Prior to the submission of the agency’s report,
the Air Force and Northrop Grumman requested that we summarily
dismiss a substantial portion of Boeing’s protest as untimely.
The agency and intervenor argued that some of Boeing’s protest
grounds were untimely challenges to alleged, apparent
solicitation improprieties. They also argued that some of
Boeing’s challenges to the agency’s evaluation of proposals were
untimely because Boeing was allegedly aware of the bases of
these protest grounds during the competition, but did not
protest until after award and the firm’s receipt of a post‑award
debriefing.
Our Bid Protest Regulations contain strict rules for the timely
submission of protests. These timeliness rules reflect the dual
requirements of giving parties a fair opportunity to present
their cases and resolving protests expeditiously without
disrupting or delaying the procurement process. Peacock, Myers &
Adams, B‑279327, Mar. 24, 1998, 98-1 CPD para. 94 at 3-4;
Professional Rehab. Consultants, Inc., B-275871, Feb. 28, 1997,
97-1 CPD para. 94 at 2. Under these rules, a protest based on
alleged improprieties in a solicitation that are apparent prior
to closing time for receipt of proposals must be filed before
that time. 4 C.F.R. sect. 21.2(a)(1). Protests based on other
than alleged improprieties in a solicitation must be filed not
later than 10 days after the protester knew or should have known
of the basis for protest, whichever is earlier. 4 C.F.R. sect.
21.2(a)(2). Our regulations provide an exception to this general
10-day rule for a protest that challenges “a procurement
conducted on the basis of competitive proposals under which a
debriefing is requested and, when requested, is required.” Id.
In such cases, as here, with respect to any protest basis which
is known or should have been known either before or as a result
of the requested and required debriefing, the protest cannot be
filed before the debriefing date offered, but must be filed not
later than 10 days after the date on which the debriefing is
held. Id.; see Bristol-Myers Squibb Co., B‑281681.12,
B-281681.13, Dec. 16, 1999, 2000 CPD para. 23 at 4.
We did not, and do not now, agree with the Air Force and
Northrop Grumman that Boeing’s protest is a challenge to the
ground rules established by the RFP for this procurement. We
find that Boeing, rather than objecting to any of the RFP’s
requirements or evaluation criteria, is instead protesting that
the Air Force failed to reasonably evaluate proposals in
accordance with the RFP’s identified requirements and evaluation
criteria. We also do not agree with the agency and intervenor
that, because Boeing was informed during the competition of the
agency’s view of the merits of its proposal and/or how the
proposals were being evaluated, Boeing was required to protest
the agency’s evaluation or evaluation methodology prior to award
and to the protester’s receipt of its required debriefing. Even
where the protester is apprised of agency evaluation judgments
with which it disagrees or where it believes the evaluation is
inconsistent with the solicitation’s evaluation scheme, our Bid
Protest Regulations require that these protest grounds be filed
after the receipt of the required debriefing.[41] See 4 C.F.R.
sect. 21.2(a)(2); see also 61 Fed. Reg. 39039, 39040 (July 26,
1996) (“to address concerns regarding strategic or defensive
protests, and to encourage early and meaningful debriefings,” a
protester shall not file an initial protest prior to its
required debriefing); Rhonda Podojil--Agency Tender Official,
B‑311310, May 9, 2008, 2008 CPD para. 94 at 3 (application of
debriefing exception to A‑76 competitions conducted on the basis
of competitive proposals).
(The
Boeing Company, B-311344; B-311344.3; B-311344.4;
B-311344.6; B-311344.7; B-311344.8; B-311344.10; B-311344.11,
June 18, 2008) (pdf)
Our timeliness rules reflect the dual requirements of giving
parties a fair opportunity to present their cases and resolving
protests expeditiously without unduly disrupting or delaying the
procurement process. Air Inc.--Recon., B-238220.2, Jan. 29,
1990, 90-1 CPD para. 129 at 2. In order to prevent these rules
from becoming meaningless, exceptions are strictly construed and
rarely used. Id. The “good cause” exception is limited to
circumstances where some compelling reason beyond the
protester’s control prevents the protester from filing a timely
protest. Dontas Painting Co., B-226797, May 6, 1987, 87-1 CPD
para. 484 at 2. The significant issue exception is limited to
untimely protests that raise issues of widespread interest to
the procurement community, and which have not been considered on
the merits in a prior decision. Schleicher Cmty. Corps. Ctr.,
Inc., B-270499.3 et al., Apr. 18, 1996, 96-1 CPD para. 192 at 7.
Here, Goel has offered no compelling reason for its failure to
protest prior to bid opening, thus the “good cause” exception
has no application. We also see nothing in the record to suggest
that Goel’s protest issue is of widespread interest to the
procurement community warranting its resolution in the context
of an otherwise untimely protest. As a consequence, we decline
to address this protest issue here.
(Goel Services, Inc.,
B-310822.2, May 23, 2008) (pdf)
While, as discussed above, our Bid
Protest Regulations provide that a protest to our Office filed
within 10 days after resolution of an agency-level protest is
timely, even when this is after the closing date, that protest
must raise the same issue as the agency-level protest. A protest
raising a new issue cannot claim the benefit of the earlier
agency-level protest for timeliness purposes. See, e.g.,
Rochester Optical Mfg. Co., B- 292137.2, Mar. 16, 2004, 2004 CPD
para. 120 at 4 n.3 (protest filed within 10 days of decision on
agency-level protest is untimely where protest is filed after
closing date and raises a new issue). Therefore, MTC’s April 10
agency-level protest, which did not raise the set-aside issue,
has no bearing on the timeliness of this protest, and cannot
provide a vehicle for viewing MTC’s protest here as timely. (Masai
Technologies Corporation, B-400106, May 27, 2008) (pdf)
Our Bid Protest Regulations contain strict rules for the timely
submission of protests. These timeliness rules reflect the dual
requirements of giving parties a fair opportunity to present
their cases and resolving protests expeditiously without
disrupting or delaying the procurement process. Professional
Rehab. Consultants, Inc., B-275871, Feb. 28, 1997, 97-1 CPD para.
94 at 2. Under these rules, a protest such as the ATO’s, based
on other than alleged improprieties in a solicitation, must be
filed not later than 10 days after the protester knew or should
have known of the basis for protest, whichever is earlier. 4
C.F.R. sect. 21.2(a)(2) (2007). An exception to this general
rule is a protest that challenges “a procurement conducted on
the basis of competitive proposals under which a debriefing is
requested and, when requested, is required.” Id. In such cases,
with respect to any protest basis which is known or should have
been known either before or as a result of the debriefing, the
protest must be filed not later than 10 days after the date on
which the debriefing is held. The MIL Corp., B-297508,
B-297508.2, Jan. 26, 2006, 2006 CPD para. 34 at 5.
In addressing the timeliness of the ATO’s protest, we first turn
to the question of when the ATO knew or should have known the
basis for protest. In this regard, the ATO argues that in
evaluating the technical proposal of the agency tender, the Army
deviated from the RFP’s evaluation factors and subfactors, which
established the requirements of acceptability. Specifically, the
protester alleges that during discussions, the Army made clear
that, in order to be found technically acceptable, the agency
tender was required to increase its staffing to meet performance
standards exceeding those set forth in the RFP. The ATO
generally alleges that the increase in costs associated with
meeting these higher standards resulted in the agency tender
having a higher adjusted price than that of Sodexho’s proposal.
Protest at 1, 3. Since the allegedly higher standards were
conveyed by the Army through discussions, the ATO knew or should
have known that the Army’s imposition of allegedly higher
standards had a prejudicial effect when she learned the results
of the cost comparison on February 12, indicating that Sodexho
had prevailed based on price. The protest, however, was not
filed until March 3, more than 10 days after February 12.
Therefore, in order for the ATO’s protest to be timely, it must
fall within the debriefing exception noted above. As stated
previously, this exception applies only where the debriefing
provided is in connection with “a procurement conducted on the
basis of competitive proposals under which a debriefing is
requested and, when requested, is required.” 4 C.F.R. sect.
21.2(a)(2). In addressing this question, we note that the term
“competitive proposals” is not defined by our Bid Protest
Regulations, nor by statute or regulation. See Systems Plus,
Inc. v. United States, 68 Fed. Cl. 206 (2005); The MIL Corp.,
supra, at 6. However, we have previously determined that the use
of negotiated procedures in accordance with Federal Acquisition
Regulation (FAR) Part 15 and as evidenced by the issuance of an
RFP, constitutes a procurement conducted on the basis of
competitive proposals for purposes of this exception to our
timeliness rules. The MIL Corp., supra; Professional Rehab.
Consultants, Inc., supra. Here, consistent with the A-76
competition process, the Army expressly incorporated and used
FAR Part 15 procedures as the framework for the A-76
competition. In this regard, pursuant to the competition process
established by the Circular, the Army issued a solicitation
seeking “proposals” (the RFP), which provided for a
lowest‑priced, technically acceptable source selection in
accordance with FAR sect. 15.101-2. The Army held discussions
with the protester and private-sector offerors in accordance
with FAR sect. 15.306, which resulted in revisions to the agency
tender and private-sector proposals consistent with FAR sect.
15.307, and after announcing the results of the cost comparison,
consistent with FAR Part 15, the Army provided the protester and
Sodexho, at their request, with debriefings. As a consequence,
we conclude that the A-76 competition here was conducted on the
basis of “competitive proposals.”
The next question is whether the debriefing was a “required”
debriefing for the purpose of applying our timeliness rules. In
this regard, when a contract is awarded on the basis of
“competitive proposals,” 10 U.S.C. sect. 2305(b)(5)(A),
implemented through FAR sect. 15.506(a)(1), provides that “an
unsuccessful offeror, upon written request received by the
agency within 3 days after the date on which the unsuccessful
offeror receives the notification of the contract award, shall
be debriefed and furnished the basis for the selection decision
and contract award.” The agency and intervenor argue that the
debriefing which the contracting officer provided the ATO here
was not a “required” debriefing for several reasons. Both point
to the fact that the Circular does not reference the type of
required debriefing contemplated by FAR sect. 15.506, but merely
requires agencies to offer a debriefing “in accordance with FAR
sect. 15.503,” which pertains solely to award notice
requirements for unsuccessful offerors. OMB Cir. A-76, Attach. B
para. D.6.d; FAR sect. 15.503 Notifications to Unsuccessful
Offerors. The intervenor further argues that the ATO’s
debriefing was not required because such debriefings are limited
to “offerors,” and the ATO is not an “offeror.” In support of
this contention, the intervenor notes that the ATO cannot be an
offeror, since if the agency tender were to prevail in the
competition, it would not result in the award of a contract,
citing our decision in Dan Duefrene et al., B-293590.2 et al.,
Apr. 19, 2004, 2004 CPD para. 82 at 5. The intervenor and the
agency further argue that, even if the possibility of a required
debriefing existed, the debriefing provided to the ATO would not
qualify, since it was not timely requested. In addressing the
specific question of whether the debriefing at issue was a
required debriefing for the purpose of establishing timeliness,
we first address the general assertion by the agency and the
intervenor that debriefings are not required in the context of
an A-76 competition. We reject this contention for the simple
reason that the statutory debriefing requirements established by
10 U.S.C. sect. 2305(b) and FAR Part 15 hinge on whether an
agency is making an award on the basis of “competitive
proposals.” Where an agency makes its selection decision under
an A-76 competition on the basis of “competitive proposals,” as
in this case, we think that the statutory and regulatory
debriefing scheme is invoked, notwithstanding the more limited
debriefing guidance set forth in the Circular.
Turning to the question of whether the public-sector competitor
in an A-76 competition can rely on the debriefing exception to
our timeliness rules for the purpose of establishing the
timeliness of its protest at our Office despite the fact that it
is not technically an “offeror,” we note that the standing of
the public-sector competitor to protest public-private
competitions conducted pursuant to A-76 has a lengthy history.
In addressing the various issues in this regard, GAO has
consistently recognized the importance of establishing, in the
conduct of A-76 competitions, a level playing field between
public and private-sector competitors, a principle unanimously
agreed to by the Congressionally-chartered Commercial Activities
Panel. Commercial Activities Panel, Final Report: Improving the
Sourcing Decisions of the Government (Apr. 2002) at 10 (stating
“[t]he Panel believes that in order to promote a more level
playing field on which to conduct public-private competitions,
the government needs to shift . . . to a FAR-type process under
which all parties compete under the same set of rules”).
Consistent with this principal, it is our intent to apply our
timeliness rules to public‑ and private-sector protesters of
A-76 competitions in an even-handed manner. As a consequence,
where an agency conducts an A-76 competition on the basis of
competitive proposals, as in this case, thereby triggering the
debriefing requirements established by statute and the FAR, we
will interpret those provisions as applying equally to
public-sector competitors for the purpose of invoking the
debriefing exception to our timeliness rules. For the same
reason, however, when protesting the results of an A-76
competition, in order to fall within the debriefing exception to
our timeliness rules, a public-sector competitor, like its
private-sector counterpart, will be held to compliance with the
rules necessary to establish its debriefing as a “required”
debriefing. As noted above, a debriefing is only required where
it is timely requested--within 3 days of receiving notice of the
award decision. In this case, the ATO’s written request for the
debriefing was made 7 days after receiving notice of the award
decision. We therefore conclude that, by its terms, the
debriefing exception does not apply. Absent application of the
debriefing exception, the ATO was required to file its protest
within 10 days of when it knew or should have known its basis of
protest; because the protest was filed more than 10 days later,
it is untimely. (Rhonda
Podojil--Agency Tender Official, B-311310, May 9, 2008) (pdf)
Apptis
first protests that an organizational conflict of interest (OCI)[5]
existed in connection with the evaluation due to DISA’s use of a
contractor employee, C.F.,[6] as an SSEB evaluator.
Specifically, Apptis alleges that at the time he evaluated
offerors’ proposals, C.F. was employed by Shim Enterprises,
Inc., a support services contractor for the DISA CS site in
Ogden, Utah. Shim, the protester contends, was responsible for
performing systems management for DISA at the time and location
that a service outage occurred, and for which the equipment
and/or support of Apptis’ primary subcontractor here, EMC, was
alleged to have been at fault (the so-called “Fairchild chip
issue”). Thus, Apptis asserts, Shim had a motivation to deflect
blame to EMC and avoid any responsibility it may have had for
the service outage problem that occurred. Apptis argues that
because the agency used as an evaluator an employee of a firm
that had an impermissible OCI, the agency’s evaluation of
proposals was unreasonable and the award to ViON improper. The
agency argues that Apptis’s protest regarding Shim’s alleged OCI
is untimely. In support of its position, the agency contends
that the RFP gave offerors notice of the fact that DISA planned
to utilize Shim in the evaluation. Further, DISA asserts that
the protester was aware of Shim’s role as DISA’s support
services contractor for the Ogden site, and had interacted
directly with Shim regarding the Fairchild chip failure
incident. The agency contends that because Apptis was aware of
the potential OCI involving Shim during the solicitation
process, but did not protest this issue until after the closing
time, the issue is untimely. We agree.
Our Bid Protest Regulations contain strict rules requiring
timely submission of protests. Under these rules, protests based
upon alleged improprieties in a solicitation which are apparent
prior to bid opening or the time set for receipt of initial
proposals must be filed prior to bid opening or the time set for
receipt of initial proposals. 4 C.F.R. sect. 21.2(a)(1) (2007).
Similarly, protests not based on solicitation improprieties must
be filed within 10 days after the basis of protest is known or
should have been known, whichever is earlier. 4 C.F.R. sect.
21.2(a)(2). As a general rule, a protester is not required to
protest that another firm has an impermissible OCI until after
the agency has made an award determination. REEP, Inc.,
B-290688, Sept. 20, 2002, 2002 CPD para. 158 at 1-2. A different
rule applies, however, where a solicitation informs offerors
that the agency plans to utilize the services of a third-party
contractor to assist in the evaluation of proposals, and the
protester knew or should have known, by means of due diligence,
that the nongovernmental entity may have, as alleged here,
impaired objectivity. In such cases, the protester cannot wait
until an award has been made to file its protest of an
impermissible OCI, but instead must protest before the closing
time for receipt of proposals. See Abt Assocs., Inc., B-294130,
Aug. 11, 2004, 2004 CPD para. 174 at 2. Here, the RFP expressly
identified Shim as a nongovernmental evaluator of offerors’
proposals, RFP sect. L at 57, and the protester itself indicates
that information regarding Shim’s role as DISA’s support
services contractor for the Ogden location was readily available
at Shim’s website. Protester’s Comments, Mar. 26, 2007, exh. A,
Printout of Shim Enterprise webpage. Moreover, EMC employees had
frequent and regular dealings with C.F. at the Ogden site, dealt
directly with C.F. regarding the Fairchild chip failure
incident, and were aware that C.F. was a Shim employee.
Protester’s Comments, Mar. 26, 2007, Second Decl. of J.S.; AR,
Apr. 17, 2007, exh. 1, Decl. of M.H.; exh. 2, Decl. of C.W. We
think that, given EMC’s prior work for DISA at the Ogden site,
and that EMC was Apptis’s primary subcontractor, Apptis knew or
should have known of Shim’s role as the DISA support services
contractor for the Ogden site where EMC had had the Fairchild
chip failure issue. Apptis’s failure to protest the alleged OCI
associated with Shim’s role in the evaluation of offerors’
proposals before the closing date for receipt of proposals makes
this issue untimely. (Apptis,
Inc., B-299457; B-299457.2; B-299457.3, May 23, 2007) (pdf)
As a final matter, CAMSS argues that the ASI brand name product
itself fails to meet certain salient characteristics included in
the solicitation. This ground of protest is untimely. The
purpose of a solicitation’s statement of salient
characteristics, as set out in FAR sect. 11.104(b), is to define
the minimum characteristics of the brand name product that an
alternative “equal” product must meet. Thus, by definition, the
salient characteristics should be derived from, and should
reflect, the essential characteristics that, in the agency’s
view, the brand name product possesses. Accordingly, a
contention that the solicitation-identified brand name item does
not meet the salient characteristics is an argument that the
solicitation is defective, because the solicitation represents
that the brand name product possesses the salient
characteristics listed, when, in the protester’s view, it does
not. Any alleged inconsistency between a brand name item and the
salient characteristics used to define an “or equal” product
thus must be protested prior to the closing time for receipt of
offers, or in this case, quotations--consistent with our
standard rule for raising challenges to solicitation
improprieties. 4 C.F.R. sect. 21.1(a)(1); M/RAD Corp., B-248146,
July 29, 1992, 92-2 CPD para. 61 at 3; VTEC Labs., Inc.,
B-245481, Dec. 26, 1991, 91-2 CPD para. 581 at 3.
(CAMSS Shelters, B-309784;
B-309784.2, October 19, 2007) (pdf)
Finally, K9 contends that the agency structured the evaluation,
including mileage costs and travel time, in such a manner that,
given its location, it could not realistically compete from a
price standpoint, and that its status as a disabled,
veteran-owned business was not given consideration in the
selection process. Under our Regulations, protests based on
alleged improprieties in a solicitation that are apparent prior
to the stated deadline for submitting offers must be filed
before that time. 4 C.F.R. sect. 21.2(a)(1). Here, the RFP, as
amended, clearly set forth the evaluation provisions about which
the protester complains, and the solicitation was not set aside
for service-disabled veterans. Therefore, it was apparent on the
face of the amended solicitation how the agency would evaluate
proposals, and that an offeror’s status as a service-disabled
veteran would not be a factor in the evaluation process. This
being the case, any protest by K9 challenging the evaluation
provisions had to be filed prior to the extended April 23
closing date for receipt of revised proposals. Since K9 did not
protest until June 27, its protest on these issues is untimely,
and will not be considered. (K9
Operations, Inc., B-299923, August 6, 2007) (pdf)
With that in mind, we must determine whether the ambiguity is
latent or patent since, if patent, it would have had to be
protested prior to the closing date for the submission of
proposals in order to be considered timely. Ashe Facility Servs.,
Inc., B-292218.3; B-292218.4, Mar. 31, 2004, 2004 CPD para. 80
at 11; see 4 C.F.R. sect. 21.2(a)(1). A patent ambiguity exists
where the solicitation contains an obvious, gross, or glaring
error (e.g., where the solicitation provisions appear
inconsistent on their face), while a latent ambiguity is more
subtle. Ashe Facility Servs., Inc., supra. Since Singleton’s
interpretation of the RFP did not directly conflict with any of
the other solicitation provisions, and the ambiguity came to
light in the context of the agency’s past performance
evaluation, we conclude that the ambiguity here was latent
rather than patent. Singleton’s protest is thus timely. Id. As
indicated, the agency intended the solicitation to provide that
only the offeror’s past performance, and not that of proposed
subcontractors, would be considered by the agency in evaluating
proposals and in making its source selection. The protester
states that, had it been aware prior to the closing date for the
receipt of proposals of the agency’s intended meaning, it would
have protested the propriety of that aspect of the RFP.
Protester’s Comments at 1. Given the protester’s position here,
and the indicated intent of FAR sect. 15.305(a)(2)(iii)--which
by using the term “should” advises agencies that they should
consider in their evaluations the past performance of proposed
“subcontractors that will perform major or critical aspects of
the requirement” unless they have a reasonable basis for not
doing so--the propriety of the agency’s decision not to follow
the approach advised in the FAR cannot be assumed. In our view,
there is thus a reasonable possibility that a timely protest
would have ultimately led to the agency’s adopting the FAR’s
recommended approach. Even if it did not, so that the
procurement was conducted under the agency’s current approach
(but unambiguously stated), the protester would have had an
opportunity to submit a proposal consistent with that approach.
In view of the potentially different outcome associated with
this necessarily speculative analysis, we find a reasonable
possibility that the protester was prejudiced by the agency’s
actions. (Singleton Enterprises,
B-298576, October 30, 2006) (pdf)
Our Bid Protest Regulations require that protests not
based upon alleged improprieties in a solicitation be filed not
later than 10 days after the basis of protest is known or should
have been known. 4 C.F.R. sect. 21.2(a)(2) (2005). More
specifically, a protest based upon information provided to the
protester at a statutorily-required debriefing is generally
untimely if filed more than 10 days after the debriefing. The
New Jersey & H St. Ltd. P’ship, B-288026, B-288026.2, July 17,
2001, 2001 CPD para. 125 at 2; Clean Venture, Inc., B-284176,
Mar. 6, 2000, 2000 CPD para. 47 at 4 n. 5. Here, during the
preaward debriefing, the protester was informed of the specific
critical failures upon which its bid sample reliability rating
was based, including the broken bolt critical failure which it
now challenges. Subsequent to the debriefing, however, the
agency reinstated Remington in the competitive range and
continued to consider Remington’s proposal for contract award.
It is clear, we think, that once the Army reinstated Remington’s
proposal in the competitive range of offerors to be further
considered for award, there was no agency action prior to the
award determination that was prejudicial to, and protestable by,
Remington. In fact, had Remington filed a protest here
challenging the agency’s reliability testing after being
reinstated in the competitive range and before award, the
protest would have been speculative and premature because it
would have merely anticipated prejudicial agency action. See
Computer Assocs. Int’l, Inc., B-292077.2, Sept. 4, 2003, 2003
CPD para. 157 at 4; Parcel 47C LLC, B-286324, B-286324.2, Dec.
26, 2000, 2001 CPD para. 44 at 10 n.13. Thus, we find
Remington’s protest here, filed within 10 days after Remington
was advised of the award decision, to be timely. (Remington
Arms Company, Inc., B-297374; B-297374.2, January 12, 2006)
(pdf)
Our Bid Protest Regulations contain strict rules for the
timely submission of protests. These timeliness rules reflect
the dual requirements of giving parties a fair opportunity to
present their cases and resolving protests expeditiously without
disrupting or delaying the procurement process. Peacock, Myers &
Adams, B-279327, Mar. 24, 1998, 98-1 CPD para. 94 at 3-4;
Professional Rehab. Consultants, Inc., B-275871, Feb. 28, 1997,
97-1 CPD para. 94 at 2. Under these rules, a protest such as
MIL’s, based on other than alleged improprieties in a
solicitation, must be filed not later than 10 days after the
protester knew or should have known of the basis for protest,
whichever is earlier. 4 C.F.R. sect. 21.2(a)(2) (2005). An
exception to this general rule is a protest that challenges “a
procurement conducted on the basis of competitive proposals
under which a debriefing is requested and, when requested, is
required.” Id. In such cases, with respect to any protest basis
which is known or should have been known either before or as a
result of the debriefing, the protest must be filed not later
than 10 days after the date on which the debriefing is held. Id.
Our determination of the timeliness of MIL’s organizational
conflict of interest issues therefore involves a twofold
analysis: (1) determining when MIL knew, or should have known,
its basis for protest here; and (2) determining whether MIL’s
protest involves a procurement conducted on the basis of
competitive proposals under which a debriefing was required. We
find that MIL knew or should have known this basis for protest
as of the date it received notice of the award to Anteon,
September 29. As the incumbent IT help-desk services contractor,
MIL was fully aware of Anteon’s duties and responsibilities as
the program management services contractor with the Navy; it was
this familiarity that provided MIL with the underlying factual
basis for its assertions that Anteon both had superior access to
information during the solicitation process, and would suffer
from impaired objectivity during contract performance. Further,
the agency asserts--and MIL does not deny--that the
organizational conflict of interest issues here were not raised
or even mentioned at the debriefing provided to MIL. While the
protester now argues that “it was at the debriefing that MIL
learned that the Navy made its award to an offeror with an
apparent [organizational conflict of interest] without
evaluating the [organizational conflict of interest] and without
imposing any appropriate mitigation,” MIL Response to Agency
Dismissal Request, Nov. 7, 2005, at 5, we fail to see how MIL
could first have become aware of this as a result of the
debriefing when it asked no questions and did not even raise the
issue. Rather, we find that the facts which provided MIL with
its basis of protest here were known to it as of the September
29 award notification date. Accordingly, since MIL’s protest was
not filed until October 24, we find that MIL did not protest the
organizational conflict of interest issue within 10 days of when
the protester knew or should have known of the basis of protest.
(The MIL Corporation, B-297508;
B-297508.2, January 26, 2006) (pdf)
Where a protest initially has been filed with a
contracting activity, any subsequent protest to our
Office, to be considered timely under our Bid Protest
Regulations, must be filed within 10 days of actual or
constructive knowledge of initial adverse agency action. 4
C.F.R. sect. 21.2(a)(3). The term “adverse agency action”
is defined in our Bid Protest Regulations to include the
agency’s proceeding with the receipt of proposals in the
face of the protest. 4 C.F.R. sect. 21.0(f); Carlisle Tire
& Rubber Co., B-235413, May 12, 1989, 89-1 CPD para. 457
at 2. Thus, it is our general view that once the
contracting activity proceeds with accepting offers, the
protester is on notice that the contracting activity will
not undertake the requested corrective action;
consequently, timeliness is measured from this point
rather than from the receipt of a subsequent formal denial
of the agency-level protest. Scopus Optical Indus.,
B-238541, Feb. 23, 1990, 90-1 CPD para. 221 at 2. Since
Lifecare learned of the initial adverse agency action on
August 9, but did not file its protest with our Office
until August 22, more than 10 days later, its protest is
untimely under our Bid Protest Regulations. 4 C.F.R. sect.
21.2(a)(3). These timeliness rules reflect the dual
requirements of giving parties a fair opportunity to
present their cases and of resolving protests
expeditiously without unduly disrupting or delaying the
procurement process. Air Inc.--Recon., B-238220.2, Jan.
29, 1990, 90-1 CPD para. 129 at 2. (Lifecare
Management Partners, B-297078; B-297078.2, November
21, 2005) (pdf)
Wescam maintains that the contentions presented in its
comments are not untimely because they merely provide
further support for its general protest contentions that
the Navy improperly failed to consider its alternate
proposals and that the agency’s price evaluation was
unreasonable, and that the issues raised therefore are not
independent protest grounds. Wescam’s reliance on general
articulations of its bases of protest is misplace. Where a
protester raises a broad ground of protest in its initial
submission but fails to provide details within its
knowledge until later, so that a further response from the
agency would be needed to adequately review the matter,
these later, more specific arguments and issues cannot be
considered unless they independently satisfy the
timeliness requirements under our Bid Protest Regulations.
Biospherics, Inc., B-285065, July 13, 2000, 2000 CPD para.
118 at 12-13. In this regard, we have found supplemental
protest grounds untimely which present “examples” of flaws
in the agency’s evaluation generally alleged in the
initial protest since such staggered presentation of
“examples,” each of which involves different factual
circumstances and requires a separate explanation from the
agency, constitutes precisely the piecemeal presentation
of issues that our timeliness rules do not permit. QualMed,
Inc., B-257184.2, Jan. 27, 1995, 95-1 CPD para. 94 at
12-13. (L-3 Systems Company
Wescam Sonoma, Inc., B-297323, December 3, 2005) (pdf)
As an initial matter the Air Force argues that the
challenges relating to the December 2004 sole-source award
to OSS should be dismissed as untimely. The agency
maintains that the award was announced on December 6, 2004
on the official website for the Department of Defense,
referred to as DefenseLink --
http://www.defenselink.mil/ -- and that the protesters
should have challenged the award within 10 days of this
announcement, yet they waited more than 6 months to file
their protests. In essence, the Air Force argues that the
award announcement on DefenseLink placed the protesters on
constructive notice of the sole-source award and that the
timeliness of their protests should be measured from this
date. We disagree.In support of its contention that the
protesters were on constructive notice by virtue of the
DefenseLink posting, the Air Force points to our decisions
holding that publication in the Commerce Business Daily (CBD)
or on the FedBizOpps website (which has replaced the CBD)
placed protesters on constructive notice of an agency’s
contract actions. For example, we have recognized that
publication in the CBD of an agency’s intent to enter into
a sole-source contract constitutes constructive notice of
that proposed contract action. See Fraser-Volpe Corp.,
B‑240499 et al., Nov. 14, 1990, 90-2 CPD para. 397 at 3;
S.T. Research Corp., B-232751, Oct. 11, 1988, 88-2 CPD
para. 342 at 1. Similarly, we have held that publication
on the FedBizOpps website places prospective contractors
on constructive notice of contract awards, such that
protests of the awards must be filed within 10 days of
publication. CBMC, Inc., B‑295586, Jan. 6, 2005, 2005 CPD
para. 2 at 2. These cases, however, are inapposite. The
doctrine of constructive notice creates a presumption of
notice in law that cannot be rebutted. See, e.g., Townsend
v. Little and Others, 109 U.S. 504, 511 (1883)
(“constructive notice is defined to be in its nature no
more than evidence of notice, the presumption of which is
so violent that the court will not even allow of its being
controverted”). By definition the doctrine imputes
knowledge to a party without regard to the party’s actual
knowledge of the matter at issue. Given the severity of
such a rule, our decisions holding protesters to
constructive notice of information published in the CBD
and now on FedBizOpps have been premised on the fact that
first the CBD and now FedBizOpps have been expressly
designated by statute and regulation as the official
public medium for providing notice of contracting actions
by federal agencies. See Herndon & Thompson, B-240748,
Oct. 24, 1990, 90-2 CPD para. 327 at 3 (protesters are
charged with constructive notice of contents of
procurement synopsis published in the CBD since it is the
official public medium for identifying proposed contract
actions); see also 15 U.S.C. sect. 637(e)(2)(A) (2000); 41
U.S.C. sect. 416(a)(7) (2000); FAR sect. 2.101
(designating FedBizOpps as the governmentwide point of
entry (GPE), “the single point where Government business
opportunities greater than $25,000, including synopses of
proposed contract actions, solicitations, and associated
information, can be accessed electronically by the
public”). In this case, the Air Force did not publish its
intent to enter into a sole-source contract with OSS, nor
did it provide notice of the award on FedBizOpps; rather,
the Air Force announced the December award solely on
DefenseLink. While the agency maintains that DefenseLink
is “as widely known as FedBizOpps and as eagerly perused,”
AR, Tab 2.a., Agency’s Request for Dismissal at 2,
DefenseLink has not been designated by statute or
regulation as an official public medium for providing
notice of contracting actions. As a consequence, and in
view of the sometimes harsh consequences of application of
the doctrine, we do not treat posting on DefenseLink as
giving rise to constructive notice. (WorldWide
Language Resources, Inc.; SOS International Ltd.,
B-296984; B-296984.2; B-296984.3; B-296984.4; B-296993;
B-296993.2; November 14, 2005) (pdf)
The agency initially asserts that Sigmatech’s protest is
untimely filed. In this regard, the agency first contends
that Sigmatech knew, or should have known, its basis for
protest as early as either the February 18, 2003 "sources
sought" notice or Sigmatech’s February 24 response to that
notice. These documents, the agency argues, show that
Sigmatech knew, or should have known, that the RSJPO
services were going to be procured by TACOM under a
different contract vehicle, and thus Sigmatech should have
protested at that time. However, the "sources sought"
notice is not a solicitation, and since our Office only
hears protests of solicitations, Pancor Corp., B-234168,
Mar. 29, 1989, 89-1 CPD para. 328 at 2, Sigmatech’s
protest would have been premature at that point. Lockheed
Martin Sys. Integration--Owego, B-287190.2, B-287190.3,
May 25, 2001, 2001 CPD para. 110 at 16 n.10. The agency
next asserts that the protest is untimely because it was
not filed within 10 days of the agency’s September 23,
2003 letter that informed Sigmatech that the contract
would be competed only among FSS 871 holders. However,
Sigmatech denies receiving this letter, and in any event
the RFQ still had not been issued (it was not issued until
December 5), so a protest again would have been premature.
Id. The agency also asserts that the firm did not
diligently pursue its protest after submitting its
response to the "sources sought" notice. Had it done so,
the Army argues, Sigmatech would have discovered that the
services would be procured only through TACOM under a BPA
issued to an FSS 871 contractor, and that Sigmatech would
be ineligible to compete because it did not hold an FSS
871 contract. However, nothing in the record (other than
the September 23 letter that Sigmatech denies receiving)
indicates that Sigmatech should have known that the TACOM
BPA would be the vehicle used to procure the RSJPO
services. Indeed, as noted above, the agency did not
"release" a copy of the RFQ to Sigmatech, from which the
firm may have been able to determine a basis for protest,
or specifically notify Sigmatech that the SETA work it was
performing for RFJPO was to be "bundled" into the BPA. In
fact, even after award of the Sverdrup BPA in 2003, AMCOM
placed orders for these services with Sigmatech extending
into 2005, and recompeted the requirement. Thus, on this
record, we cannot conclude that Sigmatech’s failure to
earlier become apprised of the Army’s asserted plan to
obtain these services through the Sverdrup BPA was the
result of a lack of diligent pursuit of this information
by the protester. In this regard, we resolve doubts over
issues of timeliness in favor of protesters. See LBM,
Inc., B-290682, Sept. 18, 2002, 2002 CPD para. 157 at 7.
The record before us indicates that it was not until
February 2005 that Sigmatech was informed by telephone of
the Army’s plan to procure the SETA services solely
through the Sverdrup BPA, and subsequent written
communications from the agency during February, March, and
April suggested that this plan was not final even then. In
fact, the AMSCOM ombudsman stated as recently as April 21,
2005 that TACOM was "considering my recommendations" to
compete the requirement and include small businesses in
this competition. As he informed Sigmatech, based on his
discussions with TACOM, "I believe there is a very high
probability that they will issue a competitive RFP for the
[SETA] services--and I see no reason that Sigmatech will
be precluded from competing." Protest, attach. 9, E-mail
from AMSCOM Ombudsman to Sigmatech (Apr. 21, 2005). The
agency does not deny that TACOM was still considering
whether to compete the requirement during this time. Given
that we resolve doubts of timeliness in favor of the
protester, we cannot on this record find Sigmatech’s
protest to be untimely. The record shows that on April 29,
Sigmatech was informed in writing that the SETA services
it was currently performing were going to be performed
under the TACOM BPA effective May 1. Sigmatech protested
to our Office within 10 days of this letter, and we find
that its protest was timely filed. 4 C.F.R. sect.
21.2(a)(1) (2005). (Sigmatech,
Inc., B-296401, August 10, 2005) (pdf)
TAL also contends that the award to SVO is improper
because the solicitation, a small business set-aside,
failed to include a mandatory provision regarding
limitations on subcontracting. Specifically, the RFP
omitted the provision at Federal Acquisition Regulation
sect. 52.219-14, applicable to small business set-aside
procurements, that provides that in a contract for
services (except construction), by submission of its offer
and execution of a contract, the contractor agrees that at
least 50 percent of the cost of contract performance
incurred for personnel will be expended for the
contractor’s own personnel.
An unsuccessful offeror cannot wait until learning of an
adverse award determination to file a protest of apparent
solicitation improprieties; rather, under our Bid Protest
Regulations, to be timely, a challenge to an apparent
solicitation defect must be filed prior to the closing
time for the receipt of proposals. 4 C.F.R. sect.
21.2(a)(1) (2005). Accordingly, to the extent TAL
challenges, post-award, the omission of the subcontracting
limitation from the solicitation, the protest is untimely.
Lockheed Eng’g and Mgmt. Servs., Inc.--Recon., B-212858.2,
Feb. 14, 1984, 84-1 CPD para. 193 at 1-2. (TransAtlantic
Lines, LLC, B-296245; B-296245.2, July 14, 2005) (pdf)
As an initial matter, the Navy argues that IMP's protest
should be dismissed as untimely because IMP, by its own
admission, received the Navy's decision denying its
agency-level protest on Saturday, March 12, yet did not
file its protest with our Office until March 24, more than
10 days after receipt of the agency-level protest
decision. The protester responds that it is not open for
business on weekends, and that although a vice-president
for IMP received the envelope containing the protest
decision on March 12 and then called another principle of
the company to inform him that a letter had arrived from
the Navy, the envelope was not opened until Monday, March
14. We do not agree with the Navy that the circumstances
of this case warrant application of a rule different from
the one articulated in Supreme Edgelight. The time period
for filing a protest with our Office commences with a
protester's actual or constructive knowledge of initial
adverse agency action. As in Supreme Edgelight, there
plainly was no actual knowledge in this case. Moreover, as
we found in Supreme Edgelight, the receipt of an
agency-level protest decision on a nonbusiness day, where
the notice is not actually read, does not constitute
constructive knowledge. While the Navy correctly points
out that protesters have a duty to diligently pursue their
bases for protest, we have never held, as the Navy would
have us do here, that such a duty extends to conducting
business outside of ordinary business hours (for example,
a weekend). In addition, contrary to the Navy's argument,
the position of the individual who receives the envelope
containing the decision but leaves it unopened (whether a
clerk, a principle of the company, or anyone else) has no
bearing on whether a protester has received constructive
notice of initial adverse agency action. Thus, we find
that receipt of the agency's unopened envelope containing
the decision on Saturday did not constitute constructive
knowledge of initial adverse agency action, given that
Saturday was not an ordinary business day for the
protester. Rather, we conclude that IMP first learned of
the agency's protest decision on Monday, March 14, the
next businessday. Accordingly, IMP's protest, which was
filed within 10 calendar days of that date, is timely. (International
Marine Products, Inc., B-296127, June 13, 2005) (pdf)
VSE's initial protest of the cancellation of the RFP,
filed December 30, 2004, specifically argued that the
"Government's real agenda [in canceling the RFP] is the
status quo, perpetuating improper sole source extensions
forever or until some indefinite future time." VSE's
Initial Protest at 18-19. We find that this constitutes a
timely protest of the proposed sole-source extension of EG&G's
contract. Although the agency argues that VSE did not then
contend that the sole-source extension of EG&G's contract
was the result of a lack of advanced planning but only
untimely raised this contention in its comments on the
agency report, this contention was based upon documents
provided in the agency report on VSE's initial protest and
is thus timely raised in VSE's comments. We consider VSE's
protest of the sole-source bridge contract to be timely
filed. On the other hand, Johnson Controls' protest, which
was filed on March 11, 2005, more than 10 days after the
announcement in FedBizOpps, is untimely and is dismissed.
Johnson Controls argues that it would have been premature
for it to protest the proposed sole-source action based
upon the FedBizOpps announcement because no solicitation
for the sole-source procurement had been issued and no
sole-source justification had been prepared. However,
nothing had really changed when Johnson Controls filed its
"piggy-back" protest on March 11, 2005, in that the agency
still had not issued a solicitation or prepared a
sole-source justification. We dismiss Johnson Controls'
protest as untimely. (VSE
Corporation; Johnson Controls World Services, Inc.,
B-290452.3; B-290452.4; B-290452.5, May 23, 2005) (pdf)
Further, we do not agree that the debriefing was
essentially ongoing pending the agency's answering the
protester's October 7 questions. Although the record
indicates that NGA did not answer all of New SI's
questions at the debriefing session, and New SI maintains
that there was "no statement by any NGA representative
that the debriefing process was concluded at the end of
the October 6, 2004 meeting," Declaration of New SI Chief
Executive Officer, Nov. 5, 2004, at 2, neither was there
any affirmative indication by the agency that the
debriefing would be considered concluded only after the
agency responded to further questions the protester might
have after the October 6 session. In fact, the source
selection authority (SSA) states that the contracting
officer informed New SI at the beginning of the debriefing
that "if it had any remaining questions after the
debriefing was finished . . . New SI could submit written
questions to the Contracting Officer after the debriefing
." Declaration of SSA, Nov. 5, 2004, at 1-2 (underlining
added). It is clear from this statement that the agency
considered the debriefing "finished" at the conclusion of
the October 6 session, notwithstanding that it was willing
to answer further questions the protester might have.
Given the absence of any affirmative indication from the
agency that the debriefing would remain open after the
scheduled session, we consider it to have concluded at the
end of that session. The fact that New SI may not have
been satisfied with all aspects of the debriefing, and
that it continued to pursue certain questions with the
agency, did not extend the time for filing a bid protest
based on the information provided during the debriefing.
See Handheld Sys., Inc. , B-288036, Aug. 10, 2001, 2001
CPD 142 at 2 (protester's continued questions to the
agency following a debriefing did not extend the time for
filing a bid protest). Since New SI's protest was filed
more than 10 days after it learned of the basis for the
protest on October 6, the protest is untimely. (New
SI, LLC, B-295209; B-295209.2; B-295209.3, November
22, 2004) (pdf)
Our
Bid Protest Regulations provide that where, as here, a
protester timely files an agency-level protest, any
subsequent protest to our Office must be filed within
10 days of actual or constructive knowledge of initial
adverse agency action. 4 C.F.R 21.2(a)(3) (2004). In an
analogous case, we found that a protester's receipt on
Saturday (a non-business day) by electronic mail of the
agency's notification that the firm had been excluded from
the competitive range should be considered as received by
the protester on the next business day for the purposes of
determining whether a request for a required debriefing
was timely. See International Res. Group , B-286663, Jan.
31, 2001, 2001 CPD 35 at 5. The agency argues that our
decision in International Res. Group is inapplicable here
because that decision did not concern the computation of
time required to file a protest with our Office but only
concerned when a protester was deemed to have received
notice of its competitive range exclusion for the purposes
of requesting a required debriefing. We do not agree that
this difference distinguishes the rule stated in
International Res. Group . In either situation, the time
period for requesting a required debriefing or filing a
protest with our Office commences with a protester's
actual or constructive knowledge of initial adverse agency
action. As we found in International Res. Group , the
mechanical receipt of notice on a non-business day, where
the notice is not actually read, does not constitute
actual or constructive knowledge. With respect to receipt
outside the protester's ordinary business hours (for
example, a weekend), we find no practical difference
between by e-mail or by the protester's clerical or
security personnel for purposes of determining whether a
protester has received constructive or actual notice of
initial adverse agency action. (Supreme
Edgelight Devices, Inc., B-295574, March 4, 2005) (pdf)
The protests challenge an evaluation and source selection
process that took place between June 2000 and June 2001.
As a procedural matter, our Office's timeliness rules
generally preclude consideration of protests challenging
agency actions, such as these, that took place in the
relatively distant past. See Bid Protest Regulations,
4C.F.R. 21.2 (2004). Here, however, the protests are based
on information first obtained by the protesters in October
2004 due to the public disclosure at that time of
documents relating to Darleen Druyun's criminal conviction
and sentencing for violation of the conflict of interest
provisions codified at 18 U.S.C. 208(a) (2000). Since the
protesters had no reason to know of the information
disclosed in those documents, we view the protests as
timely. (Lockheed Martin
Aeronautics Company; L-3 Communications Integrated Systems
L.P.; BAE Systems Integrated Defense Solutions, Inc.,
B-295401, B-293401.2, B-295401.3, B-295401.4, B-295401.5,
B-295401.6, B-295401.7, B-295401.8, February 24, 2005) (pdf)
To the extent Pitney Bowes disagrees with the agencys
interpretation of the term business rules, we view the
solicitation as patently ambiguous. As noted above, an
offeror has an affirmative obligation to seek
clarification prior to the first due date for submissions
responding to the solicitation following introduction of
the ambiguity into the solicitation. 4 C.F.R. 21.2(a)(1).
Where a patent ambiguity is not challenged prior to such
submissions, we will dismiss as untimely any subsequent
protest assertion that is based on an alternative
interpretation. Kellogg Brown & Root, Inc. , supra ; Bank
of Am. , B287608, B-287608.2, July 26, 2001, 2001 CPD 137
at 10. Our rule that protests of patent ambiguities must
be filed prior to responsive submissions is intended to
facilitate clarification of legitimate questions prior to
preparation of submissions. Since Pitney Bowes sought no
clarification of this matter prior to responding to the
solicitation, it may not now assert that the only
permissible interpretation of this term is its own. (Pitney
Bowes Inc., B-294868; B-294868.2, January 4, 2005) (pdf)
Pitney Bowes first protests that the agency lacked a
proper basis to cancel the initial delivery order. Pitney
Bowes does not dispute that its submission failed to
reflect any prices for meter head bases or scales in the
option years. Nonetheless, Pitney Bowes maintains that the
RFQ only sought vendors quotations to purchase meter head
bases and scales during the base year, and that no such
purchases were contemplated during the option years. The
record is to the contrary. As noted above, the
solicitation expressly advised the vendors that they were
to complete the following pricing, that [t]he number of
units to be provided in the option years has not been
determined, and that the vendors quotations for the
option-year quantities would be used for the purpose of
evaluating bids. RFQ at 1. Accordingly, it is clear that
quotations for all line items, including option-period
line items was required. To the extent Pitney Bowes viewed
this clear solicitation requirement as either unrealistic
or otherwise contrary to other aspects of the RFQ, any
protest on that basis had to be filed prior to the time
set for submission of quotations, in order to be timely
under our Bid Protest Regulations. 4 C.F.R. 21.2(a)(1). On
this record, we find nothing improper in the agency's
cancellation of the initial delivery order issued to
Pitney Bowes. (Pitney Bowes Inc.,
B-294868; B-294868.2, January 4, 2005) (pdf)
This case presents two related questions pertaining to
timeliness. The first is whether a time/date stamp is
determinative as to the timeliness of a protest filing
where other evidence clearly establishes the time that the
protest arrived at our Office. The answer to this question
is no. While we rely upon our time/date stamp to determine
the timeliness of protest filings with our Office where
other evidence clearly establishing the time that the
protest arrived is absent, Peacock, Myers & Adams ,
B-279327, Mar. 24, 1998, 98-1 CPD 94 at 2, we will not
rely upon the stamp where other acceptable evidence of
earlier receipt is available, as was the case here. Our
fax machine printed the time and date of receipt on each
page of the protest as it was received, and these captions
establish that all 11 pages of the protest were received
at 2:42 p.m. on July 5. In addition, there is evidence (in
the form of an e-mail message confirming receipt of the
protest that was automatically generated by our computer
system at 3:22 p.m. on July 5) that Guam Shipyard sent an
e-mail copy of its protest to our Office prior to the time
set for receipt of quotations. We turn then to our second
question, which is whether we should consider a protest
transmitted to our Office by e-mail or fax outside of
business hours as filed at the time it enters our computer
system (in the case of e-mail) or is received by our fax
machine (in the case of a fax) or whether we should
consider it as filed as of the opening of business on the
following business day. We think that the answer is the
latter. While we recognize that our Regulations define the
term "days" as "calendar days," 4 CFR 21.0(e), the clear
intent behind the Regulations, read as a whole, is that
documents may be, and are considered, filed only on days
when our Office is open for business. In this regard, 4
CFR 21.0(g) states that "[a] document is filed on a
particular day when it is received by GAO by 5:30 p.m.,
eastern time, on that day," and documents filed after 5:30
p.m. are considered filed on the next business day. See ,
e.g. , Computer One, Inc.Recon. , B-249352.7, Sept. 27,
1993, 93-2 CPD 185 at 2 n.1. The reference to the 5:30
p.m. deadline has meaning only if used in the context of
business days. See Bid Protests at GAO: A Descriptive
Guide , 15 (7th ed. 2003) (GAO's office hours are from
8:30 to 5:30 p.m., eastern time, Monday through Friday).
In an analogous situation, we have held that where e-mail
notification of an offeror's exclusion from the
competitive range enters an offeror's computer system
after close of business on a weekday or on a weekend or
holiday and is not opened before the following business
day, receipt of the notice should not be considered to
have occurred until that business day. Int'l Resources
Group, B-286663, Jan. 31, 2001, 2001 CPD 35 at 5.
Similarly here, we do not consider protest-related
submissions received via e-mail or fax outside of business
hours as effectively receivedand thus filed--until the
following business day. (Guam
Shipyard, B-294287, September 16, 2004) (pdf)
As a general rule, a protester is not required to protest
that another firm has an impermissible OCI until that firm
has been selected for award. REEP, Inc. , B-290688, Sept.
20, 2002, 2002 CPD 158 at 1-2. A different rule applies,
however, where a solicitation is issued on an unrestricted
basis, the protester is aware that a potential offeror has
participated in developing the project and is
participating in the competition, and the protester has
been advised by the agency that it considers the potential
offeror eligible for award. International Sci. and Tech.
Inst., Inc. , B-259648, Jan. 12, 1995, 95-1 CPD 16 at 3-4;
see CDR Enters., Inc. , B-293557, Mar.26, 2004, 2004 CPD
46 at 3 n.1. In such cases, the protester cannot wait
until an award has been made to file its protest, but
instead must protest before the closing date for receipt
of proposals. International Sci. and Tech. Inst., Inc. ,
supra . Here, the assessment prepared by TCGI--which
clearly showed the extent of the firm's prior involvement
in the program--was included in the solicitation. Further,
it is clear that Abt knew both that TCGI was participating
in the procurement and that the agency did not consider
TCGI to have an OCI that precluded it from receiving the
award. Under these circumstances, Abt's protest is
untimely because it was not filed prior to the closing
date for receipt of proposals. International Sci. and
Tech. Inst., Inc. , supra . (Abt
Associates, Inc., B-294130, August 11, 2004) (pdf)
In requesting reconsideration, AMI claims that the
late-December conversation conveyed to AMI only that PTBS
had filed a complaint alleging that it should have
received award after application of the 10-percent
preference, and that the agency was imposing a stop-work
order until a decision could be made, which would be made
known to AMI at that time. According to AMI, it became
aware that the agency had made a final determination to
terminate the Good Housekeeping portion of AMI's contract
only when it received the amendment/modification to that
effect on January 7, and that the timeliness period
therefore should commence on that date, making the January
13 agency protest timely. Our original decision found that
the stop-work order plus the contracting officer's
explanation that application of the 10-percent preference
could result in the contract going to PTBS gave AMI
sufficient information to file a protest. On reflection,
however, and in light of our rule that doubt as to when a
protester became aware of its basis for protest should be
resolved in favor of the protester, Metro Monitoring Servs.,
Inc. , B-274236, Nov. 27, 1996, 96-2 CPD 204 at 4, we have
decided that AMI should be given the benefit of the doubt
about the content of the conversation with the contracting
officer. While the information given to AMI in late
December clearly conveyed that the Good Housekeeping
portion of its contract was in jeopardy, we are willing to
assume, for purposes of determining timeliness of the
subsequent protest, that the agency left AMI with reason
to believe that a final determination had yet to be made.
When a firm has been notified that the agency is
considering taking an action adverse to the firm's
interests, but has not made a final determination, the
firm need not file a defensive protest, since it may
presume that the agency will act properly. See Haworth,
Inc.; Knoll North America, Inc. , B-256702.2, B-256702.3,
Sept. 9, 1994, 94-2 CPD 98 at 4-5; Tamper Corp. ,
B-235376.2, July 25, 1989, 89-2 CPD 79 at 2; Dock Express
Contractors, Inc. , B-227865.3, Jan. 13, 1988, 88-1 CPD 23
at 6. (American Multi Media,
Inc.--Reconsideration, B-293782.2, August 25, 2004) (pdf)
As an initial matter, the protester’s allegation that the
agency improperly failed to make a cost/technical
tradeoff, including crediting Dix with superior
experience, is an untimely protest of an ambiguity
apparent on the face of the RFQ. Although RFQ, at section
3-7, included language consistent with making a “best
value” selection, such as the relative weights of
evaluation factors, suggesting that the agency would
conduct a cost/technical tradeoff if necessary, that
section of the RFQ also stated that “[i]t is the
Government’s intent to award to the offeror who receives a
Satisfactory or better rating in sub-factors 1, 2, 3, and
4, and who has the lowest price.” RFQ § 3-7(a)(1). As the
protester itself acknowledges, these provisions are in
“inherent conflict.” Dix Comments, May 19, 2004, at 5.
Where a solicitation contains such a patent ambiguity, an
offeror has an affirmative obligation to seek
clarification prior to the first due date for responding
to the solicitation following introduction of the
ambiguity into the solicitation. 4 C.F.R. § 21.2(a)(1)
(2004); see American Connecting Source d/b/a/ Connections
, B-276889, July 1, 1997, 97-2 CPD ¶ 1 at 3. The purpose
of our timeliness rule in this regard is to afford the
parties an opportunity to resolve ambiguities prior to the
submission of solicitation responses, so that such
provisions can be remedied before firms formulate their
responses. Gordon R. A. Fishman , B-257634, Oct. 11, 1994,
94-2 CPD ¶ 133 at 3. Where a patent ambiguity is not
challenged prior to submission of solicitation responses,
we will dismiss as untimely any subsequent protest
assertion that is based on one of the alternative
interpretations as the only permissible interpretation.
U.S. Facilities, Inc. , B-293029, B-293029.2, Jan. 16,
2004, 2004 CPD ¶ 17 at 10. (Dix
Corporation, B-293964, July 13, 2004) (pdf)
On March 30, the contracting officer informed CDC via
e-mail that VA had not selected CDC’s quotation. CDC
immediately sent an e-mail to the contracting officer
advising that it would protest VA’s decision upon receipt
of formal notification and explanatory documents. In a
letter dated April 5, postmarked April 8, and received by
CDC April 11, VA again notified CDC of its decision to
select Braun and briefly explained the reasons for its
decision. CDC filed its protest with our Office on April
12. VA argues that CDC’s protest is untimely because it
was not filed within 10 days of the contracting officer’s
preliminary e-mail notice that CDC’s quotation had not
been selected. See Bid Protest Regulations, 4 C.F.R. §
21.2(a)(2) (2004). We disagree. The agency’s April 5
e-mail advising that Braun’s quotation had been selected
did not contain sufficient information to put CDC on
notice of its basis for protest. Immediately after
receiving that e-mail, CDC acted reasonably and promptly
by first requesting further information from the agency,
and then filing its protest on April 12, the same day it
received the agency’s letter explaining in some further
detail the basis for the selection decision. See Alliance
Properties, Inc., B-203539, Oct. 28, 1981, 81-2 CPD ¶ 357
at 2. (Chicago Dryer Company,
B-293940, June 30, 2004) (pdf)
While we acknowledge the significance of the matters
Saltwater raises, these issues are not timely at this
juncture. Our Bid Protest Regulations require that
improprieties in a solicitation--including those which did
not exist in the initial solicitation, but were
subsequently incorporated--must be raised prior to the
next closing time for receipt of proposals. 4 C.F.R. §
21.2(a)(1); East Penn Mfg. Co., Inc., B-261046, Aug. 1,
1995, 95-2 CPD ¶ 50 at 3. Put simply, Saltwater’s
contention that it became aware of these potential
ambiguities upon receipt of the modification on December
2, rather than upon receipt of the agency’s November 18
second request for FPRs, is not persuasive. As set forth
above, a comparison of the November 18 request for a
revised proposal with the terms of the modification
provided to implement the new selection decision shows
nothing in the modification that was not previously
disclosed to the company in the November 18 request.
Specifically, the November 18 request: (1) expressly
advises that fisheries observers will be viewed as
non-exempt employees eligible for overtime; (2) advises
that overtime must be paid at a rate not less than 1½
times the basic rate of pay for hours worked in excess of
40 per week; and (3) advises that NMFS views these
requirements as applicable whether an observer is within
or without U.S. territorial waters. AR, Tab 16, at 1. Each
of these issues is reflected, in very similar terms, in
the December 2 modification. Indeed, Saltwater’s response
to the request for a second FPR indicates to us that the
company fully understood the implications of the NMFS
policy statement--and had concerns about it. In this
regard, it advised the agency that while it had revised
its proposal, it did not want its actions to be construed
as agreement that the NMFS policies were required by law.
In our view, the clear language of the November 18 notice,
Saltwater’s caveat about it, and the lack of any
meaningful difference between the notice and the December
2 modification, mean that Saltwater was required to raise
any challenge to these overtime policies prior to
submitting its second FPR. Its attempt to do so now--as
the underlying basis for challenging the termination of
its contract for its refusal to execute the
modification--is untimely. (Saltwater
Inc., B-293335.3, April 26, 2004) (pdf)
Reedsport also questions the CO’s justification for
removing Station Tillamook from Lot 4, on the basis that
the agency report shows that the justification was based
in part on the CO’s miscalculation of transit times from
Modutech’s and Reedsport’s facilities. This allegation
also is untimely. Even if the protester was unaware of the
underlying justification for the amendment until it
received the agency report, a challenge to an amendment
that could have been timely raised cannot subsequently be
revived by an event--such as the protester’s receipt of
documents indicating the agency’s reasoning for the
amendment--that only serves to confirm the untimely
protest grounds. All Phase Envtl., Inc., B-292919.2 et
al., Feb. 4, 2004, 2004 CPD ¶ __ at 9 n.4. In any case,
prejudice is a necessary element of every viable protest,
and since Reedsport was able to bid on both Lot 3 and Lot
4, it is not apparent how the firm was competitively
harmed. Indeed, Reedsport won Lot 3, and the MLBs from
Station Tillamook therefore will provide additional work
for Reedsport under the contract. Parmatic Filter Corp.,
B-285288.3, B-285288.4, Mar. 30, 2001, 2001 CPD ¶ 71 at
11; see Statistica, Inc. v. Christopher, 102 F. 3d 1577,
1581 (Fed. Cir. 1996). (Reedsport
Machine & Fabrication, B-293110.2; B-293556, April 13,
2004) (pdf)
Under our Bid Protest Regulations, protests must be
filed in our Office no later than 10 days after the
protest grounds were known or should have been known. 4
C.F.R. § 21.2(a)(2) (2003). Supplemental protests must
independently satisfy our timeliness requirements. Saco
Defense Corp., B-283885, Jan. 20, 2000, 2000 CPD ¶ 34 at
5-6, n.3. The record shows that ACT received its copy of
the agency report--which contained the information on
which ACT’s additional arguments are based--on November
10, 2003, and that its comments on the report were not
filed in our Office until November 21. By letter dated
November 11, the protester’s counsel advised us that,
although he had actually been handed a copy of the report
at 6:00 p.m. on November 10, this was after the firm’s
regular business hours; protester’s counsel therefore
asserted that the 10-day period for filing comments and
for raising any new protest grounds based on the report
did not begin to run until the next day, November 11, and
that both ACT’s comments and any supplemental protest
grounds were due by November 21. By telephone, on November
17, we granted ACT’s request to file its comments on
November 21. Although ACT’s counsel asserts to the
contrary, we did not further state that the timeliness
period for raising new protest grounds was extended. Nor
do we believe it would have been appropriate to grant such
an extension, since ACT’s counsel concedes that he was in
actual receipt of the agency report on November 10 (as
opposed to November 11). This being the case, ACT was
required to file any supplemental protest grounds within
10 days after November 10, that is, no later than November
20. Since the supplemental bases for protest were not
filed until 11 days after ACT’s receipt of the agency
report, they are untimely and will not be considered. (AC
Technologies, Inc., B-293013; B-293013.2, January 14,
2004) (pdf)
Our Bid Protest Regulations contain strict rules for the
timely submission of protests. Under these rules, a
protest based on other than alleged improprieties in a
solicitation must be filed not later than 10 calendar days
after the protester knew, or should have known, of the
basis for protest, whichever is earlier. 4 C.F.R. §
21.2(a)(2) (2003). Our timeliness rules reflect the dual
requirements of giving parties a fair opportunity to
present their cases and resolving protests expeditiously
without unduly disrupting or delaying the procurement
process. Dominion Aviation, Inc.--Recon., B-275419.4, Feb.
24, 1998, 98-1 CPD ¶ 62 at 3. Here, NVT acknowledged
receipt on July 31 of the agency’s document addressing the
regulatory requirements for a substantial bundling
analysis. However, since NVT did not challenge the merits
of the agency’s substantial bundling analysis until more
than 10 days after it received the relevant document, we
will not consider NVT’s protest in this regard. (NVT
Technologies, Inc., B-292302.3, October 20, 2003) (pdf)
Gamut maintains that its protest was timely because it
did not notice the improprieties prior to its proposal's
rejection, which then prompted it to perform a “detailed
analysis of the solicitation,” and because it was unaware
that the agency considered the solicitation a BAA until
after Gamut had filed its original protest. Response to
Motion to Dismiss, June 6, 2003; Gamut Letter, June 11,
2003 at 1. This argument is without merit. The
solicitation plainly laid out all aspects of the
requirement that Gamut now protests: the phased nature of
the procurement, the evaluation criteria, and the agency's
significant discretion in selecting all, some, or none of
the proposals for demonstration or awards. Thus, Gamut
was, or should have been, fully aware of all the matters
it now challenges, and could not delay protesting until it
completed its “detailed analysis.” While Gamut may not
have been aware that the solicitation was a BAA, the
essence of its protest--that the agency's substantive
approach to the procurement was flawed--was not dependent
upon this information, and the fact that the protest
incorporated this information therefore did not render it
timely. Gamut asserts that we should consider its
untimely arguments under the significant issue exception
to our timeliness requirements. 4 C.F.R. § 21.2(c). Under
this exception, we may consider a protest notwithstanding
its untimeliness when, in our judgment, doing so would be
in the interest of the procurement system. ABB Lummus
Crest Inc., B‑244440, Sept. 16, 1991, 91-2 CPD ¶ 252 at 4.
The exception is limited to protests that raise issues of
widespread interest to the procurement community, and that
have not been considered on the merits in a previous
decision. Id. We find no basis for applying the exception
here since, while the protest is of interest to Gamut,
there is no reason to believe that the issues raised would
be of widespread interest to the procurement community.
DSDJ, Inc., B‑288438 et al., Oct. 24, 2001, 2002 CPD ¶ 50
at 3. (Gamut Electronics, LLC,
B-292347; B-292347.2, August 7, 2003) (pdf)
As stated in the supplemental agency protest, the
protester's allegation was based upon information first
learned at the debriefing, namely that the Air Force had
rated Platinum and Clay the same for past performance and
thus found them to be “equally as qualified.”
Protester's Comments, Tab G, Supplemental Agency Protest,
at 1-2. Because this protest ground was received by the
Air Force within 10 days of the debriefing, it was timely
filed with the agency, and Clay's subsequent protest was
timely filed at our Office because it was received here
within 10 days of when Clay received notice of the Air
Force's dismissal of its agency protests.[3] The agency's
argument that Clay's entire protest should be dismissed
because it did not timely request a debriefing is
meritless, given that non-required debriefings are
permitted, see Federal Acquisition Regulation (FAR) §
15.506(a)(4)(i), and a protest based on information first
revealed in a non-required debriefing, as here, is timely
if filed within 10 days of the debriefing. Beneco Enters.,
Inc., B-283154, Oct. 13, 1999, 2000 CPD ¶ 69 at 6 n.6. (Robert
Clay, Inc., B-292443, August 14, 2003) (pdf)
Here, HMX's proposal explicitly takes exception to the
solicitation's requirements for proposal information, such
as cost and pricing data and technical data requirements.
Agency Report, Tab L, HMX's Proposal, at H-1 through H-4.
This portion of the proposal sets forth HMX's position
that the NRA's proposal preparation instructions do not
comply with the Commercial Space Act, and that the Act
permitted HMX to deviate from the terms of the NRA to
comply instead with the standards for proposals for
commercial items as reflected in FAR Part 12, Acquisition
of Commercial Items. However, the NRA did not reference
the Act or FAR Part 12. Therefore, even if we accept
the protester's interpretations of the Act as both
applying to this NRA by operation of law and requiring
acquisition of the launch services proposed by HMX
consistent with the regulations governing the acquisition
of commercial items, there remains the unavoidable fact
that the express terms of the NRA are inconsistent with
HMX's interpretation of the Act. This obvious conflict can
only be viewed as an alleged impropriety apparent on the
face of the solicitation. Since HMX did not protest until
after its proposal was rejected--i.e., well after the time
set for receipt of proposals--the protest is untimely.
(HMX,
Inc., B-291102, November 4, 2002) (txt
version)
We do not agree that Payne's protest is untimely. The
protester is objecting to the agency's failure to consider
its quotation; accordingly, we think that Payne's period
for filing a protest did not begin to run until the
contracting officer notified it that he had not considered
the quotation. The notification that the protester
received on October 15 did not start the 10-day period
running because, while it informed the protester of the
selection of Ridgley, it did not advise the protester that
its quotation had not been considered; thus, it did not
furnish the protester with the information providing the
basis for its protest. Further, we do not think that
the conversation between the Payne representative and a
contracting office employee on October 16 constituted
notice sufficient to start the 10-day period running
because while the employee initially informed the
protester that its quotation had not been considered
because the RFQ was not open to it, she then backtracked,
stating that there appeared to be serious problems with
the solicitation and that the protester would need to
speak with the contracting officer. Under the
circumstances of this case, we do not think that the
protester can be said to have learned of its basis for
protest until October 21 at the earliest, when a
representative of the company spoke with the contracting
officer and was told that its quotation had not been
considered. Accordingly, we consider its protest filed on
October 30 to be timely. (Payne
Construction, B-291629, February 4, 2003) (txt
version)
AST's argument is untimely. The essence of AST's
contention is that a site visit was critical to its
competitors' submitting proposals with prices that reflect
what AST views as the actual amount of liquid required to
be disposed under the contract. This is essentially a
challenge to the terms of the solicitation, which did not
make attendance at the site visit mandatory.
Alternatively, AST's presumably believes that the RFP
should have identified the amount of liquid the contractor
would be required to dispose of, or, at the least, it
should have required offerors to disclose the amount of
liquid whose removal their proposed prices reflect (which
AST itself appears not to have disclosed in its proposal).
Protests challenging alleged defects in a solicitation
must be filed prior to the time set for receipt of
proposals. 4 C.F.R. ¶ 21.2(a)(1) (2002). As the incumbent,
AST was uniquely knowledgeable of any such defect here and
thus in a position to protest without waiting to learn
that it had lost the competition. See Allstate Van &
Storage, Inc., B-247463, May 22, 1992, 92-1 CPD ¶ 465 at
5-6. Because it did not protest the alleged solicitation
defects prior to the closing date, its protest is
untimely. (AST
Environmental, Inc., B-291567, December 31, 2002.)
We have recognized that the increasing use of ID/IQ
contracts with very broad and often vague statements of
work may place an unreasonable burden upon potential
offerors, who may be required to guess as to whether
particular work, for which they are interested in
competing, will be acquired under a particular ID/IQ
contract. See Valenzuela Eng'g, Inc., B-277979, Dec. 9,
1997, 98-1 CPD P: 51 (Letter to the Acting Sec'y of the
Army, Jan. 26, 1998, at 2). This burden may be
particularly problematic for small businesses. Id. In
our view, it is unreasonable to require a small business
that believes that one specific acquisition should
continue to be set aside for small businesses to
identify the possibility, at the time proposals for
ID/IQ contracts to perform a broad and undefined scope
of work are solicited, that the specific, and relatively
small, acquisition it is interested in may ultimately be
transferred to the ID/IQ contracts. The breadth and
vagueness of the LOGJAMSS scope of work illustrate this,
since it encompassed a *wide range of logistical
functions and supporting tasks* and was undefinitized at
the time the LOGJAMSS contracts were solicited.
Accordingly, we conclude that LBM could not reasonably
be aware, and required to protest, at the time the
LOGJAMSS contracts were being competed (and apparently
years before the Army considered using those contracts
for the Fort Polk motor pool services), that the broad
and nonspecific scope of work in the LOGJAMSS
solicitation could be improperly used as a vehicle for
the agency to perform the motor pool services at Fort
Polk without first taking the steps legally required
regarding a possible further acquisition of that work
under a small business set-aside. (LBM,
Inc., B-290682, September 18, 2002) (pdf)
In a supplemental protest filed by HG more than 3 months after the underlying lease
was awarded to POC, raising issues which allegedly were based upon HG’s review of
a copy of that lease included in the agency’s report on HG’s initial protest,
HG raised numerous challenges to, among other things, the evaluation and acceptance of the
POC offer. Given the substantial passage of time since that lease was awarded,
however, we conclude that the challenges are untimely. A
protester is required to diligently pursue information forming the basis for a protest. Here, HG waited
months before it requested and reviewed information about that award for possible
bases of protest. This delay simply does not meet our requirements for the
expeditious pursuit of information.1 See Professional Rehab. Consultants, Inc.,
B-275871, Feb. 28, 1997, 97-1 CPD ¶ 94 at 2-3. (HG
Properties A, LP, B-290416; B-2904162, July 25, 2002 (pdf))
Protests
that merely anticipate improper agency action are
premature. See Saturn Indus.--Recon., B-261954.4, July
19, 1996, 96-2 CPD para. 25 at 5. Here, the Navy has, as
the protester acknowledges, not yet decided what action
or actions the agency will take in response to the
appeal authority's decision, so that there is no agency
action for our Office to review. We share the
protester's concern about the process being drawn out
unnecessarily, and in this regard it is helpful that the
Navy appears committed to moving forward expeditiously.
We recognize, however, that the issues identified by the
appeal authority are significant, and we believe that
the agency should have a reasonable opportunity to
review the appeal authority's decision to determine its
course of action. Once the Navy decides what action to
take in response to the appeal authority decision, that
decision may form the basis for a valid bid protest,
which IT or another interested party may file with our
Office at that time. (A-76 Issue) (IT
Corporation, B-288507, September 7, 2001)
Protest presenting
argument raised in appeal under Office of Management and
Budget Circular No. A-76 is untimely where filed with
the General Accounting Office more than 10 days after
contracting agency denied protester's appeal. While the
protest was filed within 10 days of cancellation of the
underlying solicitation, cancellation was merely
implementation of the denial of the appeal. (Crown
Support Services, Inc., B-287070, January 31,
2001) (pdf)
Protest based on
information obtained during post-award debriefing is not
timely filed where protester who was excluded from
competitive range requested that the debriefing be
delayed until after award. (United
International Investigative Services, Inc.,
B-286327, October 25, 2000) (pdf)
Protester's contention
that a solicitation improperly requires submission of
proprietary technical data for evaluation of a
commercial item in violation of the regulations
governing commercial item acquisitions is rendered
academic when the agency waives the application of the
regulation, and the protester fails to raise a timely
objection to the waiver. (ATA
|