Next, L-3 argues that the agency's discussions were inadequate
because they failed to advise the protester that it had not
provided sufficient detail regarding the asset identification
information to be recorded and stored in its configuration
management database. In this connection, the SOW instructed
offerors to "provide, configure, populate, and manage a
Configuration Management Database (CMDB)" identifying all assets
supporting NRC services. The SOW further instructed that
offerors should
Minimize the discrepancy between
assets/inventory recorded in the CMDB and actual NRC
assets/inventory. This includes ensuring minimally the
following information for each unit:
-
Asset Tag
-
Serial Number
-
User Location (PCs and related
peripherals only)
-
Configuration (OS, loaded
software, etc.)
-
Asset Status
-
Responsible Owner
-
Host Name (Servers only)
-
IP Address (Servers only)
-
Business Function/Application
(Servers only)
-
Business Owner (Servers only)
-
Make/Model
-
Physical Location (Non-mobile
units)
-
Warranty Info/Maintenance
Certificate Number (Servers only)
SOW sect. C.5.2.3.3.2(5).
During the initial round of discussions, the agency instructed
the protester to address the requirement to "minimize the
discrepancy between assets/inventory recorded in CMDB and actual
NRC assets/inventory. (PSOW C.5.2.3.3.2(5), p. 61)," since L-3
had not addressed this requirement in its initial proposal. AR,
Tab 11c, Discussion Questions for L-3 at 1. In its response, L-3
failed to describe how it would ensure that the specific
information identified in SOW sect. C.5.2.3.3.2(5) (i.e., asset
tag, serial number, etc.) was recorded in the CMDB. In his
source selection determination, the SSO found the lack of detail
regarding the information concerning assets to be recorded and
stored in the protester's CMDB to be a "worrisome" aspect of
L-3's proposal.
The protester argues that the agency's discussion question
failed to furnish it with adequate notice of the weakness in its
proposal because it cited only the first sentence of SOW sect.
C.5.2.3.3.2(5)--that is, according to the protester, while the
agency notified L-3 that it had failed to address the
requirement to minimize the discrepancy between assets/inventory
recorded in the CMDB and actual NRC assets/inventory, the agency
did not also indicate that its failure to address the recording
of the asset tag, serial number, etc., was also considered to be
a weakness.
We find the protester's argument to be without merit. Agencies
are not required to "spoon-feed" offerors during discussions,
but rather need only lead offerors into the areas of their
proposals that require amplification or revision. Martin Elecs.,
Inc.; AMTEC Corp., B-404197 et al., Jan. 19, 2011, 2011 CPD para.
25 at 6. The agency's discussion question here specifically
informed the protester that it had not adequately addressed the
requirement set forth in SOW sect. C.5.2.3.3.2(5) to minimize
the discrepancy between actual and recorded assets/inventory.
Moreover, the clear terms of SOW sect. C.5.2.3.3.2(5) furnished
notice that minimizing the discrepancy required that, at a
minimum, information such as the asset tag and serial number be
recorded in the CMDB. In our view, the foregoing was more than
sufficient to lead the protester into the area of its proposal
that required amplification. Having sufficiently led L-3 to the
area of concern in the first round of discussions, NRC was not
required to raise the matter again in any subsequent round of
discussions, even where it continued to be considered a concern
by the agency. U.S. Filter Operating Serv's., Inc., B-293215,
Feb. 10, 2004, 2004 CPD para. 64 at 3. (L-3
STRATIS, B-404865, June 8, 2011) (pdf)
ACS protests the adequacy of the agency's discussions in
connection with a single aspect of its proposed solution to the
requirement. ACS, the incumbent contractor, has been providing
the agency's requirements using a highly customized software
product developed for DOL, and [deleted]. In its initial
proposal, ACS offered to transition its software product from
the [deleted] it currently uses to an [deleted] solution
(referred to in the record as [deleted] or [deleted]), and to do
so during performance under its predecessor contract, so that
ACS could offer the [deleted] solution to the agency for the
solicited requirement. The protester maintains that the
[deleted] solution would offer improved performance and,
potentially, lower cost over the life of the solicited
requirement.
After evaluating ACS's initial proposal and advising the firm
that implementation of the [deleted] solution under its
predecessor contract was not acceptable, the agency subsequently
advised the protester during discussions that its proposal was
based on an incorrect assumption, specifically, the assumption
that the agency would allow ACS to migrate its existing system
to an [deleted] solution during performance of the predecessor
contract. The agency therefore advised ACS that "'[b]ecause [ACS's]
assumption is incorrect, the Offeror may wish to reconsider the
effect of this incorrect assumption and revise its proposal
accordingly."' AR, exh. C-5, Initial Ratings, Factor 1,
deficiency.
In response to the agency's initial discussion question, ACS
eliminated the proposed migration from its current [deleted]
system to its originally proposed [deleted] solution, stating as
follows:
ACS understands, respects, and
will attend to the DOL's remarks regarding the [deleted]
Migration referenced in our original proposal. In response to
DOL's concerns, ACS has halted the [deleted] Migration and
removed [deleted] from the revised proposal. Instead, ACS will
deliver a . . . solution based upon the proven [deleted].
AR, exh. J-1-1, File 6, at 2.
In the source selection decision,
the agency identified a risk associated with the firm's use of
its existing [deleted] system. Specifically, the agency noted
that, because ACS was proposing legacy technology (i.e., its
[deleted] system), support for the system might end, and the
expertise required for the [deleted] system and the [deleted]
used by ACS in its [deleted] system solution could become scarce
over time. Source Selection Decision Document, at 9.
ACS asserts that the agency never identified this specific risk
during discussions, despite the fact that the agency engaged in
several additional rounds of discussions after ACS proposed
eliminating the [deleted] solution and using its [deleted]
solution instead. According to the protester, the agency's
failure in this regard amounted to inadequate discussions
because this risk constituted a new deficiency in its proposal,
and the agency was obliged to discuss it with ACS.
We have no basis to object to the adequacy of discussions here.
Discussions are adequate where offerors are advised of the
weaknesses, excesses or deficiencies in their proposals. US
Filter Operating Serv's., Inc., B-293215, Feb. 10, 2004, 2004
CPD para. 64 at 3. While discussions should be as specific as
practicable, there is no requirement that they be
all-encompassing or extremely specific in describing the
agency's concerns; rather, the legal requirement is that they
generally lead the offerors into the areas of their proposals
that require amplification or correction, without being
misleading. Id. Moreover, where an agency has advised an offeror
of its concern, there is no requirement that it raise the issue
again in subsequent rounds of discussions, even where the issue
continues to be a concern to the agency. Id.
Subsequent to the written discussions described above, the
agency and ACS engaged in oral discussions, during which ACS
again represented that it intended to use its [deleted] solution
instead of the [deleted] solution originally proposed.
Specifically, the protester's representative stated:
ACS has withdrawn and completely
removed any references to our technology refresh initiative.
We referred to this previously as [deleted] migration . . . .
We intended to have this refresh completed in our current
contract year. And quite frankly, cost . . . lower cost
infrastructure was the driver behind that . . . . We decided
not to put it in our current proposal because we believe that
implementing both the enhancements [to the [deleted] system]
to meet the additional requirements and the technology refresh
quite honestly compounded the complexity and introduced risk.
Video 1, at 13:00-13:49. ACS's
representative also specifically recognized during those oral
discussions that its current [deleted] solution, while generally
meeting the solicitation requirements, nevertheless was, in his
words, "'short of state-of-the-art."' Id. at 40:15.
The protester's representatives went on to suggest that, once
its [deleted] solution was fully implemented and certified, ACS
intended again to propose to the agency migration from the
[deleted] solution to the [deleted] solution. Video 1, at
41:55-42:22. In response to that suggestion, the agency's
technical evaluation panel chairman specifically cautioned the
protester that it would not receive credit for any proposed
migration from one [deleted] to another, unless such a migration
was included in the firm's proposal:
[A]ny tech value enhancement . . .
would probably, may, add value to the best value decision that
we have to make. But, what you just stated about doing this
sometime in the future, we can't consider that unless it's
part of the proposal.
Video 1, at 42:31-42:49. In
response, the protester's representative specifically
acknowledged that he understood, but that the firm had made a
decision--based on its assessment of implementation risk--to
forego offering the migration from one [deleted] to another as
part of its proposal. Id.
In summary, the record shows that ACS understood that its
proposed [deleted] solution was "'short of state-of-the-art,"'
but that it had made a business decision to forego
implementation of the state of the art [deleted] solution
because of risks inherent in implementing any migration. The
record further shows that ACS understood that the agency would
not give it credit in the evaluation and source selection
decision based merely on a suggestion that the migration could
take place sometime in the future. While the protester is
correct that the agency did not expressly identify the specific
risk it ultimately articulated in its source selection decision
during discussions, we think it nonetheless adequately led the
protester into that area of its proposal, and made clear to the
protester that the consequences of not including the [deleted]
solution in its proposal would affect the agency's best value
deliberations. In response, the protester clearly decided, on
the basis of its business judgment, that not including the
[deleted] solution in its proposal was its best--least
risky--proposal strategy. We therefore conclude that the
agency's discussions with the protester in this area were
adequate. Simply stated, an agency need not identify every
conceivable consequence of an offeror's business decision in
order to discharge its duty to engage in meaningful discussions.
(ACS Federal Solutions, LLC,
B-404129, January 7, 2011) (pdf)
ITW complains that it was misled
during discussions. Specifically, the protester maintains that
the Navy improperly advised it during discussions that its
prices for two contract line item numbers (CLIN) were "somewhat
lower" than the independent government estimate (IGE). ITW
states that, in reliance on this notification, it increased its
final price for these two CLINS. ITW also maintains that it was
required to review its final pricing for all CLINs as result of
the Navy's comments with respect to these two CLINs. Protester's
Comments at 3.
When discussions are conducted, they must at a minimum identify
deficiencies and significant weaknesses in each
competitive-range offeror's proposal. Federal Acquisition
Regulation (FAR) sect. 15.306(d)(3); Multimax, Inc., et al.,
B-298249.6 et al., Oct. 24, 2006, 2006 CPD para. 165 at 12.
Discussions must be "meaningful," that is, sufficiently detailed
so as to lead an offeror into the areas of its proposal
requiring amplification or revision. Smiths Detection, Inc.,
B-298838, B-298838.2, Dec. 22, 2006, 2007 CPD para. 5 at 12. An
agency may not mislead an offeror--through the framing of a
discussion question or a response to a question--into responding
in a manner that does not address the agency's concerns, or
misinform the offeror concerning a problem with its proposal or
about the government's requirements. Academy Facilities
Mgmt.--Advisory Opinion, B-401094.3, May 21, 2009, 2009 CPD para.
139 at 6; Multimax, Inc., et al., supra. In the context of
discussions relating to cost or price, agencies may not coerce
or mislead an offeror during discussions into raising its
prices. Academy Facilities Mgmt.--Advisory Opinion, supra.
Here in its discussions with ITW, the Navy identified a number
of weaknesses and deficiencies in the protester's initial
proposal; these weaknesses and deficiencies were identified in
25 evaluation notices (ENs). AR at 3. The agency's concerns with
ITW's proposed prices were not discussed in any of the ENs, but
were communicated to ITW in the letter transmitting the ENs.[3]
With respect to the pricing for the two CLINs (for which the
agency was concerned the pricing was low), the agency informed
ITW as follows:
[Y]ou are advised to carefully
review the price proposal for any misunderstanding of the
requirements, as several proposed . . . CLINs appear out of
line with the Government estimate. . . . [B]ased on market
research . . . CLINs . . . appear to be priced somewhat lower
than the government estimate; therefore you are advised to
carefully review your price proposal for any misunderstanding
of the requirements.
AR, Tab 2, Navy Discussions with
ITW, at 1.
In its FPR, ITW raised its prices for these two CLINs by
approximately $32,000, and lowered its overall price by more
than $1 million. AR, Tab 11, Navy Analysis of ITW's Prices, at
3.
We do not find that the Navy's discussions with ITW were
misleading. The record shows that the Navy found that in these
two particular instances ITW's prices appeared understated in
comparison to the IGE. The agency accurately conveyed its
concerns to ITW in discussions. ITW does not dispute that its
pricing for these two CLINs was below the IGE. Rather, ITW
essentially argues that the Navy "implie[d]" that unless the
offeror raised its prices it would be removed from the
competition and/or downgraded regarding its ability to perform
the work at the proposed price. Protest, Sept. 14, 2010, at 1;
Protest, Oct. 23, 2010, at 3 ("how else would ITW be expected to
respond other than increase [its] pricing?"). We find no merit
to this argument. The agency simply communicated to ITW that its
CLIN pricing appeared lower than that of the IGE in two
particular regards, and asked the protester to review its
pricing. This did not compel ITW to take any particular action,
but left to the firm's business judgment whether it should raise
its prices or explain the prices earlier submitted. (ITW
Military GSE, B-403866.3, December 7, 2010) (pdf)
CIGNA points out that while the
agency conducted three rounds of discussions with the
competitive range offerors, the only issue regarding CIGNA's
approach to printing and postage costs raised by the agency
concerned CIGNA's initial failure "to include HH&H claims volume
in calculating the proposed costs for Internet/Communications
and Output Mail Postage," which CIGNA corrected in its FPR.
Protester's Comments at 11; see AR, Tab 17, CIGNA Discussion
Questions and Responses (Sept. 30, 2008), at 101. As noted by
CIGNA, the record shows that the agency did not raise any other
concerns during discussions regarding CIGNA's proposed printing
and postage costs.
The Federal Acquisition Regulation (FAR) requires that where an
agency undertakes discussions with offerors, the contracting
officer shall discuss with each firm being considered for award
deficiencies and significant weaknesses identified in the firm's
proposal. FAR sect. 15.306(d)(3). Discussions must be
meaningful, equitable, and not misleading. Cygnus Corp., Inc.,
B-292649.3; B-292649.4, Dec. 30, 2003, 2004 CPD para. 162 at 4;
Lockheed Martin Corp., B-293679, May 27, 2004 CPD para. 115 at
7. Discussions cannot be meaningful unless they lead an offeror
into those weaknesses, excesses or deficiencies in its proposal
that must be addressed in order for the proposal to have a
reasonable chance of being selected for contract award. Cygnus
Corp., Inc., supra; Lockheed Martin Corp., supra.
The agency does not argue that it raised its concerns regarding
CIGNA's proposed printing and postage costs during its
discussions with the protester, acknowledging that, as reflected
in the record, the "discrepancy" between the printing and
postage costs proposed by the other competitive range offerors
and CIGNA "was only identified after the submission of FPRs,
when each offeror's proposed costs were compared with one
another." AR at 45 n.7; Agency Supp. Report at 11. Rather, the
agency contends that its "cost adjustment to [CIGNA's] proposal
was minor," in that "it increased [CIGNA's] total evaluated cost
by [DELETED]% and reduced the cost difference between [CIGNA]
and [Highmark] from [DELETED]% to [DELETED]%." Agency Supp.
Report at 17. The agency continues here by arguing that because
the adjustment was "minor," the "adjustment was not the
equivalent of a 'significant weakness,' nor did it concern 'an
aspect[] of the offeror's proposal that could, in the opinion of
the contracting officer, be altered or explained to enhance
materially the proposal's potential for award," and thus the
agency's concerns here did not have to be raised with CIGNA
during discussions. Agency Supp. Report at 17 (quoting FAR sect.
15.306(d)(3)).
We disagree. In this regard, we first reject the agency's
contention that its concerns with CIGNA's proposed printing and
postage costs, and the resultant upward adjustment to CIGNA's
proposed costs, were "minor" or otherwise concerned matters that
did not have to be raised with CIGNA in order for discussions to
be meaningful. As set forth above, the agency's upward
adjustment constituted, by the agency's own calculations, an
$[DELETED] or [DELETED] percent increase to CIGNA's proposed
costs, which caused the cost advantage associated with CIGNA's
proposal to be reduced from [DELETED] percent to [DELETED]
percent. We simply fail to see, and do not believe that the
agency has adequately explained, why an upward adjustment to
CIGNA's proposed costs of [DELETED] percent can reasonably be
characterized as "minor" or otherwise inconsequential under the
circumstances here. Additionally, we note that the agency has
not pointed to anything in the contemporaneous record of the
evaluation and source selection stating or otherwise providing
that the failure to raise this issue with CIGNA during
discussions was due to the agency's view that the cost
adjustment was "minor." As such, we give little weight to the
agency's assertions crafted in the heat of litigation that the
agency's upward cost adjustment to CIGNA's proposal would have
been and should be considered "minor," and thus was not required
to be raised during discussions. Novex Enters., B-297660;
B-297660.2, Mar. 6, 2006, 2006 CPD para. 51 at 4; Boeing
Sikorsky Aircraft Support, B-277263.2, B‑277263.3, Sept. 29,
1997, 97-2 CPD para. 91 at 15. In the context of the trade-off
actually made here, we cannot conclude that this adjustment was
"minor."
Although the agency correctly points out that an agency has no
duty to reopen discussions to allow an offeror to address
proposal defects or significant weaknesses first introduced in
the offeror's response to discussions or in a post-discussion
proposal revision, Honeywell Tech. Solutions, Inc., B-400771;
B-400771.2, Jan. 27, 2009, 2009 CPD para. 49 at 10, such was not
the case here. That is, the agency does not claim, and there is
nothing in the record to indicate, that the discrepancy between
CIGNA's proposed printing and postage costs and the other
offerors' proposed printing and postage costs was different in
any material way between the offerors' initial proposals and
FPRs. In other words, the aspect of CIGNA's cost proposal that
caused the agency concern was present in CIGNA's initial
proposal. The fact that the agency did not realize until after
discussions had concluded and the agency had received FPRs that
CIGNA's proposed printing and mailing costs were substantially
lower than the costs proposed for these same services by the
other offerors, and thus, in the agency's view, were
understated, does not relieve the agency of its obligation to
conduct meaningful discussions. Al Long Ford, B-297807, Apr. 12,
2006, 2006 CPD para. 68 at 8. Where, as here, an agency, after
discussions are completed, identifies a concern pertaining to
the proposal as it was prior to discussions that would have had
to be raised if it had been identified before discussions were
held, the agency is required to reopen discussions in order to
raise its concern with the relevant offeror. Id.
(Sections deleted)
In sum, we find that the agency's
concerns with CIGNA's proposed printing and postage costs should
have been raised with CIGNA during discussions in order for
discussions to have been meaningful, and sustain the protest on
this basis. (CIGNA Government
Services, LLC, B-401062.2; B-401062.3, May 6, 2009) (pdf)
AMEC argues that the agency's discussions regarding the weakness
identified in its proposal under factor 3, preliminary project
schedule, were not meaningful because they did not disclose the
true nature of the agency's concern regarding its proposed use
of the Microsoft Project software. AMEC also contends that the
agency failed to properly consider as part of its technical
evaluation under factor 2, particular project execution
strategies, the fact that the seed project site has been
designated as a wetlands area, as disclosed by AMEC during its
discussions with the agency.
The record reflects that the agency's discussions with AMEC with
respect to factor 3 were flawed. It is a fundamental precept of
negotiated procurements that discussions, when conducted, must
be meaningful, equitable, and not misleading. AT&T Corp.,
B-299542.3, B-299542.4, Nov. 16, 2007, 2008 CPD para. 65 at 6.
An agency may not mislead an offeror‑‑through the framing of a
discussion question or a response to a question--into responding
in a manner that does not address the agency's concerns, or
misinform the offeror concerning a problem with its proposal or
about the government's requirements. MCT JV, B-311245.2,
B-311245.4, May 16, 2008, 2008 CPD para. 121 at 15-16; Multimax,
Inc., et al., B-298249.6 et al., Oct. 24, 2006, 2006 CPD
para.165 at 12; Metro Mach. Corp., B‑281872 et al., Apr. 22,
1999, 99-1 CPD para. 101 at 6.
Here, as noted above, the agency's technical evaluation team
identified a weakness in AMEC's technical proposal based on its
use of the software program Microsoft Project, which the agency
concluded was "not the most applicable for managing the
[design/build] process or construction projects . . . lacks the
analytical capabilities of other construction oriented software
. . . and may adversely impact the overall management and
reporting effort." AR, Tab 15, Technical Evaluation, at 000485.
In its discussions with AMEC, the agency's questions, however,
focused on specific features of the Microsoft Project software,
in particular, its ability to manage schedule "float." While
AMEC was able to satisfactorily address the agency's specific
questions in this regard, the record reflects that the agency
continued to fault AMEC for proposing Microsoft Project as
adversely impacting the overall management and reporting effort
of the project, and that it was the presence of this weakness
which prevented AMEC from achieving a higher rating under factor
3, therefore materially affecting the agency's technical
evaluation of AMEC's proposal. In this regard, the record
reflects the agency's view that AMEC's proposal had several
strengths under factor 3 and no other weaknesses, but that,
based on the risks associated with its software selection, AMEC
was not entitled to a higher technical rating. AR, Tab 19,
Technical Evaluation Report, at 000584. By being asked only to
address specific questions regarding the particular features of
Microsoft Project, AMEC could not have reasonably understood the
true nature of the agency's broader concerns about the use of
Microsoft Project. As a consequence, the agency's discussions
were materially misleading, thereby depriving AMEC of an
opportunity to address the agency's concern regarding the use of
Microsoft Project in the management of the seed project.
The agency raises several arguments in defense of the adequacy
of discussions, none of which alters our conclusion that its
discussions with AMEC were fundamentally flawed. Specifically,
the agency contends that, pursuant to FAR sect. 15.306(d)(3), it
was not required to discuss its general concerns regarding
AMEC's use of Microsoft Project since the weakness was not
"significant," and it was not identified as a deficiency. In
this regard, the agency suggests that it did not consider AMEC's
use of Microsoft Project to be an unacceptable approach since
the technical evaluation team determined that it had the
"minimum acceptable level of scheduling capabilities." AR, Tab
15, Technical Evaluation, at 000485. Moreover, the agency argues
that identifying the use of Microsoft Project as a weakness
would have been inappropriate since it would have been
tantamount to directing AMEC to implement a particular technical
approach and thereby imposing an undisclosed requirement.
While it is true that agencies are only required to address
"significant" weaknesses and deficiencies during discussions,
FAR sect. 15.306(d)(3) further indicates that these are the
"minimum" areas for discussion. The record reveals that the
agency went well beyond these minimum requirements during its
discussions with the eight firms in the phase II competition. In
this regard, the record reflects that the agency identified
nearly every weakness, in most instances verbatim, from the
technical evaluation findings, without regard to whether the
weakness was considered "significant" or whether the weakness
was associated with an "unacceptable" approach. By way of
example, in its discussions with one of the awardees, the agency
indicated that it considered the offeror's use of soil-supported
ground slabs to be "acceptable," yet the agency advised the
offeror that its proposed approach was considered "to be more
prone to long term settlement issues." AR, Tab 16, Agency's
Discussion Questions, at 000572. Given the agency's decision to
hold broad discussions with all firms, which went well beyond
the FAR's minimum requirements, it was incumbent on the agency
to do so with all offerors equally, and it may not now defend
its failure to have apprised AMEC of a perceived weakness in
AMEC's proposal based on the FAR's minimum discussion
requirements. See also, FAR sect. 15.306(e) (an agency shall not
engage in exchanges that "favors one offeror over another.")
In addition, we find the agency's concerns about directing AMEC
toward a particular technical approach to be misplaced. Had the
agency simply identified to AMEC the perceived risks associated
with AMEC's proposed software, AMEC would then have been in a
position to develop an appropriate response, which could have
ranged from continuing to propose the software notwithstanding
the associated risk, justifying its decision to the agency, or
proposing to use a different software package, any of which
could have addressed the agency's concerns. While there might
have been tradeoffs associated with these various options, AMEC
should have been allowed to make such a decision based on an
understanding of the true nature of the agency's concerns
regarding its technical proposal.
We also find that the agency's consideration of the wetlands
issue under evaluation factor 2 was improper. AMEC argues that
it was the only offeror to have identified the project site as a
potential wetland and that the agency failed to reasonably
consider this fact in its evaluation of the other offerors'
proposals. As noted above, for factor 2, particular project
execution strategies, offerors were required to address project
site specific conditions at Cape May, New Jersey, to include
"environmental, and complications related to doing work in the
New Jersey area." RFP at 82. This provision essentially required
offerors to perform due diligence regarding the nature of the
agency's requirements and to incorporate their findings in their
proposals.
In its initial proposal, AMEC
advised the agency that the project site "may be classified as
wetlands in accordance with State of New Jersey standards," and
went on to address the potential wetlands designation as an
aspect of the permitting process, which was incorporated in
AMEC's project schedule. AMEC Proposal at 000686-000688. The
record indicates that the other offerors did not specifically
identify this potential concern.
During discussions, the agency asked AMEC to clarify its wetland
reference and to identify "information which would alter the
conclusion that the site is not in a designated wetland area."
AR, Tab 17, Discussion Questions, at 000566. In its response,
AMEC provided the agency with publicly available information
contained in the New Jersey Department of Environmental
Protection's iMap-NJ system, which specifically identified the
project site as a wetland, and provided the basis for AMEC's
belief that there was a need for the wetland issue to be
addressed with the state of New Jersey, notwithstanding the fact
that it was unlikely the project site ultimately would be found
to be a wetland.
The agency concedes that the iMap-NJ system does in fact
identify the project site as a wetland and it does not dispute
the propriety of AMEC's consideration of the iMap information.
Contracting Officer's Supplemental Statement, at 000873. Rather,
the agency asserts that the site is not in fact considered a
wetland by the state of New Jersey, as reflected by a 2003
Integrated Natural Resources and Environmental Assessment, which
had been provided to the agency by the New Jersey Department of
Environmental Protection, as well as information solicited from
an official within the New Jersey Department of Environmental
Protection, thereby rendering immaterial the failure of the
other offerors to identify the project as potentially a wetland.
Supplemental Agency Report, at 000865. We disagree.
The information upon which the agency now relies was not
publicly available and was not otherwise made available to any
of the offerors during the competition. For this reason, once
the agency learned of AMEC's reasonable reliance on the publicly
available iMap information, which was in direct conflict with
the information that was in the agency's sole possession which
shaped the premise of its technical evaluation of the other
offerors' proposals, the agency was obligated to clarify the
agency's understanding of wetland requirement with AMEC. Absent
clarification of the matter, AMEC was placed in the position of
addressing a solicitation requirement in a manner different than
the other offerors and which placed it at a competitive
disadvantage to the other offerors given the conflicting public
and nonpublic information. The agency's failure to clarify the
wetland issue was contrary to the fundamental principle that a
solicitation must provide for the submission of proposals based
on a common understanding of the agency's requirements. See
Media Funding, Inc. d/b/a Media Visions, Inc., B-265642,
B-265642.2, Oct. 20, 1995, 95-2 CPD para. 185 at 3. We therefore
sustain the protest on this basis as well. (AMEC
Earth & Environmental, Inc., B-401961; B-401961.2, December
22, 2009) (pdf)
Sabre asserts that the agency
failed to provide it with meaningful discussions regarding
previously unidentified weaknesses under the demonstrated
understanding and management/technical approach subfactors. For
example, it maintains that the weaknesses related to its DPM,
quality assurance surveillance plan, updated CSA manuals, and
work breakdown structure (WBS) stemmed from issues present in
its original proposal and were unrelated to the discussion
questions raised, such that it was not on notice of the specific
issues of concern to the agency.
When an agency engages in discussions with an offeror, the
discussions must be meaningful, that is, they must lead the
offeror into the areas of its proposal that require correction
or amplification. Hanford Envtl. Health Found., B‑292858.2,
B‑292858.5, Apr. 7, 2004, 2004 CPD para. 164 at 8. However, an
agency is not obligated to reopen negotiations to give an
offeror the opportunity to remedy a defect that first appears in
a revised proposal. American Sys. Corp., B-292755, B‑292755.2,
Dec. 3, 2003, 2003 CPD para. 225 at 8.
The discussions here were unobjectionable. For example, the
agency's initial discussions noted that Sabre's WBS did not
provide sufficient detail to depict all SOW requirements. In our
view, the initial question was sufficient to lead Sabre to
provide a response that included a more detailed WBS, and the
TET found Sabre's response to this weakness to be adequate
during the FPR evaluation. In re-evaluating the FPRs, however,
the TEP came to a different conclusion based on its identifying
continuing weaknesses, specifically, missing milestones
regarding some operational tasks and deliverables. There was
nothing unreasonable or improper in the TEP's changing its
original view as to the adequacy of Sabre's discussions response
based on the re-evaluation. Since the identified weaknesses
represented defects first appearing in Sabre's FPR in response
to the original discussions--rather than newly identified
weaknesses in Sabre's initial proposal--the agency was not
required to reopen negotiations to provide Sabre another
opportunity to respond.
We reach the same conclusion with regard to Sabre's proposed DPM.
As mentioned above, during the original discussions, the TEP
identified a weakness regarding Sabre's failure to clearly
identify the different roles and responsibilities related to
implementing its communications initiatives. TEP Evaluation at
10. When Sabre's FPR added a DPM as part of its solution, the
TEP identified a new weakness based on the lack of information
on this individual; since the weakness was introduced in Sabre's
FPR, the agency did not raise the matter again. Id. Sabre argues
that, since its initial proposal mentioned the DPM (e.g., in its
organization chart and part of its risk review team), but did
not then identify him, his role, or his function, the DPM
concern really was a weakness in its original proposal--rather
than a new weakness--that the agency should have raised during
the original discussions. Thus, once the agency's re‑evaluation
identified the lack of that information as a weakness, the
agency was required to re‑open discussions to address it. See
Lockheed Martin Simulation, Training & Support, B-292836 et al.,
Nov. 24, 2004, 2005 CPD para. 27 at 11 (where weakness, present
in initial proposal, is identified for first time in
re-evaluation, agency must discuss the new weakness).
We disagree. The fact that Sabre's initial proposal contained
little information on the DPM is irrelevant; it was Sabre's
proposing the DPM as part of its communication initiatives,
without detailed information, that led to the agency's specific
concern. Prior to that time, the agency had no specific reason
to be concerned about the lack of detail on the DPM's role and
function. Once Sabre proposed the DPM as part of its solution to
an identified weakness, it was Sabre's responsibility to provide
complete information. See Carlson Wagonlit Travel, B‑287016,
Mar. 6, 2001, 2001 CPD para. 49 at 3 (offeror is responsible for
submitting an adequately written proposal). Its failure to do so
here led to a new evaluated weakness, which--because it was
introduced for the first time in its FPR--did not obligate the
agency to reopen discussions following the re-evaluation.
American Sys. Corp., supra.
The protest is denied. (Sabre
Systems, Inc., B-402040.2; B-402040.3, June 1, 2010) (pdf)
The protester argues that the
agency conducted materially misleading discussions regarding
Ewing's proposed roofing system, and that the agency's
evaluation of Ewing's and Overland's proposals was unreasonable
in a number of respects.
This protest is illustrative of one of the challenges an agency
faces when, for whatever reason (but here in taking corrective
action in response to a previous protest), the agency
reevaluates proposals after discussions are complete. In this
regard, we have held that where an agency, during a reevaluation
of proposals, identifies new concerns in a proposal and those
concerns would have had to be raised had they been identified
before discussions were held, the agency is required to reopen
discussions and raise the new concerns with the offeror.
Lockheed Martin Simulation, Training & Support, B-292836.8 et
al., Nov. 24, 2004, 2005 CPD para. 27 at 11; DevTech Sys., Inc.,
B-284860.2, Dec. 20, 2000, 2001 CPD para. 11 at 4.
Here, prior to taking corrective action, the agency raised its
concerns regarding Ewing's proposed roofing system during
discussions, and specifically identified its concerns as a
"significant weakness." After evaluating Ewing's final proposal
revision, the agency assigned the proposal ratings of "marginal"
under the technical solution factor and "satisfactory" overall.
AR, Tab 5, Ewing Discussion Letter (June 8, 2009). These ratings
were consistent with the terms of the solicitation, which stated
that a "significant weakness" may result in an adverse impact on
the proposal's rating under the technical solution factor and
overall rating. RFP at 10.
In contrast, during the reevaluation--performed as part of the
agency's corrective action in response to Ewing's initial
protest--the agency determined that Ewing's proposed roofing
system constituted a "deficiency in meeting the stated
solicitation requirements." Rather than downgrading Ewing's
proposal, this reassessment rendered the proposal "ineligible
for award," in accordance with the terms of the RFP--which, as
quoted above, expressly stated that proposals with uncorrected
deficiencies would be ineligible for award. AR, Tab 2, BCM, at
15, 19-20; RFP at 10. Because the agency did not reopen
discussions with the offerors, Ewing was never informed that its
proposal was deficient. Although the agency is correct that its
concern with Ewing's proposed roofing system was raised during
discussions (such that the concern is not a "new concern"), the
identification of the concern as a "significant weakness,"
rather than a "deficiency," misled the protester. Specifically,
the protester was never apprised of the severity of the agency's
concern, or the ramifications of not adequately addressing it--i.e.,
ineligibility for award.
It is a fundamental concept of negotiated procurements that
discussions, when conducted, must be meaningful; that is,
discussions may not mislead offerors and must identify
deficiencies and significant weaknesses in each offeror's
proposal that could reasonably be addressed in a manner to
materially enhance the offeror's potential for receiving award.
Federal Acquisition Regulation (FAR) sect. 15.306(d); Lockheed
Martin Corp., B-293679 et al., May 27, 2004, 2004 CPD para. 115
at 7. An agency may not, through silence, the framing of a
discussion question, or in a response to a question, mislead an
offeror into responding in a manner that does not address the
agency's concerns, or that misinforms the offeror concerning a
problem with its proposal or the government's requirements.
Lockheed Martin Corp., supra; Metro Mach, Corp., B-281872 et
al., Apr. 22, 1999, 99-1 CPD para. 101 at 6.
Under the circumstances here, since the agency's concerns with
the protester's proposed approach changed during the
reevaluation to the point that, should they remain unaddressed,
the proposal would be rejected as ineligible for award, the
agency was required to reopen discussions. On this issue, the
protester represents that "[h]ad the Agency identified the
proposed roof design as a deficiency during discussion[s],
[Ewing] would have been made aware that its proposal was
ineligible for award, which would have elicited a different
response from [Ewing] to the Discussion Letter." Protest at 6;
see Protester's Comments at 6.
The protest is sustained. (Ewing
Construction Co., Inc., B-401887.3; B-401887.4, April 26,
2010) (pdf)
Lack of
Meaningful Discussions
The protester argues that the evaluators failed to conduct
meaningful discussions with it by failing to advise it that they
considered its schedule to be overly aggressive. We agree.
When an agency engages in discussions with a vendor, the
discussions must be "meaningful," that is, sufficiently detailed
to lead the vendor into the areas of its quotation requiring
amplification or revision. Honeywell Tech. Solutions, Inc.,
B‑400771, B-400771.2, Jan. 27, 2009, 2009 CPD para. 49 at 10.
Here, we do not think that the request for a new schedule
reasonably conveyed to the protester that the evaluators viewed
its proposed schedule as too aggressive; given that a period of
over a year had elapsed between submission of the vendors'
initial quotations and submission of their final quotations, we
think that vendors could reasonably have understood the request
to be nothing more than a request for updated information. We
note in this connection that the evaluators furnished precisely
the same request for a new schedule to Privasoft, and in its
case, the request was not intended to convey a concern over the
duration of the schedule. We think that by failing to advise the
protester in discussions that they considered its project
schedule to be too short, the evaluators failed to conduct
meaningful discussions with it. Moreover, we think under these
circumstances that the advice given at the debriefing did not
obviate the need to raise this concern when the agency reopened
discussions. (AINS, Inc.,
B-400760.4; B-400760.5, January 19, 2010) (pdf)
As discussed
above, on June 6, after various conference calls regarding the
terms of the Velos license agreement, the contracting officer
prepared a marked up version of the document that reflected the
areas where the agency and Velos had agreed upon the terms of
the special license agreement for the software. See AR, Tab 33,
Email from Contracting Officer to Velos (June 6, 2008); Tr. at
323-28, 338. As indicated above, however, the contracting
officer, in his award determination, found the Velos license
agreement submitted with its July 7 final proposal revision was
unacceptable because the language containing paragraph 2.1
(quoted above) conflicted with the RFP requirements that the
agency be granted a perpetual use license to distribute and use
the software without limits within the boundaries of the NCI
Clinical Research Enterprise. The record evidences that
paragraph 2.1 of the license submitted with Velos's final
proposal revision is the exact language that Velos and the
contracting officer agreed was acceptable after lengthy
discussions. Tr. at 323‑28; compare AR, Tab 33, Velos's Final
Proposal Revision (July 7, 2008), Special License Agreement)
(also designated Hearing exh. No. 3) with Hearing exh. No. 15,
Marked Up Velos License Prepared by Contracting Officer (June 6,
2008).
As to Velos's refusal to agree to a provision stating that "any
conflict between the terms of this Agreement, and the Contract
or applicable Federal law of regulation, shall be resolved by
the terms of the Contract or applicable Federal Law or
Regulation," Velos asserts that this was a matter discussed
earlier in the negotiations. Velos's Post-Hearing Comments at
10. According to Velos, this matter was resolved by including
the following language defining "Contract" in the software
license and agreeing to include the license in Attachment J-1 to
the contract:
"Contract" shall mean Contract No. 1406-04-08-CT-20201,
executed by and between the Parties hereto on June XX, 2008.
This Special License Agreement shall be Attachment J-1 to the
Contract and shall be incorporated by reference into the
Contract at Section J.
AR, Tab 33, Velos's Final Proposal Revision (July 7, 2008),
Special License Agreement), Definitions, at 1. Velos explains
that under the contract's order of precedence clause,
incorporating the license in Attachment J would subordinate it
to the rest of the contract. Velos Post‑Hearing Comments at 10;
see FAR sect. 52.215-8 (incorporated by the RFP at 38). As
argued by Velos, the record shows that the identical provision
defining "Contract" included in the earlier markup that Velos
and the contracting officer agreed was acceptable to the parties
was contained in the final proposal revision. See Tr. at 329-30;
compare Tab 33, Velos's Final Proposal Revision (July 7, 2008),
Special License Agreement) (also designated Hearing exh. No. 3)
with Hearing exh. No. 15, Marked Up Velos License Prepared by
Contracting Officer (June 6, 2008).
The problems the contracting officer found with the language in
Schedule B are based solely upon the problems that he now has
with paragraph 2.1 of the license and not the Schedule B
language per se. See AR, Tab 51, Award Summary, at 15. In fact,
at the hearing, the contracting officer admitted that he may
well have prepared the Schedule B language in question. Tr. at
352.
As to the escrow agreement, the record shows that this agreement
was not required by the RFP and was only included at the request
of the agency. See Contracting Officer's Statement at 12. The
contracting officer also testified that he never advised Velos
during the negotiations that there was a problem with the
proposed terms of Velos's escrow provision. Tr. at 350.
The agency asserts that there was no agreement on the terms of
the Velos license. Hearing exh. No. 16, Statement of Contracting
Officer (Oct. 31, 2008). In support of this assertion the agency
references a string of emails that occurred after June 6,
culminating in the June 27 email closing negotiation because of
numerous unresolved issues and advising that the competition
would be reopened. Id. The agency also references the request
for final proposal revisions (quoted above) and an email in
response to a question submitted after the request for final
proposal revisions that advised offerors to be aware that
licenses that were inconsistent with federal law, regulation, or
the solicitation requirements might result in the proposal being
eliminated. AR, Tab 37, Request for Final Proposal Revisions
(June 27, 2008); Hearing Exh. No. 13, Email from Contracting
Officer (July 2, 2008). In fact, Velos agrees that there was no
final agreement on the terms of its license when the
negotiations were closed. Velos's Post Hearing Comments at 6.
However, there is no evidence in the record that the contracting
officer ever specifically or even generally told Velos that the
previously agreed-upon language in its license agreement in the
"Grant of License" paragraph and in the "Contracts" definition
was considered unacceptable by the agency. Because the reasons
provided by the contracting officer in determining that the
Velos license was unacceptable are based upon the precise
language that Velos and the agency had found acceptable, and
because the agency had not advised Velos that this language was
no longer acceptable, we find that Velos was prejudicially
misled in submitting its final proposal revision that included
the agreed-upon language. We sustain the protest on this basis.
(Velos, Inc.; OmniComm Systems, Inc.;
PercipEnz Technologies, Inc., B-400500; B-400500.2;
B-400500.3; B-400500.4; B-400500.5; B-400500.6; B-400500.7,
November 28, 2008) (pdf)
Clark/Caddell
also argues that the agency failed to engage in meaningful
discussions regarding the performance capability evaluation
factor issue in that the agency asked misleading questions and
failed to provide meaningful responses. Specifically, the
protester contends that the agency did not provide meaningful
guidance to remedy the purported discrepancy between the
protester's CLIN schedule and its summary schedule.
Discussions, when conducted, must be meaningful; that is,
discussions may not mislead offerors and must identify
deficiencies and significant weaknesses in each offeror's
proposal that could reasonably be addressed in a manner to
materially enhance the offeror's potential for receiving award.
PAI Corp., B-298349, Aug. 18, 2006, 2006 CPD para. 124 at 8.
Agencies are not required to "spoon-feed" an offeror during
discussions; agencies need only lead offerors into the areas of
their proposals that require amplification. LaBarge Elecs.,
B-266210, Feb. 9, 1996, 96-1 CPD para. 58 at 6.
As a preliminary matter, we recognize that the first IFN
erroneously directed Clark/Caddel to confirm the correct number
of days proposed for construction duration, as opposed to
contract duration. On the other hand, the words of the schedule
were clear, i.e., the CLIN entry (identified in the discussion
question) was preceded by the words "Contract Duration in
Calendar Days After the Notice to Proceed is received." RFP at
1.
That said, we think that by holding two rounds of discussions,
the agency guidance was ultimately sufficient to put the
protester on notice that the agency wanted the CLIN schedule to
include the total contract duration. As discussed above, the
agency's concerns that the protester's summary schedule in its
technical proposal for contract duration was different from the
enforceable contract duration listed in the CLIN schedule was
reasonable, especially given the liquidated damages provisions
of the RFP.
Furthermore, we note evidence in the record that suggests the
protester understood the agency's concerns. In a declaration
submitted by a representative of Clark/Caddell describing his
conversation with the contract specialist on September 18, the
representative stated that he asked the contract specialist "how
Clark/Caddell could commit to a fixed duration when Clark/Caddell
had no control over the actions of others." Clark/Caddell
Response to Agency Dismissal Request, Nov. 2, 2009, Exh. 10, at
2. The Clark/Caddell official explained that his "was an attempt
to get [the contract specialist] to understand that the longest
fixed duration in the solicitation is the 450-day duration for
construction, which would be the only reasonable and enforceable
entry on the CLIN Schedule." Id. Thus, it appears that the
protester was concerned about being bound to an overall contract
duration period as opposed to the construction duration period.
In conclusion, we see no support for the protester's arguments
that the discussions here were misleading.
The protest is denied. (Clark/Caddell
Joint Venture, B-402055, January 7, 2010) (pdf)
In its revised
proposal, TMM provided a revised drawing of its plan and a chart
that compared the proposed size of TMM’s rooms with that
required by the SFO. TMM’s chart showed that a number of TMM’s
proposed rooms were smaller than that specified by the SFO.
TMM’s Revised Proposal, Room Size Chart. With regard to
renovations to its existing building, TMM informed VA that
“[o]ther than painting, we do not believe there will be many
renovations in the existing space.” TMM also did not propose to
widen the 5-foot corridor, but did offer that “[i]f the VA wants
all the fifty doors to be enlarged from 36” doors to 42” doors,
the cost would be an additional $50,000 ($1,000 per door).” AR,
Tab 4, TMM Revised Proposal, at 2.
VA determined that TMM’s revised proposal did not reflect the
best value to the government, although TMM offered the lowest
evaluated price of $4,790,436. Specifically, VA noted that TMM
failed to meet the contract requirements for corridor width,
room square footage, and TMM “would only [be] making minor
renovations (painting) to the existing . . . space.”[3] AR, Tab
6, Price Negotiation Memorandum, at 11. In contrast, the agency
found that Alpine’s proposal at an evaluated price of $5,215,654
offered “the best proposed” layout for the space, meeting the
specified room sizes. Id. at 10. Award was made to Alpine, and
this protest followed.
TMM complains that VA did not conduct meaningful discussions
with the firm. Specifically, TMM argues that the agency’s
request that TMM “clarify” its room sizes was inadequate to put
the firm on notice that the agency had found TMM’s room sizes to
be a deficiency. We disagree.
Discussions, when conducted, must be meaningful; that is,
discussions may not mislead offerors and must identify
deficiencies and significant weaknesses in each offeror’s
proposal that could reasonably be addressed in a manner to
materially enhance the offeror’s potential for receiving award.
PAI Corp., B-298349, Aug. 18, 2006, 2006 CPD para. 124 at 8.
Here, we find that VA conducted meaningful discussions with TMM.
Specifically, VA informed TMM that it should “clarify” its room
sizes “in accordance with Schedule A.” This request should have
informed TMM of the agency’s concern under the technical quality
evaluation factor that TMM had not demonstrated “how they are
going to meet the identified space and square footage
requirements and room build‑out details in Schedule A.” See SFO
at 17. Although TMM believes that the agency should have been
more specific about its concerns, an agency is not required to
“spoon-feed” an offeror during discussions, but need only lead
the offeror into the areas of its proposal that requires
amplification. LaBarge Elecs., B-266210, Feb. 9, 1996, 96-1 CPD
para. 58 at 6.
TMM also appears to argue that VA’s discussions were not
meaningful because the agency did not inform TMM that the agency
viewed the firm’s proposed build-out plans to be inadequate. The
record indicates that TMM was also led into this area of its
proposal that required amplification. In any event, the
protester fails to show that it was prejudiced. Competitive
prejudice is an essential element of a viable protest; where the
protester fails to demonstrate that, but for the agency’s
actions, it would have had a substantial chance of receiving the
award, there is no basis for finding prejudice, and our Office
will not sustain the protest. Trauma Serv. Group, B‑254674.2,
Mar. 14, 1994, 94-1 CPD para. 199 at 6; see Statistica, Inc. v.
Christopher, 102 F.3d 1577 (Fed. Cir. 1996). TMM does not state
that, had it been notified of the agency’s concerns in this
regard, it would have offered any renovations to its space or
otherwise modified its proposal in any way. (TMM
Investments, Ltd., B-402016, December 23, 2009) (pdf)
Argon maintains that any inadequacy of the MTBOMF1
information it provided was the result of its being misled by
the agency regarding its MTBF information during discussions.
Specifically, Argon asserts that, because the agency did not
object to Argon’s MTBF data (provided in its response to the
initial discussion questions) being based on performance of its
CPS at 55C, it assumed that it could also present its MTBOMF
data based on 55C.
This argument is without merit. Discussions, when held, must be
meaningful; that is, they must lead offerors into those areas of
their proposals requiring amplification or revision, and may not
prejudicially mislead the offeror. American States Utilities
Servs., Inc., B-291307.3, June 30, 2004, 2004 CPD para. 150 at
6-7. However, agencies are not required to engage in successive
rounds of discussions until all proposal defects have been
corrected, nor are agencies required to reiterate concerns that
were not alleviated by a firm’s proposal revisions. Id. Where an
agency engages in initial discussions that lead an offeror to
revise its proposal, the agency’s subsequent silence in
connection with those proposal revisions during a subsequent
round of discussions cannot reasonably be understood as an
indication that the agency determined that the initial weakness
or deficiency was cured. Id.
Here, under the circumstances, there was no reasonable basis for
Argon to interpret the agency’s silence regarding the MTBF data
as a waiver of the plainly stated RFP requirements regarding
MTBOMF. See American States Utilities Servs., Inc., supra.
Simply stated, since the RFP clearly required MTBOMF information
to be presented in terms of a particular temperature, and the
RFP was not amended in this regard, Argon was required to
provide the information in those terms. To the extent Argon
chose to rely on its impressions from the agency’s silence
instead of complying with the RFP’s clear requirements, it did
so at its peril.
(Argon ST, Inc., B-401387, August
6, 2009) (pdf)
---------------------------
1 mean time between operation mission failure.
Discussions
AAA next argues that the Forest Service never advised the
company that its dressing area drainage was insufficient, and
therefore the agency failed to conduct meaningful discussions
regarding this perceived deficiency in its units. Protest at 15.
In negotiated procurements, contracting agencies generally must
conduct discussions with all offerors whose proposals are within
the competitive range. Federal Acquisition Regulation sect.
15.306(d)(1). Agencies are not required to afford offerors
all-encompassing discussions. Reflectone Training Sys., Inc.;
Hernandez Eng'g Inc., B-261224; B-261224.2, Aug. 30, 1995, 95-2
CPD para. 95 at 10. Although discussions must be meaningful,
leading an offeror into the areas of its proposal requiring
amplification or revision, the agency is not required to
"spoon-feed" an offeror as to each and every item that could be
revised or addressed to improve its proposal. Comprehensive
Health Serv., Inc., B-310553, Dec. 27, 2007, 2008 CPD para. 9 at
7.
Here, as noted above, the agency conducted oral and written
discussions with AAA, during which it noted the apparent
problems with drainage in the dressing area. In the handwritten
notes attached to the May 17 discussion letter, the Forest
Service expressed a "concern that [the] dressing area does not
have the ability to contain all gray water" and that the units
"may have a drainage issue." AR at 448 (AAA Discussion Letter
Notes at 1). As evidenced by the record here, the agency clearly
communicated its concerns that the dressing area drainage was
deficient. Also, it is clear from the protester's cover
letter--discussed in greater detail below--that it was aware of
these issues from the discussions. AR at 455-56 (AAA's Cover
Letter to its Final Proposal, May 29, 2008 at 2-3). Therefore,
we deny AAA's contention that discussions in this area were
inadequate. (AAA Mobile
Showers, Inc., B-311420.2, March 27, 2009) (pdf)
Lack of
Meaningful Discussions
Honeywell protests that the agency failed to conduct meaningful
discussions by failing to raise the one technical weakness it
found in Honeywell's FPR.
As set forth above, the RFP contained four RTOs that offerors
were to address in their technical proposals, either by the
submission of a TIP and cost proposal (RTOs #1-3) or a study
paper (RTO #4). RTO #1 concerned a new space-to-ground link
terminal (SGLT) at the White Sands Complex, New Mexico. The RFP
informed offerors that as part of an effort to ensure adequate
SN grounds systems resources were available, a project to
develop a new SGLT was being initiated. The stated task
requirement was for the contractor to complete the first phase
of the new SGLT project, including planning, definition of the
architecture, operations concepts, requirements, external
interfaces, and preliminary design. RFP, RTO #1, at 01245. The
solicitation also informed offerors that a TIP submission was to
include, at a minimum, the technical approach for the specific
requirements of the task, identification of potential technical
challenges, identification and mitigation of risks, and a
detailed description of any assumptions made in the response.
SOW at 00845.
Honeywell submitted its TIP for RTO #1 as part of its initial
proposal. AR, Tab 13, Honeywell Initial Proposal (Mission
Suitability), at 2021-47. The SEB rated Honeywell's initial
proposal, including RTO responses, excellent under the technical
approach subfactor, and identified a total of seven strengths
and two weaknesses supporting its determination. Id., Tab 40,
Initial SEB Report, at 09941-47. Both of the technical approach
weaknesses identified in Honeywell's initial proposal concerned
its RTO #1 TIP. The SEB first found that Honeywell's RTO #1
response did not identify certain specific noteworthy risks
associated with the completion of the RTO #1 requirement.
Second, the agency evaluators found that Honeywell's RTO #1 TIP
contained various questionable assumptions. Id. at 09946-47. It
is the second of the identified weaknesses that is the subject
of Honeywell's protest here.
NASA then conducted discussions with Honeywell and informed the
offeror of both identified technical approach weaknesses. With
regard to the second weakness, the agency stated, "Honeywell's
RTO #1 response contains the following questionable assumptions,
which require clarification and/or substantiation, or should be
corrected and their impact on the RTO be addressed," and then
identified the specific assumptions the agency evaluators had
questioned. Id., Tab 43, NASA Discussions with Honeywell, at
10143.
Honeywell addressed the agency's discussion topics as part of
its FPR. The offeror's FPR included a "highlighted" version that
specifically indicated those portions of its revised proposal
that had been changed (either added or deleted). The SEB
considered Honeywell's discussion responses as part of the
evaluation of the offeror's revised proposal, and determined
that Honeywell had remedied both originally-identified
weaknesses. Specifically, with respect to the second
weakness--that Honeywell's RTO #1 TIP contained various
questionable assumptions--the SEB found the offeror's revised
proposal had adequately addressed each assumption. Id., Tab 80,
Final SEB Report, at 23649-50.
The SEB determined, however, that Honeywell's FPR contained a
new weakness, namely that the offeror's response demonstrated an
inadequate understanding of the requirements analysis, trade
study execution and analysis, and requirements identification
aspects of the systems engineering process. Id. at 23647-48.
Each of the findings on which the SEB based its determination of
the new weakness in Honeywell's FPR resulted from the new (i.e.,
highlighted) sections in the offeror's revised proposal. Id.,
Tab 46, Honeywell's FPR, at 10663-80. For example, Honeywell's
assertion that the candidate architecture could be interfaced
with the legacy antenna interconnect mechanisms was a new
section in the offeror's revised proposal, as was Honeywell's
assertion that a to-be-completed upgrade to the White Sands
Complex local area network would have sufficient margin to
support the requirements for the new SGLT. Id. at 10674-75,
10680.
Although discussions must address deficiencies and significant
weaknesses identified in proposals, the precise content of
discussions is largely a matter of the contracting officer's
judgment. See FAR sect. 15.306(d)(3); American States Utils.
Servs., Inc., B-291307.3, June 30, 2004, 2004 CPD para. 150 at
6. When an agency engages in discussions with an offeror, the
discussions must be "meaningful," that is, sufficiently detailed
so as to lead an offeror into the areas of its proposal
requiring amplification or revision. Hanford Envtl. Health
Found., B-292858.2, B-292858.5, Apr. 7, 2004, 2004 CPD para. 164
at 8. Where proposal defects are first introduced either in a
response to discussions or in a post-discussion proposal
revision, an agency has no duty to reopen discussions or conduct
additional rounds of discussions. L-3 Commc'ns Corp., BT Fuze
Prods. Div., B-299227, B-299227.2, Mar. 14, 2007, 2007 CPD para.
83 at 19; Cube-All Star Servs. Joint Venture, B-291903, Apr. 30,
2003, 2003 CPD para. 145 at 10-11.
We conclude that NASA's discussions with Honeywell were
meaningful. As set forth above, the discussions expressly
informed Honeywell of the specific weaknesses that the SEB had
identified in the offeror's initial proposal. Further, the
record clearly reflects that the specific significant weakness
which Honeywell claims that NASA failed to mention in
discussions was first introduced in Honeywell's post-discussions
FPR and was not part of its initial proposal. As a result, NASA
had no obligation to conduct additional rounds of discussions in
order to permit the offeror to address this matter. See L-3
Commc'ns Corp., BT Fuze Prods. Div., supra. (Honeywell
Technology Solutions, Inc., B-400771; B-400771.2, January
27, 2009) (pdf)
As noted above, if the agency in accordance with FAR sect.
25.502 determines that Tiger’s vehicles are TAA-compliant, then
the agency must evaluate Tiger’s quotation, including whether
Tiger’s quoted price is fair and reasonable. We recognize that
the agency determined that Tiger’s price was “exorbitantly
unreasonable” and found Tiger ineligible for award on this
basis. AR, Tab 56, Price Negotiation Memorandum, at 13. However,
the record also confirms that the agency failed to raise this
issue during discussions, even though it held numerous rounds of
discussions with the vendors and requested revised quotations
inviting vendors to reduce their price. Although the agency
asserts that “discussions were not intended” and were not held,
we find that the “numerous questions and clarifications” issued
to vendors followed by the agency’s request for “best and final
offers,” which included revisions to vendor’s prices,
constitutes discussions as contemplated by the FAR. AR, Tab 56,
Price Negotiation Memorandum, at 12; Contracting Officer’s
Statement at 9; Tr. at 173; see FAR sect. 15.306(d).
Although the solicitation here did not require the agency to
hold discussions with vendors, once an agency chooses to do so,
as occurred here, the discussions are required to be meaningful;
that is, the agency is required to raise with a vendor
significant weaknesses and deficiencies identified in the
vendor’s quotation. FAR sect. 15.306(d)(3). Discussions cannot
be meaningful if a vendor is not advised of the significant
weaknesses or deficiencies that must be addressed in order for
its quotation to be in line for award. DevTech Sys., Inc.,
B-284860.2, Dec. 20, 2000, 2001 CPD para. 11 at 4. There is no
doubt that Tiger’s quoted price was viewed by the agency as a
deficiency, as Tiger’s price was the sole basis for the agency’s
finding that the quotation was ineligible for award. In holding
discussions with Tiger, but not raising with the firm the
concern that Tiger’s price was unreasonable, the agency did not
provide Tiger with meaningful discussions. DevTech Sys., Inc.,
supra, at 4-5.
We find a reasonable possibility that Tiger was prejudiced by
the agency’s failure to hold discussions concerning the
reasonableness of the firm’s price. Had the agency raised its
concern with Tiger, then Tiger would have had the opportunity to
explain why its price was fair and reasonable or to reduce it,
such that the agency may have ultimately found the price to be
fair and reasonable and, thus, Tiger’s quotation would have been
in line for award. Coupled with the agency’s failure to properly
evaluate TAA eligibility, we find that the agency’s failure to
hold meaningful discussions prejudiced the protester, and we
sustain the protest on these bases. See Cogent Sys., Inc.,
B‑295990.4, B‑295990.5, Oct. 6, 2005, 2005 CPD para. 179 at
10-11. (Tiger Truck, LLC,
B-400685, January 14, 2009) (pdf)
Burchick complains that VA did not conduct meaningful
discussions with Burchick, given that VA did not apprise the
firm of, or provide it with the opportunity to address,
significant evaluated weaknesses in its technical proposal. The
protester contends that it could have resolved the agency’s
concerns with the firm’s proposal had the firm been provided
with discussions concerning its technical proposal.
VA argues that the scope and extent of discussions to be
conducted with offerors is “a matter of contracting officer
judgment” and that agencies are not required to discuss every
area in which a proposal can be improved. In this regard, VA
contends that the agency was not required to conduct discussions
with respect to Burchick’s technical proposal, given that the
contracting officer concluded that the firm could not have
materially improved its technical proposal. AR at 6-7.
We agree with VA that a procuring agency has considerable
discretion in determining whether and how to conduct discussions
in a negotiated procurement under Federal Acquisition Regulation
(FAR) Part 15. However, where, as here, discussions are
conducted, they must at a minimum identify deficiencies and
significant weaknesses in the proposals of each competitive
range offeror. FAR sect. 15.306(d)(3); Multimax, Inc., et al.,
B-298249.6 et al., Oct. 24, 2006, 2006 CPD para. 165 at 12; PAI
Corp., B-298349, Aug. 18, 2006, 2006 CPD para. 124 at 8.
Discussions must be “meaningful,” that is, sufficiently detailed
so as to lead an offeror into the areas of its proposal
requiring amplification or revision. Smiths Detection, Inc.,
B-298838, B‑298838.2, Dec. 22, 2006, 2007 CPD para. 5 at 12;
Symplicity Corp., B-297060, Nov. 8, 2005, 2005 CPD para. 203 at
8.
We find that VA did not conduct meaningful discussions with
Burchick, since the agency limited its discussions to the firm’s
cost proposal and did not identify any of the agency’s
significant concerns with Burchick’s technical proposal that
resulted in the firm’s proposal receiving only 50.8 points out
of 100 possible points.[6] In particular, the protester’s
proposal received only 22 of 40 available points under the past
performance factor, based upon the agency’s judgment that
Burchick had provided detailed information on only one relevant
project, where the solicitation requested a minimum of four
projects. Similarly, Burchick’s proposal received only 14.4 of
30 available points under the construction management factor,
based upon the agency’s conclusion that Burchick had failed to
identify a project manager and to detail its quality control
plan, as required by the RFP. Burchick’s proposal received no
points under the small business participation factor, because
the agency found that Burchick had essentially not provided the
required small business participation plan. Given the
significant reductions in Burchick’s technical point score
associated with these identified concerns, and the importance to
the agency of the omitted information, we find that these
concerns can only be considered to be significant weaknesses or
deficiencies, and that the agency’s failure to identify them
during discussions was inconsistent with its obligation to
conduct meaningful discussions.
We also do not agree with VA that Burchick could not have
materially improved its proposal if discussions were conducted
with the firm with respect to the evaluated concerns in its
technical proposal. The protester has explained that it could
have addressed each of the agency’s concerns that resulted in
Burchick’s technical proposal being downgraded. For example,
with respect to the evaluation of the firm’s past performance,
Burchick contends that it identified 37 other healthcare
projects in its technical proposal, which the protester could
have detailed if the firm had been asked in discussions.
Protester’s Comments at 4. With respect to the identity of its
project manager and to its proposed quality control plan under
the construction management factor, Burchick states that, had it
received discussions, the firm would have clarified the identity
of its project manager and provided further detail with respect
to its quality control plan. Id. at 6-7. With respect to the
small business participation factor, Burchick states that it
could have further explained the firm’s proposed teaming
relationship with a service-disabled veteran-owned small
business.
In sum, we find that VA failed to conduct meaningful discussions
with Burchick, because the agency failed to identify significant
weaknesses or deficiencies in the firm’s technical proposal. We
also find a reasonable possibility that Burchick was prejudiced
by the agency’s failure to conduct meaningful discussions, given
that Burchick offered the lowest price and could have addressed
these concerns in its technical proposal such that it may have
been found to offer the best value to the agency. (Burchick
Construction Company, B-400342, October 6, 2008) (pdf)
The record
demonstrates that the agency, in conducting discussions with the
protester, forwarded a detailed list of discussion questions to
IVI, and answered a number of questions from IVI regarding the
discussion questions. Contrary to the protester’s assertion, we
find based upon our review of the record that the agency’s
discussions were meaningful.
For example, IVI argues that the agency “failed to conduct
meaningful discussions regarding software engineering.”
Protester’s Comments at 21. In this regard, the protester first
points that the agency’s initial technical evaluation noted as a
weakness under the technical approach criterion to the technical
factor that
[t]he Software Engineering section of this proposal is not
discussed in detail. This could lead to major deficiencies in
the design, implementation, and testing of the suggested
software development tasks.
AR, Tab 3, Initial Technical Evaluation, at 26. The protester
next points out that the relevant discussion question it
received was as follows:
The software section of the proposal is not discussed in
detail. This could lead to major deficiencies in the design,
implementation, and testing of the offeror’s proposed changes
in software.
AR, Tab 5, IVI Discussion Questions, at 5. The protester argues
that “[s]oftware engineering is a different concern than
software in general,” and that because of the discussion
question IVI received from the agency, “IVI was not informed of
the potential significant weakness in its software engineering.”
Protester’s Comments at 21.
The agency explains that the reference in the initial evaluation
to “software engineering” was a simple error, given that the
neither the RFP nor IVI’s proposal contained “software
engineering” sections, but rather, both included sections
addressing software maintenance and security. Agency Supp.
Report at 10; RFP amend. 6, at 5-6. The agency explains that the
contracting officer, in preparing IVI’s discussion questions,
deleted the discussion question’s reference to “software
engineering” in order to correct this error, and that IVI was in
fact properly informed during discussions of the agency’s
perceived weaknesses in the software section of IVI’s proposal.
Agency Supp. Report at 10.
Although IVI continues to complain “that the agency misled IVI
from addressing the evaluators’ actual concern: software
engineering,” and that because of this, the “evaluators may have
downgraded IVI for failing to answer a question that was not
asked,” see Protester’s Supp. Comments at 12, the protester does
not explain, and we cannot see, how this could possibly be the
case, given that neither the RFP nor IVI’s proposal included a
“software engineering” section, and given that there is no
evidence in the agency’s evaluation of FPRs that IVI’s FPR was
downgraded for failing to address “software engineering.”
As another example, the protester argues that the agency “failed
to conduct meaningful discussions regarding the biweekly
literature surveillance memoranda.” Protester’s Comments at 4;
Protester’s Supp. Comments at 13. The record reflects that the
agency noted as a “strength” in IVI’s proposal that it provided
“a clear discussion of how the biweekly literature reports will
be organized,” and that the “[o]rganization of [the biweekly
literature reports appears to be relevant to the aims of the . .
. staff.” AR, Tab 3, Initial Evaluation, at 25. The agency also
commented while noting the various weaknesses in IVI’s initial
proposal that “[b]iweekly literature surveillance memos would be
helpful in judging the potential quality of the data output.”
Id. at 26.
In response to the protester’s complaint that it “was not
informed during discussions that the agency found IVI’s proposed
biweekly literature surveillance memoranda problematic,”
Protester’s Supp. Comments at 13, the agency explains that it
did not raise this evaluated weakness with IVI during
discussions given its overall view that “IVI’s proposal with
respect to biweekly literature surveillance reports was at least
as much a strength as it was a weakness.” Agency Supp. Report at
13. The agency concludes that the concern expressed in its
initial evaluation regarding IVI’s biweekly literature
surveillance memoranda was not significant, and that under the
circumstances, did not have to be raised with IVI during
discussions. Id. We agree.
As stated previously, the record reflects that the agency had
extensive discussions with IVI regarding its proposal, and that
the agency’s concerns regarding this aspect of IVI’s proposal
were insignificant given the other evaluated weaknesses in IVI’s
proposal, as well as the fact that overall this aspect of IVI’s
proposal was found to constitute a strength. Additionally, IVI
has not pointed to, and we cannot find, any indication in the
evaluation of IVI’s FPR, or source selection documents, that
this aspect of IVI’s proposal was considered a weakness or had
any effect on either IVI’s overall rating or the source
selection. In light of this, and the fact that agency’s are not
required to identify other than deficiencies and significant
weaknesses in each offeror’s proposal, or to conduct discussions
that are all encompassing, we cannot find the agency’s conduct
here to be objectionable. See PAI Corp., supra. (Information
Ventures, Inc., B-299361.2; B-299361.3, October 1, 2008) (pdf)
Turning to
NAVSEA’s evaluation of the cost proposal submitted by MCT JV,
while we find that the agency had reasonable concerns about MCT
JV’s allocation of labor hours in its cost proposal, we conclude
that the agency’s discussions regarding this matter were not
meaningful. Specifically, the record reflects a wide disparity
between MCT JV’s proposed allocation of labor hours in its
technical proposal and the allocation of labor hours in its cost
proposal. As noted above, in its technical proposal MCT JV
allocated [Deleted] percent of the labor hours to MHI, [Deleted]
percent to Colonna’s, [Deleted] percent to Tecnico, and the
remaining [Deleted] percent to other specialty subcontractors.
NAVSEA, however, determined that MCT JV’s final cost proposal
reflected an allocation of [Deleted] percent of the total labor
hours to MHI, [Deleted] percent to Colonna’s, [Deleted] percent
to Tecnico, and [Deleted] percent to other subcontractors. The
[Deleted] percent allocation to other subcontractors had the
effect of significantly reducing MCT JV’s estimated cost since
MCT JV proposed a significantly lower labor rate for those
subcontractors.
In its protest, MCT JV specifically complains that NAVSEA’s
reallocation of its labor hours under item 999-99-999--where the
disparity between MCT-JV’s allocation of labor hours between its
technical proposal and cost proposal is even greater--was
unreasonable. As noted above, under item 999-99-999, MCT JV
allocated only [Deleted] percent of the work to its partners and
[Deleted] percent to “other subcontractors.” Because item
999-99-999 represented approximately [Deleted] percent of the
total projected labor hours used to estimate MCT JV’s total
cost, by allocating [Deleted] percent of these labor hours to a
category of other subcontractors with a significantly lower
labor rate, MCT JV was able to significantly reduce its
estimated cost. This extensive reliance on subcontractors for
the purpose of calculating its total estimated cost, however,
was clearly at odds with MCT JV’s technical proposal, which
indicated that MCT JV would allocate a much smaller percentage
[Deleted] of the work to specialty subcontractors.
NAVSEA was thus presented with a situation similar to the one it
faced in Metro Mach. Corp., B-297879.2, May 3, 2006, 2006 CPD
para. 80, where an offeror attempted to reduce its total
estimated cost by allocating all of its labor hours for notional
work items to its team member with the lowest labor rate,
notwithstanding the fact that the entire team would be
performing the actual work under the contract. In that case, we
held that the Navy’s cost realism evaluation was unreasonable
because the Navy accepted the proposed allocation without
further question and thus failed to consider the impact of the
team members’ higher rates in determining the offeror’s probable
cost of performance under the contract. In response to our
decision in Metro, NAVSEA included item 999-99-999 to capture
the total labor effort of a typical availability when combined
with the specific notional work items identified in the RFP, and
instructed offerors to ensure that their labor hour allocations
for this item were consistent with their proposed technical
approaches. AR at 23-24; RFP at 124-25.
While we commend NAVSEA’s efforts to adjust MCT JV’s allocation
of labor hours to reflect a labor mix that was more consistent
with its technical proposal and MCT JV’s joint venture
agreement, and therefore reflective of a more realistic total
probable cost for MCT JV, given our conclusion, discussed below,
that NAVSEA’s discussions with MCT JV regarding its concerns in
this regard were fundamentally flawed, any allegation regarding
the propriety of NAVSEA’s reallocation is academic at this
juncture.
It is a fundamental precept of negotiated procurements that
discussions, when conducted, must be meaningful, that is,
sufficiently detailed so as to lead an offeror into the areas of
its proposal requiring amplification or revision. Smiths
Detection, Inc., B-298838, B-298838.2, Dec. 22, 2006, 2007 CPD
para. 5 at 12; Symplicity Corp., B‑297060, Nov. 8, 2005, 2005
CPD para. 203 at 8. Further, an agency may not mislead an
offeror--through the framing of a discussion question or
otherwise--into responding in a manner that does not address the
agency’s concerns, or misinform the offeror concerning a problem
with its proposal or about the government’s requirements.
Multimax, Inc., et al., B-298249.6 et al., Oct. 24, 2006, 2006
CPD para. 165 at 12; Metro Mach. Corp., B‑281872 et al., Apr.
22, 1999, 99-1 CPD para. 101 at 6.
Here, the record reflects that with respect to the allocation of
labor hours in MCT JV’s cost proposal, NAVSEA asked MCT JV to
explain why the allocation was inconsistent with its “resource
agreement.” As noted above, MCT JV responded that the resource
agreement did not apply to its proposal; rather, it was an
agreement among MHI, Colonna’s, and Tecnico relating to a
separate proposal submitted by MHI as the prime contractor. The
record further reflects that the CAP accepted MCT JV’s response,
agreeing that the resource agreement did not apply to the joint
venture. Thus, by questioning MCT JV’s allocation of labor hours
in its cost proposal solely by reference to a resource agreement
that by its terms did not apply to this proposal, NAVSEA never
conveyed to MCT JV its actual concern--that the labor hour
allocation in the cost proposal appeared to be inconsistent with
its technical proposal and joint venture agreement. Accordingly,
we find that the agency’s discussions in this regard were
misleading and therefore not meaningful.
(MCT JV, B-311245.2; B-311245.4,
May 16, 2008) (pdf)
Discussions, when
conducted, must be meaningful, that is, they may not be
misleading and must identify proposal deficiencies and
significant weaknesses that could reasonably be addressed in a
manner to materially enhance the offeror’s potential for
receiving award. PAI Corp., B-298349, Aug. 18, 2006, 2006 CPD
para. 124 at 8. While an agency generally need only lead an
offeror into the general areas of concern about its proposal,
the agency must impart during discussions sufficient information
to afford the offeror a fair and reasonable opportunity to
identify and correct deficiencies, excesses, or mistakes in its
proposal. Advanced Sci., Inc., B‑259569.3, July 3, 1995, 95-2
CPD para. 52; Aydin Computer and Monitor Div., Aydin Corp.,
B-249539, Dec. 2, 1992, 93-1 CPD para. 135.
The discussions here were not meaningful. While the record shows
that the agency indeed advised JPDT that it could improve its
technical score by providing amenities within its offered
building, this information was conveyed, not to identify
deficiencies in JPDT’s offer, but as part of the agency’s
general advice that every offeror received. This general advice
amounted to no more than a restatement of the SFO’s evaluation
criteria. It did not reasonably apprise JPDT that the agency had
found its proposal to contain specific significant weaknesses
regarding access to amenities, including the proximity and
number of amenities generally, the proximity and number of fast
food restaurants, and the variety, quantity, and proximity of
table service restaurants. See Integrity Int’l Sec. Sys., Inc.,
B‑261226, Sept. 1, 1995, 95‑2 CPD para. 98 at 8 (general
boilerplate-type reminder that was provided to all offerors
during discussions was insufficient to provide notice of
protester’s specific deficiency).
Further, while the record also supports the agency’s claim that
it informed JPDT that it was unable to verify the existence of
two of the identified restaurants and the identified sports
club, this very specific information likewise fell short of
advising JPDT that its proposed amenities were a concern
overall. Indeed, by providing its concerns regarding particular
restaurants and a particular fitness facility without indicating
that it considered JPDT’s offer to have significant weaknesses
regarding the proximity and number of amenities generally, the
proximity and number of fast food restaurants, and the variety,
quantity, and proximity of table service restaurants, we think
GSA led JPDT reasonably to believe that GSA’s concerns were
limited to those particular establishments and were not broader
in nature. See Spherix, Inc., B‑294572, B-294572.2, Dec. 1,
2004, 2005 CPD para. 3 at 14 (agency failed to conduct
meaningful discussions where it determined that offeror’s entire
quality control plan was a significant weakness, but identified
only two specific aspects of the quality control plan in
discussions). We conclude that the agency’s discussions failed
to provide JPDT with sufficient information to afford it a fair
and reasonable opportunity to identify and correct the evaluated
significant weaknesses in its offer. (New
Jersey & H Street, LLC, B-311314.3, June 30, 2008) (pdf),
(See Trammell Crow Company,
B-311314.2, June 20, 2008) (pdf)
It is a
fundamental precept of negotiated procurements that discussions,
when held, must be meaningful; that is, discussions may not
mislead offerors and must identify deficiencies and significant
weaknesses in each offeror’s proposal that could reasonably be
addressed in a manner to materially enhance the offeror’s
potential for receiving award. Federal Acquisition Regulation
(FAR) sect. 15.306(d); Lockheed Martin Corp., B-293679 et al.,
May 27, 2004, 2004 CPD para. 115 at 7. Based on our review of
the record, and for the reasons set forth below, we find that
the agency’s discussions with the protester were meaningful.
To the extent that ICRC argues that the agency was required to
consider its proposed costs unacceptable, and thus a proposal
deficiency, we note first that the contemporaneous evaluation
record indicates that the agency did not consider the matter to
be a proposal deficiency. Instead, the evaluators reached a
different conclusion. Specifically, the agency conducted a
detailed assessment of whether the number of hours identified
was reasonably related to ICRC’s approach to the sample task.
This assessment led the agency to conclude that the proposed
solution to the sample task was an acceptable one, but one that
involved a high number of labor hours. As a result, the agency
advised ICRC during discussions that the number of labor hours
proposed appeared high. Upon receipt of this information, ICRC
reduced its overall proposed labor hours, thereby altering its
proposed costs.
Our review of the record here has revealed nothing to lead us to
conclude that the agency’s assessment was unreasonable. In fact,
the cost realism analysis here fulfilled its purpose--i.e., it
examined whether the costs proposed by ICRC’s technical approach
were consistent with the firm’s likely actual cost of
performance. While the protester claims that its own proposed
costs were per se unreasonable, given the lower costs proposed
by the awardee, it has not shown that the cost realism analysis
produced an inaccurate measure of the likely cost of
implementing the company’s proposed technical solution.
Moreover, the record shows that the contracting officer
specifically noted in his source selection decision that the
significant variance in evaluated costs was directly
attributable to the significant differences in the technical
approaches adopted by the competing offerors.
Finally, the protester has not shown that the discussions were
misleading, or, in any way, inadequate. Where an offeror’s
proposed cost is high in comparison to competitors’ costs, the
agency may, but is not required to, inform the offeror that its
costs are not as competitive as those of its competitors during
discussions. See FAR sections 15.306(d)(3), (e)(3); SOS
Interpreting, Ltd., B-287477.2, May 16, 2001, 2001 CPD para. 84
at 3; see also Mechanical Equip. Co., Inc.; Highland Eng’g,
Inc.; Etnyre Int’l, Ltd.; Kara Aerospace, Inc., B-292789.2 et
al., Dec. 15, 2003, 2004 CPD para. 192 at 18; MarLaw-Arco MFPD
Mgmt., B-291875, Apr. 23, 2003, 2003 CPD para. 85 at 6. In sum,
since ICRC’s proposed costs were not evaluated as either
unreasonable or unrealistic, and since the agency was not
obligated to advise the company that its proposed costs were not
competitive, we conclude that the agency’s discussions with ICRC
were adequate. (Integrated
Concepts & Research Corporation, B-309803, October 15, 2007)
(pdf)
Boeing also complains that the agency conducted misleading
discussions with Boeing with respect to whether Boeing had fully
satisfied the KPP No. 7 objective, Net-Ready Capability. RFP,
SRD sect. 3.2.4.1.1; app. A, Net-Ready Capability KPP, at 3. The
KPP No. 7 objective provides that the offeror’s “system should
be capable of accomplishing all operational activities
identified in Table 5.” RFP, SRD, app. A, at 4. Table 5 of the
appendix identified a number of information exchange
requirements. Id. at 15-25.
Specifically, Boeing complains that at its mid-term briefing it
was informed of an uncertainty regarding the firm’s net ready
capability, see AR, Tab 129, Mid-Term Briefing to Boeing, at 77,
and that ultimately the firm responded to an EN concerning the
firm’s System Requirements Matrix and System Specification with
respect to complying with the SRD requirements for KPP No. 7.
See AR, Tab 210, Boeing Response to EN BOE-MC1-041. Boeing
believed that its EN response charted how its proposal met the
KPP No. 7 thresholds and objective in total, see Boeing’s
Comments at 29, and during the firm’s Pre-Final Proposal
Revision Briefing the Air Force informed Boeing that the firm
“met” both the KPP thresholds and the objective requirements for
KPP No. 7. See AR, Tab 135, Boeing’s Pre‑Final Proposal Revision
Briefing, at 57. Accordingly, Boeing made no further revisions
to its proposal in this area. Boeing’s Second Supplemental
Protest at 53. The Air Force, however, changed its evaluation
rating of this aspect of Boeing’s proposal to “partially met”
the KPP objective (the same rating that Northrop Grumman
received) without further notice to Boeing. Boeing contends that
the Air Force’s misleading discussions prevented the firm from
addressing the agency’s concerns with respect to this objective.
The Air Force does not dispute that it informed Boeing during
discussions that the firm had satisfied all of the thresholds
and the objective under KPP No. 7, but contends that at the time
it later determined that Boeing had not fully satisfied this
objective, discussions had already been closed. See Second
Supplemental COS at 77. The agency argues that, in any event, it
was under no obligation to inform Boeing of the changed
evaluation rating associated with this objective because the
objective “constituted trade space,” the absence of which would
not be a deficiency or weakness. Agency Memorandum of Law at
131.
We do not agree with the Air Force that the agency was
permitted, after informing Boeing that its proposal fully met
this objective, to change this evaluation conclusion without
affording Boeing the opportunity to satisfy this requirement. It
is a fundamental precept of negotiated procurements that
discussions, when conducted, must be meaningful, equitable, and
not misleading. See 10 U.S.C. sect. 2305(b)(4)(A)(i); AT&T
Corp., B-299542.3, B‑299542.4, Nov. 16, 2007, 2008 CPD para. 65
at 6. Here, by informing Boeing prior to the submission of the
firm’s final proposal revision that it satisfied all aspects of
KPP No. 7, the Air Force deprived the firm of the opportunity to
further address these particular requirements. See AT&T Corp.,
supra, at 12; see also Bank of Am., B‑287608, B-287608.2, July
26, 2001, 2001 CPD para. 137 at 13.
In contrast, the Air Force informed Northrop Grumman prior to
the submission of that firm’s final proposal revision that it
had only partially met this KPP objective, which permitted that
firm the opportunity to further address the KPP objective
requirements. See AR, Tab 205, Northrop Grumman’s Pre-Final
Proposal Revision Briefing, at 61. Moreover, Boeing submitted
its final submission addressing this KPP objective several
months prior to the pre-FPR briefing, and, as indicated above,
the agency actually reopened discussions on other subjects after
submission of the FPRs and obtained revised FPRs. Boeing’s
Protest at 66; Boeing’s Second Supplemental Protest at 53. In
short, the Air Force misled Boeing when the agency advised the
firm that it met this objective, but later determined that
Boeing did not fully meet this objective, and did not reopen
discussions with Boeing on this issue. The Air Force also
treated the firms unequally when it provided Northrop Grumman,
but not Boeing, with continued discussions on this same
objective. It is axiomatic that procuring agencies may not
conduct discussions in a manner that favors one offeror over
another. See FAR sect. 15.306(e)((1); Chemonics Int’l, Inc.,
B-282555, July 23, 1999, 99-2 CPD para. 61 at 8-9.
We also find a reasonable possibility that Boeing was prejudiced
by the Air Force’s misleading and unequal discussions, given the
greater weight that KPPs were supposed to receive in the
agency’s evaluation. In this regard, if Boeing had been
evaluated as fully satisfying this KPP objective, which was the
only KPP objective in the operations utility area, it could well
have been considered to be superior in this area to Northrop
Grumman, which was evaluated as only partially satisfying this
KPP objective.
(The
Boeing Company, B-311344; B-311344.3; B-311344.4;
B-311344.6; B-311344.7; B-311344.8; B-311344.10; B-311344.11,
June 18, 2008) (pdf)
The protester next argues that the EPA failed to conduct
meaningful discussions regarding several issues. The record,
however, does not support the protester’s allegations with
regard to any of the areas where it argues that the agency
failed to provide meaningful discussions. For example, IBM
argues that it was misled during discussions regarding page
limitations. Specifically, IBM claims that the agency advised
IBM that Volume 3 of its proposal exceeded the page limitation,
but orally advised that IBM could include additional pages
regarding its work breakdown structure (WBS) and integrated
master plan (IMP) in Volume 5, rather than Volume 3 of its
proposal--despite the fact that the RFP expressly required that
these matters be addressed in Volume 3. IBM contends that it
relied on the agency’s advice and placed those items in Volume
5, which, unlike Volume 3, had no page limitations. In
evaluating IBM’s proposal, the agency did not provide the WBS
and IMS documents to the evaluators because they were not
contained in Volume 3; the agency evaluators concluded that the
absence of a detailed WBS and IMP constituted a weakness in the
proposal. AR, Tab 41, SSD at 23. The protester argues that
the agency’s discussions here were misleading, and therefore not
consistent with the agency’s obligation to ensure that
discussions are meaningful. See L-3 Comm. Corp., BT Fuze Prods.
Div., B-299227, B-299227.2, Mar. 14, 2007, 2007 CPD para. __ at
18-19. The agency denies making such a statement, and notes that
such instructions would have been contrary to the RFP
instructions. Because the allegedly misleading agency statements
would have resulted in a material deviation from the
solicitation, namely the page limitation, the protester could
not reasonably rely on such oral advice--even if the record
demonstrated that the agency made such a statement, which it
does not. S3 LTD, B-287019.2 et al., Sept. 14, 2001, 2001 CPD
para. 165 at 6. Offerors cannot rely on oral modifications to an
RFP which are inconsistent with its written terms, absent a
written amendment to the RFP or written confirmation of the oral
modification. Id. This clear principle provides fairness to all
parties by ensuring that competitions are conducted under equal
terms, and protects both protesters and agencies from the kind
of credibility disputes raised here, as well as protecting the
integrity of the procurement process overall. Id. (IBM
Corporation, B-299504; B-299504.2, June 4, 2007) (pdf)
AT&T protests that the agency failed to adequately raise the
concerns it had regarding AT&T’s staffing plan during the
discussions held with the offeror. AT&T also contends that the
agency’s discussions were misleading, because SSA identified one
narrow area of the offeror’s staffing plan as lacking sufficient
detail and failed to inform AT&T of the true nature and breadth
of the evaluated weaknesses here. The protester argues that the
lack of meaningful discussions was prejudicial to it, since the
perceived weaknesses in AT&T’s staffing plan became a major
factor in the agency’s subsequent best value tradeoff
determination. Protest, Sept. 20, 2007, at 44-51.
When discussions are conducted, they must at a minimum identify
deficiencies and significant weaknesses in each
competitive-range offeror’s proposal. Federal Acquisition
Regulation (FAR) sect. 15.306(d)(3); Multimax, Inc., et al.,
B-298249.6 et al., Oct. 24, 2006, 2006 CPD para. 165 at 12; PAI
Corp., B-298349, Aug. 18, 2006, 2006 CPD para. 124 at 8.
Discussions must be “meaningful,” that is, sufficiently detailed
so as to lead an offeror into the areas of its proposal
requiring amplification or revision. Smiths Detection, Inc.,
B-298838, B-298838.2, Dec. 22, 2006, 2007 CPD para. 5 at 12;
Symplicity Corp., B-297060, Nov. 8, 2005, 2005 CPD para. 203 at
8. For example, discussions are not meaningful where the agency
fails to apprise an offeror that its staffing levels are viewed
as unreasonably low. Professional Servs. Group, Inc.,
B-274289.2, Dec. 19, 1996, 97-1 CPD para. 54 at 4. Further, an
agency may not mislead an offeror--through the framing of a
discussion question or a response to a question--into responding
in a manner that does not address the agency’s concerns, or
misinform the offeror concerning a problem with its proposal or
about the government’s requirements. Multimax, Inc., et al.,
supra; Metro Mach. Corp., B-281872 et al., Apr. 22, 1999, 99-1
CPD para. 101 at 6.
(sections deleted)
In its report to our Office,
SSA argues that its actions here were proper for the following
reasons: (1) the weaknesses found by the agency in AT&T’s
staffing plan were not significant ones, so no discussions were
in fact required here; (2) the agency nevertheless conducted
meaningful discussions with AT&T regarding its staffing plan;
and (3) the agency was not required to re-open discussions with
AT&T simply because AT&T’s staffing plan subsequently became a
discriminator for source selection purposes. AR, Oct. 1, 2007,
at 1-5, AR, Nov. 2, 2007, at 1-6. As discussed in detail
below, we conclude that the agency’s actions were improper
because: (1) the agency’s initial technical evaluation regarded
AT&T’s staffing plan as a significant weakness; (2) the agency
failed to conduct meaningful discussions with AT&T regarding
this significant weakness; and (3) the agency’s substantial
reliance on AT&T’s staffing plan in its best value tradeoff
determination clearly demonstrates that the lack of meaningful
discussions here was prejudicial to AT&T.
As set forth above, the record reflects that the TET’s initial
evaluation of proposals identified two separate concerns with
AT&T’s proposed staffing plan. First, the evaluators found that
AT&T’s staffing appeared to be at minimal levels in relation to
the RFP’s requirements. Second, the TET also believed that
AT&T’s entire staffing plan lacked sufficient detail, as
exemplified by the offeror’s staffing for the VNOC and help-desk
personnel at the Durham and NCC locations. Moreover, the agency
evaluators considered AT&T’s staffing plan to be a significant
weakness, as evidenced by the initial evaluation report.
Specifically, in addition to stating that “[t]he proposed
staffing at current levels would be considered inconsistent with
the proposal implementation schedule without a clear
understanding of the support personnel,” the TET expressly found
that “[t]he risk of implementing a minimal staffing plan as
[AT&T] presented could jeopardize the success of the project.”
AR, Tab 13, Initial Technical Evaluation Report, app. 5,
Evaluation of Proposed Project Lifecycle Staffing Plans, at 7.
We think that when an agency finds, as it did here, that the
risk associated with a given aspect of an offeror’s proposal may
jeopardize the overall success of the project, this represents a
significant weakness. See FAR sect. 15.001 (a “significant
weakness” in an offeror’s proposal is a flaw that appreciably
increases the risk of unsuccessful contract performance). Given
this finding regarding the risk associated with AT&T’s staffing
plan, the fact that SSA did not expressly characterize the
staffing plan as a significant weakness is not controlling. See
Alliant Techsystems, Inc.; Olin Corp., B-260215.4, B-260215.5,
Aug. 4, 1995, 95-2 CPD para. 79 at 7-8. Accordingly, we conclude
that the agency was required to conduct discussions with AT&T
regarding its staffing plan. Further, while the record
shows that SSA did conduct discussions with AT&T regarding its
staffing plan, we think that these discussions were not
meaningful. As set forth above, the agency provided AT&T with
one discussion item regarding its staffing plan. This item
informed AT&T only of SSA’s concern that the staffing plan
lacked sufficient detail (“the personnel staffing charts do not
provide sufficient information to determine that the staffing
levels are consistent with AT&T’s proposed programmatic
methods,” AR, Tab 15, Discussions with AT&T, at 13-14), and
completely failed to mention the agency’s equal, if not greater,
independent concern that AT&T’s staffing levels were considered
too low. An agency’s belief that an offeror’s staffing levels
are too low is materially different from a concern that a
staffing plan lacks sufficient detail; the fact that both
involve staffing is not sufficient to conclude that the agency
here provided meaningful notice to AT&T as to the total scope of
its concern. See Andrew M. Slovak, B-253275.2, Nov. 2, 1993,
93-2 CPD para. 263 at 4 (discussions limited to a food menu’s
item cycle did not put offeror on notice of the agency’s
separate concern that the menu also failed to provide for
healthy food items). Moreover, the discussion item here
specified only one particular area of AT&T’s staffing plan as
lacking sufficient detail (“[s]pecifically, staffing levels for
VNOC and Help Desk problem intake,” id. at 14), when the
agency’s real concern was that AT&T’s entire staffing plan
lacked sufficient information. See Spherix, Inc., B-294572,
B-294572.2, Dec. 1, 2004, 2005 CPD para. 3 at 14 (agency failed
to conduct meaningful discussions when it determined that
offeror’s entire quality control plan was a significant
weakness, but identified only two specific aspects of the
quality control plan in discussions). In our view, not only was
AT&T inadequately advised of other areas of its staffing plan
that lacked sufficient detail, but the agency’s failure to
identify the scope of its concern may have misled the offeror
into believing that those areas did not require further
adjustment.[18] Also, unlike other identified management
approach weaknesses, the discussions here did not characterize
AT&T’s staffing plan as a significant weakness, or inform the
offeror of the agency’s belief that the risk associated with
AT&T’s minimal staffing plan could jeopardize the success of the
project. See AR, Tab 15, Agency Discussions with AT&T, at 8,
13-14. Under the circumstances here, we cannot conclude that
AT&T, reviewing the agency’s discussions in conjunction with the
material that it had submitted with its proposal, reasonably
could have recognized the total scope of the agency’s concerns
regarding both the staffing levels and the lack of detail in
AT&T’s entire staffing plan. The record also reflects that
AT&T was prejudiced by the lack of meaningful discussions
regarding its staffing plan. In its final evaluation report, the
TET found that AT&T’s staffing levels, while higher than those
proposed originally, were still “minimal and conservative,” and
the lack of detail in AT&T’s staffing plan (in areas other than
VNOC and Help desk, which AT&T’s FPR specifically addressed)
represented potential performance risks if AT&T was unable to
staff appropriately. Id., Tab 33, Final Technical Evaluation
Report, at 9, app. II, Evaluation of Proposal Project Lifecycle
Staffing Plans, at 6. The agency’s subsequent best value
tradeoff determination then went further, and characterized
AT&T’s staffing levels as the offeror’s “principal weakness and
area of risk,” since its staffing levels were “so low as to
potentially threaten the ability of the vendor to successfully
deliver the proposed solution in accordance with the
Government’s delivery schedule and to support the TSRP user
community across the contract term in a fully satisfactory
manner.” Id., Tab 35, Best Value Tradeoff Memorandum, at 22.
Quite simply, AT&T’s staffing plan, which the agency considered
to be a significant weakness from the time of the initial
evaluation, was a material factor in the agency’s source
selection determination. (AT&T
Corp., B-299542.3; B-299542.4, November 16, 2007) (pdf)
DRS maintains that the agency engaged in unequal discussions,
specifically, that it was given more exacting questions and was
required to provide far more detail in its responses than Onan.
In effect, DRS is arguing that it was given a greater level of
detail in its discussions than was given to Onan. We fail to see
how providing more detailed discussions to DRS was improper or
prejudicial to DRS. Discussions need not be identical; rather,
discussions are to be tailored to each offeror’s proposal.
Federal Acquisition Regulation sect. 15.306(d)(1), (e)(1);
PharmChem, Inc., B-291725.3 et al., July 22, 2003, 2003 CPD para.
148 at 6. We find no impropriety here. DRS also asserts
that its discussions were misleading. As noted, the agency
relaxed the solicitation’s requirements relating to the fuel
efficiency standards for the generator sets. The agency advised
both offerors of its intention to relax the specifications, and
requested comments relating to the revisions, by e-mail dated
October 18, 2006. AR, exh. 30. DRS commented by letter dated
October 23, stating that, in its view, the changes were
unnecessary because it could meet the original, more stringent,
standards. AR, exh. 31. Notwithstanding DRS’s position, the
agency revised the specifications on November 1. AR, exh. 32.
Thereafter, by letter of November 2, DRS requested that the Army
engage in discussions relating to the deficiencies identified in
its original phase II and III proposal. In response, the agency
provided DRS with two rounds of discussion questions, first by
letter dated November 3, and subsequently by letter dated
January 16, 2007. In both letters, the agency provided DRS with
detailed questions that had been developed by the evaluators
after their review of DRS’s initial proposal, including
questions relating to DRS’s ability to meet the original, more
stringent, fuel efficiency standards. (Engineered
Electric Company d/b/a/ DRS Fermont, B-295126.5; B-295126.6,
December 7, 2007) (pdf)
Discussions, when conducted, must be meaningful, that is, they
may not be misleading and must identify proposal deficiencies
and significant weaknesses that could reasonably be addressed in
a manner to materially enhance the offeror’s potential for
receiving award. PAI Corp., B‑298349, Aug. 18, 2006, 2006 CPD
para. 124 at 8. However, agencies are not required to “spoon
feed” an offeror during discussions; they need only lead
offerors into the areas of their proposal that require
amplification. LaBarge Elecs., B‑266210, Feb. 9, 1996, 96-1 CPD
para. 58 at 6. The discussions here were unobjectionable.
As noted above, the discussion letter specifically advised Blane
that its delivery plan was difficult to read and follow. In this
regard, Blane’s initial delivery plan consisted of a chart
containing various item descriptions (down the left hand side of
the chart), amounts (throughout the chart, including various
blank spaces), and country names (down the right hand side of
the chart), formatted in such a manner that the columns
contained no headings--thus making it unclear to what the
columns referred--and the rows contained amounts that were not
clearly on the same line, making it unclear which amount
referred to which item description.[2] Since the nature of the
agency’s difficulty with the chart was, simply, that it was
difficult to read and follow, the discussion letter was
sufficient to lead Blane into the area of its proposal that
required improvement or further clarification. Blane asserts
that the agency should have reviewed its entire proposal,
including the quantities contained in a “transportation matrix,”
and then brought any discrepancies to its attention during
discussions. Protester’s Comments at 3. However, while the
protester may believe that it would have been better able to
address the deficiencies in its delivery plan if the agency had
approached discussions as it suggests, the agency was not
required to do so; again, the agency was only required to lead
the protester into the area of concern. Moreover, given the lack
of clarity in the chart, and the agency’s resultant inability to
determine precisely what Blane intended, we think the agency was
not in a position to provide more information in its discussion
letter; certainly, it was not required to provide more detailed
questions based on its speculation as to what Blane may have
intended. (Blane International
Group, Inc., B-310329, December 13, 2007) (pdf)
Cornell next argues that, because the agency had “serious
concerns about the location offered by Cornell from the time
that the site visit was performed,” Comments at 7, the agency
was required by the FAR to raise those concerns in discussions.
When discussions are held they must at least address
deficiencies and significant weaknesses in the proposals. FAR
sect. 15.306(d)(3). However, the agency is not required to
discuss every area where a proposal could be improved, and the
scope and extent of discussions is a matter within the
contracting officer’s discretion. Id. In this regard, we review
the adequacy of discussions to ensure that agencies point out
weaknesses that, unless corrected, would prevent an offeror from
having a reasonable chance of award. Brown & Root, Inc. and
Perini Corp., a joint venture, B-270505.2, B-270505.3, Sept. 12,
1996, 96-2 CPD para. 143 at 6. As discussed above, the
record demonstrates that Cornell’s site location was never
considered to be a significant weakness or deficiency, and never
prevented Cornell from having a reasonable chance for award.
Nowhere in the SSEB working papers, the SSEB consensus papers,
the technical/management evaluation memorandum, or the SSD was
the weakness of Cornell’s site location characterized as
significant or as a deficiency. [2] Further, Cornell’s proposed
site location was found to meet the requirements of the
solicitation at every stage of the evaluation. Because there is
no evidence to suggest that Cornell’s site location ever kept
its proposal from being rated acceptable under the site location
or technical/management factor, or otherwise prevented Cornell
from having a reasonable chance of receiving award, the agency
was not required to raise the issue in discussions. See Northrop
Grumman Info. Tech. Inc., B-290080 et. al., June 10, 2002, 2002
CPD para. 136 at 6; Brown & Root, Inc. and Perini Corp., a joint
venture, supra. (Cornell
Companies, Inc., B-310548, December 3, 2007) (pdf)
We recognize, as
PADCO points out, that the TEC did in fact describe the level of
effort feature of its proposal as a “weakness.” Contrary to
PADCO’s argument, however, discussions are not inadequate simply
because a weakness, which was not addressed during discussions,
subsequently becomes a determinative factor in choosing between
two closely ranked proposals, as was the case here. See, e.g.,
Gracon Corp., B-293009 et al., Jan. 14, 2004, 2004 CPD para. 58
at 3; Hines Chicago Inv., LLC, B‑292984, Dec. 17, 2003, 2004 CPD
para. 5 at 3-4. Further, regarding PADCO’s contention that the
weakness must have been significant because its final ratings
were decreased, the agency reports, and the record confirms,
that this weakness was not viewed by the agency as significant.
At PADCO’s debriefing, USAID expressly stated that it did not
consider the above weakness to be significant. Consistent with
this statement, the evaluation documents show that none of the
evaluation comments characterize PADCO’s distribution of its
level of effort as a “significant weakness,” a term the agency
had used to describe other weaknesses it identified in its
evaluation. See, e.g., AR, Tab 55, Competitive Range
Determination, at 9 (discussing a “significant weakness” in the
initial proposal submitted by The Services Group). While the
distribution of PADCO’s level of effort presented a “risk,” as
indicated by the TEC, there is nothing to suggest that it
created an unacceptable level of risk or “appreciably” increased
the risk of PADCO’s proposal. See FAR sect. 15.001 (defining a
“weakness” as “a flaw . . . that increases the risk of
unsuccessful contract performance” and a “significant weakness”
as “a flaw that appreciably increases the risk of unsuccessful
contract performance”). Ultimately, under both the management
and staffing plan subfactor and the overall technical approach
factor, PADCO’s proposal received a rating of “acceptable,”
which, as noted above, was defined by the RFP as a proposal
which meets all solicitation requirements, is “complete” and
“comprehensive,” and exemplifies an understanding of the tasks
required. RFP at M-2. (Planning And
Development Collaborative International, B-299041, January
24, 2007) (pdf)
It is a fundamental precept of negotiated procurements that
discussions, when conducted, must be meaningful; that is,
discussions must identify deficiencies and significant
weaknesses in each offeror’s proposal that could reasonably be
addressed so as to materially enhance the offeror’s potential
for receiving award. PAI Corp., B‑298349, Aug. 18, 2006, 2006
CPD para. 124 at 8; Spherix, Inc., B-294572, B-294572.2, Dec. 1,
2004, 2005 CPD para. 3 at 13. An agency fails to conduct
meaningful discussions where it fails to apprise an offeror that
its prices were viewed as unreasonably high. Price Waterhouse,
B-220049, Jan. 16, 1986, 86-1 CPD para. 54 at 6-7. Further, an
agency may not mislead an offeror--through the framing of a
discussion question or a response to a question--into responding
in a manner that does not address the agency’s concerns;
misinform the offeror concerning a problem with its proposal; or
misinform the offeror about the government’s requirements. Metro
Mach. Corp., B‑281872 et al., Apr. 22, 1999, 99-1 CPD para. 101
at 6. In conducting exchanges with offerors, agency personnel
also may not “engage in conduct that . . . favors one offeror
over another,” FAR sect. 15.306(e)(1); in particular, agencies
may not engage in what amounts to disparate treatment of the
competing offerors. Front Line Apparel Group, B-295989, June 1,
2005, 2005 CPD para. 116 at 3-4. Here, in the discussions
questions issued to NGI and Multimax (as well as to other
offerors such as BAE) questioning the proposed rates for
particular labor categories as significantly overstated, the
agency advised as follows: “Your proposed labor rates are
significantly higher than the Independent Government Cost
Estimate (IGCE) rates for the following labor categories . . . .
The offeror should consider revising the price proposal. If you
do not revise the identified rates, please provide an
explanation for the basis of the rate.” See IFN1 to
NGI no. 51, Nov. 3, 2005; IFN to NGI no. 298, Jan. 6, 2006; IFN
to BAE no. 50, Nov. 3, 2005; IFN to BAE no. 297, Jan. 6, 2006;
IFN to Multimax no. 49, Nov. 11, 2006. Thus, there was no
reference in the IFNs to the agency’s reliance on the
two-standard-deviation calculation, but instead only to the
proposed labor rate being “significantly higher than” the IGCE
as the basis for the IFN. The Army’s price discussions with NGI
and Multimax (as well as with BAE) were inadequate because, due
to the agency’s reliance on the two-standard-deviation formula
to identify “outlier” rates--and the broad range of acceptable
prices resulting from the formula--it failed to bring to the
protesters’ attention numerous rates that reasonably should have
been considered significantly overstated. In this regard, the
record shows that proposed rates that were not questioned in the
IFNs could actually exceed the IGCE rates by a greater
percentage than the rates that were identified. Thus, for
example, although NGI’s rate for [REDACTED] at the contractor
site was [REDACTED] percent higher than the IGCE rate, this rate
was not identified in an IFN because it was within the wide
range of acceptable prices established under the formula. At the
same time, although NGI’s proposed rate for [REDACTED] at the
contractor site was only [REDACTED] percent higher than the IGCE
rate, because it fell outside the range established by the
two-standard-deviation test, NGI was advised that its rate was
“significantly higher” than the IGCE. There simply is no
reasonable basis for bringing the former rate to the offeror’s
attention, but not the latter. The above example is not an
isolated one. NGI calculates that [REDACTED] of its proposed
labor rates that were not identified during price discussions
were similar to this example--they exceeded the corresponding
IGCE rate by a higher percentage than one or more of the rates
identified in its price IFNs. NGI notes further that [REDACTED]
of its unquestioned rates exceeded the IGCE rates by a greater
percentage than did some rates that were questioned in other
offerors’ IFNs. Likewise, the record indicates that Multimax was
not advised that its proposed rates for a significant number of
labor categories were higher than the corresponding IGCE rates,
despite the fact that these proposed rates deviated from the
IGCE by a greater percentage than rates that were identified in
discussions with Multimax or other offerors. Multimax calculates
that [REDACTED] of its unquestioned rates (only [REDACTED] of
its rates were identified in IFNs) exceeded the IGCE rates by a
greater percentage than the rates that were questioned in other
offerors’ IFNs (during initial price discussions). We conclude
that not only were offerors not adequately advised of all of
their significantly overstated rates, but the agency’s failure
to identify the additional rates actually misled the offerors
into believing that those rates did not require further
adjustment. In these circumstances, we conclude that the agency
failed to conduct meaningful discussions with the protesters.
(Multimax, Inc.; NCI
Information Systems, Inc.; BAE Systems, B-298249.6, B-298249.7,
B-298249.8, B-298249.9, B-298249.10,October 24, 2006) (pdf)
————————————————
1 Items for negotiation (IFN)
Where
contracting agencies conduct discussions with offerors whose
proposals are within the competitive range, the discussions must
be meaningful. Professional Servs. Group, Inc., B-274289.2, Dec.
19, 1996, 97-1 CPD para. 54 at 3. Discussions cannot be
meaningful if an offeror is not advised of the weaknesses,
deficiencies, or excesses in its proposal that must be addressed
in order for the offeror to be in line for award. Mechanical
Contractors, S.A., B-277916.2, Mar. 4, 1998, 98-1 CPD para. 68
at 4. Here, we think that the agency’s failure to raise its
concerns regarding the achievability of ALF’s proposed delivery
schedule constituted a failure to conduct meaningful discussions
because the protester might well have been determined to be in
line for award if it had been able to validate its proposed
schedule. Further, we do not think that the agency was relieved
of its obligation to conduct discussions due to the circumstance
that it did not learn of the information giving rise to its
concerns until after discussions had concluded. If, after
discussions are completed, the agency identifies concerns
pertaining to the proposal as it was prior to discussions that
would have had to be raised if they had been identified before
discussions were held, the agency is required to reopen
discussions in order to raise the concerns with the offerors.
See DevTech Sys., Inc., B-284860.2, Dec. 20, 2000, 2001 CPD para.
11 at 4. The key fact is that the concerns (while identified
after discussions have been closed) relate to the proposal as it
was prior to discussions. Id. (Al Long
Ford, B-297807, April 12, 2006) (pdf)
IAP also
complains that the Navy improperly failed to inform IAP that its
proposed price was too high. In this regard, IAP notes that its
proposed price was substantially higher than both the government
estimate (by 34 percent) and EJB’s price (by 21 percent) for the
definite-quantity elements of the RFP, and 39 percent higher
than EJB’s price for the ID/IQ elements. Where an
offeror’s price is high in comparison to competitors’ prices or
the government estimate, the agency may, but is not required to,
address the matter during discussions. Grove Resource Solutions,
Inc., B-296228, B-296228.2, July 1, 2005, 2005 CPD para. 133 at
5 n.5. Thus, if an offeror’s price is not so high as to be
unreasonable and unacceptable for contract award, the agency
reasonably may conduct discussions without advising the offeror
that its prices are not competitive. Id.; cf. Creative Info.
Tech., Inc., B-293073.10, Mar. 16, 2005, 2005 CPD para. 110 at 7
(price nearly 7 times the government estimate and 4.6 and 9
times competitors’ prices is unreasonable on its face). Here,
the agency determined that IAP’s overall price was reasonable
for the work to be performed and for what IAP proposed, SSB
Report at 19, and the price difference, even as calculated by
IAP, is not of a magnitude that suggests that IAP’s price was
unreasonable on its face. See Grove Resource Solutions, Inc.,
supra (agency not required to discuss protester’s high price
where awardee’s price was about 40 percent lower). Under these
circumstances, the Navy was not required to raise the matter of
IAP’s higher price during discussions. (IAP
World Services, Inc., B-297084, November 1, 2005) (pdf)
We find that the record does not establish a reasonable basis
for the agency’s assessment of a significant weakness with
respect to Cogent’s proposed scanner. First, as the record shows
and the Army now admits (see Agency’s Hearing Comments at
13-14), the evaluators failed to recognize that Cogent had
proposed a different scanner in its revised proposals to satisfy
the solicitation requirements--this failure itself renders
unreasonable the agency’s evaluation judgment concerning
Cogent’s proposed scanner. Despite the error, the Army’s
evaluator nevertheless asserted that the weakness was based upon
Cogent’s failure to explain how it could offer a compliant
scanner when the firm had asserted in its initial proposal and
earlier protest that no such scanner existed. TR at 122-24.
However, even assuming this latter evaluation judgment was
reasonable, the Army failed to provide Cogent with meaningful
discussions with respect to this scanner. The FAR requires at a
minimum that contracting officers discuss with each firm being
considered for award “deficiencies, significant weaknesses, and
adverse past performance information to which the offeror has
not yet had an opportunity to respond.” FAR sect. 15.306(d)(3).
Here, the Army twice provided Cogent with written discussions
after it proposed the Epson Perfection 4870 scanner as a
compliant product, but never identified its concern that Cogent
had not explained how it was now able to offer a compliant
product, even though the evaluators regarded this as a
significant weakness. In short, we find no reasonable basis in
the record for the agency’s judgment that Cogent’s proposed
scanner was a significant proposal weakness. We also find that,
in any event, the Army failed to conduct meaningful discussions
with Cogent with respect to this aspect of the agency’s
evaluation. (Cogent Systems, Inc.,
B-295990.4; B-295990.5, October 6, 2005) (pdf)
When contracting agencies conduct discussions with offerors in
the competitive range, such discussions must be meaningful.
Kaneohe Gen. Servs., Inc., B-293097.2, Feb. 2, 2004, 2004 CPD
paragraph 50 at 3. In order for discussions to be meaningful,
agencies must advise an offeror of weaknesses, excesses, or
deficiencies in its proposal, correction of which would be
necessary for the offeror to have a reasonable chance of being
selected for award. In this regard, the actual content and
extent of discussions are matters of judgment primarily for
determination by the agency involved, and we generally limit our
review of the agency's judgments to a determination of whether
they are reasonable. J.G. Van Dyke & Assocs. , B-248981,
B-248981.2, Oct. 14, 1992, 92-2 CPD paragraph 245 at 4.
Specifically, with regard to the adequacy of discussions of
price, an agency generally does not have an obligation to tell
an offeror that its price is high, relative to other offers,
unless the government believes the price is unreasonable. State
Mgmt. Servs., Inc.; Madison Servs., Inc., B-255528.6 et al. ,
Jan. 18, 1995, 95-1 CPD paragraph 25 at 5-6; Marwais Steel Co.,
B-254242.2, B-254242.3, May 3, 1994, 94-1 CPD paragraph 291 at
6. The issue here is whether the Army's discussions with CITI
were meaningful where the Army advised CITI merely that its
total price appeared "overstated," given the unique
circumstances of this case--specifically, the extraordinary
disparity between CITI's proposed level of effort and price as
compared to the government estimate as well as the level of
effort and prices of the other offerors in the competitive
range. We conclude that they were not. In addressing this issue,
we recognize that it is within the agency's discretion to decide
whether to inform an offeror that its price is considered too
high and to reveal the results of the analysis supporting that
conclusion or to indicate to all offerors the cost or price that
the government's price analysis, market research, and other
reviews have identified as reasonable. See FAR 15.306(e). The
question is whether the agency's judgment in this instance was
reasonable. While an agency is not required to "spoon-feed" an
offeror during discussions as to each and every item that could
be revised to improve its proposal, see ITT Fed. Sys. Int'l
Corp. , B-285176.4, B-285176.5, Jan. 9, 2001, 2001 CPD paragraph
45 at 6, agencies must impart sufficient information to afford
offerors a fair and reasonable opportunity to identify and
correct deficiencies, excesses or mistakes in their proposals.
Matrix Int'l Logistics, Inc. , B-272388.2, Dec. 9, 1996, 97-2
CPD paragraph 89 at 9. In this case, we conclude that CITI could
not be reasonably expected to have understood the true nature
and magnitude of the agency's concern with its proposal based
upon the information provided by the Army during its discussions
with CITI, thus rendering those discussions essentially
meaningless. (Creative
Information Technology, Inc., B-293073.10, March 16, 2005) (pdf)
In order for discussions to be meaningful, agencies must, at a
minimum, point out to competing firms deficiencies, significant
weaknesses, and adverse past performance information to which
the firm has not previously had an opportunity to respond. FAR
15.306(d)(3). The FAR also encourages contracting officers to
discuss other aspects of a firm's proposal that could, in the
opinion of the contracting officer, be altered or explained to
enhance materially the proposal's potential for award. Id.
Discussions must be meaningful, equitable and not misleading;
discussions cannot be meaningful unless a firm is led into those
weaknesses, excesses or deficiencies that must be addressed in
order for it to have a reasonable chance for award. TDS, Inc.,
supra, at 6-7. LMC asserts that the agency identified 11
weaknesses in its proposal that were based on language from the
earlier, pre-corrective action, version of its proposal. LMC
maintains that the agency was required to discuss these 11
weaknesses with the firm pursuant to our decision in DevTech
Sys., Inc. , B-284860.2, Dec. 20, 2000, 2001 CPD 11 in which we
held that, where an agency identifies new weaknesses in a
proposal during a reevaluation of that proposal in an
acquisition where discussions have previously occurred, it is
required to discuss those new weaknesses with the offeror. The
agency responds that, with respect to 6 of the 11 alleged
weaknesses arising from proposal language that predated the
current FPRs, the agency did not assign a weakness to the LMC
proposal during its evaluation, and thus was not required to
raise the matter in discussions. Agency Legal Memorandum, Sept.
30, 2004, at 11833. While the agency is correct that the six
weaknesses to which LMC refers were not identified as weaknesses
in the technical evaluation report on LMC's proposal, all six
are specifically identified in the agency's final evaluation and
tradeoff analysis report as weaknesses and as bases for
distinguishing between the LMC and EDS proposals. AR, exh. 116,
atviix,xiv. Given that they ultimately were listed in the best
value analysis--they related to 6 of the agency's 10 identified
best value items--and that they contributed in some manner to
the proposal's receiving an overall marginal/high risk rating,
we do not think the fact that they were captured in the best
value determination, rather than the technical evaluation
report, provided a basis for concluding that these issues were
not significant weaknesses. Further, while it is not clear how
significant they were, given that they played a large part in
the best value determination--and therefore presumably were
among the most important reasons for downgrading LMC's
proposal--absent some clear showing by the agency that they were
not significant, since they were based on information in LMC's
original proposal, and the agency had not previously discussed
the issues with LMC, it was obliged to do so. DevTech Sys., Inc.
, supra , at 4-5. (Lockheed Martin
Simulation, Training & Support, B-292836.8; B-292836.9;
B-292836.10, November 24, 2004) (pdf)
We do not agree with CHS that the agency's referring to staffing
and labor hours interchangeably was misleading. Rather, we think
the agency's references to "labor hours for full time employees"
(oral discussions) and the adequacy of CHS's proposed EAP staff
(written discussions) both reasonably could be interpreted in
only one way: the agency was concerned that CHS had not proposed
enough staff to perform adequately. The agency's questions were
adequate to bring this concern to CHS's attention, and therefore
were meaningful. (Comprehensive
Health Services, Inc., B-294608, December 1, 2004) (pdf)
As described above, the SSET identified Spherix's marketing
approach, including a lack of projected growth, to be a
"significant weakness." See AR, Supplemental Documents, Source
Selection Briefing Slides, at 2985. Spherix's approach to the
marketing plan requirement was not discussed with the protester,
and therefore we conclude that the agency failed to conduct
meaningful discussions with the firm in this respect. We also
find that the agency did not conduct meaningful discussions with
Spherix with respect to its proposed quality control plan, which
was also determined to be a significant weakness. The RFP
provided for the evaluation of offerors' draft comprehensive
quality control plan "to include a Performance Work Summary (PRS)
with Standards, Acceptable Quality Level (AQL), and Incentives."
RFP M, at 333. Spherix's initial proposal described its proposed
quality control plan, see AR, Tab103, Spherix Initial Proposal,
at 2139-214, which the SSET evaluated to be a weakness, stating
that Spherix's "overall quality control plan . . . is not a
complete approach . . . Vendor must amplify a more thorough
approach to quality control ensuring that [DELETED] are
addressed." See AR, Supplemental Documents, Final SSET
Evaluation Worksheets for Spherix, at 2997. The SSET also
evaluated Spherix's proposed approach to the PRS and AQL
requirements to be weaknesses. Id. In its discussions with
Spherix, the agency addressed only the firm's proposed approach
to the PRS and AQL requirements, and Spherix's proposal
revisions sufficiently addressed those aspects of its proposal
such that the agency no longer identified them as proposal
weaknesses. Id. The agency did not otherwise address Spherix's
quality control plan during discussions. Id. In its final
evaluation, the SSET noted that Spherix had not changed its
proposal with respect to its proposed quality control plan, and
stated that discussions were not conducted on this weakness
because Spherix "had a plan[; the] plan was simply weak." Id.
Ultimately, this aspect of Spherix's proposal was identified by
the SSET identified to be a "significant weakness." See AR,
Supplemental Documents, Source Selection Briefing Slides,
at2985. We therefore find that the agency failed to conduct
meaningful discussions with Spherix with respect to its proposed
quality control plan. We also find that Spherix did not receive
meaningful discussions with respect to its proposed transition
period staffing, which was evaluated as a part of the proposed
project implementation plan under the management approach
factor. See RFP M, at 333. Spherix's response to this
requirement was evaluated as a weakness, because the SSET found
that Spherix did not provide detailed information; SSET did not
conduct discussions on the matter with Spherix because it
concluded that Spherix's proposal "spoke to staffing but weak in
identification." See AR, Supplemental Documents, Final SSET
Consensus Evaluation Worksheets for Spherix, at 2999. This
aspect of Spherix's proposal, which was identified by the SSET
as a "significant weakness," see AR, Supplemental Documents,
Source Selection Briefing Slides, at2985, also should have been
raised with Spherix during discussions, but was not. (Spherix,
Inc., B-294572; B-294572.2, December 1, 2004) (pdf)
PDMG asserts that the agency improperly failed to conduct
adequate discussions for the Area 5 and 6 awards and, as a
result, treated offerors unequally. Specifically, PDMG maintains
that, after the initial rounds of discussions--during which the
agency asked PDMG about its experience as it related to
performing the RFP's mortgagee compliance requirements--the
agency continued to have a concern in the area, but did not
again raise it with PDMG. The protester contrasts this with the
agency's actions in conducting discussions with SAAM; in both
the first and second rounds of discussions, the agency pointed
out to SAAM that its prices for certain line items appeared low.
PDMG asserts that the agency's repeated discussions with SAAM in
the area of price, compared to the single round of technical
discussions with PDMG covering the agency's experience concern,
evidence disparate treatment. This argument is without merit.
PDMG's proposals received good ratings in the area of experience
following the agency's discussions in the area. AR, exhs. 9 at
80, 10 at 57. Agencies are not required to discuss every element
of a technically acceptable proposal that receives less than the
maximum possible score, nor are they required to afford an
offeror multiple opportunities to cure a weakness remaining in a
proposal that previously was the subject of discussions. Bioqual,
Inc. , B-259732.2., B259732.3, May 15, 1995, 95-1 CPD 243 at 45.
In any case, the record shows that the two firms were given the
same opportunity to revise their proposals as to both technical
matters and price during the first round of discussions, AR,
exhs. 5, 6, 7, 8, and that revisions for both firms were limited
to the pricing proposals during the second round. Id. Thus,
contrary to PDMG's assertion, both firms received virtually
identical discussions, albeit in different proposal areas
depending on the particulars of their offers. (Portfolio
Disposition Management Group, LLC, B-293105.7, November 12,
2004) (pdf)
Chapman also argues that HUD misled it into believing that its
responses to the discussion questions had satisfied HUD's
concerns. Specifically, Chapman asserts that, during each round
of discussions, HUD required Chapman to address only those
issues currently raised and informed it that all prior issues
had been resolved. Chapman's assertions are belied by the
record. While HUD's discussion letters included the statement
Your written responses to the written negotiations/ discussions
should address only the areas set forth above. . . . (emphasis
in original), the letters nowhere stated that prior issues had
been resolved, and (other than the initial letter, which did not
request FPRs) specifically advised that offerors may address any
area in their FPR. Discussion Letters dated Apr. 27, 2004, May
21, 2004, and June 8, 2004. (Chapman
Law Firm, LPA, B-293105.6, B-293105.10, B-293105.12,
November 15, 2004) (pdf)
NIH's discussions with Cygnus did not comply with the
requirement that discussions be meaningful. As noted above, in
explaining why THG's proposal was superior to Cygnus's proposal
such that, notwithstanding the significantly lower cost of
Cygnus's proposal, THG's proposal represented the best value to
the government, the source selection authority cited a number of
weaknesses in Cygnus's proposal (as well as strengths in THG's
proposal). NIH, however, failed to raise several of these
weaknesses during the discussions with Cygnus. Thus, the agency
failed to advise Cygnus that the agency viewed as a major
weakness (under the single most important technical evaluation
subcriterion) the evaluated limited [DELETED]; had assigned a
weakness to Cygnus's proposal on the basis that [DELETED]; and
had concluded that Cygnus, although displaying an understanding
of the scope of work, had not presented a [DELETED]. At the
least, in conducting discussions with Cygnus, the agency was
required to discuss the first of these concerns, since the
agency indisputably viewed it as major weakness. Moreover, while
NIH did raise other matters of concern during discussions, the
record indicates that the agency misled the protester as to the
results of those discussions, advising Cygnus that it had
successfully addressed the agency's concerns when this in fact
does not appear to have been the case. In this regard, NIH
advised Cygnus during discussions of its concern that the
proposed leader of Cygnus's team of meeting planners would
[DELETED]. Further, NIH viewed Cygnus's failure to furnish
samples of its graphics designers' work to be a major weakness,
and the agency therefore requested that Cygnus submit such
samples. NIH Discussions Letter to Cygnus, Oct.9, 2002. In
response, Cygnus sought to explain its rationale for the
specified level of effort for [DELETED]. In addition, Cygnus
furnished [DELETED]. Cygnus Discussions Response, Oct. 24, 2002.
NIH also requested and received from Cygnus additional
information regarding, and verification of, several elements of
Cygnus's proposed costs, and the agency specifically negotiated
[DELETED]. See , e.g. , NIH Discussion Letters to Cygnus, Oct.9,
2002, Dec. 2, 2002, and Jan. 28, 2003. NIH did not find Cygnus's
response with respect to the team [DELETED] to be satisfactory,
and, according to the agency, it [DELETED]. Further, as noted
above, the agency considered the costs negotiated with Cygnus to
be [DELETED]. Nevertheless, notwithstanding its continuing
concerns with Cygnus's proposal, the agency advised Cygnus in
the March 26 request for an FPR that as a result of the oral
discussions with it, "in which we negotiated cost issues
concerning your proposal," including the [DELETED], a "total
estimated cost of[DELETED] . . . is considered to be fair and
reasonable." NIH Request to Cygnus for FPR, Mar. 26, 2003. NIH
further advised Cygnus on March 27 that "[d]iscussions
concerning Cygnus Corporation's proposal have concluded... . It
is understood that these discussions have resulted in agreement
of all technical and cost issues raised during negotiations."
NIH Request to Cygnus for FPR, Mar. 27, 2003. Likewise, when the
agency afforded Cygnus and the other offerors on April30 an
opportunity to submit a second FPR, it advised Cygnus in its
letter that "discussions held on March 26, 2003, resulted in
agreement of all technical and cost issues raised during
negotiations." NIH Request to Cygnus for FPR, Apr. 30, 2003. (Cygnus
Corporation, Inc., B-292649.3; B-292649.4, December 30,
2003) (pdf)
Here, ASUS admits that, “[d]uring discussions . . . the Navy
expressed concerns about [the subcontractor’s] size and its
capability to perform the subcontracted work if it were to
experience rapid growth as a result of this project.” ASUS
Comments at 7. However, ASUS notes that, in response to these
expressed concerns, it provided financial records regarding the
subcontractor’s viability, a corporate guarantee from ASUS’s
parent company, and an explanation of the subcontractor’s plans
to hire the workers from the existing government workforce
necessary to operate the wastewater systems. ASUS argues that
the agency’s apparent “acceptance” of the information and
“failure to point out any continuing perceived weaknesses” was
misleading and denied ASUS the opportunity to revise it
proposal. Id. at 8. We disagree. Nothing in the record
suggests that the agency misled ASUS regarding its concerns.
ASUS has pointed to no affirmative statements by the Navy
indicating that the agency viewed the concerns it had raised
regarding the proposed subcontractor as having been resolved.
Further, since the agency was not required to reiterate concerns
that were not alleviated after reviewing the protester’s
response to the initial discussions, OMV Med., Inc. , supra ,
the mere fact that the Navy remained silent after the
protester’s response could not reasonably be understood here as
an indication that the agency found ASUS’s response to be
satisfactory. (American States
Utilities Services, Inc., B-291307.3, June 30, 2004) (pdf)
Here, as discussed above, despite Lockheed’s inclusion in its
initial proposal of “contractor-specific” savings, including the
savings associated with the [deleted], the agency declined
during discussions to indicate in any way that such savings
would be excluded from the agency’s calculation of AUPC.[13] The
agency asserts that Lockheed should have known that
“contractor-specific” savings would be excluded from the
agency’s AUPC calculation due to the RFP’s statements that an
“independent Government estimate” of AUPC would be conducted and
that various estimating tools would be used to “either validate
contractors’ cost estimates or to develop Government cost
estimates.” RFP § M.3.1.1.1. We disagree. Neither the language
of the solicitation, nor the information provided by the agency
during discussions, reasonably placed the offerors on notice
that “contractor-specific” savings would have no effect on the
agency’s calculation of AUPC. Although we agree that, if the
agency actually intends to compete the follow-on production
contract, there is nothing inherently unreasonable in evaluating
only “design-specific” costs,[14] the offerors were not clearly
advised of this. As noted above, the RFP stated that the agency
would evaluate the AUPC of “the offeror’s proposed munition” and
that such evaluation would be based on an assessment of “the
bidders’ production cost estimates.” RFP § M.3.1.1.1. Further,
the agency clearly knew, or should have known, that Lockheed’s
initially proposed AUPC was based on “contractor-specific”
costs, including the costs associated with the proposed
[deleted]; yet the agency failed to advise Lockheed during
discussions that such costs would be replaced with “industry
rates” in calculating the evaluated AUPC. Consistent with the
terms of the solicitation, and the information provided during
discussions, Lockheed reasonably believed that it could reduce
its evaluated AUPC by increasing its proposed
“contractor-specific” savings. On this record, the agency failed
to conduct meaningful discussions because it failed to advise
Lockheed that “contractor-specific” savings would not be
reflected in the agency’s calculation of AUPC. (Lockheed
Martin Corporation, B-293679; B-293679.2; B-293679.3, May
27, 2004) (pdf)
USF does not protest the evaluation of its proposed price.
Rather, USF maintains that the agency failed to engage in
meaningful discussions with it by failing to provide adequate
notice that its price exceeded the government estimate, and by
failing to adequately discuss the implications of its “all or
none” proposal. With respect to the former point, the record
shows that the agency did apprise USF in the second negotiation
message that its proposed price exceeded the government
estimate. USF maintains, however, that when it thereafter
submitted pricing that continued to exceed the government
estimate, the agency was required to again raise the matter with
the firm. With respect to the latter point, the record shows
that, in its request for FPRs, the agency asked USF to clarify
whether its offer was still “all or none.” AR, exh. 12, at 1.
USF maintains that the agency was required to apprise it of the
fact that unbundling the proposal could have made it eligible
for award of the wastewater system. We have no basis to object
to the adequacy of discussions here. Discussions are legally
adequate where offerors are advised of the weaknesses, excesses
and deficiencies in their proposals. Professional Performance
Dev. Group, Inc., B‑279561.2 et al., July 6, 1998, 99-2 CPD ¶ 29
at 5. While discussions should be as specific as practicable,
there is no requirement that they be all-encompassing or
extremely specific in describing the agency's concerns; rather,
the legal requirement is that they generally lead offerors into
the areas of their proposals that require amplification or
correction, without being misleading. Id. Where an agency has
advised an offeror of an area of concern, there is no legal
requirement that it raise the issue again in a subsequent round
of discussions, even where the issue continues to be of concern
to the agency. Id. at 5 n.3. (USFilter
Operating Services, Inc., B-293215, February 10, 2004) (pdf)
An agency is not required to afford offerors all encompassing
discussions, or to discuss every aspect of a proposal that
receives lower than the maximum score, and is not required to
advise an offeror of a minor weakness that is not considered
significant, even where the weakness subsequently becomes a
determinative factor in choosing between two closely ranked
proposals. Northrop Grumman Info. Tech., Inc., B‑290080 et al.,
June 10, 2002, 2002 CPD ¶ 136 at 6. Here, none of the identified
weaknesses prevented AO’s proposal from being considered fully
acceptable or otherwise from having a reasonable chance of
receiving the award. Rather, the weaknesses merely resulted in
AO’s proposal being rated good rather than excellent under the
factors in question, and the award ultimately was made to AMTEC,
not because AO’s proposal was deficient, but because AMTEC’s was
superior. Development Alternatives, Inc., B-279920, Aug. 6,
1998, 98-2 CPD ¶ 54 at 7. Under these circumstances, the agency
was not required to discuss these weaknesses with AO. (American
Ordnance, LLC, B-292847; B-292847.2; B-292847.3, December 5,
2003) (pdf)
Although discussions must address at least deficiencies and
significant weaknesses identified in proposals, the scope and
extent of discussions are largely a matter of the contracting
officer’s judgment. In this regard, we review the adequacy of
discussions to ensure that agencies point out weaknesses that,
unless corrected, would prevent an offeror from having a
reasonable chance for award. For discussions to be meaningful,
they must lead offerors into the areas of their proposals
requiring amplification or revision. The Communities Group,
B‑283147, Oct. 12, 1999, 99-2 CPD ¶ 101 at 4. The agency
provided MacB with meaningful discussions. Specifically, it
issued several evaluation notices (EN), two of which requested
clarification of MacB’s plans to use incumbent personnel. The
first sought clarification of the “commitment of individuals
listed as key technical personnel . . . and . . . who they
propose to fill key . . . positions if incumbents are not
interested.” AR 14 at 1. A second EN sought clarification of an
apparent contradiction in MacB’s proposal relating to its plan
to offer the right of first refusal to incumbent personnel while
at the same time proposing to have 30 percent of the effort
staffed by subcontractor personnel. Id. While these ENs did not
specifically refer to “risk,” they clearly were sufficient to
communicate the agency’s concerns about MacB’s ability to
successfully acquire the incumbent workforce, upon which the
moderate risk rating ultimately was based. This satisfied the
requirement for meaningful discussions in this area. (MacAulay-Brown,
Inc., B-292515; B-292515.2, September 30, 2003) (pdf)
The agency's initial evaluation under this sub-criterion
downgraded M&S Farms' proposal for not identifying what each
individual would do, and downgraded Carr's proposal to the same
degree because its resumes did not list references. Agency
Report, Tab 7, Initial Rating Sheets for M&S Farms'
Proposal, at 51, 109; Tab 8, Initial Rating Sheets for Carr's
Proposal, at 22, 51. Discussions with M&S Farms did not
include a question regarding this sub-criterion, or otherwise
identify the concern for which M&S Farms' proposal was
downgraded, Agency Report, Tab 11, Discussions with M&S
Farms, but discussions with Carr did include a question that
disclosed the agency's concern under this sub-criterion. Agency
Report, Tab 12, Discussions with Carr (Feb. 14, 2002), at 2.
Carr then provided the requested references and the agency
increased Carr's score to the maximum points available under the
sub-criterion, which accounts for the majority of the difference
in technical scores between these proposals. Agency Report, Tab
14, Carr's Response to Discussions, at 34; Tab 17, Revised
Rating Sheets for Carr's Proposal, at 3. The agency thus treated
the offerors unequally on this point, with the awardee receiving
a prejudicial competitive advantage as a result. (M&S
Farms, Inc., B-290599, September 5, 2002) (pdf)
However,
as the agency points out, this was just one of several noted
weaknesses in Northrop's approach to performing the contract,
with no indication that it was considered significant. COR at
23-24. This being the case, and since there is no evidence that
the weakness prevented the proposal from being rated acceptable
under the systems management/program management subfactor, or
otherwise prevented Northrop from having a reasonable chance of
receiving the award, the agency was not required to discuss this
issue with Northrop. See Brown & Root, Inc. and Perini
Corp., a joint venture, supra. (Northrop
Grumman Information Technology, Inc., B-290080; B-290080.2;
B-290080.3, June 10, 2002) (pdf)
While agencies generally are
required to conduct meaningful discussions by leading offerors
into the areas of their proposals requiring amplification, this
does not mean that an agency must "spoon-feed" an
offeror as to each and every item that could be revised or
otherwise addressed to improve its proposal. LaBarge Elecs.,
B-266210, Feb. 9, 1996, 96-1 CPD para. 58 at 6. (DeLeon
Technical Services, Inc.; TekStar, Inc., B-288811;
B-288811.2; B-288811.3, December 12, 2001)
Where agency knew or should have
known that the protester interpreted the solicitation as
limiting technical proposals to 100 pages, discussions with the
protester were not meaningful when the agency did not advise
protester that the solicitation permitted 200 page proposals,
declined to advise the protester of the agency's repeatedly
expressed concerns that the protester's proposal lacked detail,
and advised the protester there were no technical weaknesses in
its proposal. (Bank
of America, B-287608; B-287608.2, July 26, 2001)
Under Federal Acquisition
Regulation (FAR) § 15.306(e)(3), "the [CO] may inform an
offeror that its price is considered by the Government to be too
high, or too low, and reveal the results of the analysis
supporting that conclusion." This language clearly gives
the CO discretion to inform the offeror that its price is too
high, but does not require that the CO do so, especially where,
as here, the agency does not consider the price a significant
weakness or deficiency that the offeror could alter or explain
to enhance the proposal's potential for award. National
Projects, Inc., B-283887, Jan. 19, 2000, 2000 CPD
¶ 16 at 5; see also KBM Group, Inc.,
B-281919, B-281919.2, May 3, 1999, 99-1 CPD ¶ 118 at 8-9
(agency did not mislead protester during discussions, even
though award was ultimately made based on price and agency did
not inform protester that its price was higher than awardee's
price, where agency did not believe that protester's price was
too high for the approach taken). (SOS Interpreting,
Ltd., B-287477.2, May 16, 2001)
The agency's discussions with
IRRI specifically identified the individual CLINs for which the
agency considered IRRI's proposed prices too low, which
constituted half of the CLINs, as well as that IRRI's overall
price was too low. It then afforded IRRI an unrestricted
opportunity to submit final proposal revisions. The record thus
shows that the Air Force conducted meaningful discussions on the
issue. (International Resources Recovery,
Inc., B-287160, March 30, 2001)
We will not find that an agency
improperly failed to advise an offeror of a weakness reasonably
viewed during the evaluation as minor merely because, as the
competition played out, the weakness could have been a
determinative factor in choosing between two closely ranked
proposals. Brown & Root, Inc. and Perini Corp., a joint
venture, B-270505.2, B-270505.3, Sept. 12, 1996, 96-2 CPD para.
143 at 6. (Millar Elevator Service
Company, B-284870.4, December 27, 2000)
This case highlights the
challenge that an agency may face when, for whatever reason, it
reevaluates initial proposals after discussions are complete. If
during the reevaluation of proposals the agency identifies
concerns that would have had to be raised had they been
identified before discussions were held, the agency is required
to reopen discussions in order to raise the concerns with the
offerors. Mechanical Contractors, S.A., supra, at 5-6; CitiWest
Properties, Inc., supra, at 5. The key fact is that the concerns
(while identified relatively late) relate to the proposals as
they were prior to discussions. (DevTech
Systems, Inc., B-284860.2, December 20, 2000)
Contracting agencies are not
obligated to afford all-encompassing discussions that
"spoon-feed" an offeror each item that must be
addressed to improve a proposal; agencies are only required to
lead offerors into the areas of their proposals considered
deficient and requiring amplification. (SDS International,
B-285821, September 21, 2000)
Contracting agencies are not
obligated to afford all-encompassing discussions that
"spoon-feed" an offeror each item that must be
addressed to improve a proposal; agency reasonably led protester
into the areas of its proposal with shortcomings that warranted
amplification or clarification. (Arctic Slope World Services,
Inc., B-284481; B-284481.2, April 27, 2000)
Allegation that discussions with
protester were not meaningful is sustained where the record
shows that the evaluators were concerned over the protester's
pricing methodology and the source selection official shared
that concern, but the protester was not afforded an opportunity
during discussions to explain its pricing strategy. (ACS
Government Solutions Group, Inc., B-282098; B-282098.2;
B-282098.3, June 2, 1999)
For discussions to be
meaningful, they must lead offerors into the areas of their
proposals requiring amplification or revision; the agency is not
required to "spoon-feed" an offeror as to each and
every item that could be revised so as to improve its proposal,
however. Du and Assocs., Inc., supra, at 7-8; Applied Cos.,
B-279811, July 24, 1998, 98-2 CPD para. 52 at 8. (LB&B Associates,
Inc., B-281706, March 24, 1999)
Protest that discussions were
not meaningful because agency failed to point out excesses in
protester's technical proposal is denied where claimed
beneficial features in fact were not excesses, but rather (1)
were considered by the agency to be desirable, (2) were simply
protester's approach to complying with the solicitation
requirements, or (3) did not render the proposal unacceptable,
result in a significant reduction in score, or result in an
unreasonable, grossly excessive price. (Consolidated Engineering Services,
Inc, B-279565.5, March 19, 1999)
Written discussion questions
generated by a contracting agency should reasonably apprise
offerors of the areas that the agency considers deficient such
that the offerors will understand the agency's concerns. (Stratus Systems,
Inc., B-281645, February 24, 1999)
|