When an agency evaluates a proposal for the award of a
cost-reimbursement contract, an offeror’s proposed estimated
costs are not dispositive because, regardless of the costs
proposed, the government is bound to pay the contractor its
actual and allowable costs. Federal Acquisition Regulation (FAR)
sections 15.305(a)(1); 15.404-1(d); Tidewater Constr. Corp.,
B-278360, Jan. 20, 1998, 98-1 CPD para. 103 at 4. Consequently,
the agency must perform a cost realism analysis to determine the
extent to which an offeror’s proposed costs are realistic for
the work to be performed. FAR sect. 15.404-1(d)(1). An agency is
not required to conduct an in-depth cost analysis, see FAR sect.
15.404-1(c), or to verify each and every item in assessing cost
realism; rather, the evaluation requires the exercise of
informed judgment by the contracting agency. Cascade Gen., Inc.,
B-283872, Jan. 18, 2000, 2000 CPD para. 14 at 8. Further, an
agency’s cost realism analysis need not achieve scientific
certainty; rather, the methodology employed must be reasonably
adequate and provide some measure of confidence that the rates
proposed are reasonable and realistic in view of other cost
information reasonably available to the agency as of the time of
its evaluation. See SGT, Inc., B‑294722.4, July 28, 2005, 2005
CPD para. 151 at 7; Metro Mach. Corp., B-295744; B‑295744.2,
Apr. 21, 2005, 2005 CPD para. 112 at 10-11. Because the
contracting agency is in the best position to make this
determination, we review an agency’s judgment in this area only
to see that the agency’s cost realism evaluation was reasonably
based and not arbitrary. Hanford Envtl. Health Found.,
B‑292858.2, B-292858.5, Apr. 7, 2004, 2004 CPD para. 164 at 8-9.
NHIC contends that the cost realism analysis was not adequately
documented. Although the record consists of multiple documents
and reports reflecting the analysis performed by the SMEs, TEP,
and BEP, NHIC contends that the documents themselves do not
explain the agency’s rationale and contain only “checked boxes
[referring to worksheets where a SME or TEP member checked “yes”
or “no” as to whether there was a basis for adjusting costs],
conclusory assertions, and discussions questions” to show that
costs were realistic. NHIC's Post-Hearing Comments at 2. We find
that the record shows that the agency performed a comprehensive
and thorough cost realism analysis that considered all of the
major cost elements for each of the functional areas to be
performed under the contract. The agency relied on the TEP
members and SMEs, each of whom has special expertise in the
functional areas, to review whether the proposed labor hours and
mix of labor categories were realistic for the work to be
performed and were consistent with the offeror’s technical
approach. In addition, the BEP consulted with the DCAA to verify
that labor rates and other costs were reasonable. The record
contains extensive contemporaneous documentation--numerous
spreadsheets, worksheets, discussion questions and responses,
and reports--that were created by the SMEs, TEP, and BEP.
Although it is true that the documents are replete with
conclusory statements that proposed costs were realistic, the
record nonetheless evidences that a comprehensive cost realism
analysis was performed and contains documents, such as the
briefing slides to the SSB and the source selection
determination, that provide the rationale for the agency’s cost
realism conclusions. E.g., AR, Tab 58, SSB Presentation, at
10-13; Tab 57, Supplemental SSB Presentation, at 2-4; Tab 56,
Source Selection Determination, at 3-4; see also Contracting
Officer's Statement paras. 61-73.
During the hearing held by our Office, and as reflected in the
contemporaneous documents, the agency explained why, and how,
the evaluators determined that Palmetto’s proposed costs,
including labor costs, were realistic, even though they were
lower than the costs proposed by NHIC.[11] Specifically, as
stated above, Palmetto took advantage of the opportunity,
throughout its proposal, to [REDACTED]. Tr. at 26. Other
identified reasons for Palmetto’s lower costs were that Palmetto
[REDACTED] and identified a number of “efficiency drivers” for
claims processing, appeals, and medical review. AR, Tab 56,
Source Selection Determination, at 2-3; Tab 57, Supplemental SSB
Presentation, at 2‑4; Contracting Officer’s Statement paras.
61-73; Tr. at 17-27, 30-31, 34, 38-39, 105-06, 406-17. Specific
examples of some of these “efficiency drivers” for three of the
major activities (claims processing, appeals, and medical
review), as enumerated in the contemporaneous documents,
include:
(Deleted sections)
NHIC contends that
there is no basis to conclude that any of the proposed
“efficiency drivers” would result in cost savings, since the
agency failed to quantify any of the asserted cost savings.
However, an adequate cost realism analysis does not require an
in‑depth verification of each and every item; an agency may
reasonably rely on statements in an offeror's proposal which
demonstrate the realism of its proposed costs, without
independently verifying each item of proposed costs. Pacific
Architects and Eng'rs, Inc., B‑274405.2, B-274405.3, Dec. 18,
1996, 97‑1 CPD para. 42 at 7; Ferguson-Williams, Inc.; Hawk
Mgmt. Servs., Inc., B-232334, B‑232334.2, Dec. 28, 1988, 88-2
CPD para. 630 at 6. Here, Palmetto’s proposal explained that its
“labor estimating approach” was based on [REDACTED]. Palmetto’s
proposal identified [REDACTED]. Agency Hearing exh. A,
Palmetto's Initial Proposal, at 26-61. As the contracting
officer explained, Palmetto “did a really good job of laying out
‘this is what we’ve been doing, this is what we're going to do
for you now, and this is the impact.'”Tr. at 91, 174. The SMEs
and TEP members considered this information contained in
Palmetto's proposal, looked to see whether the approach was
feasible, and based on their own experience, could find no basis
to upwardly adjust Palmetto's proposed costs. Tr. at 453, 483,
492-93, 522‑23. NHIC has not shown that the agency's evaluation
was unreasonable.
(sections
deleted)
In sum, NHIC has
not shown the agency's "bottom up" cost realism evaluation to be
unreasonable. As discussed above, the agency followed a process
that is consistent with the FAR, in that the
agency“independently review[ed] and evaluat[ed] specific
elements of each offeror's proposed cost estimate to determine
whether the estimated proposed cost elements are realistic for
the work to be performed; reflect a clear understanding of the
requirements; and are consistent with the unique methods of
performance and materials described in the offeror’s technical
proposal.” FAR sect. 15.404-1(d)(1). Moreover, except for its
arguments that historical data should have been the basis for
the cost realism analysis, which we have rejected, NHIC has not
demonstrated, or even attempted to quantify, that cost realism
adjustments in the challenged areas would have eliminated the
$92 million cost differential and resulted in NHIC's most
probable cost being lower than Palmetto’s; thus, NHIC has not
shown that its proposal, which was technically equal to
Palmetto's, had a substantial chance for award. (NHIC
Corporation, B-310801; B-310801.2, February 12, 2008) (pdf)
The protester first argues that the EPA made improper “realism”
adjustments to certain fixed-price elements of IBM’s proposal,
and failed to equally or reasonably evaluate CGI’s proposal. As
discussed above, the agency stated that it would perform both a
cost realism and price realism analysis, as well as assess the
“total cost of ownership” associated with offerors’ proposals.
In the discussion that follows, we address the adjustments that
were made to IBM’s proposal for SCORPIOS replacement, Tier 3
hosting requirements, EPA implementation efforts, and IFMS
retirement costs. We conclude with a discussion of EPA’s
evaluation of certain elements of CGI’s costs.
A cost realism analysis is required when an agency evaluates
proposals for the award of a cost-reimbursement contract. Under
such a contract, an offeror’s proposed costs are not considered
controlling because, regardless of the costs proposed, the
government is bound to pay the contractor its actual and
allowable costs. Federal Acquisition Regulation (FAR) sections
15.305(a)(1), 15.404-1(d). Consequently, an agency must perform
a cost realism analysis to determine the extent to which an
offeror’s proposed costs represent what the contract should
cost, assuming reasonable economy and efficiency. FAR sect.
15.404-1(d)(2); Hanford Envtl. Health Found., B-292858.2,
B-292858.5, Apr. 7, 2004, 2004 CPD para. 164 at 8-9. Although
there is no requirement that an agency perform a cost realism
analysis when offerors propose to perform work on a T&M basis
with fixed-price labor rates, agencies may, as here, provide for
such an evaluation in a solicitation. Resource Consultants,
Inc., B-290163, B-290163.2, June 7, 2002, 2002 CPD para. 94 at
n.1. Cost realism may involve adjustments to proposed costs to
calculate the most probable cost to the government of the
offeror’s proposed approach. In contrast, where an RFP
contemplates the award of a fixed-price contract, or fixed-price
portion of a contract, an agency may also provide in the
solicitation for the use of a price realism analysis for the
limited purpose of measuring an offeror’s understanding of the
requirements or to assess the risk inherent in an offeror’s
proposal. Puglia Eng’g of California, Inc., B-297413 et al.,
Jan. 20, 2006, 2006 CPD para. 33 at 6-7. Although the FAR does
not use the term “price realism,” it provides that cost realism
analysis may be used to evaluate fixed-price proposals as
follows:
Cost realism analyses may also be used on competitive
fixed-price incentive contracts or, in exceptional cases, on
other competitive fixed-price-type contracts when new
requirements may not be fully understood by competing offerors,
there are quality concerns, or past experience indicates that
contractors’ proposed costs have resulted in quality or service
shortfalls. Results of the analysis may be used in performance
risk assessments and responsibility determinations. However,
proposals shall be evaluated using the criteria in the
solicitation, and the offered prices shall not be adjusted as a
result of the analysis.
FAR sect. 15.404-1(d)(3). Thus, as the FAR explains, a
price realism analysis may affect the technical evaluation, but
cannot result in an adjustment of an offeror’s proposed fixed
prices. Id.; see also Puglia Eng’g of California, Inc., supra;
Verestar Gov’t Servs. Group, B-291854, B-291854.2, Apr. 3, 2003,
2003 CPD para. 68 at 6 n.3; Marquette Med. Sys., Inc.,
B-277827.5, B-277827.7, Apr. 29, 1999, 99-1 CPD para. 90 at 6.
Specifically, an agency cannot make upward price adjustments for
cost elements that the agency thinks may be priced too low. All
Phase Environmental, Inc., B-292919.2 et al., Feb. 4, 2004, 2004
CPD para. 62 at 8. (IBM Corporation,
B-299504; B-299504.2, June 4, 2007) (pdf)
Fedcar also asserts that the agency’s price evaluation was
unreasonable because the agency inserted incorrect numbers into
the price evaluation spreadsheet, which resulted in an error in
favor of Duke’s present value ANSI/BOMA office area per square
foot price. In its report, the agency admits that it erred in
calculating the present value of the rent being offered by Duke,
and that, instead of a price difference of [DELETED] per ANSI/BOMA
square foot, the actual price advantage of the rent offered by
Fedcar was [DELETED] per ANSI/BOMA square foot. Supplemental AR
(Feb. 25, 2008) at 5; AR, Tab 40, Net Present Value
Recalculation. The agency further admits that this error results
in a net present value difference of [DELETED] per year, or
[DELETED] over the 15-year life of the lease. Supplemental AR
(Feb. 25, 2008), at 6. However, the agency dismisses this
mistake as inconsequential and asserts that Fedcar is not
prejudiced by the error because the solicitation stated that
“the technical evaluation factors, when combined, are
significantly more important than price.” Id.
We disagree. As indicated above, the record shows the technical
evaluation of the two proposals was relatively close with Duke’s
technical proposal having only a [DELETED]-point advantage (out
of 100 points) over Fedcar’s proposal. AR, Tab 35, Price
Negotiation Memorandum (Dec. 17, 2007), at 3. While it is true
that the technical evaluation factors were said to be
significantly more important than price, the SFO also stated,
“[a]s proposals become more equal in their technical merit, the
evaluation of price becomes more important.” SFO, as amended, at
32. With an initial price differential of only [DELETED] per
square foot, the source selection authority (SSA) could
reasonably place greater emphasis on technical merit in
selecting Duke. Now, however, since the actual price
differential ([DELETED] per square foot) between the offers is
significantly (more than [DELETED] times) greater, if the award
decision were to be based on this revised price difference,
price under the SFO’s evaluation scheme could reasonably become
more important and change the award decision. While the agency
argues that the outcome of the SSA’s cost/technical tradeoff
would be the same regardless of the re-calculated price, our
Office affords little weight to an agency’s post-protest
arguments that are based on judgments the agency asserts it
would have made because such judgments made in the heat of
litigation and based on facts that were not previously
considered that are materially different from those on which the
agency relied in making the original decision may not represent
the fair and considered judgment of the >agency. Global, A 1st
Flagship Co., B-297235.2, Dec. 27, 2005, 2006 CPD para. 14 at 8.
Under the circumstances, we give little weight to the agency’s
assertion that the outcome would have been the same, given that
Fedcar now has a significantly greater price advantage than
found by the agency when it made its source selection decision.
Where a source selection authority bases his or her source
selection decision on figures that do not reasonably represent
the differences in costs to be incurred under competing
proposals, the source selection is not reasonably based. See
Gemmo Impianti SpA, B-290427, Aug. 9, 2002, 2002 CPD para. 146
at 5-6. Thus, Fedcar was prejudiced by the agency’s error in
calculating the price difference between the offers. (Fedcar
Company, Ltd., B-310980; B-310980.2; B-310980.3,March 25,
2008) (pdf)
CHS asserts that
the agency failed to properly evaluate LHI’s price for
reasonableness. Specifically, CHS notes that more than 100 of
LHI’s individual medical procedure prices exceeded the agency’s
independent government cost estimates (IGCE), and that LHI’s
overall price exceeds the agency’s average IGCE. Where, as here,
a solicitation provides for award of a fixed-price
contract--under which the government’s liability is fixed and
the contractor bears the risk and responsibility for the actual
costs of performance--the agency need only evaluate an offeror’s
price for fairness and reasonableness. Federal Acquisition
Regulation (FAR) sections 15.402(a), 15.404-1(a); SAMS El
Segundo, LLC, B-291620.3, Feb. 25, 2003, 2003 CPD para. 48 at 8.
Agencies may use various price analysis techniques and
procedures to ensure a fair and reasonable price, including the
comparison of proposed prices received in response to the
solicitation and comparison with an IGCE. FAR sect.
15.404-1(b)(2)(i), (v). Agencies may rely upon adequate price
competition alone to assess price reasonableness. MVM, Inc.,
B-290726 et al., Sept. 23, 2002, 2002 CPD para. 167 at 6. A
price reasonableness determination is a matter of administrative
discretion involving the exercise of business judgment by the
contracting officer that we will question only where it is
unreasonable. The Right One Co., B-290751.8, Dec. 9, 2002, 2002
CPD para. 214 at 5. The price reasonableness evaluation here,
based on adequate price competition and a comparison of prices
with the agency IGCEs, complied with the RFP’s requirements and
was unobjectionable. The RFP provided that price was to be
evaluated for completeness and reasonableness and to ensure that
the offeror understood the scope of work. RFP at 97. In
evaluating offerors’ prices, the agency compared each offeror’s
individual line item prices to those of the other offerors and
to the agency’s IGCEs, which represented both the low and high
range of estimated costs for each medical and dental procedure.
LHI’s initial overall price was approximately 19 percent higher
than the average IGCE, and CHS’s approximately 2 percent higher,
and the agency found that both prices were reasonable based on
adequate price competition and its conclusion that the prices
were within a reasonable range of the average IGCE. AR, Tab 17,
at 3. In discussions, the agency requested both offerors to
review their work scope and pricing for certain individual
procedures whose prices were lower than the low range IGCE or
higher than the high range IGCE. Both offerors changed some, but
not all, identified prices, and also reduced their overall
prices, resulting in LHI’s price being 11.05 percent higher than
the average IGCE, and CHS’s 0.10 percent higher. AR, Tab 32, at
3‑4, 8. The agency again found that there was adequate price
competition, and that both offerors’ overall prices were within
a reasonable range of the average IGCE. While CHS asserts that
LHI’s price was too far above the average IGCE to be considered
reasonable, as noted by the agency, LHI’s price was lower than
the agency’s high range IGCE. Given this fact, we find no basis
to object to the agency’s price evaluation. CHS’s disagreement
with the agency’s judgment does not make the evaluation
unreasonable. Hughes Georgia, Inc., B-272526, Oct. 21, 1996,
96-2 CPD para. 151 at 7. (Comprehensive
Health Services, Inc., B-310553, December 27, 2007) (pdf)
ITT further contends that NASA’s cost realism evaluation was
flawed because it failed to properly consider Defense Contract
Audit Agency (DCAA) audit results identifying irregularities
with BATC’s compliance with cost accounting standards (CAS)--specifically,
CAS 420--concerning, as relevant here, BATC’s allocation of its
costs for independent research and development. As a
consequence, ITT contends that NASA’s “most probable cost”
estimate for BATC was not reasonably supported. Specifically,
ITT highlights the fact that DCAA qualified its audit results
for BATC based on the fact that BATC was “noncompliant” with CAS
420, which had been reported in prior audits, indicated that the
cost impacts had not been determined, and stated that these
issues “may have a significant effect on the final cost
allocations for CAS covered Government contracts.” AR, Tab 50,
DCAA Audit for BATC, 08221. In addition, DCAA explained that the
Divisional Administrative Contracting Officer (DACO) of the
Defense Contract Management Agency for BATC would separately
negotiate the cost impact of the noncompliance. Id. The record
shows that NASA further questioned DCAA on this issue, asking
whether it could provide some indication of the magnitude of the
cost impact. DCAA responded that it could not provide such an
estimate, simply noting that the matter would be addressed by
the DACO. NASA did not pursue the matter with BATC during
discussions and did not make any adjustments to BATC’s costs as
result of the DCAA qualification. In a hearing held by our
Office, however, the DACO for BATC, who is responsible for,
among other things, cost allowability issues and interacting
with DCAA regarding its contractor audit reports with respect to
BATC’s contracts, provided testimony regarding this issue. The
DACO explained that BATC’s noncompliance relates to a 2001 audit
finding, which has not yet been resolved, that any cost impact
would be limited to fiscal year 2000 incurred costs, and that
any cost adjustment would be limited to a decrease in costs to
the government--BATC’s noncompliance would not result in
increased costs to the government. Hearing Transcript (Hearing
Tr.) at 173. Moreover, the DACO indicated that even if the
noncompliance identified in the 2001 audit were a continuing
issue, such that it implicated BATC’s 2007 contracts (something
which the DACO indicated has not been identified by DCAA), such
noncompliance by BATC again would not result in any increased
costs to the government, thus negating any concern that BATC’s
costs under the OLI contract would increase as a consequence of
the outstanding CAS issue. Id. While ITT contends that the issue
was raised by DCAA and that the DACO cannot speak for DCAA, the
record reflects that DCAA expressly indicated that the matter
would be addressed by the DACO and ITT has not explained why the
DACO’s testimony should be regarded as unreliable or otherwise
unreasonable. As a consequence, on this record, ITT’s challenge
does not provide a basis for our Office to sustain its protest
with regard to this issue. (ITT
Industries Space Systems, LLC, B-309964; B-309964.2,
November 9, 2007) (pdf)
GDIT maintains that there were a number of inconsistencies in
RTSC’s price proposal, with the labor rates included in the B.4
table being higher than the rates included in the B.2 table. The
protester identifies two areas where these inconsistencies
appear. First, RTSC’s FPR eliminated a [deleted] percent
escalation rate that it previously had applied to its direct
labor rates for its [deleted] employees. Although the firm
submitted a revised B.2 table with its FPR that reflected the
elimination of this [deleted] percent escalation rate, it did
not submit a revised B.4 table. Second, the protester has
identified some 40 additional labor categories where RTSC’s
rates in its B.4 table are higher than the rates included in the
firm’s B.2 table. According to the protester, the agency’s
failure to include the higher of these inconsistent prices in
RTSC’s evaluated price--as expressly provided for in the
RFP--resulted in an understatement of RTSC’s total evaluated
price of approximately $97 million. The agency responds that,
with respect to the [deleted] labor rates, it reasonably relied
on language appearing in the May 7 cover letter accompanying
RTSC’s FPR to conclude that the firm had reduced its pricing in
both the B.2 and B.4 tables, notwithstanding any apparent
inconsistencies between the prices in tables B.2 and B.4. This
letter provided, in pertinent part: “Our proposed burdened labor
rates for the categories and locations attached to this letter
are hereby updated accordingly for both Section B.2 and B.4.
These rates represent a total reduction of $[deleted] in our
evaluated B.2 price.” AR exh. 75, Cover Letter. The agency
maintains that this language was sufficient to obligate RTSC to
provide rates without the [deleted] percent escalation. The
agency maintains, moreover, that, even if this language was
inadequate to obligate RTSC, this is a minor clerical error that
can be corrected after award. With respect to the other 40
inconsistent labor rates, the agency states that it relied on
similar language appearing in the firm’s proposal providing
that: “Raytheon assures that the rates proposed in Section B.2
‘T&M Evaluation Worksheets’ are consistent with B.4 ‘Loaded
Labor Rates Matrix,’” and further providing that “[e]ach site
referenced in the B.2 tables has been mapped into the
corresponding B.4 Appendix B Locations on the tabs of the B.4
workbooks.” AR exh. 60, Volume 5_Book 2_CP_rev2.doc, at 76. The
agency asserts that this was sufficient to indicate that RTSC
intended to be bound by the lower rates appearing in the B.2
table.
We find that the agency improperly failed to include an
additional $97 million (consistent with GDIT’s calculation) in
RTSC’s evaluated price. The RFP was unequivocal regarding how
the agency was to evaluate proposals in the event of an
inconsistency between the B.2 and B.4 tables:
Section B.2 ‘Time and Materials
Evaluation Worksheets’ will be evaluated to ensure that the
rates proposed are consistent with the B.4 ‘Loaded Labor
Rates Matrix’ . . . . Inconsistencies between B.2 and B.4
rates, or between B.3 and B.5/B.6 FFP, will result in the
Government using the higher of the inconsistent rates/prices
for the Total Evaluated Price.
RFP at M-3. It is undisputed that
RTSC’s B.2 table included revised prices that were inconsistent
with the higher prices in its B.4 table. Under the above-quoted
language, in this situation, the agency was to include the
higher prices in the evaluation. The agency, in relying upon the
information in RTSC’s cover letter, disregarded this express RFP
provision in arriving at RTSC’s total evaluated price. The
agency’s reliance on the language in the May 7 cover letter, in
lieu of the approach plainly set forth in the RFP, was
misplaced. Not only was such reliance inconsistent with the
plain language of the RFP but, in any case, the cover letter
language rendered RTSC’s proposal, at best, ambiguous. In this
regard, although RTSC purported to revise both its B.2 and B.4
tables by the terms of the cover letter, as noted, it submitted
only a revised B.2 table and stated that its proposed change
“represents a total reduction of $[deleted] in our evaluated B.2
price.” AR exh. 75. Other portions of RTSC’s proposal--including
its B.4 table--remained unchanged by the May 7 revision,
including the narrative replacement pages to its proposal that
RTSC had previously submitted in connection with its earlier
offer of the [deleted] percent escalation for its [deleted]
employees. AR exh. 42d, Vol. 5, book 2 change pages, at 157-57f.
Thus, RTSC’s B.4 table and narrative proposal continued to offer
the [deleted] percent annual escalation to its [deleted]
employees’ compensation, notwithstanding the language of its
cover letter. Agencies are required to evaluate proposals
in a manner consistent with the solicitation. Clean Harbors
Env’t Servs., Inc., B-296176.2, Dec. 9, 2005, 2005 CPD para. 222
at 3. The RFP here expressly provided that the agency would
evaluate inconsistent pricing in a very specific manner, and the
agency failed to evaluate RTSC’s proposal consistent with the
RFP ground rules. (General Dynamics
Information Technology, B-299873, September 19, 2007) (pdf)
An agency may not
reasonably award a cost‑reimbursement contract to an offeror
whose cost proposal evidenced a different technical approach
than that presented in the technical proposal, without resolving
the inconsistency. See TRW, Inc., B‑254045.2, Jan. 10, 1994,
94-1 CPD para. 18 at 8-9. Here, the agency failed to resolve the
inconsistency presented in MTJV’s cost and technical proposals.
In any case, we find no reasonable basis in the record for the
Navy’s “assumption” that Tecnico’s rates were “representative of
prevailing Mayport area labor rates.” As noted by the protester,
Tecnico’s burdened labor rate of $[Deleted] was significantly
lower than all but one of the other offerors’ and their
subcontractors’ burdened labor rates. In fact, we calculate the
average burdened labor rate for offerors and their
subcontractors to be $[Deleted].[6] More specifically, Tecnico’s
burdened labor rate was significantly lower than the rates
proposed by Earl ($[Deleted]), Atlantic Marine ($[Deleted]), and
QED ($[Deleted]), which were the firms specifically identified
by MTJV for possible performance of [Deleted] percent of the
contract work. Although the Navy provided the declaration of the
CAP chairperson, who generally states that he found that
Tecnico’s rate was comparable to rates of other contractors
working in the Mayport area, see Navy’s Response to Earl’s
Comments, attach. D, Declaration of CAP Chair, at 2, this
declaration does not explain with any specificity how he
determined this, nor does the Navy otherwise address or rebut
the protester’s arguments concerning Tecnico’s lower rate
compared to the offerors’ rates in this competition. We also
note that allowing MTJV to propose subcontracting a significant
amount of the contract to unnamed subcontractors appears to also
be inconsistent with the RFP’s requirements to identify and
provide cost proposals for significant subcontractors, which the
RFP defined, in part, to be contractors that were providing
effort consisting of 5 percent of total direct dollars. See RFP
sect. L, at 154, 159. With respect to the Navy’s contention that
Earl similarly proposed to perform [Deleted] percent of the
contract with subcontractors other than those it proposed in its
cost proposal, we fail to see how, even if this were true, this
demonstrates that the agency’s cost realism evaluation was
reasonable. In any event, as noted above, MTJV stated in its
technical proposal that it would allocate [Deleted] percent of
its productive hours assigned to Tecnico at that firm’s low
labor rate to other “miscellaneous specialty contractors,” which
all appear to have higher labor rates than Tecnico’s. Earl, on
the other hand, stated in its technical proposal that [Deleted]
percent of the contract work would be performed by its
identified team of subcontractors (whose labor rates were
considered in the agency’s cost realism analysis), and that Earl
would “accomplish the remaining work with the assistance of our
Surge/Specialty Subcontractors” (all of which were also
specifically identified in Earl’s proposal). See AR, Tab 5, Earl
Technical Proposal, at 25-26. There is no evidence in the
record, nor has the agency provided any argument, that indicates
that any of the surge/specialty subcontractors identified by
Earl in its proposal have higher rates than Earl. In any event,
unlike MTJV’s unequivocal statement that work allotted to
Tecnico would be performed by others, Earl stated it would
perform [Deleted] percent of the contract work, albeit with the
assistance of the identified surge/specialty subcontractors.
(Earl Industries, LLC, B-309996;
B-309996.4, November 5, 2007) (pdf)
Navarro challenges the adequacy of the agency’s price realism
analysis. In this regard, section M of the RFP stated that
proposals “will be evaluated to determine if the proposed costs
are realistic and consistent with the Technical Proposal with
regard to the nature, scope, and duration of the work to be
performed. Inconsistencies between the Cost/Price Proposal and
other portions of the proposal could raise concerns regarding
the offeror’s understanding of the requirements and ability to
perform the work for the proposed price.” RFP at 92. Where
a fixed-price contract--including a fixed-rate contract such as
this one--is to be awarded, an agency may provide for the use of
a price realism analysis in a solicitation for such purposes as
measuring an offeror’s understanding of the solicitation’s
requirements and for assessing the risk inherent in an offeror’s
proposal. Star Mountain, Inc., B-285883, Oct. 25, 2000, 2000 CPD
para.189 at 4. The Federal Acquisition Regulation (FAR)
identifies a number of price analysis techniques that may be
used to determine whether prices are reasonable and realistic,
including comparison of the prices received with each other and
with the independent government estimate, and analysis of
pricing information provided by the offeror. FAR sect.
14.404-1(b)(2). The nature and extent of a realism analysis
ultimately are matters within the agency’s discretion, unless
the agency commits itself to a particular methodology in the
solicitation. Id. DOE’s realism analysis consisted of
comparing the proposed rates for the specified labor categories
to both the government estimate and the other proposed prices,
and the use of statistical analysis techniques to analyze the
information. Technical Evaluation Report (TER) at 37-46 and
attach. 4. As a result of its analysis, the agency concluded
that all offerors’ total prices were realistic, including
Stoller’s, which was approximately 11.6 percent lower than the
government estimate. AR at 25, 28. In this regard, the agency
found that some of Stoller’s and other offerors’ labor rates
were lower than the government estimate and that some were
higher, but concluded that, overall, all offerors’ proposed
rates were consistent with the estimate. AR at 25. In addition,
DOE verified that each offeror’s prices reflected the estimated
number of labor hours for each labor category specified in the
RFP. We find nothing objectionable in the agency’s evaluation
methodology. Navarro complains that the realism analysis
was flawed because it was based on a government estimate that
was not prepared until after the proposals were received.
However, there is nothing per se improper in an agency’s
reliance on a government estimate revised after offers are
received where it determines that the original estimate is
erroneous. McCarthy Mfg. Co., B-186550, Feb. 17, 1977, 77‑1 CPD
para. 116 at 3-4. DOE explains that it reduced the government
estimate after proposals were received to correct errors and to
account for inapplicable and likely inaccurate assumptions. For
example, among other things, DOE reduced the overhead rate
assumption from 100 percent to 50 percent because the lower rate
was consistent with similar contracts performed on government
property. The agency also reduced the profit rate to correspond
to the rates offerors actually proposed. AR at 29-30. Navarro
does not challenge any specific changes made by the agency, and
does not assert--and we find no reason to conclude--that the
estimate itself is unreasonable. Accordingly, we find no basis
for questioning the agency’s use of the revised estimate. (Navarro
Research and Engineering, Inc., B-299981; B-299981.3,
September 28, 2007) (pdf)
Protest is sustained where (1) solicitation for combat search
and rescue aircraft provided that cost/price would be calculated
on the basis of Most Probable Life Cycle Cost, including both
contract and operations and support (O&S) costs, (2)
solicitation requested detailed information quantifying required
maintenance for proposed aircraft, and (3) agency nevertheless
normalized cost of maintenance when calculating O&S costs,
thereby ignoring potentially lower cost of asserted low
maintenance helicopters; once offerors are informed of criteria
against which proposals will be evaluated and award made, agency
must adhere to those criteria. (Sikorsky
Aircraft Company; Lockheed Martin Systems Integration‑Owego,
B-299145; B-299145.2; B-299145.3, February 26, 2007) (pdf)
The FAR provides a number of price analysis techniques that may
be used to determine whether prices are fair and reasonable,
including comparison of the prices received with each other;
comparison of previously proposed prices for the same or similar
items; and comparison with the independent government estimate.
FAR sect. 15.404-1(b)(2). A price reasonableness determination
is a matter of administrative discretion involving the exercise
of business judgment by the contracting officer that we will
question only where it is unreasonable. The Right One Co.,
B-290751.8, Dec. 9, 2002, 2002 CPD para. 214 at 5. Our review of
the record here provides no basis to question the reasonableness
of the contracting officer’s determination. Section M of
the RFP, quoted above, clearly stated that an offeror’s
evaluated price would be calculated by multiplying each of the
priced line items by the estimated quantities and by adding all
of the extended prices to arrive at the lowest total evaluated
price for the varied quantities. RFP amend. 2, adden., attach.
1, Price Evaluation. Further, section M did not require the use
of price realism analysis to measure the offerors’ understanding
of the government’s requirements or to assess the risk inherent
in an offeror’s proposal. PHP Healthcare Corp., B-251933, May
13, 1993, 93-1 CPD para. 381 at 5. Rather, as described above,
the record shows that the contracting officer agency conducted a
price reasonableness evaluation based upon adequate price
competition, which reflected approximately a 4 percent
differential between the proposals of USDC and USTI, along with
comparison of the proposed prices to the government estimate.
Although USDC’s essential complaint is that the contracting
officer’s analysis should have been more exhaustive, our review
confirms that the price evaluation conducted by the agency was
reasonable and fully consistent with the provisions of the RFP.
USDC asserts that the contracting officer should have obtained
and analyzed additional information in evaluating offerors’
proposed prices. In support of its position, USDC points to
language in section L of the RFP which states that information
other than costs and pricing data may be required to support
price reasonableness. As discussed above, in this case, section
M of the RFP did not require that additional information would
be evaluated as part of the agency’s price evaluation. Absent an
RFP provision in a solicitation for a fixed-price contract
requiring a price realism analysis, no such analysis is
required. Dismas Charities, Inc., B-289575.2; B-289575.3, Feb.
20, 2004, 2004 CPD para. 66 at 4. (U.S.
Dynamics Corporation, B-298889, December 19, 2006) (pdf)
The RFP provided possible methods for evaluating price
reasonableness: information submitted with the offeror’s
proposal, the comparison of other competitive offers, the
independent government cost estimate (IGCE), or on any other
reasonable basis. RFP amend. 3, sect. M, at 35. Of these
options, the agency chose to evaluate price reasonableness by
comparing price proposals to each other as well as to the IGCE.
The agency has adequately documented its price analysis and
reasonably determined, based on a comparison of price proposals
and comparison of the prices to the IGCE, that the awardees’
prices were fair and reasonable. Agency Report, Tab 25,
Cost/Price Analysis Report, at 1. While the protester alleges
the agency should have conducted a more in-depth analysis of the
price proposals, the depth of an agency’s price analysis is a
matter within the sound exercise of the agency’s discretion; we
find no legal requirement here for the agency to have done a
more in-depth analysis than was undertaken here. See Redcon,
Inc., B‑285828, B‑285828.2, Oct. 11, 2000, 2000 CPD para. 188 at
9. Given that Indtai’s price is significantly higher than the
awardees’ prices, many of the protester’s contentions concern
the agency’s alleged failure to perform sufficient analysis to
determine whether the awardees’ prices were too low or consider
the performance risk of these assertedly low prices. However,
the purpose of a price reasonableness analysis is to determine
whether the prices offered are higher--as opposed to lower--than
warranted. See Dismas Charities, Inc., B‑289575.2, B-289575.3,
Feb. 20, 2004, 2004 CPD para. 66 at 4; Sterling Servs. Inc.,
B-291625, B-291626, Jan. 14, 2003, 2003 CPD para. 26 at 3. In
contrast, arguments that the agency did not perform an
appropriate analysis to determine whether prices are too low
such that there may be a risk of poor performance concern price
realism not price reasonableness; price realism is not required
to be evaluated by the agency unless the solicitation provides
for such an analysis. Dismas Charities, Inc., supra. Here, the
solicitation did not provide for a cost realism analysis and the
agency therefore did not have to perform such an analysis.
(Indtai
Inc., B-298432.3, January 17, 2007)
(pdf)
CAS
401--which is applicable to ACC--requires a contractor’s
practices in estimating costs for a proposal to be consistent
with cost accounting practices used by the contractor in
accumulating and reporting costs. 48 C.F.R. sect. 9904.401-20
(2005). This requirement is imposed because “[c]onsistency in
the application of cost accounting practices is necessary to
enhance the likelihood that comparable transactions are treated
alike,” so that, among other things, there is “financial control
over costs during contract performance.” Id. More significantly,
CAS 402--also applicable to ACC--states:
All costs incurred for the
same purpose, in like circumstances, are either direct costs
only or indirect costs only with respect to final cost
objectives. No final cost objective shall have allocated to it
as an indirect cost any cost, if other costs incurred for the
same purpose, in like circumstances, have been included as a
direct cost of that or any other final cost objective.
Further, no final cost objective shall have allocated to it as
a direct cost any cost, if other costs incurred for the same
purpose, in like circumstances, have been included in any
indirect cost pool to be allocated to that or any other final
cost objective.
48 C.F.R. sect. 9904.402-40.
Because of these requirements, ACC was and will be required to
account for its costs in a manner consistent with its
established accounting practices during the course of this
contract performance. General Research Corp., B-241569, Feb. 19,
1991, 91-1 CPD para. 183 at 9; CACI, Inc.--Fed., B‑216516, 84-2
CPD para. 542 at 10‑13. Consequently, in determining ACC’s
evaluated probable cost for performing this contract, the agency
could not reclassify costs that ACC treats as indirect costs in
its accounting system as direct costs. See General Research
Corp., supra; CACI, Inc.--Fed., supra. The agency argues that
this adjustment was necessary in order to allow for a more
“equitable” comparison of the cost proposals. In effect, the
agency here has selectively “normalized” the cost elements
included in the offerors’ indirect cost pools. Normalization is
a technique sometimes used within the cost evaluation/adjustment
process that involves measuring offerors against the same cost
standard or baseline where there are no logical differences in
approach or in situations where insufficient information is
provided in the proposals. General Research Corp., supra. Such a
normalization process was improper here because ACC’s proposal
necessarily accounted for PMO costs as part of its indirect
costs, which were required to be accounted for in a like manner
under this contract.[4] Therefore, the agency’s “normalization”
of PMO costs among the offerors with different accounting
systems necessarily resulted in an unreasonable estimate of the
offerors’ proposed costs for performing this contract. General
Research Corp., supra, at 5-6, 9. Moreover, the agency has never
explained why deleting PMO costs from proposed indirect costs
will result in a more equitable comparison of proposals. There
is no evidence in the record that the shifting of costs from
indirect to direct can result in a number that represents the
probable costs of a particular proposal in performing the
contract, because there is no indication that the cost model’s
plug number represents the direct cost approach that will be
taken by each contractor. The agency asserts that because
an RFP amendment advised offerors, in response to an offeror’s
question, that a “standing PMO” would not be funded, offerors
were on notice that PMO costs were “within the scope of direct
costs fixed by the Navy.” Agency Brief (Oct. 20, 2006) at 2; see
RFP amend. 3, attach. 1, Q&A 44. The agency posits that its cost
evaluation adjustment to account for ACC’s different treatment
of PMO costs was therefore appropriate in order to allow for an
“equitable” comparison of the proposals. This argument is
meritless for a variety of reasons. First, the statement that
the agency would not fund a “standing PMO” does not suggest that
PMO costs were included as direct costs; if anything, it
suggests the opposite. Also, as noted above, the agency does not
explain how this statement would allow ACC to vary from its
established accounting practices with regard to PMO costs.
Finally, there is no evidence that any PMO costs were included
in the “plug” numbers for direct costs. The agency argues that
KBR was not prejudiced because it was also the beneficiary of a
downward cost adjustment in its indirect costs. However, as
noted above, the adjustment to KBR’s probable costs was to
properly account for an apparent overstatement in several of its
indirect rates, which is an entirely different proposition than
reclassifying costs that had been properly included in indirect
cost pools to direct costs. Finally, as noted by the protester,
several of ACC’s indirect cost rates are significantly less than
those proposed by the other offerors, which KBR suggests
evidences that costs which other offerors charged as indirect
costs may be charged as direct costs by ACC. KBR contends that
given the multiple accounting variances amongst the offerors,
the agency’s “singling out” of ACC’s PMO costs to adjust from
indirect costs to direct costs was unreasonable and represented
unequal treatment. The agency has offered no substantive
response to this KBR contention, which, based on this record,
appears to have merit. In sum, the agency’s adjustment to ACC’s
proposal was unreasonable and prejudiced KBR because it resulted
in ACC being evaluated as having a lower cost than KBR, such
that no cost/technical tradeoff was performed. (Kellogg
Brown & Root Services, Inc., B-298694; B-298694.2;
B-298694.3, November 16, 2006) (pdf)
Multimax, BAE and Pragmatics assert that the Army’s evaluation
of proposed labor rates was unreasonable. In this regard, the
Army reports that it employed a two‑step approach to evaluating
labor rates for purposes of determining price reasonableness,
detecting unbalanced pricing, and identifying labor rates to
question during discussions: first, it compared an offeror’s
rate for a labor category to the IGCE rate for that category,
and then it compared the rate to the mean of all offerors’
evaluated rates for each labor category using a
two‑standard‑deviation measure. The agency’s price evaluator
explained the second step as follows:
Next, the Price evaluation team calculated the mean of all
offerors’ evaluated labor rates for each labor category. The
mean evaluated labor rates were then used to calculate the
standard deviation from the mean. In order to determine the
most appropriate measure of comparison, the following were
calculated: mean plus and minus one standard deviation, mean
plus and minus two standard deviations, and mean plus and
minus three standard deviations. A comparison was made, using
the three separate standard deviations, to determine which
offerors’ average labor rates for each labor category fall
outside the range of each standard deviation. The majority of
the offerors’ average labor rates fell outside the range of
one standard deviation and no offeror’s average labor rates
fell outside the range of three standard deviations.
Therefore, it was determined that two standard deviations was
the most appropriate measure of comparison to use for the
reasonableness assessment.
Memorandum of Agency Price Evaluator to Source Selection
Evaluation Board (SSEB) Chairperson, Nov. 29, 2005, at 2-3;
Agency Comments, Sept. 21, 2006, at 3.
Under this two-step approach, the agency would issue an IFN1 to
an offeror questioning a proposed labor rate as significantly
overstated (or understated) only if the rate both exceeded (or
was lower than) the IGCE rate, and was more than two standard
deviations greater (or less) than the mean rate of all offerors
for that category. According to the contracting officer (who was
responsible for conducting discussions and determining overall
price reasonableness), the two-step evaluation was used to
identify “extraordinary outlier rates,” that is, “rates that
were significantly overstated or understated and which might
pose a risk to the Government of paying an unreasonable amount
during performance. . . . Rates that did not meet [both] tests
were not considered outliers and were not questioned.” Second
Declaration of Contracting Officer at 1; see Agency Comments,
Sept. 8, 2006, 3-8, 16; Agency Comments, Sept. 21, 2006, at 3;
Declaration of Agency Price Evaluator, Aug. 18, 2006, at 1.
The two-standard-deviation formula resulted in an extremely wide
range of acceptable rates for the labor categories. The upper
end of the range was significantly above the IGCE for some of
the labor categories, and in some instances was nearly, or more
than, twice the IGCE (such as $[REDACTED] versus the $[REDACTED]
IGCE rate for Application System Analyst-Senior, $[REDACTED]
versus the $[REDACTED] IGCE rate for Software Engineer-Senior,
and $[REDACTED] versus the $[REDACTED] IGCE rate for Information
Security Specialist-Senior). Likewise, the lower end, in some
instances, was below the federal minimum wage or was even a
negative number (such as $[REDACTED] for Project Administrator,
$[REDACTED] for Information Security Specialist-Senior, and
$[REDACTED] for Information Security Specialist‑Associate).
There is no indication that the agency ever reviewed the results
of the formula to assure that the prices at the extreme end of
the ranges reflected reasonable pricing; rather, the agency
mechanistically applied the formula and accepted the results
without further analysis. We conclude that the agency’s
methodology did not provide a valid means for identifying
“outlier” (questionable) rates, and this aspect of the
evaluation therefore was unreasonable. See generally Metro Mach.
Corp., B‑297879.2, May 3, 2006, 2006 CPD para. 80 at 9‑10
(mechanical application of an agency’s own estimates for labor
hours or costs to determine evaluated costs, without the
exercise of informed judgment by the contracting agency in
independently analyzing the offeror’s proposed costs based upon
its particular approach and circumstances, was unreasonable);
The Jonathan Corp.; Metro Machine Corp., B-251698.3, B-251698.4,
May 17, 1993, 93-2 CPD para. 174 at 11-13; United Int’l Eng’g,
Inc. et al., B-245448.3 et al., Jan. 29, 1992, 92-1 CPD para.
122 at 11. We therefore sustain the protests of Multimax, BAE
and Pragmatics on the basis that the Army failed to reasonably
evaluate proposed labor rates. (Multimax, Inc.; NCI
Information Systems, Inc.; BAE Systems, B-298249.6, B-298249.7,
B-298249.8, B-298249.9, B-298249.10,October 24, 2006) (pdf)
——————————————
1 Items for Negotiation
(IFN)
EHMC challenges the agency’s determination that its price was
unreasonably high, noting that its price was lower than both the
prices VA has paid for the same services under a previous
contract, and the cost guidelines utilized by the Medicare
program for home oxygen services. The agency formulated the
government estimate based primarily on the prices it was
currently paying under the 6‑month contract extension negotiated
in October, but increased the price for CLIN 1--for oxygen
concentrators, which formed the largest single segment of the
contract--from $60 (the extension price) to $90. Even with this
50-percent increase in the CLIN 1 price, as noted, EHMC’s price
exceeded the estimate by 39 percent. Notwithstanding that there
may have existed other price measures that would have been more
favorable to EHMC, comparison of prices to a government estimate
is a legitimate means of determining price reasonableness. See
Bahan Dennis, Inc., B‑249496.3, Mar. 3, 1994, 94-1 CPD para. 184
at 3 (cancellation based solely on comparison to the government
estimate was reasonable). This is particularly the case here,
since the estimate was largely based on prices currently being
paid under an existing contract. EHMC asserts that the
estimate was too low and did not constitute a proper basis for
determining price reasonableness. Specifically, EHMC argues
that, since the prior contract was awarded to MCS on January 1,
2001, and since the prices in that contract remained constant
throughout the base year and 4 option years, those prices--which
were reflected in the 6-month extension and, thus, the
estimate--were not an accurate reflection of the current cost of
oxygen equipment and services. We disagree. While EHMC is
correct that the prices in the 6‑month extension were similar to
those under the preceding contract, this fact in no way
diminishes their validity for purposes of determining price
reasonableness. Since the prices in the 6-month extension were
negotiated in October 2005, and MCS was actually performing the
work at the negotiated price when the RFP was issued, we see no
reason why the agency could not accept those prices as
representative of the current market price. The protester has
not shown that the agency failed to consider market conditions
or other extenuating circumstances that rendered the negotiated
price an invalid basis for comparison. Moreover, the agency did
not merely rely on the extension prices; rather, as noted above,
it increased the estimate for CLIN 1, the largest segment of the
work under the RFP, 50 percent above the fourth option year
price under MCS’s contract. Regarding CLIN 1, although MCS was
performing at a unit price of $60 (and, as noted, had been
performing at that price during the fourth option year of its
contract), the contracting officer (CO) explains that the 50
percent upward adjustment was based on his discussions with
another contracting official who had contacted other VA medical
centers to obtain prices. CO’s Statement, Sept. 21, 2006, at 2.
The $90 unit price also closely reflected offerors’ prices under
the same CLIN for the 2001-05 contract‑-offerors there proposed
level 5-year pricing (except for MCS’s reduced fourth year
option price) of $90, $93, and $95. Protester’s Comments, Sept.
26, 2006, exh. 1. Thus, while the $90 unit price was similar to
prices from proposals that were submitted in 2000, those
proposals essentially reflected the offerors’ views that prices
would not increase significantly through 2005. Against this
backdrop, given MCS’s willingness, as of January 2006, to
perform CLIN 1 at a substantially lower price, the agency
certainly had ample reason to believe that $90 did not
understate the current market price. The protester also argues
that the estimate was flawed in that it did not provide for
inflation over the life of the contract. However, while the
estimate apparently was based on level pricing ($719,000) for
the base and 4 option years, as already discussed, under the
prior contract each of the offerors proposed level pricing over
the 5 contract years. Id. Furthermore, while the protester
maintains that some significant inflation factor should be
applied to each contract year, we note that the protester itself
only proposed to increase prices in 2 of the 4 option years. The
protester also has failed to provide any evidence establishing
that cost increases for home oxygen services and supplies are,
or should be, expected to occur over the contract term. We
therefore are not persuaded that inflation should have been
factored into the government estimate. (Eagle
Home Medical Corporation, B-298478, October 13, 2006) (pdf)
UMS and AKSM again were the only two firms to submit proposals.
Regarding prices for the YAG laser system, UMS’s proposal
listed, in the appropriate blanks to the right of the item
description, a unit price of $1,325 for the system and a total
price of $15,900 (the price for 12 units) for the base year. In
addition to the blanks next to the item description, the pricing
sheet also contained another blank under the description, in
which offerors were again to fill in the unit price for each
item. Here, UMS did not write $1,325 for the laser system, but
instead wrote [deleted] (emphasis in original), and then added
[deleted] additional lines containing prices for [deleted]
different size fibers (ranging from [deleted] to [deleted]). UMS
repeated this pricing scheme for the YAG laser system for each
of the option years, changing only the total prices to reflect
the different number of units in the option years (25 units for
each year). In contrast, AKSM’s proposal listed a unit price of
$900 for the YAG laser system in both the blank next to the
description and the blank below the description. Regarding
prices for the standby charges, UMS’s proposal listed, in the
appropriate blanks to the right of the item description, a unit
price of $250 for standby charges, and a total price of $1,250
(the price for 5 units) for the base year. In the blank under
the item description, UMS again listed $250, but included the
phrase [deleted] (emphasis in original) after the unit price.
Again, UMS repeated this pricing for each of the option years,
changing only the total prices to reflect the changed number of
units (10 units for each year). In contrast, AKSM’s proposal
listed standby charges of $475 in both blanks. Finally, for the
ESWL, UMS listed a unit price of $875 in the blank next to the
item description and the blank below the item description. AKSM
listed a price of $1,400 in both places. UMS primarily alleges
that VA performed an improper price evaluation. Specifically,
whereas VA based UMS’s total evaluated price on a unit price of
$1,325 for the YAG laser system, UMS alleges that this was not
its lowest possible price; rather, its lowest price was the
price listed under the item description--[deleted] for the least
expensive fiber, for a total unit price of $1,200. Since this
price would have left UMS as the low offeror, it concludes that
the agency’s price evaluation was materially flawed.
The price evaluation here was reasonable. Regarding the laser
system, it was proper for the agency to use $1,325 as the item
price for evaluation purposes, given that $1,325 was the unit
price that UMS provided in the space to the right of the item
description, and that it was the only firm, fixed unit price
offered. In any case, even if UMS were correct that its range
pricing should have been used in the evaluation, $1,200 would
not be the proper evaluated unit price. In this regard, where an
offeror provides a range of prices where a single firm, fixed
price is required, the evaluation must be based on the highest,
not the lowest, price in the range, since this could be the
ultimate cost to the government if award were made to that firm.
See Tri-State Gov’t Servs., Inc., B‑277315.2, Oct. 15, 1997,
97-2 CPD para. 143 at 4-5. The highest unit price in UMS’s
proposed price range was [deleted] ([deleted] for the fiber).
Accordingly, this price, not $1,200, would be the appropriate
price for the agency to use if it were to evaluate UMS’s range
pricing. (United Medical Systems-DE,
Inc., B-298438, September 27, 2006) (pdf)
In our view, the record here lacks any persuasive evidence that
the agency examined the completeness of the offerors’ price
proposals as called for by the RFP. We note that the
solicitation here did not merely use the term “completeness” in
setting out the parameters of the price evaluation, but
explained, in detail, that the agency planned to evaluate
completeness, and identified the kind of back-up pricing data
that offerors needed to produce for the agency’s evaluation; the
agency’s failure to conduct this review was clearly contrary to
the solicitation’s requirements. See OMNIPLEX World Servs.
Corp., B‑291105, Nov. 6, 2002, 2002 CPD para. 199 at 10. (Advanced
Systems Development, Inc., B-298411; B-298411.2, September
19, 2006) (pdf)
Where, as here, an RFP contemplates the award of a fixed-price
contract, an agency may provide for the use of a price realism
analysis for the limited purpose of measuring an offeror’s
understanding of the requirements or to assess the risk inherent
in an offeror’s proposal. Rodgers Travel, Inc., B-291785, Mar.
12, 2003, 2003 CPD para. 60 at 4; Star Mountain, Inc., B-285883,
Oct. 25, 2000, 2000 CPD para. 189 at 2. The nature and extent of
the agency’s price analyses are matters within the sound
exercise of the agency’s discretion, and our review of such an
evaluation is limited to determining whether it was reasonable
and consistent with the provisions of the solicitation. Id.
Among the price analysis techniques that may be used is an
analysis based on previous proposed prices or contract prices.
Federal Acquisition Regulation (FAR) sect. 15.404-1(b)(2). We
agree with the protester that the contract specialist’s
“adjustments” to the fixed prices proposed were problematic. A
price realism analysis, if conducted, may affect the technical
evaluation; it cannot properly lead to adjustment of proposed
fixed prices. See Verestar Gov’t Servs. Group, B‑291854,
B-291854.2, Apr. 3, 2003, 2003 CPD para. 68 at 6 n.3. If the
selection decision had been based on those “adjusted” or
“factored” prices, the procurement might have been fatally
flawed. The tradeoff analysis in the PNM, however, was
explicitly based on the unadjusted proposed prices, and the
source selection decision, as quoted above, explicitly found
that “the advantages of having Todd perform [the work] is worth
the additional financial outlay (regardless of whether that
amount is based upon the original proposed values or adjusted
values).” Accordingly, any flaws in the conduct of the price
realism analysis did not prejudice PECI. Competitive prejudice
is an essential element of a viable protest and where no
prejudice is shown, or is otherwise not evident from the record,
our Office will not sustain a protest, even if a deficiency in
the procurement is found. Orion Int’l Tech., Inc., B-293256,
Feb. 18, 2004, 2004 CPD para. 118 at 3. (Puglia
Engineering of California, Inc., B-297413; B-297413.2;
B-297413.3, January 20, 2006) (pdf)
One example of how the agency’s limited review may have led to
acceptance of a questionable contingency cost was SCA’s
allowance for the possibility that if sodium pools were
encountered during the removal of residual sodium, a strong
sodium/hydrated sodium hydroxide reaction would occur. SCA
listed the “owner” of this risk as SCA and Framatone ANP, a
proposed subcontractor that would be involved in removing
residual sodium. Although SCA rated the probability of this
occurring as very low, that is, 0 to 20 percent, it recognized
that the cost overrun that would result in the event that it
occurred would total between $7,140,000 and $16,660,000, and the
probable schedule impact would be between 7.3 and 18.2 weeks of
delay. Nevertheless, presumably as the anticipated result of its
proposed mitigation approach, SCA allocated no contingency
allowance either in terms of dollars or weeks of delay. SCA
Revised Proposal, fig. C-21, C-23, C-24. That this result may
not fully reflect the likely risks is supported by the testimony
of the FFTF project director (who was not involved in evaluating
SCA’s contingency allowance in this regard, but was the agency’s
leading technical expert on sodium removal at the hearing), who
answered in the affirmative when asked whether he would be
surprised to learn that the risk analysis in this regard
resulted in zero risk (and thus had no effect on the contingency
allowance0. Tr. 919‑20. While it appears that the agency
concluded that SCA’s method for calculating contingency was
sound, it is clear from the limitations acknowledged by the
agency that it was unable to conclude that SCA’s significantly
lower contingency allowance, and the resulting difference in
evaluated cost, reasonably represented the difference between
the costs that actually would be incurred under SCA’s and FRC’s
proposals. The evaluation in this area therefore was
unreasonable. (EPW Closure Services,
LLC; FFTF Restoration Co., LLC, B-294910; B-294910.2;
B-294910.3; B-294910.4; B-294910.5; B-294910.6; B-294910.7,
January 12, 2005) (pdf)
The agency
performed its price analysis by first establishing a “minimum
objective” price, a “target objective” price, and a “maximum
objective” price, for each of the 355 Lot I CLINs and 194 Lot II
CLINs. AR, Tab 13, Pre-Negotiation Briefing Memorandum, at 5-6,
attach. A. The “minimum objective” price equated to the
determined “Fair Market Price less 5 % to allow for negotiation
flexibility.” Id. at 5. The agency’s “target objective” prices
were “based on the previous procurement prices” adjusted by a
set percentage for inflation and a “learning curve adjustment
for quantity,” and the agency’s “maximum objective” prices
equated to the determined fair market price “with 5% added to
allow for unknown market conditions.” Id. The agency then
identified those CLINs in the offerors’ proposals where the
total prices proposed (unit price multiplied by the estimated
quantity) were at least $7,000 less than the agency’s minimum
objective prices, 50 percent or more below the agency’s maximum
objective prices, and/or “out of line” with the other offerors’
proposed prices. AR, Tab 13, Pre-Negotiation Briefing
Memorandum, at 5. The agency provided each offeror with a
pricing matrix identifying those CLINs where the prices proposed
met the above criteria, and, as mentioned previously, requested
that the offeror “verify that these prices are correct for price
realism.” AR, Tab 14, Negotiation Letters to EHC and Grauch
(Sept. 1, 2004). The agency received proposal revisions from the
offerors, and with regard to Grauch, “was satisfied with the
price realism of [its] proposal[].” AR at 13. EHC challenges the
depth of DLA’s price analysis, arguing that “there is no
discussion in any of [the agency’s] final evaluation documents
regarding the cost realism of Grauch’s offer.” Protester’s
Comments at 12. The protester concludes that the agency “did
nothing to investigate Grauch’s significantly lower prices or to
confirm that Grauch could deliver the requested items at these
prices,” and therefore “failed to conduct a proper price realism
analysis.” Protester’s Supplemental Comments at 10. The
protester notes that Grauch’s proposed prices after negotiations
were “still 32% below [the agency’s] Minimum Objective for Lot I
and 35% below [the agency’s] Minimum Objective for Lot II.”[4]
Id. We find from our review of the contemporaneous record that
the agency had concerns with the low prices proposed by the
offerors for certain CLINs in Lots I and II, and that it handled
these concerns in a reasonable manner. That is, the agency’s
price negotiation memorandum shows that the agency was aware and
accurately calculated the number of CLINs on which Grauch’s and
EHC’s proposed prices fell within the agency’s criteria for
requiring verification for price realism purposes, that the
agency brought these CLINs to the offerors’ attention during
negotiations, and was satisfied with the responses it received.
There is no requirement that the agency conduct a “cost realism”
analysis in evaluating proposals for a fixed-price contract as
asserted by the protester, nor is an agency required to
“investigate” in the context of a price realism analysis whether
Grauch can deliver the items for the prices proposed as required
by the resultant contract.[5] See Citywide Managing Servs. of
Port Washington, Inc., supra, at 6. (Electronic
Hardware Corporation, B-295345, January 28, 2005) (pdf)
Although agencies are required to perform some sort of price or
cost analysis on negotiated contracts to ensure that proposed
prices are fair and reasonable, where, as here, the award of a
fixed-price contract is contemplated, a proposal’s price realism
is not ordinarily considered, since a fixed-price contract
places the risk and responsibility for contract costs and
resulting profit or loss on the contractor. However, an agency
may provide in the solicitation for a price realism analysis for
such purposes as measuring an offeror’s understanding of the
solicitation requirements, or to avoid the risk of poor
performance from a contractor who is forced to provide goods or
services at little or no profit. The depth of an agency’s price
realism analysis is a matter within the sound exercise of the
agency’s discretion. Citywide Managing Servs. of Port
Washington, Inc., B-281287.12, B‑281287.13, Nov. 15, 2000, 2001
CPD para. 6 at 4-5. In reviewing protests challenging price
realism evaluations, our focus is whether the agency acted
reasonably and in a way consistent with the terms of the
solicitation. The protester first argues that under the
solicitation its proposal cannot be rejected as unacceptable
because its price was considered unrealistically low. However,
as indicated, the solicitation expressly provided that "[p]roposals
will be evaluated to determine whether offered prices are
realistic,” and specifically informed offerors that the analysis
would include the distinct queries of whether the prices were
realistic “in relation to the work to be performed, reflect a
clear understanding of the requirements, and are consistent with
other portions of the offeror’s proposal.” RFP at 16.
Accordingly, this is not an instance, such as pointed to by the
protester in Possehn Consulting, B-278759, Jan. 9, 1998, 98-1
CPD para. 10, where the rejection of a proposal because its
pricing was found to be unrealistic was determined to be a
matter of responsibility due to the solicitation’s lack of any
evaluation factor or criterion related to price realism. See
also CSE Constr., B-291268.2, Dec. 16, 2002, 2002 CPD para. 207
at 4-5 (where there is no relevant evaluation criterion
pertaining to price realism or understanding, a determination
that an offeror’s price on a fixed-price contract is too low
generally concerns the offeror’s responsibility). In our view,
given the RFP’s specific provision regarding the performance of
a price realism analysis, as well as the remainder of the RFP’s
terms, the agency could reject a proposal that lacked price
realism, or consider a proposal’s lack of price realism in its
source selection. We have found that the risk of poor
performance when a contractor is forced to provide services at
little or no profit under a fixed-price contract is a legitimate
concern that can be considered under a price realism evaluation.
Ameriko, Inc., B‑277068, Aug. 29, 1997, 97-2 CPD para. 76 at 3;
GEC-Maconi Electronic Sys. Corp., B‑276186, B-276186.2, May 21,
1997, 97-2 CPD para. 23 at 5. Here, the agency reasonably found
IOS’s price to be unrealistic, and because of this, determined
that there was a significant risk that IOS’s performance under
the contract may be so unprofitable that the performance of this
contract--which is considered extremely important to DeCA--would
be adversely affected. Under the circumstances, we find the
agency had a reasonable basis to reject IOS’s proposal. (International
Outsourcing Services, B-295959, LLC, May 25, 2005) (pdf)
Agencies must consider cost to the government in evaluating
proposals, 41 U.S.C. sect. 253a(b)(1)(A), (c)(1)(B) (2000), and
while it is up to the agency to decide upon some appropriate and
reasonable method for the evaluation of offerors’ prices, an
agency may not use an evaluation method that produces a
misleading result. See Bristol-Myers Squibb Co., B-294944.2,
Jan. 18, 2005, 2005 CPD para. 16 at 4; AirTrak Travel et al.,
B-292101 et al., June 30, 2003, 2003 CPD para. 117 at 22. The
method chosen must also include some reasonable basis for
evaluating or comparing the relative costs of proposals, so as
to establish whether one offeror’s proposal would be more or
less costly than another’s. Id.; see FAR sect. 15.405(b)(“the
contracting officer’s primary concern is the overall price the
government will actually pay”). For example, in Health Servs.
Int’l, Inc.; Apex Envtl., Inc., B-247433, B-247433.2, June 5,
1992, 92-1 CPD para. 493, the solicitation contemplated the
award of a fixed-price, indefinite-quantity contract and
offerors’ proposals were required to include hourly rates for
six categories of labor. We sustained a protest challenging the
agency’s price evaluation because it was based solely upon
offerors’ average hourly labor rates, without consideration of
the estimated quantities of each labor category the agency
expected to order, and thereby failed to establish whether one
offeror’s proposal was in fact more or less costly than
another’s. Based on our review of the record here, we
conclude that the Forest Service’s price evaluation, including
the determination that Port-A-Pit’s prices were not fair and
reasonable, was fundamentally flawed because it did not reflect
the actual cost to the government of the offerors’ competing
proposals. In performing the evaluation of offerors’ prices, the
contracting officer did not utilize any quantity estimates for
the meals, mileage, and handwashing unit items, but instead
limited her evaluation to offerors’ unit prices. The contracting
officer determined that while Port-A-Pit’s unit prices for meals
and handwashing units were not objectionable, its unit price for
mileage was not fair and reasonable, in comparison to both the
government estimate and the average price of other offerors. AR,
Tab 15, TEB Best Value Analysis Report, at 1, 4-5. Based on the
contracting officer’s determination that Port-A-Pit’s price for
mileage was not fair and reasonable, the Forest Service found
Port-A-Pit ineligible for contract award. Id. at 6; Contracting
Officer’s Statement, July 18, 2005, at 11 (“I made the
determination based on price analysis that [Port-A-Pit’s]
mileage price was not fair and reasonable and could not form the
basis for award”). The record reflects that mileage is by no
means the largest component of cost to the government. Rather,
the parties agree that meals are the primary cost for the
services to be provided under the contract.[10] Protest, June
21, 2005, at 8, exh. 1; AR, Tab 15, TEB Best Value Analysis
Report, at 1. For example, the record indicates that under a
predecessor contract, Port-A-Pit provided a total of [DELETED]
meals and drove a total of [DELETED] miles in response to a fire
in Ash, Arizona.[11] Protest, June 21, 2005, exh. 1, at 1. Using
the unit prices proposed by Port-A-Pit here, meal costs would
have been approximately $39,644, while mileage costs, in
comparison, would have been approximately $17,100. Similarly,
the record indicates that with regard to a fire in Jimtown,
Montana, meal costs to the government would have been
approximately $69,285 while mileage costs would have been
approximately $35,600.[13] In light of the substantial
difference in the relative costs for meals and mileage, the
agency’s price evaluation, to the extent that it considered only
offerors’ unit prices, failed to reflect the likely actual cost
to the government of the offerors’ approaches. (R&G
Food Service, Inc., d/b/a Port-A-Pit Catering, B-296435.4;
B-296435.9, September 15, 2005) (pdf)
In sum, we conclude that, in light of DCAA’s inability to
develop evaluated direct labor rates based on SGT’s cost
proposal and staffing approach, the agency’s experience with
SES’s costs under the incumbent proposal as detailed in the
September 2003 DCAA audit, and in the absence of other data in
SGT’s proposal that would address the agency’s concerns, the
agency’s cost realism analysis was reasonable. The adjustments
to both the SCA-exempt and non-exempt rates and the use of the
September 2003 audited rates as the most recently evaluated
rates were reasonable in light of the information available to
the agency. This aspect of the protest is denied. (SGT,
Inc., B-294722.4, July 28, 2005) (pdf)
We find that GSA's pricing analysis was unreasonable because the
comparison of offerors' "discount rates" did not reflect the
actual proposed prices or cost to the government for these
services. While Maximus's warehouse price may have included
additional services not offered by Liquidity, the fact remains
that the price to the government for Maximus's warehouse space
will be higher than the price for an equivalent amount of
Liquidity warehouse space, and the price evaluation did not
reflect this difference in cost to the government. (In this
regard, the agency did not find that the additional warehouse
services allegedly offered by Maximus would result in
quantifiable savings in costs that the government would
otherwise incur.) Furthermore, we find that the agency's
rationale for reducing Liquidity's price advantage for warehouse
services is unsupported by the contemporaneous record. While the
agency explains that the reduction in discount rate from
[redacted] percent to [redacted] percent was due to differences
in proposal approaches, the contemporaneous record does not
demonstrate that the agency evaluated the asserted differences
in warehousing services. Indeed, the agency's current assertion
that it did so is inconsistent with the remainder of its pricing
analysis, which did not take into account any differences in
offerors' proposal approaches under any of the other service
areas considered in the price evaluation. For example,
Liquidity's price proposal states that many of its warehousing
services are included with its value-added-services pricing, yet
GSA did not make any adjustments to the value-added-services
pricing to take into account this proposal difference, as it did
with warehousing. In fact, we note that the agency asserts, in
response to other protest challenges to the price evaluation,
that differences in proposal approaches were to be evaluated
only under the technical approach factor, and not the price
factor. See , e.g. , Agency Report, July 2, 2004, at 3. We also
find that GSA erred in calculating its discount rate for
transportation services. Although it may have been reasonable to
assume that most of the transportation provided would be short
hauls at less-than-full truckloads, there is no basis for
excluding all of the long distances from consideration, as if no
long haul services would be used. The agency does not claim that
no long haul services would be used, the RFP does not specify
that long hauls would not be required or considered in the
evaluation, and, consistent with the RFP, both offerors proposed
prices for both long and short hauls. On these facts, we find
that the agency must consider in its price evaluation all of the
costs of long haul transportation that it reasonably expects to
use during contract performance, and, moreover, should disclose
to offerors the basis for its evaluation of these costs prior to
proposal submission. (Liquidity
Services, Inc., B-294053, August 18, 2004) (pdf)
This problem with the way the IGSE was developed is significant
because the IGSE was used in what appears to be a mechanical way
in the cost realism evaluation. A reasonably derived estimate of
labor hours and material costs can provide an objective standard
against which the realism of proposed costs can be measured. IT
Facility Servs.-Joint Venture, B-285841, Oct. 17, 2000, 2000 CPD
paragraph 177 at 6-7; Theta Eng'g, Inc., B-271065, B-271065.2,
June 12, 1996, 96-2 CPD paragraph 76 at 6. However, an agency
may not mechanically apply that estimate to determine the most
probable costs associated with proposals, without regard to the
individual proposal's technical approach. The Jonathan Corp.;
Metro Mach. Corp. , B-251698.3, B-251698.4, May 17, 1993, 93-2
CPD paragraph 174 at 11; Kinton, Inc. , B-228260.2, Feb. 5,
1988, 88-1 CPD paragraph 112 at 4. This is so because in some
instances an estimate has limited applicability to a particular
proposal due to, for example, the skill of the labor force or
innovative work methods proposed. In those cases, any rigid
reliance on the government estimate could have the effect of
arbitrarily and unfairly penalizing (or rewarding) one firm and
depriving the government of the benefit available from the
different approaches of the various offerors. Accordingly, in
order to undertake a proper cost realism evaluation, the agency
must independently analyze the realism of an offeror's proposed
costs based upon its particular approach, personnel, and other
circumstances. The Jonathan Corp.; Metro Mach. Corp. , supra .
Here, the record does not indicate that the agency engaged in an
absolutely rigid application of the IGSE to the offerors'
proposals. There do appear to be instances where the agency
accepted proposed staffing for a particular function or labor
category that was less than that reflected in the IGSE, and in
other instances, the agency made adjustments to an offeror's
proposed staffing that put the probable staffing associated with
the proposal at a level between that set forth in the proposal
and that provided by the agency in its IGSE. Nevertheless, the
record also reflects that in the vast majority of instances
where an offeror proposed a staffing level that differed from
the IGSE, the staffing level was adjusted during the cost
evaluation to the IGSE staffing level, with the primary
documented reason by the agency being that the proposal did not
provide "sufficient rationale" for the proposed staffing, with
little further elaboration. See AR, Tab 43, Honeywell Cost
Realism Rationale; at 2; Tab 47, Wyle Cost Realism Rationale, at
2; Tab 49, Sverdrup Cost Realism Rationale, at 2. As the
protesters point out, the consistency of the agency's approach
in this regard is readily apparent when the offerors' varying
proposed staffing levels are compared to their staffing levels
as adjusted by the agency and the IGSE. That is, although the
agency found "that there was a wide range of disparate
approaches from the offerors," with the five offerors proposing
staffing levels that varied considerably ( i.e. , 198, 241, 248,
260, and 287 FTEs), the SEB adjusted the staffing levels
proposed by all five offerors to within 4 FTEs of the IGSE of
293. Agency's Post-Hearing Comments at 10; exh. B, Cost Proposal
Evaluation Results (July 22, 2003). This, along with the sparse
evaluation documentation, suggests that the IGSE was used in a
mechanical way in the cost realism evaluation, notwithstanding
the encouragement in the RFP for proposing innovative
approaches. That the agency used the IGSE in the cost realism
evaluation in a mechanical way is supported by other evidence in
the record. For example, before this issue became the gravamen
of the protests, the agency stated in its initial report on the
protests that "[u]niformly, NASA base lined [the offerors'] FTEs
against the government staffing estimate." AR at 22, 25.
Moreover, given the testimony of the SEB member that the
Marshall estimate was essentially inflexible and any proposed
staffing plan that did not comport precisely with the Marshall
estimate would be "[c]ompletely unacceptable," the fact that
variances from the estimate were not tolerated was
understandable. [9] Tr. at 78, 80-81, 100, 107. Of most
significance in showing that the IGSE was used in a mechanical
way is the fact that Honeywell's proposed staffing was
characterized as "appropriate" during the evaluation of its
proposal under the technical performance subfactor, but was then
adjusted upwards by 43 FTEs to within 2 FTEs of the IGSE during
the cost realism evaluation. In sum, we find the agency's cost
realism evaluation unreasonable. (Honeywell
Technology Solutions, Inc.; Wyle Laboratories, Inc.,
B-292354; B-292388, September 2, 2003) (pdf)
The realism analysis here was unobjectionable. The Army
evaluated Sunny Point's proposal and determined that the
proposed labor mix and hours were consistent with its technical
proposal and acceptable to perform the contract. SSD at 3. The
Army also reviewed Sunny Point's price proposal and found that
it was complete and adequate, Price Analysis Worksheet at 1, and
also determined that it complied with the Service Contract Act
wage determination with respect to both rates and fringe
benefits. Price Analysis Report at 1. The Army noted that Sunny
Point's price was lower than the government estimate, but
attributed this to the fact that Sunny Point proposed a labor
mix and staffing level different--but acceptable to
perform--than that on which the government estimate had been
based. SSD at 3. The agency also concluded that the government
estimate was overstated. Id. Given this analysis, we have no
basis to question the Army's realism evaluation. (Satellite
Services, Inc., B-295866; B-295866.2, April 20, 2005) (pdf)
In contrast, where, as here, with regard to a BPA contemplating
fixed-price or fixedrate task orders to be issued against the
vendors' GSA FSS contracts, the "realism" of vendor's proposed
pricing is not ordinarily considered because the fixed-price
contracting vehicle places the risk and responsibility for
contract costs and ensuing profit or loss on the contractor. See
Camber Corp. , B-293930; B293930.2, July 7, 2004, 2004 CPD 144
at4; OMNIPLEX World Servs. Corp. ; B291105, Nov. 6, 2002, 2002
CPD 199 at 9. However, because there is a risk of poor
performance in certain circumstances, such as where a contractor
fails to obtain and keep qualified personnel, an agency may, in
its discretion, provide for a price realism analysis in a
solicitation that contemplates the issuance of a BPA against the
vendors' GSA FSS contracts. OMNIPLEX World Servs. Corp. , supra
. Here, the methodology used by the agency in evaluating
quotations under the pricing structure criterion was consistent
with that provided in part 15 of the FAR for the performance of
price realism analyses--the comparison of proposed prices, in
the form of loaded labor rates, with prior contract prices for
the same or similar services and with an independent government
cost estimate. See Acepex Mgmt. Corp. , supra , at8; FAR
15.404-1(b). As noted, the agency's conclusion that S3's
quotation warranted a "moderate risk" rating under the pricing
structure criterion is not only consistent with the RFP
evaluation scheme but is reasonably supported by the record. As
indicated, the agency's evaluation of quotations under the
pricing structure criterion was relatively detailed, and
included an analysis of the labor rate quoted for each of the
labor categories set forth in S3's quotation. S3's quoted rates
in some instances were substantially lower, and overall were
slightly lower, than the agency's calculated historical rates
for the same positions, and as such, we believe that the agency
reasonably determined that there was "some doubt that [S3's]
pricing structure will support the [agency's] requirements with
highly qualified personnel." AR, Tab I, Source Selection Report,
at16. S3 has not showed that the loaded rates reflected in the
historical averages were erroneous, unreasonable or unrealistic
or that the comparison of S3's loaded rates to the historical
averages was flawed. (Systems,
Studies, and Simulation, Inc., B-295579, March 28, 2005) (pdf)
The
evaluated prices as reported to the SSA improperly failed to
reflect a common number of sites to be serviced. Treasury
reports that the solicitation attachment listing 1,042 Treasury
sites for which service was required included a number of
errors. Second Agency Report at20. As a result, and as
recognized in Treasury's price evaluation reports, offerors'
MDOs were based on different total numbers of sites to be
served, as well as different numbers of high bandwidth Category
1, lesser bandwidth Category 2, and least bandwidth Category 3
sites, as follows:
| |
Category 1
|
Category 2
|
Category 3
|
Total |
|
[DELETED] |
70 |
63 |
862 |
995 |
|
[DELETED] |
73 |
66 |
916 |
1,055 |
|
[DELETED] |
63 |
76 |
857 |
996 |
|
[DELETED] |
58 |
83 |
855 |
996 |
|
[DELETED] |
61 |
77 |
828 |
966 |
|
[DELETED] |
54 |
59 |
|