
record reflects that the blended labor rates of all of the
offerors, other than Analytic Strategies, were relatively close
to each other and to the IGCE. Analytic Strategies' proposed
blended labor rate was significantly less than those proposed by
the other offerors and the IGCE. As noted previously, the agency
determined that Analytic Strategies' low labor rates "present[]
a significant risk to the Government that there could be a
relatively high turnover rate among the assigned staff due to
low salaries," and concluded that "[t]his prevents their
proposal from being the best value to the Government." Id. at
11.
Although Analytic Strategies disagrees with the agency's
conclusion and asserts that its personnel will be able to
perform the contract at the rates proposed, the fact remains
that, as found by the agency, Analytic Strategies' labor rates
were significantly lower than the IGCE, as well as the labor
rates proposed by all of the remaining offerors. Based on our
review, we cannot find the agency's evaluation to be
unreasonable. (Analytic
Strategies, B-404840, May 5, 2011) (pdf)
Goel/Grunley next argues that the agency
acted improperly by evaluating its proposal for price realism,
asserting that the agency evaluated its proposal on the basis of
an unstated evaluation factor. The protester argues that, in a
fixed-priced environment, the submission of a low price is not
improper so the agency's concerns about a too-low price are
unreasonable. Furthermore, even if a realism analysis were
proper, the protester contends that the agency's analysis was
flawed here. Comments at 15-22.
The agency responds that its analysis was permitted because the
RFP required detailed cost and pricing information, and offerors
were advised that their understanding of the work would be
evaluated elsewhere in the solicitation. AR at 12-13.
Before awarding a fixed-price contract, an agency is required to
determine whether the price offered is fair and reasonable. FAR
sect. 15.402(a). An agency's concern in making this
determination in a fixed-price environment is primarily whether
the offered prices are too high, as opposed to too low, because
it is the contractor and not the government that bears the risk
that an offeror's low price will not be adequate to meet the
costs of performance. Sterling Servs., Inc., B-291625, B-291626,
Jan. 14, 2003, 2003 CPD para. 26 at 3. An agency may, in its
discretion, provide for a price realism analysis for the purpose
of assessing whether an offeror's price is so low as to evince a
lack of understanding of the contract requirements or for
assessing risk inherent in an offeror's approach. METAG Insaat
Ticaret A.S., B‑401844, Dec. 4, 2009, 2010 CPD para. 86 at 6.
However, offerors competing for award of a fixed-price contract
must be given reasonable notice that a business decision to
submit a low-priced proposal will be considered as reflecting on
their understanding or risk associated with their proposal.
Milani Constr., Inc., B-401942, Dec. 22, 2009, 2010 CPD para. 87
at 4; CSE Constr., B-291268.2, Dec. 16, 2002, 2002 CPD para. 207
at 4-5. Where a solicitation for a fixed-price contract omits a
provision for realism but requests detailed cost or pricing
information, we have found that an agency may properly consider
whether an unreasonably low price poses proposal risk if the
solicitation, in either the technical or price factors, provides
for the evaluation of an offeror's understanding of the
requirements. METAG Insaat Ticaret A.S., supra; SEEMA, Inc.,
B-277988, Dec. 18, 1997, 98-1 CPD para. 12 at 5. Conversely,
where the solicitation lacks either a technical or price
evaluation factor that provides for the offerors' understanding
of the requirements, and the solicitation also does not require
detailed cost or pricing information, then the agency may not
consider whether unreasonably low prices pose proposal risk.
Milani Constr., Inc., supra.; CSE Constr., supra.
As noted above, the RFP here asked for (and the agency
repeatedly requested during discussions) direct and indirect
cost information to be separately provided for each facade for
the following categories: design, labor, materials, equipment,
bonding, overhead, and profit. RFP at 32-33. The RFP also
required offerors to "provide all necessary supporting
documentation for cost breakdown of design, labor, materials and
equipment," and it encouraged offerors to provide "any other
price or financial information that may be helpful in the
understanding and evaluation of the Price Proposal." Id.
Furthermore, the RFP contained an evaluation factor, technical,
that required the evaluation of the offeror's "understanding of
the work," and offerors were informed that their proposals had
to "[d]emonstrate the efficiency and cost effectiveness of
[their proposed] approach." Id. at 31, 36. Based on this record,
we conclude that the RFP provided adequate notice to the
offerors that their low prices could be considered as reflecting
on their understanding or risk associated with their proposals.
See METAG Insaat Ticaret A.S., supra.
We also find the agency's price evaluation to be reasonable. As
noted in the source selection decision, Goel/Grunley's labor
costs, overhead, and profit were "very low" as compared to the
government estimate. AR, Tab 13, Source Selection Decision, at
376. In this regard, Goel/Grunley proposed approximately
[deleted] fewer labor hours and its overall price was
approximately [deleted] percent lower than the government
estimate; Goel/Grunley's overall proposed price was also found
to be outside the competitive range. Id. at 376, 378. Based on
the information requested in the RFP and included in Goel/Grunley's
price proposal, the agency concluded that the low price
presented a "potential risk of failure" and increased the
probability that the work would not be completed on time. Id. at
378. We find nothing improper in this aspect of the agency's
evaluation.
In sum, the protester's arguments do not call into question the
reasonableness of the agency's best value determination. Based
on our review of the record, and after considering all of the
protester's arguments, we find that the agency's selection of a
higher-rated, higher-price proposal for award was consistent
with the evaluation criteria and was reasonable. (Goel
Services, Inc. in association with Grunley Construction Co.,
Inc., B-404168, January 12, 2011) (pdf)
Moreover, there is no basis for CGI's
contention that the agency's cost evaluation was flawed because
it was not based on the government estimate. As a preliminary
matter, CMS explains that it did not utilize the government
estimate because it was not a good indicator of cost since it
was largely based on costs associated with non‑competitively
awarded work. Thus, the agency had a reasonable basis to
disregard its estimate in this case. See The S.M. Stoller Corp.,
B‑400937, et al., Mar. 25, 2009, 2009 CPD para. 193 at 16 n.8.
Further, as a general matter, when assessing cost realism, there
is no per se requirement that an agency compare offerors'
proposed costs with the government estimate. See, e.g., Advanced
Commc'n Sys., Inc., B‑283650, et al., Dec. 16, 1999, 2000 CPD
para. 3 at 6. Rather, the relevant question is whether the
methodology used by CMS to evaluate CSC's costs was reasonable.
While CGI contends it was not possible to determine whether
CSC's proposed level of effort for the various task groups was
reasonable without reference to the government estimate, or some
other type of cost baseline, as explained above, CMS's business
and technical evaluators carefully examined CSC's level of
effort for each task group, and, based on their expertise,
concluded that CSC's level of effort and proposed approach were
realistic to perform the requirements. CGI has not provided any
basis for our Office to conclude that the agency's exercise of
its considered judgment in this regard was unreasonable or
otherwise improper. (CGI
Federal Inc., B-403570; B-403570.2; B-403570.3; B-403570.4,
November 5, 2010) (pdf)
The protester contends that the agency
accepted unreasonably low prices and that the technical
evaluation was flawed.
With respect to the price evaluation, the protester contends
that the agency "fail[ed] to fulfill the responsibility to
assure realistic and reasonable pricing." Protest at 2. It
argues that the awardees' prices are "artificially low" and
"predatory." Id. The protester complains that the awardees'
offers "to do the job at little or no profit . . . is a
conscious attempt to exclude competitors from the seed project
and entire [MACC] program," Comments at 1-2, and that awarding
C.L. Price a contract would "guarantee balance" and "provide
increased value to the Government." Protest at 3. The protester
asserts that the fact that the government estimate was higher
than the awardees' prices is further evidence that the
government "ignored the issues of reasonableness and realism."
Comments at 2.
As noted above, the awards in this procurement were based on the
evaluation of a fixed-price seed project. Although an agency is
required to determine that offered prices are fair and
reasonable before awarding a fixed-price contract, Federal
Acquisition Regulation (FAR) sect. 15.402(a), the purpose of a
price reasonableness evaluation in a fixed-price environment is
to determine whether prices are too high, as opposed to too low,
because it is the contractor and not the government that bears
the risk that an offeror's low price will not be adequate to
meet the costs of performance. Sterling Servs., Inc., B-291625,
B-291626, Jan. 14, 2003, 2003 CPD para. 26 at 3. Arguments that
an agency did not perform an appropriate analysis to determine
whether prices are too low, such that there may be a risk of
poor performance, concern price realism. SDV Solutions, Inc.,
B-402309, Feb. 1, 2010, 2010 CPD para. 48 at 4. However, a price
realism evaluation is not required where, as here, the
solicitation provides for the award of a fixed-price contract
and does not include a requirement for price realism. Id. Thus,
the protester's assertion that the agency failed to perform a
realism analysis or consider whether the awardees' prices are
too low does not provide a basis to sustain the protest.
With regard to an agency's obligation to ensure fair and
reasonable pricing in awarding fixed-price contracts, the FAR
permits the use of various price analysis techniques and
procedures, including the comparison of proposed prices received
in response to the solicitation to each other or to an
independent government estimate. FAR sect. 15.404-1(b)(2);
Comprehensive Health Servs., Inc., B‑310553, Dec. 27, 2007, 2008
CPD para. 9 at 8. In fact, agencies may rely upon adequate price
competition alone to assess price reasonableness. See FAR sect.
15.404-1(b)(2)(i); Patriot Taxiway Indus., Inc., B-403690, Dec.
6, 2010, 2010 CPD para. __ at 7.
Here, the agency compared offerors' proposed prices to the IGE,
to the other prices received, and to the median proposal price
of the offerors in the competitive range. AR, Tab 4, Business
Clearance Memorandum, at 8. The agency did not, however, view
the IGE as the best basis of comparison of fair and reasonable
pricing, given that offerors were encouraged to provide their
lowest possible prices on the seed project in order to receive a
MACC and be eligible for further task orders. Id. at 9. The
agency instead determined that the "significant extent of
competition" was a better comparison tool to establish fair and
reasonable pricing. Id. The record shows that the awardees'
proposed prices for the seed project ranged from $137,000 to
$220,000, all of which were below the IGE and the median
proposed price. Id. at 8. Based on the adequacy of price
competition, these prices were found to be fair and reasonable.
Id. at 9, 12. In addition, the agency found the protester's
proposed price of $248,000 to be fair and reasonable, even
though it was 11 percent higher than the highest-priced proposal
selected for award and 2.5 percent higher than the median price.
Id. at 8, 12. Based on this record and the fact that there was
adequate price competition, we find nothing improper in the
agency's determination that the awardees' and the protesters'
proposed prices were fair and reasonable. (C.L.
Price & Associates, Inc., B-403476.2, January 7, 2011)
(pdf)
As a threshold matter, the parties
disagree as to whether the RFP in fact required the Air Force to
perform a price realism evaluation. FlightSafety argues that the
RFP provided for assessing price realism where it indicated that
the Air Force may reject an offeror's proposal if it is
determined to be "unreasonably . . . low in cost when compared
to Government estimates, such that the proposal is deemed to
reflect an inherent lack of competence or failure to comprehend
the complexity and risks of the program," RFP at 243, and that
the agency failed to properly consider whether CAE-USA's low
price was in fact realistic. The Air Force maintains that the
RFP merely established that the offerors' prices would be
evaluated for reasonableness.
As a general matter, when awarding a fixed-price contract, an
agency is only required to determine whether offered prices are
fair and reasonable. Federal Acquisition Regulation (FAR) sect.
15.402(a). An agency's concern in making a price reasonableness
determination focuses primarily on whether the offered prices
are higher than warranted. See McDonnell Douglas Corp.,
B-259694.2, B-259694.3, June 16, 1995, 95-2 CPD para. 51 at 9.
Moreover, since the government's liability is fixed when it
awards a fixed-price contract--the contractor bears the risk and
responsibility for actual performance, see FAR sect.
15.404-1(a)--an agency need not concern itself with the
contractor's actual costs of performance when awarding a
fixed-price contract. It may, nonetheless, include in a
solicitation a provision which provides for a price realism
evaluation for the purpose of assessing whether an offeror's low
price reflects on its understanding of the contract
requirements. Grove Resource Solutions, Inc., B-296228,
B‑296228.2, July 1, 2005, 2005 CPD para. 133 at 4-5. Where a
solicitation provides for a price realism evaluation, the depth
of an agency's evaluation in this regard is a matter within the
sound exercise of the agency's discretion. Citywide Managing
Servs. of Port Washington, Inc., B-281287.12, B-281287.13, Nov.
15, 2000, 2001 CPD para. 6 at 4-5. In reviewing protests
challenging price realism evaluations, our focus is on whether
the agency's review was reasonable and consistent with the terms
of the solicitation. Grove Resource Solutions, Inc, supra. Where
there is no relevant evaluation criterion pertaining to realism
or understanding, however, a determination that an offeror's
price on a fixed-price contract is too low generally concerns
the offeror's responsibility, i.e., the offeror's ability and
capacity to successfully perform the contract at its offered
price. See J.A. Farrington Janitorial Servs., B-296875, Oct. 18,
2005, 2005 CPD para. 187 at 4; CSE Constr., B‑291268.2, Dec. 16,
2002, 2002 CPD para. 207 at 4-5.
Here, although the RFP did not state that offerors' prices would
be evaluated for "realism" per se, it effectively provided for
such an evaluation where it established that the Air Force could
reject a proposal if the offeror's low price reflected an
inherent lack of competence or failure to comprehend the
complexity and risks of the program. As explained above,
analyzing whether an offeror's fixed price is so low that it
reflects a lack of understanding of solicitation requirements is
the crux of a price realism evaluation, and by informing
offerors that their proposals would be evaluated in this regard,
the RFP established that the Air Force would, in essence, assess
offerors' prices for realism.
Having concluded that the RFP contemplated what was, in essence,
a price realism assessment, the question becomes whether the Air
Force properly evaluated CAE‑USA's price, in light of this
provision. The record reflects that the Air Force reasonably
considered CAE-USA's low price and concluded that its low price
did not warrant rejection of CAE-USA's offer.
Notwithstanding the fact that the Air Force has argued that it
was not required to evaluate CAE-USA's price for realism,
throughout the evaluation process, the Air Force was, in fact,
keenly aware of, and concerned about, how low CAE‑USA's total
evaluated price was as compared to the total evaluated prices of
the other offerors.[2] As reflected in the agency's initial
evaluation documents, the Air Force evaluation team specifically
questioned whether CAE‑USA's low price reflected its "failure to
grasp overall complexity, technical understanding, and risks of
the program." Agency Report (AR), Tab 4(a), Initial Evaluation
Briefing Slides, at 54. As a consequence, the Air Force
specifically raised the matter with CAE-USA in discussions. In
one of the evaluation notices sent to CAE‑USA, the Air Force
advised the firm that its proposed prices were "significantly
below the government anticipated costs" and that it was the Air
Force's belief that CAE-USA had "significantly underpriced its
proposal," and asked CAE-USA to "carefully review all
requirements and ensure that the proposed pricing for all CLINs
is sufficient, such that the offeror is confident that [it]
could perform all requirements of the contract in a profitable,
or at least a non-loss pricing position." AR, Tab 5, CAE-USA
Evaluation Notice, at 2-3.
During face-to-face discussions, CAE-USA explained that it had
proposed [DELETED] for the fixed-price CLINs and stated that the
KC-135 Aircrew Training Systems contract is a very important
program for CAE-USA. This is an expansion of what we do every
day internationally. We build and manage training centers all
over the world. We have a lot of military operations, as well.
We operate a C-130 training center – the only commercial C-130
training center in the world in Tampa, but we don't have an
[Aircrew Training System] to manage. And this is very key to our
strategic plan, so we were very aggressive in our approach. We
understand that.
AR, Tab 6, CAE-USA Discussions Journal, at 51.
CAE-USA also provided a written response to the Air Force's
concerns about its low price, and reiterated its position that
the contract was very important and linked to CAE-USA's
"corporate strategic goals." AR, Tab 5, CAE-USA Discussion
Questions and Responses, at 3. CAE-USA emphasized that it
operated multiple training centers throughout the world and that
it had "a full grasp of the overall scope and complexity of the
KC-135 program." Id. CAE-USA further explained as follows:
We performed a thorough
analysis of the requirements of this effort. Based on our
experience from relevant programs, we carefully estimated our
costs incorporating efficiencies from lessons learned to offer
the Government a competitive price. . . . We are confident that
we can perform all requirements of the contract in a non-loss
position.
Id.
After receiving final proposals, and reviewing CAE-USA's
response to the evaluation notice question regarding its
pricing, the Air Force again considered the fact that CAE‑USA's
price was very low and concluded that it did not provide a basis
to reject the proposal submitted by CAE-USA. AR, Tab 8.b, Final
Evaluation Meeting Minutes, at 2.
FlightSafety argues that the Air Force's determination in this
regard was not reasonably based because the Air Force merely
accepted a general response from CAE-USA regarding its low
price. According to FlightSafety, the Air Force should have more
critically questioned and analyzed what it characterizes as "red
flags" associated with CAE-USA's low price, such as CAE-USA's
expectation that [DELETED] (the Air Force learned this fact as a
consequence of CAE-USA explaining, during discussions, why it
appeared that CAE-USA [DELETED]); the fact that it proposed
[DELETED] for the fixed-price CLINs; the large disparity between
CAE‑USA's prices for CLINs 0003 and 0004, as compared to those
of FlightSafety (CAE-USA's prices for those CLINs were [DELTED]
and accounted for [DELETED] the price difference); and the fact
that CAE-USA was aggressively pricing the contract.
Notwithstanding the so-called "red flags" which FlightSafety
maintains should have prompted greater concern within the Air
Force, or at a minimum a more probing analysis, as noted above,
the depth of an agency's price realism evaluation is a matter
within the agency's discretion. Citywide Managing Servs. of Port
Washington, Inc., supra. The record shows that the Air Force
recognized that 1) CAE-USA's price was low as compared with the
prices submitted by the other offerors; 2) the issue was raised
with CAE-USA in discussions; 3) CAE-USA expressly confirmed its
understanding of the requirements, an understanding supported by
CAE-USA's experience performing similar requirements; and 4)
CAE-USA explained that it was aggressively pursuing the contract
and therefore intended for its price to be low since it viewed
the contract as an important aspect of its corporate strategy.
After considering CAE-USA's response, the Air Force declined to
reject CAE-USA's proposal, thereby accepting CAE-USA
explanations, as well as any of the risks that might underlie
CAE-USA's low price. A more probing inquiry was simply not
contemplated by the RFP, or otherwise required, given that the
RFP did not provide for the submission of underlying cost
information for CLINs 0003 and 0004 [DELETED]. To the extent
FlightSafety believes that the magnitude of the price difference
demonstrated that CAE-USA's price was too low to be acceptable,
this argument reflects FlightSafety's disagreement with the
agency's decision not to reject CAE-USA's proposal and does not
provide a basis for our Office to conclude that the agency's
decision in this regard was unreasonable. (Flight
Safety Services Corporation, B-403831; B-403831.2, December
9, 2010) (pdf)
CTA next argues that the Army's evaluation
of its price was fundamentally inconsistent with the evaluation
methodology established by the TOPR [task order proposal
request] and that it was unreasonable. In this regard, CTA
contends that the TOPR merely provided that the Army would
evaluate total price for reasonableness, and that the agency had
no basis on which to find its labor rates unrealistically low.
CTA also argues that it should not have been penalized because
it did not separately price its incoming and outgoing transition
efforts since the TOPR expressly authorized firms to identify
contract line items as "not separately priced." CTA's arguments
are without merit.
Where, as here, award is to be made on a fixed-rate basis, the
realism of a firm's proposed labor rates is not ordinarily
considered, since the risk and responsibility for contract costs
and resulting profit or loss rests on the contractor. PharmChem,
Inc., B-291725.3, et al., July 22, 2003, 2003 CPD para. 148 at
7. An agency may, however, at its discretion, provide for the
use of a price realism analysis under a fixed-price solicitation
for various reasons, such as to assess the risk in a firm's
approach. Id. The nature and extent of an agency's price realism
analysis are matters within the agency's discretion, and our
review is limited to determining whether the evaluation was
reasonable and consistent with the solicitation's evaluation
criteria. Grove Resource Solutions, Inc., B-296228, B-296228.2,
July 1, 2005, 2005 CPD para. 133 at 4-5.
Here, notwithstanding CTA's suggestions to the contrary, the
TOPR specified that the Army would consider whether the
underlying costs of firms' price proposals were realistic. In
this regard, the TOPR required firms to provide labor rate
information with their price proposals, and advised that
"unsubstantiated costs that are considered unrealistic, not
fully supported, or both, may cause the overall technical
evaluation to be adjusted in one or more of the non cost/price
evaluation factors." TOPR at 14.
As noted above, the Army identified CTA's labor rates for
certain key personnel labor categories as being "well below the
market rates for these positions." AR, Tab 5, Evaluation Board
Consensus Report, at 29. The record reflects that the Army used
various indicia of the labor market (i.e., the average labor
rates for the same key personnel labor categories of the other
TEAMS contractors, relevant GSA rates, as well as the labor
rates actually billed by CTA in its performance of the incumbent
contract) in reaching its conclusion that CTA's labor rates were
significantly below market, and therefore unrealistic. While CTA
maintains that the Army should have considered other indicia of
the labor market which suggested that CTA's labor rates were not
unrealistic—specifically, the labor rates of CTA's
subcontractors, which were only somewhat higher than those used
by CTA--we have no basis to conclude that the labor market
research performed by the Army, which considered a wide range of
labor rates, was inherently unreliable, unreasonable, or
otherwise improper.
In the Army's view, CTA's failure to identify realistic labor
rates increased the risk associated with CTA's technical
proposal due to concerns about whether CTA would be able to hire
and maintain key personnel with the level of technical expertise
needed to perform as CTA had proposed. This finding of technical
risk was consistent with the TOPR's evaluation scheme where the
TOPR provided that unrealistic costs could be used as a basis
for adjusting the technical evaluation findings, as well as one
of the fundamental concepts of price realism analysis, which is
to identify risk associated with a firm's technical approach.
PharmChem, Inc., supra; Federal Acquisition Regulation sect.
15.404-1(d)(3) (explaining that cost realism analysis may be
used on competitive fixed-price contracts to assess performance
risk). Given this record, we have no basis to conclude that the
Army acted unreasonably or contrary to the terms of the
solicitation, procurement law, or regulation when it found that
certain of CTA's key personnel labor rates were unrealistic, and
associated the risk posed by this lack of price realism with
CTA's technical performance in making the tradeoff decision.
(Computer Technology Associates, Inc.,
B-403798; B-403798.2, December 2, 2010) (pdf)
Where, as here, an agency is evaluating
proposals for the award of a cost reimbursement contract, an
offeror's proposed costs are not dispositive since, regardless
of the costs proposed, the government will be liable to pay the
contractor its allowable and allocable costs. Federal
Acquisition Regulation (FAR) sections 15.305 (a)(1),
15.404-1(d); Frank A. Bloomer--Agency Tender Official,
B-401482.2,B-401482.3, Oct. 19, 2009, 2009 CPD para. 203 at 10.
Consequently, an agency must perform a cost realism evaluation
to determine the extent to which an offeror's proposed costs are
realistic for the work to be performed. Id. Such an evaluation
involves independently reviewing and evaluating elements of each
offeror's cost (and making adjustments thereto) to determine
whether the proposed cost elements are realistic for the work to
be performed, reflect a clear understanding of the requirements,
and are consistent with the methods of performance and materials
described in the offeror's technical proposal. We will review an
agency's cost realism analysis for reasonableness. ITT Fed.
Servs. Int'l Corp., B-289863 et al., Dec. 16, 2002, 2002 CPD
para. 216 at 2-3. We find that the agency's evaluation of MH's
proposed cost was unreasonable.
Condition Report Estimates, Production Planning and
Estimating, and Program Management Production Phase
MH asserts that the agency improperly calculated its probable
cost to perform three aspects of the requirement relating to
estimating and managing work to be accomplished under the
contract. The crux of MH's argument is that the agency
miscalculated the estimated number of hours per day, per
availability required for this work, which resulted in the
agency's arriving at a higher number of hours per day and a
correspondingly higher cost. In these areas, the agency concedes
that its methodology was flawed, as the protester asserts, and
that it improperly added $[deleted] to MH's evaluated cost for
these three items. Supp. AR, at 14-16. As the parties agree
concerning the nature of the flaw in the agency's evaluation in
these areas, we need not discuss them further; these aspects of
the evaluation were unreasonable.
Ship's Force Parking
The protester asserts that the agency improperly increased its
proposed cost to account for the cost of security guard services
for ship's force parking areas; the RFP provided an estimated
3,780 hours per availability for ship's force parking. RFP at
165. In its second FPR, MH proposed a deviation from this aspect
of the requirement, explaining that it recently acquired a
street dividing two parcels comprising its facility. The
protester states that this acquisition has enabled it to join
the two parcels into one larger parcel, to place a security
perimeter around the entire facility, and to create sufficient
new parking for all of the ship's force for this contract. MH's
proposal concluded as follows:
[deleted]
AR, exh. 17a, at E-1. MH
asserts that the agency improperly added the cost of providing
3,780 hours of security guard services per availability (as well
as the cost of certain materials) to its evaluated cost.
The agency responds that the upward adjustment was reasonable
because MH did not provide historical evidence showing that it
had previously treated ship's force parking as an indirect, as
opposed to a direct, cost. According to the agency, MH
historically has charged ship's force parking as a direct cost,
as evidenced by several recent contracts.
We find that the agency unreasonably added the cost of security
guard services for ship's force parking to MH's proposed cost.
As noted, MH's FPR unequivocally proposed to provide ship's
force parking inside the fenced perimeter of MH's facility at no
direct cost to the government, and fully explained the basis for
this approach. In rejecting MH's approach, the agency relied
solely on the fact that MH had billed this item as a direct cost
under prior contracts. Given the explanation in MH's FPR,
however, we think this sole reliance was unreasonable. While
MH's practice under prior similar contracts might have been
relevant, the FPR essentially explained why MH's prior practice
was not relevant. The agency never determined that this
explanation was unpersuasive or unrealistic in any way, and even
now has not established that there was reason to question the
basis for MH's indirect cost approach.
Further, the agency ignored the fact that MH's proposed
allocation of the cost of security guard services to an indirect
cost pool was entirely consistent with the accounting practices
specifically approved for MH by the Defense Contract Audit
Agency (DCAA). In this regard, the record shows that every
iteration of MH's proposal included a copy of the latest version
of its DCAA-approved forward pricing rate agreement. AR, exh.,
3, attach. C.1-2; exh. 13b, attach. Q-7-1; exh. 17, attach.
FPR2; see also AR, attach 3. These forward pricing rate
agreements specifically identify watchman services as an
indirect cost for accounting purposes.
We conclude that the agency has failed to establish a reasonable
basis for increasing MH's evaluated cost to include security
guard services for ship's force parking as a direct cost; the
record supports the conclusion that the amount of the improper
upward adjustment was $[deleted].
Fire Watch
MH asserts that the agency improperly increased its evaluated
cost to account for certain fire watch services (fire watch
services must be provided whenever "hot work" such as welding,
or any other fire or spark producing work, is being performed).
MH proposed [deleted] hours of fire watch services per
availability, but the agency adjusted its proposed hours upward
to [deleted] hours per availability. MH concedes that its fire
watch services hours were somewhat understated, but asserts that
the upward adjustment to [deleted] hours per availability is
excessive.
Fire watch hours were calculated as a percentage of production
hours under the contract. The parties essentially now agree that
[deleted] is the correct coefficient to apply (although during
its evaluation, the agency used a figure of [deleted] percent),
but disagree regarding the appropriate production hours basis to
which the percentage should be applied. The protester maintains
that it should have been applied to a basis of [deleted]
production hours, whereas the agency maintains that the
appropriate basis is [deleted] production hours (thereby
yielding a new figure calculated during the protest of [deleted]
fire watch hours per availability). The difference between the
parties relates to whether certain hours should have been
included in the basis as production hours. The protester
maintains that two categories of production hours--"temporary
services" and "pumping and cleaning"-- should have been excluded
because neither of these categories requires performance of "hot
work." The agency maintains that it was proper to include these
hours because these categories could include hot work.
We agree with the protester that temporary services and pumping
and cleaning should not have been included in the fire watch
services calculation. The protester asserts--and the agency has
not persuasively refuted--that there is no hot work involved in
temporary services. Temporary services are confined to
facilities-related work, such as the installation of temporary
gangways, landing platforms, piping, lighting, handrails and the
like, to enable ready access to the ship for workers and their
tools and supplies. MH explains that, because these features
involve a connection between the ship and shore, they must be
flexible to accommodate the movement of the ship, and that
welding, for example, would be impractical because it would
result in a rigid, rather than a flexible, connection. MH
concludes that all of this work must be accomplished without
performing any hot work. Supp. Comments, Sept. 24, 2010, exh. 2,
at 2. The protester further explains that cleaning and pumping
involves the evacuation and cleaning of shipboard storage tanks
that contain flammable materials such as gasoline, oil or
lubricants. This work does not involve hot work (after cleaning
and pumping the tanks, they must be certified "gas free" before
any hot work can occur). Id. Again, the agency has not
persuasively shown that this work could involve hot work.
Thus, we conclude that it was unreasonable for the agency to
include these hours in the production hour basis used in
calculating the appropriate number of fire watch services hours
that would be required. Accordingly, the appropriate production
hours basis is [deleted] hours; applying the [deleted] percent
coefficient yields [deleted] hours of fire watch services per
availability.
As with the ship's force parking issue, the protester also
asserts that the agency used an inappropriately high hourly rate
when calculating the evaluated cost of fire watch services for
MH. According to the protester, the agency used MH's skilled
tradesmen average rate of $[deleted], rather than the rate of
$[deleted] that it proposed. The agency essentially concedes
that it used an inappropriately high hourly rate. In the final
analysis, the record shows that the agency's calculation of the
overstatement in this area was unreasonable due to the use of
both excessive hours and an unreasonably high hourly rate, and
that the overstatement is in the amount of $[deleted] for labor.
(The agency calculated an understatement in this area of
$[deleted] based on the use of the lower hourly rate, AR at 22,
n.19, but this calculation does not take into consideration the
reduction of fire watch services hours resulting from the use of
the lower production hours basis discussed above.)
Summary
The errors in the agency's cost evaluation discussed above
resulted, conservatively, in an overstatement of MH's evaluated
cost by $[deleted]. Reducing MH's evaluated cost by this amount
would move its cost below Earl's. Since the source selection
decision was premised on MH's cost being higher than Earl's, we
conclude that the source selection decision was unreasonable,
and sustain the protest on this basis. (Marine
Hydraulics International, Inc., B-403386; B-403386.2,
November 3, 2010) (pdf)
Aegis challenges the agency's conclusion
that TigerSwan's lower price was realistic notwithstanding its
significantly lower pricing for the security team CLINs. In this
regard, Aegis asserts that the agency improperly failed to use
the IGCE in its price realism analysis. Aegis also argues that
the contracting officer's consideration of the [DELETED] task
order to assess the realism of TigerSwan's pricing was
unreasonable because the [DELETED] task order did not provide a
valid basis for comparison since it involved convoy security
services, which are less complex and expensive as compared with
the personal security detail services required by the RFP, and
because the contracting officer misunderstood and miscalculated
the [DELETED] security team pricing.
Where an RFP contemplates the award of a fixed-price contract,
an agency may, as here, provide in the solicitation for the use
of a price realism analysis for the limited purpose of measuring
an offeror's understanding of the requirements or to assess the
risk inherent in an offeror's proposal. Puglia Eng'g of
California, Inc., B‑297413 et al., Jan. 20, 2006, 2006 CPD para.
33 at 6. Although the Federal Acquisition Regulation (FAR) does
not use the term "price realism," it states that cost realism
analysis may be used to evaluate fixed-price proposals for
purposes of assessing proposal risk, but not for the purpose of
adjusting an offeror's evaluated price. FAR sect.
15.404-1(d)(3).
As our Office has repeatedly held, the depth of an agency's
price realism is a matter within the sound exercise of the
agency's discretion. Citywide Managing Servs. of Port
Washington, Inc., B-281287.12, B-281287.13, Nov. 15, 2000, 2001
CPD para. 6 at 4-5. In reviewing protests challenging price
realism evaluations, our focus is on whether the agency's review
was reasonable and consistent with the terms of the
solicitation. Grove Resource Solutions, Inc., B-296228,
B-296228.2, July 1, 2005, 2005 CPD para. 133 at 4-5.
Here, TigerSwan's pricing for its security teams was
significantly lower than that of the other two offerors and the
IGCE. The record reflects that the price difference stemmed
primarily from TigerSwan's use of a different staffing approach,
one which was based on a much less expensive workforce through
its employment of TCNs, as opposed to expatriates. Given this
difference in approach, simply comparing TigerSwan's pricing
with the other offerors' pricing would not have been a valid
approach to evaluating TigerSwan's pricing for realism.
Similarly, the record reflects that the CO considered the IGCE
as part of his realism assessment, but reasonably gave it
"little weight" due, in part, to the fact that the IGCE was
derived from the incumbent contract pricing, which was based on
the extensive use of expatriate staffing for the security teams,
whereas TigerSwan's pricing was premised on staffing its
security team largely with TCNs. AR, Tab 10, Source Selection
Decision, at 4.
Recognizing the problem with comparing TigerSwan's pricing with
the other offerors' pricing and the IGCE, the agency sought to
account for the different staffing approaches in its realism
analysis by comparing TigerSwan's pricing with the pricing for
the [DELETED] task order, where the security teams were composed
primarily of TCNs and LNs as opposed to the significantly more
expensive expatriates, an approach more closely aligned with the
staffing approach used by TigerSwan.
As noted above, Aegis contends that the agency misunderstood and
miscalculated the [DELETED] task order pricing and argues that
the [DELETED] task order did not provide a valid basis for
comparison since it involved less complex requirements. After
accounting for these issues, Aegis asserts, it should have been
apparent to the agency that TigerSwan's pricing actually was
substantially lower than the [DELETED] pricing, and thus that
TigerSwan's pricing was unrealistic. In our view, the record
shows that the agency's realism analysis of TigerSwan's pricing
was reasonable.
Aegis maintains that when the contracting officer found that
TigerSwan's pricing for CLIN 0003 ($492,229) was in line with
the [DELETED] task order security team price of [DELETED], he
failed to appreciate the fact that TigerSwan's CLIN 0003 price
reflected a price for two security teams, while the [DELETED]
price was for only one security team. After accounting for this
difference, Aegis argues, it is apparent that TigerSwan's
security team pricing is actually much lower than that of the
[DELETED]. The record reflects, however, that the contracting
officer's price realism analysis was not based on a comparison
of TigerSwan's total CLIN 0003 price for two teams with the
[DELETED] total price for a single team. Rather, the contracting
officer compared the average per person/per month prices for
TigerSwan and the [DELETED], an approach which accounts for the
different number of teams reflected in TigerSwan's and the [DELETED]'s
total pricing. Using the per person pricing, the contracting
officer was able to compare, albeit a somewhat crude comparison,
the labor costs of two offerors' security teams, which had a
similar staffing composition. Based on this comparison, the
contracting officer concluded that TigerSwan's average per
person monthly pricing was in line with [DELETED]'s average per
person monthly pricing. Aegis' challenge in this regard is
therefore without merit.
Aegis argues that the per person monthly price comparison was
flawed because the per person/per month price for the [DELETED]
task order security team was understated. In this regard, Aegis
explains that the contracting officer erroneously calculated the
per person price based on a team composed of [DELETED]
individuals, yet the record reflects that the teams under the
[DELETED] task order were composed of only [DELETED] members.
Accounting for this difference, Aegis asserts, the average per
person price for the [DELETED] security teams should have been
[DELETED], not [DELETED].
In our view, the agency's calculation error was not material.
The agency specifically concluded that TigerSwan's calculated
per person/per month price of [DELETED] was in line with the
[DELETED] price calculated for the [DELETED]. This comparison
was, by its nature, limited since the [DELETED] pricing was
based on fully burdened rates--the agency did not have a
breakdown of the [DELETED] rate information (overhead, profit,
etc.)--and the contracting officer did not know the country of
origin of the TCNs used on the [DELETED] security teams.
Moreover, this comparison was made relative to Aegis' much
higher average per person monthly price of $26,631, the other
basis of comparison. Given the limited nature, and context, of
the agency's comparison, there is nothing to suggest that
increasing this difference by $800 would have led the agency to
conclude that TigerSwan's pricing was unrealistic.
Aegis also contends that it was unreasonable to compare pricing
for the [DELETED] convoy security task order requirements with
the RFP's PSD requirements since the requirements are not
similar. To the extent the record indicates that the two
requirements are not identical--the [DELETED] task order
involved providing convoy escort security teams to protect
20-160 flatbed truck convoys and their drivers while en route to
sites throughout Iraq, and the RFP's PSD work requires providing
personal protection for individuals traveling throughout
Iraq--the RFP established that the agency in fact considered the
work to be comparable. Specifically, under the technical
capability section, the RFP provided that experience of proposed
personnel could be based on experience "in PSD operations or
Convoy Security operations which shall carry equal weight when
evaluated." RFP at 58. Similarly, the past performance factor
provided that the agency's evaluation would be based on an
assessment of an offeror's relevant past performance, "which
includes PSD or Convoy Security missions." Id. at 59. Aegis'
challenge to the agency's judgment in this regard constitutes
mere disagreement, and does not establish that the agency acted
unreasonably in using the [DELETED] task order as a basis for
evaluating TigerSwan's pricing. (Aegis
Defence Services, B-403226; B-403226.2; B-403226.3,Ltd.,
October 1, 2010) (pdf)
The RFP included the GSA's standard
Commercial Sales Practices Format for FSS contract awards, which
offerors were required to complete as part of their proposals.
The basic goal of the Commercial Sales Practices Format is to
obtain appropriate and sufficient data, so that the contracting
officer can perform a price analysis, determine price
reasonableness, and develop objectives for negotiations. The
Commercial Sales Practices Format requires offerors to "[p]rovide
[for the previous year] the dollar value of sales to the general
public at or based on an established catalog or market price."
48 C.F.R. sect. 515.408(b)(1). It also requires offerors to show
the "total projected annual sales to the Government under this
contract for the contract term, excluding options, for each SIN
[Special Item Number] offered." 48 C.F.R. sect. 515.408(b)(2).
Offerors were asked by the Commercial Sales Practices Format to
provide information regarding their written discounting policies
and to respond "yes" or "no" to the following question:
[A]re the discounts and any concessions which you offer the
Government equal to or better than your best price (discount and
concessions in any combination) offered to any customer
acquiring the same items regardless of quantity or terms and
conditions?
48 C.F.R. sect. 515.408(b)(2). The Commercial Sales Practices
Format provides the following chart for offerors to complete for
each SIN:
Column 1
Customer |
Column 2
Discount |
Column 3
Quantity/Volume |
Column 4
FOB Team |
Column 5
Concessions |
48 C.F.R. sect. 515.408(b)(4)(a). The instructions for this
chart state:
Column 1-Identify the Applicable Customer or Category of
Customer
A 'customer' is any entity, except the Federal Government, which
acquires supplies or services from the Offeror. The term
customer includes, but is not limited to original equipment
manufacturers, value added resellers, state and local
Governments, distributors, educational institutions (an
elementary, junior high, or degree granting school which
maintains a regular faculty and established curriculum and an
organized body of students), dealers, national accounts, and end
users.
48 C.F.R. sect. 515.408(c). Offerors are also informed that, if
they are a dealer or reseller "without significant sales to the
general public," then the same information required by the
Commercial Sales Practices Format would be required to be
submitted for the manufacturers, "if the manufacturer's sales
under any resulting contract are expected to exceed $500,000."
48 C.F.R. sect. 515.408(b)(5). "Th[is] information is required
in order to enable the Government to make a determination that
the offered price is fair and reasonable." Id. The RFP finally
advised that offerors may be required to provide additional
supporting information requested by the contracting officer, but
only "to the extent necessary to determine whether the price(s)
offered is fair and reasonable." 48 C.F.R. sect. 515.408(a)(3).
(sections deleted)
Affirmative argues that the
agency improperly concluded that Affirmative lacked "significant
sales to the general public," and that the agency's request for
data about the commercial sales of the manufacturer was
unreasonable. In this regard, the protester first contends that
the VA was required to consider sales of commercial items to
both Government and non‑Government customers as a reseller's
"sales to the general public" in determining whether these sales
were "significant" under 48 C.F.R. sect. 515.408(b)(5), which
Affirmative claims GSA does in making awards under other FSS
contracts. We disagree.
As noted above, the Commercial Sales Practices Format included
in the solicitation is GSA's mechanism for evaluating whether
FSS vendors are offering fair and reasonable commercial item
prices. As quoted above, the instructions for the Commercial
Sales Practices Format expressly provide that sales to the
Federal Government are not counted in determining commercial
sales to the general public. While the protester has provided
evidence that the GSA has previously considered Federal
Government sales in determining whether offered prices were
reasonable in awarding other FSS contracts, we solicited the
views of the GSA, which advised that "the Commercial Sales
Practices Format requires offerors for FSS contracts to provide
sales information for non-government customers, and specifically
prohibits such sales information for sales to federal government
customers." GSA Report at 7. We find that the VA reasonably
decided not to consider Affirmative's sales to the Federal
Government in determining whether or not it had significant
levels of commercial sales to the general public under 48 C.F.R.
sect. 515.408(b)(5).
Affirmative next argues that even if the contracting officer
only considered Affirmative's $3.6 million in sales to two
non-government hospitals, that amount, by itself, should have
been considered significant. According to the protester, the GSA
has regularly concluded under 48 C.F.R. sect. 515.408(b) that a
reseller's sales of $3 million or less in commercial items
constitutes "significant" sales to the public.
In response, the contracting officer stated:
In a vacuum, disclosed
commercial sales of $3,650,471 for a Small Disadvantaged Veteran
Owned Small Business who provides no value added services, such
as Affirmative, might be considered to be significant. However,
other factors became relevant as the potential FSS contract
valuation escalated well beyond the Offeror's estimation and,
consequently, Affirmative's commercial sales were assessed by
the [contracting officer] to be insignificant. Such factors
include 1) reported annual federal Government open market
purchases of $29.6 million are much higher than commercial sales
of $3.6 million; 2) commercial sales of $3.6 million to two
private facilities are vastly insignificant when compared to
Medtronic's [fiscal year] 2009 sales of $3.4 billion for the
spinal product line being offered, and 3) terms afforded to two
"Medical Centers" are typically not representative of the terms
provided to the largest customers (such as GPOs and national
accounts) in a sales base of $3.4 billion.
Contracting Officer's Supp.
Statement at 2.
The GSA states that it has provided no specific guidance to
contracting officers about whether disclosed public sales are
significant, to assist them in determining whether to request
manufacturer data to ascertain whether the prices are fair and
reasonable. The GSA states such contracting officer
determinations are discretionary, taking into account
information available through contractor disclosures and market
research. Agency Report, Tab 18, Declaration of GSA
Representative (July 7, 2010), at 4.
We agree that a determination concerning price reasonableness is
a matter of administrative discretion involving the exercise of
business judgment by the contracting officer; therefore, we will
question such a determination only where it is clearly
unreasonable or there is a showing of bad faith or fraud.
Concepts Bldg. Sys., Inc., B-281995, May 13, 1999, 99-1 CPD para.
95 at 5. A contracting agency may reasonably conclude that
offered prices are unreasonable under a multiple-award FSS
procurement where the vendor provides insufficient data to
support the allowance of such costs. American Seating Co.,
B-230171.36, Aug. 31, 1989, 89-2 CPD para. 195 at 5-6.
Based on our review, we find that the VA, in exercising its
business judgment, reasonably determined that Affirmative's
sales to the general public were not significant. Specifically,
it was reasonable to consider the relatively small amount of
these two commercial sales to individual hospitals compared to
the $3.6 billion in total sales of these products by the
manufacturer. See 48 C.F.R. sect. 538.270(c) (agency should
consider such factors in determining Government's price
negotiation objectives). In the VA's view, volume sales to
entities such as national accounts would be far more relevant
than Affirmative's limited commercial sales to two hospitals in
assessing whether prices are fair and reasonable. See
Contracting Officer's Supp. Statement at 1. Moreover, the
contracting officer explains that because Affirmative reports
insignificant sales to the general public, she was unable to
determine if the prices offered are based on the manufacturer's
commercial list price, a manufacturer's suggested retail price,
or some other discounted starting point established by
Affirmative as a dealer/reseller. Id. at 3. In sum, we think
that the VA could reasonably determine that manufacturer
information was required to determine whether the offered prices
were fair and reasonable because the public sales were not
considered significant under the circumstances. (Affirmative
Solutions, LLC, B-402996, September 8, 2010) (pdf)
PJ asserts that
the agency improperly determined that its price was
unreasonable, noting that the agency actually found higher
prices for B-214s to be reasonable under previous solicitations
for services at the same bases, notwithstanding a virtually
identical price differential. Protest at 2; Protester Comments
at 3. PJ contends that the agency has offered no evidence for
its proposition that the availability of aircraft supported
different price reasonableness determinations under the
different procurements. Protester’s Comments at 3.
In evaluating price reasonableness, agencies may use a variety
of techniques, including comparison of the proposed prices
received in response to the solicitation, comparison of the
proposed prices to prices previously paid for the item being
acquired, comparison of the prices proposed with published
commercial price lists and comparison of the prices received
with an independent government estimate. Federal Acquisition
Regulation (FAR) sect. 15.404-1(b)(2). A price reasonableness
determination is a matter of administrative discretion involving
the exercise of business judgment by the contracting officer
that we will question only where it is unreasonable. The Right
One Co., B-290751.8, Dec. 9, 2002, 2002 CPD para. 214 at 5.
The price reasonableness determination here was unobjectionable.
The agency used one of the acceptable evaluation methods
specifically identified in the FAR--comparison of prices
received--as the basis for its analysis, which revealed a
significant price difference between the B-214 prices and the
prices for other offered helicopters. While the protester points
to the fact that similar prices were deemed reasonable under
prior solicitations, the record shows that the agency was
cognizant of that fact and, as noted, determined that, here, it
was not under the same time and supply constraints that led to
its contracting for B-214s at a similarly high price under those
prior solicitations. Contrary to the protester’s position, we
find that this rationale fully explains the agency’s different
price reasonableness determination in this case. Moreover, the
underlying premise of PJ’s argument--that a price reasonableness
determination under a prior solicitation can affect the
propriety of a current reasonableness determination--ignores the
well-established principle that each federal procurement stands
on its own. Sabreliner Corp., B-275163 et al., Dec. 31, 1996,
96-2 CPD para. 244 at 2 n.2. The fact that the Forest Service
previously determined that B-214 prices were reasonable thus did
not compel it to reach the same determination here.
PJ argues that the agency improperly rejected its B-214
helicopters based on price alone, without considering their
technical merits. However, where an agency determines that a
proposal offers unreasonably high prices, it properly may reject
the proposal solely on that basis. Gold Cross Safety Corp.,
B-296099, June 13, 2005, 2005 CPD para. 118 at 2. In any case,
as noted above, the record clearly indicates that,
notwithstanding its finding that PJ’s price was unreasonable,
the agency evaluated the technical merits of the B-214
helicopter and conducted a best value trade-off; it determined
that, notwithstanding the B-214s’ higher technical rating, there
was insufficient benefit to the agency to justify their
significantly higher price. AR, Tab H, TET Summarization,
Reference B, at 3; Tab I, Recommendation Letter to Source
Selection Authority, at 6. (PJ
Helicopters, Inc., B-402524.2, May 20, 2010) (pdf)
Metro protests
that the Navy's cost realism analysis of BAE's proposal was
improper insofar as the agency failed to adjust BAE's projected
costs to account for the firm's increased employee pension
costs. Metro alleges that, prior to the submission of FPRs, BAE
was aware that the contribution rates to its employees' pension
trust were increasing. The protester contends that neither BAE's
FPR nor the Navy's cost realism analysis adjusted BAE's overhead
rates to account for these increased pension costs. Metro argues
that BAE's higher pension costs would have increased the
offeror's total evaluated cost by approximately $5 million.
Protest, Apr. 12, 2010, at 10-12.
On November 11, 2009, BAE received notice from the
Boilermaker-Blacksmith National Pension Trust regarding pension
contribution rate changes. The notice stated that the pension
trustees had determined the adverse financial conditions
affecting the pension fund would result in increased
contribution rates from all contributing employers, effective
January 1, 2010. The pension trust notice also contained a
provision stating, "[i]f all or part of the [increase] is taken
from employees' wages, this must be handled as a reduction of
the employees' wage rate, rather than a deduction from the
employees' wages." Id., Exh. 5, Pension Trust Notice, at 1-2.
The following facts are based largely on declarations of various
BAE employees, which we have no reason to question. BAE
conducted an extensive review of the pension trust notice with
internal and external legal counsel and pension consultants in
the weeks following its receipt. BAE submitted its FPR on
December 4 without making adjustment for or mentioning the
pension trust notice, and the CAP had no knowledge of any
pension trust contribution increases when performing its cost
realism analysis of the offerors' FPRs. AR, Apr. 21, 2010, at
10-12, attach. 1, Declaration of BAE Human Resources Director,
Apr. 20, 2010, at 1-2, attach. 2, Declaration of BAE Finance
Director, Apr. 20, 2010, at 1-3.
By December 9, BAE determined that the increased pension
liability was a company responsibility; while the pension fund
trustees were not a party to and did not have authority to
modify BAE's employee wages as established by the parties'
collective bargaining agreement (CBA), the trustees did have
authority to increase the contributing employers' pension
contributions. Even at this point, however, BAE was unaware of
the cost impact of the increased pension liability on its
Norfolk shipyard or its proposal, for various reasons. First,
BAE believed that one option available to it--as suggested by
the pension trust notice--was to reduce employee wages to offset
any increase in BAE's required pension contributions.
Additionally, BAE was then engaged in negotiations with the
local IBB union for a new CBA which would determine, among other
things, how BAE's higher pension contributions would be funded.
Id.
BAE and the local union did not begin negotiations on the
economic portion of the new CBA until January 2010. The Navy
awarded the contract to BAE on February 19, and BAE concluded
CBA negotiations with the local union on March 5. BAE's
increased pension contributions were one of several issued
addressed collectively in the CBA negotiations; while some of
the contractor's labor costs increased, others were reduced. BAE
subsequently calculated that the cost impact to its proposal
here for the increased pension fund contributions was
approximately $2.5 million. Id.
While under certain circumstances an offeror is required to
advise the agency of material changes to its proposal, even
after submission, in order to ensure that the agency's
evaluation is based on consideration of the proposal as it
actually exists at the time it is being evaluated, Greenleaf
Constr. Co., Inc., B-293105.18, B-293105.19, Jan. 17, 2006, 2006
CPD para. 19 at 10; Dual, Inc., B-280719, Nov. 12, 1998, 98-2
CPD para. 133 at 3-6, we do not think that such a duty to report
arose here given that the impact of the increased pension costs
was not known until after award was made.
As detailed above, BAE received the pension fund notice on
November 11 and had not determined whether this in fact
represented a BAE financial liability prior to its December 4
FPR submission. Even after determining on December 9 that the
increased pension liability was a company responsibility, BAE
was unaware of the cost impact of the increased pension
liability on its Norfolk shipyard or its proposal. As suggested
by the pension trust notice, one option potentially available to
BAE was to reduce employee wages to offset any increase in
required pension contributions. Moreover, BAE was engaged in CBA
negotiations with the local IBB union that would determine,
among other things, how BAE's higher pension contributions would
be funded. These CBA negotiations did not conclude until March
5, well after the February 19 award date. It was only at such
time that BAE could realistically estimate the cost impact of
the pension fund notice.
In sum, the record shows that the cost impact of the increased
pension fund contribution was not certain enough prior to award
to constitute a material change to BAE's proposal and, as a
result, BAE was not required to advise the agency of the matter
during the evaluation process. (Metro
Machine Corp., B-402567; B-402567.2, June 3, 2010) (pdf)
Milani disputes
the agency's determination that the firm's proposed price was
unreasonably low, reflected a lack of understanding of the
project requirements, and posed a performance risk. In this
respect, Milani argues that it was improper for the agency to
perform a price realism analysis because doing so in effect
constituted application of an unspecified evaluation criterion;
that Milani's prices--both by CLIN and overall--were not
unrealistically low; and that the agency's price realism
analysis was based on such limited information as to make its
conclusions unreasonable. Comments, Oct. 29, 2009, at 8-22. As
detailed below, we find the agency's decision to use a price
realism analysis as part of the source selection to be improper.
Before awarding a fixed-price contract, an agency is required to
determine that the price offered is fair and reasonable. Federal
Acquisition Regulation (FAR) sect. 15.402(a). An agency's
concern in making a price reasonableness determination focuses
primarily on whether the offered prices are higher than
warranted. See McDonnell Douglas Corp., B-259694.2, B‑259694.3,
June 16, 1995, 95-2 CPD para. 51 at 9. Although not required, an
agency may also provide for a price realism analysis in a
solicitation for the award of a fixed-price contract for the
purpose of assessing whether an offeror's low price reflects on
its understanding of the contract requirements or the risk
inherent in an offeror's approach. Grove Resource Solutions,
Inc., B-296228, B-296228.2, July 1, 2005, 2005 CPD para. 133 at
4-5. However, where there is no relevant evaluation criterion
pertaining to realism or understanding, a determination that an
offeror's price on a fixed-price contract is too low generally
concerns the offeror's responsibility, i.e., the offeror's
ability and capacity to successfully perform the contract at its
offered price. See J.A. Farrington Janitorial Servs., B-296875,
Oct. 18, 2005, 2005 CPD para. 187 at 4; CSE Constr., B-291268.2,
Dec. 16, 2002, 2002 CPD para. 207 at 4-5.
Here, there was no technical or price evaluation factor
providing for the evaluation of the offerors' understanding of
the requirements such that a price realism analysis was
reasonably foreseeable by the offerors. In this regard, the
price evaluation factor provided only for the evaluation of the
"reasonableness" of the proposed price (that is, whether the
offeror's price was unreasonably high), and whether the price
proposal was unbalanced, which is not contended here. See RFP
sect. M.1.C. Moreover, the RFP did not request cost or pricing
information or any other information that would allow the agency
to reasonably determine that a low proposed price reflected a
lack of understanding of the project requirements.
While the agency contends that the price realism analysis was
proper in light of certain language in the RFP, see DOI Email to
GAO, Dec. 14, 2009, we disagree. In our view, the solicitation
provisions to which the agency refers did not provide offerors
with adequate notice that NPS intended to perform a price
realism analysis, especially since the price evaluation
factor--under which such notice would logically appear--did not
in any way suggest that a price realism analysis would be
performed and offerors were not required to submit any cost or
pricing information that could be used in such an analysis. The
reference in RFP sect. M.1.B to "assessing the degree of risk
associated with the proposal," is simply too general to
constitute adequate notice that the agency would consider price
realism in the source selection decision. In this regard, since
the submission of even a "below-cost" price is not by itself
improper, see Arctic Slope World Servs., Inc., B-284481,
B-284481.2, Apr. 27, 2000, 2000 CPD para. 75 at 13, offerors
competing for award of a fixed-price contract must be given
reasonable notice that a business decision to submit a
low-priced proposal will be considered as reflecting on their
understanding or the risk associated with their proposal. See
CSE Constr., supra. The RFP here did not meet this standard of
reasonable notice. (Milani
Construction, LLC, B-401942, December 22, 2009) (pdf)
The RFP
contemplated the award of a fixed-labor-rate,
time-and-materials, incentive‑type contract to provide services
at up to 81 sites. Offerors were required to propose labor
categories, fixed labor rates, and the hours necessary to
perform each task at each location. The RFP included an
estimated number of hours the agency believed would be needed to
perform each task at each location, but noted that this was an
estimate only and that offerors were encouraged to propose
efficiencies that would allow them to perform with fewer than
the estimated hours. RFP at IV-5. The RFP provided that
cost/price would be evaluated for reasonableness, realism and
completeness; to be found realistic, prices were required to be
realistic for the work to be performed, reflect a clear
understanding of contract requirements, and be consistent with
the technical proposal. RFP at V-6.
CMI maintains that the agency unreasonably found Perot’s
proposed price to be realistic because it did not adequately
consider the fact that Perot proposed fewer hours than the
government estimated. More specifically, CMI asserts that the
agency did not analyze the distribution of lower hours among
labor categories, and did not compare Perot’s proposed hours to
the government estimate by line item.
Agencies are not required to conduct an in-depth analysis or
verify each and every item in conducting a realism analysis.
Id.; Innovative Techs. Corp., B-401689 et al., Nov. 9, 2009,
2009 CPD para. 235. Our review of an agency’s realism evaluation
is limited to determining whether it was reasonable and
consistent with the solicitation. Teledyne-Commodore, LLC,
B‑278408.5, B‑278408.6, Mar. 8, 1999, 99‑1 CPD para. 60 at 14.
In evaluating Perot’s price, the business evaluation team (BET)
was concerned that Perot’s proposed hours were lower than the
government estimate. Initial Business Evaluation Report, attach.
1, item 8. During discussions, the agency asked Perot to explain
why the reduced hours did not put the government at risk. Id. In
response, Perot, an incumbent subcontractor currently providing
services at approximately 50% of the sites, outlined its
methodology in developing its proposed labor hours [DELETED] Id.
Perot provided details explaining how it reached its
conclusions. For example, [DELETED] The BEC reviewed Perot’s
explanation and found it acceptable. The BEC then provided
Perot’s proposed labor hours to the technical evaluation
committee (TEC), which determined that Perot’s staffing was
adequate to perform given its proposed approach. Id.
The realism evaluation was unobjectionable. The agency was fully
aware that Perot proposed fewer labor hours than provided for in
the government estimate, and requested that Perot address its
resulting concern. Perot fully explained its approach, detailing
how its performance history as an incumbent subcontractor
demonstrated how labor hour efficiencies were possible and the
strategies it planned to utilize to ensure that it would meet
its proposed efficiencies. While the protester may disagree with
the agency’s ultimate judgment that Perot’s explanation was
sufficient to support its proposal, nothing on the face of
Perot’s explanation appears unreasonable, and CMI has not shown
that the agency’s conclusions regarding Perot’s labor hours were
incorrect or unreasonable. In this regard, the agency’s failure
to analyze labor hours across labor categories and line
items--as CMI asserts it should have done--is not a basis for
objecting to the evaluation; again, there is no requirement that
an agency follow a particular approach in its analysis, only
that the approach followed be reasonable. Innovative Techs.
Corp., supra. We conclude that the agency reasonably determined
that Perot’s low proposed labor hours did not render its price
unrealistic. (CMI Management,
Inc., B-402172; B-402172.2, January 26, 2010) (pdf)
Price Realism
Evaluation of the CSC Proposal
Both protesters maintain that the agency unreasonably concluded
that CSC's pricing was realistic. In this regard, the RFP
required the agency to evaluate price proposals for realism as
follows:
The Government will also evaluate the offeror's Total Evaluated
Price to determine fairness and reasonableness, as well as
realism. The Government will assess how well the Total Evaluated
Price realistically reflects an understanding of the
solicitation requirements as well as a consistency with the
approach proposed by the Offeror in the Volumes
I-IV proposals [volume I to III were to include the firms'
technical proposals while volume IV was to include the firms'
price proposals].
ARs, exhs. 10, at GD BATES 795, Unisys BATES 803.
Price realism need not necessarily be considered in the
evaluation of proposals for the award of a fixed-price contract,
because these contracts place the risk of loss upon the
contractor rather than the government. However, in light of
various negative impacts on both the agency and the contractor
that may result from an offeror's overly optimistic proposal, an
agency may, as TSA did here, expressly provide that a price
realism analysis will be performed in order to assess an
offeror's understanding of the requirements and/or the risk
inherent in a proposal. Health Net Fed. Servs., LLC, B-401652.3,
B-401652.5, Nov. 4, 2009, 2009 CPD para. 220 at 19. In reviewing
protests challenging an agency's evaluation of these matters,
our focus is on whether the agency acted reasonably and in a
manner consistent with the solicitation's requirements. Id.
Evaluation of CSC's Proposed Level of Effort
Unisys asserts that CSC's low proposed price should have been
found to be unrealistic because it reflected proposed staffing
that was both inadequate to meet the requirements of the RFP and
inconsistent with staffing information included in the firm's
technical/management proposal. The solicitation required
offerors to propose staffing in four areas--business activities
(BA), security (ITSEC), operational effectiveness (OE), and
solutions delivery (SD)--and Unisys claims that there were
significant disparities between the staffing in CSC's
technical/management proposal and its pricing proposal.
The record bears out Unisys's allegation regarding the staffing
disparity. In its technical/management proposal, CSC offered
[deleted] full-time equivalents (FTE), allocated among the four
staffing areas as follows: BA-[deleted], ITSEC-[deleted], OE-[deleted],
and SD‑[deleted]. ARs, exhs. 21, at GD BATES 4469, 4481; Unisys
BATES 4611, 4623. CSC's technical proposal further represented
as follows:
Exhibit 3-2 [showing this staffing profile] illustrates
our proposed staffing levels to perform the required services of
the solicitation. Team CSC is proactively engaged to achieve
this staffing at contract startup and throughout the life of
the contract.
Id. at GD BATES 4469, Unisys BATES 4611 (emphasis supplied).
Contrary to this representation, and in contrast to the staffing
profile in CSC's technical/management proposal, CSC's price
proposal contained staffing that decreased steadily through the
option years, to a level significantly below that outlined in
CSC's technical/ management proposal. The FTEs included in CSC's
price proposal were as follows:
|
NOTE: Table
deleted because it added nothing. All table
information was "deleted." |
CSC Price Proposal, at 28A-30B. Thus, by the final year of
contract performance, CSC's price proposal included [deleted]
fewer FTEs--an approximately [deleted] percent reduction--than
in its base year staffing.
We find nothing in CSC's proposal that adequately explains the
decline in option year staffing in its price proposal, or the
inconsistency between the staffing in its technical/ management
and price proposals, and it appears that the agency was not
aware of these staffing issues during the evaluation and award
process. Nonetheless, the agency states that the TMET reviewed
the technical/management proposals to determine whether adequate
staffing was offered by the firms and that, thereafter, the PET
reviewed the staffing in the price proposals to determine
whether it was consistent with the staffing in the
technical/management proposal. With respect to CSC's proposal,
the final price evaluation report states as follows:
Labor Hours/Categories
We tested the proposed hours in Volume IV Price to the Staffing
Plan in Volume II Management (of the tech proposals). In all
cases the Staffing Plan FTEs tied to the price proposals. The
Tech Team stated the Staffing Plans were adequate. We then had
the Tech team chair review the proposed labor categories for the
offerors and he determined that each offeror used realistic
categories and hours for their offered technical solution. The
three offerors proposed cost were determined to be realistic in
relation to their proposed ITIP SOW technical solution.
ARs, exhs. 29, at GD BATES 6785, Unisys BATES 7850. Since there
is no mention of the staffing disparity between CSC's
technical/management and price proposals, the price evaluators
appear not to have considered the disparity at the time their
views were memorialized in the price evaluation report.
The agency has submitted several affidavits from its evaluators
in an attempt to support its price realism evaluation of CSC's
proposal. The first of these affidavits, executed by the
chairman of the PET, states:
Labor Hours
We had a technical person as a member of the PET so he could
review the proposed labor hours. During discussions we had
questions to all Offerors about elements of the Basis of
estimates. Our technical person determined that CSC's proposed
labor hours were realistic. We also tested the proposed hours in
Volume IV Price to the Staffing Plans in Volume II Management
(of the tech proposals). In all cases the Staffing Plan FTEs
tied to the price proposals. The staffing plans show that CSC
proposed more FTEs than the other Offerors as shown in the table
below.
As a last element of the realism for labor hours we had the Tech
team chair review the proposed labor categories for the offerors
and he determined that each offeror used realistic categories
and hours for their offered technical solution. It should be
noted that the labor hour analysis included the hours of all
subcontractors. This way we could determine realism of the
entire contract not just of the prime contractors work. At no
time did the TET chair question the realism of CSC's proposed
hours or labor rates.
Affidavit of PET Chairman, Nov. 12, 2009, at 8. Below this
statement appeared a table in the affidavit that outlined what
were purportedly a comparison of the offerors' option 1 staffing
profiles. However, the hours noted in the table as included in
the CSC proposal are the hours in the technical/management
proposal, not the price proposal. Id. There is nothing in this
statement that indicates the chairman was aware of, or ever
considered, [deleted] or the disparity between the
technical/management and price proposal staffing.
The agency furnished a second affidavit from the PET chairman
elaborating on the representations in his first affidavit. That
affidavit states (in relevant part) as follows:
When the PET traced the staffing plan from the Management
proposal to the price proposal that was intended to verify
accuracy. I did make a mistake in the Price Report and in my
prior Declaration when I said the staffing plans were verified
to the Option Year 1. The Staffing plans were verified to the
Base Year of CSC Labor Distribution Table pages 28-A to 30-B. AR
Tab 26 at Unisys 06488-90. While this is a mistake it has no
bearing on the determination of realism of any of the proposals
because both the technical person on the PET and the TET chair
determined the proposed hours found within the CSC Proposal
Volume IV--Price Proposal bases of estimates were realistic for
CSC's approach.
Second Affidavit of PET Chairman, submitted by agency on Dec.
12, 2009, at 2.
We have no basis to question the chairman's explanation that
only the base year staffing was considered in the realism
evaluation. Indeed, this explanation is totally consistent with
the fact that, as noted, proposed staffing in the base year of
CSC's price proposal was similar to the staffing in its
technical/management proposal. However, the evaluation was to
include the option years and this statement still does not
address the option year staffing decline in the price proposal.
It certainly does not establish that the PET ever considered
these issues in the evaluation.
The agency also furnished an affidavit from the member of the
PET with expertise in the technical aspects of the requirement,
who actually performed the detailed price realism evaluation
referred to by the PET chairman; according to the agency, he was
selected to perform this evaluation because, in addition to
being capable of evaluating the proposed prices, he had the
technical expertise necessary to assess the offerors' proposed
solutions to meeting the agency's requirements. The PET
evaluator states that he read the price proposals and, where
necessary, the technical proposals, and that the focus of his
evaluation was on the offerors' respective bases of estimates (BOE).
More specifically, he states as follows:
[F]or this part of the evaluation I concentrated on BOE
Attachment 1, which lists details on each section including:
[deleted]. Attachment 1--BOE and Organization Charts, (pg 84-A
through 431) [deleted]. For each CLIN and each section of the
WBS, I verified that the proposed labor categories and the
number of hours were in my professional opinion sufficient and
reasonable to complete the work required by the SOW. Whenever I
had questions or areas of concern/focus, I referred back to the
specific sections of the SOW, the technical proposal and/or the
management proposal to verify that the required function was
adequately addressed either by CSC's approach, their experience,
the proposed tools, covered in another section/CLIN, or was
otherwise explained in sufficient detail as to present a
reasonable solution and low risk to the government. If any
questions or areas of focus remained I submitted them to the
Price Evaluation Team, which passed them to the Technical
Evaluation Team, and as appropriate to the Contracting Officer
(CO) for clarification or discussion.
An example of the process is CLIN Y-5-12-0000, described on page
394-A of the BOE. CSC proposed [deleted]. I verified this
against WBS section 5.12 and the SOW to ensure this was
permissible and a valid method of supporting the requirements.
This approach does represent a valid approach and per the BOE
for CLINs Y-3-01-0000 & Y-3-03-0000 there are sufficient and
appropriate resources to cover the function. The side effect of
this and similar methodologies proposed by CSC [deleted]. This
is a valid and arguably significantly more cost effective
approach [deleted].
Affidavit of PET Evaluator, at 2.
While we find no basis for questioning the PET evaluator's
statement that CSC was able to achieve certain efficiencies with
its proposed staffing approach (and correspondingly reduce its
overall staffing profile), this statement--as with the two
statements by the PET chairman--does not address the fact that
the staffing proposed in CSC's price proposal decreased
significantly--by [deleted] FTE--in the option years of the
contract and was inconsistent with the staffing in CSC's
technical/management proposal.
We conclude that there is no indication in the record that the
agency considered in the evaluation either the significant
staffing decrease in the option years under CSC's price
proposal, or the staffing inconsistency between CSC's price
proposal and technical/management proposal. Meanwhile, it
appears that the TMET based its technical findings and ratings
of CSC's technical/management proposal on the underlying
assumption that CSC was offering the staffing indicated in its
technical/management proposal which contained the [deleted]
staffing numbers. In light of the significantly
different—[deleted]--staffing in CSC's price proposal, this
assumption, without some explanation for the staffing
inconsistency between the technical/management and the price
proposals, was unwarranted. The staffing decline and disparity
bear on both the realism and technical quality of CSC's
proposal. It follows that the agency's evaluation conclusions
that CSC's proposal was technically superior to the other two
firms' proposals, and that its price was realistic, necessarily
is not supported by the record. Pemco Aeroplex, Inc., B-310372,
Dec. 27, 2007, 2007 CPD para. 2 at 10-12. Accordingly, we
sustain this aspect of the protests.
Evaluation of CSC's Low Labor Rates
Both GD and Unisys assert that the agency's realism analysis
failed to give adequate consideration to CSC's comparatively low
proposed labor rates in light of the firm's proposal to hire
incumbent personnel to perform the requirement. The protesters
assert that such consideration was necessary for the purpose of
determining whether CSC's proposed pricing (labor rates) was
consistent with its proposed technical approach of hiring
incumbent personnel. GD notes in this regard, for example, that
the agency's evaluation found that CSC had the lowest proposed
labor rates (among the three offerors) for [deleted] of the
contract's 71 labor categories and that, within those
categories, CSC's proposed rates are significantly--in some
cases more than [deleted] percent--lower than the rates proposed
by Unisys, the incumbent contractor. ARs, exhs. 29, at GD BATES
6780-6782, Unisys BATES 7845-7847. The protesters maintain that
these low rates should have led the agency to question CSC's
ability to implement its plan to hire incumbent personnel.
The agency responds, first, that the labor rates in all three of
the offerors' contracts are not wage rates, but fully burdened
hourly rates for categories of employees. The agency maintains
that a comparison of the proposed labor rates alone therefore
does not necessarily show that the actual wages to be paid by
CSC are lower than the wages proposed by the incumbent. The
agency also asserts that it considered the fact that CSC's
proposal included the lowest proposed labor rates for many of
the contract labor categories, but concluded that this would not
be problematic because, for several key employee categories, CSC
had offered the highest wages among all of the offerors; the
agency reasoned that CSC would be able to attract the incumbent
employees for these key personnel positions, and that its rates
for the remaining labor categories were 'competitive." ARs, exhs.
30, at GD BATES 6807, Unisys BATES 7872.
We agree with the protesters that the evaluation in this area
was unreasonable. First, the agency has presented, and the
record contains, no evidence or information supporting its
assertion that the comparison of CSC's and Unisys's fully
burdened labor rates would not be meaningful because a
comparison of these burdened rates would not effectively reflect
the difference in the wages that actually will be paid. More
specifically, the agency has not shown that it ever determined
that there really was no substantial difference in the wage rate
component of the burdened rates, and that the apparent
difference was explained, for instance, by a substantial
disparity in the two firms' indirect rates. To the extent that
the agency evaluated the offerors' proposed rates, its
evaluation was confined to a comparison of the fully burdened
labor rates. ARs exhs. 29, at GD BATES 6780-6782; Unisys BATES
7845-7847. In the absence of such an analysis, there is no
support in the record for the agency's assertion that the firms
actually could--or would--pay similar wages, even though their
proposed labor rates were dramatically different.
Second, it appears fundamentally inconsistent for the agency to
assert, on the one hand, that the labor rates are not a
meaningful basis for evaluation, and then, on the other hand, to
state that it relied on the firms' comparative labor rates in
finding that certain CSC high labor rates would better enable it
to recruit, hire and retain a number of key personnel who would
ensure CSC's successful performance. ARs. exhs. 30, at GD BATES
6807‑6808, Unisys BATES 7871-7872; Affidavit of Contracting
Officer, Dec. 10, 2009, at 2-3. If, as the agency suggests, the
firms' proposed labor rates provided no meaningful insight into
wages actually to be paid, then it was unreasonable for the
agency to rely on those same proposed rates to support a
favorable evaluation of CSC's ability to recruit, hire and
retain certain key personnel.
Third, not only is the agency's litigation position--that
comparing CSC's labor rates to the incumbent's rates would not
be meaningful--not reflected in the contemporaneous record, the
record shows that, on the contrary, some concern was raised
during the evaluation that CSC's proposed labor rates were so
low as to indicate a risk that CSC would be unable to hire
incumbent employees, as it proposed to do. Specifically, after
the source selection recommendation was presented to the SSAC
(which was comprised of the heads of each of the four functional
areas under the task order), the director of the operational
effectiveness (OE) division (one of the members of the SSAC)
expressed concern regarding CSC's low proposed labor rates,
stating:
Headquarters/Field/FC -- Based on the low labor rates provided
by CSC, I feel that an evaluation of their rates be conducted to
determine whether or not the successful hiring of incumbent
staff could be accomplished. Not being able to hire incumbent
staff members would pose a major risk to our daily operations
based on the incumbents institutional knowledge of TSA and the
customers that they support.
ARs, exhs. 31, at GD BATES 6820, Unisys BATES 7885. The record
shows the agency determined that this concern was overstated
because the OE division was 'not the most important subfactor
within the factor." Contracting Officer's Affidavit, Dec. 10,
2009, at 4. The contracting officer explains, in this regard, as
follows:
On September 1, 2009, the SSAC was reconvened to address the
SSAC member memos [one of which is quoted above] and the SSA
comments to v [version] 3.2 of the Source Selection
Recommendation. During this meeting I addressed with [the
Director of the OE division] and the rest of the SSAC the
analysis of CSC's proposed labor rates. In addition, I affirmed
that OE was not the most important subfactor within the factor
and the evaluation team had determined the technical approach to
be realistic and the level of staffing to support the approach
to be realistic. I asked the SSAC if [the Director of the OE
division's] concerns were of such a magnitude [as to merit my]
direct[ing] the evaluation team to go back and look at the
proposal for OE again. [The Director of the OE division] stated
that given the order of importance he believed his concerns
associated with CSC's proposal were acceptable and manageable by
TSA and CSC management. The SSAC concurred with [the Director of
the OE division] and agreed that the risk associated with CSC's
support of OE were not unreasonable and expected during a
transition of this size, scope and complexity and should not by
itself prevent CSC from receiving award . . . .
CO Affidavit, Dec. 10, 2009, at 4. The record also contains an
affidavit in which the SSA also describes the meeting discussed
by the contracting officer above, and states further that, in
light of that discussion, she considered the matter 'closed."
SSA Affidavit, Dec. 11, 2009, at 2. The agency's briefs and
other submissions similarly suggest that it viewed this concern
as limited to the OE area. See, e.g., Supplemental Agency
Report, GD Protest, at 6-8.
The above suggests that the agency ultimately disregarded CSC's
low labor rates, not because there was no basis for comparing
them to the incumbent rates, but because it concluded that the
impact of the low rates was limited to the OE division. To the
extent that this was the case, the agency's conclusion was not
based on a complete examination of the proposed labor rates,
since CSC's proposed labor rates were low by a significant
margin across the board. Thus, the impact from any difficulties
CSC experienced in recruiting incumbent employees based on
inadequate compensation would not be limited to the OE division,
but would extend to the entire contract effort in all functional
areas. Simply stated, the fact that only the agency's OE
director expressed concern about CSC's low labor rates did not
provide a reasonable basis for the agency to conclude that the
impact of low wage rates would be limited to the director's area
of responsibility.
Finally, the record shows, that there was no reasonable basis
for the agency to be unconcerned with CSC's comparatively low
labor rates in the main, based on the fact that, for a few
select labor categories, CSC offered the highest labor rates.
The record shows that the number of labor categories considered
by the agency in its analysis was [deleted][14], ARs, exhs. 30,
at GD BATES 6807, Unisys BATES 7872, Contracting Officer's
Affidavit, Dec. 10, 2009, at 2-3, and the number of employees
proposed in these categories by CSC ([deleted] in the base year,
declining to [deleted] in the final option year) is low in
relation to the overall number of staff proposed by CSC
([deleted] in the base year, declining to [deleted] in the
fourth option year). CSC Price Proposal, at 28‑A-30-B.
Accordingly, it is not clear why CSC's high proposed rates for
these key employees would be viewed as eliminating the need to
consider CSC's low rates under the other labor categories, which
include the overwhelming majority of CSC's proposed staff
([deleted] employees in the base year, declining to [deleted]
employees in the fourth option year). Id.
The record thus shows that CSC's staffing strategy contemplated
hiring incumbent personnel, but offered labor rates that were
significantly lower than the rates proposed by the incumbent.
The agency's failure to consider this price realism concern in
both its price and technical evaluations was unreasonable, and
we therefore also sustain this aspect of the protests.
In sum, and as noted at the outset of our discussion, agencies
are not necessarily required to perform realism evaluations in
fixed price contract settings. Nonetheless, if the agency
undertakes to do so, as was the case here, its evaluation must
be consistent with the provisions of the FAR governing the
conduct of price realism evaluations, and more specifically,
with any evaluation standards established in the solicitation.
Here, the RFP provided generally for the agency to assess the
realism of the proposed prices, and more specifically called for
an evaluation of the consistency between the
technical/management and price proposals, as well as an
assessment of how well the firms' prices realistically reflected
an understanding of the solicitation's requirements.
As the foregoing discussion demonstrates, the agency here did
not observe, much less analyze, the fact that the staffing
included in CSC's proposed pricing was inconsistent with the
staffing proposed in its technical/management proposal; nor did
the agency analyze the degree to which CSC's proposed
prices--specifically its proposed labor rates--would enable it
to implement its offered technical solution of hiring incumbent
staff. Although the agency's numerous post hoc assertions have
necessitated a somewhat lengthy discussion of these
considerations, nonetheless, the agency has failed to establish
that it performed an adequate price realism evaluation. (General
Dynamics One Source, LLC; Unisys Corporation, B-400340.5;
B-400340.6, January 20, 2010) (pdf)
LexisNexis argues
that the agency conducted an improper price evaluation because,
in the protester's words, the agency "evaluated price based on a
15,240 user basis of total price for all CLINs, instead of
evaluating based on the CLINs as specified in the solicitation."
Initial Protest at 19. The protester also contends it was misled
about the agency's intended pricing evaluation during
discussions. LexisNexis maintains that had it known the Air
Force was going to evaluate price based on an all user
population, it would have offered a significantly lower price to
the Air Force. We see no merit to either argument.
Before turning to the specifics of the agency's price
evaluation, we note, as a preliminary matter, that the
protester's arguments are based on an apparent misunderstanding
during the debriefing between representatives of the Air Force
and LexisNexis. In essence, LexisNexis left the debriefing with
the view that the Air Force evaluated prices in a manner
different from the stated evaluation scheme.
Our standard of review for a price evaluation is to determine
whether it was reasonable and consistent with the solicitation's
evaluation criteria. The Arora Group, Inc., B-277674, Nov. 10,
1997, 98-1 CPD para. 64 at 4. Based on our review of the record
here, we see no support for the protester's contentions.
As explained above, the RFP clearly stated that offerors were to
insert proposed unit and extended prices in the pricing
schedule. The RFP then stated that offerors' proposed prices
would be determined by multiplying the quantities identified in
the price schedule by the proposed unit price for each CLIN to
confirm the extended amount for each. The extended amounts would
then be added together to determine the total evaluated price.
This is exactly how the agency performed its price evaluation.
While the protester argues that the RFP (and the ENs provided
during discussions) led it to propose pricing that was based on
economies of scale for each individual CLIN, it is clear that
the pricing strategy used by the protester was not required by
the RFP. The RFP required only that offerors provide pricing for
each individual CLIN and that this price be multiplied by the
listed quantities for that CLIN to determine the extended price.
We also do not think the ENs issued to the protester were
misleading. During discussions, the agency expressed concern
that the protester's prices appeared to be unbalanced in that
some CLINs were discounted, while others contained higher
prices. As previously stated, the RFP specifically stated that
prices were to be evaluated to determine if they are unbalanced.
Moreover, the protester has not suggested how the price
evaluation should have been conducted in order to be based
purely on a per-CLIN basis. In any event, the record shows that
for all CLINs, except one, West's proposed per user/total price
was lower than the protester's proposed price. AR, Tab 22, Price
Memo at 4.
The protest is denied. (LexisNexis,
B-402114, December 30, 2009) (pdf)
Health Net challenges TMA’s price/cost evaluation in several
respects. Among other things, Health Net contends that TMA’s
price realism evaluation regarding AGHP’s proposal was flawed
because it failed to reasonably consider AGHP’s low staffing for
PMPM. Health Net also argues that TMA failed to reasonably
consider whether AGHP’s proposed employee compensation posed a
risk to AGHP’s proposed plan to hire large numbers of incumbent
employees. We agree.
Price realism is not ordinarily considered in the evaluation of
proposals for the award of a fixed-price contract, because these
contracts place the risk of loss upon the contractor. However,
in light of various negative impacts on both the agency and the
contractor that may result from an offeror’s overly optimistic
proposal, an agency may, as here, expressly provide that a price
realism analysis will be applied in order to measure the
offeror’s understanding of the requirements and/or to assess the
risk inherent in an offeror’s proposal. See, e.g., Wackenhut
Servs., Inc., B-286037, B‑286037.2, Nov. 14, 2000, 2001 CPD para.
114 at 3; Molina Eng’g, Ltd./Tri-J Indus., Inc. Joint Venture,
B-284895, May 22, 2000, 2000 CPD para. 86 at 4. Although the FAR
identifies permissible price analysis techniques, FAR sect.
15.404-1, it does not mandate any particular approach; rather,
the nature and extent of a price realism analysis, as well as an
assessment of potential risk associated with a proposed price,
are generally within the sound exercise of the agency’s
discretion. See Comprehensive Health Servs., Inc., B‑310553,
Dec. 27, 2007, 2008 CPD para. 9 at 8; Legacy Mgmt. Solutions,
LLC, B‑299981.2, B-299981.4, Oct. 10, 2007, 2007 CPD para.197 at
3. In reviewing protests challenging an agency’s evaluation of
these matters, our focus is whether the agency acted reasonably
and in a way consistent with the solicitation’s requirements.
See, e.g., Grove Res. Solutions, Inc., B‑296228, B-296228.2,
July 1, 2005, 2005 CPD para. 133 at 4-5.
The record reflects that CLIN X009, PMPM, accounted for
[Deleted] of the price differential between AGHP’s and Health
Net’s proposals. TMA’s price/cost Chairperson attributed this
difference to [Deleted] factors: [Deleted] and FTEs. As noted
above, in her report, the price/cost Chairperson noted
significant differences in the AGHP and Health Net proposed
direct-labor FTE staffing for this CLIN, with AGHP maintaining
[Deleted] fewer FTEs than Health Net (a difference of [Deleted])
for the first year, with the difference increasing to [Deleted]
FTEs [Deleted] in year 5. AR, Tab 12, Price/Cost Report, at 8.
Acknowledging AGHP’s lower FTE staffing for PMPM, the price/cost
Chairperson noted that the TET had “concluded that Aetna
proposed adequate staffing to perform the contract
requirements.” AR, Tab 12, Price/Cost Report, at 8. The record
reflects, however, that the TET was not privy to offerors’
proposed staffing by CLIN for either offeror; rather, the TET
only reviewed Health Net’s and AGHP’s staffing for year 1 by
“function” in the context of their overall staffing, as
identified in each offeror’s technical proposal. Thus, the
technical team never in fact specifically reviewed or evaluated
Health Net’s or AGHP’s staffing for the PMPM CLIN, or any other
CLIN for that matter. Tr. at 1069, 1092, 1196. Given the TET’s
lack of information or analysis regarding this matter, to the
extent the price/cost Chairperson relied on the TET’s staffing
assessments for Health Net and AGHP, it did not provide any
technical analysis regarding the widely disparate labor
allocations between the offerors for the PMPM CLIN. Moreover,
the price/cost Chairperson indicated that she lacked a technical
understanding of how the offerors would perform the work and did
not necessarily know which functions corresponded to the various
CLINs. Tr. at 1070.
Evidently, in an effort to assess whether AGHP’s staffing was
too low for the PMPM CLIN, and thereby reflected a lack of
understanding of the technical requirements or created
performance risk, the price/cost Chairperson compared all
offerors’ proposed staffing across all regions. Although
unstated, it appears that given her lack of technical
understanding, the price/cost Chairperson’s rationale for
performing this high level comparison across regions was that if
Health Net’s and AGHP’s total staffing, (which the TET had found
to be adequate) was in line or out of line with the proposed
staffing of other offerors, then, by analogy, one could conclude
that Health Net’s and AGHP’s PMPM staffing was similarly either
in line or out of line with other offerors’. Depending on the
outcome of this comparison, the price/cost Chairperson would
then be able to determine whether the staffing difference was
meaningful. Ultimately finding that Health Net had the
[Deleted], and AGHP did not have the lowest total staffing, it
appears that the price/cost Chairperson concluded that the PMPM
staffing differential was likely due to the fact that Health
Net’s overall approach was based on using higher staffing, and
thus while AGHP had lower PMPM staffing, AGHP’s staffing was not
indicative of a lack of understanding nor would it appear to
present technical risk. AR, Tab 12a, Price/Cost Work Papers, at
73.
As an initial matter, we find such a high level comparison of
total staffing to be of limited value in analyzing the realism
associated with staffing for individual CLINs. Rather, one would
expect the TET to have considered the offeror’s staffing at the
CLIN level to assess whether the proposed staffing was
realistic, or reflected a lack of technical understanding or
created performance risk based on the specific technical
approach of the offeror. See FAR sect. 15.404-1 (realism
analysis based on “unique methods of performance and materials
described in the offeror’s technical proposal”); Hughes STX
Corp., B-278466, Feb. 2, 1998, 98-1 CPD para. 52 at 8
(sustaining protest where agency failed to consider offeror’s
technical approach as part of realism evaluation). Thus, any
comparison of offerors’ staffing for the purpose of assessing
realism is an inherently limited methodology given the
requirement to consider each offeror’s unique technical
approach. In any event, as explained below, the price/cost
Chairperson’s evaluation was inherently flawed because in
performing her high-level comparison of total staffing, she
based her comparison on total staffing levels, which were never
in fact considered by the TET and therefore had not been
assessed for technical capability to meet CLIN requirements.
This disconnect severed the link, already tenuous, between the
TET’s technical findings regarding offerors’ overall staffing
and the price/cost Chairperson’s efforts to gain insight
regarding the significant staffing differential for the PMPM
CLIN.
The RFP required offerors to submit a staffing chart as part of
their technical proposals, showing “all staffing” needed to
perform the T-3 requirements. RFP at 102. In their technical
proposals, all offerors, for all regions, submitted their total
staffing charts, which provided the basis for the TET’s
technical evaluation. Tr. 1058, 1189-90. Although not required,
some offerors, in their technical proposal staffing charts,
identified staffing positions as corresponding to “direct” FTEs,
and categorized others as “indirect” FTEs. The TET, however, as
noted above, based its technical evaluation on total staffing,
without regard to whether the FTEs had been identified as
“direct” or “indirect.”
In her total staffing comparison, however, the price/cost
Chairperson admittedly only compared offerors’ total proposed
“direct” FTEs. This had the effect of carving out significant
numbers of FTEs from several offerors’ proposals when comparing
total staffing. Using an “average direct” FTE analysis, as the
Price/Cost Chairperson did, the resulting comparison was as
follows:
(table deleted because
useful information was deleted from table)
AR, Tab 12a, Price/Cost
Working Papers, at 73; Price/Cost Chairperson Declaration, Sept.
10, 2009.
When comparing all offerors’ total staffing, including their
direct and indirect FTEs, as the TET had evaluated them, a
different picture emerges, with Health Net positioned towards
the middle, and AGHP second from the bottom:
(table deleted because
useful information was deleted from table)
Protester’s Filing
Regarding FTEs & Price Realism, Sept. 29, 2009, Second Supp.
Decl. of Protester’s Consultant, at 2.
By focusing her comparison on “average direct” FTEs, the
price/cost Chairperson’s comparison did not align with the
underlying basis for the TET’s technical findings, which were
based on all staffing, as proposed by the offerors, to include
direct and indirect FTEs, and, given her admitted limited
ability to make technical evaluations, her analysis could not
have provided a reliable substitute for determining AGHP’s
technical understanding or proposal risk. Moreover, with Health
Net towards the middle, and AGHP towards the bottom, of total
proposed FTEs, as staffing had been evaluated by the TET, the
very premise of TMA’s determination that the large difference in
PMPM staffing between offerors was merely a reflection of Health
Net’s generally high staffing approach, is without a basis.
TMA argues that it was proper to consider only direct FTEs since
offerors were only asked to submit direct FTE staffing with
their price/cost proposals, and because there is great
variability in how offerors account for “indirect” staff in
building up their prices. TMA explains that, depending on the
offerors’ various accounting methodologies, some offerors may
choose to identify all their staffing as direct FTEs, while
others may identify indirect FTEs, or not identify indirect
staffing at all, rather including it as part of their general
and administrative rates. According to TMA, such an evaluation
would be comparing “apples-to-oranges.” We find TMA’s arguments
to be unpersuasive.
First, TMA in fact required AGHP, and other offerors, to provide
a crosswalk of FTEs to specifically address any differences
between staffing in their technical and price proposals. The
crosswalk submitted by AGHP specifically identifies its total
staffing, not merely AGHP’s direct staffing. AR, Tab 73, AGHP
Price/Cost Proposal, at 774-778. Moreover, the record reflects
that the price proposals for all offerors identified their total
staffing, including direct and indirect FTEs. Regarding the
second issue, TMA mistakenly highlights different ways that
offerors build up their prices as a basis for not knowing how
their staffing compared, when a true apples-to-apples comparison
in fact existed in the offerors’ “total staffing,” which they
were required to identify in their technical proposals. RFP at
95. This staffing, which was to reflect “total staffing”
necessary to perform the requirements, was to be identified
regardless of how the offeror built up its price and whether it
reflected direct or indirect FTEs.
In assessing realism, TMA also failed to reasonably assess
whether AGHP’s proposed technical approach of hiring incumbent
employees was realistic. In its technical proposal, AGHP clearly
indicated that it intended to hire a “high percentage” of the
outgoing contractor’s employees, to include “managers” for the
purpose of performing certain functions, to include case
management, activities at the TSCs, and call center operations.
AR, Tab 72, AGHP Final Technical Proposal, at 233, 299-300.
Moreover, in its price/cost proposal, AGHP added some greater
specificity to its plans, stating that it anticipated hiring
[Deleted] of its TSC staff and [Deleted] of the Hampton,
Virginia (“Tidewater”) Operations Center staff from the outgoing
contractor, Health Net. AGHP had proposed 252.25 FTEs for the
TSCs and 288.75 FTEs at the Tidewater Operations Center. AR, Tab
72, AGHP Final Technical Proposal, at 386.
In this regard, the TET Chairperson testified that AGHP’s
approach was “to hire outgoing staff from Health Net,
particularly in TRICARE service centers and at the [Tidewater
Operations Center].” Tr. at 1241. She further explained that the
TET believed this to be a “good practice,” and that it reflected
“clear advantages,” particularly with respect to customer
service activities. Tr. at 1242-43. The record also reflects
that AGHP was assigned a rating of “low risk” regarding its
approach to the “beneficiary satisfaction/customer service”
subfactor.
Health Net argues that, notwithstanding AGHP’s proposed plan to
hire “high percentages” of Health Net’s employees and the
advantages accompanying such an approach, TMA never in fact
considered whether AGHP’s approach in this regard was realistic
because it never compared AGHP’s proposed compensation to the
compensation that Health Net is providing. According to Health
Net, had TMA done such a comparison, TMA would have realized
that AGHP’s proposed compensation was significantly lower than
Health Net’s, thereby undermining AGHP’s ability to achieve its
plan to capture the incumbent workforce.
In its defense, TMA maintains that there is nothing to suggest
that AGHP would not simply pay the difference. Because AGHP has
demonstrated a willingness to absorb large costs in other areas,
TMA argues “it cannot logically be argued that AGHP would not
pay a few dollars more per hour to a handful of employees if
that is what it took to perform the contract.” TMA’s Second
Agency Report, at 84. This argument, however, fundamentally
misunderstands the nature of a fixed-price contract. If AGHP’s
technical approach of hiring the incumbent workforce proves more
costly than anticipated, AGHP, because it bears the risk, has
two options: either pay more to hire these individuals, and
thereby take less profit than anticipated, or simply hire
non‑incumbents at a lower rate. The latter of the two options,
however, would not achieve the advantages associated with AGHP’s
proposed approach. A proper realism evaluation alerts agencies
to those aspects of an offeror’s technical proposal which do not
appear to be feasible based on what the offeror has indicated in
its price proposal. As a consequence, on the record here, we
find that TMA failed to consider the realism of AGHP’s proposed
approach based on hiring the incumbent workforce. Cf. Magellan
Health Servs., B‑298912, Jan. 5, 2007, 2007 CPD para. 81 at
16-17 (sustaining protest challenging agency’s cost realism
evaluation where the agency failed to reasonably adjust
awardee’s costs based on its proposed approach to capture the
incumbent workforce). (Health
Net Federal Services, LLC, B-401652.3; B-401652.5, November
4, 2009) (pdf)
EMS challenges the Navy's determination that its proposed price
was unreasonable. First, EMS asserts that there were several
flaws in the original IGE used by the agency in evaluating
initial proposals. EMS Letter, Sept. 4, 2009, at 5. For example,
EMS points-out that the original IGE was not revised to reflect
deletion from the RFP of a requirement for dry ice ventilation
cleaning and asserts that the Navy's decision to leave the IGE
"as is" was based on an improper hypothetical calculation of
what the remaining services would cost, without a comprehensive
review and market analysis. Id. at 6. Further, EMS asserts that
the Navy's use of the IGE was not based on market research and
did not involve "careful consideration of the products or
services being acquired." Id. at 5.
These arguments are without merit. First, as the Navy points
out, while the original IGE challenged by the protester was used
in the initial evaluation, it was not used in the evaluation of
FPRs. Navy Letter, Sept. 10, 2009, at 4. Rather, the Navy's
evaluation was based on the IGE as revised following issuance of
amendment No. 8, together with a comparison with other proposed
prices. As discussed, the IGE revisions were aimed at resolving
the CLIN discrepancies underlying the protester's challenge to
the original IGE. Id.; PNM at 7. EMS also challenges the revised
IGE, asserting that the Navy "fails to explain how the [revised]
IGE was calculated or to give any indication that it was
prepared any differently than the first IGE or the 'market'
average." EMS Letter, Sept. 17, 2009, at 2. However, this
assertion fails to state a valid basis of protest, since the
protester has provided no argument or evidence indicating that
the new IGE may have been erroneous. See, e.g., Saturn Landscape
Plus, Inc., B-297450.3, Apr. 18, 2006, 2006 CPD para. 70 at 9.
For example, unlike its challenge to the original IGE, EMS does
not identify any specific alleged flaws in the revised IGE. The
Navy was not required to "explain" its IGE in the absence of a
valid protest assertion that the IGE is in some way erroneous.
EMS asserts that the agency's reliance on a comparison of
offerors' prices was unreasonable, since it included only the
proposed prices, rather than prices in the "larger market
place." EMS Letter, Sept. 4, 2009, at 6. This argument is
without merit. The FAR specifically provides that a price
reasonableness determination may be based on a comparison of
prices received in response to the solicitation. FAR sect.
15.404-1(b)(2)(i); Comprehensive Health Servs., Inc., B‑310553,
Dec. 27, 2007, 2008 CPD para. 9 at 8. There is no requirement
that an agency consider broader marketplace prices in its
analysis.
Before awarding a fixed-price contract, an agency is required to
determine that the offered price is fair and reasonable, FAR
sect. 15.402(a); CSE Constr., B-291268.2, Dec. 16, 2002, 2002
CPD para. 207 at 4. Because the Navy found EMS's proposed price
to be unreasonable, EMS was ineligible for award. (EMS
Ice, Inc., B-401688.3; B-401688.6, October 8, 2009) (pdf)
Offerors were required to submit a fixed-price coefficient
multiplier for several areas identified in the RFP. The
coefficients proposed by the offerors were to be multiplied by
the unit prices in the RS Means (RSM) Facilities Construction
Cost Data Book, a trade publication, to calculate a price
for individual task orders. The RFP further provided that these
coefficients must include, among other items, contractor's and
subcontractor's overhead and profit; insurance; all costs
associated with bonding; employee payroll taxes, insurance and
fringe benefits; business taxes; and sales taxes. The RFP stated
that each coefficient would be evaluated to determine cost
reasonableness and completeness of the coefficient in terms of
the agency's requirement. Id.
(sections deleted)
The RFP provided that price would
be evaluated using price and/or cost analysis techniques to
determine the reasonableness and completeness of each offeror's
proposed coefficient. RFP, amend. 2, at 68. The RFP stated that
the government was interested in proposals that offer value in
meeting the requirements, with an acceptable performance risk,
at a fair and reasonable price. Id.
Price realism is not ordinarily a consideration in fixed-price
contracts, since the risk of performing the contract at the
proposed price is borne by the contractor. Here, however, the
agency elected to use a price realism review not to evaluate
prices, but to assess the risk of poor performance in an
offeror's approach and to measure each offeror's understanding
of the solicitation's technical requirements. PHP Healthcare
Corp., B-251933, May 13, 1993, 93-1 CPD para. 381 at 5. The
manner in which a price realism analysis is conducted is a
matter subject to a contracting agency's sound discretion, which
we will not disturb unless it lacks a reasonable basis. OMV
Med., Inc., B-281490, Feb. 16, 1999, 99-1 CPD para. 38 at 8.
In our view, the agency's price realism analysis was reasonable.
DMS's protest is primarily based on its belief that the agency
simply compared the proposed coefficients and did not consider
He & I's substantial reductions in price over the course of this
extended procurement. DMS also contends that He & I's price
coefficient does not contain all the elements required by the
RFP.
The record shows that the agency specifically determined that
each offeror's total proposed coefficients were realistic based
on each offeror's understanding of the complexity and risk
associated with the requirement. AR, Tab 35, Source Selection
Document at 12. In this regard, the price analysis recognized
that He & I calculated its coefficient factors using the latest
five years of actual historical cost figures derived from 222
actual job order contract projects at Fort Sill, as well as
using the 2009 Means Facility Construction Cost Data. AR, Tab
34, Price Evaluation Report, FPR at 3. In fact, the agency
specifically found that He & I's proposal actually posed
significantly less risk than the other proposals. Id.
To the extent that DMS argues that He & I omitted certain cost
elements from its coefficient calculation, DMS's complaint
amounts to no more than a challenge to He & I's submission of a
below-cost proposal. Such a complaint does not provide a basis
for protest as there is no prohibition against an agency's
decision to accept a below-cost proposal on a fixed-price
contract. Ocean House Builders, B-283057, Sept. 21, 1999, 99-2
CPD para. 53 at 6. To the extent DMS is arguing that He & I
cannot perform this work at its proposed price, this matter
concerns He & I's responsibility. We will not consider protests
challenging affirmative determinations of responsibility except
under limited, specified exceptions that are not applicable
here. 4 C.F.R. sect. 21.5(c) (2009); T. F. Boyle Transp., Inc.,
B-310708, B-310708.2, Jan. 29, 2008, 2008 CPD para. 52 at 5. As
explained above, the agency specifically determined that He &
I's low coefficient did not indicate a lack of understanding of
the requirement. On this record, we have no basis to conclude
that this determination was unreasonable. (DMS-All
Star Joint Venture, B-310932.6; B-310932.7,October 9, 2009)
(pdf)
FedSys argues that the Army's cost realism evaluation made two
unreasonable adjustments to the protester's proposed costs.
These two adjustments increased FedSys' evaluated costs by
approximately $[deleted] million, and narrowed the difference
between FedSys' costs and ATS's higher costs from approximately
[deleted] percent to approximately 3 percent. For the reasons
discussed below, we find no merit to the protester's arguments.
When an agency evaluates a proposal for the award of a
cost-reimbursement contract, an offeror's proposed estimated
costs are not dispositive because, regardless of the costs
proposed, the government is bound to pay the contractor its
actual and allowable costs. Federal Acquisition Regulation (FAR)
sections 15.305(a)(1); 15.404-1(d); Palmetto GBA, LLC, B-298962,
B-298962.2, Jan. 16, 2007, 2007 CPD para. 25 at 7. Consequently,
the agency must perform a cost realism analysis to determine the
extent to which an offeror's proposed costs are realistic for
the work to be performed. FAR sect. 15.404-1(d)(1).
First, the protester contends that the agency made an improper
adjustment to its proposed labor hours. As discussed above,
offerors were required to propose 40 hour workweeks for CONUS
employees, 80 hour workweeks for OCONUS employees, and were
advised that OCONUS labor costs should include a premium for
hazard and hardship pay. RFP amend. 2, Q&A 1; RFP amend. 2, Q&A
18. The protester's cost proposal, however, stated that FedSys
and O'Gara personnel, both CONUS and OCONUS, would work
[deleted] hours per year--corresponding to 40 hour workweeks.
AR, Tab 15, FedSys Cost Proposal, Schedule 1 (FedSys Direct
Labor); Schedule 2 (O'Gara Direct Labor). The cost proposal did
not state whether hazard and premium pay was included. Id. In
response, the Army adjusted the proposed OCONUS salaries for
FedSys and O'Gara, to account for 80 hour workweeks, and to add
a 35 percent premium for hazard and hardship pay. AR, Tab 9,
Cost and Price Analysis, at 4, 10.
FedSys concedes that its cost proposal worksheets showed 40 hour
workweeks for its OCONUS personnel, rather than the 80 hour
workweeks required by the RFP. Protester's Comments on AR at
3-4. FedSys argues, however, that the cost adjustment was not
warranted because the proposed salaries were correct, and the
proposal’s reference to [deleted] hours per year, rather than
[deleted] hours per year, was simply an error. In this regard,
the protester points to its higher proposed salaries for OCONUS
personnel--which were more than twice those proposed for CONUS
personnel--as evidence that it was offering both the higher
hours and hardship and hazard pay, and argues that it should
have been clear to the Army that the proposal was compliant with
the terms of the solicitation. Id. In addition, the protester
argues that the agency's adjustment of the OCONUS salaries led
to an "absurd" result, whereby the evaluated salaries for OCONUS
personnel were two to three times higher than proposed, and more
than five times higher than it proposed for CONUS personnel.
To the extent the protester argues that the agency should have
understood or inferred that the higher salaries were intended to
reflect the protester intention to propose 80 hour workweeks for
OCONUS personnel, we disagree. The protester's proposal, on its
face, listed salaries and labor rates for OCONUS personnel, but
indicated that those rates and salaries applied to 40 hour
workweeks. The protester does not argue, and the record does not
show, that the proposal explained that the higher salaries for
OCONUS personnel were intended to reflect 80 hour workweeks or
hazard and hardship pay.
Moreover, we do not agree with the protester's contention that
the salaries proposed for OCONUS personnel clearly demonstrate
that the protester intended for the higher salaries to cover 80
hour workweeks and hazard and hardship pay. In this regard, the
data provided in FedSys' cost proposal were internally
consistent, that is, both the hourly rate and the salaries for
employees were consistent with 40 hour workweeks. Thus, even if,
as the protester contends, its proposed salaries are correct and
its proposal erroneously listed [deleted] instead of [deleted]
hours, the protester would also have had to change the labor
rates proposed for each position.
Further, while the salaries proposed by FedSys for its OCONUS
employees were more than twice those proposed for its CONUS
personnel, this was not the case for its subcontractor, O'Gara.
In this regard, the salaries proposed by FedSys for OCONUS
personnel for 40 hour workweeks ranged from [deleted] to
[deleted] times higher than those proposed for CONUS personnel
for 40 hour workweeks. AR, Tab 15, FedSys Cost Proposal,
Schedule 1 (FedSys Direct Labor). In contrast, O'Gara's proposed
OCONUS salaries were only [deleted] to [deleted] times as high
as those it proposed for CONUS personnel. Id., Schedule 2
(O’Gara Direct Labor). If FedSys' argument were correct--i.e.,
that the proposed salaries were accurate and were intended to
reflect 80 hour workweeks plus hazard and hardship pay--O’Gara
would be paying its OCONUS personnel less per hour than its
CONUS personnel.
Under the circumstances, we think the Army was required to
address the shortfall between the 40 hour workweeks proposed by
the FedSys, and the 80 hour workweeks required by the RFP. We do
not think that the record here shows that the agency should have
understood the protester's proposal to have included all of the
required hours as well as hazard and hardship pay for OCONUS
personnel. As a result, we think that the agency's cost realism
adjustment was reasonable.
Second, while FedSys again concedes that it failed to propose
any travel costs for OCONUS personnel, as required by the RFP,
it argues that the independent government cost estimate (IGCE)
for the travel costs used by the agency in its adjustment
($408,522 per year) was too high. An agency may reasonably use
an IGCE or its past experience in assessing the realism of an
offeror's approach, and we will not sustain a protest of an
agency's cost estimate where the protester does not show that
the agency's estimates are unreasonable. Pueblo Envtl. Solution,
LLC, B-291487, B- 291487.2, Dec. 16, 2002, 2003 CPD para. 14 at
13-14.
Here, FedSys omitted the necessary costs from its proposal and
presents--in the course of its comments on this protest--certain
"assumptions" about those costs that it argues demonstrates that
the agency's IGCE was unreasonable. While we have reviewed the
FedSys' contentions, the protester does not explain or provide
any support for its assumptions regarding the travel costs, and
we see nothing in this record to lead us to conclude that the
agency's estimate was unreasonable. See NAC Int'l, Inc.,
B-310065, Nov. 21, 2007, 2008 CPD para. 3 at 8 n.7 (protest is
denied where protester does not provide any support for its
calculations challenging agency cost analysis). (FedSys,
Inc., B-401453, September 8, 2009) (pdf)
The RFP provided for award to the firm submitting the
technically acceptable offer with the lowest price for the first
task order (the RFP included the scope of work for the first
task order). RFP at 39. Acceptability was to be determined based
on three technical factors--experience, past performance, and
key personnel. RFP at 39-45. With regard to the price
evaluation, the RFP provided that a price analysis would be
performed--by comparing proposal prices to other prices
received, available historical information, and the government
estimate--and that unrealistically low prices could be grounds
for eliminating a proposal from the competition, on the basis
that the offeror does not understand the requirement. RFP at
44-45.
ATI and Environet submitted proposals; both were found
technically acceptable. COS at 4. (A third proposal was rejected
as unacceptable. Id.) ATI's and Environet's proposed prices and
the government estimate for the first task order were as
follows:
|
Offeror |
Proposed Price |
|
ATI |
$1,143,448 |
|
Environet |
$596,102 |
|
Gov't Estimate |
$2,585,503 |
Id. at 5. Environet's
proposal--the apparent low-priced, technically acceptable
offer‑‑was evaluated for price reasonableness, and award
subsequently was made to Environet on May 22. This protest was
filed on June 1.
ATI asserts that, since
Environet's proposed price is approximately one-quarter of the
government estimate and one-half of ATI's price, it is
"inconceivably low." Protest at 4. The protester asserts that
the Army must have disregarded the evaluation process set forth
in the RFP. Id. at 6.
In general, there is no requirement that a price realism
analysis be performed when award of a fixed-price contract is
contemplated. Phoebe Putney Mem'l Hosp., B‑311385, June 19,
2008, 2008 CPD para. 128 at 2. As was the case here, however, a
solicitation for a fixed-price contract may provide for a price
realism analysis for the purpose of assessing offerors'
understanding of the requirements or the risk inherent in
offerors' proposals. PHP Healthcare Corp., B-251933, May 13,
1993, 93-1 CPD para. 381 at 5. The nature and extent of a price
realism analysis ultimately are matters within the exercise of
the agency's discretion, and our review of such an evaluation is
limited to determining whether it was reasonable and consistent
with the solicitation's evaluation criteria. Northrop Grumman
Info. Tech., Inc. et al., B‑295526 et al., Mar. 16, 2005, 2005
CPD para. 45 at 19. We find that the Army's evaluation of
Environet's cost proposal was unobjectionable.
The Army conducted two separate analyses of Environet's price.
First, concurrently with the technical evaluation, the Army
reviewed both offerors' proposed rates to determine if they were
fair and reasonable. This review resulted in a finding that
"there was a great difference" with regard to several proposed
rates in comparison to the government estimate and that these
rates "should be validated." AR, Tab K, Memorandum, Apr. 7,
2009. The agency thereafter conducted an "expanded price
analysis," which indicated that Environet's price for the first
task order was "significantly lower" than the government
estimate. The agency went on to determine, however, that this
difference resulted substantially from the conservative nature
of the government estimate and Environet's status as an
incumbent contractor. Specifically, the Army explained as
follows:
The Government performed a thorough review of EI's [Environet's]
proposal. The primary reason for the difference in price is due
to the fact that the GE [government estimate] is conservatively
based on the use of a contractor who is not familiar with the
Waikoloa Maneuver Area (WMA) and would be working in this area
for the first time. EI is the incumbent contractor … and based
their proposal on their familiarity of the site, and their
current production rates when it comes to MEC clearance. …
Therefore, with actual cost data available from performance of
the work, EI's proposal appears to be more realistic in
comparison with the GE, and shows that the offeror has a clear
understanding of the SOW, and includes sufficient effort to
complete what is required in the SOW.
AR, Tab N, Price Evaluation Report, Apr. 30, 2009, at 2-3.
The agency went on to address in detail each of seven cost
elements where Environet's price was substantially lower than
the estimate. Id. at 3-6. In each case, the agency determined
that there was a reasonable explanation for the difference in
cost. For example, with regard to [deleted], the agency
determined that the [deleted] proposed by Environet were
"consistent with" the [deleted] existing contract with Environet
for ongoing MEC clearance at Waikoloa. Id. at 4. The agency
noted that, unlike the government estimate, Environet's proposal
provided for use of "existing plans that were accepted by the
Government" and proposed to only "update them for this new
project site." Id. Similarly, the agency found that Environet's
proposal [deleted] adequately substantiated in Environet's
proposal, which listed [deleted] under an ongoing contract. Id.
As a further example, the agency found that Environet's low
costs for [deleted] were due in substantial part to the fact
that, unlike the government estimate, Environet's proposal did
not include the cost of [deleted]. Id. Likewise, with regard to
Environet's proposed [deleted], Environet explained that
[deleted]. Id. at 4-5.
ATI asserts that, rather than accept Environet's explanations at
face value, the Army should have further investigated those
representations. However, no such further investigation was
required. The Army requested information where pricing anomalies
were apparent, and then assessed whether the information that
was in the proposal or furnished by Environet provided a logical
explanation for the anomalies. We find that, on their face,
Environet's information and explanations provided a logical
basis for its low price. This being the case, and absent any
countervailing evidence, we think the agency reasonably could
conclude that the information and explanations provided were
sufficient to establish that Environet's pricing was not based
on a misunderstanding of the requirement, which was the limited
purpose of the price analysis under the RFP. See Pemco Aeroplex,
Inc., B-310372.3, June 13, 2008, 2008 CPD para.126 at 8 (protest
challenging price realism evaluation in fixed-price contract
denied where protester failed to demonstrate that agency's
actions, inactions, or analyses were inconsistent with the terms
of the solicitation). (American
Technologies, Inc., B-401445, August 28, 2009) (pdf)
The BAA contemplated a two-phase award process for the
development and testing of a prototype waterjet to eventually be
utilized in advanced Navy ships. For phase one, the solicitation
required offerors to propose pump design, model fabrication, and
a large-scale demonstration plan. Phase two required large-scale
at-sea demonstrations and testing. The solicitation stated that
"it is anticipated that ONR [Office of Naval Research] will
award one or more Cost type contracts for this effort." BAA at
7.
Wartsila and one other firm received phase one contract awards
under the solicitation. While the other firm received a
cost-plus-fixed-fee contract as anticipated by the solicitation,
ONR issued Wartsila a fixed-price contract because Wartsila did
not have an accounting system approved by the Defense Contract
Audit Agency (DCAA), and could not be awarded a cost-type
contract. Agency Motion to Dismiss, Apr. 9, 2009, Contracting
Officer’s Affidavit, at 1. After Wartsila was awarded a
fixed-price phase one contract, Wartsila suggested to ONR that
it might submit a fixed-price proposal for the upcoming phase
two award. In response, ONR stated by email that it “awarded the
first contract as a FFP [firm-fixed-price] to allow Wartsila
time to implement an approved accounting system. ONR will not
award Phase II as a FFP contract.” Id.
(section deleted)
The contracting officer
encountered two major obstacles to an award to Wartsila. First,
the contracting officer found that Wartsila’s cost proposal did
not provide the level of detail required by the solicitation,
preventing the contracting officer from proceeding with the cost
analysis. Second, although Wartsila’s cost proposal stated that
Wartsila could accommodate a fixed-price, time and materials, or
cost-type contract award, the contracting officer found that
Wartsila essentially insisted that the award be made on a
fixed-price basis, and eventually determined that Wartsila was
ineligible for a cost-type award. Id. Negotiations between the
contracting officer and Wartsila continued for several months,
but were unsuccessful.
In March 2009, Wartsila discovered that a phase two award had
been made to the other phase one contract holder on March 23. On
March 26, Wartsila contacted the agency to request confirmation
of the award and a post-award debriefing. The agency orally
confirmed the award, but did not offer a debriefing. Wartsila
then filed this protest with our Office on March 27. Wartsila
challenges the rejection of its proposal, arguing that the
solicitation did not require submission of a cost-type proposal
but merely stated that the agency anticipated making a cost-type
contract award, and that the agency properly could consider
Wartsila’s fixed-price proposal.
A fixed-price proposal generally may be considered by an agency
notwithstanding that the agency otherwise indicated a preference
for a cost-type award. See Warren Pumps, Inc., B-248145.2, Sept.
18, 1992, 92-2 CPD para. 187 at 4 n.3; Marine Mgmt. Sys., Inc.,
B-185860, Sept. 14, 1976, 76-2 CPD para. 241 at 6-7. As
explained in FAR sect. 16.103(a), the agency’s objective is to
select a contract type that will result in reasonable contractor
risk and provide the contractor with the greatest incentive for
efficient and economical performance. Thus, while the FAR calls
for the use of fixed-price contracts when the risk involved is
minimal or can be predicted with an acceptable degree of
certainty, it states that other contract types should be
considered where a reasonable basis for firm pricing does not
exist. FAR sect. 16.103(b)
(sections deleted)
Ultimately, selecting the
appropriate contract type is the responsibility of the
contracting officer, as informed by obtaining the
recommendations of technical personnel. FAR sect. 35.006(b). The
contracting officer’s decision, as with any other exercise of
discretion, must have a reasonable basis. Surface Tech. Corp.,
B-288317, Aug. 22, 2001, 2001 CPD para. 147 at 3. Here, we
conclude that the contracting officer had a reasonable basis to
conclude that the criteria set out in DFARS sect. 235.006(b)(ii)
were not met and that a fixed-price contract therefore could not
be awarded for this R&D procurement. As a result, we see no
basis to object to the contracting officer’s refusal to consider
Wartsila’s fixed-price proposal.
As explained above, during contract negotiations, the agency
reminded Wartsila that ONR anticipated awarding cost-type
contracts under the solicitation, and explained that “ONR
considers sufficient uncertainties to be involved with any
effort under this program to not allow for the use of a
fixed-price contract.” Wartsila Response, Apr. 15, 2009, Exh. 1,
Email from ONR, Oct. 20, 2008. Further, the BAA for phase two
describes a substantial development process leading up to at-sea
demonstrations of a large-scale waterjet. BAA at 4. The record
also includes an affidavit supplied by the program officer that
explains the “uncertainties” involved in the procurement as they
relate to the choice of contract type. The program officer
states that some of the costs to the companies under the phase
two contract could not be reasonably quantified in advance.
These costs include “ship hull modifications to accommodate
instrumentation, such as sensors, needed to measure the
prototype’s at-sea performance.” Agency Supplemental Submission,
Apr. 21, 2009, Program Officer’s Affidavit, at 1. The program
officer also states that he reviewed DFARS sect. 235.006(b)(ii)
and concluded that “[t]he work needed to do detailed design,
construction, delivery, and installation of a complete 21-22
megawatt large scale waterjet for at-sea testing on a candidate
platform not yet constructed cannot be realistically priced at
this time. Use of a fixed-price contract by any company for this
effort would not permit an equitable and sensible allocation of
program risk between the contractor and the Government.” Id. at
2.
In sum, based on the record here, we conclude that the
contracting officer reasonably determined that the conditions
required for the award of a fixed-price contract under DFARS
sect. 235.006(b)(ii) were not present in this procurement and
thus properly decided not to consider Wartsila’s fixed-price
proposal for a phase two contract award. (Wartsila
Defense, Inc., B-401224, May 26, 2009) (pdf)
Privasoft and
AINS submitted quotations and participated in product
demonstrations. Both quotations were evaluated as satisfying the
requirements of the performance work statement, but AINS's was
scored higher technically. With regard to price, both vendors
included separate unit prices for each license and related
maintenance for each of the 25 specified NUs for the base and
option years.
The agency initially calculated a total price for each vendor
using their quoted prices for 25 NUs for the base and option
years. Based on these calculations, AINS's total evaluated price
was $1,076,914.63 and Privasoft's, including volume discounts
for the base year, was $1,089,759.26. Because the agency did not
have a current need for all 25 licenses and related maintenance,
it re-evaluated both vendors' pricing using 18 NUs for the base
year and 25 NUs in the option years, which resulted in an
evaluated price of $1,028,556.53 for AINS and $1,043,605.10 for
Privasoft. Since AINS's evaluated price was lower under both
calculations, DEA issued a delivery order to AINS.
Privasoft challenges the evaluation of its quoted price. We will
review a price evaluation to determine whether it was reasonable
and consistent with the solicitation's evaluation criteria. The
Arora Group, Inc., B‑277674, Nov. 10, 1997, 98‑1 CPD para. 64 at
4. The evaluation here was reasonable.
Privasoft asserts that, because its quotation identified its
licenses as "perpetual," and notwithstanding that it priced the
25 licenses for each option year as directed by the RFQ, the
agency's price evaluation improperly included the price of all
25 licenses in each option year. In Privasoft's view, since the
agency issued the order based on the price of 18 licenses in the
base year, the only additional cost (for Privasoft) would be for
up to 7 additional perpetual licenses in each option year. (In
this regard, Privasoft asserts that the agency properly included
AINS's price for all 25 licenses in the option years because
AINS did not identify its licenses as perpetual.) Had the agency
used the reduced quantities in its evaluation, Privasoft's total
price would be lower than AINS's.
This assertion is without merit. The agency made clear through
its response to question 25, that it expected vendors to quote a
price for "the cost of the initial 25 licenses for subsequent
years" and Privasoft did this. AR, Tab 8, at Answer 25. While
Privasoft's quotation identified its licenses as "perpetual," it
did not indicate that this designation would result in any
reduction in price. To the contrary, its price for each license
in the option years was equal to or greater than the price
quoted for the base year. To the extent Privasoft intended to
quote a reduced price for licenses in the option years, it was
required to clearly indicate this in its quotation, not leave it
to the agency to deduce from its reference to perpetual
licenses. Since an agency's evaluation is dependent upon the
information furnished in a quotation, it is the vendor's burden
to submit an adequately written quotation for the agency to
evaluate; a protester's failure to fulfill its obligation in
this regard does not render the evaluation unreasonable. SOS
Interpreting, Ltd., B‑287505, June 12, 2001, 2001 CPD para. 104
at 12. Given the absence of any indication in Privasoft's
quotation of reduced pricing for the option years, the agency
reasonably considered Privasoft's option prices and
quantities--as quoted--in its evaluation.
In its comments in response to the agency report, Privasoft
asserts that the agency improperly applied its quoted volume
discounts only to the base year prices; the discounts also
should have been applied to the option year prices. Privasoft
notes, in this regard, that its quotation included two
discounts--a "DEA volume discount on total order" for orders
placed by a specific date, and an additional discount for an
earlier order--and did not limit application of the discounts to
the base year only. Comments at 3-4. According to the
protester's calculations, proper application of these discounts
would have resulted in its evaluated price being lower than
AINS's. In the alternative, Privasoft asserts that its price
would have been lower than AINS's had the agency evaluated only
the base year pricing. In this regard, it notes that neither the
RFQ, nor the response to question 25, indicated that the agency
intended to evaluate prices based on both the base and option
periods. Id. at 4.
A protest based on other than alleged improprieties in a
solicitation must be filed no later than 10 calendar days after
the protester knew, or should have known, of the basis for
protest, whichever is earlier. Bid Protest Regulations, 4 C.F.R.
sect. 21.2(a)(2) (2008). Privasoft learned the basis of both of
these protest grounds in a post-award letter from DEA explaining
that the price analysis had included both the base and option
years, resulting in 5-year prices for both vendors. DEA Letter,
Nov. 21, 2008. The letter also included a table with
calculations clearly showing that the agency had used
Privasoft's base and option year pricing in the evaluation and
had applied Privasoft's volume discounts only to its base year
prices. Id. Since Privasoft did not specifically challenge these
aspects of the evaluation until it filed its comments, more 1
month after receiving the November 21 letter, this aspect of the
protest is untimely and will not be considered. (Privasoft
Inc., B-400853, January 27, 2009) (pdf)
Unlike the cost
proposal submitted by ARTS, SP Systems' weighted labor rate for
the senior-level positions exactly matched the library rates for
all six labor categories.
With respect to both the cost evaluation and the significant
weakness identified in ARTS' proposal, a key issue is the rates
being paid to the incumbent workforce and how ARTS' proposed
labor rates compared to those rates. Because both ARTS and SP
Systems proposed to retain a very high proportion of the
incumbent workforce, the agency was justifiably focused on how
the offerors' proposed rates compared to those of the incumbent.
This affected the agency's cost-realism adjustment to proposed
costs, since the agency rightly assumed that, absent some valid
explanation, an offeror proposing to retain a very high
proportion of the incumbent workforce would need to pay at least
equal to the incumbent workforce's rates. Because this is a
cost-reimbursement contract, a cost realism analysis was
required to determine the extent to which each offeror's
proposed costs represent the offeror's likely costs in
performing the contract under the offeror's technical approach,
assuming reasonable economy and efficiency. See Federal
Acquisition Regulation (FAR) sections 15.305(a)(1),
15.404‑1(d)(1). The proposed labor rates also affected the
agency's evaluation of proposals under the management plan
subfactor for offerors proposing to retain the incumbent
workforce, since proposing labor rates lower than the
incumbents' could reasonably be found to represent a management
plan weakness.
Unfortunately, NASA's solicitation did not disclose the
incumbent workforce's actual labor rates to offerors, at least
not in a meaningful way, and those conducting the evaluation may
not have had access to the actual rates. The library rates are
unweighted averages, which do not reflect the distribution of
actual labor rates among the sub-levels within the
junior/intermediate/senior levels that the incumbent uses. This
problem with the RFP was not protested, however, so that the
agency was free to choose any reasonable method, within the
context of the RFP, to assess the evaluated cost of each
proposal and to evaluate the cost-related technical factors,
such as the management plan subfactor.
With respect to the cost-realism analysis, the agency, as noted
above, took the reasonable view that it could adjust proposed
costs up to reflect the rates paid to the incumbent workforce,
if the offeror proposed to retain the great majority of the
incumbent workforce, as both ARTS and SP Systems did. The
problem in making that adjustment, however, was that those
conducting the evaluation apparently did not have access to the
incumbent's actual weighted rates. Instead, the agency relied on
the unweighted library rates and treated them as reflecting the
rates paid the incumbent workforce.
While it would clearly have been preferable to use the incumbent
workforce's weighted rates in calculating offerors' evaluated
costs, we believe that it was adequate, as a legal matter, that
the offerors were treated equally, through the agency's use of
the library rates as a “plug number.” This methodology of
treating the incumbent workforce cost as, in effect, a
normalized cost was reasonable, since the cost of the incumbent
workforce would not have been unique to the particular approach
of any individual offeror (nor has there been a suggestion to
the contrary), and offerors such as ARTS were not in a position
to know the actual cost of the incumbent workforce. In other
words, one would reasonably expect that the direct labor cost of
the incumbent workforce should be the same among all offerors.
Absent persuasive explanation for any deviation (which ARTS did
not offer here), a reasonably derived estimate of direct,
unburdened labor rates for comparable labor categories can
provide an objective standard against which the realism of
proposals can be measured. United Int'l Eng'g et al., B‑245448.3
et al., Jan. 29, 1992, 92-1 CPD para. 122 at 11. As a
consequence, there is no basis for our Office to question the
agency's upward adjustment of ARTS' cost, as part of the
cost-realism analysis, to account for the cost of the incumbent
workforce.
We do not, however, find support in the record for the
determination that ARTS' proposed rates were inadequate to
retain the incumbent workforce. For this reason, we find
problematic both the input that NASA received from the Defense
Contract Audit Agency (DCAA) and NASA's assignment of a
significant weakness to ARTS' proposal under the management plan
subfactor.
Regarding the DCAA input, with respect to ARTS' proposed labor
rates for labor categories at the senior level, DCAA noted that
ARTS proposed to capture 98 percent of the incumbent workforce
and determined that “the method used by [ARTS] to compute the
proposed senior level direct labor rates resulted in a potential
understatement of direct labor rates. [ARTS] used a weighted
average which resulted in a rate lower than the straight average
rate.” AR, Tab 33, DCAA Audit of ARTS Cost Proposal, at 5. DCAA
then calculated an unweighted average rate with respect to the
rates proposed by ARTS under the senior level labor categories
and determined that the unweighted average was identical to the
library rates. Without further elaboration, DCAA determined that
the library rates were a more reliable and reasonable basis for
the proposed senior level rates. Id. As explained above, there
is no way to tell, from the unweighted library rates, how much
the incumbent workforce is being paid. Indeed, DCAA's analysis
demonstrates this. As DCAA discovered, ARTS' proposed rates,
when averaged without weighting, are precisely the same as the
unweighted library rates, so that it is theoretically possible
that ARTS' proposed labor rates are in fact identical to those
actually being paid by the incumbent. In any event, because the
record does not establish a connection between the library rates
and the incumbent’s actual, weighted rates, we see no basis in
the record to support DCAA's analysis.
More importantly, we find no reasonable basis for the agency's
assignment of a significant weakness to ARTS' proposal under the
management plan subfactor. Absent more information, there
simply is no way for the agency to determine whether the library
rates or the weighted averages proposed by any offeror are
closer to the incumbent's direct labor cost. In addition, if one
compares the weighted rates proposed by ARTS and SP Systems, it
is not possible in many instances to determine whether one firm
will be more or less likely to attract the incumbent workforce
in any given labor category, since the firms proposed different
high and low rates within a labor category, in some instances
different numbers of levels of sub-categories, and different
percentages of effort for each sub-level. For any given labor
category, it may be that, as compared to the incumbent
workforce, one offeror’s rates are high, the other's are low;
neither the evaluators nor the offerors had any basis to know.
ARTS, like the other offerors, proposed to perform the PAAC III
contract utilizing the existing incumbent workforce. However, as
explained above, offerors such as ARTS did not have access to
the actual labor rates that the incumbent was paying its
workforce. Nonetheless, offerors proposing to use the incumbent
workforce, including ARTS, had to account for the cost of this
workforce in their proposals. ARTS attempted to do this by
including a blanket statement committing ARTS to paying
incumbent employees their current salaries, at a minimum, and
providing labor rates based in part upon outside salary survey
information. While the rates proposed by ARTS, when averaged on
a weighted basis, were lower than the non-weighted library
rates, they were identical to the library rates, when averaged
on a straight line basis, as the library rates themselves had
been calculated.
As relevant here, the agency could only assign ARTS' proposal a
significant weakness under the management plan subfactor based
on a determination that ARTS is unlikely to be able to retain
the incumbent workforce with its proposed labor rates. There is
simply no basis in the record for that. ARTS proposed rates may
be lower than those paid to the incumbent workforce--but they
may be higher than the incumbents rates. Indeed, as noted above,
they may be identical to the rates of the incumbent. Yet, under
the management plan subfactor, NASA questioned the ability of
ARTS to achieve its proposed 98 percent incumbent capture given
its "unreasonably low" labor rates for the senior-level
positions as compared to the library rates. AR, Tab 37, SEB
Report, at 65. Given the meaninglessness of the library rates as
a criterion for retaining the incumbent workforce, the
conclusion drawn by the agency in assessing ARTS' ability to
retain that workforce was unreasonable, especially where ARTS
committed to paying incumbents their current wages, at a
minimum. Accordingly, we conclude that the agency's evaluation
in this regard was unreasonable.
While our findings regarding the technical evaluation and the
cost-realism adjustment may appear inconsistent with regard to
the treatment of the library rates, we believe that they are
consistent. In the cost-realism analysis, we found that the
agency could reasonably use a "plug number" for labor rates for
all offerors that proposed to retain the incumbent workforce. We
found use of the library rates acceptable, under the
circumstances--not because they reflected the incumbent's rates,
but simply because they were a constant used equally for all
offerors. From that standpoint, the agency could just as well
have used ARTS' labor rates, or SP Systems', as the plug
numbers. With regard to the technical evaluation evaluation,
however, the agency was finding that ARTS had proposed rates so
much lower than the incumbent's as to present a significant
management plan weakness, and that finding could not be
supported without evidence that the library rates were closer
than ARTS' rates to the incumbent's rates--and the record
provides no basis for that finding. (ASRC
Research & Technology Solutions, LLC, B-400217; B-400217.2,
August 21, 2008) (pdf)
JVPB challenges
the Navy's determination that its indefinite-quantity pricing
for minor work was unreasonably low and unacceptable, arguing
that the determination was based on a faulty price realism
analysis.
Before awarding a fixed-price contract, an agency is required to
determine that the offered price is fair and reasonable. Federal
Acquisition Regulation (FAR) sect. 15.402(a). An agency's
concern in making a price reasonableness determination focuses
on whether the offered prices are too high, not too low.
Medical Matrix, LP, B-299526, B‑299526.2, June 12, 2007,
2007 para. 123 at 9 n.6. Although not required, an agency may
also provide for a price realism analysis in a solicitation for
award of a fixed-price contract for the purpose of assessing an
offeror's understanding of the requirements and the risk
inherent in an offeror's proposal. L-3 Commc'ns, KDI
Precision Prod., Inc., B-290091 et al., June 14, 2002, 2002
CPD para. 155 at 5-6. In this regard, the risk of poor
performance when a contractor is forced to provide services at
little or no profit is a legitimate concern in evaluating
proposals. Molina Eng'g, Ltd/Tri-J Indus., Inc. Joint Venture,
B-284895, May 22, 2000, 2000 CPD para. 86 at 4. We will review
the price evaluation conducted to determine whether it was
reasonable and consistent with the RFP evaluation criteria. The
Arora Group, Inc., B-277674, Nov. 10, 1997, 98‑1 CPD para.
64 at 4.
Here, the record does not show that the agency performed a
reasonable price evaluation. Although the Navy rejected JVPB's
proposal on the basis of low indefinite-quantity pricing for
minor work, the record does not provide any evidence that the
agency considered whether this reflected a lack of understanding
of the requirements, or that there was a credible risk to
performance. The agency did not consult with the TEB to consider
whether JVPB could perform the work at the prices proposed. In
fact, the SSB concluded that JVPB 'successfully demonstrated a
good understanding of the requirements.'AR, exh. 16, Final SSB
Report, at 4.
The agency explains that "significant" proposal risk stems from
its belief that "under the [indefinite-quantity] portion [of
minor work], the Contractor has the option of returning, and
ultimately rejecting work if they do not agree with the Category
the Government is issuing it under." AR, exh. 15, Final PEB
Report, at 4-5. In this regard, the agency is referring to the "Recategorization"
provision of the PWS that allows the contractor to challenge the
categorization of fixed-quantity minor work--that is, whether
the work should be classified as category I, II, III, or IV. RFP
sect. C, PWS, at 41. According to the agency, this provision
also applies to indefinite-quantity minor work.
We first note that it is not evident from the record that the "Recategorization"
provision applies to the indefinite-quantity minor work. The
provision is not included or referenced in the
indefinite-quantity portion of the PWS addressing minor work.
Although the PWS for indefinite-quantity minor work incorporates
by reference fixed-quantity "[p]erformance standards," id. at
43, the "Recategorization" provision is not listed as a
performance standard. Likewise, the ELIN schedule for
indefinite-quantity minor work references "Requirement 1503090
in Section C" (i.e., the PWS), but the "Recategorization"
provision appears at 1503040 of the PWS.
Furthermore, in response to inquiries from our Office, the
agency conceded that neither the "Recategorization" provision,
nor any other provision of the RFP, permits the contractor to
reject minor work orders issued by the contracting officer.
Agency Response to GAO's Interrogatories (Apr. 30, 2008), at 4.
Thus, the reason given contemporaneously for rejecting JVPB's
proposal was conceded to be erroneous. The agency now argues
that JVPB's low indefinite-quantity pricing will encourage the
firm to challenge categories (essentially arguing that it should
be paid a higher price for the particular "minor work" to be
performed), which will place a "significant administrative
burden" on the agency in responding to these challenges. Id. at
5. Even though, as discussed above, it is not clear from the
record that the "Recategorization" provision applies to the
indefinite-quantity minor work, the fact that a contractor may
exercise a contract right is not a legitimate reason for
rejecting its proposal.
Moreover, the indefinite-quantity portion of minor work
represents only a small fraction of the overall contract and may
never be ordered. See RFP sect. C, PWS, at 43
(indefinite-quantity minor work will be ordered only "if and
when needed"). Thus, even if JVPB's prices were considered too
low for this aspect of minor work, this does not seem to support
the agency's conclusion that the performance risk to the overall
contract is "extremely high."
Also, if low prices "incentivize" a contractor to challenge
minor work categories, as the agency now contends, then the
awardee is similarly "incentivized." As the record shows, BOS's
proposed prices for minor work were lower than JVPB’s for all of
the fixed-quantity categories, and were just below the
established ranges for all minor work categories (both
fixed-quantity and indefinite-quantity), except for category I.
As noted by the protester, because of its low prices, BOS may be
even more "incentivized" to challenge categories for both
fixed-quantity minor work (where order quantities are
guaranteed) and indefinite‑quantity minor work (where orders are
placed only when needed). Indeed, it would appear that, since
fixed-quantity orders will definitely occur, the likelihood of
category challenges with fixed-quantity work is greater than
with indefinite-quantity work. Thus, it is not apparent how the
protester's pricing of indefinite-quantity minor work will cause
significantly more of an administrative burden to the agency
under the "Recategorization" provision than the awardee's
pricing.
In sum, we sustain the protest because the Navy's price
evaluation of the protester's proposal lacks a reasonable basis,
and is not supported by the contemporaneous evaluation record.
Under the circumstances, we recommend that the agency reevaluate
proposals, conduct discussions if necessary, perform a
price/technical tradeoff if required, and make a new source
selection decision. The agency should also consider whether to
clarify for offerors whether proposed prices for minor work must
be within the category ranges stated in the ELIN schedule. In
addition, we recommend that the agency reimburse JVPB the
reasonable costs of filing and pursuing the protest, including
reasonable attorneys' fees. 4 C.F.R. sect. 21.8(d)(1). JVPB's
certified claim for costs, detailing the time spent and the
costs incurred, must be submitted to the agency within 60 days
of receiving this decision. 4 C.F.R. sect. 21.8(f)(1). (Joint
Venture Penauille/BMAR & Associates, LLC, B-311200;
B-311200.2, May 12, 2008) (pdf)
Price realism is
not ordinarily considered in the evaluation of proposals for the
award of a fixed-price contract, because these contracts place
the risk of loss upon the contractor. However, in light of
various negative impacts on both the agency and the contractor
that may result from an offeror’s overly optimistic proposal, an
agency may, as here, expressly provide that a price realism
analysis will be applied in order to measure the offerors’
understanding of the requirements and/or to assess the risk
inherent in an offeror’s proposal. See, e.g., Wackenhut Servs.,
Inc., B-286037, B‑286037.2, Nov. 14, 2000, 2001 CPD para.
114 at 3; Molina Eng’g, Ltd./Tri-J Indus., Inc. Joint Venture,
May 22, 2000, B-284895, 2000 CPD para. 86 at 4. Although the
Federal Acquisition Regulation (FAR) identifies permissible
price analysis techniques, FAR sect. 14.404-1, it does not
mandate any particular approach; rather, the nature and extent
of a price realism analysis, as well as an assessment of
potential risk associated with a proposed price, are generally
within the sound exercise of the agency’s discretion. See
Legacy Mgmt. Solutions, LLC, B‑299981.2, Oct. 10, 2007, 2007
CPD para.197 at 3; Comprehensive Health Servs., Inc.,
B‑310553, Dec. 27, 2007, 2007 CPD para. 9 at 8. In reviewing
protests challenging an agency’s evaluation of these matters,
our focus is whether the agency acted reasonably and in a way
consistent with the solicitation’s requirements. See, e.g.,
Grove Res. Solutions, Inc., B‑296228, B-296228.2, July 1,
2005, 2005 CPD para. 133 at 4-5.
Here, as discussed above, the record establishes that the agency
performed various analyses regarding price realism and proposal
risk in the context of Boeing’s final proposal revisions.
Specifically, the agency’s actions included an analysis of the
[deleted] proposed by Boeing to [deleted] with the [deleted]
that have been most recently experienced [deleted] internally at
Tinker Air Force Base; an analysis of Boeing’s [deleted];
consideration of the impact [deleted] will have on [deleted]
within the context of the provisions of this solicitation;
consideration of the [deleted] contemplated to [deleted];
consideration of the [deleted] proposed; comparison of offerors’
[deleted], [deleted], and [deleted]; recognition of, and
adjustment for, the offerors’ different methods of [deleted];
and consideration of Boeing’s proposed use of its [deleted] to
[deleted] and mitigate the potential risk for schedule
disruption, cost increases, and need for government oversight.
AR, Tab 59 at 9-10; Tab 60 at 6‑19, 68‑69; Tab 61 at 71-75,
179-80.
Although Pemco raises the full range of possibitilites--that is,
that the agency should not have considered certain information,
that the agency should have considered certain other
information, that the agency should have performed alternative
analyses, and/or that the price realism and risk assessments
should have been dispositively resolved by comparison to various
benchmarks including Pemco’s own proposal--its protest fails to
demonstrate that any of the agency’s actions, inactions, or
analyses are inconsistent with, or contrary to, the terms of the
solicitation or applicable statute or regulation. As discussed
above, an agency has considerable discretion in determining the
nature and extent of required price realism and proposal risk
assessments in the context of fixed-price contracts. Based on
our review of the record, we conclude that Pemco’s various
arguments challenging the agency’s analysis and judgments
reflect Pemco’s mere disagreement or dissatisfaction with the
agency’s determinations.
Accordingly, based on our review of the entire record, including
the agency’s documentation responding to our prior decision, we
see no basis to question the adequacy or reasonableness of the
agency’s actions, its analysis, or its conclusions. Pemco’s
protest challenging the agency’s cost/price evaluation is
without merit.
(Pemco Aeroplex, Inc.,
B-310372.3, June 13, 2008) (pdf)
Guam also
challenges the agency's evaluation of its proposal under the
price realism subfactor of the performance risk factor, and the
finding that its price was unrealistically low. The protester
only generally asserts that because it used its currently
approved labor rates in formulating its price, its price must be
considered realistic; similarly, Guam contends that the
higher-priced IGE must be flawed because it exceeds Guam's labor
rates. As the agency points out, however, Guam's proposed price
was not found to be unrealistically low based only on its lower
labor rates; rather, Guam's low price also reflected lower
prices for materials than those proposed by the other offerors
and included in the IGE. Additionally, the protester's failure
to identify any profit added to the agency's concerns about
whether the firm's substantially lower-priced proposal would
affect performance of the contract, since, as indicated in the
RFP, financial loss, including a lack of or little profit, may
cause a contractor to 'cut corners' in the performance of the
required work.
The depth of an agency's price realism analysis is a matter
within the sound exercise of the agency's discretion. Comparison
of proposed prices with each other and an IGE are recognized
price analysis techniques for a price realism review. See
Quality Elevator Co., Inc., B-276750, July 23, 1997, 97‑2 CPD
para. 28 at 7. Here, the agency compared the protester's
proposed price to the other offerors' prices and concluded that,
as the lowest-priced offer, with a price substantially lower
than Gulf Copper's next low price, there is some degree of
performance risk associated with the protester's lower price;
Guam's price also was evaluated as approximately 23 percent
lower than the IGE. Given the reasonableness of the agency's
concern regarding quality of performance in light of Guam's low
price, we have no reason to question the determination that the
proposed price is unrealistically low and, consistent with the
definition of unrealistic pricing in the RFP, could result in
financial loss for the contractor in performance of the
contract. In light of the reasonableness of the performance risk
assessment here, including the recent marginal past performance
by the firm, we find no basis to question the agency's
determination that the potential savings offered by Guam's very
high risk proposal is not worth the increased risk to the
government. (Guam
Shipyard, B-311321; B-311321.2, June 9, 2008) (pdf)
GSN argues that
AC's price is so low as to be unreasonable, and that AC's low
price will effectively prevent it from performing at the
required levels--while developing additional business--as
required by the terms of the RFP. GSN argues that AC's low
prices should have placed the Army on notice that AC lacked
understanding of the requirement, and faced a significant risk
of unsuccessful performance.
The Army responds that it appropriately evaluated AC's price as
reasonable after comparing AC's price to the government
estimate, to GSN's proposed price, and to the price offered by
the third offeror. While acknowledging that AC's price is
lower than the government estimate, the Army argues that the
government estimate was based significantly on GSN's incumbent
staffing approach. Therefore, the Army argues that neither the
government estimate, nor GSN's proposed prices, could be treated
as a definitive standard of price reasonableness. The Army
emphasizes that the third offeror's price was only slightly
higher than AC's price, and argues that it was reasonable to use
that comparison to find AC's price to be reasonable. AR at
17‑18.
Where, as here, a solicitation provides for award of a
fixed-price contract--under which the government's liability is
fixed and the contractor bears the risk and responsibility for
the actual costs of performance--the agency is only required to
evaluate an offeror's price for fairness and reasonableness. FAR
sections 15.402(a), 15.404-1(a); SAMS El Segundo, LLC,
B-291620.3, Feb. 25, 2003, 2003 CPD para. 48 at 8. It is
well-established that price reasonableness in a fixed-price
setting relates to whether a firm’s prices are too high, not too
low. Medical Matrix, LP, B‑299526, B‑299526.2, June 12, 2007,
2007 CPD para. 123 at 9 n.6. Here, GSN has provided no basis to
question the Army’s conclusion that AC’s price was reasonable
simply because it was lower than the government estimate or
GSN's price. Even though GSN argues that AC will not be able to
perform adequately at its price, the Army has shown that its
evaluation of the completeness and reasonableness of AC's price
was appropriate for this fixed-price contract. (Global
Solutions Network, Inc., B-298682.3; B-298682.4,June 23,
2008) (pdf)
Evaluation of MILCON Costs
Boeing also complains that the Air Force did not reasonably
evaluate the firms’ cost/price proposals in accordance with the
RFP. As noted above, the solicitation provided that the Air
Force would calculate an MPLCC estimate for each offeror, which
reflected the agency’s independent estimate of all contract,
budgetary, and other government costs associated with all phases
of the aircraft’s life cycle from SDD through production and
deployment and O&S; MILCON costs were specifically identified as
a cost that the agency would evaluate in calculating the firms’
MPLCCs. See RFP sect. M.2.5.2. Boeing contends that the Air
Force’s evaluation of MILCON costs greatly understated the
difference between the firms’ MILCON costs and that Northrop
Grumman’s much larger and heavier aircraft would have
correspondently higher MILCON costs. See Boeing’s Comments at
110-18; Boeing’s Post-Hearing Comments at 117-18.
The Air Force disputes Boeing’s complaint, contending that it
reasonably assessed the likely life cycle costs associated with
each firm’s proposed aircraft. In this regard, the agency states
that, because it did not know at which bases (“beddown sites”)
the new KC-X aircraft would be assigned, it conducted site
surveys at four airbases ([Deleted] Air Force Base (AFB),
[Deleted] AFB, [Deleted] AFB, and [Deleted] AFB) to determine
what military construction would be required at those bases for
the offerors’ proposed aircraft. The agency then extrapolated
those results to six other airbases to calculate the agency’s
MILCON costs for the offerors. Air Force’s Memorandum of Law at
221-22; Air Force’s Post-Hearing Comments at 120‑22. As
indicated above, the agency added $[Deleted] billion in MILCON
costs to Boeing’s MPLCC and $[Deleted] billion in MILCON costs
to Northrop Grumman’s MPLCC. AR, Tab 55, PAR, at 40-43.
An agency’s life cycle cost evaluation, like other cost
analyses, requires the exercise of informed judgment concerning
the extent to which proposed costs or prices represent a
reasonable estimation of future costs. Our review of the
agency’s cost analysis is limited to the determination of
whether the evaluation was reasonable and consistent with the
terms of the RFP. See Cessna Aircraft Co., B-261953.5, Feb. 5,
1996, 96-1 CPD para. 132 at 21. The agency’s analysis need not
achieve scientific certainty; rather, the methodology employed
must be reasonably adequate to provide some measure of
confidence that the agency’s conclusions about the most probable
costs under an offeror’s proposal are realistic in view of other
cost information reasonably available to the agency at the time
of its evaluation. See Information Ventures, Inc., B‑297276.2 et
al., Mar. 1, 2006, 2006 CPD para. 45 at 7.
As a threshold matter, the Air Force admits that in “defending
this protest” it discovered five errors in its assessment of
MILCON costs, which, when corrected, would result in Boeing
displacing Northrop Grumman as the offeror with the lowest
evaluated MPLCC. Specifically, the Air Force states that it
underestimated Northrop Grumman’s MILCON costs by $122.5
million, and overestimated Boeing’s costs by $3.3 million. After
correction of these $125.8 million in errors, Boeing’s MPLCC
would be $108.041 billion and Northrop Grumman’s would be
$108.133 billion.[80] Air Force’s Memorandum of Law at 201-02.
Here, the record shows that the agency’s MILCON cost evaluation
was otherwise flawed. In this regard, the RFP contemplated that
the agency’s MILCON cost evaluation would be based upon “the
offeror’s proposed KC-X aircraft solution,” see RFP sect.
M.2.5.2.4, which is consistent with the rule that an agency must
consider an offeror’s proposed approach in estimating the likely
costs associated with that offeror’s proposal. See Hughes STX
Corp., B-278466, Feb. 2, 1998, 98-1 CPD para. 52 at 8. The
record shows, however, that the agency’s evaluation of MILCON
costs was based upon site surveys that were conducted prior to
the receipt of proposals in response to the RFP. HT at 472-73,
1293; Air Force’s Post-Hearing Comments at 120. Admittedly, the
agency’s site surveys were based upon the size and dimensions of
the A330-200 and 767-200, the commercial aircraft from which the
offerors’ proposed KC-X aircraft were derived. See, e.g., AR,
Tab 297, Site Survey Report for [Deleted] Air Force Base, at 3.
However, it is equally clear that the Air Force could not and
did not evaluate MILCON costs associated with some aspects of
the offerors’ proposed aircraft because the site surveys were
conducted before the receipt of proposals, and no further
evaluation of the additional MILCON costs for the
improvements/changes necessary to support each of these
particular aircraft was performed after the proposals were
received.
For example, although the Air Force recognizes that there will
be a “need for seat storage” associated with the KC-X aircraft,
the survey teams were unable to assess the likely MILCON costs
associated with this need because, at the time of the surveys,
the agency did not know the number of seats associated with the
firms’ respective aircraft. See Air Force’s Post‑Hearing
Comments at 127. Accordingly, at [Deleted] AFB, the team assumed
that the offerors’ aircraft had seating capacities similar to
that of the KC-10 and, on this basis, concluded that the
facilities at [Deleted] AFB were adequate. HT at 497. The KC-10,
however, has only 75 seats, which is far less than the [Deleted]
seats carried by the KC-30 and less than the [Deleted] seats
carried by the KC‑767. Similarly, at [Deleted] AFB, the survey
team assigned no MILCON costs associated with seat storage
because it determined, without any actual knowledge of the
number of seats the proposed aircraft would carry, that there
would be adequate storage available. Air Force’s Post-Hearing
Comments at 128. At [Deleted] AFB, the survey team concluded
that there would be insufficient storage space to accommodate
the seats and that an additional storage facility would need to
be constructed; the cost of this facility ($[Deleted] million)
was estimated to be the same for both offerors because the team
did not know how many seats the aircraft carried and therefore
“assigned a seat requirement the same for both aircraft.” HT at
499‑500.
(The
Boeing Company, B-311344; B-311344.3; B-311344.4;
B-311344.6; B-311344.7; B-311344.8; B-311344.10; B-311344.11,
June 18, 2008) (pdf)
Accumark asserts that the agency unreasonably determined that
InfraMap's proposed prices were realistic. InfraMap reduced its
price in its FPR and the protester maintains that this was a
dramatic price reduction that should have led the agency to
conclude that there would be an adverse impact on InfraMap's
technical capability to perform the contract.
In the context of a solicitation that provides for award of a
fixed-price contract, an agency may, in its discretion, provide
for considering the realism of offered prices for purposes of
assessing whether a price is so low as to evince a lack of
technical understanding on the part of the offeror. Consolidated
Servs., Inc., B-276111.4, Dec. 29, 1997, 98-1 CPD para. 14 at 4.
In such a context, an agency’s simple comparison of the prices
received with one another, as well as with a government
estimate, can serve as an adequate basis to establish the
realism of the proposed prices where, as here, there was
adequate competition, and the proposed prices fall within a
narrow range. Id. at 5. The realism determination here was
unobjectionable. The record shows that InfraMap's initial
price--$[deleted]--was found by the agency to be unreasonably
high, AR, exh. 27, at 5, and the agency so advised InfraMap
during discussions. AR, exh. 8, at 1. InfraMap reduced its price
in its FPR, and the agency compared this reduced price to the
other prices received to determine whether it was realistic. The
agency found that InfraMap's price compared favorably to the
other prices. It thus concluded that, since there was adequate
price competition, InfraMap's proposed price was realistic,
reasonable and complete. AR, exh. 22, at 3, 5-8. The agency's
methodology was consistent with the applicable standard, and its
conclusion was reasonable in light of the fixed-price nature of
the requirement, the comparability of the prices received and
the adequacy of the competition. Under these circumstances, the
protester's general assertion that InfraMap may not have
understood the requirement is not sufficient to bring the
agency’s determination into question. In this regard, the agency
rated InfraMap's proposal superior to the others received, and
Accumark has raised no substantive challenge to the agency’s
evaluation conclusions. See Consolidated Servs., Inc., supra. (Accumark,
Inc., B-310814, February 13, 2008) (pdf)
When an agency evaluates a proposal for the award of a
cost-reimbursement contract, an offeror’s proposed estimated
costs are not dispositive because, regardless of the costs
proposed, the government is bound to pay the contractor its
actual and allowable costs. Federal Acquisition Regulation (FAR)
sections 15.305(a)(1); 15.404-1(d); Tidewater Constr. Corp.,
B-278360, Jan. 20, 1998, 98-1 CPD para. 103 at 4. Consequently,
the agency must perform a cost realism analysis to determine the
extent to which an offeror’s proposed costs are realistic for
the work to be performed. FAR sect. 15.404-1(d)(1). An agency is
not required to conduct an in-depth cost analysis, see FAR sect.
15.404-1(c), or to verify each and every item in assessing cost
realism; rather, the evaluation requires the exercise of
informed judgment by the contracting agency. Cascade Gen., Inc.,
B-283872, Jan. 18, 2000, 2000 CPD para. 14 at 8. Further, an
agency’s cost realism analysis need not achieve scientific
certainty; rather, the methodology employed must be reasonably
adequate and provide some measure of confidence that the rates
proposed are reasonable and realistic in view of other cost
information reasonably available to the agency as of the time of
its evaluation. See SGT, Inc., B‑294722.4, July 28, 2005, 2005
CPD para. 151 at 7; Metro Mach. Corp., B-295744; B‑295744.2,
Apr. 21, 2005, 2005 CPD para. 112 at 10-11. Because the
contracting agency is in the best position to make this
determination, we review an agency’s judgment in this area only
to see that the agency’s cost realism evaluation was reasonably
based and not arbitrary. Hanford Envtl. Health Found.,
B‑292858.2, B-292858.5, Apr. 7, 2004, 2004 CPD para. 164 at 8-9.
NHIC contends that the cost realism analysis was not adequately
documented. Although the record consists of multiple documents
and reports reflecting the analysis performed by the SMEs, TEP,
and BEP, NHIC contends that the documents themselves do not
explain the agency’s rationale and contain only “checked boxes
[referring to worksheets where a SME or TEP member checked “yes”
or “no” as to whether there was a basis for adjusting costs],
conclusory assertions, and discussions questions” to show that
costs were realistic. NHIC's Post-Hearing Comments at 2. We find
that the record shows that the agency performed a comprehensive
and thorough cost realism analysis that considered all of the
major cost elements for each of the functional areas to be
performed under the contract. The agency relied on the TEP
members and SMEs, each of whom has special expertise in the
functional areas, to review whether the proposed labor hours and
mix of labor categories were realistic for the work to be
performed and were consistent with the offeror’s technical
approach. In addition, the BEP consulted with the DCAA to verify
that labor rates and other costs were reasonable. The record
contains extensive contemporaneous documentation--numerous
spreadsheets, worksheets, discussion questions and responses,
and reports--that were created by the SMEs, TEP, and BEP.
Although it is true that the documents are replete with
conclusory statements that proposed costs were realistic, the
record nonetheless evidences that a comprehensive cost realism
analysis was performed and contains documents, such as the
briefing slides to the SSB and the source selection
determination, that provide the rationale for the agency’s cost
realism conclusions. E.g., AR, Tab 58, SSB Presentation, at
10-13; Tab 57, Supplemental SSB Presentation, at 2-4; Tab 56,
Source Selection Determination, at 3-4; see also Contracting
Officer's Statement paras. 61-73.
During the hearing held by our Office, and as reflected in the
contemporaneous documents, the agency explained why, and how,
the evaluators determined that Palmetto’s proposed costs,
including labor costs, were realistic, even though they were
lower than the costs proposed by NHIC.[11] Specifically, as
stated above, Palmetto took advantage of the opportunity,
throughout its proposal, to [REDACTED]. Tr. at 26. Other
identified reasons for Palmetto’s lower costs were that Palmetto
[REDACTED] and identified a number of “efficiency drivers” for
claims processing, appeals, and medical review. AR, Tab 56,
Source Selection Determination, at 2-3; Tab 57, Supplemental SSB
Presentation, at 2‑4; Contracting Officer’s Statement paras.
61-73; Tr. at 17-27, 30-31, 34, 38-39, 105-06, 406-17. Specific
examples of some of these “efficiency drivers” for three of the
major activities (claims processing, appeals, and medical
review), as enumerated in the contemporaneous documents,
include:
(Deleted sections)
NHIC contends that
there is no basis to conclude that any of the proposed
“efficiency drivers” would result in cost savings, since the
agency failed to quantify any of the asserted cost savings.
However, an adequate cost realism analysis does not require an
in‑depth verification of each and every item; an agency may
reasonably rely on statements in an offeror's proposal which
demonstrate the realism of its proposed costs, without
independently verifying each item of proposed costs. Pacific
Architects and Eng'rs, Inc., B‑274405.2, B-274405.3, Dec. 18,
1996, 97‑1 CPD para. 42 at 7; Ferguson-Williams, Inc.; Hawk
Mgmt. Servs., Inc., B-232334, B‑232334.2, Dec. 28, 1988, 88-2
CPD para. 630 at 6. Here, Palmetto’s proposal explained that its
“labor estimating approach” was based on [REDACTED]. Palmetto’s
proposal identified [REDACTED]. Agency Hearing exh. A,
Palmetto's Initial Proposal, at 26-61. As the contracting
officer explained, Palmetto “did a really good job of laying out
‘this is what we’ve been doing, this is what we're going to do
for you now, and this is the impact.'”Tr. at 91, 174. The SMEs
and TEP members considered this information contained in
Palmetto's proposal, looked to see whether the approach was
feasible, and based on their own experience, could find no basis
to upwardly adjust Palmetto's proposed costs. Tr. at 453, 483,
492-93, 522‑23. NHIC has not shown that the agency's evaluation
was unreasonable.
(sections
deleted)
In sum, NHIC has
not shown the agency's "bottom up" cost realism evaluation to be
unreasonable. As discussed above, the agency followed a process
that is consistent with the FAR, in that the
agency“independently review[ed] and evaluat[ed] specific
elements of each offeror's proposed cost estimate to determine
whether the estimated proposed cost elements are realistic for
the work to be performed; reflect a clear understanding of the
requirements; and are consistent with the unique methods of
performance and materials described in the offeror’s technical
proposal.” FAR sect. 15.404-1(d)(1). Moreover, except for its
arguments that historical data should have been the basis for
the cost realism analysis, which we have rejected, NHIC has not
demonstrated, or even attempted to quantify, that cost realism
adjustments in the challenged areas would have eliminated the
$92 million cost differential and resulted in NHIC's most
probable cost being lower than Palmetto’s; thus, NHIC has not
shown that its proposal, which was technically equal to
Palmetto's, had a substantial chance for award. (NHIC
Corporation, B-310801; B-310801.2, February 12, 2008) (pdf)
The protester first argues that the EPA made improper “realism”
adjustments to certain fixed-price elements of IBM’s proposal,
and failed to equally or reasonably evaluate CGI’s proposal. As
discussed above, the agency stated that it would perform both a
cost realism and price realism analysis, as well as assess the
“total cost of ownership” associated with offerors’ proposals.
In the discussion that follows, we address the adjustments that
were made to IBM’s proposal for SCORPIOS replacement, Tier 3
hosting requirements, EPA implementation efforts, and IFMS
retirement costs. We conclude with a discussion of EPA’s
evaluation of certain elements of CGI’s costs.
A cost realism analysis is required when an agency evaluates
proposals for the award of a cost-reimbursement contract. Under
such a contract, an offeror’s proposed costs are not considered
controlling because, regardless of the costs proposed, the
government is bound to pay the contractor its actual and
allowable costs. Federal Acquisition Regulation (FAR) sections
15.305(a)(1), 15.404-1(d). Consequently, an agency must perform
a cost realism analysis to determine the extent to which an
offeror’s proposed costs represent what the contract should
cost, assuming reasonable economy and efficiency. FAR sect.
15.404-1(d)(2); Hanford Envtl. Health Found., B-292858.2,
B-292858.5, Apr. 7, 2004, 2004 CPD para. 164 at 8-9. Although
there is no requirement that an agency perform a cost realism
analysis when offerors propose to perform work on a T&M basis
with fixed-price labor rates, agencies may, as here, provide for
such an evaluation in a solicitation. Resource Consultants,
Inc., B-290163, B-290163.2, June 7, 2002, 2002 CPD para. 94 at
n.1. Cost realism may involve adjustments to proposed costs to
calculate the most probable cost to the government of the
offeror’s proposed approach. In contrast, where an RFP
contemplates the award of a fixed-price contract, or fixed-price
portion of a contract, an agency may also provide in the
solicitation for the use of a price realism analysis for the
limited purpose of measuring an offeror’s understanding of the
requirements or to assess the risk inherent in an offeror’s
proposal. Puglia Eng’g of California, Inc., B-297413 et al.,
Jan. 20, 2006, 2006 CPD para. 33 at 6-7. Although the FAR does
not use the term “price realism,” it provides that cost realism
analysis may be used to evaluate fixed-price proposals as
follows:
Cost realism analyses may also be used on competitive
fixed-price incentive contracts or, in exceptional cases, on
other competitive fixed-price-type contracts when new
requirements may not be fully understood by competing offerors,
there are quality concerns, or past experience indicates that
contractors’ proposed costs have resulted in quality or service
shortfalls. Results of the analysis may be used in performance
risk assessments and responsibility determinations. However,
proposals shall be evaluated using the criteria in the
solicitation, and the offered prices shall not be adjusted as a
result of the analysis.
FAR sect. 15.404-1(d)(3). Thus, as the FAR explains, a
price realism analysis may affect the technical evaluation, but
cannot result in an adjustment of an offeror’s proposed fixed
prices. Id.; see also Puglia Eng’g of California, Inc., supra;
Verestar Gov’t Servs. Group, B-291854, B-291854.2, Apr. 3, 2003,
2003 CPD para. 68 at 6 n.3; Marquette Med. Sys., Inc.,
B-277827.5, B-277827.7, Apr. 29, 1999, 99-1 CPD para. 90 at 6.
Specifically, an agency cannot make upward price adjustments for
cost elements that the agency thinks may be priced too low. All
Phase Environmental, Inc., B-292919.2 et al., Feb. 4, 2004, 2004
CPD para. 62 at 8. (IBM Corporation,
B-299504; B-299504.2, June 4, 2007) (pdf)
Fedcar also asserts that the agency’s price evaluation was
unreasonable because the agency inserted incorrect numbers into
the price evaluation spreadsheet, which resulted in an error in
favor of Duke’s present value ANSI/BOMA office area per square
foot price. In its report, the agency admits that it erred in
calculating the present value of the rent being offered by Duke,
and that, instead of a price difference of [DELETED] per ANSI/BOMA
square foot, the actual price advantage of the rent offered by
Fedcar was [DELETED] per ANSI/BOMA square foot. Supplemental AR
(Feb. 25, 2008) at 5; AR, Tab 40, Net Present Value
Recalculation. The agency further admits that this error results
in a net present value difference of [DELETED] per year, or
[DELETED] over the 15-year life of the lease. Supplemental AR
(Feb. 25, 2008), at 6. However, the agency dismisses this
mistake as inconsequential and asserts that Fedcar is not
prejudiced by the error because the solicitation stated that
“the technical evaluation factors, when combined, are
significantly more important than price.” Id.
We disagree. As indicated above, the record shows the technical
evaluation of the two proposals was relatively close with Duke’s
technical proposal having only a [DELETED]-point advantage (out
of 100 points) over Fedcar’s proposal. AR, Tab 35, Price
Negotiation Memorandum (Dec. 17, 2007), at 3. While it is true
that the technical evaluation factors were said to be
significantly more important than price, the SFO also stated,
“[a]s proposals become more equal in their technical merit, the
evaluation of price becomes more important.” SFO, as amended, at
32. With an initial price differential of only [DELETED] per
square foot, the source selection authority (SSA) could
reasonably place greater emphasis on technical merit in
selecting Duke. Now, however, since the actual price
differential ([DELETED] per square foot) between the offers is
significantly (more than [DELETED] times) greater, if the award
decision were to be based on this revised price difference,
price under the SFO’s evaluation scheme could reasonably become
more important and change the award decision. While the agency
argues that the outcome of the SSA’s cost/technical tradeoff
would be the same regardless of the re-calculated price, our
Office affords little weight to an agency’s post-protest
arguments that are based on judgments the agency asserts it
would have made because such judgments made in the heat of
litigation and based on facts that were not previously
considered that are materially different from those on which the
agency relied in making the original decision may not represent
the fair and considered judgment of the >agency. Global, A 1st
Flagship Co., B-297235.2, Dec. 27, 2005, 2006 CPD para. 14 at 8.
Under the circumstances, we give little weight to the agency’s
assertion that the outcome would have been the same, given that
Fedcar now has a significantly greater price advantage than
found by the agency when it made its source selection decision.
Where a source selection authority bases his or her source
selection decision on figures that do not reasonably represent
the differences in costs to be incurred under competing
proposals, the source selection is not reasonably based. See
Gemmo Impianti SpA, B-290427, Aug. 9, 2002, 2002 CPD para. 146
at 5-6. Thus, Fedcar was prejudiced by the agency’s error in
calculating the price difference between the offers. (Fedcar
Company, Ltd., B-310980; B-310980.2; B-310980.3,March 25,
2008) (pdf)
CHS asserts that
the agency failed to properly evaluate LHI’s price for
reasonableness. Specifically, CHS notes that more than 100 of
LHI’s individual medical procedure prices exceeded the agency’s
independent government cost estimates (IGCE), and that LHI’s
overall price exceeds the agency’s average IGCE. Where, as here,
a solicitation provides for award of a fixed-price
contract--under which the government’s liability is fixed and
the contractor bears the risk and responsibility for the actual
costs of performance--the agency need only evaluate an offeror’s
price for fairness and reasonableness. Federal Acquisition
Regulation (FAR) sections 15.402(a), 15.404-1(a); SAMS El
Segundo, LLC, B-291620.3, Feb. 25, 2003, 2003 CPD para. 48 at 8.
Agencies may use various price analysis techniques and
procedures to ensure a fair and reasonable price, including the
comparison of proposed prices received in response to the
solicitation and comparison with an IGCE. FAR sect.
15.404-1(b)(2)(i), (v). Agencies may rely upon adequate price
competition alone to assess price reasonableness. MVM, Inc.,
B-290726 et al., Sept. 23, 2002, 2002 CPD para. 167 at 6. A
price reasonableness determination is a matter of administrative
discretion involving the exercise of business judgment by the
contracting officer that we will question only where it is
unreasonable. The Right One Co., B-290751.8, Dec. 9, 2002, 2002
CPD para. 214 at 5. The price reasonableness evaluation here,
based on adequate price competition and a comparison of prices
with the agency IGCEs, complied with the RFP’s requirements and
was unobjectionable. The RFP provided that price was to be
evaluated for completeness and reasonableness and to ensure that
the offeror understood the scope of work. RFP at 97. In
evaluating offerors’ prices, the agency compared each offeror’s
individual line item prices to those of the other offerors and
to the agency’s IGCEs, which represented both the low and high
range of estimated costs for each medical and dental procedure.
LHI’s initial overall price was approximately 19 percent higher
than the average IGCE, and CHS’s approximately 2 percent higher,
and the agency found that both prices were reasonable based on
adequate price competition and its conclusion that the prices
were within a reasonable range of the average IGCE. AR, Tab 17,
at 3. In discussions, the agency requested both offerors to
review their work scope and pricing for certain individual
procedures whose prices were lower than the low range IGCE or
higher than the high range IGCE. Both offerors changed some, but
not all, identified prices, and also reduced their overall
prices, resulting in LHI’s price being 11.05 percent higher than
the average IGCE, and CHS’s 0.10 percent higher. AR, Tab 32, at
3‑4, 8. The agency again found that there was adequate price
competition, and that both offerors’ overall prices were within
a reasonable range of the average IGCE. While CHS asserts that
LHI’s price was too far above the average IGCE to be considered
reasonable, as noted by the agency, LHI’s price was lower than
the agency’s high range IGCE. Given this fact, we find no basis
to object to the agency’s price evaluation. CHS’s disagreement
with the agency’s judgment does not make the evaluation
unreasonable. Hughes Georgia, Inc., B-272526, Oct. 21, 1996,
96-2 CPD para. 151 at 7. (Comprehensive
Health Services, Inc., B-310553, December 27, 2007) (pdf)
ITT further contends that NASA’s cost realism evaluation was
flawed because it failed to properly consider Defense Contract
Audit Agency (DCAA) audit results identifying irregularities
with BATC’s compliance with cost accounting standards (CAS)--specifically,
CAS 420--concerning, as relevant here, BATC’s allocation of its
costs for independent research and development. As a
consequence, ITT contends that NASA’s “most probable cost”
estimate for BATC was not reasonably supported. Specifically,
ITT highlights the fact that DCAA qualified its audit results
for BATC based on the fact that BATC was “noncompliant” with CAS
420, which had been reported in prior audits, indicated that the
cost impacts had not been determined, and stated that these
issues “may have a significant effect on the final cost
allocations for CAS covered Government contracts.” AR, Tab 50,
DCAA Audit for BATC, 08221. In addition, DCAA explained that the
Divisional Administrative Contracting Officer (DACO) of the
Defense Contract Management Agency for BATC would separately
negotiate the cost impact of the noncompliance. Id. The record
shows that NASA further questioned DCAA on this issue, asking
whether it could provide some indication of the magnitude of the
cost impact. DCAA responded that it could not provide such an
estimate, simply noting that the matter would be addressed by
the DACO. NASA did not pursue the matter with BATC during
discussions and did not make any adjustments to BATC’s costs as
result of the DCAA qualification. In a hearing held by our
Office, however, the DACO for BATC, who is responsible for,
among other things, cost allowability issues and interacting
with DCAA regarding its contractor audit reports with respect to
BATC’s contracts, provided testimony regarding this issue. The
DACO explained that BATC’s noncompliance relates to a 2001 audit
finding, which has not yet been resolved, that any cost impact
would be limited to fiscal year 2000 incurred costs, and that
any cost adjustment would be limited to a decrease in costs to
the government--BATC’s noncompliance would not result in
increased costs to the government. Hearing Transcript (Hearing
Tr.) at 173. Moreover, the DACO indicated that even if the
noncompliance identified in the 2001 audit were a continuing
issue, such that it implicated BATC’s 2007 contracts (something
which the DACO indicated has not been identified by DCAA), such
noncompliance by BATC again would not result in any increased
costs to the government, thus negating any concern that BATC’s
costs under the OLI contract would increase as a consequence of
the outstanding CAS issue. Id. While ITT contends that the issue
was raised by DCAA and that the DACO cannot speak for DCAA, the
record reflects that DCAA expressly indicated that the matter
would be addressed by the DACO and ITT has not explained why the
DACO’s testimony should be regarded as unreliable or otherwise
unreasonable. As a consequence, on this record, ITT’s challenge
does not provide a basis for our Office to sustain its protest
with regard to this issue. (ITT
Industries Space Systems, LLC, B-309964; B-309964.2,
November 9, 2007) (pdf)
GDIT maintains that there were a number of inconsistencies in
RTSC’s price proposal, with the labor rates included in the B.4
table being higher than the rates included in the B.2 table. The
protester identifies two areas where these inconsistencies
appear. First, RTSC’s FPR eliminated a [deleted] percent
escalation rate that it previously had applied to its direct
labor rates for its [deleted] employees. Although the firm
submitted a revised B.2 table with its FPR that reflected the
elimination of this [deleted] percent escalation rate, it did
not submit a revised B.4 table. Second, the protester has
identified some 40 additional labor categories where RTSC’s
rates in its B.4 table are higher than the rates included in the
firm’s B.2 table. According to the protester, the agency’s
failure to include the higher of these inconsistent prices in
RTSC’s evaluated price--as expressly provided for in the
RFP--resulted in an understatement of RTSC’s total evaluated
price of approximately $97 million. The agency responds that,
with respect to the [deleted] labor rates, it reasonably relied
on language appearing in the May 7 cover letter accompanying
RTSC’s FPR to conclude that the firm had reduced its pricing in
both the B.2 and B.4 tables, notwithstanding any apparent
inconsistencies between the prices in tables B.2 and B.4. This
letter provided, in pertinent part: “Our proposed burdened labor
rates for the categories and locations attached to this letter
are hereby updated accordingly for both Section B.2 and B.4.
These rates represent a total reduction of $[deleted] in our
evaluated B.2 price.” AR exh. 75, Cover Letter. The agency
maintains that this language was sufficient to obligate RTSC to
provide rates without the [deleted] percent escalation. The
agency maintains, moreover, that, even if this language was
inadequate to obligate RTSC, this is a minor clerical error that
can be corrected after award. With respect to the other 40
inconsistent labor rates, the agency states that it relied on
similar language appearing in the firm’s proposal providing
that: “Raytheon assures that the rates proposed in Section B.2
‘T&M Evaluation Worksheets’ are consistent with B.4 ‘Loaded
Labor Rates Matrix,’” and further providing that “[e]ach site
referenced in the B.2 tables has been mapped into the
corresponding B.4 Appendix B Locations on the tabs of the B.4
workbooks.” AR exh. 60, Volume 5_Book 2_CP_rev2.doc, at 76. The
agency asserts that this was sufficient to indicate that RTSC
intended to be bound by the lower rates appearing in the B.2
table.
We find that the agency improperly failed to include an
additional $97 million (consistent with GDIT’s calculation) in
RTSC’s evaluated price. The RFP was unequivocal regarding how
the agency was to evaluate proposals in the event of an
inconsistency between the B.2 and B.4 tables:
Section B.2 ‘Time and Materials
Evaluation Worksheets’ will be evaluated to ensure that the
rates proposed are consistent with the B.4 ‘Loaded Labor
Rates Matrix’ . . . . Inconsistencies between B.2 and B.4
rates, or between B.3 and B.5/B.6 FFP, will result in the
Government using the higher of the inconsistent rates/prices
for the Total Evaluated Price.
RFP at M-3. It is undisputed that
RTSC’s B.2 table included revised prices that were inconsistent
with the higher prices in its B.4 table. Under the above-quoted
language, in this situation, the agency was to include the
higher prices in the evaluation. The agency, in relying upon the
information in RTSC’s cover letter, disregarded this express RFP
provision in arriving at RTSC’s total evaluated price. The
agency’s reliance on the language in the May 7 cover letter, in
lieu of the approach plainly set forth in the RFP, was
misplaced. Not only was such reliance inconsistent with the
plain language of the RFP but, in any case, the cover letter
language rendered RTSC’s proposal, at best, ambiguous. In this
regard, although RTSC purported to revise both its B.2 and B.4
tables by the terms of the cover letter, as noted, it submitted
only a revised B.2 table and stated that its proposed change
“represents a total reduction of $[deleted] in our evaluated B.2
price.” AR exh. 75. Other portions of RTSC’s proposal--including
its B.4 table--remained unchanged by the May 7 revision,
including the narrative replacement pages to its proposal that
RTSC had previously submitted in connection with its earlier
offer of the [deleted] percent escalation for its [deleted]
employees. AR exh. 42d, Vol. 5, book 2 change pages, at 157-57f.
Thus, RTSC’s B.4 table and narrative proposal continued to offer
the [deleted] percent annual escalation to its [deleted]
employees’ compensation, notwithstanding the language of its
cover letter. Agencies are required to evaluate proposals
in a manner consistent with the solicitation. Clean Harbors
Env’t Servs., Inc., B-296176.2, Dec. 9, 2005, 2005 CPD para. 222
at 3. The RFP here expressly provided that the agency would
evaluate inconsistent pricing in a very specific manner, and the
agency failed to evaluate RTSC’s proposal consistent with the
RFP ground rules. (General Dynamics
Information Technology, B-299873, September 19, 2007) (pdf)
An agency may not
reasonably award a cost‑reimbursement contract to an offeror
whose cost proposal evidenced a different technical approach
than that presented in the technical proposal, without resolving
the inconsistency. See TRW, Inc., B‑254045.2, Jan. 10, 1994,
94-1 CPD para. 18 at 8-9. Here, the agency failed to resolve the
inconsistency presented in MTJV’s cost and technical proposals.
In any case, we find no reasonable basis in the record for the
Navy’s “assumption” that Tecnico’s rates were “representative of
prevailing Mayport area labor rates.” As noted by the protester,
Tecnico’s burdened labor rate of $[Deleted] was significantly
lower than all but one of the other offerors’ and their
subcontractors’ burdened labor rates. In fact, we calculate the
average burdened labor rate for offerors and their
subcontractors to be $[Deleted].[6] More specifically, Tecnico’s
burdened labor rate was significantly lower than the rates
proposed by Earl ($[Deleted]), Atlantic Marine ($[Deleted]), and
QED ($[Deleted]), which were the firms specifically identified
by MTJV for possible performance of [Deleted] percent of the
contract work. Although the Navy provided the declaration of the
CAP chairperson, who generally states that he found that
Tecnico’s rate was comparable to rates of other contractors
working in the Mayport area, see Navy’s Response to Earl’s
Comments, attach. D, Declaration of CAP Chair, at 2, this
declaration does not explain with any specificity how he
determined this, nor does the Navy otherwise address or rebut
the protester’s arguments concerning Tecnico’s lower rate
compared to the offerors’ rates in this competition. We also
note that allowing MTJV to propose subcontracting a significant
amount of the contract to unnamed subcontractors appears to also
be inconsistent with the RFP’s requirements to identify and
provide cost proposals for significant subcontractors, which the
RFP defined, in part, to be contractors that were providing
effort consisting of 5 percent of total direct dollars. See RFP
sect. L, at 154, 159. With respect to the Navy’s contention that
Earl similarly proposed to perform [Deleted] percent of the
contract with subcontractors other than those it proposed in its
cost proposal, we fail to see how, even if this were true, this
demonstrates that the agency’s cost realism evaluation was
reasonable. In any event, as noted above, MTJV stated in its
technical proposal that it would allocate [Deleted] percent of
its productive hours assigned to Tecnico at that firm’s low
labor rate to other “miscellaneous specialty contractors,” which
all appear to have higher labor rates than Tecnico’s. Earl, on
the other hand, stated in its technical proposal that [Deleted]
percent of the contract work would be performed by its
identified team of subcontractors (whose labor rates were
considered in the agency’s cost realism analysis), and that Earl
would “accomplish the remaining work with the assistance of our
Surge/Specialty Subcontractors” (all of which were also
specifically identified in Earl’s proposal). See AR, Tab 5, Earl
Technical Proposal, at 25-26. There is no evidence in the
record, nor has the agency provided any argument, that indicates
that any of the surge/specialty subcontractors identified by
Earl in its proposal have higher rates than Earl. In any event,
unlike MTJV’s unequivocal statement that work allotted to
Tecnico would be performed by others, Earl stated it would
perform [Deleted] percent of the contract work, albeit with the
assistance of the identified surge/specialty subcontractors.
(Earl Industries, LLC, B-309996;
B-309996.4, November 5, 2007) (pdf)
Navarro challenges the adequacy of the agency’s price realism
analysis. In this regard, section M of the RFP stated that
proposals “will be evaluated to determine if the proposed costs
are realistic and consistent with the Technical Proposal with
regard to the nature, scope, and duration of the work to be
performed. Inconsistencies between the Cost/Price Proposal and
other portions of the proposal could raise concerns regarding
the offeror’s understanding of the requirements and ability to
perform the work for the proposed price.” RFP at 92. Where
a fixed-price contract--including a fixed-rate contract such as
this one--is to be awarded, an agency may provide for the use of
a price realism analysis in a solicitation for such purposes as
measuring an offeror’s understanding of the solicitation’s
requirements and for assessing the risk inherent in an offeror’s
proposal. Star Mountain, Inc., B-285883, Oct. 25, 2000, 2000 CPD
para.189 at 4. The Federal Acquisition Regulation (FAR)
identifies a number of price analysis techniques that may be
used to determine whether prices are reasonable and realistic,
including comparison of the prices received with each other and
with the independent government estimate, and analysis of
pricing information provided by the offeror. FAR sect.
14.404-1(b)(2). The nature and extent of a realism analysis
ultimately are matters within the agency’s discretion, unless
the agency commits itself to a particular methodology in the
solicitation. Id. DOE’s realism analysis consisted of
comparing the proposed rates for the specified labor categories
to both the government estimate and the other proposed prices,
and the use of statistical analysis techniques to analyze the
information. Technical Evaluation Report (TER) at 37-46 and
attach. 4. As a result of its analysis, the agency concluded
that all offerors’ total prices were realistic, including
Stoller’s, which was approximately 11.6 percent lower than the
government estimate. AR at 25, 28. In this regard, the agency
found that some of Stoller’s and other offerors’ labor rates
were lower than the government estimate and that some were
higher, but concluded that, overall, all offerors’ proposed
rates were consistent with the estimate. AR at 25. In addition,
DOE verified that each offeror’s prices reflected the estimated
number of labor hours for each labor category specified in the
RFP. We find nothing objectionable in the agency’s evaluation
methodology. Navarro complains that the realism analysis
was flawed because it was based on a government estimate that
was not prepared until after the proposals were received.
However, there is nothing per se improper in an agency’s
reliance on a government estimate revised after offers are
received where it determines that the original estimate is
erroneous. McCarthy Mfg. Co., B-186550, Feb. 17, 1977, 77‑1 CPD
para. 116 at 3-4. DOE explains that it reduced the government
estimate after proposals were received to correct errors and to
account for inapplicable and likely inaccurate assumptions. For
example, among other things, DOE reduced the overhead rate
assumption from 100 percent to 50 percent because the lower rate
was consistent with similar contracts performed on government
property. The agency also reduced the profit rate to correspond
to the rates offerors actually proposed. AR at 29-30. Navarro
does not challenge any specific changes made by the agency, and
does not assert--and we find no reason to conclude--that the
estimate itself is unreasonable. Accordingly, we find no basis
for questioning the agency’s use of the revised estimate. (Navarro
Research and Engineering, Inc., B-299981; B-299981.3,
September 28, 2007) (pdf)
Protest is sustained where (1) solicitation for combat search
and rescue aircraft provided that cost/price would be calculated
on the basis of Most Probable Life Cycle Cost, including both
contract and operations and support (O&S) costs, (2)
solicitation requested detailed information quantifying required
maintenance for proposed aircraft, and (3) agency nevertheless
normalized cost of maintenance when calculating O&S costs,
thereby ignoring potentially lower cost of asserted low
maintenance helicopters; once offerors are informed of criteria
against which proposals will be evaluated and award made, agency
must adhere to those criteria. (Sikorsky
Aircraft Company; Lockheed Martin Systems Integration‑Owego,
B-299145; B-299145.2; B-299145.3, February 26, 2007) (pdf)
The FAR provides a number of price analysis techniques that may
be used to determine whether prices are fair and reasonable,
including comparison of the prices received with each other;
comparison of previously proposed prices for the same or similar
items; and comparison with the independent government estimate.
FAR sect. 15.404-1(b)(2). A price reasonableness determination
is a matter of administrative discretion involving the exercise
of business judgment by the contracting officer that we will
question only where it is unreasonable. The Right One Co.,
B-290751.8, Dec. 9, 2002, 2002 CPD para. 214 at 5. Our review of
the record here provides no basis to question the reasonableness
of the contracting officer’s determination. Section M of
the RFP, quoted above, clearly stated that an offeror’s
evaluated price would be calculated by multiplying each of the
priced line items by the estimated quantities and by adding all
of the extended prices to arrive at the lowest total evaluated
price for the varied quantities. RFP amend. 2, adden., attach.
1, Price Evaluation. Further, section M did not require the use
of price realism analysis to measure the offerors’ understanding
of the government’s requirements or to assess the risk inherent
in an offeror’s proposal. PHP Healthcare Corp., B-251933, May
13, 1993, 93-1 CPD para. 381 at 5. Rather, as described above,
the record shows that the contracting officer agency conducted a
price reasonableness evaluation based upon adequate price
competition, which reflected approximately a 4 percent
differential between the proposals of USDC and USTI, along with
comparison of the proposed prices to the government estimate.
Although USDC’s essential complaint is that the contracting
officer’s analysis should have been more exhaustive, our review
confirms that the price evaluation conducted by the agency was
reasonable and fully consistent with the provisions of the RFP.
USDC asserts that the contracting officer should have obtained
and analyzed additional information in evaluating offerors’
proposed prices. In support of its position, USDC points to
language in section L of the RFP which states that information
other than costs and pricing data may be required to support
price reasonableness. As discussed above, in this case, section
M of the RFP did not require that additional information would
be evaluated as part of the agency’s price evaluation. Absent an
RFP provision in a solicitation for a fixed-price contract
requiring a price realism analysis, no such analysis is
required. Dismas Charities, Inc., B-289575.2; B-289575.3, Feb.
20, 2004, 2004 CPD para. 66 at 4. (U.S.
Dynamics Corporation, B-298889, December 19, 2006) (pdf)
The RFP provided possible methods for evaluating price
reasonableness: information submitted with the offeror’s
proposal, the comparison of other competitive offers, the
independent government cost estimate (IGCE), or on any other
reasonable basis. RFP amend. 3, sect. M, at 35. Of these
options, the agency chose to evaluate price reasonableness by
comparing price proposals to each other as well as to the IGCE.
The agency has adequately documented its price analysis and
reasonably determined, based on a comparison of price proposals
and comparison of the prices to the IGCE, that the awardees’
prices were fair and reasonable. Agency Report, Tab 25,
Cost/Price Analysis Report, at 1. While the protester alleges
the agency should have conducted a more in-depth analysis of the
price proposals, the depth of an agency’s price analysis is a
matter within the sound exercise of the agency’s discretion; we
find no legal requirement here for the agency to have done a
more in-depth analysis than was undertaken here. See Redcon,
Inc., B‑285828, B‑285828.2, Oct. 11, 2000, 2000 CPD para. 188 at
9. Given that Indtai’s price is significantly higher than the
awardees’ prices, many of the protester’s contentions concern
the agency’s alleged failure to perform sufficient analysis to
determine whether the awardees’ prices were too low or consider
the performance risk of these assertedly low prices. However,
the purpose of a price reasonableness analysis is to determine
whether the prices offered are higher--as opposed to lower--than
warranted. See Dismas Charities, Inc., B‑289575.2, B-289575.3,
Feb. 20, 2004, 2004 CPD para. 66 at 4; Sterling Servs. Inc.,
B-291625, B-291626, Jan. 14, 2003, 2003 CPD para. 26 at 3. In
contrast, arguments that the agency did not perform an
appropriate analysis to determine whether prices are too low
such that there may be a risk of poor performance concern price
realism not price reasonableness; price realism is not required
to be evaluated by the agency unless the solicitation provides
for such an analysis. Dismas Charities, Inc., supra. Here, the
solicitation did not provide for a cost realism analysis and the
agency therefore did not have to perform such an analysis.
(Indtai
Inc., B-298432.3, January 17, 2007)
(pdf)
CAS
401--which is applicable to ACC--requires a contractor’s
practices in estimating costs for a proposal to be consistent
with cost accounting practices used by the contractor in
accumulating and reporting costs. 48 C.F.R. sect. 9904.401-20
(2005). This requirement is imposed because “[c]onsistency in
the application of cost accounting practices is necessary to
enhance the likelihood that comparable transactions are treated
alike,” so that, among other things, there is “financial control
over costs during contract performance.” Id. More significantly,
CAS 402--also applicable to ACC--states:
All costs incurred for the
same purpose, in like circumstances, are either direct costs
only or indirect costs only with respect to final cost
objectives. No final cost objective shall have allocated to it
as an indirect cost any cost, if other costs incurred for the
same purpose, in like circumstances, have been included as a
direct cost of that or any other final cost objective.
Further, no final cost objective shall have allocated to it as
a direct cost any cost, if other costs incurred for the same
purpose, in like circumstances, have been included in any
indirect cost pool to be allocated to that or any other final
cost objective.
48 C.F.R. sect. 9904.402-40.
Because of these requirements, ACC was and will be required to
account for its costs in a manner consistent with its
established accounting practices during the course of this
contract performance. General Research Corp., B-241569, Feb. 19,
1991, 91-1 CPD para. 183 at 9; CACI, Inc.--Fed., B‑216516, 84-2
CPD para. 542 at 10‑13. Consequently, in determining ACC’s
evaluated probable cost for performing this contract, the agency
could not reclassify costs that ACC treats as indirect costs in
its accounting system as direct costs. See General Research
Corp., supra; CACI, Inc.--Fed., supra. The agency argues that
this adjustment was necessary in order to allow for a more
“equitable” comparison of the cost proposals. In effect, the
agency here has selectively “normalized” the cost elements
included in the offerors’ indirect cost pools. Normalization is
a technique sometimes used within the cost evaluation/adjustment
process that involves measuring offerors against the same cost
standard or baseline where there are no logical differences in
approach or in situations where insufficient information is
provided in the proposals. General Research Corp., supra. Such a
normalization process was improper here because ACC’s proposal
necessarily accounted for PMO costs as part of its indirect
costs, which were required to be accounted for in a like manner
under this contract.[4] Therefore, the agency’s “normalization”
of PMO costs among the offerors with different accounting
systems necessarily resulted in an unreasonable estimate of the
offerors’ proposed costs for performing this contract. General
Research Corp., supra, at 5-6, 9. Moreover, the agency has never
explained why deleting PMO costs from proposed indirect costs
will result in a more equitable comparison of proposals. There
is no evidence in the record that the shifting of costs from
indirect to direct can result in a number that represents the
probable costs of a particular proposal in performing the
contract, because there is no indication that the cost model’s
plug number represents the direct cost approach that will be
taken by each contractor. The agency asserts that because
an RFP amendment advised offerors, in response to an offeror’s
question, that a “standing PMO” would not be funded, offerors
were on notice that PMO costs were “within the scope of direct
costs fixed by the Navy.” Agency Brief (Oct. 20, 2006) at 2; see
RFP amend. 3, attach. 1, Q&A 44. The agency posits that its cost
evaluation adjustment to account for ACC’s different treatment
of PMO costs was therefore appropriate in order to allow for an
“equitable” comparison of the proposals. This argument is
meritless for a variety of reasons. First, the statement that
the agency would not fund a “standing PMO” does not suggest that
PMO costs were included as direct costs; if anything, it
suggests the opposite. Also, as noted above, the agency does not
explain how this statement would allow ACC to vary from its
established accounting practices with regard to PMO costs.
Finally, there is no evidence that any PMO costs were included
in the “plug” numbers for direct costs. The agency argues that
KBR was not prejudiced because it was also the beneficiary of a
downward cost adjustment in its indirect costs. However, as
noted above, the adjustment to KBR’s probable costs was to
properly account for an apparent overstatement in several of its
indirect rates, which is an entirely different proposition than
reclassifying costs that had been properly included in indirect
cost pools to direct costs. Finally, as noted by the protester,
several of ACC’s indirect cost rates are significantly less than
those proposed by the other offerors, which KBR suggests
evidences that costs which other offerors charged as indirect
costs may be charged as direct costs by ACC. KBR contends that
given the multiple accounting variances amongst the offerors,
the agency’s “singling out” of ACC’s PMO costs to adjust from
indirect costs to direct costs was unreasonable and represented
unequal treatment. The agency has offered no substantive
response to this KBR contention, which, based on this record,
appears to have merit. In sum, the agency’s adjustment to ACC’s
proposal was unreasonable and prejudiced KBR because it resulted
in ACC being evaluated as having a lower cost than KBR, such
that no cost/technical tradeoff was performed. (Kellogg
Brown & Root Services, Inc., B-298694; B-298694.2;
B-298694.3, November 16, 2006) (pdf)
Multimax, BAE and Pragmatics assert that the Army’s evaluation
of proposed labor rates was unreasonable. In this regard, the
Army reports that it employed a two‑step approach to evaluating
labor rates for purposes of determining price reasonableness,
detecting unbalanced pricing, and identifying labor rates to
question during discussions: first, it compared an offeror’s
rate for a labor category to the IGCE rate for that category,
and then it compared the rate to the mean of all offerors’
evaluated rates for each labor category using a
two‑standard‑deviation measure. The agency’s price evaluator
explained the second step as follows:
Next, the Price evaluation team calculated the mean of all
offerors’ evaluated labor rates for each labor category. The
mean evaluated labor rates were then used to calculate the
standard deviation from the mean. In order to determine the
most appropriate measure of comparison, the following were
calculated: mean plus and minus one standard deviation, mean
plus and minus two standard deviations, and mean plus and
minus three standard deviations. A comparison was made, using
the three separate standard deviations, to determine which
offerors’ average labor rates for each labor category fall
outside the range of each standard deviation. The majority of
the offerors’ average labor rates fell outside the range of
one standard deviation and no offeror’s average labor rates
fell outside the range of three standard deviations.
Therefore, it was determined that two standard deviations was
the most appropriate measure of comparison to use for the
reasonableness assessment.
Memorandum of Agency Price Evaluator to Source Selection
Evaluation Board (SSEB) Chairperson, Nov. 29, 2005, at 2-3;
Agency Comments, Sept. 21, 2006, at 3.
Under this two-step approach, the agency would issue an IFN1 to
an offeror questioning a proposed labor rate as significantly
overstated (or understated) only if the rate both exceeded (or
was lower than) the IGCE rate, and was more than two standard
deviations greater (or less) than the mean rate of all offerors
for that category. According to the contracting officer (who was
responsible for conducting discussions and determining overall
price reasonableness), the two-step evaluation was used to
identify “extraordinary outlier rates,” that is, “rates that
were significantly overstated or understated and which might
pose a risk to the Government of paying an unreasonable amount
during performance. . . . Rates that did not meet [both] tests
were not considered outliers and were not questioned.” Second
Declaration of Contracting Officer at 1; see Agency Comments,
Sept. 8, 2006, 3-8, 16; Agency Comments, Sept. 21, 2006, at 3;
Declaration of Agency Price Evaluator, Aug. 18, 2006, at 1.
The two-standard-deviation formula resulted in an extremely wide
range of acceptable rates for the labor categories. The upper
end of the range was significantly above the IGCE for some of
the labor categories, and in some instances was nearly, or more
than, twice the IGCE (such as $[REDACTED] versus the $[REDACTED]
IGCE rate for Application System Analyst-Senior, $[REDACTED]
versus the $[REDACTED] IGCE rate for Software Engineer-Senior,
and $[REDACTED] versus the $[REDACTED] IGCE rate for Information
Security Specialist-Senior). Likewise, the lower end, in some
instances, was below the federal minimum wage or was even a
negative number (such as $[REDACTED] for Project Administrator,
$[REDACTED] for Information Security Specialist-Senior, and
$[REDACTED] for Information Security Specialist‑Associate).
There is no indication that the agency ever reviewed the results
of the formula to assure that the prices at the extreme end of
the ranges reflected reasonable pricing; rather, the agency
mechanistically applied the formula and accepted the results
without further analysis. We conclude that the agency’s
methodology did not provide a valid means for identifying
“outlier” (questionable) rates, and this aspect of the
evaluation therefore was unreasonable. See generally Metro Mach.
Corp., B‑297879.2, May 3, 2006, 2006 CPD para. 80 at 9‑10
(mechanical application of an agency’s own estimates for labor
hours or costs to determine evaluated costs, without the
exercise of informed judgment by the contracting agency in
independently analyzing the offeror’s proposed costs based upon
its particular approach and circumstances, was unreasonable);
The Jonathan Corp.; Metro Machine Corp., B-251698.3, B-251698.4,
May 17, 1993, 93-2 CPD para. 174 at 11-13; United Int’l Eng’g,
Inc. et al., B-245448.3 et al., Jan. 29, 1992, 92-1 CPD para.
122 at 11. We therefore sustain the protests of Multimax, BAE
and Pragmatics on the basis that the Army failed to reasonably
evaluate proposed labor rates. (Multimax, Inc.; NCI
Information Systems, Inc.; BAE Systems, B-298249.6, B-298249.7,
B-298249.8, B-298249.9, B-298249.10,October 24, 2006) (pdf)
——————————————
1 Items for Negotiation
(IFN)
EHMC challenges the agency’s determination that its price was
unreasonably high, noting that its price was lower than both the
prices VA has paid for the same services under a previous
contract, and the cost guidelines utilized by the Medicare
program for home oxygen services. The agency formulated the
government estimate based primarily on the prices it was
currently paying under the 6‑month contract extension negotiated
in October, but increased the price for CLIN 1--for oxygen
concentrators, which formed the largest single segment of the
contract--from $60 (the extension price) to $90. Even with this
50-percent increase in the CLIN 1 price, as noted, EHMC’s price
exceeded the estimate by 39 percent. Notwithstanding that there
may have existed other price measures that would have been more
favorable to EHMC, comparison of prices to a government estimate
is a legitimate means of determining price reasonableness. See
Bahan Dennis, Inc., B‑249496.3, Mar. 3, 1994, 94-1 CPD para. 184
at 3 (cancellation based solely on comparison to the government
estimate was reasonable). This is particularly the case here,
since the estimate was largely based on prices currently being
paid under an existing contract. EHMC asserts that the
estimate was too low and did not constitute a proper basis for
determining price reasonableness. Specifically, EHMC argues
that, since the prior contract was awarded to MCS on January 1,
2001, and since the prices in that contract remained constant
throughout the base year and 4 option years, those prices--which
were reflected in the 6-month extension and, thus, the
estimate--were not an accurate reflection of the current cost of
oxygen equipment and services. We disagree. While EHMC is
correct that the prices in the 6‑month extension were similar to
those under the preceding contract, this fact in no way
diminishes their validity for purposes of determining price
reasonableness. Since the prices in the 6-month extension were
negotiated in October 2005, and MCS was actually performing the
work at the negotiated price when the RFP was issued, we see no
reason why the agency could not accept those prices as
representative of the current market price. The protester has
not shown that the agency failed to consider market conditions
or other extenuating circumstances that rendered the negotiated
price an invalid basis for comparison. Moreover, the agency did
not merely rely on the extension prices; rather, as noted above,
it increased the estimate for CLIN 1, the largest segment of the
work under the RFP, 50 percent above the fourth option year
price under MCS’s contract. Regarding CLIN 1, although MCS was
performing at a unit price of $60 (and, as noted, had been
performing at that price during the fourth option year of its
contract), the contracting officer (CO) explains that the 50
percent upward adjustment was based on his discussions with
another contracting official who had contacted other VA medical
centers to obtain prices. CO’s Statement, Sept. 21, 2006, at 2.
The $90 unit price also closely reflected offerors’ prices under
the same CLIN for the 2001-05 contract‑-offerors there proposed
level 5-year pricing (except for MCS’s reduced fourth year
option price) of $90, $93, and $95. Protester’s Comments, Sept.
26, 2006, exh. 1. Thus, while the $90 unit price was similar to
prices from proposals that were submitted in 2000, those
proposals essentially reflected the offerors’ views that prices
would not increase significantly through 2005. Against this
backdrop, given MCS’s willingness, as of January 2006, to
perform CLIN 1 at a substantially lower price, the agency
certainly had ample reason to believe that $90 did not
understate the current market price. The protester also argues
that the estimate was flawed in that it did not provide for
inflation over the life of the contract. However, while the
estimate apparently was based on level pricing ($719,000) for
the base and 4 option years, as already discussed, under the
prior contract each of the offerors proposed level pricing over
the 5 contract years. Id. Furthermore, while the protester
maintains that some significant inflation factor should be
applied to each contract year, we note that the protester itself
only proposed to increase prices in 2 of the 4 option years. The
protester also has failed to provide any evidence establishing
that cost increases for home oxygen services and supplies are,
or should be, expected to occur over the contract term. We
therefore are not persuaded that inflation should have been
factored into the government estimate. (Eagle
Home Medical Corporation, B-298478, October 13, 2006) (pdf)
UMS and AKSM again were the only two firms to submit proposals.
Regarding prices for the YAG laser system, UMS’s proposal
listed, in the appropriate blanks to the right of the item
description, a unit price of $1,325 for the system and a total
price of $15,900 (the price for 12 units) for the base year. In
addition to the blanks next to the item description, the pricing
sheet also contained another blank under the description, in
which offerors were again to fill in the unit price for each
item. Here, UMS did not write $1,325 for the laser system, but
instead wrote [deleted] (emphasis in original), and then added
[deleted] additional lines containing prices for [deleted]
different size fibers (ranging from [deleted] to [deleted]). UMS
repeated this pricing scheme for the YAG laser system for each
of the option years, changing only the total prices to reflect
the different number of units in the option years (25 units for
each year). In contrast, AKSM’s proposal listed a unit price of
$900 for the YAG laser system in both the blank next to the
description and the blank below the description. Regarding
prices for the standby charges, UMS’s proposal listed, in the
appropriate blanks to the right of the item description, a unit
price of $250 for standby charges, and a total price of $1,250
(the price for 5 units) for the base year. In the blank under
the item description, UMS again listed $250, but included the
phrase [deleted] (emphasis in original) after the unit price.
Again, UMS repeated this pricing for each of the option years,
changing only the total prices to reflect the changed number of
units (10 units for each year). In contrast, AKSM’s proposal
listed standby charges of $475 in both blanks. Finally, for the
ESWL, UMS listed a unit price of $875 in the blank next to the
item description and the blank below the item description. AKSM
listed a price of $1,400 in both places. UMS primarily alleges
that VA performed an improper price evaluation. Specifically,
whereas VA based UMS’s total evaluated price on a unit price of
$1,325 for the YAG laser system, UMS alleges that this was not
its lowest possible price; rather, its lowest price was the
price listed under the item description--[deleted] for the least
expensive fiber, for a total unit price of $1,200. Since this
price would have left UMS as the low offeror, it concludes that
the agency’s price evaluation was materially flawed.
The price evaluation here was reasonable. Regarding the laser
system, it was proper for the agency to use $1,325 as the item
price for evaluation purposes, given that $1,325 was the unit
price that UMS provided in the space to the right of the item
description, and that it was the only firm, fixed unit price
offered. In any case, even if UMS were correct that its range
pricing should have been used in the evaluation, $1,200 would
not be the proper evaluated unit price. In this regard, where an
offeror provides a range of prices where a single firm, fixed
price is required, the evaluation must be based on the highest,
not the lowest, price in the range, since this could be the
ultimate cost to the government if award were made to that firm.
See Tri-State Gov’t Servs., Inc., B‑277315.2, Oct. 15, 1997,
97-2 CPD para. 143 at 4-5. The highest unit price in UMS’s
proposed price range was [deleted] ([deleted] for the fiber).
Accordingly, this price, not $1,200, would be the appropriate
price for the agency to use if it were to evaluate UMS’s range
pricing. (United Medical Systems-DE,
Inc., B-298438, September 27, 2006) (pdf)
In our view, the record here lacks any persuasive evidence that
the agency examined the completeness of the offerors’ price
proposals as called for by the RFP. We note that the
solicitation here did not merely use the term “completeness” in
setting out the parameters of the price evaluation, but
explained, in detail, that the agency planned to evaluate
completeness, and identified the kind of back-up pricing data
that offerors needed to produce for the agency’s evaluation; the
agency’s failure to conduct this review was clearly contrary to
the solicitation’s requirements. See OMNIPLEX World Servs.
Corp., B‑291105, Nov. 6, 2002, 2002 CPD para. 199 at 10. (Advanced
Systems Development, Inc., B-298411; B-298411.2, September
19, 2006) (pdf)
Where, as here, an RFP contemplates the award of a fixed-price
contract, an agency may provide for the use of a price realism
analysis for the limited purpose of measuring an offeror’s
understanding of the requirements or to assess the risk inherent
in an offeror’s proposal. Rodgers Travel, Inc., B-291785, Mar.
12, 2003, 2003 CPD para. 60 at 4; Star Mountain, Inc., B-285883,
Oct. 25, 2000, 2000 CPD para. 189 at 2. The nature and extent of
the agency’s price analyses are matters within the sound
exercise of the agency’s discretion, and our review of such an
evaluation is limited to determining whether it was reasonable
and consistent with the provisions of the solicitation. Id.
Among the price analysis techniques that may be used is an
analysis based on previous proposed prices or contract prices.
Federal Acquisition Regulation (FAR) sect. 15.404-1(b)(2). We
agree with the protester that the contract specialist’s
“adjustments” to the fixed prices proposed were problematic. A
price realism analysis, if conducted, may affect the technical
evaluation; it cannot properly lead to adjustment of proposed
fixed prices. See Verestar Gov’t Servs. Group, B‑291854,
B-291854.2, Apr. 3, 2003, 2003 CPD para. 68 at 6 n.3. If the
selection decision had been based on those “adjusted” or
“factored” prices, the procurement might have been fatally
flawed. The tradeoff analysis in the PNM, however, was
explicitly based on the unadjusted proposed prices, and the
source selection decision, as quoted above, explicitly found
that “the advantages of having Todd perform [the work] is worth
the additional financial outlay (regardless of whether that
amount is based upon the original proposed values or adjusted
values).” Accordingly, any flaws in the conduct of the price
realism analysis did not prejudice PECI. Competitive prejudice
is an essential element of a viable protest and where no
prejudice is shown, or is otherwise not evident from the record,
our Office will not sustain a protest, even if a deficiency in
the procurement is found. Orion Int’l Tech., Inc., B-293256,
Feb. 18, 2004, 2004 CPD para. 118 at 3. (Puglia
Engineering of California, Inc., B-297413; B-297413.2;
B-297413.3, January 20, 2006) (pdf)
One example of how the agency’s limited review may have led to
acceptance of a questionable contingency cost was SCA’s
allowance for the possibility that if sodium pools were
encountered during the removal of residual sodium, a strong
sodium/hydrated sodium hydroxide reaction would occur. SCA
listed the “owner” of this risk as SCA and Framatone ANP, a
proposed subcontractor that would be involved in removing
residual sodium. Although SCA rated the probability of this
occurring as very low, that is, 0 to 20 percent, it recognized
that the cost overrun that would result in the event that it
occurred would total between $7,140,000 and $16,660,000, and the
probable schedule impact would be between 7.3 and 18.2 weeks of
delay. Nevertheless, presumably as the anticipated result of its
proposed mitigation approach, SCA allocated no contingency
allowance either in terms of dollars or weeks of delay. SCA
Revised Proposal, fig. C-21, C-23, C-24. That this result may
not fully reflect the likely risks is supported by the testimony
of the FFTF project director (who was not involved in evaluating
SCA’s contingency allowance in this regard, but was the agency’s
leading technical expert on sodium removal at the hearing), who
answered in the affirmative when asked whether he would be
surprised to learn that the risk analysis in this regard
resulted in zero risk (and thus had no effect on the contingency
allowance0. Tr. 919‑20. While it appears that the agency
concluded that SCA’s method for calculating contingency was
sound, it is clear from the limitations acknowledged by the
agency that it was unable to conclude that SCA’s significantly
lower contingency allowance, and the resulting difference in
evaluated cost, reasonably represented the difference between
the costs that actually would be incurred under SCA’s and FRC’s
proposals. The evaluation in this area therefore was
unreasonable. (EPW Closure Services,
LLC; FFTF Restoration Co., LLC, B-294910; B-294910.2;
B-294910.3; B-294910.4; B-294910.5; B-294910.6; B-294910.7,
January 12, 2005) (pdf)
The agency
performed its price analysis by first establishing a “minimum
objective” price, a “target objective” price, and a “maximum
objective” price, for each of the 355 Lot I CLINs and 194 Lot II
CLINs. AR, Tab 13, Pre-Negotiation Briefing Memorandum, at 5-6,
attach. A. The “minimum objective” price equated to the
determined “Fair Market Price less 5 % to allow for negotiation
flexibility.” Id. at 5. The agency’s “target objective” prices
were “based on the previous procurement prices” adjusted by a
set percentage for inflation and a “learning curve adjustment
for quantity,” and the agency’s “maximum objective” prices
equated to the determined fair market price “with 5% added to
allow for unknown market conditions.” Id. The agency then
identified those CLINs in the offerors’ proposals where the
total prices proposed (unit price multiplied by the estimated
quantity) were at least $7,000 less than the agency’s minimum
objective prices, 50 percent or more below the agency’s maximum
objective prices, and/or “out of line” with the other offerors’
proposed prices. AR, Tab 13, Pre-Negotiation Briefing
Memorandum, at 5. The agency provided each offeror with a
pricing matrix identifying those CLINs where the prices proposed
met the above criteria, and, as mentioned previously, requested
that the offeror “verify that these prices are correct for price
realism.” AR, Tab 14, Negotiation Letters to EHC and Grauch
(Sept. 1, 2004). The agency received proposal revisions from the
offerors, and with regard to Grauch, “was satisfied with the
price realism of [its] proposal[].” AR at 13. EHC challenges the
depth of DLA’s price analysis, arguing that “there is no
discussion in any of [the agency’s] final evaluation documents
regarding the cost realism of Grauch’s offer.” Protester’s
Comments at 12. The protester concludes that the agency “did
nothing to investigate Grauch’s significantly lower prices or to
confirm that Grauch could deliver the requested items at these
prices,” and therefore “failed to conduct a proper price realism
analysis.” Protester’s Supplemental Comments at 10. The
protester notes that Grauch’s proposed prices after negotiations
were “still 32% below [the agency’s] Minimum Objective for Lot I
and 35% below [the agency’s] Minimum Objective for Lot II.”[4]
Id. We find from our review of the contemporaneous record that
the agency had concerns with the low prices proposed by the
offerors for certain CLINs in Lots I and II, and that it handled
these concerns in a reasonable manner. That is, the agency’s
price negotiation memorandum shows that the agency was aware and
accurately calculated the number of CLINs on which Grauch’s and
EHC’s proposed prices fell within the agency’s criteria for
requiring verification for price realism purposes, that the
agency brought these CLINs to the offerors’ attention during
negotiations, and was satisfied with the responses it received.
There is no requirement that the agency conduct a “cost realism”
analysis in evaluating proposals for a fixed-price contract as
asserted by the protester, nor is an agency required to
“investigate” in the context of a price realism analysis whether
Grauch can deliver the items for the prices proposed as required
by the resultant contract.[5] See Citywide Managing Servs. of
Port Washington, Inc., supra, at 6. (Electronic
Hardware Corporation, B-295345, January 28, 2005) (pdf)
Although agencies are required to perform some sort of price or
cost analysis on negotiated contracts to ensure that proposed
prices are fair and reasonable, where, as here, the award of a
fixed-price contract is contemplated, a proposal’s price realism
is not ordinarily considered, since a fixed-price contract
places the risk and responsibility for contract costs and
resulting profit or loss on the contractor. However, an agency
may provide in the solicitation for a price realism analysis for
such purposes as measuring an offeror’s understanding of the
solicitation requirements, or to avoid the risk of poor
performance from a contractor who is forced to provide goods or
services at little or no profit. The depth of an agency’s price
realism analysis is a matter within the sound exercise of the
agency’s discretion. Citywide Managing Servs. of Port
Washington, Inc., B-281287.12, B‑281287.13, Nov. 15, 2000, 2001
CPD para. 6 at 4-5. In reviewing protests challenging price
realism evaluations, our focus is whether the agency acted
reasonably and in a way consistent with the terms of the
solicitation. The protester first argues that under the
solicitation its proposal cannot be rejected as unacceptable
because its price was considered unrealistically low. However,
as indicated, the solicitation expressly provided that "[p]roposals
will be evaluated to determine whether offered prices are
realistic,” and specifically informed offerors that the analysis
would include the distinct queries of whether the prices were
realistic “in relation to the work to be performed, reflect a
clear understanding of the requirements, and are consistent with
other portions of the offeror’s proposal.” RFP at 16.
Accordingly, this is not an instance, such as pointed to by the
protester in Possehn Consulting, B-278759, Jan. 9, 1998, 98-1
CPD para. 10, where the rejection of a proposal because its
pricing was found to be unrealistic was determined to be a
matter of responsibility due to the solicitation’s lack of any
evaluation factor or criterion related to price realism. See
also CSE Constr., B-291268.2, Dec. 16, 2002, 2002 CPD para. 207
at 4-5 (where there is no relevant evaluation criterion
pertaining to price realism or understanding, a determination
that an offeror’s price on a fixed-price contract is too low
generally concerns the offeror’s responsibility). In our view,
given the RFP’s specific provision regarding the performance of
a price realism analysis, as well as the remainder of the RFP’s
terms, the agency could reject a proposal that lacked price
realism, or consider a proposal’s lack of price realism in its
source selection. We have found that the risk of poor
performance when a contractor is forced to provide services at
little or no profit under a fixed-price contract is a legitimate
concern that can be considered under a price realism evaluation.
Ameriko, Inc., B‑277068, Aug. 29, 1997, 97-2 CPD para. 76 at 3;
GEC-Maconi Electronic Sys. Corp., B‑276186, B-276186.2, May 21,
1997, 97-2 CPD para. 23 at 5. Here, the agency reasonably found
IOS’s price to be unrealistic, and because of this, determined
that there was a significant risk that IOS’s performance under
the contract may be so unprofitable that the performance of this
contract--which is considered extremely important to DeCA--would
be adversely affected. Under the circumstances, we find the
agency had a reasonable basis to reject IOS’s proposal. (International
Outsourcing Services, B-295959, LLC, May 25, 2005) (pdf)
Agencies must consider cost to the government in evaluating
proposals, 41 U.S.C. sect. 253a(b)(1)(A), (c)(1)(B) (2000), and
while it is up to the agency to decide upon some appropriate and
reasonable method for the evaluation of offerors’ prices, an
agency may not use an evaluation method that produces a
misleading result. See Bristol-Myers Squibb Co., B-294944.2,
Jan. 18, 2005, 2005 CPD para. 16 at 4; AirTrak Travel et al.,
B-292101 et al., June 30, 2003, 2003 CPD para. 117 at 22. The
method chosen must also include some reasonable basis for
evaluating or comparing the relative costs of proposals, so as
to establish whether one offeror’s proposal would be more or
less costly than another’s. Id.; see FAR sect. 15.405(b)(“the
contracting officer’s primary concern is the overall price the
government will actually pay”). For example, in Health Servs.
Int’l, Inc.; Apex Envtl., Inc., B-247433, B-247433.2, June 5,
1992, 92-1 CPD para. 493, the solicitation contemplated the
award of a fixed-price, indefinite-quantity contract and
offerors’ proposals were required to include hourly rates for
six categories of labor. We sustained a protest challenging the
agency’s price evaluation because it was based solely upon
offerors’ average hourly labor rates, without consideration of
the estimated quantities of each labor category the agency
expected to order, and thereby failed to establish whether one
offeror’s proposal was in fact more or less costly than
another’s. Based on our review of the record here, we
conclude that the Forest Service’s price evaluation, including
the determination that Port-A-Pit’s prices were not fair and
reasonable, was fundamentally flawed because it did not reflect
the actual cost to the government of the offerors’ competing
proposals. In performing the evaluation of offerors’ prices, the
contracting officer did not utilize any quantity estimates for
the meals, mileage, and handwashing unit items, but instead
limited her evaluation to offerors’ unit prices. The contracting
officer determined that while Port-A-Pit’s unit prices for meals
and handwashing units were not objectionable, its unit price for
mileage was not fair and reasonable, in comparison to both the
government estimate and the average price of other offerors. AR,
Tab 15, TEB Best Value Analysis Report, at 1, 4-5. Based on the
contracting officer’s determination that Port-A-Pit’s price for
mileage was not fair and reasonable, the Forest Service found
Port-A-Pit ineligible for contract award. Id. at 6; Contracting
Officer’s Statement, July 18, 2005, at 11 (“I made the
determination based on price analysis that [Port-A-Pit’s]
mileage price was not fair and reasonable and could not form the
basis for award”). The record reflects that mileage is by no
means the largest component of cost to the government. Rather,
the parties agree that meals are the primary cost for the
services to be provided under the contract.[10] Protest, June
21, 2005, at 8, exh. 1; AR, Tab 15, TEB Best Value Analysis
Report, at 1. For example, the record indicates that under a
predecessor contract, Port-A-Pit provided a total of [DELETED]
meals and drove a total of [DELETED] miles in response to a fire
in Ash, Arizona.[11] Protest, June 21, 2005, exh. 1, at 1. Using
the unit prices proposed by Port-A-Pit here, meal costs would
have been approximately $39,644, while mileage costs, in
comparison, would have been approximately $17,100. Similarly,
the record indicates that with regard to a fire in Jimtown,
Montana, meal costs to the government would have been
approximately $69,285 while mileage costs would have been
approximately $35,600.[13] In light of the substantial
difference in the relative costs for meals and mileage, the
agency’s price evaluation, to the extent that it considered only
offerors’ unit prices, failed to reflect the likely actual cost
to the government of the offerors’ approaches. (R&G
Food Service, Inc., d/b/a Port-A-Pit Catering, B-296435.4;
B-296435.9, September 15, 2005) (pdf)
In sum, we conclude that, in light of DCAA’s inability to
develop evaluated direct labor rates based on SGT’s cost
proposal and staffing approach, the agency’s experience with
SES’s costs under the incumbent proposal as detailed in the
September 2003 DCAA audit, and in the absence of other data in
SGT’s proposal that would address the agency’s concerns, the
agency’s cost realism analysis was reasonable. The adjustments
to both the SCA-exempt and non-exempt rates and the use of the
September 2003 audited rates as the most recently evaluated
rates were reasonable in light of the information available to
the agency. This aspect of the protest is denied. (SGT,
Inc., B-294722.4, July 28, 2005) (pdf)
We find that GSA's pricing analysis was unreasonable because the
comparison of offerors' "discount rates" did not reflect the
actual proposed prices or cost to the government for these
services. While Maximus's warehouse price may have included
additional services not offered by Liquidity, the fact remains
that the price to the government for Maximus's warehouse space
will be higher than the price for an equivalent amount of
Liquidity warehouse space, and the price evaluation did not
reflect this difference in cost to the government. (In this
regard, the agency did not find that the additional warehouse
services allegedly offered by Maximus would result in
quantifiable savings in costs that the government would
otherwise incur.) Furthermore, we find that the agency's
rationale for reducing Liquidity's price advantage for warehouse
services is unsupported by the contemporaneous record. While the
agency explains that the reduction in discount rate from
[redacted] percent to [redacted] percent was due to differences
in proposal approaches, the contemporaneous record does not
demonstrate that the agency evaluated the asserted differences
in warehousing services. Indeed, the agency's current assertion
that it did so is inconsistent with the remainder of its pricing
analysis, which did not take into account any differences in
offerors' proposal approaches under any of the other service
areas considered in the price evaluation. For example,
Liquidity's price proposal states that many of its warehousing
services are included with its value-added-services pricing, yet
GSA did not make any adjustments to the value-added-services
pricing to take into account this proposal difference, as it did
with warehousing. In fact, we note that the agency asserts, in
response to other protest challenges to the price evaluation,
that differences in proposal approaches were to be evaluated
only under the technical approach factor, and not the price
factor. See , e.g. , Agency Report, July 2, 2004, at 3. We also
find that GSA erred in calculating its discount rate for
transportation services. Although it may have been reasonable to
assume that most of the transportation provided would be short
hauls at less-than-full truckloads, there is no basis for
excluding all of the long distances from consideration, as if no
long haul services would be used. The agency does not claim that
no long haul services would be used, the RFP does not specify
that long hauls would not be required or considered in the
evaluation, and, consistent with the RFP, both offerors proposed
prices for both long and short hauls. On these facts, we find
that the agency must consider in its price evaluation all of the
costs of long haul transportation that it reasonably expects to
use during contract performance, and, moreover, should disclose
to offerors the basis for its evaluation of these costs prior to
proposal submission. (Liquidity
Services, Inc., B-294053, August 18, 2004) (pdf)
This problem with the way the IGSE was developed is significant
because the IGSE was used in what appears to be a mechanical way
in the cost realism evaluation. A reasonably derived estimate of
labor hours and material costs can provide an objective standard
against which the realism of proposed costs can be measured. IT
Facility Servs.-Joint Venture, B-285841, Oct. 17, 2000, 2000 CPD
paragraph 177 at 6-7; Theta Eng'g, Inc., B-271065, B-271065.2,
June 12, 1996, 96-2 CPD paragraph 76 at 6. However, an agency
may not mechanically apply that estimate to determine the most
probable costs associated with proposals, without regard to the
individual proposal's technical approach. The Jonathan Corp.;
Metro Mach. Corp. , B-251698.3, B-251698.4, May 17, 1993, 93-2
CPD paragraph 174 at 11; Kinton, Inc. , B-228260.2, Feb. 5,
1988, 88-1 CPD paragraph 112 at 4. This is so because in some
instances an estimate has limited applicability to a particular
proposal due to, for example, the skill of the labor force or
innovative work methods proposed. In those cases, any rigid
reliance on the government estimate could have the effect of
arbitrarily and unfairly penalizing (or rewarding) one firm and
depriving the government of the benefit available from the
different approaches of the various offerors. Accordingly, in
order to undertake a proper cost realism evaluation, the agency
must independently analyze the realism of an offeror's proposed
costs based upon its particular approach, personnel, and other
circumstances. The Jonathan Corp.; Metro Mach. Corp. , supra .
Here, the record does not indicate that the agency engaged in an
absolutely rigid application of the IGSE to the offerors'
proposals. There do appear to be instances where the agency
accepted proposed staffing for a particular function or labor
category that was less than that reflected in the IGSE, and in
other instances, the agency made adjustments to an offeror's
proposed staffing that put the probable staffing associated with
the proposal at a level between that set forth in the proposal
and that provided by the agency in its IGSE. Nevertheless, the
record also reflects that in the vast majority of instances
where an offeror proposed a staffing level that differed from
the IGSE, the staffing level was adjusted during the cost
evaluation to the IGSE staffing level, with the primary
documented reason by the agency being that the proposal did not
provide "sufficient rationale" for the proposed staffing, with
little further elaboration. See AR, Tab 43, Honeywell Cost
Realism Rationale; at 2; Tab 47, Wyle Cost Realism Rationale, at
2; Tab 49, Sverdrup Cost Realism Rationale, at 2. As the
protesters point out, the consistency of the agency's approach
in this regard is readily apparent when the offerors' varying
proposed staffing levels are compared to their staffing levels
as adjusted by the agency and the IGSE. That is, although the
agency found "that there was a wide range of disparate
approaches from the offerors," with the five offerors proposing
staffing levels that varied considerably ( i.e. , 198, 241, 248,
260, and 287 FTEs), the SEB adjusted the staffing levels
proposed by all five offerors to within 4 FTEs of the IGSE of
293. Agency's Post-Hearing Comments at 10; exh. B, Cost Proposal
Evaluation Results (July 22, 2003). This, along with the sparse
evaluation documentation, suggests that the IGSE was used in a
mechanical way in the cost realism evaluation, notwithstanding
the encouragement in the RFP for proposing innovative
approaches. That the agency used the IGSE in the cost realism
evaluation in a mechanical way is supported by other evidence in
the record. For example, before this issue became the gravamen
of the protests, the agency stated in its initial report on the
protests that "[u]niformly, NASA base lined [the offerors'] FTEs
against the government staffing estimate." AR at 22, 25.
Moreover, given the testimony of the SEB member that the
Marshall estimate was essentially inflexible and any proposed
staffing plan that did not comport precisely with the Marshall
estimate would be "[c]ompletely unacceptable," the fact that
variances from the estimate were not tolerated was
understandable. [9] Tr. at 78, 80-81, 100, 107. Of most
significance in showing that the IGSE was used in a mechanical
way is the fact that Honeywell's proposed staffing was
characterized as "appropriate" during the evaluation of its
proposal under the technical performance subfactor, but was then
adjusted upwards by 43 FTEs to within 2 FTEs of the IGSE during
the cost realism evaluation. In sum, we find the agency's cost
realism evaluation unreasonable. (Honeywell
Technology Solutions, Inc.; Wyle Laboratories, Inc.,
B-292354; B-292388, September 2, 2003) (pdf)
The realism analysis here was unobjectionable. The Army
evaluated Sunny Point's proposal and determined that the
proposed labor mix and hours were consistent with its technical
proposal and acceptable to perform the contract. SSD at 3. The
Army also reviewed Sunny Point's price proposal and found that
it was complete and adequate, Price Analysis Worksheet at 1, and
also determined that it complied with the Service Contract Act
wage determination with respect to both rates and fringe
benefits. Price Analysis Report at 1. The Army noted that Sunny
Point's price was lower than the government estimate, but
attributed this to the fact that Sunny Point proposed a labor
mix and staffing level different--but acceptable to
perform--than that on which the government estimate had been
based. SSD at 3. The agency also concluded that the government
estimate was overstated. Id. Given this analysis, we have no
basis to question the Army's realism evaluation. (Satellite
Services, Inc., B-295866; B-295866.2, April 20, 2005) (pdf)
In contrast, where, as here, with regard to a BPA contemplating
fixed-price or fixedrate task orders to be issued against the
vendors' GSA FSS contracts, the "realism" of vendor's proposed
pricing is not ordinarily considered because the fixed-price
contracting vehicle places the risk and responsibility for
contract costs and ensuing profit or loss on the contractor. See
Camber Corp. , B-293930; B293930.2, July 7, 2004, 2004 CPD 144
at4; OMNIPLEX World Servs. Corp. ; B291105, Nov. 6, 2002, 2002
CPD 199 at 9. However, because there is a risk of poor
performance in certain circumstances, such as where a contractor
fails to obtain and keep qualified personnel, an agency may, in
its discretion, provide for a price realism analysis in a
solicitation that contemplates the issuance of a BPA against the
vendors' GSA FSS contracts. OMNIPLEX World Servs. Corp. , supra
. Here, the methodology used by the agency in evaluating
quotations under the pricing structure criterion was consistent
with that provided in part 15 of the FAR for the performance of
price realism analyses--the comparison of proposed prices, in
the form of loaded labor rates, with prior contract prices for
the same or similar services and with an independent government
cost estimate. See Acepex Mgmt. Corp. , supra , at8; FAR
15.404-1(b). As noted, the agency's conclusion that S3's
quotation warranted a "moderate risk" rating under the pricing
structure criterion is not only consistent with the RFP
evaluation scheme but is reasonably supported by the record. As
indicated, the agency's evaluation of quotations under the
pricing structure criterion was relatively detailed, and
included an analysis of the labor rate quoted for each of the
labor categories set forth in S3's quotation. S3's quoted rates
in some instances were substantially lower, and overall were
slightly lower, than the agency's calculated historical rates
for the same positions, and as such, we believe that the agency
reasonably determined that there was "some doubt that [S3's]
pricing structure will support the [agency's] requirements with
highly qualified personnel." AR, Tab I, Source Selection Report,
at16. S3 has not showed that the loaded rates reflected in the
historical averages were erroneous, unreasonable or unrealistic
or that the comparison of S3's loaded rates to the historical
averages was flawed. (Systems,
Studies, and Simulation, Inc., B-295579, March 28, 2005) (pdf)
The
evaluated prices as reported to the SSA improperly failed to
reflect a common number of sites to be serviced. Treasury
reports that the solicitation attachment listing 1,042 Treasury
sites for which service was required included a number of
errors. Second Agency Report at20. As a result, and as
recognized in Treasury's price evaluation reports, offerors'
MDOs were based on different total numbers of sites to be
served, as well as different numbers of high bandwidth Category
1, lesser bandwidth Category 2, and least bandwidth Category 3
sites, as follows:
| |
Category 1
|
Category 2
|
Category 3
|
Total |
|
[DELETED] |
70 |
63 |
862 |
995 |
|
[DELETED] |
73 |
66 |
916 |
1,055 |
|
[DELETED] |
63 |
76 |
857 |
996 |
|
[DELETED] |
58 |
83 |
855 |
996 |
|
[DELETED] |
61 |
77 |
828 |
966 |
|
[DELETED] |
54 |
59 |
850 |
963 |
|
[DELETED] |
102 |
117 |
618 |
837 |
However, notwithstanding the
significant differences with respect to the total number of
sites and numbers of sites within each category in the offerors'
MDOs, Treasury did not adjust offerors' proposed prices so as to
ensure that the evaluated prices reflected a common number of
sites to be serviced. For example, Treasury did not adjust [DELETED]'s
evaluated price upward notwithstanding the fact that, by
Treasury's own calculation, [DELETED] had excluded from its MDO
pricing [DELETED] sites for which service was required. Based
upon the assumption that the omitted sites were a representative
sample of the total universe of sites, and because the [DELETED]
sites represented approximately [DELETED] percent of the 1,042
sites listed in the agency attachment, Treasury reports that it
determined that the [DELETED] omitted sites warranted an upward
adjustment to [DELETED]'s proposed price of between [DELETED] (a
[DELETED] percent increase in [DELETED]'s proposed price) and
[DELETED]. Second Agency Report at 20, 4243; Tr. at 657-59,
777-79. However, although the SSA had specifically questioned
the TCE Program Manager/Technical Chairman as to whether [DELETED]'s
price was complete, the SSA was not advised of this required
upward evaluated price adjustment, with the result that the SSA
erroneously concluded that no changes in [DELETED]'s proposal
were required. Tr. at 782, 1253, 1349. In our view, Treasury's
failure to base the evaluated prices for all offerors on a
common number of sites to be serviced was unreasonable. (Northrop
Grumman Information Technology, Inc.; Broadwing, B-295526;
B-295526.2; B-295526.3; B-295526.4; B-295526.5; B-295526.6;,
March 16, 2005) (pdf)
The record indicates that for its Spanish linguist prices,
McNeil has not followed the RFP's proposal instructions by
accounting in its proposed price for "any increases," as was
contemplated by the RFP. Rather, it appears that its Spanish
linguist prices were premised upon receiving equitable
adjustments to its contract price if an SCA wage determination
were issued that increased its salary or benefit obligations for
Spanish linguists. That is, while it appears that the proposals
that followed the proposal instructions may have accounted for
possible SCA increases in their escalated prices for the option
years, it appears that McNeil did not do so for the Spanish
linguists, but retained the right to obtain an increase in its
contract price in such circumstances. Therefore, it appears that
the proposal prices may not have been compared on an equal basis
to account for the real cost to the government of accepting a
particular proposal for award because some proposals apparently
took into account possible SCA increases, while, for the Spanish
linguist line items, McNeil's did not. An agency, at a minimum,
is required to evaluate offerors on an equal basis and in a
manner such that the total cost to the government for the
required services can be meaningfully assessed. See Symplicity
Corp. B-291902, Apr. 29, 2003, 2003 CPD 89 at 7; Lockheed
Aeronautical Sys. Co. , B-252235.2, Aug. 4, 1993, 93-2 CPD 80 at
7 ("apples and oranges" cost evaluation is "inherently
improper"). According to the protester, if McNeil had included
escalation in its Spanish linguist prices at the same escalation
rates it used for its other prices, its total evaluated price
would have been almost1.5 million higher. Given the possible
impact of this discrepancy in McNeil's proposal on the
competition, this matter should be resolved with McNeil during
discussions. (SOS Interpreting, LTD.,
B-293026; B-293026.2; B-293026.3, January 20, 2004) (pdf)
The record here supports the protester's premise that some
portion of the VA's ARB use will be at dosing levels different
from the standard recommended dose for treating diabetic
nephropathy. That, in turn, supports the contention that the
possible use of different dosing levels could have an adverse
effect on the pricing methodology's usefulness for predicting
actual costs. Nonetheless, based on our understanding of the
ways in which different dosing levels (and different tablet
strengths) could be used, we have no reason to believe that this
influence renders unreasonable the RFP's pricing approach.
SmithKline Beecham , supra , at 5. Our conclusion is premised on
the following possible reasons for using the ARB selected with
this procurement at dosages different from those recommended for
the treatment of diabetic nephropathy: (1) the VA doctor is
prescribing an ARB for the treatment of simple hypertension and
is doing so either improperly (in disregard of the VA's
guidance), or is doing so properly (after trying other classes
of drugs for the treatment of simple hypertension and finding
them ineffective or not well-tolerated); or (2) the VA doctor
has just started prescribing an ARB regimen for the treatment of
diabetic nephropathy and the patient is still "ramping up" to
the recommended optimal dosing levels, or the patient is proving
unable to achieve the target dosage recommended for the optimal
treatment of diabetic nephropathy. (Bristol-Myers
Squibb Company, B-294944.2, January 18, 2005) (pdf)
Here, the contracting officer compared KMRs price to other
prices received in response to the solicitation and determined
that KMRs price was less than 4 percent below the second lowest
technically acceptable offer. Contracting Officers Statement, at
3; AR, Tab 11, Price Competition Memorandum, attach. 2, Revised
Comparison of Pricing. The record also reflects that the third
lowest technically acceptable offer was less than 13 percent
higher than KMRs proposal. AR, Tab 11, Price Competition
Memorandum, attach. 2, Revised Comparison of Pricing.
Additionally, the contracting officer noted that KMRs price was
3 percent more than the government estimate, which was based on
the costs of the incumbent contract. AR, Tab 11, Price
Competition Memorandum, at 3. The manner and depth of an agencys
price analysis is a matter within the sound exercise of the
agencys discretion, and we will not disturb such an analysis
unless it lacks a reasonable basis. Gentex Corp.--Western
Operations , B-291793 et al., Mar.25, 2003, 2003 CPD 66 at 21.
We conclude that reliance on the closeness in price between KMRs
proposal price and two other offers with passing mission
capability ratings provided a reasonable basis for the Air Force
to determine that KMRs price is realistic. (Mindleaf
Technologies, Inc., B-294242, B-294242.2, August 24, 2004) (pdf)
First, price realism is not required to be considered in the
evaluation of proposals for the award of a fixed-price contract
unless the solicitation provides for a price realism analysis to
assess an offeror’s understanding of the requirements or the
risk of poor performance inherent in a proposal. AllWorld
Language Consultants, Inc., B-291409, B-291409.2, Dec. 16, 2002,
2003 CPD ¶ 13 at 2. Here, as the solicitation did not require a
price realism analysis, the agency was not required to perform
one. Dismas’s argument regarding price reasonableness is based
on the agency’s alleged failure to use Bannum’s revised prices
in a comparison with the government estimate. According to
Dismas, BOP used prices of $73.00 for Bannum’s base period and
$64.00 for the two option periods, instead of Bannum’s revised
prices of $72.50 for the base period and $63.00 for the option
periods. This argument is without merit. The purpose of a price
reasonableness evaluation, is to determine whether offered
prices are higher, not lower, than warranted. Efficiency Mgmt. &
Eng’g Co., Norcor Techs. Corp., B‑292676, B-292676.2, Oct. 31,
2003, 2003 CPD ¶ __. Since the agency found that prices higher
than Bannum's revised prices were reasonable, using Bannum’s
lower revised prices in the comparison obviously would not
affect the price reasonableness determination. (Dismas
Charities, Inc., B-289575.2; B-289575.3, February 20, 2004)
(pdf)
In any event, assuming the validity of BRC’s argument that the
appropriate reference should have been wages paid in the
Huntsville area, we point out, as described above, that BRC’s
proposed price was substantially lower (by approximately 25 to
27 percent) than the prices proposed by the three other
Huntsville-based offerors, including FRC. We conclude, based on
this record, that BRC has not provided any meaningful basis for
our Office to question the reasonableness of the agency’s
conclusion that BRC’s price was unreasonably low not only with
reference to the government estimate, but also in comparison to
the prices proposed by the other offerors, including competitors
from the same geographic area as BRC which presumably would be
recruiting from the same local pool of information technology
professionals. (Bevilacqua Research
Corporation, B-293051, January 12, 2004) (pdf)
We agree with BHI that the agency improperly failed to evaluate
proposals in accordance with the established evaluation scheme,
and that BHI was competitively prejudiced by the agency’s
actions. Specifically, DOE failed to adequately take into
consideration the comparative realism of the proposals, as
indicated by the degree to which their MPCs deviated from their
proposed target costs. Based on the RFP and the
information provided to BHI and WCC during discussions, we
conclude that offerors were on notice that, as BHI asserts, the
evaluation scheme in particular (as well as the agency’s use of
a CPIF contract more generally) called for the agency to
evaluate realistic proposals--as measured by the amount by which
the MPC deviated from the target cost--more favorably than
unrealistic proposals in determining which proposal represented
the best value to the government. In effect, the agency was
obliged in making its source selection to consider, among other
things, which proposal’s target cost was more realistic. We also
conclude that BHI heeded the RFP and the agency’s instructions,
and submitted (as the agency found) a very realistic target
cost, [deleted]. In confining its cost realism analysis to the
calculation of MPCs and in otherwise discounting the difference
in realism between the two proposals, the agency failed to
adhere to the announced evaluation scheme. (Bechtel
Hanford, Inc., B-292288; B-292288.2; B-292288.3, August 13,
2003) (pdf)
EMEC’s assertion that Cirrus’s rates were too low provides no
basis to question the reasonableness of its proposed prices. The
purpose of a price reasonableness review is to determine whether
the prices offered are higher--as opposed to lower--than
warranted. Rodgers Travel, Inc., B-291785, Mar. 12, 2003, 2003
CPD ¶ 60 at 3 n.1. Thus, we find nothing objectionable in the
price evaluation.[4] As for whether Cirrus’s price otherwise was
too low, the RFP advised offerors that the Service Contract Act
was applicable and, because the specified labor categories were
not defined in the wage determination, set a minimum rate. The
price evaluators analyzed the individual line item labor rates,
and determined that all were within a reasonable range of those
proposed by the other offerors. Agency Report (AR), Tab 11. In
this regard, while EMEC’s labor rates were higher than those
proposed by Cirrus, Cirrus’s rates were comparable and well
exceeded the minimum set forth in the RFP. (Efficiency
Management & Engineering Company, B-292676; B-292676.2,
October 31, 2003) (pdf)
The price realism evaluation here was reasonable. The agency
evaluated each line item and the total price for each proposal
and compared them with its independent estimate and with other
offerors' prices. The agency noted STL's proposal of a $0.00
rate for the two personnel positions and specifically raised the
matter in discussions. In response, STL's revised proposal
explained:
STL's decision not to charge the government directly or
indirectly in the base year or in any of the option years for
CLINs 1014 and 1015 is a business decision and it is based on a
realistic understanding of the work to be performed under this
contract. STL is not [deleted] to obtain this particular
contract or any future contract. STL Proposal at TCP 1. STL also
included the requisite total compensation plan, as well as
salary and benefit packages for the proposed labor categories.
The contracting officer reviewed this information and concluded
that, overall, the proposed compensation was fair and in line
with market prices. AR, Tab 34, at 5. Proposal of below-cost
rates--including a rate of $0.00--for certain labor categories,
is permissible in a fixed-rate environment, even where, as here,
the RFP requires offerors to propose fully-loaded rates. GTSI
Corp., B‑286979, Mar. 22, 2001, 2001 CPD ¶ 55 at 5; ORI, Inc.,
B‑215775, Mar. 4, 1985, 85‑1 CPD ¶ 266 at 4. Having reviewed
STL's labor pricing and having ensured that STL understood the
ramifications of its pricing strategy, the agency fulfilled its
responsibility to conduct a reasonable analysis of the
challenged prices. (PharmChem, Inc.,
B-291725.3; B-291725.4; B-291725.5, July 22, 2003) (pdf)
Since the ultimate cost to the government depends upon whether
the contractor meets its target cost, the reliability of the
price evaluation for purposes of comparing proposals depends to
a large extent on the realism of that target cost; it follows
that use of this contract type requires a realistic target cost
estimate. See generally Universal Techs., Inc., B‑241157, Jan.
18, 1991, 91-1 CPD ¶ 63 at 10. The RFPs here seem to have
recognized the importance of price realism; as quoted above, the
RFPs contained several provisions indicating that realism would
be considered in the evaluation. In our view, the agency could
not meaningfully evaluate the realism of the proposed pricing
without determining whether, and to what extent, offerors were
likely to meet their target costs; this determination was
particularly important here in light of the [DELETED] reductions
in SMM's FPR. (Eurest
Support Services, B-285813.3; B-285813.4; B-285813.5;
B-285882.4; B‑285882.5; B-285882.7, July 3, 2001) (pdf)
Under the circumstances, in the absence of a reasonable basis to
determine that SRS’s proposed use of uncompensated overtime was
unacceptable or unreasonable, or question whether the agency
would in fact receive the savings attributable to SRS’s proposed
use of uncompensated overtime, the agency, in its cost realism
analysis, was required to accept SRS’s proposed labor rates
based on its use of uncompensated overtime.8 See General
Research Corp., supra at 7-9. There was no reasonable basis for
the agency to equate the cost proposals of SRS and Sparta in
terms of uncompensated overtime, and to normalize the proposed
costs in the cost realism analysis by eliminating from SRS’s
most probable cost the value of proposed uncompensated overtime
from SRS’s proposed labor costs. Id. at 9. The record shows that
if this adjustment had not been made to SRS’s proposed costs,
the evaluated cost difference between the proposals would have
been $[DELETED] rather than $[DELETED]. Thus, the source
selection decision was unreasonable. We sustain SRS’s protest on
this basis. (SRS Technologies,
B-291618.2; B-291618.3, February 24, 2003)
(pdf)
Finally, we disagree with Nutech
that its incumbent contract price requires a determination that
its proposed price is per se reasonable. Indeed,
FAR § 15.404-1 identifies that previous contract prices “may” be
considered “if both the validity of the comparison and the
reasonableness of the previous price(s) can be established.”
Here, as NIH explains, price competition did not occur under the
prior procurement and, as noted in the linen study, NIH may have
been paying “exorbitant” costs for laundry services as a
result. Based upon this information, we think NIH had
sufficient reason to question the reasonableness of Nutech's
incumbent contract price. (Nutech
Laundry & Textiles, Inc., B-291739, February 10, 2003)
(txt
version)
Where, as here, a solicitation contemplates the award of a
fixed-price, rather than a cost-reimbursement, contract, the
agency is not required to conduct a price realism analysis,
because a fixed-price contract places the risk and
responsibility for loss on the contractor rather than the
government. PHP Healthcare Corp.; Sisters of Charity of the
Incarnate Word, B-251799 et al., May 4, 1993, 93-1 CPD
¶ 366 at 5. An agency may provide for a price realism analysis
for the limited purpose of measuring offerors' understanding of
the requirements or to assess the risk inherent in an offeror's
proposal, but there is no requirement that it do so. Id. Here,
the solicitation did not provide that the agency would conduct a
price realism analysis, or otherwise assess technical
understanding with reference to the offered prices.
Consequently, since the agency determined that Worldwide is
responsible and, thus, that it can perform at its offered price,
Worldwide's low price does not provide a basis for questioning
the award. WorldTravelService, B-284155.3, Mar. 26, 2001,
2001 CPD
¶ 68 at 3. (AllWorld
Language Consultants, Inc., B-291409; B-291409.2;, December
16, 2002) (txt
version) (FAR 8.404)
The
purpose of a price reasonableness evaluation in a fixed-price
contract setting is to determine whether prices are too high, as
opposed to too low (the contractor, not the government, bears
the risk that a low price will not be adequate to meet the costs
of performance). USATREX Int'l, Inc., B-275592, B-275592.2, Mar.
6, 1997, 98-1 CPD
¶ 99 at 7. The record
shows that the contracting officer determined that the awardee's
price was reasonable--that is, not too high--based on adequate
competition, AR, exh. 10, at 2, and Sterling's protest that the
awardee's price is too low provides no reason to question this
conclusion. As noted, the RFP did not require technical
proposals detailing a firm's proposed staffing or approach, and
did not provide for an evaluation of proposals on any basis
other than past performance and price. It follows that alleged
understaffing by the awardee, even if demonstrated to be the
case (in fact, we find nothing supporting the allegation), was
not a basis for rejecting or downgrading the awardee's proposal. (Sterling
Services, Inc., B-291625; B-291626, January 14, 2003)
(pdf) (txt
version)
We find that the Army appropriately used the IGE and its past
experience as tools in assessing the amount of additional
staffing that Pueblo Environmental would require for contract
performance. An agency may reasonably use an IGE or its past
experience in assessing the realism of an offeror's approach,
and we will not sustain a protest of an agency's staffing
estimate where, as here, the protester does not show that the
agency's estimates are unreasonable. See, e.g., IT Facility
Servs.-Joint Venture, B-285841, Oct. 17, 2000, 2000 CPD ¶ 177 at
6-9; National Steel and Shipbuilding Co., B-281142, B-281142.2,
Jan. 4, 1999, 99-2 CPD ¶ 95 at 12-13. (Pueblo
Environmental Solution, LLC, B-291487; B-291487.2, December
16, 2002) (pdf) (txt
version)
In sum, the current record shows that the agency (1) failed to
quantify the potential cost growth associated with DynCorp's low
proposed rates of compensation during its cost realism
evaluation; (2) failed to assess the non-cost considerations
associated with DynCorp's low rates of compensation; and (3)
failed to seek an explanation for why DynCorp was required under
its current contract to [deleted] its initial rates of
compensation--even though those initial rates were the same as
the rates currently being proposed. Under these circumstances,
we find this aspect of the agency's evaluation unreasonable.
(ITT
Federal Services International Corporation, B-289863.4;
B-289863.6; B-289863.7; B-289863.8, December 16, 2002) (pdf)
Here,
the agency had before it two technical proposals that received
virtually identical technical evaluations. [Deleted.] In view of
these evaluations, where BOA's claimed cost savings could be
expected to be, and were, in fact, dispositive in the award
determination, and BOA's proposed savings were justified, in
part, by [deleted], it was particularly important that the
agency perform and document a meaningful realism assessment
regarding the proposed savings. The record before our Office
does not establish that the agency had a reasonable basis to
accept BOA's proposed staffing costs as realistic. The
agency clearly recognized that BOA needed to provide more
support for its proposed staff reductions than it initially did;
as discussed above, the agency repeatedly asked BOA to provide
additional, detailed explanation regarding the bases for its
proposed reductions. The agency did not, however, satisfy the
requirement for a meaningful cost realism analysis simply by
asking, repeatedly, for such support. The fact is that,
despite the agency's repeated requests, BOA failed to provide
the information requested. While BOA did provide a [deleted] of
its proposed staffing reductions, it failed to provide any link
between the majority of these reductions and any particular
aspect of its technical approach. Rather, as the protester
accurately points out, BOA's proposal revisions, including its
FPR, contain, primarily, vague and cursory explanations for its
proposal to dramatically eliminate staff. (National
City Bank of Indiana, B-287608.3, August 7, 2002) (pdf)
First, as noted by the protester,
the agency, in the revised source selection statement determined
that the cost of Carr's proposal was actually lower than M&S
Farms' lower-priced proposal by adding to the offerors' proposed
prices the estimated costs of shipping animals between the
proposed facilities and individual adoption sites (including
return shipping costs for unadopted animals). Agency Report at
19-20; Tab 30, Source Selection Statement Addendum, at 2-3.
However, the contracting officer admits that the RFP does not
contain a requirement for delivery of animals to any site.
Contracting Officer's Statement at 11. Moreover, the RFP does
not indicate in any way that the cost of such deliveries would
be considered in the price evaluation, or otherwise indicate
that price would be evaluated based on location of a proposed
facility. It is improper for an agency to evaluate price based
on an evaluation scheme not set forth in the RFP. See P.G. Elecs.,
Ltd., B-261883, Nov. 1, 1995, 95-2 CPD P: 202 at 5; Department
of the Air Force et al., B 253278.3 et al., Apr. 7, 1994, 94-1
CPD P: 247 at 13; Environmental Techs. Group, Inc., B-235623,
Aug. 31, 1989, 89-2 CPD P: 202 at 4. Also, as pointed out
by the protester, the agency failed to consider costs to
government for line items for which the offerors actually
proposed unit prices in their proposals. Specifically, the price
schedule at line item 0001H (and corresponding line items for
the option years) required offerors to propose a unit price per
day for providing additional labor at adoption events.[12]
Although the RFP price schedule only provided space to insert a
proposed unit price on the item said to be supplied on an
"as required" basis, and did not state an estimated
quantity or provide a space for total proposed price per
contract year for that line item, the RFP nevertheless elsewhere
identified the level of work that the agency anticipated--the
SOW stated that approximately one adoption event would be held
each month, and that each event would require the contractor to
keep its facility open to the public and provide full staffing
necessary to facilitate the adoption event for 9 hours a day for
3 consecutive days. RFP § C.8(a), (c). The total prices
evaluated by the agency, which the SSA relied upon in the source
selection decision, did not include proposed prices for this
item. However, since an estimate of this item was identified in
the SOW, there is a reasonable basis to determine the associated
total cost that the agency will incur under each proposal for
this item. Thus, we think the terms of the RFP entitled the
offerors to assume that the proposed prices for providing labor
at adoption events would be considered in determining total
evaluated price. See Aurora Assocs., Inc., B-215565, Apr. 26,
1985, 85-1 CPD P: 470 at 3. (M&S
Farms, Inc., B-290599, September 5, 2002) (pdf)
We find reasonable the Army's
evaluation of the protester's quote. Faced with a quote that was
not based upon the solicitation's estimated labor hours, the
agency properly calculated the protester's net quote price by
multiplying the protester's fixed unit prices (that is, labor
hour rates) against RFQ estimates. In the context of this
solicitation, allowing one vendor to use lower labor hour
estimates than that required for, and relied upon by, the other
vendors would have resulted in an unfair and unequal
competition. See Ross Aviation, Inc., B-219658, Dec. 11, 1985,
85-2 CPD P: 648 at 4. (Planned
Systems International, Inc., B-290626, September 4,
2002) (pdf)
The RFP included a Department of
Labor (DOL) wage determination, which required a minimum
employer contribution of $2.56 per hour for fringe benefits.
[Deleted]. Since comparison to a DOL wage determination is a
reasonable method of assessing the realism of an offeror's labor
rates, Advanced Communication Sys., Inc., supra, at 8 n.9, we
see no reason to object to the agency's conclusion that
Bionetics' proposed fringe benefit rate, [deleted], was
realistic. The fact that Wyle, the incumbent contractor,
proposed a higher fringe benefit rate than Bionetics provides no
basis to find that Bionetics' proposed rates are unrealistic.
See Calspan Corp., B-255268, Feb. 22, 1994, 94-1 CPD para. 136
at 8, recon. denied, B-255268.2, July 5, 1994, 94-2 CPD para. 6.
Accordingly, we deny the protester's argument that Bionetics'
evaluated cost should have been adjusted upwards by [deleted] to
account for the lower fringe benefit rates that it
proposed. (Wyle
Laboratories, Inc., B-288892; B-288892.2, December 19, 2001)
Moreover, simply comparing various cost elements in an independent government
estimate to offerors' cost elements for the same items does not suffice as a
sufficient analysis of cost realism where the agency has not considered the
offerors' individual technical approaches or determined whether the offeror's
proposals are consistent with the technical and cost parameters that were
reflected in the government estimate. See Tidewater Constr.
Corp., supra, at 5. The record here is devoid of any evidence
that NIAID made any attempt to adjust offerors' proposed cost or to develop most
probable costs estimates based on the offerors' technical approaches. Nor
is there any reason evident from the record why the probable costs for the two
offerors' ODC cost element should materially differ, which suggests that, had
NIAID made an appropriate cost-realism adjustment, Priority One's proposal would
have displaced SoBran's as the lowest cost proposal. In any event, because
the record shows that NIAID did not perform a reasonable cost-realism analysis,
the conclusion that SoBran's proposal was the best value lacks a reasonable
basis, and we sustain the protest on this basis. See The Futures
Group Int'l, B‑281274.2, Mar. 3, 1999, 2000 CPD ¶ 147 at 8.
(Priority One Services, Inc. B-288836; B-288836.2,
December 17, 2001)
Here, the RFP did not provide that
the agency would conduct a realism analysis of the proposals, or
otherwise assess technical understanding with reference to the
offered prices. [1] Rather, the RFP provided only for
multiplying the fixed unit prices by the estimated (historical)
volume of tickets--an analysis designed to assess whether offers
were unbalanced--and for a price reasonableness determination
for the value-added services. RFP sect.sect. M.3, M.4. Under
these circumstances, the agency was not required to evaluate
Omega's price against the technical requirements. (WorldTravelService,
B-284155.3, March 26, 2001)
Agency unreasonably discounted
Defense Contract Audit Agency audit finding, based on the
awardee's actual contract performance, that the awardee's
proposed uncapped indirect rates were considerably understated
for the first 2 years of the 5-year contract and found that the
awardee's proposed rates should be judged only on the basis of
the awardee's knowledge when it submitted its proposal; a cost
realism analysis, even on reevaluation, should consider all
information reasonably available as of the time of the
evaluation. (The
Futures Group International, B-281274.5; B-281274.6;
B-281274.7, March 10, 2000)
Protester's challenge to the price
evaluation scheme included in a solicitation for prescription
drugs that anticipates evaluation of a per-dose price based on
the only use for which all three of the competing drugs are
approved by the Food and Drug Administration is denied, even
though the evaluation does not consider certain uses of the
solicited drugs that will have a different cost profile, where
the per-dose price requested provides a common basis for
evaluating prices, the agency has no basis for providing
estimates for the other uses of these drugs, and the protester
has not established that the solicitation's approach will
produce a materially misleading result. (SmithKline
Beecham Corporation, B-283939, January 27, 2000)
Although price realism is not
ordinarily considered in the evaluation of proposals for the
award of a fixed-price contract, an agency may provide, as here,
for the use of a price realism analysis in a solicitation for
the award of a fixed-price contract for the purpose of assessing
the risk inherent in an offeror's proposal. PHP Healthcare
Corp., B-251933, May 13, 1993, 93-1 CPD para. 381 at 5. (Sabreliner
Corporation, B-284240.2; B-284240.6, March 22, 2000)
Where, as here, the award of a
fixed-price contract is contemplated, a proposal's price realism
is not ordinarily considered, since a fixed-price contract
places the risk and responsibility for contract costs and
resulting profit or loss on the contractor. OMV Med., Inc.;
Saratoga Med. Ctr., Inc., B-281387 et al., Feb. 3, 1999, 99-1
CPD para. 52 at 5. However, an agency may provide for price
realism analysis in the solicitation of fixed-price proposals
for such purposes as measuring an offeror's understanding of the
solicitation requirements, The Cube Corp., B-277353, Oct. 2,
1997, 97-2 CPD para. 92 at 4, or to avoid the risk of poor
performance from a contractor who is forced to provide services
at little or no profit. Ameriko, Inc., B-277068, Aug. 29, 1997,
97-2 CPD para. 76 at 3. (Integrity
Management Services, Inc., B-283094.2, May 3, 2000)
Because the agency's analysis
was based on the mistaken assumption that the cap was above the
proposed rate, there was no reasonable basis for the agency's
cost realism concern, and the resulting adjustment to CHM's
proposed cost was unjustified. The record does not demonstrate
that the agency considered CHM's costs to be unrealistic based
on any independent review of the reasonableness of the proposed
rates themselves, or that its conclusions were substantiated
through market surveys or historical cost data from similar
contracts. (Future-Tec
Management Systems, Inc.; Computer & Hi-Tech,
B-283793.5; B-283793.6, March 20, 2000)
Agency's
"normalization" of offerors' prices was not reasonable
where it double counted the cost difference associated with the
use of new rather than upgraded existing items by both deducting
the price of new items from the total price of the offeror
proposing them and adding the price of replacement items to the
price of the offeror proposing to upgrade existing ones. (Marquette
Medical Systems, Inc., B-277827.5; B-277827.7, April 29,
1999)
Evaluation of awardee's proposal
for cost-reimbursement contract was unreasonable where awardee's
cost proposal was based on use of personnel in labor category
with wage determination labor rate substantially lower than that
of labor category required to perform tasks set out in
solicitation's performance work statement. Protest is
sustained where agency did not assess the realism of the
awardee's proposed overhead rate, which was significantly below
its most recent Defense Contract Audit Agency (DCAA) approved
rate. (E.
L. Hamm & Associates, Inc., B-280766.3, April 12, 1999) |