|
FAR
9.400: Debarment, Suspension, and Ineligibility |
|
Comptroller
General - Key Excerpts |
FAS argues that
the Air Force unreasonably refused to reinstate its proposal
into the competition following the lifting of its suspension
from contracting. The protester also argues that the agency
unreasonably evaluated VBR's proposal. As discussed below, we
find that the Air Force reasonably exercised its discretion to
not reinstate FAS's proposal. Because we conclude that FAS was
reasonably excluded from the competition, FAS is not an
interested party to challenge the Air Force's evaluation of
VBR's proposal.
Agency Denial of Reinstatement Request
The FAR prohibits an agency from awarding a contract to a
debarred or suspended contractor. FAR sect. 9.405. The FAR also
provides, however, that "[i]f the period of ineligibility
expires or is terminated prior to award, the contracting officer
may, but is not required to, consider" an offeror's proposal.
FAR sect. 9.405(d)(3). The FAR clearly commits the decision
whether to reinstate an offeror into a competition following the
lifting of a suspension to the discretion of a CO. See South
Texas Turbine Supply, B-272163, Sept. 5, 1996, 96-2 CPD para.
105 at 3.
As a preliminary matter, FAS makes extensive arguments that its
suspension from contracting was improper, and that the agency
abused its discretion by improperly relying on that suspension
in concluding that reinstatement of FAS's proposal into the
competition was not warranted. In its report on the protest, the
Air Force argues that DLA properly concluded that, under the
facts of PWC's suspension, FAS's suspension was proper. Agency
Legal Memo at 9-10. We need not resolve whether FAS's suspension
by DLA was improper. As our Office has held, suspension and
debarment of a contractor is a matter of agency contract
administration that we do not review. Shinwha Elec., B-291064 et
al., Sept. 3, 2002, 2002 CPD para. 154 at 4.
As discussed above, the Air Force's refusal to reinstate FAS's
proposal into the competition was based on the CO's concerns
regarding the delay to the procurement, and the CO's view that
FAS's proposal did not have a likely chance for award. AR, Tab
17, Reinstatement Decision, at 4-7. We think that the agency's
concern regarding delay to the procurement was reasonable, and
in turn, provided a reasonable basis for declining to reinstate
FAS's proposal into the competition.
First, the CO concluded that the removal of Taos/Agility as a
joint venture partner would require the agency to conduct a new
evaluation of FAS's past performance because FAS itself had no
past performance, and instead relied on the past performance of
its two joint venture partners. AR, Tab 17, Reinstatement
Decision, at 5. FAS's proposal cited four past performance
examples: (1) the incumbent contract for the agency's
maintenance requirements in Spain, which was performed by a
different joint venture between FSSI and Taos/Agility; (2) a
base operations contract at Diago Garcia, performed by a joint
venture where FSSI was the managing partner; (3) a base
operations contract in Guam where FSSI was a joint venture
partner; and (4) a warehouse design/build and management
contract in Kuwait, which was performed by Taos/Agility. The CO
found that the Kuwait contract was actually performed by
Taos/Agility and thus was not relevant to the agency's review of
past performance for FAS. Id. at 5. With regard to the other
contracts--particularly the FSSI and Taos/Agility joint venture
for the Spain maintenance contract--the CO stated that FAS's
past performance would need to be reconsidered in light of the
fact that FSSI would be performing the contract entirely on its
own. Id.
Next, with regard to the technical acceptability factor, CO
concluded that the agency would need to conduct a new evaluation
to determine the extent to which FAS's technical proposal relied
on the resources of Taos/Agility. Id. at 5. The CO also
concluded that the agency would need to reopen discussions to
allow FAS to revise its technical approach to account for the
removal of the suspended partner. Id. The record shows that
FAS's technical proposal discusses in numerous areas the
capabilities of both FSSI and Taos/Agility. For example, the
protester's proposal states that the joint venture is
"structured to capitalize on the collected capabilities and
assets" of FAS and Taos/Agility. AR, Tab 9, FSS Initial
Proposal, Vol. 3, at 26. With regard to management, the proposal
states that "FAS is governed by a streamlined Board of Directors
whose members are selected from [FSSI] and Agility . . . [which]
will oversee the contract and represent the shareholders." Id.
Additionally, FAS's proposal cites the experience of FSSI and
Taos/Agility in performing the Spain contract's requirements, as
evidence of the protester's technical capabilities, as follows:
"A key discriminator for this contract is the composition of the
phase-in team . . . [which is comprised of] core members of the
[Spain contract] phase-in team that successfully transitioned
the contract in 60 days." See, e.g., AR, Tab 9, FAS Initial
Proposal, at ES6.
With respect to the amount of delay at issue, the CO concluded
that reinstatement of FAS's proposal would require an estimated
6 months to address the anticipated additional discussions,
proposal revisions, and evaluation. AR, Tab 17, Reinstatement
Decision, at 6. The CO viewed this delay as unacceptable because
it would require sole-source extensions of the two incumbent
contracts. Id. In this regard, the CO was concerned that such an
extension would present difficulties for the agency because the
incumbent contract for the requirements in Spain was performed
by a joint venture between FAS's sole remaining partner, FSSI,
and Agility, one of the companies that had been suspended by DLA
in November. Id. In contrast, the CO stated that VBR had
addressed all of the technical acceptability concerns and the
agency was ready to proceed with award. Id. at 3-4.
FAS does not dispute that it would need to revise its proposal
to account for the removal of Taos/Agility from the joint
venture. See Protester's Comments on AR at 10-11. Instead, the
protester contends that it could have addressed all of the
agency's concerns through discussions. See id. The protester
further argues that the magnitude of required revisions would
not be "substantial" because, in the protester's view, FSSI is
capable of performing all of the contract requirements. See id.
We think that the agency's concerns regarding delay were
reasonable. As discussed above, the record clearly shows that FAS's proposal was based on the combined experience and past
performance of FSSI and Taos/Agility. We agree with the agency
that, at a minimum, the protester would need to revise its
proposal to address how FSSI would perform the contract on its
own, and the agency would need to conduct a new evaluation of
FSSI's technical acceptability and past performance. In sum, we
think the agency reasonably declined to reinstate FAS's proposal
into the competition. (FAS
Support Services, LLC, B-402464; B-402464.2; B-402464.3,
April 21, 2010) (pdf)
Greenleaf asserts that the award to CLF was improper because
CLF's proposal misrepresented the resources and staff CLF
intended to use to perform the contract. An offeror’s material
misrepresentation in its proposal can provide a basis for
disqualification of the proposal and cancellation of a contract
award based upon the proposal. A misrepresentation is material
where the agency relied upon it and it likely had a significant
impact upon the evaluation. Integration Techs. Group, Inc., B-
291657, Feb. 13, 2003, 2003 CPD para. 55 at 2-3; Sprint
Communications Co. LP; Global Crossing Telecommunications.,
Inc.--Protests and Recon., B-288413.11, B‑288413.12, Oct. 8,
2002, 2002 CPD para. 171 at 4; AVIATE L.L.C., B-275058.6,
B‑275058.7, Apr. 14, 1997, 97-1 CPD para. 162 at 11. Based on
our review of the record, we find that HUD’s evaluation of CLF’s
proposal was unreasonable because it was based on aspects of
CLF’s proposed resources and technical approach that, after the
submission of CLF’s FPR, and unbeknownst to the agency,
materially changed such that the agency never evaluated the
awardee’s actual resources and technical approach as they
existed at the time of award. (Greenleaf
Construction Company, Inc., B-293105.18; B-293105.19,
January 17, 2006) (pdf)
Here,
even if we assume, arguendo, that AKMI is not, and has never
been, affiliated with Keith Moving, Inc., AKMI provided no
information in its proposal to suggest that the D&B report,
which reflected that AKMI was an alternate name for Keith
Moving, Inc., was inaccurate or otherwise unreliable. On the
contrary, at the time of the contemporaneous evaluation of
proposals, there was sufficient information in AKMI's proposal,
particularly when read in conjunction with information in the
D&B report, for GSA to reasonably conclude that AKMI was
affiliated with Keith Moving, Inc., a firm that had been
proposed for debarment, thereby making AKMI ineligible for
award. (Aardvark
Keith Moving, B-290565, August 8, 2002) (pdf) |
|
|
Comptroller
General - Listing of Decisions |
|
For
the Government |
For
the Protester |
|
FAS Support Services, LLC, B-402464;
B-402464.2; B-402464.3, April 21, 2010 (pdf) |
Greenleaf Construction Company, Inc.,
B-293105.18; B-293105.19, January 17, 2006 (pdf) |
|
Shinwha
Electronics, B-290603; B-290603.2; B-290931; B-290932,
B-290932.2, B-291064, September 3, 2002 |
|
|
Aardvark
Keith Moving, B-290565, August 8, 2002 (pdf) |
|
|
U.
S. Court of Federal Claims - Key Excerpts |
C. The Air Force Decision Not to Reinstate FAS in the
TSBMC Procurement
The suspension of FAS required its removal from competition for the TSBMC.
This left the Air Force with one offeror, VBR, for the contract award. After FAS
divested its 49% owner, Taos-Agility, and DLA then removed FAS from the EPLS,
FAR 9.405(d)(3) provided that the contracting officer “may, but is not required
to,
consider” the proposal FAS had previously submitted. Plaintiff asserts that the
contracting officer’s exercise of the discretion provided by FAR 9.405(d)(3)
must be
closely scrutinized to fulfill the mandates of the Competition in Contracting
Act of
1984 (“CICA”), Pub. L. No. 98-369, § 2713, 98 Stat. 1175, 1182 (1984). See Birch
& Davis Int’l, Inc. v. Christopher, 4 F.3d 970, 974 (Fed. Cir. 1993). The CICA
requires full and open competition. 41 U.S.C. § 253(a)(1)(A). Competition is
required so that “a sufficient number of offers is received to ensure that the
government’s requirements are filled at the lowest possible cost.” H.R. Rep. No.
1157, 98 Cong., 2d Sess. 17 (1984). See th United States v. Thorson Co., 806
F.2d
1061, 1064 (Fed. Cir. 1986).
Defendant and intervenor argue that close scrutiny is not
required for the FAR
9.405(d)(3) decision not to reinstate FAS, but if required, even under this
level of
scrutiny the decision was reasonable. Plaintiff argues that the contracting
officer
abused her discretion in deciding not to reinstate FAS and that the decision
lacks a
reasonable basis. FAS asserts that the contracting officer’s concern with the
delay
involved in reinstating FAS was not reasonable. Reliance is placed on the short
response time given to FAS in a draft list of questions concerning the
responsibility
determination the contracting officer would have to make had Taos-Agility
remained
one of the owners of FAS. However, there is a considerable difference between
the
time that would be required to explain the Taos-Agility function in an unchanged
FAS proposal and the time required to redraft and submit a new proposal without
Taos-Agility involvement and for the Air Force to complete the required
evaluations
and discussions on such a new proposal. The evaluations and discussions on the
proposal FAS submitted on May 22, 2009, were not completed until September 30,
2009. (AR 002158.) Plaintiff also indicates that the contracting officer on the
date
of issuing her seven-page “Justification” for not reinstating FAS had knowledge
of
the agency-level protest that FAS submitted on the same date requesting
reinstatement. Since an award could not be made until the protest was concluded,
plaintiff argues that delay involving a new FAS proposal in the procurement, was
not
a reasonable concern because there would be delay in any event due to the
protest.
FAS’s protest does not refer to the contracting officer’s Justification and the
Justification does not refer to the protest, indicating that neither party had
knowledge
of the other’s submission when drafting their own. The fact that delay could
occur
from a protest submission in no way impacts whether the contracting officer’s
concern over delay a new FAS proposal eliminating Taos-Agility would engender
was reasonable.
A close examination of the reasons given for
the decision not to reinstate FAS
after it had divested its Taos-Agility ownership leads to the conclusion that
the
reasons have a rational basis. Delay was a factor and the contracting officer’s
Justification in this regard demonstrates a rational basis for the conclusion
reached.
The full and open competition requirement of CICA was not violated. There was
competition up to the point where FAS was suspended and the price proposals of
the
two competitors were evaluated. FAS did not change its price proposal in its FPR,
whereas VBR substantially lowered its already lower price proposal in its FPR
and
retained this lower price up to award. Based on this history, the contracting
officer
rationally concluded that with the substantial challenges ahead that FAS would
face,
were it to be reinstated, it was unlikely that FAS would lower its price
proposed,
when it had not done so previously. In this circumstance, with the award to VBR,
the
Air Force obtained the lowest possible cost that competition, as required by
CICA,
was intended to achieve.
Finally, the contracting officer in her
Justification for not reinstating FAS
concluded that with the divesting of Taos-Agility, entities that FAS relied upon
in its
proposal for performance, resources and past performance, FAS’s higher price,
and
the challenges ahead in submitting and obtaining successful evaluations for a
new
proposal, FAS did not have a reasonable chance to receive the award of the TSBMC.
In this procurement protest matter the issue is whether the agency action has a
rational, reasonable basis. Impresa Construzioni Geom. Domenico Garufi v. United
States, 238 F.3d 1324, 1332-33 (Fed. Cir. 2001); Honeywell, Inc. v. United
States, 870 F.2d 644, 648 (Fed. Cir. 1989). For the reasons stated in the
Justification issued
by the contracting officer, the suspension of Agility-Taos, resulting in the
removal of
49% of the ownership of FAS, and the challenges this presented to the viability
of a
new FAS proposal, comprised a rational basis for her conclusion that the
reorganized
FAS, at this stage of the procurement, had no reasonable chance of obtaining the
award of TSBMC. Plaintiff has failed to meet the heavy burden of demonstrating a
lack of rational basis for the contracting officer’s decision in the record of
this protest. (FAS Support Services, LLC v. U.
S. and Vinnell Brown & Root LLC, No. 10-289C, August 4, 2010) (pdf)
See above FAS
Support Services, LLC, B-402464; B-402464.2; B-402464.3,
April 21, 2010 (pdf)
The United States Court of Appeals for the Federal Circuit held
in Planning Research
Corp. v. United States, 971 F.2d 736 (Fed. Cir. 1992) that:
[T]he submission of a misstatement . . . which materially influences
consideration
of a proposal should disqualify the proposal. The integrity of the system
demands
no less. Any further consideration of the proposal in these circumstances would
provoke suspicion and mistrust and reduce confidence in the competitive
procurement system.
Id. at 741 (citation omitted).
Therefore, to establish a material misrepresentation, Sealift must demonstrate
both that TAL intentionally made a false statement and that MSC relied on that false
statement in awarding
the contract to TAL. See Blue & Gold Fleet, LP v. United States, 70 Fed. Cl.
487, 495 (2006)
("To establish a material misrepresentation, plaintiff must demonstrate that (1)
[the awardee]
made a false statement; and (2) the [agency] relied on that false statement in
selecting [the
awardee’s] proposal for the contract award. . . . To preserve the integrity of
the solicitation
process when such a material misrepresentation influences the award of the
proposal, the proposal
is disqualified from consideration.") (citations omitted), aff'd, 492 F.3d 1308
(Fed. Cir. 2007);
see also Northrop Grumman Corp. v. United States, 50 Fed. Cl. 443, 468 (2001)
("[I]t is quite
common for proposals to fall short of their assertions; it is not something to
be punished unless
the errors were willful and egregious."). Intent may be established by
circumstantial evidence.
See Planning Research Corp., 971 F.2d at 742 ("This court has held that intent
frequently must be proved by circumstantial evidence.”) (citing Klein v.
Peterson, 866 F.2d 412, 415 (Fed. Cir.
1989)).
In awarding this contract, MSC advised that:
It is useful to compare the offered rate to previous contract awards for
comparable
vessels under similar requirements. . . . Th[ese] comparisons provide support
that
the rates offered by [TAL] and Sealift under this procurement are both highly
competitive and very reasonable.
AR 1985.
MSC's price analysis also stated that:
[T]he daily rate proposed by [TAL] is considered fair and reasonable based on
price competition and comparison with previous competitively awarded prices for
comparable vessels under similar requirements in accordance with FAR [] 15.404-
1(b)(2)(i) and (ii)15 respectively.
AR 1992.
Sealift's primary evidence that TAL misrepresented the Bonito's warranted fuel
consumption is the Raggio Declaration that relies on a single data point found
on a website. See AR 2266. The Government, however, states that: "[t]o assess [TAL]'s
compliance with its fuel
warranties, it is necessary to gather information on the vessel's speed, weather
conditions, load,
and fuel consumption for each voyage the vessel makes." See AR 2513. Sealift
agrees that "[g]auging actual fuel consumption requires some research, judgment, and
initiative" in addition
to "expert review of the varying factors that affect vessel operations." Pl. Mem.
at 16.
The March 31, 2006 Solicitation provided that the "[c]ost of fuel consumed will
be based
on an operational scenario of 60% underway laden at 12 knots . . . , 28% in-port
idle . . . , and
12% in-port discharge[.]" AR 1572. The Raggio Declaration, however, only
considered the
Bonito's fuel consumption "when steaming at 12 knots." AR 2266 (Raggio
Declaration ¶ 6).
Moreover, it did not consider the March 31, 2006 Solicitation’s required
“operational scenario.”
See AR 1572. The Raggio Declaration also assumed that "[t]he slightly larger
engine on the
Bonito should have a fuel consumption no less than that of the Montauk." See AR
2266 (Raggio
Declaration ¶3) (emphasis added). Other evidence, however, indicates that the
Montauk burned
188 grams of fuel per KWH under a 100 percent load and 187 grams of fuel per KWH
under an
85 percent load, while the Bonito burned 182 grams of fuel per KWH, under a 100
percent load,
and 180 grams of fuel under an 85 percent load. See AR 2266, 2476-77, 2481
(citing
http://www.sea-web.com, an online service of LLOYD'S LIST). Sealift did not
challenge this
data.
Nordtank does not guarantee or warrant the data on the website. See AR 2301-07.
In
addition, the cases cited by Sealift are not precedential and do not stand for
the proposition that
fuel consumption rates on a website are warranted. See Pl. Reply at 5. Instead,
they hold that a
representation of fuel consumption in a charter may create a warranty in certain
circumstances.
See Transatlantic Lines, LLC, Soc’y of Mar. Arb., No. 3834 (Nov. 4, 1998)
(determining that
"speed and fuel consumption capabilities" were incorporated into a contract
through an annex);
see also Denholm Shipping Co., 47 F.2d at 214-15 ("[A] description of a ship's
capacity, in speed,
as well as in any other respect, when inserted in the body of a charter, will
support a suit for
damages.") (citation omitted) (emphasis added); The Atlanta, 82 F. Supp. at 230
(a statement as
to speed and fuel consumption in a charter results in a warranty "rather than a
representation,
even though the statement is not expressly designated as a warranty").
Accordingly, the court has determined that the Bonito's fuel consumption rate,
posted on Nordtank's website, does not evidence a material misrepresentation by TAL,
particularly since
Sealift has not proffered any independent evidence that the information on
Nordtank's website
was reliable. See AR 2301-07. In addition, the Administrative Record contains no
evidence that
the Bonito did not achieve a consumption rate of [redacted] barrels per day,
although the court afforded Sealift the opportunity to supplement the
Administrative Record with post-award
information. See AR 2536-3047; see also 1/17/08 TR 38, 41-42.
For these reasons, the court has determined that, as a matter of law, Sealift
did not
establish a false statement was made by TAL to the CO. See Blue & Gold Fleet,
LP, 70 Fed. Cl.
at 495.
(Sealift, Inc., v. U. S., No.
07-627C, July 11, 2008) (pdf) |
|
| U.
S. Court of Federal Claims - Listing of Decisions |
| For
the Government |
For
the Protester |
|
FAS Support Services, LLC v. U. S. and
Vinnell Brown & Root LLC, No. 10-289C, August 4, 2010 (pdf)
See above FAS
Support Services, LLC, B-402464; B-402464.2; B-402464.3,
April 21, 2010 (pdf) |
|
|
Sealift, Inc., v. U. S., No.
07-627C, July 11, 2008 (pdf) |
|
|
|