New
Organizational Conflicts of Interest
AdvanceMed and TrustSolutions each argue that the award to
Cahaba was tainted by OCIs arising from Cahaba’s status as
a wholly-owned subsidiary of Blue Cross/Blue Shield of
Alabama (BCBSAL), as well as conflicts arising from
Cahaba’s own business activities. For the reasons
discussed below, we conclude that CMS reasonably evaluated
the potential conflicts posed by the award to Cahaba, and
concluded that the conflicts were either mitigated, or did
not constitute significant OCIs that merited exclusion of
Cahaba’s proposal from the competition.
The Federal Acquisition Regulation (FAR) requires that
contracting officers avoid, neutralize or mitigate
potential significant OCIs so as to prevent an unfair
competitive advantage or the existence of conflicting
roles that might impair a contractor’s objectivity. FAR §§
9.504(a), 9.505. The responsibility for determining
whether an actual or apparent conflict of interest will
arise, and to what extent the firm should be excluded from
the competition, rests with the contracting agency. Aetna
Gov’t Health Plans, Inc.; Foundation Health Fed. Servs.,
Inc., B-254397.15 et al., July 27, 1995, 95-2 CPD ¶ 129 at
12.
The protesters’ arguments here concern the category
described in FAR subpart 9.5 and the decisions of our
Office as arising from impaired objectivity. An impaired
objectivity OCI exists where a firm’s work under one
government contract could entail its evaluating itself.
FAR § 9.505-4; Aetna Gov’t Health Plans, Inc.; Foundation
Health Fed. Servs., Inc., B-254297.15 et al., July 27,
1995, 95-2 CPD ¶ 129 at 13. The concern in such “impaired
objectivity” situations is that a firm’s ability to render
impartial advice to the government will be undermined by
its relationship to the product or service being
evaluated. PURVIS Sys., Inc., B-293807.3, B-293807.4, Aug.
16, 2004, 2004 CPD ¶ 177 at 7.
In reviewing bid protests that challenge an agency’s
conflict of interest determinations, the Court of Appeals
for the Federal Circuit has mandated application of the
“arbitrary and capricious” standard established pursuant
to the Administrative Procedures Act. See Axiom Res.
Mgmt., Inc. v. United States, 564 F.3d 1374, 1381 (Fed.
Cir. 2009). To demonstrate that an agency’s OCI
determination is arbitrary or capricious, a protester must
identify “hard facts” that indicate the existence or
potential existence of a conflict; mere inference or
suspicion of an actual or potential conflict is not
enough. Turner Constr. Co., Inc. v. United States, 645
F.3d 1377, 1387 (Fed. Cir. 2011); PAI Corp. v. United
States, 614 F.3d 1347, 1352 (Fed. Cir. 2010). In Axiom,
the Court of Appeals noted that “the FAR recognizes that
the identification of OCIs, and the evaluation of
mitigation proposals are fact-specific inquiries that
require the exercise of considerable discretion.” Axiom
Res. Mgmt., Inc., 564 F.3d at 1382. The standard of review
employed by this Office in reviewing a contracting
officer’s OCI determination mirrors the standard required
by Axiom. In this regard, we review the reasonableness of
the CO’s investigation and, where an agency has given
meaningful consideration to whether an OCI exists, will
not substitute our judgment for the agency’s, absent clear
evidence that the agency’s conclusion is unreasonable. See
Enterprise Info. Servs., Inc., B-405152 et al., Sept. 2,
2011, 2011 CPD ¶ 174 at 8.
BCBSAL’s Relationship with Prime Therapeutics LLC
AdvanceMed argues that the agency failed to reasonably
evaluate an OCI arising from BCBSAL’s 17-percent ownership
stake in Prime Therapeutics LLC, a pharmacy benefit
management company. The protester contends that BCBSAL’s
ownership of Prime Therapeutics creates an OCI in the
event that Cahaba is issued a task order to conduct audits
in connection with Medicare part D, which is for
prescription drug benefits, and part C, which can include
part D coverage.
As part of its corrective action in response to
AdvanceMed’s and TrustSolution’s initial protests, CMS
asked Cahaba to address the potential OCI arising from
BCBSAL’s ownership stake in Prime Therapeutics. The CO
noted that BCBSAL “acquired 16.78% investment interest in
Prime Therapeutics LLC (Prime) in 2010,” and holds one of
the 10 seats on Prime Therapeutics’ board of directors.
AR, Tab 22a, Letter from CMS to Cahaba (June 28, 2011) at
2. The CO further noted that “Prime offers pharmacy
services, Medicare Part D administration, and other
consulting services” for customers of Blue Cross Blue
Shield plans, and also provides services for four
customers in Zone 3. Id. Based on these concerns, the CO
stated that she determined that an unmitigated impaired
objectivity OCI existed “because in the event that a Part
D task order is issued, [Cahaba] may have to
investigate/evaluate Prime in its role as a [pharmacy
benefit management] company for possible fraud, waste and
abuse.” Id. The CO requested that Cahaba provide a
mitigation plan to address the concern.
In response to the request for a mitigation plan, Cahaba
expressed its view that its ownership stake in Prime
Therapeutics did not create an OCI because: (1) there are
no direct contractual relationships between Prime
Therapeutics and Cahaba; (2) Cahaba does not receive any
direct financial benefit from Prime Therapeutics’ actions;
(3) Cahaba’s management is independent of BCBSAL; and (4)
in Cahaba’s view, BCBSAL’s “small ownership interest in
Prime is too attenuated to create an OCI.” AR, Tab 22i,
Letter from Cahaba to CMS (July 22, 2011), at 4-5.
Nonetheless, Cahaba also proposed several mitigation
strategies, including [deleted]. Id. at 16-17.
The CO advised Cahaba that the agency did not accept its
views concerning BCBSAL’s ownership of Prime Therapeutics,
and still viewed the relationship as creating a
potentially disqualifying OCI for Cahaba. The CO also
stated that the agency did not view the proposed
mitigation strategies as acceptable, in part because of
the additional administrative duties they would impose on
the agency. The CO advised that Cahaba was required to
provide an acceptable response to the agency’s concerns,
and that “failure to avoid, neutralize or mitigate a
conflict of interest may result in the award of this
contract to another offeror.” AR, Tab 22b, Letter from CMS
to Cahaba (Sept. 23, 2011), at 3.
Cahaba subsequently advised CMS that BCBSAL had agreed to
divest itself of Cahaba upon notice that CMS intended to
issue a task order for Medicare parts C or D. AR, Tab 22h,
Letter from Cahaba to CMS, Sept. 29, 2011, at 1. Cahaba’s
proposed mitigation approach provided a timeline with five
milestones from the date of CMS’s announcement of its
intent to issue a task order: (1) within [deleted]:
establish the terms of sale, obtain approval from BCBSAL’s
Board of Directors, and issue a formal announcement of the
intent to sell Cahaba; (2) within [deleted]: identify and
vet prospective buyers, conduct industry research of
prospective buyers, and conduct OCI analyses; (3) within
[deleted]: agree on terms of sale with buyer; (4) within
[deleted]: execute the sale and complete all required
corporate actions and approvals; and (5) within [deleted]:
execute state corporate documents and novate required
leases. Id. at 2-3. In addition, Cahaba provided the
following “contingency plan” in the event that the
milestones are not met:
If BCBSAL cannot identify a buyer within the timeline
listed above, BCBSAL shall [deleted].
Id. at 3-4. Cahaba’s response also included a letter from
the BCBSAL Senior Vice President and Chief Financial
Officer stating that the parent company “is in agreement
with the mitigation plan proposed by Cahaba . . . related
to any future Part C or D task order for the above
mentioned solicitations [zones 3 and 6].” AR, Tab 22g,
Letter from BCBSAL to CMS (Sept. 29, 2011), at 1.
The CO concluded that Cahaba’s proposed mitigation plan
was acceptable. AR, Tab 22d, OCI Memorandum, at 6. The CO
found that Cahaba’s proposed [deleted] schedule for
divestiture was reasonable and realistic. In this regard,
the CO noted that CMS expected that it could take between
7-8 months from announcement of the agency’s intent to
issue a task order for part C or D to develop a statement
of work, obtain funding approval, negotiate the task order
with Cahaba, and complete the transition of the work from
the incumbent. Id. at 5.
The CO also stated that, in the event the divestiture
could not be achieved within the proposed [deleted] time
frame, and CMS required the services from Cahaba at that
time, the cognizant head of the CMS contracting activity
(HCA) “will authorize a waiver of the Prime Therapeutics
conflict during the time that the contingency plan is in
place.” Id. at 6. The FAR provides that an HCA may “waive
any general rule or procedure of this subpart by
determining that its application in a particular situation
would not be in the Government’s interest.” FAR § 9.503.
Here, the OCI memorandum included a memorandum from the
HCA, which stated as follows:
With regard to the mitigation strategy for the OCI
caused by BCBSAL’s ownership in Prime Therapeutics,
should it be necessary to afford [Cahaba] additional
time, in excess of the [deleted] proposed, to finalize
the sale of [Cahaba] and should CMS require [Cahaba] to
begin work on a Part C and/or Part D task order, the HCA
will authorize a waiver in accordance with FAR 9.503
while the contractor’s contingency plan is being
finalized. The waiver would be in affect only until such
time as the sale of [Cahaba] is completed. Once the sale
of [Cahaba] is completed, the waiver would no longer be
necessary and the conflict would be fully mitigated.
AR, Tab 22d, OCI Memorandum, at 11.
AdvanceMed argues that the CO unreasonably accepted the
divestiture plan because it did not provide adequate
details to address the OCI. In particular, AdvanceMed
contends that the plan lacks specificity because it does
not identify a potential buyer or sales terms. The
protester cites two decisions in which our Office
sustained protests of awards to AdvanceMed for ZPIC zones
1 and 2, based on what the protester contends were similar
OCI concerns and divestiture plans to those at issue here.
See C2C Solutions, Inc., B-401106.5, Jan. 25, 2010, 2010
CPD ¶ 38; Cahaba Safeguard Adm’rs, LLC, B-401842.2, Jan.
25, 2010, 2010 CPD ¶ 39. As relevant here, we concluded in
both protests that the CO failed to evaluate AdvanceMed’s
proposed mitigation approach of divestiture, in part
because the proposed plans lacked any meaningful detail.
In this regard, the record in the C2C Solutions and Cahaba
decisions shows that the CO’s OCI analysis merely observed
that “[t]he other mitigation strategy, total divestiture
of AdvanceMed, includes some uncertainties as to the
particulars of the divestiture that are and cannot be
known at this time.” C2C Solutions, Inc., supra, at 5;
Cahaba Safeguard Adm’rs, LLC, supra, at 6. In light of the
lack of any meaningful details to support the divestiture
plans, we sustained both protests.
In contrast to C2C Solutions and Cahaba, however, the
awardee’s mitigation plan here provided specific details
and milestones. As discussed above, the awardee stated
that BCBSAL would, upon notice of the agency’s intent to
begin the process of issuing a task order for Medicare
parts C and D, commence the necessary steps to divest
itself of Cahaba. The mitigation plan included five
milestones, which the agency evaluated and concluded were
reasonable. Additionally, as the intervenor notes, the
lack of a specific price or buyer was not unreasonable, as
there was no timeframe for a possible parts C and D task
order at the time of the award.[6] On this record, we
conclude that the CO acted within the reasonable exercise
of her discretion in concluding that Cahaba’s proposed
mitigation plan adequately addressed the OCI concerning
BCBSAL’s ownership of Cahaba and its 17 percent stake in
Prime Therapeutics.
BCBSAL’s Other Contractual Relationships
Next, AdvanceMed argues that Cahaba will be in a position
to conduct audits of companies with whom BCBSAL has
contracts, thereby creating an OCI. In this regard,
AdvanceMed argues that those providers could threaten to
sever their relationship with BCBSAL in the event of an
audit or negative finding by Cahaba, and that the threat
of such actions would impair Cahaba’s judgment.
During the corrective action, the CO asked Cahaba to
address BCBSAL’s contractual relationships with healthcare
facilities and providers who operate within zone 3. AR,
Tab 22a, Letter from CMS to Cahaba (June 28, 2011), at
3-4. The CO requested that Cahaba address the “perception
that [Cahaba’s] objectivity could be viewed as being
impaired” when it investigates an entity that has a
contractual relationship with BCBSAL. Id. at 4.
Cahaba stated that BCBSAL has a network of preferred
provider relationships with national companies, or
affiliates of national companies. Under this arrangement
the healthcare provider agrees to participate in the
BCBSAL network, and BCBSAL agrees to pay claims in
accordance with a fee schedule. AR, Tab 22i, Letter from
Cahaba to CMS (July 22, 2011), at 22. Cahaba acknowledged
that BCBSAL has contractual relationships with entities,
who, in turn, have affiliates that provide services within
Zone 3. Id. at 21-22. Cahaba argued, however, that such
BCBSAL relationships do not give rise to a disqualifying
OCI for Cahaba because the relationship is too remote and
attenuated to constitute a disqualifying OCI. Id. at 22.
With regard to scenarios where BCBSAL has a contract with
an entity who is affiliated with a healthcare provider,
who provides services in zone 3, the CO concluded that the
possibility of a conflict was too remote and too far
removed to constitute an OCI that requires mitigation. Id.
at 10. In this regard, the CO stated that the possibility
that the health care provider would complain to its
affiliate in order to have the affiliate pressure BCBSAL
to in turn pressure Cahaba was “too remote and too far
removed to be considered an OCI that requires mitigation.”
Id. Additionally, in response to the protest, the CO also
noted Cahaba’s explanation that the relationships between
BCBSAL and its contractual partners creates a “strong,
pre-existing financial incentive not to terminate their
relationship with BCBSAL” because of the benefit that the
contractual partner enjoys from having access to the
BCBSAL customer network. Supp. CO Statement (Dec. 13,
2011) at 6.
Our Office has recognized that an agency may reasonably
find that certain relationships between companies or
corporate affiliates are too remote or that the
possibility of a conflict is too unlikely or speculative
to conclude that there is a disqualifying OCI. See Valdez
Int’l Corp., B-402256.3, Dec. 29, 2010, 2011 CPD ¶ 13 at
5-6; L-3 Servs., Inc., B-400134.11, B-400134.12, Sept. 3,
2009, 2009 CPD ¶ 171 at 15; American Mgmt. Sys., Inc.,
B-285645, Sept. 8, 2000, 2000 CPD ¶ 163 at 5. In such
cases, we look for some indication that there is a direct
financial benefit to the firm alleged to have the OCI.
Here, the CO concluded that the relationship between
Cahaba and the contractual partners of its parent company
were too remote, and that there was no direct financial
benefit to Cahaba. We conclude that the CO was within her
discretion to draw these conclusions and therefore find no
basis to sustain the protest.
Cahaba’s LASER SA2PHE2 Service
Finally, AdvanceMed and TrustSolutions argue that Cahaba
offers an auditing service, known as LASER SA2PHE2, which
could create an OCI. This service is a data analysis tool
offered by Cahaba to assist clients in the identification
and prevention of healthcare fraud, waste, and abuse.
Unlike the potential conflicts arising from Cahaba’s
relationship with BCBSAL, the protesters argue that
Cahaba’s offered services would create a direct OCI by
creating the possibility that the awardee would audit
companies for which the awardee had provided data analysis
services.
During corrective action, the CO asked Cahaba to identify
the clients for whom it has provided services though its
LASER SA2PHE2 solution, and to propose a mitigation
strategy to address any conflicts that could arise from
its provision of these services. AR, Tab 22a, Letter from
CMS to Cahaba (June 28, 2011), at 3.
Cahaba responded that it had used LASER SA2PHE2 for its
contracts with CMS and the TRICARE Management Activity,
and also has a master services agreement which allows
[deleted] to place task orders with Cahaba for data
analytics services (such as LASER SA2PHE2). AR, Tab 22i,
Letter from Cahaba to CMS (July 22, 2011), at 18-19. The
awardee stated that it currently “does not have active
task orders with [deleted] and has no other commercial
clients,” and further stated that the company [deleted].
Id. at 19. Cahaba also stated that it would advise the CO
of any requests for work concerning LASER SA2PHE2 from
[deleted], and “will not contest any Contracting Officer
determination that the task order gives rise to a
[conflict of interest] and will refuse any task order as
to which the Contracting Officer has made such a
determination.” Id.
The CO concluded that Cahaba’s use of the LASER SA2PHE2
solution for contracts performed for the government did
not give rise to any OCIs. AR, Tab 22d, OCI Memorandum, at
7. The CO also concluded that because Cahaba did not have
existing commercial clients and [deleted] there were no
potential OCIs. Id.
The protesters argue that the CO’s conclusion was
unreasonable because it relied on Cahaba’s statement that
[deleted] for its LASER SA2PHE2 service. In this regard,
the protesters contend that Cahaba could, in effect,
change its mind and [deleted] and thereby create an OCI.
We think that the CO was within her discretion to conclude
that there was no OCI, based on her acceptance of Cahaba’s
statements regarding its LASER SA2PHE2 solution.
On this record, we find no basis to sustain any of the
protesters’ arguments regarding the CO’s OCI analysis.
(AdvanceMed Corporation;
TrustSolutions, LLC,
B-404910.4,B-404910.5,B-404910.6,B-404910.9, B-404910.10,
Jan 17, 2012) (pdf)
[Satellite Communications program] SATCOM [Special
Interest Program Manager] PM's Activities at the Agency
TCS argues that the SATCOM PM's participation in this
procurement was very limited and did not warrant the
disqualification of TCS from the competition. The record
shows that the SATCOM PM continued in his position until
he decided to retire from Government service in June 2009.
On November 2, 2009, the SATCOM PM signed a memorandum
addressed to his supervisor, which stated that the SATCOM
PM was seeking employment outside of the Government and
that he would disqualify himself from any involvement in
matters (including this RFP) that would have a direct and
predictable effect on any potential private sector firm
with whom he was seeking employment. AR, attach. 4, Tab
19, SATCOM PM Memorandum, Nov. 2, 2009. TCS asserts that,
prior to November 2, the SATCOM PM's participation in this
procurement was "limited to summary information only" and
"early market research activities aimed at exploring
industry capabilities and abilities to meet the Satellite
Communication program objectives." Protest at 10. TCS
further claims that, after November 2, the SATCOM PM did
not participate in any non-written communications
concerning the RFP. Id. The protest states that the SATCOM
PM does not recall being copied on any acquisition
sensitive information, but, if he was, he did not solicit
such information, and did not provide such information to
TCS. Id. at 11. The SATCOM PM began his employment
discussions with TCS [deleted], TCS submitted its proposal
on April 24, 2010, and the former SATCOM PM began working
for TCS on May 17, 2010. Id.
The contracting officer determined that the documentary
evidence he compiled indicated that the SATCOM PM's
participation in the procurement was more involved than
being "limited to summary information only" and "early
market research exploring industry capabilities," and that
the SATCOM PM did, in fact, have access to, and receive,
acquisition sensitive information. Contracting Officer's
Investigation Report at 22.
For example, the contracting officer found that numerous
industry responses (marked proprietary) to the request for
information (RFI), including those from Stratos and TCS,
received in March 2009, were provided to an individual
supervised by the SATCOM PM. Id. at 3. The contracting
officer found that although "[i]t is not clear in the
record whether [the SATCOM PM] received and reviewed the
individual responses," they were provided to an individual
supervised by him and were used for "one on one meetings
with contractors during Industry Days held in April 2009."
Id. at 14, 22.
The contracting officer further notes that in October 2009
the SATCOM PM took part in at least one meeting concerning
"critical decisions" about the procurement—i.e., the
source selection strategy and process, the requirements
for a statement of work or performance work statement, the
desired selection team skill mix, and whether alternate
proposals would be allowed. Id. at 4, 15; see AR, attach.
4, Tabs 13 and 17, E-mails and Attachments. At around the
same time, the SATCOM PM was a recipient of a 75‑page
e-mail attachment containing a cost/benefit analysis,
prepared by his office; this document was marked "FOUO
[For Official Use Only], close hold, pre‑decisional, not
releasable under [Freedom of Information Act]," and
included a detailed discussion of technical alternatives,
their potential costs, and associated risks. Contracting
Officer's Investigation Report at 4, 15; see AR, attach.
4, Tab 16, E‑mail, Oct. 20, 2009; Cost/Benefit Analysis,
May 20, 2009.
The contracting officer also considered documentary
evidence that, after November 2, the SATCOM PM received a
consolidated list of comments to a draft RFP, which
identified vendors by name, in preparation for a
teleconference meeting in November 2009 to discuss certain
elements of the RFP. Contracting Officer's Investigation
Report at 4-5, 16-17, 22; AR, attach. 4, Tab 18, E-mail,
Oct. 30, 2009; Tab 23, Meeting Minutes, Nov. 19, 2009. The
contracting officer noted that issues discussed at the
meeting (attended by the SATCOM PM) included market
research, industry responses, and a risk assessment of the
acquisition. Also discussed were the composition of the
technical evaluation team, the requirement of a statement
of objectives or a statement of work in the solicitation,
and the possible use of operational capability
demonstrations during the evaluation. Contracting
Officer's Investigation Report at 6; AR, attach. 4, Tab
23, Meeting Minutes, Nov. 19, 2009.
The contracting officer also found that the SATCOM PM
participated in another meeting 4 days later, where the
topics again included specific issues for this
procurement, including acquisition and source selection
plans, peer review, dedicated source selection team
members, and the use of operational capability
demonstrations in the evaluation. Contracting Officer's
Investigation Report at 6, 17, 22; AR, attach. 4, Tab 24,
Meeting Minutes, Nov. 23, 2009. The contracting officer
further determined that in December, the SATCOM PM was
included among the addressees on an e-mail that discussed
various cost estimates and identified the current
independent government cost estimate for this acquisition.
Contracting Officer's Investigation Report at 6; AR,
attach. 4, Tab 25, E-Mail, Dec. 11, 2009.
Based on his review of the record, the contracting officer
found that prior to his employment with TCS, the SATCOM PM
had access to non-public procurement sensitive
information, and possibly had access to the proprietary
information of potential offerors. Contracting Officer's
Investigation Report at 22. The contracting officer found
that this access continued even after the SATCOM PM
promised to disqualify himself from any involvement in
this procurement because the SATCOM PM "failed to properly
remove himself from the . . . procurement." Id. at 23. We
find that that the contracting officer's judgments were
reasonable and consistent with the record.
SATCOM PM's Employment With TCS
TCS also claims that the former SATCOM PM was "walled off"
after he was employed by TCS and that he had nothing to do
with this procurement. TCS first notes here that it
submitted its proposal prior to hiring the SATCOM PM.
Protest at 11. TCS further states that "[u]pon his
employment [with TCS], [the former SATCOM PM] was 'walled
off' from all activities related to this procurement;"
that he "has not had any discussions with TCS personnel
regarding its proposal, the relevant RFP, or the
procurement generally;" and that TCS took "extraordinary
measures to be certain that [the former SATCOM PM's]
employment with TCS was in no way related to this
procurement." AR, attach. 4, Tab 79, TCS Responses to
Agency Questions, Feb. 4, 2011, at 1. TCS stated in a
later response that it "took appropriate steps to "wall
[the former SATCOM PM] off completely from the proposal
and the proposal effort." AR, attach. 4, Tab 81, TCS
Responses to Agency Questions, Feb. 11, 2011, at 3. TCS
also stated:
In fact, TCS was so concerned about making sure its
competitive position on this procurement was not tainted
by the employment of [the former SATCOM PM] that the
interviews discussions specifically did not mention this
procurement and the capture responsibilities were assigned
to another company vice president, . . . , with specific
instructions to maintain a firewall with [the former
SATCOM PM] for all matters related to this procurement.
AR, attach. 4, Tab 79 at 2.
The contracting officer reviewed numerous communications
involving the former SATCOM PM while employed by TCS
indicating that he was privy to, and had input regarding,
information concerning TCS's revised proposal under the
procurement. Contracting Officer's Investigation Report at
19, 24. The contracting officer found that the former
SATCOM PM's participation in TCS's response to this
procurement included reviewing and providing feedback on
TCS's [deleted]Id. at 19-22; see AR, attach. 4, Tabs
44‑67, E-mails dated August 19 through October 8, 2010.
Based on his review, the contracting officer determined
that rather than being completely walled off from all
activities related to this procurement as alleged by TCS,
the former SATCOM PM "was repeatedly and regularly
informed of the progress of revisions to the final
proposal and asked for his opinion regarding some of those
revisions." Contracting Officer's Investigation Report at
24. While the protester asserts that the contracting
officer has overstated the former SATCOM PM's involvement
in the preparation of TCS's revised proposal, we find that
the contracting officer could reasonably be concerned
about the propriety of these activities.
Conclusion
Based on the record, we conclude that the contracting
officer conducted a thorough and well-documented
investigation. We further conclude that the contracting
officer reasonably determined that "the manner and extent
of [the SATCOM PM's] involvement in the procurement may
have created an actual unfair competitive advantage, but
certainly created an appearance of impropriety that is
based on significant documentary evidence and cannot be
avoided, neutralized or mitigated." Id. at 24. In this
regard, the contracting officer determined that the facts
here indicated that the SATCOM PM not only had access to
non-public information, but also provided input related to
TCS's revised proposal. Contracting Officer's
Investigation Report at 22-24. These facts, as identified
by the contracting officer, create the presumption that an
unfair competitive advantage has arisen, without the need
to inquire as to whether the information was actually used
by TCS in the preparation of its proposal. See Health Net
Fed. Servs., LLC, supra.; Aetna Gov't. Health Plans, Inc.;
Foundation Health Fed. Servs., Inc., supra. While TCS
disagrees with the contracting officer's determination to
terminate TCS's contract and to eliminate it from the
competition because of an apparent conflict of interest,
it has not shown that the contracting officer's conclusion
was unreasonable or not based on hard facts. Because the
agency has given meaningful consideration to whether a
conflict of interest existed and its judgment has not been
shown to be unreasonable, we will not substitute our
judgment for that of the agency. See CIGNA Gov't Servs.,
LLC, supra. (TeleCommunication
Systems Inc., B-404496.3,October 26, 2011) (pdf)
Unequal
Access to Information
EIS argues that Paragon had access to RTGX's proprietary
information, and that this access created an unequal
access to information OCI. Under the PMOS contract,
Paragon provides support to USTRANSCOM for acquisition of
information technology goods and services. CO Statement at
24. Paragon's duties include management of cost, schedule,
performance, and risk for a variety of agency
requirements, such as program control, resources
management, requirements management, configuration
management, test and evaluation, systems engineering,
program management support, risk management, information
technology administrative support, and acquisition
support. Id. at 24-25. EIS contends that under the PMOS
contract Paragon had the ability to access RTGX's
proprietary technical and cost information, such as RTGX's
rates, which created an unequal access to information OCI.
Supp. Protest at 38.
In her initial response to the protest, the CO stated that
Paragon did not have access to confidential or proprietary
RTGX information under the PMOS contract:
Paragon's PMOS contract does not provide it with access
to any contractor rates or prices. Even though Paragon
may be privy to some of the Programs of Records
estimates, neither IRMDR contractor rates nor ITS
information are included in this system. In addition, a
contractor's proposal or labor rates would not be
available for any Paragon employee or any other
contractor to access. Contractor rates are not entered
into any system accessible to, or maintained by, the
PMOS contractor.
CO Statement at 25.
The CO also noted that the PMOS contract required each
Paragon employee to sign a non-disclosure agreement (NDA)
with the agency. Id. at 26. These agreements stated in
relevant part as follows:
This Non-Disclosure Agreement is a standard agreement
designed for use by contractor (including subcontractor)
employees assigned to work on USTRANSCOM contracts. Its
use is designed to protect non-public government
information from disclosures and prevent violations of
federal statutes/regulations.
* * * * *
3. In the course of performing under
contract/order/solicitation # [GS-35-F-0484N] or some
other contract or subcontract for the USTRANSCOM, I
agree to:
a) Use only for Government purpose any and all
confidential business information, contractor bid or
proposal information, and/or source selection sensitive
information to which I am given access. I agree not to
disclose "non-public information" by any means (in whole
or in part, alone or in combination with other
information, directly or indirectly or derivatively) to
any person except to a U.S. Government official with a
need to know or to a non-Government person (including,
but not limited to, a person in my company, affiliated
companies, subcontractors, etc.) who has a need to know
related to the immediate contract/order, has executed a
valid form of this non-disclosure agreement, and
receives prior clearance by the contracting officer. All
distribution of the documents will be controlled with
the concurrence of the contracting officer.
b) "Non-public information", as used herein, includes
trade secrets, confidential or proprietary business
information (as defined for government employees in 18
USC 1905); advance procurement information (future
requirements, acquisition strategies, statements of
work, budget/program/planning data, etc.); source
selection information (proposal rankings, source
selection plans, contractor bid or proposal
information); . . .
c) Not to use such information for any non-governmental
purposes, including, but not limited to, the preparation
of bids or proposals, or the development or execution of
other business or commercial ventures.
AR, Tab 10, Sample NDA, at 1-2.
In its comments and supplemental protest, and supported by
a declaration of RTGX's Business Manager, the protester
contended that RTGX's proprietary information, such as
labor categories, cost data, and other performance-related
data, were available in a networked computer system to
which Paragon had access through its performance of the
PMOS contract. Decl. of RTGX Business Manager at 1. Id.
The protester also contended that RTGX provided invoices
and other proprietary data to a Paragon employee in
connection with Paragon's performance of the PMOS
contract. Id. at 2.
In response, the CO acknowledged that her initial view of
the potential access to information Paragon had under the
PMOS contract was not correct. In her supplemental
statement, the CO stated as follows:
[I]n investigating EIS's allegation, I did find an
instance where a Paragon employee . . . in the DPS
program office may have had access to RTGX rate
information from invoice reviews as part of the duties
under the PMOS support contract. However, [the Paragon
employee] had previously signed a non-disclosure
statement which is on file, and is included as an
attachment in [the PMOS CO's] declaration (PMOS CO
Declaration, Attachment 1). Even if [the Paragon
employee] did have access to rates on invoices, he was
precluded from disclosing this information to Paragon or
using this information by the terms of his nondisclosure
agreement.
Supp. CO Statement, July 20, 2011, at 8.
Notwithstanding her revised understanding of the
information to which Paragon may have had access under the
PMOS contract, the CO confirmed her finding that no
disqualifying OCI existed because the NDAs signed by
Paragon employees prohibited any disclosure which could
have affected the ITS competition. Id. Specifically, the
CO stated that she viewed the NDAs as precluding Paragon
employees from disclosing the information to any parties
not authorized to receive the information, including other
Paragon employees not covered by the NDAs. Id. at 12, 14.
As our Office has held, mitigation efforts that screen or
wall-off certain individuals within a company from others,
in order to prevent an improper disclosure of information,
may be an effective means to address an unequal access to
information OCI. See Axiom Resource Mgmt., Inc.,
B-298870.3, B-298870.4, July 12, 2007, 2007 CPD para. 117
at 7 n.3; Aetna Gov't Health Plans, Inc., supra, at 13.
EIS argues, however, that the CO did not reasonably
conclude that the NDAs mitigated the potential OCI that
arose from Paragon's performance of the PMOS contract. EIS
first argues that the CO's reliance on the NDAs signed by
Paragon employees was unreasonable because the FAR
requires a different form of NDA. In this regard, FAR
sect. 9.505-4(a) states that "[w]hen a contractor requires
proprietary information from others to perform a
Government contract and can use the leverage of the
contract to obtain it, the contractor may gain an unfair
competitive advantage unless restrictions are imposed." In
order to mitigate the potential competitive harm, the FAR
mandates the following actions:
A contractor that gains access to proprietary
information of other companies in performing advisory
and assistance services for the Government must agree
with the other companies to protect their information
from unauthorized use or disclosure for as long as it
remains proprietary and refrain from using the
information for any purpose other than that for which it
was furnished. The contracting officer shall obtain
copies of these agreements and ensure that they are
properly executed.
FAR sect. 9.505-4(b).
We agree with the protester that the PMOS CO failed to
comply with the express requirements of FAR sect.
9.505-4(b). The record shows that, contrary to the
requirements set forth above, Paragon did not enter into
an NDA with RTGX for the PMOS contract, nor did the PMOS
CO require that Paragon do so. Supp. CO Statement, July
20, 2011, at 14; PMOS CO Statement at 2. Despite this
error, we do not think that the protester was prejudiced
here. Competitive prejudice must be established before we
will sustain a protest; where the record does not
demonstrate that the protester would have had a reasonable
chance of receiving the award but for the agency's
actions, we will not sustain a protest, even if
deficiencies in the procurement process are found.
McDonald-Bradley, B-270126, Feb. 8, 1996, 96‑1 CPD para.
54 at 3.
Although the NDAs obtained by the PMOS CO did not take the
form required by FAR sect. 9.505-4(b), we think that the
CO for the ITS contract nonetheless concluded that the
NDAs adequately mitigated the possibility that Paragon had
an unequal access to information OCI. While the protester
contends that the NDAs apply only to "government
information," the record shows that the agreements cover a
broad range of contractor business information, including
"any and all confidential business information, contractor
bid or proposal information, and/or source selection
sensitive information." AR, Tab 10, Sample NDA, at 1-2.
The NDAs prohibit Paragon employees from disclosing this
information to "a non-Government person (including, but
not limited to, a person in my company, affiliated
companies, subcontractors, etc.)" unless that person has a
valid "need to know," has executed a NDA, and has received
prior clearance from the CO. Id. at 2. Finally, the NDA
prohibits use of the information for "any non-governmental
purposes, including, but not limited to, the preparation
of bids or proposals." Id. Thus, we think the CO could
reasonably find that the NDAs apply to any information
provided by RTGX to Paragon employees in the course of
either party's performance of any contract with USTRANSCOM,
and place appropriate restrictions on the disclosure or
use of that information. On this record, we conclude that
the CO reasonably exercised her judgment by relying on the
NDAs as mitigating the possible OCI arising from Paragon's
access to RTGX information under the PMOS contract.
EIS argues, however, that the company-to-company
agreements required under the FAR and the PMOS contract
(which contains a requirement that mirrors FAR sect.
9.505‑4, AR, Tab 19, PMOS Contract, at 51-52) provide
protections that are not provided by the NDAs between
Paragon and the government. Specifically, the protester
contends that "only a company-to-company agreement, as
required by the FAR and OCI clause, establishes a binding
contracting commitment with legal remedies in the event a
company's proprietary data has been improperly used by a
contractor acting on behalf of the government." Supp.
Comments, July 25, 2011, at 5 n.1. However, the absence of
additional protections and benefits that might be afforded
to contractors under a company-to-company agreement does
not render unreasonable the CO's judgment that the NDAs
adequately mitigated the possible OCIs in question here.
In sum, we find that although the PMOS CO did not follow
the requirements of the FAR to obtain company-to-company
NDAs for the PMOS contract, this error did not prejudice
the protester. In this regard, we conclude that the CO for
the instant award gave meaningful consideration to the
record, and reasonably relied on those NDAs as addressing
the potential for an unequal access to information OCI
that arose from Paragon's performance of the PMOS
contract. Thus, notwithstanding the agency's error
concerning the type of NDA obtained, we find no basis to
sustain the protest. (Enterprise
Information Services, Inc., B-405152; B-405152.2;
B-405152.3, September 2, 2011) (pdf)
In its
current protest, TAG asserts that the agency failed to
adequately consider and investigate whether SAIC has an
"impaired objectivity" OCI. In this connection, TAG
principally asserts that the agency's OCI review
improperly was limited primarily to information provided
by SAIC; according to the protester, since SAIC in effect
selected the information reviewed by the agency in
analyzing the OCI question, the agency's conclusion is
inherently unreasonable. TAG further asserts that since
the agency's analysis of the OCI question was faulty, its
execution of the D&F waiving any remaining OCI also was
faulty inasmuch as the waiving authority was unable to
appreciate the actual potential risk of an OCI. Finally,
in connection with the D&F, TAG also asserts that it
improperly included a blanket waiver of potential OCIs
that may arise in the future.
The responsibility for determining whether a conflict
exists rests with the procuring agency. CIGNA Gov't Servs.,
LLC, B-401068.4, B-401068.5, Sept. 9, 2010, 2010 CPD para.
230 at 12; Aetna Gov't Health Plans, Inc.; Foundation
Health Fed. Servs., Inc., B‑254397.15 et al., July 27,
1995, 95-2 CPD para.129 at 12. In making this
determination, the FAR expressly directs contracting
officers to examine the particular facts associated with
each situation, giving consideration to the nature of the
contracts involved, and further directs contracting
officers to obtain the advice of counsel and appropriate
technical specialists before exercising their own sound
discretion in determining whether an OCI exists. Federal
Acquisition Regulation (FAR) sections 9.504, 9.505. In
reviewing bid protests that challenge an agency's
conflicts determinations, the Court of Appeals for the
Federal Circuit has mandated application of the "arbitrary
and capricious" standard established pursuant to the
Administrative Procedures Act (APA). See Axiom Res. Mgmt,
Inc. v. United States, 564 F.3d 1374, 1381 (Fed. Cir.
2009). In Axiom, the Court of Appeals noted that "the FAR
recognizes that the identification of OCIs, and the
evaluation of mitigation proposals are fact-specific
inquiries that require the exercise of considerable
discretion." Id. The standard of review employed by this
Office in reviewing a contracting officer's OCI
determination mirrors the standard required by Axiom. In
this regard, where an agency has given meaningful
consideration to whether an OCI exists, we will not
substitute our judgment for the agency's, absent clear
evidence that the agency's conclusion is unreasonable.
See, e.g., MASAI Tech. Corp., B-298880.3, B-298880.4,
Sept. 10, 2007, 2007 CPD para. 179 at 8; Business
Consulting Assocs., LLC, B‑299758.2, Aug. 1, 2007, 2007
CPD para. 134 at 9-10; Overlook Sys. Techs., Inc.,
B‑298099.4, B‑298099.5, Nov. 28, 2006, 2006 CPD para. 185
at 10-18; Alion Sci. & Tech. Corp., B‑297022.4,
B‑297022.5, Sept. 26, 2006, 2006 CPD para. 146 at 5-8.
We have no basis to object to the adequacy of the agency's
inquiry into whether SAIC has an OCI. The protester is
correct that the starting point for the agency's effort
was to obtain information from SAIC that was to be
submitted in response to the discussions conducted during
the agency's corrective action; both SAIC and TAG were
requested to provide detailed information relating to any
potential OCI, and the firm's strategy to mitigate any
potential OCI. AR, exhs. 2, 3. In response to this request
for information, SAIC provided detailed information,
including a matrix[1] listing some [deleted] contracts
that SAIC had identified as potentially presenting an OCI,
along with an OCI mitigation plan intended to address any
OCI concerns. SAIC Revised Cost Proposal, Tab F.
The record shows that SAIC's matrix was not simply
accepted by the agency without critical analysis. Rather,
the record shows that the agency's OCI analysis team
carefully reviewed the contracts listed in SAIC's matrix;
while the team agreed with SAIC's characterization of the
contracts (and the potential for mitigating possible OCIs)
in some instances, it disagreed in other instances. For
example, the record shows that, in reviewing SAIC's
contracts, the OCI analysis team reached the following
conclusion relating to the tier one and two contracts:
The single most significant potential impaired
objectivity OCI that SAIC noted revolves around the
Joint Capabilities Integration and Development System (JCIDS).
SAIC mentions JCIDS in its discussion of all [deleted]
of the Tier 1 and Tier 2 contracts.[2] A5XP's analysis
of SAIC and JCIDS was as follows:
"The potential for an OCI in A5XP is very low. A5XP is
the Strategic Plans and Policy Division, which does not
determine requirements, capabilities, or specifications,
nor has any influence on future military acquisition of
products or services. Our role is to ensure AF policies
are in line with that of higher authorities."
"The only risk for an OCI stems from our contractor's
access to military requirements documents as they are
vetted through the Joint Capabilities Integration and
Detection System (JCIDS)."
* * * * *
"When coupled with the staffing process within A5XP,
which acts as an additional OCI mitigation layer, the
mitigation strategies outlined by SAIC [excluding itself
from participation in any JCIDS reviews or inputs
related to this program] are effective and acceptable."
* * * * *
The OCI Analysis Team accepted and concurred with A5XP's
analysis of JCIDS. SAIC's JCIDS strategies, which
include tasking one of their teaming partners with all
JCIDS reviews, when coupled with Air Force oversight of
those reviews and the limited scope of those reviews
(policy and directives compliance), taken together
constitute an effective mitigation for this potential
impaired objectivity OCI.
AR, exh. 9, at 10-11. On the other hand, the record also
shows that the agency criticized SAIC's characterization
of certain of its contracts, as well as its proposed
mitigation efforts. See e.g., AR, exh. 9, at 11-17. After
a lengthy discussion of the agency's reservations in this
connection, the agency concluded as follows:
Although these [mitigation] strategies and concepts are
useful, none of them can ensure that zero residual
potential OCI remains. As the attached Air Force
Findings attest, A5XP understands and is willing to
accept this unmitigated potential OCI risk.
AR, exh. 9, at 19.
In addition to this critical analysis of the materials
presented by SAIC, the record shows that the agency also
independently contacted references from the contracts
listed by SAIC, both to verify the accuracy of information
presented by SAIC in its matrix, and to inquire whether,
in light of the requirements being solicited, the points
of contact thought that an OCI might potentially exist in
light of the SAIC contract for which they were
responsible. AR, exhs., 4, 7, 8.
Additionally, the agency performed independent research
relating to the products and services offered by SAIC.
That review included an examination of SAIC's own
website[3] (which provides detailed information relating
to the firm's products and services), AR, exh. 5, as well
as an examination of other, independent, sources of
information about the company, many of which were critical
of the firm and its products and services. AR, exh. 6.
Finally, and most significantly, the agency, in the wake
of its review, determined that it could not rule out the
remote possibility that there was some residual potential
for an OCI because of SAIC's other contracts.
Consequently, the agency executed a D&F acknowledging and
accepting this residual risk and waiving it, consistent
with the requirements of the FAR. In this respect, the FAR
establishes that, as an alternative to avoidance,
neutralization, or mitigation, an agency head or designee
may execute a waiver. Specifically, the FAR provides:
The agency head or a designee may waive any general rule
or procedure of this subpart by determining that its
application in a particular situation would not be in
the Government's interest. Any request for waiver must
be in writing, shall set forth the extent of the
conflict, and requires approval by the agency head or a
designee.
FAR sect. 9.503.
Here, the record shows that the contracting officer
prepared and submitted a written waiver request that
described the agency's investigative efforts to determine
if SAIC had an OCI that could not be mitigated and the
extent of any residual OCI, and that provided a detailed
discussion of the bases for his conclusions that the
conflict was not significant and that waiver would be in
the best interests of the government. Contracting
Officer's Statement, Jan. 21, 2011, exh. 1. The requested
waiver was duly executed by the head of the contracting
activity, as authorized by FAR sect. 9.503. Id.
TAG challenges the adequacy of the waiver on the basis
that the agency relied solely on information provided by
SAIC to reach its conclusions regarding the possible
existence of an OCI. As discussed, however, the record
shows that the agency's efforts went well beyond mere
acceptance of the information presented by SAIC--the
agency critically examined the information presented by
SAIC, contacted the cognizant personnel for the other
contracts to inquire about potential OCIs, and conducted
its own independent research into the products and
services offered by SAIC. In these circumstances, we have
no basis to question the adequacy of the agency's
investigative efforts. CIGNA Gov't Servs., LLC, supra.
As a final matter, TAG takes issue with the terms of the
waiver itself insofar as it purports to waive future,
currently unknown, OCIs that may arise. In this respect
the waiver provides that it is being executed, in part, to
waive "[t]he risk of unknown current or future SAIC
contracts that may impact the planned A5XP task order."
Contracting Officer's Statement, exh. 1, at 7. According
to TAG, the agency cannot waive unknown future OCIs.
As an initial matter, irrespective of whether or not an
agency properly can waive future, unknown OCIs, GSA's
alleged attempt to do so here does not serve to invalidate
the agency's waiver of the known potential OCIs on the
part of SAIC, a waiver that, as discussed, we find proper.
In any case, while we agree with the protester that an
agency may not properly waive unknown or future OCIs, the
record shows that this was understood by the agency and
that the contracting officer did not intend to waive
unknown future OCIs. The contracting officer states:
As the contracting officer, in my ongoing coordination
with A5XP, I plan to remain aware of any changes that
impact potential OCIs. I will assure that the A5XP
personnel are to report any new or unknown existing
contract vehicles where additional potential risks have
been identified. My intention is to address any new OCI
issues and handle them in accordance with my duties under
the FAR. It was not my intention that the waiver would
cover unanticipated conflicts that were not considered in
the waiver request. Any new risks would go through the
same scrutiny as identified in the Waiver D&F for adequacy
of mitigation. If any risks are found to be real OCI and
complete mitigation is not provided then meetings would
ensue between the Government and the contractor to
establish acceptable mitigation procedures or complete
avoidance. The approved waiver represents the risks
currently identified and is not intended to be a catch all
for potential risks identified in the future.
Contracting Officer's Supplemental Statement, Feb. 15,
2011, at 2-3. We have no basis to question the contracting
officer's representations in this regard. Valdez Int'l
Corp., B-402256.3, Dec. 29, 2010, 2010 CPD para. 13 at 6
(GAO looks to the entire record, including the contracting
officer's statement to our Office, in reviewing a
contracting officer's judgment concerning a contractor's
possible OCI.) In light of the foregoing, we deny TAG's
protest of the OCI review. (The
Analysis Group, LLC, B-401726.3, April 18, 2011)
(pdf)
OCI
Allegations
The situations in which OCIs arise, as described in
Federal Acquisition Regulation (FAR) subpart 9.5 and the
decisions of our Office, can be broadly categorized into
three groups. The first group consists of situations in
which a firm has access to nonpublic information as part
of its performance of a government contract and that
information provides a competitive advantage in a later
competition (a “biased ground rules” OCI). FAR § 9.505-4.
The second group consists of situations in which a firm,
as part of its performance of a government contract, has
in some way set the ground rules for another contract
competition, thereby skewing the competition in its own
favor (an “unequal access to information” OCI). Id. §§
9.505-1, 9.505-2. The third group consists of situations
in which a firm’s ability to render impartial advice to
the government would be undermined by the firm’s competing
interests (an “impaired objectivity” OCI). Id. § 9.505-3.
QinetiQ contends that certain work performed by CSC under
the predecessor contract created the first and second
types of OCIs, i.e., “unequal access to information” and
“biased ground rules” OCIs. QinetiQ also contends that the
agency improperly failed to recognize or address the
alleged OCIs. With respect to the alleged biased ground
rules OCI, QinetiQ points out that certain key personnel
résumés submitted with CSC’s proposal show that the
individuals reviewed, analyzed, and defined FAA
operational requirements under the predecessor contract.
Comments and Supp. Protest at 14-17 (referencing AR, Tab
9, CSC Technical Proposal, at 2-8, 2-9, 2-15, 2-16).
QinetiQ argues that CSC was therefore in a position to
have skewed the competition in its own favor. Id.
The responsibility for determining whether an OCI exists
rests with the procuring agency. Aetna Gov’t Health Plans,
Inc.; Foundation Health Fed. Servs., Inc., B-254397.15 et
al., July 27, 1995, 95-2 CPD ¶ 129 at 12. In making the
determination, the FAR expressly directs contracting
officers to examine the particular facts associated with
each situation, giving consideration to the nature of the
contracts involved, and further directs contracting
officers to obtain the advice of counsel and appropriate
technical specialists before exercising their own sound
discretion in determining whether an OCI exists. FAR §§
9.504, 9.505. In reviewing bid protests that challenge an
agency’s OCI determination, the Court of Appeals for the
Federal Circuit has mandated application of the “arbitrary
and capricious” standard established pursuant to the
Administrative Procedures Act. See Axiom Res. Mgmt., Inc.
v. United States, 564 F.3d 1374, 1381 (Fed. Cir. 2009). To
demonstrate that an agency’s OCI determination is
arbitrary or capricious, a protester must identify “hard
facts” that indicate the existence or potential existence
of a conflict; mere inference or suspicion of an actual or
potential conflict is not enough. Turner Constr. Co. v.
United States, No. 2010-5146, slip. op. at 17-18 (Fed.
Cir. July 14, 2011); PAI Corp. v. United States, 614 F.3d
1347, 1352 (Fed. Cir. 2010). In Axiom, the court noted
that “the FAR recognizes that the identification of OCIs,
and the evaluation of mitigation proposals are
fact-specific inquiries that require the exercise of
considerable discretion.” Id. The standard of review
employed by this Office in reviewing a contracting
officer’s OCI determination mirrors the standard required
by Axiom. In this regard, where an agency has given
meaningful consideration to whether an OCI exists, we will
not substitute our judgment for the agency’s, absent clear
evidence that the agency’s conclusion is unreasonable.
CIGNA Gov’t Servs., LLC, B-401068.4; B-401068.5, Sept. 9,
2010, 2010 CPD ¶ 230 at 12.
In resolving this protest, our Office conducted a 2-day
hearing on the record, during which testimony was provided
by the contracting officer, the TET chairman, and a
QinetiQ vice president who serves as the program manager
for QinetiQ’s V-TRIPS contract. At the hearing, the
contracting officer testified that he considered the
existence of OCIs on an ongoing basis during the
procurement, and that it was his view that CSC’s prior
work did not create an OCI. Hearing Tr. at 11, 30, 40-41,
110. The contracting officer stated that his OCI analysis
included consideration of the circumstances described in
FAR subpart 9.5. Hearing Tr. 11, 40-41. He stated that he
also considered that all of the V-TRIPS contracts included
a clause requiring the contractors to disclose any OCIs
known before award, or discovered after award, and that
CSC had made no disclosures. Id. at 260-63 (referencing
AR, Tab 35, QinetiQ V-TRIPS Contract, § H.14(a), (e)).
With regard to CSC’s work under the predecessor contract,
the contracting officer testified that he knew that CSC
had analyzed and defined agency requirements. Id. at 49,
92-93. He also testified that he had reviewed the résumés
in CSC’s proposal that described analysis and definition
of requirements under the predecessor contract. Id. at
95-97. The contracting officer acknowledged, however, that
he did not know, or inquire, whether CSC had participated
in the preparation of the SOW for the protested task
order, or whether those who prepared that SOW had used
materials that CSC created under the predecessor
contract.8 Id. at 37-38, 62-65, 68-6
At the hearing, the TET chairman, whose day-to-day
responsibilities include management of projects supported
by TRIPS and V-TRIPS contractors, testified that CSC’s
analysis and definition of requirements under the
predecessor contract involved identifying system features
that are required by system users. Id. at 113-14, 136-37,
194-95, 200. This work generally occurred, he explained,
in connection with routine efforts to create enhancements
to those systems Id. at 131, 200-01. The TET chairman
further testified that he had responsibility over
preparation of the SOW at issue in this protest. Id.
at 118-19, 127-28. No contractors, he testified, assisted
with preparation of the SOW, and no contractor-prepared
documents--including the system requirement definitions
prepared by CSC--or contractor input were considered in
connection with preparing the SOW. Id. at 120, 128, 131,
136, 142. Additionally, he testified that even if CSC had
not performed the requirements definition work, portions
of the SOW relevant to this protest would not have been
changed from the way that they appear in the SOW. Id. at
198-99, 205, 219-20, 224.
Notwithstanding the TET chairman’s testimony, QinetiQ
argues that CSC shaped the SOW because, according to
QinetiQ, the SOW includes requirements that were not
included in the TRIPS contract SOW and that CSC allegedly
defined. Post-Hearing Comments at 16. The only such
requirement identified by QinetiQ, however, is compliance
with the SWIM methodology. Id. at 12-14, 16. In this
regard, QinetiQ points out that one of CSC’s key personnel
résumés reflects support of the FAA SWIM/ITWS program. Id.
at 12-14 (referencing AR, Tab 9, CSC Technical Proposal,
at 2-9).
As discussed above, FAA’s SWIM program aims to increase
the sharing of ATMS information. See FAA SWIM Questions
and Answers, http://www.faa.gov/about/ office_org/headquarters_offices/ato/service_units/techops/atc_comms_services/
swim/qanda/ (last visited July 25, 2011); see also CSC
Hearing Exhibits, Exh. 1, at 23; Hearing Tr. at 185. As
also discussed above, 4 of the more than 125 activities
described in the SOW referenced compliance with the SWIM
methodology. RFP § C.3, at 8-10. In his testimony, the TET
chairman characterized the SOW references to SWIM as “very
generic” and indicated that they were included in the SOW
for the general purpose of informing offerors that the
agency has adopted the SWIM methodology. Hearing Tr. at
167-70. The TET chairman also testified that there was no
connection between CSC’s work on the SWIM/ITWS program and
the SOW. Id. at 165. For these reasons, and because the
record does not reflect hard facts to show that CSC’s work
under the predecessor contract put the firm in a position
to materially affect the protested procurement--for
example by influencing the agency’s decision to structure
its projects to comply with the SWIM methodology--QinetiQ’s
protest that CSC’s prior work created a potential or
actual biased ground rules OCI is denied. See DRS C3 Sys.,
LLC, B-310825, B-310825.2, Feb. 26, 2008, 2008 CPD ¶ 103
at 7-8; Operational Res. Consultants, Inc., B-299131.1,
B-299131.2, Feb. 16, 2007, 2007 CPD ¶ 38 at 6; Mechanical
Equip. Co., Inc. et al., B-292789.2 et al., Dec. 15, 2003,
2004 CPD ¶ 192 at 26-27.
QinetiQ also argues that the award to CSC violates FAR §
9.505-1 because, as alleged by QinetiQ, the record
reflects that under the protested task order, CSC will be
developing and integrating system enhancements that are
connected with the requirements defined by CSC under the
predecessor contract. Post-Hearing Comments at 8-14. FAR §
9.505-1 requires that a contractor that provides systems
engineering and technical direction for a system for which
it does not have overall responsibility for development,
integration, assembly, and checkout, or for its
production, shall not be awarded a contract to supply the
system. FAR § 9.505-1(a). The regulation states that
systems engineering includes a combination of
“substantially all” of the following activities:
determining specifications, identifying and resolving
interface problems, developing test requirements,
evaluating test data, and supervising design. Id. §
9.505-1(b). It also states that technical direction
includes a combination of “substantially all” of the
following activities: developing work statements,
determining parameters, directing other contractors’
operations, and resolving technical disputes. Id.
According to the regulation, a contractor performing these
activities occupies a highly influential position in
determining a system’s basic concepts and supervising
their execution, and thus should not be in a position to
make decisions favoring its own products or capabilities.
Id.
At the hearing, the contracting officer denied that CSC
performed technical direction under the predecessor
contract. Hearing Tr. at 41-42. Further, nothing in the
record, and nothing offered by QinetiQ, demonstrates that
CSC performed the technical direction activities described
in FAR § 9.505-1(b), much less “substantially all” of
those activities. Moreover, the basis for QinetiQ’s
invocation of FAR § 9.505-1 is unclear given that FAR §
9.505-1 pertains to contracts for the “supply of [a]
system or any of its major components,” and the SOW here
does not call for the supply of a system or major
components of a system. For these reasons, we see no merit
in QinetiQ’s claim that the award to CSC violates FAR §
9.505-1.
With respect to the
alleged unequal access to information OCI, QinetiQ asserts
that certain résumés included with CSC’s proposal
demonstrate that CSC had access to nonpublic information
under the predecessor contract that gave CSC an unfair
competitive advantage. Comments and Supp. Protest at 6, 9.
The only specific information to which QinetiQ alleges CSC
had access, however, is the agency’s preference for
minimizing custom coding. Id. at 11. QinetiQ argues that
the agency’s determination to assign a strength to CSC’s
proposal for an emphasis on minimizing custom coding
demonstrates that QinetiQ suffered prejudice as a result
of the role that CSC played in developing the “configure
don’t code” approach. Id. at 10 (referencing AR, Tab
11(a), TET Report Excerpt--CSC, at 6).
At base, QinetiQ’s
position is that an unequal access to information OCI
arose because, in QinetiQ’s words, QinetiQ’s personnel did
not “have nearly the same level of inside knowledge and
experience that [CSC’s personnel] enjoy[ed] through
[their] roles at the Volpe Center.” Supp. Comments at 21.
It is well-settled that an offeror may possess unique
information, advantages, and capabilities due to its prior
experience under a government contract--either as an
incumbent contractor or otherwise; further, the government
is not necessarily required to equalize competition to
compensate for such an advantage, unless there is evidence
of preferential treatment or other improper action. See
FAR § 9.505-2(a)(3); CACI, Inc.--Fed., B-403064.2, Jan.
28, 2011, 2011 CPD ¶ 31 at 10; MASAI Tech. Corp.,
B-298880.3, B-298880.4, Sept. 10, 2007, 2007 CPD ¶ 179 at
8. The existence of an advantage, in and of itself, does
not constitute preferential treatment by the agency, nor
is such a normally occurring advantage necessarily unfair.
Council for Adult & Experiential Learning, B-299798.2,
Aug. 28, 2007, 2007 CPD ¶ 151 at 6; Government Bus. Servs.
Group, B-287052 et al., Mar. 27, 2001, 2001 CPD ¶ 58 at
10.
The portions of the CSC
résumés on which QinetiQ’s argument hinges reflect that
CSC personnel had experience with supporting various Volpe
Center activities, including development of a “configure
don’t code” approach in connection with SWIM. See AR, Tab
9, CSC Technical Proposal, at 2-3, 2-5, 2-7, 2-9. The
agency’s determination to credit CSC’s proposal for
demonstrating that experience--together with the absence
of evidence of any preferential treatment or unfair action
by the agency--amounts to no more than a reflection of the
normally occurring advantage that an incumbent may
possess. See CACI, Inc.--Fed., supra; Council for Adult &
Experiential Learning, supra. (QinetiQ
North America, Inc.
B-405008; B-405008.2, Jul 27, 2011) (pdf)
OCI
Allegations
PCCP and Bechtel protest that CBY has an impermissible OCI that
the Corps failed to reasonably investigate or mitigate.
Specifically, the protesters argue that CBY's employment of the
agency's Chief of Program Execution of the Hurricane Protection
Office (HPO)--the office within the Corps responsible for this
project and procurement--provided the awardee with an unfair
competitive advantage that was based upon an unequal access to
information OCI. The protesters complain that the CO's
investigation of this potential OCI explored only the Chief's
responsibility for this procurement prior to leaving the Corps,
and did not consider the Chief's access to source selection
sensitive information.
In answer, the Corps contends that the hiring of the Corps's
Chief of Program Execution for the HPO by CBY's managing partner
did not provide CBY with competitively useful, non-public
information; the Corps also defends the CO's review of the
situation, and his conclusions. See Supp. Legal Memorandum at 9,
citing AR, Tab 15, OCI Determination & Findings (D&F). The
agency contends that our review of the CO's determination is
limited to determining whether the CO reasonably concluded that
no actual OCI existed. Id. at 10.
At the time of his retirement from the Corps on August 31, 2010,
the Chief of Program Execution held the most senior civilian
position at the HPO. In this role, the Chief had full authority
for management decisions related to major elements of the
hurricane protection program and projects, including the
permanent pumps project. See AR, Tab 16, October 13, 2009
Post-Employment Ethics Guidance Letter. Less than a month later,
on September 20, the Chief began working as a project manager
for CDM, which was the managing partner of the CBY joint
venture, the awardee here. At some point thereafter, his title
changed from project manager to strategic accounts manager. At
the time the Chief left government service and was hired by CDM,
offerors were preparing their phase II initial proposals.
After the Chief had left the Corps and was working for CDM, and
after the Corps had evaluated the final proposal revisions
submitted under the permanent pumps procurement, the CO began an
investigation to determine whether an OCI existed. CO's
Statement at 5. The CO prepared a Determination and Findings
(D&F) of the potential OCI, which focused on the Chief of
Program Execution's responsibilities and activities with respect
to this procurement. In the OCI D&F, the CO stated that as a
result of his investigation and interviews, he found that the
Chief retired prior the submission of phase II proposals and
that the "structure and ground rules for phase II continued to
evolve and changed substantially" after his retirement. The CO
concluded that the Chief "effectively removed himself from any
involvement in this procurement beginning approximately June
2010." AR, Tab 15, OCI D&F, at 2, 4.
During the course of this protest, the CO revisited his review
and expanded it to include consideration of a possible violation
of the procurement integrity provisions of the Office of Federal
Procurement Policy Act. In the Procurement Integrity D&F, the CO
provided more detail supporting his conclusion that the Chief
was effectively removed from participation in this procurement
prior to the phase II competition. In this regard, the CO noted
that the Chief stated that he reached an agreement with the
Colonel heading the HPO, in June, 2009, that the Chief would
have no further responsibility for acquisition activities, in
order to minimize restrictions on the Chief's search for
post-government employment. AR, Tab 15, Procurement Integrity
D&F, at 4.
Before we begin our review, we note that the FAR requires that
contracting officials avoid, neutralize or mitigate potential
significant conflicts of interest so as to prevent an unfair
competitive advantage or the existence of conflicting roles that
might impair a contractor's objectivity. FAR sections 9.504(a),
9.505. The responsibility for determining whether an actual or
apparent conflict of interest will arise, and to what extent the
firm should be excluded from the competition, rests with the
contracting agency. Aetna Gov't Health Plans, Inc.; Foundation
Health Fed. Servs, Inc., B-254397 et al., July 27, 1995, 95-2
CPD 129 at 12. In making this determination, the FAR expressly
directs contracting officers to examine the particular facts
associated with each situation, giving consideration to the
nature of the contracts involved, and further directs
contracting officers to obtain the advice of counsel and
appropriate technical specialists before exercising their own
sound discretion in determining whether an OCI exists. FAR
sections 9.504, 9.505; CACI, Inc.-Fed., B-403064.2, Jan. 28,
2011, 2011 CPD para. 31 at 9.
The FAR recognizes that conflicts may arise in factual
situations not expressly described in the relevant FAR sections,
and advises contracting officers to examine each situation
individually and to exercise "common sense, good judgment, and
sound discretion" in assessing whether a significant potential
conflict exists and in developing an appropriate way to resolve
it. FAR sect. 9.505. The regulation identifies situations in
which an OCI may arise, including, as relevant here, where a
firm competing for a government contract has "[p]roprietary
information (that was obtained from a Government official
without proper authorization)" or "source selection information
. . . that is relevant to the contract but was not made
available to all competitors, and such information would assist
the contractor in obtaining the contract." FAR sect. 9.505(b).
In reviewing bid protests that challenge an agency's conflict of
interest determinations, the Court of Appeals for the Federal
Circuit has mandated application of the "arbitrary and
capricious" standard established pursuant to the Administrative
Procedures Act. See Axiom Res. Mgmt, Inc. v. United States, 564
F.3d 1374, 1381 (Fed. Cir. 2009). To demonstrate that an
agency's OCI determination is arbitrary or capricious, a
protester must identify "hard facts" that indicate the existence
or potential existence of a conflict; mere inference or
suspicion of an actual or potential conflict is not enough.
Turner Constr. Co., Inc. v. United States, No. 2010-5146, slip.
op. at 17-18 (Fed. Cir. July 14, 2011); PAI Corp. v. United
States, 614 F.3d 1347, 1352 (Fed. Cir. 2010). In Axiom, the
Court of Appeals noted that "the FAR recognizes that the
identification of OCIs, and the evaluation of mitigation
proposals are fact-specific inquiries that require the exercise
of considerable discretion." Axiom Res. Mgmt., Inc., 564 F.3d at
1382. The standard of review employed by this Office in
reviewing a contracting officer's OCI determination mirrors the
standard required by Axiom. In this regard, we review the
reasonableness of the CO's investigation and, where an agency
has given meaningful consideration to whether an OCI exists,
will not substitute our judgment for the agency's, absent clear
evidence that the agency's conclusion is unreasonable. See CACI,
Inc.-Fed., supra, at 9; CIGNA Gov't Servs., LLC, B-401068.4;
B-401068.5, Sept. 9, 2010, 2010 CPD para. 230 at 12.
As set forth more fully below, we find that the CO did not
conduct a reasonable investigation to determine whether CBY's
employment of the agency's former Chief of Program Execution
provided the firm with access to non-public, selection sensitive
information that gave CBY an unfair competitive advantage. The
record shows that the CO's investigation was narrowly focused
upon what role the former government employee had in the conduct
of the procurement before his retirement (and even then did not
consider pertinent information), and did not explore the Chief's
access to proprietary or source selection information and
whether this information provided an unfair competitive
advantage to CBY.
The Chief's Role for the Corps and His Continued Involvement
in the Procurement
As indicated above, at the time of his retirement from the
Corps, the Chief held the most senior civilian position at the
HPO, and in that position he had full authority for management
decisions related to major elements of the hurricane protection
program and projects, including the permanent pumps project. See
AR, Tab 16, Post‑Employment Ethics Guidance Letter, Oct. 13,
2009. The HPO was responsible for the permanent pumps project,
and the Permanent Pumps Station branch reported directly to the
Chief. See AR, Tab 15, Procurement Integrity D&F, attach. 4, HPO
Organizational Chart. The HPO activities the Chief directed
included construction management, levees, floodwalls and
armoring, existing pump stations, permanent pump stations, and
the Inner Harbor Navigation Canal, among others. See AR, Tab
32a, Post‑Employment Ethics Opinion, July 22, 2010, at 1-2. The
Corps's ethics counselor found that the Chief had participated
personally and substantially in nearly all matters within HPO,
specifically naming the permanent pumps project. Id. at 2. The
Chief participated in the Corps's preparation of the Acquisition
Strategy for the permanent pumps. AR, Tab 15, attach. 8,
Acquisition Plan, at 48. The Chief was listed as an advisor to
the SSEB for both phases of the procurement (although he denies
having acted in that capacity). The Director of Task Force Hope,
or overall manager of the $14 billion hurricane protection
system program, who was the SSA for this procurement, asked the
Chief to intervene with the senior project manager for this
procurement to have a different contracting officer assigned to
the job. Tr. at 1091. The person whom the Chief approached in
this regard, who was working as a deputy in the district at that
time, was then moved to the HPO to become the chief of one of
the HPO's contracting groups, and CO for this procurement in
April 2010. Id.
The record does not support the agency's OCI conclusion that the
Chief had removed himself from the procurement in June of 2010.
See AR, Tab 15, OCI D&F, at 2. Instead, the record shows that
until he retired, the Chief continued to work in close proximity
and communication with the agency's project manager for the
permanent pumps project, who reported to the Chief throughout
his employment with the Corps. Tr. at 1043. The project manager
testified, for example, that he had conversations with the Chief
in hallways or in his office, Tr. 77, discussing such matters as
the costs and the risks of the project, the RFP, how
build-to-budget was received by industry, performance
requirements, updates, and, in general, discussed the project
with the Chief frequently. See Tr. at 76-78. The project manager
further testified that there was never a formal declaration,
even to him, that the Chief had recused himself from the
project. Tr. at 944.
Other evidence supports the Chief's continued involvement in the
procurement prior to his retirement. For example, Bechtel
provided a sworn declaration of its Operations Manager, who
stated that he and another Bechtel employee met with the
agency's Chief and the Colonel in charge of the HPO on July 6,
2010, after Phase II had begun, and discussed with them the
build-to-budget concept. See Bechtel Supp. Protest, exh. 2, Decl.
of Bechtel Operations Manager, June 6, 2011. The Corps has
offered no rebuttal to this sworn statement.
In addition, we find the assertion that there was an agreement
between the Chief and the Colonel in 2009, under which the Chief
allegedly agreed to have no further responsibility for
acquisition activities beginning approximately a year prior to
his retirement, deserving of little probative weight. This
agreement (which was mentioned for the first time in a
post-protest D&F) is not contemporaneously documented, and it
does not appear that other government personnel were aware of
its existence. In this regard, although the Chief asserted that
he had made sure that the permanent pumps project manager (who
was also the head of the project delivery team, source selection
advisory council member, and Permanent Pump Station Branch
chief) and the rest of his staff knew of the agreement with the
Colonel, Tr. at 1057, the project manager testified that he was
unaware of the agreement until after the protests were filed.
Tr. at 972. Similarly, the contracting officer was not told of
the agreement until after the protests were filed, see AR, Tab
15, Procurement Integrity D&F, at 5, although he would have been
expected to learn of such an agreement as a result of his
investigation of CBY's potential OCI. Moreover, it was revealed
at the hearing that the Colonel did not independently recall the
agreement with sufficient clarity to be willing to sign a
declaration (prepared in connection with this protest) about his
recollection of it, until after a copy of the declaration was
provided to the Chief to "make sure [the Chief] didn't see any
problems with it before [the Colonel] signed it." Tr. at
1125-30.
Despite the Chief's continued close contact within the office
responsible for this procurement, the D&Fs (and the record
generally) do not show any investigation into whether any
boundaries or restrictions were placed on the Chief's access to
non-public, competitively sensitive information. In this
connection, the Corps argues in its post-hearing comments that
"[e]ven absent a proactive firewall excluding [the Chief] from
the acquisition, all members of the selection team told the CO
that they had never discussed the acquisition with [the Chief],"
citing the OCI D&F as support for this assertion. See Agency's
Post-Hearing Comments at 49. We give little weight to this
assertion, however, given that the OCI D&F, in contrast to the
Corps's post‑protest assertions, states only that the CO
inquired whether members of the selection team had discussions
about the phase II evaluation with the Chief "following his
departure from federal service." See AR, Tab 15, OCI D&F, at 4.
This does not account for the Chief's access to non-public,
selection sensitive information prior to his retirement.
The Chief's Access to Non-Public, Selection Sensitive
Information and Provision of Such Information to CBY
The Corps and CBY contend that the protesters cannot show that
the Chief provided non-public, competitively useful information
to CBY. However, Bechtel and PCCP point to the Corps's
interpretation of the RFP's build-to-budget approach, and CBY's
apparently unique knowledge that offerors were permitted to
propose less than the $700 million ceiling for this contract.
The record shows that the Corps began considering the
build-to-budget approach for this procurement as early as
February 2009, when, according to the Corps, the Chief still had
responsibility for the project. Also, the record shows that the
Chief was a required attendee at a February 1, 2010, permanent
pumps build-to-budget briefing, in which this approach, and the
decision to use it, were explained to the Colonel, and at which
briefing the Chief was given slides showing feedback on this
issue from one-on-one meetings held with prospective
competitors. See AR, Tab 15, Procurement Integrity D&F,
attach. 7, Feb. 1, 2010 E-mail Confirming the Chief's Required
Attendance; Tab 30, Decl. of Project Manager, at 1. A briefing
slide from that meeting expressly provides, "Require offerors to
submit proposals at or below the budgeted amount," a phrase that
was not included on slides from briefings to industry and did
not appear in the RFP. See PCCP's Supp. Protest, exh. 34,
Build-to-Budget Briefing, at 2 (emphasis added).
The record also shows that on July 22, 2010, while the Chief was
still working at the Corps—after phase II of the procurement had
begun—the Chief received an e-mail from the agency's permanent
pumps project manager, marked "high importance," concerning the
build-to-budget provision and setting forth a proposed
clarification to the RFP. See Hearing exh. 6 at 6. Following the
proposed clarification, the e-mail asks whether "this solves the
issue." The e-mail, initially sent from the contracting officer
to the consultant who introduced the build-to-budget concept and
the project manager, was forwarded directly to the Chief by the
project manager. There is no explanation in the record of why
the Chief was continuing to receive procurement information
regarding the build-to-budget issue.
The record further shows that the Chief, after accepting
employment with CBY, responded to CBY's request for advice about
whether the firm should take an "opportunity to come in below
$700 million." Tr. at 1113. The Chief testified that he advised
CBY that, "if you could increase your value for the program,
increase it . . . [i]f not, you know, it says within the number.
It doesn't say you've got to hit $700 million. So don't just add
money to add money." Tr. at 1114. In short, he advised CBY that,
notwithstanding the RFP's express direction not to offer a lower
price, CBY could offer a lower price. As noted above, CBY was
the only offeror to propose less than $700 million.
Agency's Failure to Investigate Chief's Role at CBY and CBY's
Access to Non‑Public, Selection Sensitive Information
The record does not show that the CO reasonably investigated the
Chief's role and activities with CBY and whether CBY had access
to non-public, selection sensitive information through the
Chief. Rather, the CO merely stated in his D&Fs that the Chief's
name did not appear in any of CBY's proposal documents and that
nothing in CBY's proposal indicated that the awardee had
received superior knowledge from the Chief. See AR, Tab 15, OCI
D&F, at 2, 5; see also Procurement Integrity D&F, at 9. No
support for these conclusory statements is provided in the D&Fs,
or elsewhere in the record. Although the OCI D&F was dated March
24, 2011--approximately 6 months after the Chief started working
for CBY's managing joint venture partner--it is written as if
the Chief had not yet been hired by CDM. The contracting officer
did not contact the Chief for a first‑hand account of his
activities after he retired from the Corps or to learn what role
he played at CDM. The record shows, in contrast to the CO's
conclusions, that, following employment by CBY's managing joint
venture partner, the Chief participated in "red team" reviews on
CBY's phase II proposal and FPR, see Tr. at 43, and as explained
above, the Chief counseled CBY that it could offer less than the
build-to-budget amount identified in the RFP.
We note that the OCI D&F concludes that "some mitigation of the
potential for an appearance of a conflict occurred when [the
Chief] was counseled, when he withdrew from advising the SSO,
and when Corps employees were instructed to refrain from
discussions with [the Chief] about the project." OCI D&F at 4.
We do not believe that the CO could reasonably view the cited
events as reliable evidence of mitigation. For example, we
understand the "counseling" to refer to a post-employment ethics
opinion the Chief received from the Corps after he was offered
employment by CBY's managing partner. AR, Tab 32a,
Post-Employment Ethics Opinion, July 22, 2010; Tr. at 1095. The
Ethics Opinion was issued based on information the Chief
provided, including a job description. AR, Tab 32a. After
reciting the facts, the opinion concludes that the Chief
participated personally and substantially in nearly all matters
within HPO, and includes the permanent pump station projects
among the three specific areas in which he personally and
substantially participated. Id. at 2. With respect to the
Chief's prospective employer, the opinion states, "[y]ou advise
that CDM does not currently have any contracts on any projects
under HPO's area of responsibility," id. at 3, without any
apparent consideration of CDM's role in CBY. The opinion
directed the Chief to "immediately seek an updated opinion" if
his duties with CDM changed or were different from those
described in the opinion. The Chief testified that he assumed
the ethics counselor would verify the documents he had signed,
and that, once he went to work for CDM, he "saw no reason" to
ever tell the ethics counselor that he was working on the
permanent pumps project. Tr. at 1247-48. With respect to his
withdrawal from advising the SSO, and instructions to Corps
employees not to discuss the project with the Chief, we find no
contemporaneous documentation--or other meaningful evidence in
the record--to support that these events took place.
In sum, we find that hard facts exist to suggest the existence
of a potential, if not actual, OCI that the Corps failed to
reasonably evaluate and avoid, neutralize, or mitigate. In this
regard, the Corps did not reasonably investigate the extent to
which the Chief had access to non-public, source selection
information and whether this information provided a competitive
advantage to CBY. Specifically, the agency failed to reasonably
consider the Chief's access to build-to-budget information that
appears to have provided CBY with a competitive advantage in
this procurement. In our view, the agency's failure to
reasonably investigate the OCI taints the integrity of the
procurement process. We therefore sustain PCCP's and Bechtel's
protests of this issue. (PCCP
Constructors, JV; Bechtel Infrastructure Corporation,
B-405036; B-405036.2; B-405036.3; B-405036.4; B-405036.5;
B-405036.6, August 4, 2011) (pdf)
CACI again
protests that BAH's role as [Defense Human Resources Activity]
DHRA support contractor created an "unequal access to
information" OCI that cannot be mitigated, and as such, BAH
should have been excluded from the competition. CACI also again
argues that because of BAH's performance as a support contractor
to DHRA's Program Management Office, BAH has "a unique knowledge
of the government's plans, attitudes and preferences for future
[Defense Personnel Records Information Retrieval System] DPRIS
development." Protest at 13. In support of this assertion, the
protester points, without explanation, to the previously
discussed statements provided by the CACI employees to the
agency in response to the agency's August 13 request. The
protester also points to BAH's technical proposal in support of
its assertion that BAH's participation in the competition
created an unequal access to information OCI, noting, for
example, that BAH's proposal states that BAH has a "unique
understanding" of the agency's "needs and strategic vision."
Id.; see AR, Tab 62, BAH Technical Proposal, at 1-1. The
protester also again argues that BAH, in its performance of the
DHRA task order, attended meetings at which CACI and agency
personnel had been present, and that these meetings exposed BAH
personnel to certain CACI proprietary information regarding
CACI's performance as the incumbent DPRIS support contractor.
The responsibility for determining whether a conflict exists
rests with the procuring agency. Aetna Gov't Health Plans, Inc.;
Foundation Health Fed. Servs., Inc., supra, at 12. In making
this determination, the FAR expressly directs contracting
officers to examine the particular facts associated with each
situation, giving consideration to the nature of the contracts
involved, and further directs contracting officers to obtain the
advice of counsel and appropriate technical specialists before
exercising their own sound discretion in determining whether an
OCI exists. FAR sections 9.504, 9.505. In reviewing bid protests
that challenge an agency's conflict determinations, the Court of
Appeals for the Federal Circuit has mandated application of the
"arbitrary and capricious" standard established pursuant to the
Administrative Procedures Act. See Axiom Res. Mgmt, Inc. v.
United States, 564 F.3d 1374, 1381 (Fed. Cir. 2009). In Axiom,
the Court of Appeals noted that "the FAR recognizes that the
identification of OCIs, and the evaluation of mitigation
proposals are fact-specific inquiries that require the exercise
of considerable discretion." Id. The standard of review employed
by this Office in reviewing a contracting officer's OCI
determination mirrors the standard required by Axiom. In this
regard, where an agency has given meaningful consideration to
whether an OCI exists, we will not substitute our judgment for
the agency's, absent clear evidence that the agency's conclusion
is unreasonable. CIGNA Gov't Servs., LLC, B‑401068.4;
B‑401068.5, Sept. 9, 2010, 2010 CPD para. 230 at 12.
As indicated by the discussion above, the record reflects that
the agency performed a comprehensive OCI analysis. The TEBC/DPRIS
PM and contracting officer, as well as individuals associated
with DHRA's Office of the General Counsel and Procurement
Support Office, all participated in the OCI analysis, and
clearly gave "meaningful consideration to whether an OCI exists"
with regard to BAH's performance as the DHRA support contractor.
The protester's assertion that BAH's DHRA task order gave BAH an
unfair competitive advantage because BAH gained a "unique
understanding" of the agency's plans and needs was expressly
addressed by the agency during its OCI analysis, and found to be
without merit. As explained above, the agency states that
certain information regarding its plans for DPRIS had been
released publicly, and that it failed to understand, based upon
its analysis and CACI's generalized assertions, why BAH could be
considered to have any such "unique awareness." In this regard,
the agency also noted that to the extent BAH had an advantage in
this competition because of its performance of the DHRA task
order, CACI enjoys a similar or greater advantage because of its
15 years of performance as the DPRIS support contractor under
its task order.
Based on our review of the record, we cannot conclude that this
aspect of the agency's OCI determination was unreasonable or
reflected an abuse of discretion. We agree with the agency that,
with the exception of the generalized statements in BAH's
technical proposal, CACI has failed to point to any specific
agency information BAH may have learned during its performance
of the DHRA task order that provided BAH with an unfair
advantage in competing for this award. Moreover, and in regard
to BAH's alleged "unique awareness" of the agency's needs or
plans, it is well settled that an offeror, such as BAH (or CACI),
may possess unique information, advantages and capabilities due
to its prior experience under a government contract--either as
an incumbent contractor or otherwise; further, the government is
not necessarily required to equalize competition to compensate
for such an advantage, unless there is evidence of preferential
treatment or other improper action. MASAI Techs. Corp.,
B‑298880.3, B-2988880.4, Sept. 10, 2007, 2007 CPD para. 179 at
8. The existence of an advantage, in and of itself, does not
constitute preferential treatment by the agency, nor is such a
normally occurring advantage necessarily unfair. Id. With regard
to the language in BAH's technical proposal, which is the only
specific evidence the protester contends supports its assertion
here, we cannot find that such statements, which amount to
"puffery," are sufficient to establish that BAH had an unfair
competitive advantage, particularly given the agency's other
findings to the contrary. See Imperial Schrade Corp.,
B‑223527.2, Mar. 6, 1987, 87-1 CPD para. 254 at 12 (statements
made by retired Army officer that only he knew the agency's
needs were mere puffery and insufficient to disqualify firm from
the competition). Under the circumstances here, the protester's
contentions amount to no more than bare speculation that BAH had
unequal access to competitively useful information, and as such
provides no basis to find that BAH had a conflict of interest.
See Mechanical Equip. Co., Inc., et al., B-292789.2 et al., Dec.
15, 2003, 2004 CPD para. 192 at 29.
We also do not find unreasonable the agency's determination that
BAH, in its performance of its DHRA task order, was not
improperly exposed to CACI proprietary or confidential
information. We first note that certain of the information CACI
asserts or suggestimplies was improperly disclosed was either
information that in fact was not disclosed to BAH, such as the
information referred to in the statement of the CACI engineer,
or was information to which the agency had "unlimited data
rights," and thus was "permitted to disclose" to third parties.
See AR, Tab 56, TEBC/DPRIS PM OCI Memorandum, at 9, 13. With
regard to the other information referenced by CACI, and provided
to the agency as attachments, we find reasonable the agency's
position that "it was incumbent upon CACI, to control its own
information and CACI cannot now claim information as non-public
or proprietary that it freely disclosed to BAH during
performance of the contract." Id. at 19. In this regard, our
Office has stated that, as a general rule, proprietary
information is that which is so marked or otherwise submitted in
confidence to the government. Snell Enters., Inc., B‑290113,
B‑290113.2, June 10, 2002, 2002 CPD para. 115 at 6; Interior
Sys., Inc., B-271469, July 23, 1996, 96‑2 CPD para. 34 at 2. In
this regard, FAR sect. 9.505‑4(a) specifically provides:
When a contactor requires proprietary information from others
to perform a Government contract and can use the leverage of
the contract to obtain it, the contractor may gain an unfair
competitive advantage unless restrictions are imposed. These
restrictions protect the information and encourage companies
to provide it when necessary for contract performance. They
are not intended to protect information—
(1) Furnished voluntarily without limitations in its use; or
(2) Available to the Government or contractor from other
sources without restriction.
Here, the record reflects that the information now claimed by
CACI as proprietary was "furnished voluntarily without
limitations on its use." That is, the record reflects that the
information was not marked as proprietary, nor was it submitted
in confidence to the government or BAH. Specifically, CACI has
not pointed to any information that was marked or otherwise
identified as proprietary or confidential in either its
statements furnished to the agency in August 2010, or its
submissions to our Office during this protest. Moreover, we have
no reason to disagree with the agency's conclusion that none of
CACI's proprietary or non-public information was ever disclosed
to BAH by agency personnel. Nor does the record reasonably show
that CACI was somehow misled by BAH or government personnel into
believing that BAH would not compete for future DPRIS work, or
that the information being freely shared would be treated as
proprietary or confidential.
In sum, we find reasonable the agency's determination that BAH
did not have OCIs that precluded award under this RFP. (CACI,
Inc.-Federal, B-403064.2, January 28, 2011) (pdf)
Ellwood asserts
that, at a minimum, M&T has a potential unfair access to
information OCI by virtue of its relationship with CTS and, more
specifically, with Ellwood's former employee. Ellwood reiterates
its position that this individual had access to its non-public
information relating to the fabrication of HP-9-4-20M steel, and
that the information would be competitively useful in the
qualification process for the BLU-113 casings. Ellwod concludes
that, because the individual assisted M&T both in the
qualification process and in preparing its proposal, this
establishes a prima facie case that M&T suffers from a potential
OCI.
Ellwood's assertions are without merit. While Ellwood's argument
is based principally on the fact that Ellwood's proprietary
information was available to its former employee in his role as
a subcontractor under a SETA contract relating to the MOP
program (during which time he observed Ellwood's manufacturing
activities and was privy to Ellwood's non-public information),
Ellwood has not explained what information was gained during
that activity that was in any way new or different from the
information the individual already possessed through his
employment and consultant relationships with Ellwood. In this
regard, where information is obtained by one firm directly from
another firm--by, for example, dissemination of information by
former employees--this essentially amounts to a dispute between
private parties that we will not consider absent evidence of
government involvement. LLH & Assocs., LLC, B-297804, Mar. 6,
2006, 2006 CPD para. 52 at 5.
Ellwood's protest supports the proposition that its former
employee already possessed the information in question, stating
as follows:
Massive Ordnance Penetrator is a technology demonstration
program funded by DTRA to develop a large conventional
penetrating weapon that will defeat hard and deeply buried
targets using high-strength alloy steel casings nearly
identical to those ENF [Ellwood] produces for the BLU-113
program. See FedBizOps Website, www.fbo.gov (search
"Solicitation No. 678ARSS8JUN09"). The fundamental difference
between the casings is their respective sizes. The MOP is a
30,000-pound weapon designed to be carried onboard B-2 and
B-52 bombers while the BLU-113 is a 5,000-pound weapon carried
on most strike aircraft.
* * * * *
The [MOP] casing is comprised of the same HP-9-4-20M alloy
steel used to construct the BLU-113 casings. Proprietary
information and know-how regarding manufacture of the MOP,
therefore, is directly applicable to manufacture of the
BLU-113 and to any other penetrators made of HP-9-4-20M
material.
* * * * *
[The individual], in all three of his prior capacities: (1) as
a senior manager for ENF's [Ellwood's] predecessor, NFC
[National Forge Company]; (2) as a consultant to ENF; and (3)
as a SETA contractor to DTRA under the MOP program, [has] had
access to and observed ENF's confidential and proprietary
techniques used in the production of HP-9-4-20M material and
the associated weapons casings.
Ellwood Letter of Protest, July 19, 2010, at 5-6. Ellwood has
neither alleged nor demonstrated that information necessary to
manufacture HP-9-4-20M steel for the MOP is in any way different
from information necessary to manufacture HP-9-4-20M steel for
the BLU-113; in fact, it alleges that the information is the
same. This being the case, Ellwood's allegation amounts to no
more than an assertion that information the individual acquired
as an Ellwood employee and consultant was improperly shared with
M&T. This is not an OCI scenario; rather, it amounts to an
alleged violation of an agreement between private parties that
we will not consider. LLH & Assocs., LLC, supra. Stated
differently, where an individual obtains non-public,
competitively useful information in connection with a private
employment or consulting agreement, an allegation that the
information subsequently was shared with a competitor is a
dispute between private parties, and does not give rise to an
OCI, notwithstanding that the individual also subsequently may
have had access to the same information through performance of a
government contract.
In any case, as outlined above, the contracting officer
conducted an extensive investigation into any potential OCI.
This effort was sufficient to provide the agency with the
information necessary to reach a reasonable judgment as to the
potential OCI, and thus there is no basis for us to question the
contracting officer's determination that there was no need to
exclude M&T from competing for the requirement, because any OCI
had been mitigated or neutralized. CIGNA Govt. Servs., LLC,
B‑401068.4, B-401068.5, Sept. 9, 2010, 2010 CPD para. __ at
12-13 (where record shows that contracting officer thoroughly
considered all facts and circumstances surrounding alleged OCI
and sought the advice of counsel and technical experts, we will
not substitute our judgment for that of the contracting officer
absent clear evidence that the agency's determination was
unreasonable). (Ellwood
National Forge Company, B-402089.3, October 22, 2010)
(pdf)
CIGNA first
protests that Palmetto's performance under the HIGLAS transition
and training support contracts created "[u]nfair, [u]nmitigated,
and [u]nallowable" OCIs which the contracting officer failed to
reasonably recognize. CIGNA's Fourth Protest, June 1, 2009, at
30. CIGNA maintains that Palmetto's prior performance under
those contracts mandate its exclusion from this competition. Id.
at 3. We disagree.
The situations in which OCIs arise, as addressed in FAR subpart
9.5 and the decisions of our Office, can be broadly categorized
into three groups. The first group consists of situations in
which a firm has access to nonpublic information as part of its
performance of a government contract and that information
provides a competitive advantage in a later competition. FAR
sect. 9.505‑4. The second group consists of situations in which
a firm, as part of its performance of a government contract has,
in some way, set the ground rules for another contract
competition, thereby skewing the competition in its own favor.
FAR sections 9.505-1, 9.505-2. The third group consists of
situations where a firm's ability to render impartial advice to
the government would be undermined by the firm's competing
interests. FAR sections 9.505-3.
In challenging the award to Palmetto, CIGNA maintains that
Palmetto's performance of the HIGLAS contracts creates each of
the three types of OCIs discussed above, noting that the HIGLAS
system "interacts" with the MACs systems, will eventually be
used by all MAC contractors, and therefore will "impact" those
contractors. CIGNA's Post-Hearing Comments, Aug. 13, 2010, at
8-17. Among other things, CIGNA asserts that Palmetto's
activities regarding "workload splits," "workload renames," and
"workload merges" create OCIs. Id. at 13-17. In this context,
CIGNA also complains that QSSI/Palmetto is involved in updating
CMS's "internet only manual" (IOM), which provides instructions
to MACs regarding claims processing procedures. Id. at 10. CIGNA
further asserts that information Palmetto has received in
resolving transition problems encountered by other MACs, as well
as information obtained in performing the HIGLAS training
contract, create OCIs. Id. at 14-15. Accordingly, CIGNA
maintains that the contracting officer could not have reasonably
determined that performance of the HIGLAS contracts did not
create an OCI.
In responding to CIGNA's numerous protest assertions, the agency
has provided information and explanations regarding the HIGLAS
system, and the nature of the activities that are required by
the agency in transitioning to that system. For example, the
agency explains that Palmetto's activities with regard to
"splits," "renames," and "merges" reflect the fact that the
prior accounting system data was not divided by the geographical
boundaries established for the current MAC jurisdictions. Tr. at
40. Accordingly, Palmetto's activities regarding these matters
involve reorganization of data from the prior organizational
structure to a structure consistent with the MAC jurisdictional
boundaries--not a review of other MACs' claim processing
operations or procedures. Tr. at 43, 45; Declaration of Deputy
Director, Financial Management Systems Group, Aug. 2, 2010,
paras. 11, 13, 14. More specifically, the agency states that, in
performing the HIGLAS contracts, Palmetto does not "obtain
access to the contractor's systems, data, business process
documents, or any other documents pertaining to the
transitioning contractors." Declaration of Deputy Director,
Financial Management Systems Group, June 29, 2010, para. 30.
In responding to Palmetto's assertion's regarding the agency's
IOM, CMS states that, although QSSI/Palmetto have been tasked
with comparing the content of the IOM with the content of HIGLAS
training manuals and identifying areas in the IOM that could
benefit from the addition of HIGLAS-related information, QSSI/Palmetto's
input is made publicly available to all Medicare claims
processing contractors. Tr. at 393. Further, no IOM revisions
flowing from QSSI/Palmetto's activities have been implemented.
Id. at 395.
Consistent with the above, the agency further states that, in
assisting with specific problems encountered by transitioning
contractors, QSSI/Palmetto have viewed "screen prints" of
specific problem transactions. However, even with regard to such
"screen prints," the information accessed does not involve the
contractor's claims processing operations or procedures since "[t]he
only financial information that
HIGLAS is involved with is the accounting data." Declaration of
Deputy Director, Financial Management Systems Group, June 29,
2010, para. 30. Finally, with regard to the performance of the
HIGLAS training services contract, the agency states that
Palmetto does not have access to actual "production data" or
"contractor-specific data," but rather relies on "dummy data";
that is, data used to simulate how the modules operate and the
system works. Tr. at 44.
The responsibility for determining whether a conflict exists
rests with the procuring agency. Aetna Gov't Health Plans, Inc.;
Foundation Health Fed. Servs., Inc., B‑254397.15 et al., July
27, 1995, 95-2 CPD para.129 at 12. In making this determination,
the FAR expressly directs contracting officers to examine the
particular facts associated with each situation, paying
consideration to the nature of the contracts involved, and
further directs contracting officers to obtain the advice of
counsel and appropriate technical specialists before exercising
their own sound discretion in determining whether an OCI exists.
FAR sections 9.504, 9.505. In reviewing bid protests that
challenge an agency's conflicts determinations, the Court of
Appeals for the Federal Circuit has mandated application of the
"arbitrary and capricious" standard established pursuant to the
Administrative Procedures Act (APA). See Axiom Res. Mgmt, Inc.
v. United States, 564 F.3d 1374, 1381 (Fed. Cir. 2009). In
Axiom, the Court of Appeals noted that "the FAR recognizes that
the identification of OCIs, and the evaluation of mitigation
proposals are fact-specific inquiries that require the exercise
of considerable discretion." Id. The standard of review employed
by this Office in reviewing a contracting officer's OCI
determination mirrors the standard required by Axiom. In this
regard, where an agency has given meaningful consideration to
whether an OCI exists, we will not substitute our judgment for
the agency's, absent clear evidence that the agency's conclusion
is unreasonable. See, e.g., MASAI Tech. Corp., B-298880.3,
B-298880.4, Sept. 10, 2007, 2007 CPD para. 179 at 8; Business
Consulting Assocs., B‑299758.2, Aug. 1, 2007, 2007 CPD para. 134
at 9-10; Overlook Sys. Techs., Inc., B‑298099.4, B‑298099.5,
Nov. 28, 2006, 2006 CPD para. 185 at 10-18; Alion Sci. & Tech.
Corp., B‑297022.4, B‑297022.5, Sept. 26, 2006, 2006 CPD para.
146 at 5-8.
Here, based on our review of the entire record, we cannot
conclude that the contracting officer unreasonably determined
that Palmetto's performance of the HIGLAS contracts does not
create an OCI. That is, the record shows that the contracting
officer followed the FAR direction to consider the particular
facts involved, including the nature of the contracts at issue,
and to obtain the advice of counsel and the assistance of
technical specialists before exercising her sound discretion.
While we agree that the matters presented raise legitimate
concerns regarding Palmetto's involvement in activities that
relate to the performance of the MAC contracts, CIGNA has failed
to persuasively explain how any of Palmetto's activities or
access to information pursuant to performance of the HIGLAS
contracts provided Palmetto a competitive advantage in competing
for the jurisdiction 11 MAC contract. Based on our consideration
of the record presented, including the testimony and
declarations of the various agency personnel associated with,
and knowledgeable of, the matters at issue, we cannot conclude
that the contracting officer's decision reflected an abuse of
her discretion. CIGNA's protests to the contrary are denied.
(CIGNA Government Services, LLC,
B-401068.4, B-401068.5, September 9, 2010) (pdf)
In implementing
the corrective action, the agency issued requests to both
offerors for additional information concerning their performance
under current and recent IC [intelligence community] contracts
and followed up with clarification requests. After reviewing
these responses, the contracting officer conducted interviews
with government personnel responsible for administering the
prior contracts in order to arrive at an assessment of OCI risk.
Based on his review, the contracting officer concluded that MCR
had a medium risk OCI under 2 of 7 contracts and that Scitor had
a medium risk OCI in 2 of 16. Thereafter, the SSA prepared a
seven-page waiver request, which she forwarded to CIA's Chief of
Acquisition Services (the official authorized to grant an OCI
waiver). The request included a description of the OCI concern
and potential effect if not avoided, neutralized, or mitigated,
and the government's interest in using the offerors
notwithstanding the OCI concerns. Waiver Request at 1-3, 5-6.
The SSA explained that Scitor's and MCR's roles under existing
and past contracts presented conflicting interests that
theoretically might bias their judgment in performing the RFP
work. Id. at 2. The agency's market research indicated that the
pool of properly cleared cost estimators with sufficient
experience was narrow and that, if MCR and Scitor were precluded
from competing, it was "highly doubtful" that cleared personnel
could be located who did not also have comparable OCI issues.
Id. at 5. Given the limited number of cleared estimators and the
lack of competition that would result from eliminating Scitor
from the procurement, the SSA reasoned that, even if MCR were
deemed not to have an OCI similar to Scitor's, it was in the
government's interest to acquire the services competitively in
order to obtain the best value, and that waiver of the OCIs
therefore was justified. Id. at 5, 7. Accordingly, the
designated official approved the waiver.
(sections
deleted)
MCR asserts that
it was unreasonable for CIA to waive Scitor's OCI for a number
of reasons. For example, it maintains that the agency
unreasonably considered the offerors' OCIs as equivalent because
MCR's OCI allegedly could be easily mitigated, while Scitor's
could not be mitigated at all; that the agency's waiver was
inconsistent with CIA's earlier guidance on which OCIs precluded
an offeror's participation; and that the waiver lacked a
sufficient basis. We have considered all of MCR's assertions and
find that none has merit.
Under the Federal Acquisition Regulation (FAR) subpart 9.5, when
the facts of a procurement raise a concern that a potential
awardee might have an OCI, the agency must determine whether an
actual or apparent OCI will arise, and whether the firm should
be excluded from the competition. The specific responsibility to
avoid, neutralize or mitigate a potential significant conflict
of interest lies with the cognizant contracting officer.
Overlook Sys. Techs., Inc., B-298099.4, B-298099.5, Nov. 28,
2006, 2006 CPD para. 185 at 10-11; see FAR sect. 9.504. As an
alternative, the agency head or a designee may waive any general
rule or procedure of [FAR subpart 9.5] by determining that its
application in a particular situation would not be in the
Government's interest. Any request for waiver must be in
writing, shall set forth the extent of the conflict, and
requires approval by the agency head or a designee.
FAR sect. 9.504. Where a procurement decision--such as whether
an OCI should be waived--is committed by statute or regulation
to the discretion of agency officials, our Office will not make
an independent determination of the matter. Knights' Piping,
Inc.; World Wide Marine & Indus. Servs., B-280398.2, B-280398.3,
Oct. 9, 1998, 98-2 CPD para. 91 at 6.
Here, as outlined above, the SSA made a written request for a
waiver from CIA's Chief of Acquisition Services, describing the
OCI concern with both offerors; the potential effect if not
avoided, neutralized, or mitigated; and, the government's
interest in allowing the offerors to compete for the award
notwithstanding the OCI concerns. After reviewing the request,
the designated official approved the waiver. On this record, we
find that CIA has met the requirements of FAR sect. 9.504; MCR's
assertions to the contrary provide no basis to object to that
waiver. See Knights' Piping, Inc.; World Wide Marine & Indus.
Servs., supra. (MCR Federal,
LLC, B-401954.2, August 17, 2010) (pdf)
The protester
maintains that Boeing had an impermissible "unequal access to
information"-type OCI by virtue of the information provided to
it by ITT at the October 22 meeting regarding the SRWNM 1.0+
software product. It notes, in this regard, that not all
offerors had access to the information, and that Boeing had an
opportunity to amend its proposal after the meeting. As a
result, ITT concludes that Boeing should be excluded from the
competition because of its OCI.
We find no impermissible OCI. Contracting officials must avoid,
neutralize or mitigate potential significant OCIs so as to
prevent an unfair competitive advantage or the existence of
conflicting roles that might impair a contractor's objectivity.
Federal Acquisition Regulation (FAR) sections 9.504(a), 9.505.
The situations in which OCIs arise, as addressed in FAR subpart
9.5 and the decisions of our Office, fall under three broad
categories: unequal access to information, biased ground rules,
and impaired objectivity. Aetna Gov't Health Plans, Inc.;
Foundation Health Fed. Servs., Inc., B-254397.15 et al., July
27, 1995, 95-2 CPD para. 129 at 11-12.
As relevant here, an unequal access to information OCI exists
where a firm has access to nonpublic information as part of its
performance of a government contract and where that information
may provide the firm a competitive advantage in a later
competition. FAR sections 9.505(b), 9.505-4; Maden Techs.,
B-298543.2, Oct. 30, 2006, 2006 CPD para. 167 at 8; see also
McCarthy/Hunt, JV, B‑402229.2, Feb. 16, 2010, 2010 CPD para. 68
at 5. As the FAR makes clear, the concern regarding this
category of OCI is that a firm may gain a competitive advantage
based on its possession of "[p]roprietary information that was
obtained from a Government official without proper
authorization," or "[s]ource selection information . . . that is
relevant to the contract but is not available to all
competitors, and such information would assist that contractor
in obtaining the contract." FAR sect. 9.505(b).
At the heart of ITT's allegation is the notion that, because the
SRWNM 1.0+ software is ITT's product, ITT should have enjoyed
exclusive use of information relating to the software when
preparing its proposal. In other words, ITT is complaining, not
that Boeing had unequal access to information, but that ITT lost
an informational advantage to which it believes it was entitled.
This situation does not establish the elements of an unequal
access OCI. First, an unequal access to information OCI can only
be established where a protester shows that the awardee had
information that it did not possess. Where the protester has the
information in question and the awardee also has the same
information, the awardee cannot be said to have "unequal access
to information," and, correspondingly, the protester cannot be
said to have been prejudiced, since both it and the awardee had
access to the same information.
More fundamentally, all of the software to be integrated under
the RFP--ITT's SRWNM 1.0R and SRWNM 1.0+, as well as Boeing's
JWNM software product--was developed and provided to the
government with a government purpose rights (GPR) license.
Agency Supp. Report, Second Decl. of Agency's Deputy Project
Manager, attach.; Intervenor's Supp. Comments, July 2, 2010,
attach. D. Accordingly, and as conclusively demonstrated by the
fact that ITT was contractually required to provide the
information to Boeing at the TIM, the record establishes that
the agency had a legal right to use the information by virtue of
its GPR license. It follows that the implicit, underlying
premise of ITT's argument--that it was entitled to the unequal
advantage afforded by possession of the information because it
had an exclusive, proprietary right to the information--is
unsupported by the record. We therefore conclude that the fact
that Boeing was provided with the information did not create an
"unequal access" OCI vis-a-vis ITT, and also does not support
the finding of any other procurement impropriety. (ITT
Corporation-Electronic Systems, B-402808, August 6, 2010)
(pdf)
More generally,
SES's various protest submissions alternatively assert that,
even if the solicitation did not create a per se prohibition on
Edaptive's reliance on BCSSI as a subcontractor, the agency
failed to adequately consider the potential for impaired
objectivity conflicts flowing from the specific facts presented
here.
The responsibility for determining whether a conflict of
interest will arise, and to what extent a firm should be
excluded from the competition, rests with the contracting
agency. Aetna Gov't Health Plans, Inc.; Foundation Health Fed.
Servs., Inc., B‑254397.15 et al., July 27, 1995, 95-2 CPD
para.129 at 12. Because conflicts may arise in various factual
situations, including those not directly addressed in the
Federal Acquisition Regulation (FAR), that regulation directs
contracting officers to examine each situation individually in
assessing whether conflicts exist. FAR sect. 9.505. Provided an
agency gives meaningful and thorough consideration to potential
conflicts, our Office will not overturn a determination based on
such consideration absent a showing that it is unreasonable.
Aetna Gov't Health Plans, Inc.; Foundation Health Fed. Servs.,
Inc., supra.
In response to SES's assertions that the agency failed to
reasonably consider whether Edaptive's particular proposed use
of BCSSI as a subcontractor created impaired objectivity
conflicts of interest, this Office sought additional information
from the agency regarding the basis for its determination.
Specifically, following submission of the agency report, this
Office conducted a recorded telephone hearing during which
testimony was provided by the contracting officer regarding the
basis for determining that Edaptive's proposal of BCSSI as a
subcontractor did not create a conflict, as well as for the
agency's issuance of solicitation amendment Nos. 2 and 3;
thereafter, the agency submitted declarations from the agency's
technical evaluation panel chair and deputy director of its
information systems group further explaining the agency's
actions. Based on our review of the entire record, we do not
question the reasonableness of the agency's determination
regarding conflicts.
Specifically, as discussed above, the agency first determined
that conflict of interest concerns precluded any contractor that
performed under phase 1 (during which the program requirements
are identified) from performing in any capacity under phase 4
(during which a system will be designed/developed to meet the
requirements identified in phase 1). Given the required
separation between identification of the requirements and
design/development of a system, the agency concluded that the
objectivity of a contractor in performing the phase 2 tasks,
including testing, operating and maintaining the system as
developed by the independent phase 4 contractor, was not
threatened by the phase 2 contractor's involvement in the phase
1 identification of requirements. That is, the agency considered
the phase 4 contract to, in effect, create a "buffer" between
performance of the phase 1 and phase 2 contract requirements.
In supporting its conclusions regarding this matter, the agency
has provided a comprehensive analysis of the various tasks
contemplated under the phase 1 and phase 2 contracts. Agency's
Post-Hearing Comments; Declaration of CMS Technical Panel Chair;
Declaration of Deputy Director of CMS Information Systems Group.
The agency's analysis discusses the various activities
contemplated under each contract, and provides the agency's
narrative assessment regarding its bases for concluding that no
conflict of interest is created. Although protester's various
submissions express disagreement with the agency's analysis and
conclusions, that disagreement fails to demonstrate that such
conclusions are unreasonable or provide this Office with a basis
to question the agency's judgments. Accordingly, SES's protest
that award to Edaptive was improper due to an alleged conflict
of interest is without merit. (Software
Engineering Services, Inc., B-401645, October 23, 2009) (pdf)
ARTEL argues that
the award to Intelsat was tainted by an OCI arising from the
awardee's knowledge of the other offerors' costs for certain
satellite resources. In this regard, ARTEL contends that
Intelsat controls certain satellites that are necessary for
performance of the CBSP contract requirements. The protester
argues that, by virtue of controlling these satellites, Intelsat
knew ARTEL's costs for their use, which created an unequal
access to information OCI. The protester also argues that
Intelsat did not negotiate fairly with ARTEL, and did not allow
ARTEL to purchase services in a manner that the protester
contends is consistent with industry practice. We conclude that
these allegations, even if true, would not constitute an OCI.
Contracting officials must avoid, neutralize or mitigate
potential significant OCIs so as to prevent unfair competitive
advantage or the existence of conflicting roles that might
impair a contractor's objectivity. FAR sections 9.504(a), 9.505.
The situations in which OCIs arise, as addressed in FAR subpart
9.5 and the decisions of our Office, can be broadly categorized
into three categories: unequal access to information, biased
ground rules, and impaired objectivity. Aetna Gov't Health
Plans, Inc.; Foundation Health Fed. Servs., Inc., B-254397.15 et
al., July 27, 1995, 95-2 CPD para. 129 at 11-12.
As relevant here, an unequal access to information OCI exists
where a firm has access to nonpublic information as part of its
performance of a government contract and where that information
may provide the firm a competitive advantage in a later
competition for a government contract. FAR sections 9.505(b),
9.505-4; Maden Techs., B-298543.2, Oct. 30, 2006, 2006 CPD para.
167 at 8; see also McCarthy/Hunt, JV, B‑402229.2, Feb. 16, 2010,
2010 CPD para. 68 at 5 (protest sustained where awardee's
subcontract had access to nonpublic information through its
performance of a government contract). As the FAR makes clear,
the concern regarding this category of OCI is that a firm may
gain a competitive advantage based on its possession of "[p]roprietary
information that was obtained from a Government official without
proper authorization," or "[s]ource selection information . . .
that is relevant to the contract but is not available to all
competitors, and such information would assist that contractor
in obtaining the contract." FAR sect. 9.505(b).
Here, ARTEL does not allege that Intelsat obtained any nonpublic
information through the performance of a government contract.
Instead, the protester complains that the awardee had access to
certain cost information arising from ARTEL's negotiations with
Intelsat for the use of satellite resources that were under
Intelsat's exclusive control. We conclude that these types of
negotiations between competitors do not give rise to an OCI,
within the meaning of FAR part 9.5. (CapRock
Government Solutions, Inc.; ARTEL, Inc.; Segovia, Inc.,
B-402490; B-402490.2; B-402490.3; B-402490.4; B-402490.5, May
11, 2010) (pdf)
Unequal Access
to Information
The protester asserts that the agency unreasonably concluded
that Turner/Ellerbe did not have an unequal access to
information organizational conflict of interest or properly
mitigated it.
In order to ensure that the agency has acted in a manner
consistent with the FAR, contracting officers are required to
give meaningful, deliberate consideration to information that
may shed light on potential organizational conflicts of
interest. Toward that end, agencies must not limit their
consideration only to information that may have been furnished
by a firm. The Analysis Group, LLC, B-401726, B-401726.2, Nov.
13, 2009, 2009 CPD para. 237 at 5. Where a prospective
contractor faces a potential unequal access to information
organizational conflict of interest, the conflict may be
mitigated through the implementation of an effective mitigation
plan. Axiom Res. Mgmt., Inc., B‑298870.3, B‑298870.4, July 12,
2007, 2007 CPD para. 117 at 8-9. An agency’s reliance on a
contractor’s self-assessment of whether an organizational
conflict of interest exists or a contractor’s unilateral efforts
to implement a mitigation plan, however, is inconsistent with
the FAR. L-3 Servs., Inc., supra at 12; Johnson Controls World
Servs., Inc., B-286714.2, Feb. 13, 2001, 2001 CPD para. 20 at 8.
In other words, an agency may not, in effect, delegate to the
contractor itself complete responsibility for identifying
potential organizational conflicts of interest, The Analysis
Group, LLC, supra, or mitigating them. Johnson Controls World
Servs., Inc., supra.
Competitively useful information giving rise to an unequal
access to information organizational conflict of interest
includes proprietary information beyond offerors’ proposals,
such as source selection information and insights into a
solicitation’s requirements. As discussed below, the record in
this protest shows that AECOM, as the design contractor, was
familiar with the details of the procurement. Access to such
information gives rise to an unequal access to information
organizational conflict of interest. See L-3 Servs., Inc., supra
at 11.
AECOM’s assistant general counsel, who advised AECOM in its
negotiations to purchase EB, states:
AECOM was required to maintain the confidentiality of all EB
proprietary information and limit its disclosure within AECOM
(and to agents of AECOM) on a “need to know” basis. Further,
the confidentiality agreement expressly prohibited AECOM and
EB from disclosing to any third party, without prior written
consent, the fact that any confidential information had been
exchanged. . . . To maintain the confidentiality of the
parties’ discussions, the project would be referred to by its
code “Project PACE” designation.
Intervenor’s Comments on the AR, Exh. 2, Decl. of AECOM
Assistant General Counsel at para. 5. This is the clearest
statement in the record of the precautions taken by AECOM to
ensure that information regarding its discussions with EB was
not widely disclosed.
AECOM’s efforts are deficient in several respects. There is no
indication as to how many employees fit the “need to know”
category, who they were, or how their need to know was
determined. The assistant general counsel estimated that
approximately 25 to 30 personnel participated in the initial due
diligence review, id. at para. 10, and approximately the same
number of personnel, and approximately the same personnel,
conducted a second review. Id. at para. 16. Five AECOM
employees, who may not be included in the approximately 25 to
30, attended a briefing hosted by EB management, id. at para. 8,
and the AECOM directors--an undetermined number of
individuals--were also aware of the negotiations. However many
AECOM employees fit the definition of “need to know,” the record
contains no evidence of an effective plan, that was disclosed to
and approved by the contracting officer and subject to
monitoring by her, to ensure that information regarding AECOM’s
plans to acquire EB was kept confidential.
With respect to the other key factual element of the analysis
here--the AECOM employees’ work on the design contract--the
record is similarly lacking with regard to evidence of a plan to
prevent disclosure to EB of competitively useful information
derived from that work. In this regard, the agency identified 49
employees who worked on the design contract and who thus may
have had access to competitively useful information. After the
protest was filed, the agency obtained and submitted
declarations from 42 of them; each declaration states that the
individual did not have any knowledge of the acquisition
negotiations and had no reason to, and made no attempt to,
improperly influence the procurement. Only one declarant
expressly stated that he did not discuss the procurement with
anyone at EB. Of the 49 employees identified by the agency,
seven did not submit any declarations. In addition, while
presumably all of the 49 used e-mail in their work assisting the
agency, there is no mention in the declarations (or evidence
elsewhere in the record) of specific efforts to limit access by
others to such email.
The agency asserts that, to the extent that AECOM had access to
competitively useful information through its work on the design
contract, that information was fully disclosed to other offerors.
Moreover, the agency argues that the open-ended nature of the
procurement prevented AECOM from being able to supply EB with
competitively useful information. In our view, it was precisely
the breadth of the discretion left to the offerors in the Phase
II competition that would have made any competitively useful,
non-public information known to AECOM valuable to EB. To
illustrate: had the competition been for an automobile, with a
particular carrying capacity, towing capacity, and performance
characteristics, there would likely have been a minimal chance
that AECOM would have competitively useful information; the
specifications, if not the precise vehicle, would be largely
established and communicated to all the offerors on an equal
basis through the solicitation. In such a situation, the range
of possible responses would be relatively limited. In this
procurement, in contrast, the requirement was to design and
build a replacement hospital of 700,000 square feet costing
several hundred million dollars. AECOM was in a position to
obtain information regarding the agency’s priorities,
preferences, and dislikes relating to this broadly defined
project. AECOM knew what the agency communicated to the offerors
about the type of facility that it preferred--as well as what
the agency did not communicate. [8] On this record, we think it
was unreasonable for the agency to assume that AECOM did not
possess competitively useful information based on its role in
the procurement.
As noted above, AECOM argues that knowledge of its negotiations
to acquire or merge with EB was limited to employees with a
“need to know,” and that they kept that information
confidential. The contemporaneous record contains no indication
that that the contracting officer relied on this information
from AECOM or even was aware of AECOM’s arrangements. In any
event, in our view it would be unreasonable for the agency to
rely on a de facto mitigation plan--namely, the assurance that
the negotiations had and would only involve AECOM employees who
would keep that information confidential--when, as discussed
above, the efforts to maintain confidentiality were largely
undisclosed to, unevaluated by, and unmonitored by the Corps--in
a word, self-executing. L-3 Servs., Inc., supra at 12. Similarly
with respect to the AECOM employees who worked on the design
contract, without credible evidence that AECOM had systems in
place to prevent the receipt of competitively useful information
by EB, there is no reasonable basis to assume that the
information was not made available to EB employees.
Biased Ground Rules
The protester argues that Turner/Ellerbe also had an unmitigated
biased ground rules organizational conflict of interest stemming
from its work on the design contract. The record suggests that
AECOM had special knowledge of the agency’s requirements that
would have enabled it to give Turner/Ellerbe an unfair advantage
in the competition. AECOM’s contract with the agency
“consist[ed] of all services necessary in the preparation of
design documents, including plans, specifications, supporting
design analysis, design narrative, cost estimates, etc. to
construct a replacement hospital.” AR, Exh. M, App. A to Design
Contract at para. 1.
The agency and the intervenor offer several defenses. The
agency’s senior project manager asserts that the Corps closely
supervised AECOM’s efforts in drafting the solicitation, AR, Tab
3, Decl. of Senior Project Manager at para. 11, and that the
offerors were given the opportunity to review and comment on the
draft requirements. The agency did solicit input from the
offerors on the draft solicitation, but the record does not
establish that the agency closely supervised AECOM in drafting
the solicitation. Moreover, even assuming that the agency
closely supervised AECOM, it is unclear why it is reasonable to
assume that the agency’s mere supervision then prevented AECOM
from using its special knowledge of the agency’s requirements to
give Turner/Ellerbe an unfair advantage in the competition.
AECOM’s contract with the agency called for it to perform “all
services necessary” for preparation of the design portion of the
procurement, and nothing in the record suggests that it did
anything less--supervised or not.
The agency asserts that there is no evidence that AECOM skewed
the competition to the benefit of EB. This is not the standard
used to resolve allegations of organizational conflicts of
interest. Where the record establishes that a conflict of
interest exists, to maintain the integrity of the procurement
process we will presume that the protester was prejudiced,
unless the record establishes the lack of prejudice. See
Marinette Marine Corp., B-400697, et al., Jan. 12, 2009, 2009
CPD para. 16 at 28. Nor is the relevant concern simply whether a
firm drafted specifications that were adopted into the
solicitation; rather, we look to see whether a firm was in a
position to affect the competition, intentionally or not, in
favor of itself. FAR sections 9.505-1, 9.505-2; L-3 Servs.,
Inc., supra at 5; Snell Enters., Inc., B‑290113, B-290113.2,
June 10, 2002, 2002 CPD para.115 at 3. In short, once an
organizational conflict of interest is established, the
protester is not required to demonstrate prejudice; rather, harm
from the conflict is presumed to occur. See The Jones/Hill Joint
Venture, B-286194.4 et al., Dec. 5, 2001, 2001 CPD para. 194 at
14; Aetna Gov’t Health Plans, Inc.; Foundation Health Fed. Servs.,
Inc., supra at 18.
The intervenor argues that at all times during the course of
solicitation development, where AECOM might have been able to
skew the competition in favor of EB, AECOM and EB were not in
fruitful negotiations, and therefore the AECOM employees
assisting the agency on this procurement would have had no
knowledge of AECOM’s interest in EB. [9] Intervenor’s Comments
at 9-15. Although the protester disputes the intervenor’s claim,
we need not resolve this issue. Turner/Ellerbe’s assertion that
limited numbers of AECOM employees were aware of the
negotiations and that they kept the negotiations confidential is
based solely on the intervenor’s post-protest representations.
As noted above, the record contains no indication of how AECOM
determined which AECOM employees had a “need to know” of the
negotiations and how their confidentiality was ensured, or that
AECOM had systems in place to wall off AECOM employees with a
“need to know” from those AECOM employees uninvolved in the
negotiations.
The agency also argues that the FAR precludes a finding that
there was a biased ground rules organizational conflict of
interest, pointing to FAR sections 9.505-2(a) and (b), which set
out certain circumstances in which contractors who prepare
specifications or statements of work may not, regardless of
mitigation, provide the product described in the specifications
or the services described in the statement of work. Both of
these exclusions are subject to limited exceptions. The
exceptions merely prevent the otherwise automatic exclusion of a
firm from the competition; they are not an indication that there
can be no organizational conflicts of interest under the facts
described in the exceptions. In fact, the overarching concern
expressed in that section of the FAR is that a firm that
prepares the specifications or work statement for a contract
should not be allowed to compete, as a prime contractor or a
subcontractor, for that contract. See FAR sect. 9.505-2. Even if
an exception applied, therefore, the contracting officer would
still need to exercise sound judgment, independently investigate
the circumstances giving rise to the possible organizational
conflict of interest, and institute and monitor appropriate
measures to mitigate or avoid the organizational conflicts of
interest. See FAR sect. 9.505.
Based on the record here, we think that the agency lacked a
reasonable basis for its conclusion that AECOM’s assistance to
the agency did not place it in a position to skew the
competition, intentionally or not, in favor of EB, with whom it
was in negotiations over the course of the competition, or that
the conflict somehow was properly addressed. We therefore
sustain the allegation that Turner/Ellerbe had a biased ground
rules organizational conflict of interest. (B.L.
Harbert-Brasfield & Gorrie, JV, B-402229, February 16, 2010)
(pdf)
Unfair
Competitive Advantage
The crux of DTB’s complaint is that the RFP provides Valdez with
an unfair competitive advantage, and that this advantage will
arise particularly in the area of pricing. Specifically, DTB
contends that the performance of the RFP’s task orders will
require the use of KC-135 teardown procedures, called
“protocols,” which were developed by Valdez under its existing
task orders. DTB suggests that Valdez, by virtue of its
development of the protocols, may have an unfair price advantage
since only Valdez has “intimate” knowledge of the cost of using
the protocols to perform the KC-135 teardown and analysis work.
The Air Force explains that, when it initiated the KC-135
Teardown and Analysis Program, it knew that various contractors
and other entities would be involved and wanted to prevent the
compartmentalization of knowledge about these processes in one
single person or organization/company. To this end, CAStLE
focused on creating three items -- the protocols themselves,
Teardown Analysis Program Subject Identification Documents (TAPSID),
and a Teardown Data Management System. CO’s Statement at 8-9.
The protocols and TAPSID were contract deliverables under
Valdez’s existing task orders.
Specifically, Valdez developed eight protocols. These protocols
document the procedures and standards to be followed for each
primary element of the teardown program, and represent best
practices and lessons learned from prior teardown programs. The
TAPSID is the data package for the program. CO’s Statement at 9;
Agency Report (AR), Tabs 26 and 27 (the Protocols and TAPSID,
respectively). After the protocols were drafted, each protocol
was reviewed and approved by the program’s oversight
committee--comprised of experts from the Air Force and other
government agencies--and the protocols were validated and
modified by the government as required. AR, Tab 26, Protocol
Documents, C/KC-135 Aircraft Teardown Plan and Objectives at 4
and Protocol 2, Teardown Section/Part Identification and
Tracking, at iii. To neutralize the appearance of an OCI with
respect to Valdez, the protocols and the TAPSID information were
made available to potential offerors. CO’s Statement at 10; AR,
Tab 14, D&F OCI, at 2-5.
The Air Force contends that Valdez will not be afforded an
unfair price advantage because of its knowledge and use of the
protocols. Rather, the Air Force argues that the protocols are
standardized documents that level the playing field for
follow-on contracts, and that Valdez lost any competitive
advantage it had when its knowledge of the process was
documented in the protocols and provided to industry. We agree.
Moreover, the Air Force explains, and we agree, that the work
required by the RFP’s task orders is not, as DTB asserts,
identical to that performed by Valdez. Instead, the magnitude of
effort required by the RFP’s task orders is significantly
greater than prior efforts, and will require considerably more
nondestructive inspection and failure analysis tasks. In this
regard, the prior effort involved some 250 sections of the
airframe compared to up to 800 sections here, and sections with
different types of damage. In addition, the contractor will be
required to perform teardown and analysis activities on teardown
sections not included under the existing contract, involving
different airframes with differing structural complexities. CO’s
Statement at 36-39.
DTB’s assertion--that “possible” differences in the work is
“irrelevant”--does not provide a sufficient basis for our Office
to disagree with the agency’s position that Valdez is not
afforded an unfair price advantage by virtue of its development
and use of the protocols. Any unfair competitive advantage
Valdez might have gained through its development of the
protocols should be minimal given their general release to
prospective offerors. See Foley Co., B-203408, Sept. 14, 1993,
93-2 CPD para. 165 at 3 (bidder does not have an unfair
competitive advantage where the bidder does not possess
competitively useful information not available to other
bidders). In addition, an agency is not required to compensate
for every competitive advantage gleaned by a potential offeror’s
prior performance of a particular requirement. For example, an
incumbent contractor’s acquired technical expertise and
functional knowledge of the costs related to a requirement’s
complexity are not generally considered to constitute unfair
advantages the procuring agency must eliminate. Snell Enters.,
Inc., B-290113, B‑290113.2, June 10, 2002, 2002 CPD para. 115 at
7. (Dayton T. Brown, Inc.,
B-402256, February 24, 2010) (pdf)
C2C and TrustSolutions
argue that CMS's decision to reengage AdvanceMed regarding its
proposed OCI mitigation plan, and thereby allow AdvanceMed an
opportunity to revise the plan, is improper because it is
inconsistent with our recommendation in C2C Solutions, Inc.,
supra; it is contrary to FAR sect. 9.504(e), which, according to
the protesters, allows an agency to provide only an "apparent
awardee" with "a" (meaning one) reasonable opportunity to
respond to an agency's OCI concerns; and because allowing
AdvanceMed a further opportunity to address its mitigation plan
constitutes unequal discussions with only AdvanceMed.[2] Both
firms also challenge CMS's corrective action on the ground that
CMS has failed to "fully implement" our recommendation within 60
days, as contemplated by 31 U.S.C. sect. 3554(b)(3).
As a general matter, the details of implementing our
recommendations for corrective action are within the sound
discretion and judgment of the contracting agency. See, e.g.,
Partnership for Response and Recovery, B-298443.4, Dec. 18,
2006, 2007 CPD para. 3 at 3; NavCom Defense Elec., Inc.,
B-276163.3, Oct. 31, 1997, 97-2 CPD para. 126 at 2. In this
regard, where an agency's corrective action extends beyond that
which may be specifically called for in our recommendation, the
agency's decision to pursue such a course of action does not, by
itself, provide a basis for protest absent some showing that the
agency's proposed corrective action is contrary to procurement
law or regulation, or is otherwise improper. See, e.g., NavCom
Defense Elec., Inc., supra, at 3 (agency reasonably decided to
open discussions with offerors and obtain revised proposals
without amending RFP notwithstanding the fact that we
recommended reopening discussions only if RFP needed to be
amended).
Given CMS's inherent discretion to craft and implement what it
reasonably believes to be appropriate corrective action, the
extent to which CMS's proposed corrective action may be
characterized as broader than, or inconsistent with, our
recommendation is not the relevant inquiry. Rather, the
pertinent question is whether the corrective action proposed by
CMS is, as the protesters have alleged, contrary to FAR sect.
9.504(e) or constitutes improper discussions. We conclude that
the protester's arguments are without merit on both counts.
Under FAR sect. 9.504(e), when an agency concludes that an
apparently successful offeror is ineligible for award based on a
conflict of interest, the agency is required to notify the firm
and allow it "a reasonable opportunity to respond" to the
agency's concerns. Here, the protesters argue that it is
inconsistent with FAR sect. 9.504(e) for CMS to give AdvanceMed
an additional opportunity to address the agency's concerns
regarding its OCI mitigation plan. The protesters maintain that
FAR sect. 9.504(e) only contemplates affording AdvanceMed a
single opportunity to respond to the agency's OCI concerns, and
"does not allude to a series of reengagements that last until a
contractor finally stumbles across the correct measure." C2C
Protest at 6. In support of their position, the protesters point
to the use of the indefinite article "a" in FAR sect. 9.504(e)
("a reasonable opportunity"). C2C Protest at 6. In addition, C2C
argues that, by its terms, FAR sect. 9.504(e) does not apply
because it only speaks to providing the "apparent" awardee with
an opportunity to address the agency's OCI concerns, and
AdvanceMed is an "actual" awardee at this juncture.
In our view, CMS is not precluded from reengaging AdvanceMed
regarding its OCI mitigation plan based on the use of the
indefinite article "a" in FAR sect. 9.504(e). FAR sect. 9.504(e)
merely establishes an agency's minimum duty to provide an
offeror with an opportunity to respond to an agency's OCI
concerns where, but for the OCI concerns, the offeror would
receive an award. There is no indication in the language of the
provision that, by establishing this minimum duty, FAR sect.
9.504(e) otherwise limits an agency's reasonable exercise of its
discretion to provide an offeror with additional opportunities
to address the agency's OCI concerns. (C2C
Solutions, Inc.; TrustSolutions, B-401106.6; B-401106.7,
LLC, June 21, 2010) (pdf) (See below for C2C
Solutions, Inc., B-401106.5, January 25, 2010)
---------------------
C2C asserts that
CMS acted unreasonably in concluding that the amended mitigation
strategy presented in the letter from CSC was acceptable. We
agree.
Contracting officers are required to identify potential
conflicts of interest as early in the acquisition process as
possible. Federal Acquisition Regulation (FAR) sections 9.505,
9.508. Situations that create potential conflicts of interest
include situations in which a firm's work under a government
contract entails evaluating itself. The concern in such
"impaired objectivity" situations is that a firm's ability to
render impartial advice to the government will be undermined by
its relationship to the product or service being evaluated.
PURVIS Sys., Inc., B‑293807.3, B‑293807.4, Aug. 16, 2004, 2004
CPD para. 177 at 7. The primary responsibility for determining
whether a conflict is likely to arise, and the resulting
appropriate action, rests with the contracting agency. FAR sect.
9.505; RMG Sys., Ltd., B‑281006, Dec. 18, 1998, 98‑2 CPD para.
153 at 4. Once an agency has given meaningful consideration to
potential conflicts of interest, our Office will not sustain a
protest challenging a determination in this area unless the
determination is unreasonable or unsupported by the record.
Alion Sci. & Tech. Corp., B‑297022.4, B-297022.5, Sept. 26,
2006, 2006 CPD para. 146 at 8.
Here, it is undisputed that AdvanceMed's proposal presents the
potential for an impaired objectivity conflict of interest where
AdvanceMed, as a ZPIC contractor, could be placed in the
position of evaluating its parent corporation, CSC, in
connection with CSC's Medicare Part D work. The contracting
officer initially determined that AdvanceMed was ineligible for
award, finding that AdvanceMed's proposed mitigation strategies
were inadequate. In making this initial determination, the
record reflects that the contracting officer exercised
deliberate care in analyzing and documenting her review of the
conflicts identified by AdvanceMed in its proposal, and the
mitigation plan proposed by AdvanceMed to address these
conflicts. Specifically, the record reflects the contracting
officer's consideration of a detailed analysis of AdvanceMed's
conflicts and proposed mitigation strategies, prepared by a CMS
compliance policy specialist, as well the contracting officer's
own conclusions and documented analysis. CO Supplemental
Statement, at 4; AR, Tab A-2, Pre-award OCI Analysis.
In contrast to the contracting officer's initial, deliberate
evaluation of the conflicts posed by award to AdvanceMed and
mitigation strategies, the record reflects a seemingly
last-minute and hasty acceptance of AdvanceMed's "amended"
mitigation strategy, which itself comprised a single sentence.
The contracting officer's immediate acceptance of this revised
mitigation approach is defective in several respects. As an
initial matter, it is readily apparent that the amended plan
lacks the necessary level of detail to reasonably assess the
viability of AdvanceMed's mitigation approach. While the plan
identified three potential approaches to mitigate the identified
conflicts, there are no details explaining how any of the plans
would work or when they would, or could, be implemented. This
lack of detail is significant given the inherently complex
nature of the proposed strategies, which could involve
divestiture of a large corporate entity. Given the plan's
inherent lack of detail, it is not surprising that the record
does not contain any analysis by CMS addressing the viability of
the various plans.
CMS attempts to justify its lack of analysis by arguing that the
work which gives rise to the conflict, the Medicare Part C and D
work, would not be ordered until some point in the
future--suggesting that AdvanceMed did not need to provide a
detailed mitigation plan for this work, notwithstanding the
identified potential conflicts. CMS's arguments in this regard,
however, are contrary to the terms of the solicitation and CMS's
contemporaneous consideration of AdvanceMed's conflicts.
Specifically, sections H and M of the RFP established that CMS
would not enter into a contract with an entity that has the
potential for an unresolved OCI. This requirement expressly
applied to the Medicare Part C and D related work where the
solicitation provided as follows:
At this time, task orders will not be awarded for Part C and
Part D. CMS may award a task order for Part C and Part D no
earlier than October 2009. Although a Part C and/or Part D
task order is not being awarded at this time, Offerors are
required to propose on the [statement of work] requirements
for Part C and D as outlined in Section M. Offerors will be
required to provide an acceptable Conflict of Interest
mitigation strategy to CMS . . . if award of Part C and/or D
is an actual or perceived Conflict of Interest.
RFP, at 78, 90.
Moreover, Medicare Part C and D services were an integral part
of the agency's technical evaluation; 10 of 12 technical
approach sub-criteria involved capability to perform Part C and
D work. RFP, at 114-115.
Further, during evaluation of proposals, the contemporaneous
documentation reflects the contracting officer's recognition of
the need for AdvanceMed to submit, with its proposal, an
adequate strategy to mitigate its Medicare Part D conflicts. In
fact, regarding these conflicts, the contracting officer
specifically stated, "[e]ven though Part D work is not being
awarded at this time, AdvanceMed must identify an adequate
mitigation strategy it intends to put in place to address this
Part C&D OCI." AR, Tab A-2, at 6. Significantly, AdvanceMed's
failure to provide an adequate strategy to address the Part D
conflicts resulted in the contracting officer's initial
determination that AdvanceMed was ineligible for award. Based on
this record, it is clear that AdvanceMed was required to submit,
and CMS was required to evaluate, a mitigation strategy which
CMS could reasonably conclude would resolve AdvanceMed's
Medicare Part D conflicts. As set forth above, this did not
happen.
In addition to the undefined and general nature of AdvanceMed's
amended mitigation plan, various aspects of the plan are
fundamentally problematic. Since implementation of one of the
three identified mitigation strategies is entirely at CSC's
"discretion," each of the three options must be capable of
effectively mitigating the identified conflicts.[5] It is
apparent, however, that the contracting officer has focused her
attention on the viability of only one of the three
options--divestiture. In a supplemental statement in response to
the protest, she specifically indicates a "preference" for CSC's
divestiture of AdvanceMed, notwithstanding the fact that the
terms, timing, and process for such an involved process are
entirely undefined and there is a concomitant lack of
understanding regarding the viability of such an option.
Supplemental CO Statement, at 8. Moreover, while the contracting
officer readily admits to her "concerns regarding the
feasibility of CSC using subcontracting to mitigate conflicts,"
this option "did not alarm" her because it was only one of the
three possibilities and CMS had "reserved the right to terminate
the contract." Id.
We think that the contracting officer's underlying concerns
regarding the "subcontracting" option are understandable. While
CSC indicates a general plan to "subcontract out the functions
that pose an OCI with the work of AdvanceMed," it is not
apparent how such an option would be feasible or effectively
mitigate the conflict. As a ZPIC contractor, AdvanceMed would be
responsible for identifying fraud, waste, or abuse by performing
audit-type activities. Because such work may necessarily involve
a retrospective look at the activities performed by a particular
entity, it is not apparent how CSC's post-award subcontracting
of the particular Medicare Part D work would insulate AdvanceMed
from potentially auditing Medicare Part D work previously
performed by CSC. In addition, it is not apparent how use of
subcontractors in this situation would address the fundamental
concern in connection with AdvanceMed's impaired objectivity--AdvanceMed
being placed in the position of reviewing the work of its
parent, CSC. Since CSC would ultimately remain contractually
responsible for the functions it subcontracts, AdvanceMed's
review of work performed by CSC's subcontractors could be
considered a review of CSC's contractual obligations and
responsibilities. Thus, AdvanceMed could be viewed as in the
position of evaluating CSC, notwithstanding CSC's use of an
intervening layer of subcontractors.
In addition, regarding the latter point raised by the
contracting officer--that CMS's reservation of the right to
terminate AdvanceMed's contract somehow negated the need for
AdvanceMed to submit an adequate mitigation strategy--this
argument flies in the face of the solicitation, which, as
discussed above, expressly provided that the agency would not
make award to an offeror with an unmitigated conflict.
Accordingly, we sustain the protest on the basis that CMS failed
to reasonably consider or evaluate the OCI mitigation strategy
ultimately proposed by the awardee, AdvanceMed. (C2C
Solutions, Inc., B-401106.5, January 25, 2010) (pdf)
Also see (Cahaba
Safeguard Administrators, LLC, B-401842.2, January 25,
2010.) (pdf)
FCSO protests
that the agency was required to accept its proposed “firewalled
subcontractor” approach as an acceptable mitigation plan, and
asserts that the agency’s documentation regarding the basis for
rejecting FCSO’s proposal was inadequate. We disagree.
Contracting officers are required to identify potential
conflicts of interest as early in the acquisition process as
possible, and to avoid, neutralize, or mitigate such conflicts
to prevent the existence of conflicting roles that might impair
a contractor's objectivity. In assessing potential conflicts of
interest, the FAR directs the contracting officer to examine
each contracting situation individually on the basis of its
particular facts and the nature of the proposed contract, and to
exercise common sense, good judgment, and sound discretion with
regard to whether a conflict exists and, if so, the appropriate
means for resolving it; the primary responsibility for
determining whether a conflict is likely to arise, and the
resulting appropriate action, rests with the contracting agency.
FAR sect. 9.505; Alion Sci. & Tech., B‑297022.4, B‑297022.5,
Sept. 26, 2006, 2006 CPD para. 146 at 6; RMG Sys. Ltd.,
B-281006, Dec. 18, 1998, 98-2 CPD para. 153 at 4. Once an agency
has given meaningful consideration to potential conflicts of
interest, our Office will not sustain a protest challenging a
determination in this area unless the determination is
unreasonable or unsupported by the record. Alion Sci. & Tech.,
supra.
Here, as discussed above, FCSO’s October 8, 2008 initial
proposal contemplated that FCSO would perform both the QIC and
the MAC contracts for the same area, and that “separation and
segregation of the day-to-day management and operation” of the
two contracts should be considered sufficient COI mitigation;
alternatively, FCSO’s initial proposal contemplated transferring
performance of the QIC contract to its sister corporation. In
December, the agency clearly advised FCSO that neither approach
was acceptable, and offered FCSO another opportunity to
meaningfully address the COI. In January 2009, FCSO responded,
continuing to argue for acceptance of the novation approach it
had previously proposed. Thereafter, the agency again told FCSO
that its proposed approach was unacceptable and, yet again,
offered FCSO an opportunity to meaningfully address the COI. In
seeking yet another response from FCSO, the agency specifically
reminded FCSO that its proposed mitigation plan must be
complete, comprehensive, and detailed, and that it must discuss,
“at a minimum,” the cost and technical impact created by any
proposed revisions. Notwithstanding the agency’s clear
directions, FCSO’s response‑‑which reflected material changes to
its previously-proposed approach--provided virtually none of the
specific information the agency requested.
Based on our review of this record, as discussed above and
specifically including FCSO’s various responses to the agency’s
multiple requests that FCSO meaningfully address the clear
conflict of interest, we find no merit in FCSO’s assertion that
the agency was required to accept, or that it inadequately
documented the basis for rejecting, FCSO’s “firewalled
subcontractor” approach.
The protest is denied. (First
Coast Service Options, Inc., B-401429, July 31, 2009) (pdf)
TAG asserts that
SAIC has an "impaired objectivity" OCI. In this regard, the RFQ
requires the successful firm to provide expertise to the Air
Force in a number of subject areas. For purposes of this
allegation, task number three in the statement of work is the
focus of TAG’s protest. Under that task, the successful
contractor will be required to provide a broad range of
objective advisory and assistance services, technical analysis,
and support in the area of counter-proliferation of weapons of
mass destruction, specifically, combating chemical, biological,
radiological and nuclear (C-CBRN) weapons. RFQ, Statement of
Work (SOW), at 2-31 to 2-41. According to the protester, this
poses an impaired objectivity OCI for SAIC because the firm also
sells C-CBRN-related detection and prevention products and
services. The protester maintains that SAIC will be unable to
provide objective advice in this area because any advice given
could affect sales of its products.
The agency responds that it considered whether SAIC might have
an impaired objectivity OCI and concluded that it did not. In
this connection, the record shows that the RFQ included a
requirement for all concerns to submit an OCI statement
disclosing information concerning actual or apparent OCIs. RFQ
at 11-5. The agency asserts that the contracting officer
reviewed SAIC’s information and determined that there was no
reason to conclude that SAIC had an OCI. The agency also
maintains that it intends to monitor SAIC during performance to
ensure that there are no OCIs.
Contracting officers are required to identify and evaluate
potential OCIs as early in the acquisition process as possible.
Federal Acquisition Regulation (FAR) sect. 9.504. The FAR
specifies that an OCI exists where, because of activities or
relationships with other persons or organizations, a person or
organization is unable or potentially unable to render impartial
assistance or advice to the government. See FAR sect. 2.101.
Situations that create potential OCIs are further discussed in
FAR subpart 9.5 and decisions of our Office. One type of OCI, an
impaired objectivity OCI, is created when a contractor’s
judgment and objectivity in performing contract requirements may
be impaired due to the fact that the substance of the
contractor’s performance has the potential to affect other
interests of the contractor. Alion Sci. & Tech. Corp., B-297342,
Jan. 9, 2006, 2006 CPD para. 1 at 5-6. In order to ensure that
the agency has acted in a manner consistent with these
requirements, contracting officers are required to give
meaningful, deliberate consideration to information that may
shed light on potential OCIs. Toward that end, agencies must
give consideration not only to information that may have been
furnished by a firm, but also must consider, as appropriate, the
scope of the products manufactured or services provided by the
firm or its competitors. Id. at 11. In other words, an agency
may not, in effect, delegate to the contractor itself complete
responsibility for identifying potential OCIs.
Here, the record shows that the contractor will be involved in a
full range of activities in support of the Air Force’s C-CBRN
program. Task three of the contract specifies the following
activities:
The contractor shall support and provide AF [Air Force] unique
C-CBRN operational & hazard expertise to inform and develop
AF-wide DOTMLPF [doctrine, organization, training, material,
leadership and education, personnel and facilities] counter
WMD [weapons of mass destruction] solutions and capabilities.
Support to this task area requires codifying counter WMD in AF
operational plans, policy, doctrine, guidance and procedures;
integrating and synchronizing AF efforts across the full
counter WMD spectrum; supporting and executing the CSAF [Chief
of Staff of the Air Force] C-CBRN Master Plan & Roadmaps;
providing MAJCOM [major command] support to execute C-CBRN
activities; developing and implementing C-CBRN CONOPS [concept
of operations]; institutionalizing C-CBRN into AF education,
training and exercises . . .; leveraging science and
technology (S&T) and research, development, test and
evaluation (RDT&E) to refine hazards, reduce risk and
demonstrate capabilities; incorporate counter WMD operational
concepts into AF standards into programs and budgets; and
manage AF C-CBRN operations globally. The contractor shall
support the AF/A5XP mission by assisting them in establishing
AF operational policy, strategy, CONOPS, and doctrine on
combating WMD, CP [counter-proliferation], and C-CBRN
programs.
RFQ at 2-32. In addition to the requirements for task three
detailed above, the RFQ includes specific tasks ranging from
conducting research and analysis and presenting the results of
such efforts in briefing papers and other formats (subtask 3.1),
to providing support in developing agency strategy, policy,
doctrine and concepts of operations for the C-CBRN program
(subtask 3.2). Additionally, and perhaps most significant, the
RFQ calls for the contractor to perform detailed technical
analyses that will relate directly and predictably to the
agency’s selection of C-CBRN products and services. In this
regard, subtask 3.3 specifically provides:
The contractor shall provide technical analysis addressing
issues from the point of view of ‘what does this mean to the
USAF’ on questions that arise in the C-CBRN technical domain.
The contractor shall provide technical research and
operational evaluations to assess, interpret, shape, and
advise the Air Staff and other AF organizations regarding what
tests results mean for the operator. This understanding along
with good testing and analysis underpin the AF’s policy,
doctrine, tactics, techniques and procedures (TTPs), as well
as what equipment is best to address the threat. The general
categories of analysis and quantitative assessment the
contractor shall perform include: Threat and Vulnerability
Assessments, Basic Challenge Sources, Attack Characterization,
Atmospheric Transport Dispersion Modeling, Chem-Bio Defense (CBD)
Equipment Operations, AF Operations, Risk
Assessment/Management, Hazard Modeling and Analysis, Detector
Capability Analysis, Decontamination Requirements Analysis,
Technical Design and Conduct of Laboratory and Field Testing,
which support the development and implementation of the C-CBRN
CONOPS and other supporting efforts.
RFQ at 2-36-2-37. Also specifically required under subtask 3.3
is contractor support to ensure that development and acquisition
programs are consistent with Air Force key performance
parameters (discrete standards that new equipment must meet
before the Air Force will purchase it), as well as support in
connection with the Air Force’s operational testing and
experimentation related to its analysis of C-CBRN products,
services and procedures. RFQ at 2-37-2-38.
Thus, the contractor, while not performing acquisitions directly
for the Air Force, will be engaged in a full spectrum of
activities that, it appears, will lead directly and predictably
to developing information that may be used by the Air Force to
influence acquisition decisions.
Although performing the tasks under this order raises potential
impaired objectivity OCI concerns, the record shows that the
agency did little more than require the vendors to submit
information that they felt was germane to determining whether or
not they had an OCI. The agency did nothing to independently
consider or evaluate whether SAIC had an OCI, despite that even
a cursory review of the materials provided by SAIC in its
quotation shows that the firm provides a full spectrum of C-CBRN
products and services. AR, exh. 30. Notwithstanding that SAIC
sells a full line of C-CBRN products and services, SAIC’s
quotation states elsewhere, in discussing the solicitation’s
requirement to assess C-CBRN test results, that its work
“[e]nables objective based decisions on operational
effectiveness of equipment; thereby influencing procurement and
fielding decisions.” SAIC Oral Presentation at 37. The record
therefore appears to show that SAIC will be providing precisely
the type of advice and assistance that could influence sales of
its, or a competitor’s, C-CBRN product line, but there is
nothing to show that GSA actually considered these
circumstances. The record as it relates to the agency’s
determination of whether SAIC had an OCI, consists, in its
entirety, of the following:
SAIC acknowledges there are no known real or perceived
conflicts of interest. SAIC agrees and certifies to disclose
information concerning the actual or potential conflict with
any proposal for any solicitation relating to any work in this
effort, and to handle all actual or potential OCI situations
in accordance with FAR subpart 9.5.
AR, exh. 19, at 6. While this statement addresses SAIC’s own
evaluation of whether there were any actual or apparent OCIs
resulting from SAIC’s performance of the work, there is nothing
in the record showing that GSA ever made its own independent
determination in this regard, as was required by FAR part 9.5.
That is, there is no indication that GSA considered all of the
available information in determining whether an OCI exists, or
whether any potential OCI could be avoided, mitigated or
neutralized. Rather, it appears that GSA essentially delegated
this determination to SAIC. This was improper. Alion Sci. &
Tech. Corp., supra. Accordingly, we also sustain the protest on
this ground. (The Analysis
Group, LLC, B-401726; B-401726.2, November 13, 2009) (pdf)
Contracting officials are to avoid, neutralize or mitigate
potential significant conflicts of interest so as to prevent
unfair competitive advantage or the existence of conflicting
roles that might impair a contractor's objectivity. Federal
Acquisition Regulation (FAR ) sect. 9.504(a), 9.505.
The responsibility for determining whether an actual or apparent
conflict of interest will arise, and to what extent the firm
should be excluded from the competition, rests with the
contracting agency. Aetna Gov't Health Plans, Inc.; Foundation
Health Fed. Servs., Inc., B--254397.15 et al., July 27, 1995,
95-2 CPD para. 129 at 12. Because conflicts may arise in factual
situations not expressly described in the relevant FAR sections,
the regulation advises contracting officers to examine each
situation individually and to exercise "common sense, good
judgment, and sound discretion" in assessing whether a
significant potential conflict exists and in developing an
appropriate way to resolve it. FAR sect. 9.505. We will not
overturn the agency's determination except where it is shown to
be unreasonable. Aetna Gov't Health Plans, Inc.; Foundation
Health Fed. Servs., Inc., supra.
The situations in which organizational conflicts of interest
arise, as addressed in FAR subpart 9.5 and the decisions of our
Office, can be broadly categorized into three groups. The first
group consists of situations in which a firm has access to
nonpublic information as part of its performance of a government
contract and where that information may provide the firm a
competitive advantage in a later competition for a government
contract. FAR sect. 9.505-4. In these "unequal access to
information" cases, the concern is limited to the risk of the
firm gaining a competitive advantage; there is no issue of bias.
The second group consists of situations in which a firm, as part
of its performance of a government contract, has in some sense
set the ground rules for another government contract by, for
example, writing the statement of work or the specifications. In
these "biased ground rules" cases, the primary concern is that
the firm could skew the competition, whether intentionally or
not, in favor of itself. FAR sections 9.505-1, 9.505-2. These
situations may also involve a concern that the firm, by virtue
of its special knowledge of the agency's future requirements,
would have an unfair advantage in the competition for those
requirements. Aetna Gov't Health Plans, Inc.; Foundation Health
Fed. Servs., Inc., supra at 13.
Finally, the third group comprises cases where a firm's work
under one government contract could entail its evaluating
itself, either through an assessment of performance under
another contract or an evaluation of proposals. FAR sect.
9.505-3. In these "impaired objectivity" cases, the concern is
that the firm's ability to render impartial advice to the
government could appear to be undermined by its relationship
with the entity whose work product is being evaluated. Id.; see
also FAR sect. 9.501 (definition of organizational conflict of
interest).
Allegations Arising from the SI Divisions' Roles in Both the
Procurement Planning Work and the Subsequent Procurement
All those involved took the view initially that a company that
performed procurement planning services under the task order
could not compete for the subsequent procurement. There was a
consensus among the Army and Air Force that SI [SI
International] could not participate in the Uni-Comm
procurement because of its work under the planning effort task
order, a preclusion agreed to by SI under the terms of the task
order. That view is consistent with FAR subpart 9.5 and reflects
concern that SI International (and its affiliate, SI Telecom)
would have an unfair competitive advantage in the Uni-Comm
procurement. Specifically, without the prohibition on competing
for the Uni-Comm contract, SI Engineering's advice to the
government in the planning effort under the task order could be
tainted by its corporate interest in the subsequent procurement
and the firm could obtain nonpublic, competitively useful
information. This reflects the fact that the work under the task
order entailed being part of the government's procurement
planning process and advising the government on the "business
case" for the subsequent procurement, as well as other
acquisition planning work. In terms of FAR subpart 9.5, the
reasons for barring a firm (or its affiliate) that participated
in the task order work from competing for the subsequent
procurement reflect two types of OCIs: unequal access to
information--concern that the firm could obtain (or share with
an affiliate) through the task order work nonpublic information
that would be competitively useful in the subsequent
procurement, and biased ground rules--concern that the firm
could shape the Uni-Comm procurement in a way that favors itself
or its affiliate. [Bracketed information added for
clarification.]
Here, the Air Force eventually reversed its original decision
that SI Telecom was barred from participating in the Uni-Comm
procurement due to its affiliate's role in the procurement
planning work under the task order. The gravamen of this protest
is whether the Air Force had a reasonable basis for that
reversal. We examine first the biased ground rules concerns, and
then those related to SI's access to nonpublic, competitively
useful information.
L-3 alleges that SI has a biased ground rules organizational
conflict of interest, given the way in which the effort to
produce the Uni-Comm business or mission case and other
procurement planning was intertwined with the writing of the
statement of work. That interconnectedness can be seen clearly
in the language of the Army task order, which described six
subtasks that would be performed under phase I; five of those
six subtasks were to be performed under phase Ia, and all six
would be performed under phase Ib. See AR, Tab 249A, Task Order
at 7. Performance of both portions of phase I would include,
among others, subtask 1, Program Management, Administrative, and
Quality Assurance Services, subtask 2, Communication and IT
Requirements Identification and Analysis Services, and subtask
6, Technical Advice and Program Support Services. The one
subtask reserved for performance under phase Ib was subtask 5,
Evaluation Criteria Services.
The ability of the task order contractor under phase Ia to exert
influence on both the "go/no-go" decision and the resulting
statement of work was reflected in the consensus opinion of the
cognizant Army and Air Force officials‑‑announced during the
task order planning, included in Task Order 5017, and reiterated
after issuance of the task order--that the contractor performing
phase Ia would be excluded from participation in the Uni-Comm
procurement. On January 7, 2005, prior to the issuance of the
task order, the Air Force Uni-Comm technical manager concurred
with the Army contracting officer that a firm that performed
only in phase Ia would face organizational conflicts of
interest. See AR, Tab 249C, Response to Offeror Questions at 32
("Q: Will there still be an [organizational conflict of
interest] if phase Ib is not turned on or funded? A: Yes."); AR,
Tab 249C, E-mail from AF Technical Manager to Army Contracting
Officer, Jan. 7, 2005, at 30 ("Concur with [statement of work]
and Q&As."). Consistent with this position, the task order
itself included a clause precluding SI from participation in the
Uni-Comm procurement based on the conclusion that performance of
the Uni-Comm contract would create an unmitigable organizational
conflict of interest. In sum, as agreed by the Air Force
technical manager and the Army contracting officer, and as
confirmed in the language of the task order: performance of
phase Ia of the task order would necessarily preclude a
contractor from participating in the Uni-Comm competition.
Over a year after his original organizational conflict of
interest analysis in April 2005, the Air Force contracting
officer conducted a second analysis reversing the position that
he had shared with the Army contracting officer and the Air
Force technical manager, namely, that performance of phase Ia of
the Army task order would preclude a firm from participation in
the Uni-Comm procurement. The record shows, however, that the
Air Force contracting officer's June 2006 biased ground rules
organizational conflict of interest analysis failed to
appreciate the way in which performance of phase Ia shaped the
statement of work, thus making it inappropriate for the phase Ia
contractor to participate in the Uni-Comm procurement. The Air
Force contracting officer testified that in making his
organizational conflict of interest determination he relied on
the "clean break" between phases Ia and Ib. The record shows
that the "clean break" was illusory. As noted above, the task
order contained several critical subtasks that would be
performed in both portions of phase I. Moreover, phase Ia was
funded for a particular time period, and not for completion of
particular tasks, and thus the assumption that none of the tasks
assigned to phase Ib could be performed under phase Ia is
incorrect. In this regard, the May Monthly Status Report stated
that "[b]y direction of the [Air Force technical director],
begin [in June] the development of the Uni-Comm [statement of
work] and strategy to conduct a series of Industry Days. In
accordance with the 5017 Task Order Plan, this activity was not
scheduled to begin until Phase 1b." AR, Tab 171, Monthly Task
Order Reports at 14. Similarly, the June report states, "[b]y
direction of the [Air Force technical director], began the
development of the Uni-Comm [statement of work] and strategy to
conduct a series of Industry Days. In accordance with the 5017
Task Order Plan, this activity was not scheduled to begin until
Phase 1b." Id. at 15. These reports reflect the nearly seamless
way in which the effort under phase Ia blended into the drafting
of the statement of work under phase Ib, which likewise was
reflected in the timing of the deliverables; the draft statement
of work was due only 60 days after the last site visit, with the
final statement of work due only 30 days later, unless as
otherwise directed by the Air Force. Agency Report (AR), Tab
249A, Task Order at 13. The Air Force contracting officer
testified that he did not consider these Monthly Reports when
conducting his organizational conflict of interest analysis.
Even though his analysis reversed the earlier consensus
determination that the contractor under phase Ia would be
precluded from participation in the Uni-Comm procurement, the
Air Force contracting officer's June 1, 2006 memorandum
analyzing SI's potential conflicts of interest recognized the
interrelationship between the work performed under phases Ia and
Ib on which that preclusion had been based. He stated that "some
of the information researched by the Uni-Comm team, which
included the SI International employee, was later part of the
source information used to develop the requirement." AR, Tab 172
at 17, Organizational Conflict of Interest Analysis of June 1,
2006. He discounted that finding because "SI International's
employee was not in a position, during the business/mission case
development, to draft specifications for Uni-Comm that would
favor the employee's corporation." Id.
As an initial matter, we note that the relevant concern is not
simply whether a firm drafted specifications that were adopted
into the solicitation, but, rather, whether a firm was in a
position to affect the competition, intentionally or not, in
favor of itself. FAR sections 9.505-1, 9.505-2; Snell Enters.,
Inc., B‑290113, B-290113.2, June 10, 2002, 2002 CPD para.115 at
3. While the Air Force contracting officer here relied on our
decision in American Artisan Prods., Inc., B‑292559, B‑292559.2,
Oct. 7, 2003, 2003 CPD para. 176, as support for the proposition
that SI's participation in the business/mission case development
did not give rise to a biased ground rules organizational
conflict of interest, the facts of the two cases differ in a
critical respect. We reached our conclusion in American Artisan
Prods., Inc. because the firm alleged to have the biased ground
rules organizational conflict of interest did not "perform the
type of work solicited," American Artisan Prods., Inc., supra at
9, and thus was incapable of shaping the requirement in a way
that would have been beneficial to it, as envisioned in Snell
Enters. Inc.. That is not the case here, because SI Telecom, as
part of the GDIT [General Dynamics Information Technology, Inc.]
team, will perform [deleted] percent of the contract effort.
[Bracketed information added for clarification.]
In sum, the Air Force contracting officer's determination that
there was no biased ground rules organizational conflict of
interest was based on a misconception of the work performed
under the task order and a misreading of American Artisan
Prods., Inc. Based on the record here, we think that the agency
lacked a reasonable basis for its conclusion that SI's
performance under phase Ia of the task order did not place it in
a position to skew the competition, intentionally or not, in
favor of itself, and we therefore sustain the allegation that SI
had a biased ground rules organizational conflict of interest.
L-3 also alleges that SI's performance on Task Order 5017 gave
it access to competitively useful, non-public information and
thus created an unequal access to information organizational
conflict of interest for GDIT. The awardee and the agency assert
the following: that the information was not competitively
useful; that if it was competitively useful, the information was
fully disclosed to the other offerors; that if it was not fully
disclosed to the other offerors, the mitigation plans
effectively prevented the information's disclosure; and that,
based on our decision in Mechanical Equip. Co., Inc. et al.,
B-292789.2 et al., Dec. 15, 2003, 2004 CPD para. 192, this
Office should nevertheless dismiss the organizational conflict
of interest protests. As explained below, in our view there is
no reasonable basis on which to conclude that all competitively
useful information obtained by SI was disclosed to the other
offerors, as the agency and the intervenor argue. Nor can we
conclude that the mitigation plans and non-disclosure agreement
effectively prevented an organizational conflict of interest.
The agency has yet to adequately investigate and reasonably
determine the extent and type of information to which SI had
access or the efficacy of the non-disclosure agreement and
mitigation plans, and absent the results of those inquiries, the
record contains inadequate support for a finding that SI did not
have an unequal access to information organizational conflict of
interest.
The Air Force contracting officer's own organizational conflict
of interest analysis in June 2006 stated that SI handled
competitively useful information in the form of unredacted
copies of contracts, core communications requirements, the 38
EIG information, and proprietary information of other companies
that was subject to non-disclosure agreements. On the basis of
this memorandum alone, it would be unreasonable to conclude that
SI did not access competitively useful information in the
performance of the Army task order. Moreover, while performing
the task order, SI's employee was considered a member of the
Program Management Office with access to the Department of
Defense NIPRNET and wrote site visit reports summarizing the
Program Management Office's trips to Air Force bases. Although
the Air Force contracting officer testified that he was unaware
whether the SI employee was ever unaccompanied on the site
visits conducted under the task order, Trans. at 189-90, he
never conducted any interviews with the individuals with whom
the SI employee met to determine the kinds of information to
which he had access. Id. at 186-91. Because the Air Force
contracting officer was unaware of the full extent and nature of
the SI employee's work under the task order, he could not
reasonably conclude, with any certainty, the kinds of
information that the SI employee accessed.
Although extensive hearing testimony appeared to show that much
(and potentially most) of the known competitively useful
information was made available to the other offerors, see Trans.
at 51-104, the record shows that SI nevertheless likely had
access to other competitively useful information not known to
the Air Force. As noted above, the plain language of the task
order precluded the firm performing the task order phase Ia work
from competing under the Uni-Comm solicitation; the Army and Air
Force officials who drafted and issued the Army task order
concurred with this exclusion. With that exclusion in effect,
neither the Army, nor the Air Force, nor the task order prime
contractor or SI themselves, had any reason to track the
information being accessed by SI. In this regard, the Air Force
contracting officer stated that “[s]ince I wasn't supporting
Uni-Comm from Jan 2005 to Apr or May 2005, I didn't know what
the SI employee had worked on or had access to during the time
(Jan 2005 to about 17 Jun 05) under the subcontract to prime FCI
on the [Army] Task Order." AR, Tab 172 at 143, Contracting
Officer Memorandum for Record, Dec. 19, 2005. The Air Force
contracting officer also testified that he was unaware of any
record of the information that SI reviewed. Trans. at 179. The
earliest attempts to identify what the SI employee could have
learned were made some time after the completion of phase Ia of
the task order. In sum, the record contains no contemporaneous
account of what information SI had access to, nor is there any
accurate description in the record, memorialized after-the-fact,
containing that information. Given the various ways in which SI
could have accessed information and the lack of a record showing
what it did access, we think that it follows that there was no
support for the Air Force's belief that all competitively useful
information was made public.
The agency and GDIT argue that, even if SI obtained
competitively useful, non-public information, the mitigation
plans of SI Telecom and SI Engineering, operating alone or in
tandem, prevented disclosure of that information.
The record contains two mitigation plans, one each from SI
Engineering and SI Telecom, that were submitted to the agency
unsigned and undated in July and August 2005, respectively. The
SI Engineering mitigation plan included a signed non-disclosure
agreement for the SI employee dated January, 28, 2005. Even
assuming that the non-disclosure agreement was created in
January 2005, that agreement was binding only as to the SI
employee and not as to SI Telecom or SI Engineering; neither the
SI Telecom nor the SI Engineering plan was submitted to the Air
Force until after SI's performance under the task order had
ended. Further, because the Air Force contracting officer had a
number of significant questions concerning the adequacy of SI
Telecom's plan, the final mitigation plan was not approved for
over a year, in August 2006, and it was not until then that the
agency had before it a signed plan. The issues the Air Force
contracting officer raised as requiring clarification went to
the heart of the adequacy of the plan's efficacy in addressing
the potential organizational conflicts of interest stemming from
SI's access to competitively useful information, including: who
would decide what qualified as source selection sensitive
information, and the other kinds of information that might
require protection; how SI's internal computer systems would
function to isolate the competitively useful information; how
the government would verify that the contractor followed the
mitigation plan; how the government would enforce compliance
with the mitigation plan; and given that the two divisions of SI
were no longer physically separate, how the workspace separation
of the employees would be accomplished. AR, Tab 174 at 241-43,
Memo from Contracting Officer to SI, July 6, 2006.
Where a prospective contractor faces a potential unequal access
to information organizational conflict of interest, the conflict
may be mitigated through the implementation of an effective
mitigation plan. Axiom Res. Mgmt., Inc., B‑298870.3, B‑298870.4,
July 12, 2007, 2007 CPD para. 117. An agency's reliance on a
contractor's self-assessment of whether an organizational
conflict of interest exists or a contractor's unilateral efforts
to implement a mitigation plan, however, is inconsistent with
the FAR. Johnson Controls World Servs., Inc., B-286714.2, Feb.
13, 2001, 2001 CPD para. 20 at 8. Here, in our view, it was
unreasonable for the agency to rely on a mitigation plan that
was undisclosed to, unevaluated by, and unmonitored by the Air
Force--in a word, self-executing. Without credible evidence that
an effective mitigation plan was in effect at the start of
performance, there is no basis to assume that, even if the SI
employee himself did not disclose competitively useful
information, the information was not otherwise made available to
SI Telecom employees working on the subcontract to GDIT.
Finally, citing Mechanical Equip. Co., Inc. et al., B-292789.2
et al., Dec. 15, 2003, 2004 CPD para. 192, the intervenor argues
that the Air Force contracting officer's reassessment and later
finding that there were no organizational conflicts of interest
were based on extensive consultations with cognizant Air Force
officials, such that he could reasonably rely on their knowledge
of whether there were organizational conflicts of interest. The
record simply does not support the intervenor's position. The
agency in the Mechanical Equip. Co., Inc. protest offered
testimony or statements from five agency officials involved in
the procurement, including the chair and deputy chair of the
source selection evaluation board, who had made an independent,
contemporaneous determination, based on extensive first-hand
knowledge of the firm’s involvement in the subject procurement,
that the firm did not have an organizational conflict of
interest. Here, the record contains no contemporaneous finding
by knowledgeable Air Force Uni-Comm program officials that SI
did not have an organizational conflict of interest. Nor on this
record would it be reasonable for the Air Force contracting
officer to assume that Air Force officials possessed sufficient
familiarity with SI's participation in the procurement to make
such a determination. Simply put, the showing that the agency
made in Mechanical Equip. Co., Inc. was that agency officials
with a breadth and depth of first-hand knowledge reasonably and
contemporaneously concluded that the firm had no organizational
conflict of interest. The Air Force has made no such showing
here.
This record lacks a thorough agency inquiry into the extent of
access to information that the SI employee had and what
competitively useful information his access yielded. The record
similarly lacks any reasonable assessment of whether the
non-disclosure agreement and the mitigation plan were effective
against the disclosure of information to SI Telecom (or others).
We therefore conclude that, given the inadequacies of this
record, it was unreasonable for the agency to determine that SI
did not have an unequal access to information organizational
conflict of interest.
Allegations Arising from the Relationship Between SI and FCI
The protester argues that we should find that GDIT, through its
subcontractor SI, had an impaired objectivity organizational
conflict of interest, because the prime contractor under Army
Task Order 5017, FCI, supplied employees who acted as Mission
Capability subfactor evaluation team advisors to the Air Force.
As noted above, an impaired objectivity organizational conflict
of interest exists where a firm's work under one government
contract could entail its evaluating itself, either through an
assessment of performance under another contract or an
evaluation of a proposal submitted to obtain another contract.
Aetna Gov't Health Plans, Inc.; Foundation Health Fed. Servs.,
Inc., supra at 13.
In support of its allegation, L-3 cited FAR sect. 9.505-3, while
also noting the FAR's general admonishment "to avoid strictly
any conflict of interest or even the appearance of a conflict of
interest in Government-contractor relationships." FAR sect.
3.101-1. The "hard facts" that L-3 offered in support of such a
finding were that SI was FCI's subcontractor on the Uni-Comm
procurement, the two firms sought to work together on another
task order advising the Uni-Comm procurement, and during the Uni‑Comm
evaluation, the GDIT proposal, with SI as a subcontractor, was
evaluated by FCI. L-3's Post Hearing Comments, Aug. 5, 2009 at
76. Thus, L-3 argues, FCI and SI sought to influence the
solicitation, participate as a subcontractor in GDIT's proposal,
and assist with the evaluation of the proposals, and the agency
improperly failed to conduct and document an analysis of whether
these relationships created an impaired objectivity
organizational conflict of interest. GDIT asserts that all of
these relationships were timely reported to the Air Force and
the relationships and roles do not violate the FAR.
We will sustain an allegation that a firm has an impaired
objectivity organizational conflict of interest when the facts
of the case meet the standard in FAR sect. 9.505-3. Nortel Gov’t
Solutions, Inc., B‑299522.5, B-299522.6, Dec. 30, 2008, 2009 CPD
para. 10 (sustaining impaired objectivity organizational
conflict of interest allegation where the record showed that
contractor would review its own work on another contract); Alion
Sci. & Tech. Corp., B-297022.3, Jan. 9, 2006, 2006 CPD para. 2
(sustaining impaired objectivity organizational conflict of
interest where awardee would be required to perform analysis and
make recommendations regarding products that might be
manufactured by it or by its competitors); Ktech Corp.,
B-285330, B-285330.2, Aug. 17, 2000, 2002 CPD para. 77
(sustaining impaired objectivity organizational conflict of
interest where a firm would be responsible for helping to
determine the stringency of testing requirements and for
monitoring the performance of the tests, while at the same time,
as a subcontractor, the firm was responsible for conducting the
tests).
The relationships between firms, or the actions of individual
firms, described in the cases where we have sustained an
allegation of an impaired objectivity organizational conflict of
interest are different in kind from the relationship between FCI
and SI. There is no evidence in the record of a corporate
relationship between the firms, such that one firm is evaluating
itself or an affiliate, or evaluating products made by itself or
a competitor, or is making judgments that would otherwise
directly influence its own well-being, as there was in the cases
cited above. The protester urges us to consider that an
organizational conflict of interest exists because the two firms
contemplated additional work together on the Uni-Comm
procurement, but we decline to do so; at least in this
circumstance, what the two firms considered doing has no bearing
on our analysis of whether their actual relationship met the
standard for an organizational conflict of interest. Moreover,
we look for some indication that there is a direct financial
benefit to the firm alleged to have the organizational conflict
of interest, American Mgmt. Sys., Inc., B‑285645, Sept. 8, 2000,
2000 CPD para. 163 at 5, and there is none in this instance.
While SI performed as FCI's subcontractor on the Army task
order, the suggestion that FCI would benefit financially from
favorably evaluating GDIT's proposal is too remote a financial
relationship on which to base an impaired objectivity
organizational conflict of interest. See id. at 6. The
relationship between SI and FCI is simply too attenuated and too
dissimilar to the above cases for us to conclude that the agency
unreasonably determined that GDIT did not have an impaired
objectivity organizational conflict of interest. (L-3
Services, Inc., B-400134.11; B-400134.12, September 3, 2009)
(pdf)
The protester argues that the agency improperly failed to
consider that Bollinger has an impermissible organizational
conflict of interest (OCI) that "possibly gave [Bollinger] an
advantage in this procurement and potentially prejudiced [MMC]."
Protester's Comments at 96. As discussed above, the Coast Guard
contracted with ABS to analyze certain aspects of the offerors'
proposals. The protester points to Bollinger's FPR, which
provides in relevant part as follows:
The feedback from ABS on our
proposal was positive, and all concerns were addressed. From
this meeting Bollinger has developed and revised plans and
procedures to incorporate the recommendations of ABS. ABS
feedback has validated the FRC‑B design illustrated [below] .
. . . ABS and Bollinger have evaluated responsibilities during
plan review and agreed to milestone and submittal dates
required to meet the construction schedule. ABS has reviewed
the Bollinger engineering schedule to verify that ABS
resources can sustain an individual drawing review cycle of 30
days to support production.
AR, Tab 48, Bollinger Proposal,
vol. III, at 108. The protester adds that the agency was aware
of Bollinger's relationship with ABS, in that the PEAG Report
provides in relevant part that "ABS was sought and provided
[Bollinger] with a review of their proposal." AR, Tab 14, PEAG
Report, at 15. The protester concludes that because ABS assisted
Bollinger in some manner with the preparation of its proposal,
and then assisted the Coast Guard in its evaluation of
proposals, an impermissible OCI existed that rendered the award
to Bollinger improper.
When the facts of a procurement raise a concern that a potential
awardee might have an OCI, the FAR requires the agency to
determine whether an actual or apparent OCI will arise, and
whether the firm should be excluded from the competition. The
specific responsibility to avoid, neutralize or mitigate a
potential significant conflict of interest lies with the
cognizant contracting officer. Overlook Sys. Techs., Inc.,
B‑298099.4, B-298099.5, Nov. 28, 2006, 2006 CPD para. 185 at
10-11; see FAR sect. 9.504. As relevant here, one of the
situations that creates a potential OCI is where a firm's work
under a government contract entails evaluating itself or its own
products. FAR sections 9.505, 9.508; Overlook Sys. Techs., Inc.,
supra, at 10. The concern in such situations is that a firm's
ability to render impartial advice to the government will be
undermined or impaired by its relationship to the product or
services being evaluated; as a result, such situations are often
referred to as "impaired objectivity" conflicts if interest.
Overlook Sys. Techs., Inc., supra.
The agency explains that "[t]he assistance" it received from ABS
in the evaluation process, which was limited to the
consideration of initial proposals, "was specifically in the
area of classification of the proposed ships." Agency Supp.
Report (Nov. 25, 2008) at 27-28. The agency also states that to
its knowledge both Bollinger and MMC "sought advice from ABS,
but neither of them obtained that advice under a contract with
ABS or any of its affiliates." Id. at 28. The agency asserts
that because "ABS did not have a contract with either of the two
firms that sought its assistance, there was no conflicting
interests to avoid, neutralize or mitigate." Id. The agency adds
here that "[s]ince ABS' true role with the offerors and with the
Coast Guard was to take an independent position regarding the
application of their rules, there could be no internal conflicts
of interests." Id. at 29.
Based upon our review, we find that no significant conflict of
interest exists here. As set forth above, with regard to
Bollinger's pre-award relationship with ABS, although Bollinger
received some advice from ABS during the proposal preparation
process, ABS clearly was not part of Bollinger's "team" and
there was no financial relationship between Bollinger and ABS.
Moreover, as indicated above, both MMC and Bollinger obtained
advice from ABS during the proposal preparation process. [24]
There is no evidence or claim that the post‑award relationship
between ABS and Bollinger as the result of Bollinger's status as
the awardee is any different than would be the relationship
between ABS and MMC had MMC been awarded the contract. That is,
as recognized by the protester, the RFP required that during the
performance of the contract awarded here, the awardee must
contract with ABS for classification of the FRC‑B and structural
analysis, and that "all offerors, including [MMC], were required
to demonstrate in their proposals that they had arranged with
ABS to provide post-award classification services." Protester's
Supp. Comments (Dec. 11, 2008) at 5-6; see Protester's Comments
at 97 n.14; RFP, pt. III, sect. J, attach. 2, COR, at 000-33.
Given the lack of any financial relationship between ABS and
Bollinger prior to the award, and the fact that the relationship
of ABS with the awardee would be the same or similar whether
Bollinger or MMC were the awardee, we find that the potential
benefit to ABS here, if any, is speculative and too remote to
establish a significant conflict of interest that the
contracting agency had to avoid, neutralize, or mitigate
pursuant to FAR subpart 9.5. See sect. 9.504(a)(2); American
Mgmt. Sys., Inc., B-285645, Sept. 8, 2000, 2000 CPD para. 163 at
6; Professional Gunsmithing, Inc., B-279048.2, Aug. 24, 1998,
98-2 CPD para. 49 at 4 (FAR requires that agencies avoid or
mitigate "significant potential conflicts"). (Marinette
Marine Corporation, B-400697; B-400697.2; B-400697.3,
January 12, 2009) (pdf)
The contracting officer (who was the SSA) determined, and DEA
continues to maintain, that "SRA's performance of the FITS
contract [does] not create an 'impaired objectivity OCI" with
regard to SRA's performance of the EMS O&M contract. Contracting
Officer's Statement at 32. In explaining her position that no
OCIs will result from SRA's performance of both contracts, the
contracting officer asserts that: (1) SRA will not be in a
position to evaluate or assess its own work on the FITS
contract, nor will SRA benefit from SRA's input as the EMS
contractor since neither the EMS nor FITS systems engineering
contractor will furnish any system or software that will be
necessary to implement systems engineering solutions proposed by
the FITS contractor; (2) all systems engineering work and
implementation of systems engineering initiatives are subject to
oversight and control by DEA personnel, with government
personnel chairing any IPTs involved in the initiatives and all
systems engineering work under the FITS contract subject to
review and approval of DEA's government-led configuration
control board (CCB); (3) the input from the EMS contractor
regarding systems engineering solutions proposed by the systems
engineering FITS contractor will be essentially limited to
participating in meetings involving the implementation of
systems engineering initiatives, with such meetings occupying
only a relatively small portion of the EMS contractor's overall
contract effort; and (4) SRA committed that, in the event of a
change in these processes or if the government concluded that
additional measures were necessary, it would adopt additional
mitigation items including organizational/financial and
informational separation of the EMS work from the FITS work (a
firewall). Supplemental Contracting Officer's Statement at 2-4;
SRA Mitigation Plan at 3-5, 7.
Contracting officers are required to identify potential
conflicts of interest as early in the acquisition process as
possible. Federal Acquisition Regulation (FAR) sections 9.505,
9.508. Situations that create potential conflicts of interest
include situations in which a firm's work under a government
contract entails evaluating itself. The concern in such
"impaired objectivity" situations is that a firm's ability to
render impartial advice to the government will be undermined by
its relationship to the product or service being evaluated.
PURVIS Sys., Inc., B‑293807.3, B‑293807.4, Aug. 16, 2004, 2004
CPD para. 177 at 7. The primary responsibility for determining
whether a conflict is likely to arise, and the resulting
appropriate action, rests with the contracting agency. FAR sect.
9.505; RMG Sys., Ltd., B‑281006, Dec. 18, 1998, 98‑2 CPD para.
153 at 4. Once an agency has given meaningful consideration to
potential conflicts of interest, our Office will not sustain a
protest challenging a determination in this area unless the
determination is unreasonable or unsupported by the record.
Alion Sci. & Tech. Corp., B‑297022.4, B-297022.5, Sept. 26,
2006, 2006 CPD para. 146 at 8.
The record indicates that the agency did not give meaningful
consideration to the potential impaired objectivity OCI
involving SRA’s dual roles. Contrary to the agency’s assertion
that SRA will not be in a position to evaluate or assess its own
work on the FITS contract, the record shows that SRA, as the EMS
contractor, is expected to review and offer input from the O&M
perspective regarding systems engineering solutions proposed by
itself as the FITS contractor. SAR at 5. Moreover, that input
will involve SRA’s subjective judgment. In this regard, we note
that when asked if DEA sought the O&M (EMS) contractor’s
“subjective opinions of the design,” the TEP chair testified
that “[t]hey can be subjective . . . depending on the level of
detail of the design.” Tr. at 49. In our view, this provides an
opportunity for biased advice. See PURVIS Sys., Inc., supra,
2004 CPD para. 177 at 9 (agency improperly failed to consider
impaired objectivity OCI where same contractor was expected to
provide subjective input on its own products and services).
Further, we find persuasive the protester’s position that, while
the advice may not result in implementation work for SRA under
either contract, input from and review by SRA as the EMS
contractor regarding systems engineering solutions proposed by
SRA as the FITS contractor could have a potential impact on
SRA’s relationship with the government including past
performance evaluations and future competitions. In these
circumstances, we believe that it is clear from the record that
the performance by SRA of both the EMS and FITS contracts
presents a potential impaired objectivity OCI.
Our conclusion that a potential impaired objectivity OCI exists
is not altered by DEA's assertion that it does not rely on the
EMS contractor alone for advice, nor by its reliance on the fact
that the government retains the ultimate decisionmaking
authority. The record indicates that obtaining input from a
contractor with the O&M perspective was considered important.
According to the testimony of the TEP chair, it would be
"negligent" not to have the EMS contractor's perspective on FITS
designs and so the agency would still seek the input of SRA even
when it fulfills both roles. Tr. at 166‑68. In this regard, the
EMS contractor will replace multiple former O&M contractors with
a single O&M contractor (Tr. at 166), arguably giving it a more
important role. Thus, the possibility of obtaining O&M
perspective from other DEA contractors may necessarily be
somewhat limited. Further, the agency broadly asserts that under
its process "[a]ny contractor input" in an IPT is "vetted by the
DEA personnel" and that the CCB reviews and approves all IT
changes making the government the "final decision authority." AR
at 20. However, it is not clear from the record that this review
will address the impaired objectivity concern arising from SRA's
dual roles where, as here, the contractor is expected to have a
potentially significant role in providing input with regard to
SRA's system design. For example, neither SRA in its OCI
mitigation plan, nor the agency, provides any specifics on how
the agency will accomplish its vetting of SRA's input before
making its final decisions. As we explained in Johnson Controls
World Servs., Inc., B-286714.2, Feb. 13, 2001, 2001 CPD para. 20
at 11-12, an approach based upon ad hoc mitigation activity such
as discounting the weight given to the firm's recommendations,
even if feasible, is not a substitute for the preaward
deliberation contemplated under FAR sect. 9.504.
Moreover, although DEA asserts that the review work constitutes
only a small portion of the EMS contractor's effort, the
agency's position is not supported by the record. In this
regard, in response to NGS's protest, the agency now asserts
that only 2 percent of the contractor's time is spent in IPT
meetings and those meetings are not solely for design reviews.
AR at 21 n.8; Supplemental Contracting Officer's Statement at 4.
However, not only did a representative of NGS offer persuasive
testimony to the effect that 5 of 60 NGS engineers spent at
least 25 percent of their time working on reviews and IPT
meetings, but in addition, the TEP chair testified that the EMS
contractor was spending 10 to 15 percent of its time on reviews.
Tr. 158-61. Given this testimony, and the fact the 2 percent
figure is not supported by any meaningful contemporary
assessment, we find unpersuasive the agency's attempt to portray
the review work giving rise to an impaired objectivity OCI as
insignificant in terms of the EMS contractors overall level of
effort. More significantly, even if the review work took little
of the EMS contractor's time, there is no showing in the record
that this review process is not important to the agency's
mission, and it would not obviate the fact that a potential
impaired objectivity OCI existed which needed to be avoided or
mitigated.
Finally, SRA's proposal to separate its EMS and FITS personnel
through use of a firewall appears to be of little, if any, help
in resolving the OCI here. In this regard, the proposed firewall
provides for SRA to manage the two contracts using "separate
organizations with separate interests" and "distinct business
objectives." SRA Mitigation Plan at 5. It also prohibits SRA and
subcontractor personnel working on one contract from providing
support under the other contract, without written approval from
the contracting officer. SRA Mitigation Plan at 7. However,
while a firewall arrangement may resolve an "unfair access to
information" OCI, it is virtually irrelevant to an OCI involving
potentially impaired objectivity. See Aetna Gov't Health Plans,
Inc.; Found. Health Fed. Servs., B‑254397.15 et al., July 27,
1995, 95‑2 CPD para. 129 at 16. This is because the conflict at
issue pertains to the organization, and not the individual
employees. Id. Thus, while the firewall proposed by SRA may
create the appearance of separation to mitigate the OCI, the
fact remains that personnel under both contracts will be working
for the same organization with an incentive to benefit SRA
overall. Accordingly, the firewall does not avoid, mitigate or
neutralize the impaired objectivity OCI resulting from SRA's
performance of dual roles reviewing and providing input on its
own designs.
We sustain the protest on the basis that the record does not
support DEA's conclusion that there was no potential OCI
involving SRA's dual roles, but instead indicates that the
agency did not give meaningful consideration to this potential
impaired objectivity OCI. Since the agency needs to address the
extent of the OCI and what mitigation is appropriate, and
because the impact that mitigation may have on SRA's technical
and cost proposals is unknown, we believe that the agency will
need to reopen discussions in order to address these matters.
(Nortel Government Solutions, Inc.,
B-299522.5; B-299522.6, December 30, 2008) (pdf)
OCI
Detica asserts that CNA has an impermissible OCI, and that one
of the agency's evaluators was biased in favor of CNA. In this
connection, the protester asserts that an individual who
formerly was the director of the agency's office of preparedness
policy, planning, and analysis (PPPA), resigned from his
position and subsequently was hired by CNA. The protester
maintains that the former PPPA director was involved both in
planning the subject acquisition, and in identifying funds for
the acquisition. Detica maintains that this gives rise to an OCI
that the agency did not identify or attempt to mitigate or
neutralize. Detica also asserts that the former director
maintained a professional relationship with one of the agency's
technical evaluators; according to Detica, this resulted in bias
in favor of CNA.
The Federal Acquisition Regulation (FAR) generally requires
contracting officers to avoid, neutralize, or mitigate potential
significant OCIs in order to prevent unfair competitive
advantages or the existence of conflicting roles that might
impair a contractor's objectivity. FAR sections 9.504, 9.505. As
a general matter, OCIs can be broadly categorized into three
groups: biased ground rules, unequal access to non‑public
information, and impaired objectivity. Operational Resource
Consultants, Inc., B-299131, B-299131.2, Feb. 16, 2007, 2007 CPD
para. 38 at 5-6. Substantial facts and hard evidence are
necessary to establish the existence of an OCI; mere inference
or suspicion of an actual or apparent OCI is insufficient for
our Office to sustain a protest. Id.
Although Detica has not specifically identified the type of OCI
it is alleging, its contention that the former director
participated in planning the subject acquisition and identifying
funds within the agency suggests an alleged "biased ground
rules" OCI; such an OCI arises where an individual or concern
has, for example, prepared the SOW for a solicitation. FAR sect.
9.505-2. We find no basis to conclude that CNA has an
impermissible OCI.
The record shows that the individual in question was the
director of PPPA from September until December 2007, at which
time he tendered his resignation; shortly thereafter, he became
an employee of CNA. Intervenor's Comments, Oct. 6, 2008,
Affidavit of Former PPPA Director, at 1. The former director
states that, during this interval, PPPA's fiscal year 2008
budget remained in draft form and, although this draft budget
included funding for research and analysis, there was no SOW or
other acquisition documentation for the requirement that
eventually evolved into the SPAR acquisition, and the budget was
not finalized or approved until after his departure. Id. at 2.
These representations are corroborated by affidavits from agency
personnel. The new PPPA director states that the former director
never saw the research branch quotation that eventually became
the basis for the SPAR procurement. AR, exh. B, at 1. He further
represents that the individual responsible for preparing the
scope of work (SOW) for the SPAR procurement did not begin
working on that document until February or March 2008, after the
departure of the former director, and that the SOW document was
not forwarded to him for review (as the new PPPA director) until
March. Id.
The record also contains the affidavit of the individual who
prepared the acquisition package for the SPAR procurement,
including the SOO. She states that, at no time did she have any
interaction with the former director, and that she neither
received information from him, nor provided information to him
relating to her development of the acquisition package for the
SPAR requirement. AR, exh. C, at 1. She also states that she did
not begin preparing the solicitation's SOO until early March
2008, and that she forwarded it to her director in mid-March.
Id.
Against the backdrop of this evidence, the only evidence
presented by Detica in support of its generalized allegation of
an OCI is an affidavit in which one if its employees represents
that he has observed that the former director was responsible
for overseeing preparation of the agency's budget, that there
were several contacts between representatives of Detica and CNA
(that did not include the affiant) in February 2008 concerning
possible teaming arrangements between the two firms, and that
the former director had been involved in these contacts. Letter
of Protest, Aug. 29, 2008, attach. A, at 1-3. This affidavit
does not establish that the former director participated in
planning the subject acquisition and in identifying available
agency funding for the requirement, as Detica alleges.
We conclude from the evidence presented that the former director
was involved in the preliminary stages of preparing the agency's
annual budget; that he was aware that the budget in its draft
form included funding for some unspecified research and analysis
work; that he was no longer a federal employee at the time the
SPAR requirement was identified with specificity and did not
participate in preparing the solicitation or SOO; and that
identifying the agency's actual requirements and preparing the
acquisition package (including the SOO) was accomplished by
other individuals who were not in contact with the former
director. Simply stated, the evidence does not support a finding
of an impermissible OCI on the part of CNA. (Detica,
B-400523; B-400523.2, December 2, 2008) (pdf)
Contracting officers are required to identify potential
conflicts of interest as early in the acquisition process as
possible, and to avoid, neutralize, or mitigate such conflicts
to prevent the existence of conflicting roles that might impair
a contractor’s objectivity, such as where contract performance
entails evaluating itself or its own products, since the firm’s
ability to render impartial advice may be undermined. See FAR
sections 9.505, 9.508; PURVIS Sys., Inc., B-293807.3,
B-290807.4, Aug. 16, 2004, 2004 CPD para. 177 at 7. In assessing
potential OCIs, the FAR directs the contracting officer to
examine each contracting situation individually on the basis of
its particular facts and the nature of the proposed contract;
using sound judgment, the contracting officer is to determine
not only whether a conflict exists, but, if so, the appropriate
means for resolving it, consistent with the terms of the
solicitation and applicable procurement rules. See Alion Sci. &
Tech. Corp., B-297022.4, B‑297022.5, Sept. 26, 2006, 2006 CPD
para. 146 at 8; Lucent Techs. World Servs. Inc., B-295462, Mar.
2, 2005, 2005 CPD para. 55 at 10. Our review of the record here
supports the protester’s contention that the agency’s OCI
assessment of AT&T, as well as the agency’s disqualification of
the firm without considering its ability to avoid, neutralize,
or mitigate the alleged conflict, or otherwise allowing the firm
to respond to the reasons cited for its adverse OCI assessment,
were unreasonable.
First, although the RFP required the contracting officer to
evaluate all proposals to determine whether an apparent OCI
exists, the agency here concedes that AT&T’s proposal, which
included a proposed OCI mitigation plan, was not evaluated prior
to the firm’s disqualification; the OCI assessment, therefore,
clearly was not conducted in accordance with the terms of the
RFP, which called for such an evaluation. Second, as the
protester points out, and as stated above, the solicitation here
included provisions (referencing the general rules of FAR sect.
9.505) for limitations on contracting as a means of avoiding,
neutralizing, or mitigating perceived OCIs, but there is no
indication in the record that the agency considered their
application to AT&T prior to deciding to disqualify the firm.
While the agency suggests that, since the RFP did not
specifically request a mitigation plan from the offerors and
advised that firms with an actual or apparent OCI would be
disqualified, offerors should have known that plans to avoid,
neutralize, or mitigate an OCI would not be considered by the
agency, our review of the solicitation does not support the
agency’s position. Rather, our review shows that the RFP
contemplated that the agency would attempt to avoid, neutralize,
or mitigate perceived OCIs, at least to the extent of applying
the “contracting restrictions” provisions of the RFP. These
provisions, as stated above, allow participation in the
procurement with some performance limitations or where other
safeguards are in place to ensure objectivity; we therefore
agree with the protester that a reasonable interpretation of the
RFP is that disqualification was a determination to be made
after consideration of whether or not a perceived OCI could be
resolved short of eliminating the firm from the competition. See
RFP at 39-41. The agency, however, failed to conduct the
required review of whether or not the perceived OCI attributed
to AT&T could be resolved, i.e., avoided, neutralized or
mitigated, without the need to disqualify the firm.
Third, the agency provides no support for its conclusion that
AT&T would be evaluating its own IO security products in
performance of the tasks identified in the RFP, such as the
required analysis of the agency’s current IO systems. According
to AT&T, its IO security products are not part of the Navy’s IO
systems to be supported here; rather, AT&T’s IO products are
only available to its network subscribers and the Navy does not
subscribe to that network. The OCI determination, therefore,
appears to be based more on unsupported inference than fact.[2]
See NES Gov’t Servs., Inc.; Urgent Care, Inc., B-242358.4;
B-242358.6, Oct. 4, 1991, 91-2 CPD para. 291 at 6. We think it
was unreasonable for the agency to have assessed an OCI in this
regard without first resolving the implications of the
subscription-only limitation associated with the use of the
firm’s products and services before concluding that those
products and services would be evaluated by the firm during its
performance of the RFP’s tasks.[3] Under these circumstances, we
think that the agency’s failure to communicate its OCI concerns
to AT&T and provide an opportunity for a response from the
protester for consideration in the OCI assessment of the firm,
was unreasonable. See FAR sect. 9.504(e) (providing that before
determining to withhold an award based on conflict of interest
considerations, the contracting officer is to notify the
contractor of the reasons supporting proposed exclusion of the
firm and allow the contractor a reasonable opportunity to
respond); sect. 9.506(d)(2) (requiring the contracting officer
to consider additional information provided by prospective
contractors in response to the solicitation or during
negotiations in review of perceived OCIs); Lucent Techs. World
Servs. Inc, supra, at 11.
In light of the lack of support for the agency’s OCI assessment
of AT&T, and the failure to give AT&T an opportunity to respond
to the agency’s perceived OCI, we recommend that the agency give
the firm notice of the reasons for its OCI concerns and an
opportunity to respond. The agency’s new OCI assessment for the
firm should also include, consistent with the solicitation,
consideration of the firm’s proposal (including its proposed OCI
mitigation plan). To the extent a perceived OCI is found, the
agency should then consider the applicability of the
“contracting restrictions” provided in the solicitation to
resolve any OCI concerns, if appropriate (i.e., prior to a
disqualification determination, if any). We also recommend that
AT&T be reimbursed the costs of filing and pursuing the protest,
including reasonable attorneys’ fees. 4 C.F.R. sect. 21.8(d)(1)
(2008). AT&T should submit its certified claim for costs,
detailing the time expended and costs incurred, directly to the
contracting agency within 60 days after receipt of this
decision. 4 C.F.R. sect. 21.8(f)(1). (AT&T
Government Solutions, Inc., B-400216, August 28, 2008)
(pdf)
The record shows that while both CEDS and the HAP program
involve processing information from multiple security levels
simultaneously, the two programs apply different separation
technologies and approaches; the requirements in the two
programs here are also qualitatively different. CEDS requires,
at a minimum, the ability to simultaneously and separately
process information from six different security classifications
under the same operating system, while the HAP program involves
separating information in two adjacent levels of security
classification. CEDS involves a real-time operating system
(i.e., the results of one process are available in time for the
next computing process which requires the previous result) and
the HAP program does not. Further, while CEDS utilizes
separation kernel technology that is to be certified by NSA
against the most rigorous security assurance requirements, the
HAP program does not involve the use or adaptation of a
separation kernel, or mandate compliance with the same security
assurance requirements. RFP amend. 1, SRD sect. 3.6.2.3; GD
Comments, Dec. 31, 2007, exh. 3, HAP Statement of Work, attach.
A, Declaration of Bill Ross, at 4-8. In sum, from the record
before us, it appears that to the extent that GD was familiar
with separation kernel technology, it was not as a result of its
work on the NSA HAP program.
Contracting officers are required to identify and evaluate
potential OCIs as early in the acquisition process as possible.
Federal Acquisition Regulation (FAR) sect. 9.504(a)(1). The FAR
provides that an OCI exists when, because of other activities or
relationships with other persons or organizations, a person or
organization is unable or potentially unable to render impartial
assistance or advice to the government, or the person’s
objectivity in performing the contract work is or might be
otherwise impaired, or the person has an unfair competitive
advantage. See FAR sect. 2.101. Situations in which OCIs arise,
as addressed in FAR subpart 9.5 and the decisions of our Office,
are generally associated with a firm’s performance of a
government contract and can be broadly categorized into three
groups: (1) unequal access to information cases, where the
primary concern is that a government contractor has access to
nonpublic information that would give it an unfair competitive
advantage in a competition for another contract; (2) biased
ground rules cases, where the primary concern is that a
government contractor could have an opportunity to skew a
competition for a government contract in favor of itself; and
(3) impaired objectivity cases, where the primary concern is
that a government contractor would be in the position of
evaluating itself or a related entity (either through an
assessment of performance under a contract or an evaluation of
proposals in a competition), which would cast doubt on the
contractor’s ability to render impartial advice to the
government. Mechanical Equip. Co., Inc. et al., B-292789.2 et
al., Dec. 15, 2003, 2004 CPD para. 192 at 18; Aetna Gov’t Health
Plans, Inc.; Foundation Health Fed. Servs., Inc., B-254397.15 et
al., July 27, 1995, 95-2 CPD para. 129 at 12-13. DRS’s
allegation concerning GD here is primarily that it had an unfair
competitive advantage as a result of its work under the HAP
contract.
We find DRS's central assertion--that as the HAP contractor GD
improperly gained inside knowledge and helped to shape the
separation kernel standards applicable to the CEDS
procurement--to be unfounded. As a preliminary matter, there is
no evidence (and DRS does not assert otherwise) that GD had a
role in the development of the actual CEDS separation kernel
requirements. Further, GD's work on the HAP program did not
result in the offeror having a role in the development of NSA's
SKPP standard. As set forth above, the record clearly reflects
that the HAP program did not involve the use of separation
kernel technology, none of GD's work on the HAP program involved
the development or the delivery of NSA's SKPP standard, and none
of GD's work product from the HAP program was used by NSA for
the development of the SKPP standard.[8] Further, GD's work on
the HAP program was not directly applicable to the much more
difficult technology and security assurance requirements set
forth in the CEDS SRD: at most, GD's work on the HAP contract
taught the offeror what would not work for the CEDS procurement.
There is simply no merit to DRS's allegation that GD helped to
shape the NSA separation kernel standards that applied to the
CEDS procurement, and any exposure that GD had to separation
kernel technologies and the corresponding NSA standard was a
competitive advantage that the Navy had no duty to neutralize.
Gonzales Consulting Servs., Inc., B-291642.2, July 16, 2003,
2003 CPD para. 128 at 7; Government Bus. Servs. Group, B-287052
et al., Mar. 27, 2001, 2001 CPD para. 58 at 10. (DRSC3
Systems, LLC, B-310825; B-310825.2, February 26, 2008) (pdf)
SRA contends that
the key personnel evaluation is tainted by personal and
organizational conflicts of interest (OCI) involving an
evaluation reference, SRNS’s proposed SRNL director, and several
of SRNS’s other key personnel. SRA first argues that the
evaluation was tainted in that one of the individuals who
provided references to the SEB in connection with two proposed
key personnel provided biased information because she had a
personal conflict of interest: at the time of the evaluation,
she was married to an employee of one of SRNS’s team members.
The RFP required each proposed key personnel to provide a
reference, and stated that these “reference checks” would be
part of the key personnel evaluation. RFP sect. M‑2(a)(1). One
of SRA’s key personnel and one of SRNS’s key personnel
identified a DOE employee as a reference. As was known by SRA at
the time of its proposal submission and during the evaluation,
but was not known to the SEB or SSA, this DOE employee was
married to an employee of one of SRNS’s team members. Supp.
Contracting Officer’s Statement at 2-3. The evaluators had no
reason to suspect bias on the part of this reference, given that
it was SRA that identified this DOE individual as a key
personnel reference, and presumably SRA would not have
identified a reference that could be biased against it. Id. at
5. The DOE employee reference gave the SRA individual a somewhat
negative reference, and gave the SRNS individual a positive
reference. During the evaluation, the SEB noted that, with
regard to the one SRA key personnel, the negative reference was
inconsistent with the other positive references, and thus the
agency requested additional references, all of which were
positive. As a result, the SEB “discounted” the negative
reference, concluded that the reference checks for this SRA
individual were “[f]avorable,” and rated this SRA individual a
strength in the key personnel evaluation. Supp. Contracting
Officer’s Statement at 6; AR, Tab B.2, SEB Report, app. A, at 5,
11. With regard to the one SRNS key personnel, the DOE reference
was found to be consistent with other “[f]avorable” references,
and the SRNS individual was also given a strength in the
evaluation. Supp. Contracting Officer’s Statement at 6; Tab B.2,
SEB Report, app. A, at 5, 11.
We have recognized that an actual or apparent conflict of
interest may arise when an agency employee has both an “official
role in the procurement” and a “personal stake in the outcome.”
TPL, Inc., B-297136.10, B-297136.11, June 29, 2006, 2006 CPD
para. 104 at 8 (citing examples). Here, however, the DOE
reference in question did not have an official role in the
procurement--she was not involved in drafting, reviewing or
approving the RFP; evaluating proposals; or reviewing or
approving the award. She merely provided a personnel reference
for two individuals because she was identified by the offerors
as a person to contact as a reference check. We have found that
a conflict of interest does not necessarily exist, even where
the same agency employee provides a reference and performs the
evaluation, absent a showing (which has not been made here) of
improper influence on the evaluation. Id. at 9. Based on this
record, we find that the evaluators acted reasonably in dealing
with this reference’s comments. In any event, even if the DOE
reference were biased or had a conflict of interest, the record
shows that this had no impact on the evaluation and thus SRA was
not prejudiced as a result. See Laerdal Med. Corp., B‑297321,
B-297321.2, Dec. 23, 2005, 2005 CPD para. 12 at 7 (prejudice is
not established where, even if a conflict of interest or bias
exists, it has no impact on the evaluation).
SRA also complains that several of SRNS’s proposed key personnel
create the potential for OCIs. Specifically, it contends that
the SRNL director’s role as the president and owner of a
consulting firm “conflicts” with his role as SRNL director for
SRNS, and that the director could use information obtained
during performance for the competitive advantage of his company
and clients in the future. SRA’s Comments at 87. SRA also
contends that [REDACTED] of SRNS’s proposed key personnel have
“divided loyalty” because they are employed by SRNS’s member
companies and not SRNS itself. SRA’s Comments at 83. As
discussed below, we do not agree with SRA that the situations it
describes with regard to SRNS’s key personnel present the
potential for OCIs.
It is true that contracting officers have a duty to avoid,
neutralize, or mitigate potential significant OCIs so as to
prevent unfair competitive advantage or the existence of
conflicting roles that might impair a contractor’s objectivity.
Federal Acquisition Regulation (FAR) sections 9.504(a), 9.505;
Aetna Gov’t Health Plans, Inc.; Found. Health Fed. Servs., Inc.,
B‑254397.15 et al., July 27, 1995, 95-2 CPD para. 129 at 12-13.
As FAR Subpart 9.5 explains, OCIs that must be avoided include
situations where a company has divided loyalties that impair its
ability to render impartial advise to the government (“impaired
objectivity”), or where the company has access to information
that its competitors do not that could lead to a competitive
advantage for the firm (“unequal access to information”). FAR
sect. 9.5; Aetna Gov’t Health Plans, Inc.; Found. Health Fed.
Servs., Inc., supra, at 12-13. It must be noted, however, that
there is a distinction between an OCI and a personal conflict of
interest: with an OCI, the conflicted party is the organization;
with a personal conflict of interest, the conflict is with the
individual. See Daniel I. Gordon, Organizational Conflicts of
Interest: A Growing Integrity Challenge, 35 Pub. Cont. L.J. 25,
29 (Fall 2005) (distinguishing personal from organizational
conflicts of interests); see also FAR sections 3.101-1, 9.505,
9.508. The facts here, at most, give rise to personal conflicts
of the individual SRNS employees and are not OCIs. SRA has
not alleged, nor does the record evidence, any facts showing
that SRNS or its team member organizations have impaired
objectivity or that these entities serve multiple, or
conflicting, roles that could lead to an impaired objectivity
OCI; nor has SRA alleged that SRNS or its team member
organizations had unequal access to information that would
render this competition unfair. Rather, SRA argues merely that
the individual employees are not adequately committed to SRNS
and may use their positions to benefit their employing team
member companies, or, in the case of the SRNL director, that he
will use information in the future that will benefit his own
company. With regard to the SRNL director, the individual’s
ownership of a consulting business does not appear to “conflict”
with his role as SRNS’s proposed SRNL director, as SRA asserts.
The individual has divested himself of all of his consulting
work, except for one unrelated contract which he is performing
as a means of income until this protest is resolved. Declaration
of SRNS’s SRNL director para. 5. He and the other [REDACTED] key
personnel have signed commitment letters to work solely on the
Savannah River Site project without any “contingencies or
constraints” on their positions. SRNS’s Second Supp. Comments,
exh. 4, SRNS Key Personnel Commitment Letters. To the extent
that SRA asserts that the SRNL director or others may use
information learned during performance to benefit themselves or
their employers in future endeavors, this is speculative and
insufficient to impute any conflict of interest on these
individuals or their employers. See American Mgmt. Sys., Inc.,
B‑285645, Sept. 8, 2000, 2000 CPD para. 163 at 6 (possible
benefit from current procurement to a contractor is too
speculative and remote to establish a significant OCI). In
addition, we see no significant potential for OCIs arising out
of the fact that [REDACTED] of SRNS’s key personnel will remain
employees of the team member companies rather than become direct
employees of SRNS. Given that the employers are team members of
SRNS working together to perform the site work, we agree with
the agency that there is unlikely to be any divergence of
interest. Under the incumbent contract, currently performed by
SRA’s team members, the key personnel are employed by the team
members and not the prime contractor, WSRC. OCIs have not arisen
under that situation, and as the agency reasonably explains,
OCIs are unlikely to happen here. Contracting Officer’s
Statement at 56. The contracting officer here reviewed SRNS’s
disclosures regarding potential OCIs, and reasonably determined
that there was no basis to question these disclosures. Id. SRA’s
arguments do not call into question the reasonableness of the
contracting officer’s judgment. (Savannah
River Alliance, LLC, B-311126, B-311126.2, B-311126.3,
B-311126.4, April 25, 2008) (pdf)
Karrar asserts that the agency improperly failed to consider
that BANC3 has an impermissible OCI due to the fact that it is a
subcontractor to, and has a mentor‑protégé agreement with,
Lockheed Martin Corporation, one of the eight prime contractors
for the R2 program. Karrar’s assertion is based on its claim
that BANC3’s Internet website references the mentor-protégé
relationship. The situations in which OCIs arise are
addressed in Federal Acquisition Regulation (FAR) subpart 9.5
and in decisions of our Office. As relevant here, one type of
OCI, which reflects concerns about a firm’s “impaired
objectivity,” consists of situations where a firm’s work under
one federal contract could entail its evaluating its own or a
related entity’s performance under another federal contract,
thus undermining the firm’s ability to render impartial advice
to the government. FAR sect. 9.505-3; Aetna Gov’t. Health Plans,
Inc.: Found. Health Fed. Servs., Inc., B-254397.15 et al., July
27, 1995, 95-2 CPD para. 129 at 13.
The responsibility for determining whether an OCI exists, and
the extent to which a firm should be excluded from the
competition, rests with the contracting agency, SRS Techs.,
B-258170.3, Feb. 21, 1995, 95-1 CPD para. 95 at 8-9. Where an
agency has given thorough, documented consideration to an
offeror’s activities and their potential to create OCIs, we will
not substitute our judgment for the agency’s conclusions drawn
from such a comprehensive review, provided the conclusions are
otherwise rational and reasonable. See, e.g., Business
Consulting Assocs., B‑299758.2, Aug. 1, 2007, 2007 CPD para. 134
at 9-10; Overlook Sys. Techs., Inc., B‑298099.4, B-298099.5,
Nov. 28, 2006, 2006 CPD para. 185 at 10-18; Alion Sci. & Tech.
Corp., B-297022.4, B-297022.5, Sept. 26, 2006, 2006 CPD para.
146 at 5-8. The Army reports that it was aware of the potential
OCI here--the possibility that BANC3’s relationship with
Lockheed would undermine its ability to render impartial advice
to the agency under the contract--because BANC3 was performing
in the R2 project office as a subcontractor under a task order
issued to Lockheed, which was to expire in August 2007, but was
extended to October 31. AR at 10. The Army determined that, if
BANC3 were awarded the contract, it would have an impermissible
OCI if it continued to work with Lockheed or any other R2 prime
contractor. Accordingly, on Oct. 15, after BANC3 received the
award, the Army met with the firm to discuss its transition
plans. At this meeting, BANC3 indicated that it was withdrawing
from all teaming arrangements with R2 prime contractors and
would not compete as a prime contractor or subcontractor for any
future R2 contract. BANC3 further indicated that it would not
have any contractual relationship with Lockheed after the
current work order expired on October 31. The Army concluded
that, since any services that could result in an OCI issue would
not be ordered until after the relationship between Lockheed and
BANC3 ended, no impermissible OCI existed. As for the alleged
mentor‑protégé agreement between BANC3 and Lockheed, the Army
and BANC3 state that there is not and never has been such an
agreement. BANC3 explains that the statement on its website was
included in a draft version of its company brochure because it
explored the possibility of such an agreement, but the agreement
was never completed. The protester has provided no evidence to
the contrary. We find that, after thoroughly and reasonably
considering the possibility of an OCI, the agency reasonably
concluded that there existed no OCI that precluded BANC3 from
participating in the procurement or from receiving the award.
This argument thus provides no basis for questioning the award.
(Karrar Systems Corporation,
B-310661; B-310661.2, January 3, 2008) (pdf)
The situations in which OCIs arise, as addressed in FAR subpart
9.5 and the decisions of our Office, can be broadly categorized
into three groups: “unequal access to information” cases;
“biased ground rules” cases; and “impaired objectivity” cases.
See Aetna Gov’t Health Plans, Inc.; Foundation Health Fed. Servs.,
Inc., B‑254397.15 et al., July 27, 1995, 95-2 CPD para. 129 at
12-13. This protest concerns the first type, unequal access to
information. The record shows that an employee of TCI had access
to source selection information, including the independent
government estimate, the source selection plan, and other
offerors’ proposals. The owner of TCI, as noted, owns [DELETED]
percent of the stock of MPSC, Protest at 2 n.1, a subcontractor
of VRC under the current contract and a proposed subcontractor
under the current solicitation. In our view, these
relationships, considered together, indicate that VRC was in a
position to benefit competitively as a result of the TCI
employee’s position in NGB’s contracting office, which gave her
access to source selection information regarding this
procurement. Contracting agencies are admonished to avoid any
conflict of interest, even the appearance of a conflict of
interest, in government procurements, FAR sect. 3.101-1; see
Lancaster & Co., B-254418, Dec. 14, 1993, 93-2 CPD para. 319; on
the record here, we find reasonable the agency’s conclusion that
VRC had a conflict of interest. The protester asserts that,
regardless of the business relationships among the three
companies, the Chief of the Operational Contracting Division
(the contracting officer’s supervisor) had the authority to
decide whether the relationships in question constituted an OCI,
and the agency was bound by the Chief’s opinion that they posed
no conflict of interest. We disagree. With regard to conflicts
of interest, the FAR assigns certain duties and responsibilities
specifically to the contracting officer, some of which are noted
above. The FAR, without exception, places responsibility for
determining the existence of an OCI on the contracting officer
and makes no provision for the contracting officer to delegate
her authority. Here, the contracting officer simply exercised
her authority under the FAR, notwithstanding the Chief’s
apparent view of the matter. The protester also asserts that
there was no conflict of interest because the agency has not
shown “hard facts,” that is, that VRC was in possession of
source selection information as a result of the TCI’s employee’s
work for the agency. We disagree. It is true that a
determination to exclude an offeror must be based on facts,
rather than mere suspicion. Clement Int’l Corp., B-255304.2,
Apr. 5, 1994, 94-1 CPD para. 228 at 4; see also CACI, Inc.-Fed.
v. United States, 719 F.2d 1567 (Fed.Cir. 1983). The facts that
are required, however, are those which establish the existence
of the OCI, not the specific impact of the conflict. Aetna Gov’t
Health Plans, Inc.; Foundation Health Fed. Servs., Inc., supra,
at 18. Once the facts establishing the existence of an OCI are
present, reasonable steps to avoid, mitigate, or neutralize the
conflict are required without further need for “hard facts” to
prove the conflict’s impact on the competition. Where, as here,
the facts demonstrate that an OCI exists, the harm from that
conflict, unless it is avoided or adequately mitigated, is
presumed to occur. Id. The protester asserts that it had
measures in place, in the form of “firewall arrangements”
between the TCI employee and TCI and between TCI and MPSC/VRC,
that the contracting officer should have found sufficient to
mitigate any OCI. Protest at 6-7. The contracting officer states
that, had TCI made her aware of the ownership relationships
earlier in the procurement process, mitigation of the potential
conflict of interest might have been possible. AR, Contracting
Officer’s Statement of Facts at 4. Because the relationships
were not brought to her attention until 2 days after proposals
had been received, the contracting officer saw no way to
successfully mitigate the actual OCI and instead chose to avoid
the OCI altogether by rejecting VRC’s proposal. Again, we see no
basis in the record to question the reasonableness of the
contracting officer’s decision. In sum, even the appearance of
an unfair competitive advantage may compromise the integrity of
the procurement process, thus justifying a contracting officer’s
decision to err, if at all, on the side of avoiding the
appearance of a tainted competition. Lucent Techs. World Servs.
Inc., B‑295462, Mar. 2, 2005, 2005 CPD para. 55 at 10. Here, the
fact that an individual employed by TCI, a company with
ownership ties to the protester, was assigned to work in the
agency’s contracting office, together with the fact that the
agency was not notified of those ownership relationships until
after receipt of proposals, created a conflict of interest that
the contracting officer reasonably determined could only be
avoided by rejecting the protester’s proposal. (VRC,
Inc., B-310100, November 2, 2007) (pdf)
MTC maintains that any time an offeror, through performance of
another government contract, gains knowledge or information that
is not generally available to other offerors, that offeror has
an OCI and must be excluded from the competition. In our view,
MTC overstates the requirements of the FAR in this area. It is
well-settled that an offeror may possess unique information,
advantages and capabilities due to its prior experience under a
government contract--either as in incumbent contractor or
otherwise; further, the government is not necessarily required
to equalize competition to compensate for such an advantage,
unless there is evidence of preferential treatment or other
improper action. See FAR sect. 9.505-2(a)(3); Crux Computer
Corp., B-234143, May 3, 1989, 89-1 CPD para. 422 at 5. The
existence of an advantage, in and of itself, does not constitute
preferential treatment by the agency, nor is such a
normally-occurring advantage necessarily unfair. Crofton Diving
Corp., B‑289271, Jan. 30, 2002, 2002 CPD para. 32 at 6-7;
Government Bus. Servs. Group, B-287052 et al., Mar. 27, 2001,
2001 CPD para. 58 at 10. The responsibility for
determining whether an OCI exists, and to what extent the firm
should be excluded from the competition, rests with the
contracting agency, SRS Techs., B-258170.3, Feb. 21, 1995, 95-1
CPD para. 95 at 8-9, and the FAR directs contracting officers to
examine each situation individually and exercise “common sense,
good judgment, and sound discretion” in determining whether
significant conflicts exist. FAR sect. 9.505. The FAR and this
Office’s decisions mandate that, in meeting its obligation to
identify OCIs, an agency must give thorough consideration to the
interests and activities of an offeror that might create OCIs.
See, e.g., Alion Sci., & Tech. Corp., B-297342, Jan. 9, 2006,
2006 CPD para. 1 at 8-13; Science Applications Int’l Corp.,
B‑293601 et al., May 3, 2004, 2004 CPD para. 96 at 4-8. Where an
agency has, in fact, given thorough, documented consideration to
an offeror’s activities and their potential to create OCIs, we
will not substitute our judgment for the agency’s conclusions
drawn from such a comprehensive review, provided the conclusions
are otherwise rational and reasonable. See, e.g., Business
Consulting Assocs., B‑299758.2, Aug. 1, 2007, 2007 CPD para. 134
at 9-10; Overlook Sys. Techs., Inc., B‑298099.4, B‑298099.5,
Nov. 28, 2006, 2006 CPD para. 185 at 10-18; Alion Sci. & Tech.
Corp., B‑297022.4, B‑297022.5, Sept. 26, 2006, 2006 CPD para.
146 at 5-8.
Here, as documented extensively in the agency record, the agency
gave thorough and comprehensive consideration to the prior
activities of Denysys and its subcontractors, as well as MTC and
its subcontractors, in order to assess whether those activities
created OCIs. Specifically, the contracting officer performed an
analysis of the work that would be required under the
solicitation at issue--that is, operational sustainment of the
TEWLS system. AR, Tab 6, 26. The contracting officer then turned
to documenting an extensive review regarding the activities
previously performed by Denysys and its subcontractors, and MTC
and its subcontractors, under prior contracts. Id. In this
regard, the contracting officer noted that the TEWLS system is
comprised of software owned by SAP AG and that, in performing
its prior contracts, neither Denysys nor its proposed
subcontractors have been materially involved in development or
customizing the TEWLS system, since that function is performed
by SAP itself; that Denysys and its subcontractors have not had
a role in developing the requirements for the solicitation at
issue; that neither Denysys nor its subcontractors have had
access to any underlying software code configuration for TEWLS;
that neither Denysys nor its subcontractors provided technical
direction for TEWLS; and that neither Denysys or its
subcontractors have been involved in any discussions where
contract sensitive information has been discussed. AR, Tabs 6,
26. Additionally, the contracting officer found that MTC
has had more access to TEWLS‑related information, pursuant to
MTC’s prior contract for sustainment of the URL project, than
Denysys and its subcontractors. AR, Tab 26. Based on the
agency’s review of the offerors’ prior activities, the
contracting officer concluded that Denysys did not have an
unfair competitive advantage in this procurement. We have
reviewed the entire record, including documentation of the
contracting officer’s review and analysis of the offerors’ prior
activities, and conclude that the agency’s review was thorough
and comprehensive; in this regard, MTC has not identified any
material flaw in the agency’s review. Further, we find no basis
to question the agency’s conclusions drawn from its review.
Finally, we view MTC’s protest to be based on an interpretation
of the law which would, in effect, exclude virtually any
government contractor (including MTC in this procurement) from
competing for procurements that in any way relate to the
contractor’s prior contract performance. FAR subpart 9.5 does
not establish such a sweeping exclusionary rule. (MASAI
Technologies Corporation, B-298880.3, B-298880.4, September
10, 2007) (pdf)
The issue here is
whether the agency reasonably considered the awardee’s proposed
mitigation plan. BCA contends that MBI’s plan to move the
affected work from one team member to the other, and imposing a
firewall, does not adequately mitigate the potential OCI. It
contends that MBI’s mitigation plan should have required MBI to
subcontract the work to a firm that was not a team member of the
offeror, like BCA’s mitigation plan did. In cases such as this,
once an agency has given meaningful consideration to potential
conflicts of interest, our Office will not sustain a protest
challenging a determination in this area unless the
determination is unreasonable or unsupported by the record.
Overlook Sys. Techs., Inc., B-298099.4, B-298099.5, Nov. 28,
2006, 2006 CPD para. 185 at 16. In this regard, contracting
officer’s are allowed to exercise “common sense, good judgment,
and sound discretion” in assessing whether a potential conflict
exists and in developing appropriate ways to address it. FAR
sect. 9.505; Epoch Eng’g, Inc., B‑276634, July 7, 1997, 97-2 CPD
para. 72 at 5. Here, the agency conducted extensive discussions
with each offeror about the potential OCIs and the details of
each offeror’s proposed mitigation plan. As a result of these
discussions, the agency reasonably determined the plans to be
“similar.” In this regard, under BCA’s proposal, RER will
subcontract the affected work to a separate entity and establish
safeguards to ensure that RER employees will not work on the
affected transactions. Similarly, under MBI’s proposal, Reznick
will transfer the affected work to a separate entity (MBI) and
establish safeguards to ensure that Reznick’s employees will not
work on these transactions. In evaluating the adequacy of the
plans, the agency considered that both offerors put into place
procedures to identify the affected properties and to ensure
that the conflicted company would not be performing the work on
these properties. AR, Tab 12(B), Final TEP Report, at 19, 68.
The agency also considered whether the affected work could be
performed independently from the conflicted entity in order to
determine whether the safeguards were sufficient. Contracting
Officer’s Statement at 20-21. The agency concluded that MBI
possessed “significant experience and skill” so as to complete
the work independently of Reznick, and that the BCA team
subcontractor was able to perform the work independently of RER.
Id. The agency identified that only a small percentage of loans
(approximately [REDACTED]) could potentially be affected, such
that the proposed mitigation plans could adequately neutralize
the conflict. Id. We have found, in other “impaired objectivity”
OCI situations, that subcontracting or transferring work to a
separate entity, and establishing a firewall around the impaired
entity, can reasonably mitigate these types of OCIs. Deutsche
Bank, B‑289111, Dec. 12, 2001, 2001 CPD para. 210 at 4; see also
Alion Sci. & Tech. Corp., B‑297022.4, B‑297022.5, Sept. 26,
2006, 2006 CPD para. 146 at 10; Epoch Eng’g, Inc., supra, at 6.
Given that the agency thoroughly considered the parties’
potential OCIs and proposed mitigation plans, we find
unobjectionable the agency’s determination that MBI’s mitigation
plan adequately mitigated the potential OCI. (Business
Consulting Associates, LLC, B-299758.2, August 1, 2007) (pdf)
The situations in which OCIs arise, as addressed in FAR subpart
9.5 and the decisions of our Office, can be broadly categorized
into three groups: biased ground rules, unequal access to
non-public information, and impaired objectivity. Contracting
officers must exercise “common sense, good judgment, and sound
discretion” in assessing whether a potential conflict exists and
in developing appropriate ways to resolve it; the primary
responsibility for determining whether a conflict is likely to
arise, and the resulting appropriate action, rests with the
contracting agency. FAR sect. 9.505; Science Applications Int’l
Corp., B-293601.5, Sept. 21, 2004, 2004 CPD para. 201 at 4. Once
an agency has given meaningful consideration to potential
conflicts of interest, our Office will not sustain a protest
challenging a determination in this area unless the
determination is unreasonable or unsupported by the record.
Science Applications Int’l Corp., supra. As relevant to the
protester’s allegations, a biased ground rules OCI arises where
a firm, as part of its performance of a government contract, has
in some sense set the ground rules for the competition for
another government contract by, for example, writing the SOW or
the specifications. In these cases, the primary concern is that
the firm could skew the competition, whether intentionally or
not, in favor of itself. FAR sections 9.505-1, 9.505-2. An
unequal access to nonpublic information OCI arises where, as
part of its performance of a government contract, a firm has
access to information that may provide the firm an unfair
competitive advantage in a later competition for a government
contract. FAR sect. 9.505-4. With regard to the
protester’s claim of a biased ground rules OCI, the protester
alleges that, as the contractor for the GSA and NIH contracts
discussed above, Enspier may have had a role in drafting the
SOW. The agency states that Mitretek Systems, the incumbent
contractor for the FPKIA services that are the subject of this
procurement, was the entity that assisted the government in
developing the SOW, and that Enspier played no role in drafting
or developing the SOW. AR, at 6; Contracting Officer’s Statement
at 1. The protester fails to identify any information in the
record that demonstrates that Enspier played a role in
developing or drafting the SOW, and thus does not rebut the
agency’s specific statement that Enspier had no such involvement
with the SOW. In this regard, substantial facts and hard
evidence are necessary to establish a conflict; mere inference
or suspicion of an actual or apparent conflict is not enough.
Snell Enters., Inc., supra, at 4. With regard to the
protester’s claim of an unequal access to information OCI, the
protester alleges that Enspier may have had access to non-public
information that provided the awardee an unfair competitive
advantage in the competition. Specifically, the protester
contends that the positions held by Enspier under the GSA and
NIH contracts suggest that that firm may have had access to
non-public information. Although the agency report contained the
SOWs for Enspier’s contracts, and the record further describes
the activities of Enspier under those contracts, the protester
is unable to identify any specific examples of non-public
information that would have provided an unfair competitive
advantage to the awardee in the competition. Furthermore, as
discussed above, the activities performed by Enspier under the
NIH contract in support of the FPKIA were generally secretarial
in nature, and the work for GSA under the E-Authentication
contract pertained to the performance of validation work that
relied on publicly-available FPKIA documentation for the two
lower-tier levels of authentication, not the two higher-level
levels that are the subject of this RFQ. The protester argues
that certain publicly-available documents which were either
prepared by Enspier or refer to Enspier suggest that that firm
may have had access to non-public information. For example, the
protester argues that a publicly-available document titled
“Technical Approach for the Authentication Service Component,”
AR, Exh. 32, supports ORC’s protest to the extent that an
Enspier employee is listed as the “author” of the electronic
file. The agency explains, however, that this document is merely
a recitation of public information regarding PMO polices.
Further, even assuming that an Enspier employee was the drafter
of this document, the protester does not identify any non-public
information that might have been used in its creation, nor does
the protester suggest how any such information could have given
Enspier an unfair competitive advantage in the competition. In
sum, the protester has not provided support for its assertion
that the award to Enspier was tainted by an OCI. (Operational
Resource Consultants, Inc., B-299131.1; B-299131.2, February
16, 2007) (pdf)
Our role, within the confines of a bid protest, is to determine
whether any action of the former government employee may have
resulted in prejudice for, or on behalf of, the awardee during
the award selection process. See Creative Mgmt. Tech., Inc.,
B‑266299, Feb. 9, 1996, 96-1 CPD para. 61 at 7. Specifically, we
review whether an offeror may have prepared its proposal with
knowledge of inside information sufficient to establish a strong
likelihood that the offeror gained an unfair competitive
advantage in the procurement. PRC, Inc., B‑274698.2, B-274698.3,
Jan. 23, 1997, 97-1 CPD para. 115 at 19-20. Our review includes
consideration of whether the former government employee had
access to competitively useful information, as well as whether
the individual’s activities with the firm likely resulted in
disclosure of such information. Id. An individual’s familiarity
with the type of work required under a solicitation from prior
government employment is not, by itself, evidence of an unfair
competitive advantage. Id. Consistent with our finding in the
Philadelphia case, we conclude here that, even if this
individual’s prior employment with DeCA had given him access to
inside information regarding the agency’s initial produce
procurements, it appears much, if not all, of the alleged inside
information has in fact been shared with the produce industry
through the agency’s informational roundtables, and thus cannot
be characterized as inside information. The agency reports that
the current solicitation was issued without this individual’s
assistance and that material differences exist in each of its
Area produce procurements; here, for instance, the contractor
faces additional challenges in terms of warm climate conditions
and, in some locations, harsh terrain, as well as ensuring
produce delivery to the commissaries in Hawaii. As we noted in
the Philadelphia decision, the consultant signed a
non-disclosure agreement certifying that he would not disclose
contractor or source-selection information that he may have
learned as an evaluator. Moreover, as in that case, there is no
indication in this record that the awardee’s proposal was
prepared based on any inside information. Both the consultant
and the awardee deny that any communication involving inside
information took place. The awardee is an experienced federal
government contractor that prepared its own proposal for
additional work at numerous commissaries that it already
successfully serves. The awardee reports that the consultant did
not write the proposal, but was asked to review it prior to its
submission. The awardee and the consultant affirm that the
consultant’s suggestions were editorial in nature, including
general suggestions to provide additional detail, to identify
the proposal as containing proprietary information, to describe
workforce and activities, and to make assorted style/format
changes for consistency. This advice does not suggest the use of
inside information, or, for that matter, any information that
could reasonably be found to have provided an unfair competitive
advantage to this experienced firm. Rather, the record here
shows that the awardee’s favorable evaluation was based on the
strength of the firm’s established business operations and
experience, described in its comprehensive technical proposal.
Accordingly, we have no reason to question the propriety of the
awards. (OK Produce; Coast Citrus
Distributors, B-299058; B-299058.2, February 2, 2007) (pdf)
Our role, within the confines of a bid protest, is to determine
whether any action of the former government employee may have
resulted in prejudice for, or on behalf of, the awardee during
the award selection process. See Creative Mgmt. Tech., Inc.,
B-266299, Feb. 9, 1996, 96-1 CPD para. 61 at 7. Specifically, we
review whether an offeror may have prepared its proposal with
knowledge of inside information sufficient to establish a strong
likelihood that the offeror gained an unfair competitive
advantage in the procurement. PRC, Inc., B‑274698.2, B-274698.3,
Jan. 23, 1997, 97-1 CPD para. 115 at 17. Our review includes
consideration of whether the former government employee had
access to competitively useful information, as well as whether
the individual’s activities with the firm likely resulted in
disclosure of such information. Id. Here, the record shows
that, while he worked for DeCA, the consultant participated in
preliminary market research and strategy planning with his
supervisors who were coordinating the conversion of operations
from DSC-P, and that he was an agency spokesperson for the
agency’s two industry roundtables. However, it is clear that
those roundtables were held for the purpose of releasing to the
public for industry comment, at least in summary form, research
and planning information gathered by the agency. Specifically,
the agency not only discussed its market research and its plan
to change its produce business model, but also released to the
substantial number of vendors in attendance the terms of its
recent test program and follow-on procurement for the provision
of produce to Area 1 commissaries. The record thus shows that at
least much of the preliminary research known to the consultant
was in fact shared with other vendors and thus cannot be
characterized as inside information. As for the current
solicitation, the agency reports that the individual did not
assist in the preparation or development of the source selection
plan or the solicitation, which was issued almost 4 months after
his retirement from the government. Additionally, the agency
points out that there are differences in the terms of the
solicitation compared to the prior procurement the former
government employee participated in as an evaluator (where he
reviewed two initial technical proposals, but had no access to
price proposals). For instance, the previous solicitation
included a requirement for port delivery of produce for
commissaries in Keflavik, Iceland and Guantanamo Bay, Cuba
(including meeting airlift times and sailing dates); there are
no such requirements in the RFP for the Area 3, Group 2 award at
issue here. While we recognize that the prior and current
solicitations share similar general provisions regarding the
basic performance requirement here--delivering quality produce
to commissaries at competitive prices--the differences between
the two solicitations suggest that the information to which the
consultant had access during the prior procurement might be of
limited value in the current procurement. In any event, even
assuming that the consultant’s participation in the prior
procurement gave him access to inside information, the
consultant signed a non-disclosure agreement certifying that he
would not disclose contractor or source-selection information
that he may have learned as an evaluator, and we see no basis in
the record here to conclude that the Four Seasons proposal was
prepared based on such information. Rather, the record shows
that upon his retirement, the consultant was advised by the
agency ethics officer that offering his services as a commissary
produce consultant would be unobjectionable as long as inside
information was not used; that he relayed that information to
his client, Four Seasons; that Four Seasons confirmed the
accuracy of the restriction with the DeCA ethics officer; and
that both the consultant and the awardee deny that any
communication involving inside information took place. Our
conclusion is further supported by the responses received to our
inquiries as to the type of assistance rendered by the
consultant. The record shows that Four Seasons, a commercial
produce vendor with limited experience in contracting with the
federal government, specifically hired another consultant (a
professional federal government contract proposal writer)--not
the consultant at issue in the protest--to work closely with the
firm to prepare its proposal. The role of the consultant at
issue here was limited to the review of that proposal; the
record shows, for instance, that he made suggestions of
editorial and style changes to the proposal related to achieving
clarity and compliance with the RFP instructions calling for
offerors to provide details regarding their capabilities,
approaches, and accomplishments; this advice suggests no use of
inside information. (Philadelphia
Produce Market Wholesalers, LLC, B-298751, December 8, 2006)
(pdf)
With regard to the conflict of interest issues, Maden first
contends that BAI had an “unfair competitive advantage” due to
the fact that Robert Copeland, the director of SID, is a former
BAI employee and supervised two of the evaluators who
participated in the procurement. Maden further alleges, based on
“information and belief,” that Mr. Copeland or other DARPA
employees granted BAI “special access” to the project site prior
to the award of the contract. Maden also argues that DARPA
failed to properly consider the fact that BAI had an unfair
advantage due to its teaming with Marianne Carter; according to
Maden, Ms. Carter had worked as an evaluator for DARPA on a
previous procurement wherein Maden had submitted a proposal and
thus had access to Maden’s “proprietary information.”
Maden’s argument that BAI’s teaming arrangement with Marianne
Carter presented an organizational conflict of interest (OCI)
which should have resulted in BAI’s exclusion from the
competition, is similarly unsubstantiated and without merit.
Contracting officers are required to identify and evaluate
potential OCIs as early in the acquisition process as possible,
and to avoid, neutralize, or mitigate potential significant
conflicts of interest so as to prevent an unfair competitive
advantage or the existence of conflicting roles that might
impair a contractor's objectivity. Federal Acquisition
Regulation (FAR) sections 9.504(a); 9.505. OCIs, as addressed in
FAR subpart 9.5 and the decisions of our Office, can be broadly
categorized into three groups. The first group consists of
situations in which a firm, as part of its performance of a
government contract, has in some sense set the ground rules for
the competition for another government contract by, for example,
writing the statement of work or the specifications. FAR sect.
9.505-2; Aetna Gov’t Health Plans, Inc.; Found. Health Fed.
Servs., Inc., B-254397.15 et al., July 27, 1995, 95-2 CPD
para.129 at 13. The second group, which Maden alleges is
relevant in this case, consists of “unequal access to
information” situations in which a firm has access to nonpublic
information as part of its performance of a government contract
and where that information may provide the firm an unfair
competitive advantage in a later competition for a government
contract. FAR sect. 9.505-4; Aetna Gov’t Health Plans, Inc.;
Found. Health Fed. Servs., Inc., supra, at 12. The third group
reflects concerns about a firm’s “impaired objectivity” and
comprises cases where a firm’s work under one government
contract could entail its evaluating itself or a related entity,
thus undermining the firm’s ability to render impartial advice
to the government. FAR sect. 9.505-3; Aetna Gov’t Health Plans,
Inc.; Found. Health Fed. Servs., Inc., supra, at 13. As an
initial matter, in addressing this issue, we note that Maden
fails to describe the nature of the prior procurement in which
DARPA utilized the services of Ms. Carter as an evaluator, nor
does Maden explain how the “proprietary information” it provided
in connection with that procurement could have provided BAI with
an advantage under the current solicitation. In any event, the
record reflects that the contracting officer recognized the
potential for a conflict resulting from BAI’s use of Ms. Carter
as a subcontractor, given her work as an evaluator on a prior
DARPA procurement, and that he conducted an inquiry into her
involvement in the preparation of BAI’s proposal. Specifically,
he solicited independent statements from both BAI and Ms. Carter
to determine “exactly what information was shared between BAI
and [Carter] and to confirm that no source selection information
or proprietary information was released.” AR, Tab 22, Source
Selection Significant Event, SSP Deviations, and amend. 4
Justification, at 3. Based on the statements received, the
contracting officer was satisfied that Ms. Carter did not
provide any information to BAI on how it should structure its
proposal and found that her participation was limited to the
submission of a subcontract proposal. Moreover, the contracting
officer confirmed that Ms. Carter had signed a non-disclosure
agreement in connection with her services as an evaluator for
DARPA, which prohibited her from disclosing any source selection
or proprietary information she may have obtained while serving
as an evaluator. Upon reviewing the matter with the SSEB
chairperson and agency counsel, the contracting officer
concluded that the “potential OCI was effectively mitigated.”
AR, Tab 22, Source Selection Significant Event, SSP Deviations,
and amend. 4 Justification, at 3-4). Based on this record there
is nothing to support Maden’s contention that BAI should have
been excluded from the competition based on proposing Ms. Carter
as a subcontractor, and Maden has not shown otherwise. (Maden
Technologies, B-298543.2, October 30, 2006) (pdf)
Once an agency has given meaningful consideration to potential
conflicts of interest, our Office will not sustain a protest
challenging a determination in this area unless the
determination is unreasonable or unsupported by the record. SRS
Techs., B‑258170.3, Feb. 21, 1995, 95-1 CPD para. 95 at 9. Here,
Alion’s protest has not identified any material aspect of the
agency’s review and analysis that renders the agency’s
conclusions unreasonable. Specifically, Alion has not identified
any material aspect of ITT’s involvement in producing or
providing spectrum-related products and services that the agency
has overlooked or otherwise ignored. Based on the discussion
above, we believe the agency has reasonably identified the scope
and extent of ITT’s involvement with spectrum-related products
and services, as well as reasonably identified ITT’s competitors
and customers, including foreign governments, that possess
spectrum-related interests. Further, the agency’s consideration
of each particular contract activity listed in the solicitation,
along with consideration of every contract project performed
during the preceding fiscal year, appears to be thorough and
complete. To the extent Alion has expressed disagreement with
various agency judgments regarding the various solicitation
activities and/or performance of particular past projects that
could create OCIs for ITT, Alion’s arguments fail to identify
any material flaws that would render the agency’s overall
conclusions unreasonable. A protester’s mere disagreement with
an agency’s judgment does not establish that the judgment was
unreasonable. See, e.g., Hanford Envtl. Health Found., B-292858,
B-292858.2, Apr. 7, 2004, 2004 CPD para. 164 at 4. On this
record, we find no basis to question the reasonableness of the
agency’s conclusion regarding the portion of contract
requirements that could create OCIs for ITT. (Alion
Science & Technology Corporation, B-297022.4; B-297022.5,
September 26, 2006) (pdf)
The Federal Acquisition Regulation (FAR) instructs agencies to
identify potential OCIs as early as possible in the procurement
process, and to avoid, neutralize, or mitigate significant
conflicts before contract award so as to prevent unfair
competitive advantage or the existence of conflicting roles that
might impair a contractor’s objectivity. FAR sections 9.501,
9.504, 9.505; PURVIS Sys., Inc., B-293807.3, B293807.4, Aug. 16,
2004, 2004 CPD para. 177 at 7. The responsibility for
determining whether a contractor has a conflict of interest and
should be excluded from competition rests with the contracting
officer, who must exercise “common sense, good judgment and
sound discretion” in assessing whether a significant potential
conflict exists and in developing appropriate ways to resolve
it. FAR sections 9.504, 9.505; Aetna Gov. Health Plans, Inc.;
Foundation Health Fed. Servs., Inc., B-254397 et al., July 27,
1995, 95-2 CPD para. 129 at 12. Situations that create potential
conflicts of interest are identified and discussed in FAR
subpart 9.5, and they include situations in which a contractor’s
performance of contract requirements may affect the contractor’s
other activities and interests. See FAR sections 9.505, 9.508.
That is, a contractor’s judgment and objectivity in performing
the contract requirements may be impaired if the substance of
its performance has the potential to affect other activities and
interests of the contractor. Id.; Science Applications Int’l
Corp., B‑293601 et al., May 3, 2004, 2004 CPD para. 96 at 4. We
find that HUD failed to reasonably consider or evaluate the
potential OCI arising due to the fact that the owner of CLF (the
M&M contractor in Ohio) will be receiving payments from the
owner of the closing agent contractor for Ohio, the activities
of which CLF will oversee. Specifically, it appears that CLF’s
judgment and objectivity in performing the contract requirements
could be impaired if its performance could potentially affect
the ability of the owner of the closing agent contractor to make
the payments owed to CLF’s owner. Further, while the contracting
officer was aware of the potential OCI from having CLF’s owner
receive a share of Lakeside Title’s profits, and proceeded
properly to have CLF eliminate that OCI, it is clear that the
contracting officer failed to consider the OCI implications of
the amended version of the purchase agreement--whether the
magnitude of the payments was such as to call into question
whether CLF’s judgment and objectivity were likely to be
impaired, or whether there were suitable mitigation measures
required to address the scope of the potential conflict of
interest. In these circumstances, we sustain the protest on the
basis that HUD failed to reasonably consider or evaluate a
potential OCI that may result from an award to CLF. (Greenleaf
Construction Company, Inc., B-293105.18; B-293105.19,
January 17, 2006) (pdf)
Contracting officers are required to identify and evaluate
potential conflicts of interest as early in the acquisition process as possible. Federal Acquisition Regulation
(FAR) sect. 9.504. The FAR provides that
an OCI exists when, because of activities or relationships with other persons or
organizations, a person or organization is unable or potentially unable to
render impartial assistance or advice to the government. See FAR sect. 2.101. Situations that create potential
OCIs are further discussed in FAR subpart 9.5 and the decisions of our Office;
specifically, what is frequently referred to as an "impaired objectivity" OCI is
created when a contractor’s judgment and objectivity in performing the contract
requirements may be impaired due to the fact that the substance of the
contractor’s performance has the potential to affect other interests of the
contractor.
Id.; PURVIS Sys.,
Inc., B‑293807.3, B‑293807.4, Aug. 16, 2004, 2004 CPD para. 177; Science
Applications Int’l Corp., B‑293601 et al., May 3, 2004, 2004 CPD
para. 96; Aetna Govt. Health Plans, Inc.; Foundation Health Fed. Servs.,
Inc., B‑254397.15 et al.,
July 27, 1995, 95-2 CPD para. 129 at 13. In reviewing this protest, we considered the contract
requirements, as reflected in the solicitation and ITT’s proposed PWS tasks, and
the basis for the agency’s assessment that ITT was likely to experience
impaired-objectivity OCIs only "7.3 percent of the time over the entire contract
effort."
As discussed below, the agency’s assessment regarding the extent and
impact of OCIs with regard to ITT’s contract performance is not reasonably
supported by the record. Overall, as discussed above, the agency
maintains that "an impaired objectivity OCI [is] likely to occur
[for ITT] approximately 7.3 percent of the time over the entire
contract effort." Contracting Officer’s Statement at 16. Based
on our review of the record, discussed above, the agency’s
assessment is not reasonably supported by the record.
Specifically, the aggregate level of effort proposed with regard
to only the PWS tasks discussed above make up more than
[deleted] percent of the total level of effort proposed. Agency
Report, Tab 10. As discussed above, a significant portion of the
activities described under each of the PWS tasks addressed above
involve analysis, evaluation, and subjective judgment with
regard to matters in which DOD, ITT, ITT’s competitors, and
ITT’s customers are likely to have direct, and likely divergent,
interests. Further, in light of the interrelated nature of the
activities both within tasks and between tasks, it does not
appear from the record here that the agency, or ITT, can expect
to meaningfully identify potential conflicts prior to the time
the specific activities are performed, rationally segregate such
conflicted portions of the contract, and successfully perform
those requirements with "firewalled" subcontractors. In short,
the record shows that the agency failed to reasonably identify
and evaluate the extent of OCIs associated with ITT’s
performance of this contract, as well as the effect of potential
OCIs on contract performance. (Alion
Science & Technology Corporation, B-297342, January 9, 2006)
(pdf)
Contracting officers are required to identify and evaluate
potential conflicts of interest as early in the acquisition
process as possible. FAR sect. 9.504. The FAR provides that an
OCI exists when, because of activities or relationships with
other persons or organizations, a person or organization is
unable or potentially unable to render impartial assistance or
advice to the government. See FAR sect. 2.101. Situations that
create potential conflicts are further discussed in FAR subpart
9.5 and the decisions of this Office; specifically, an “impaired
objectivity” OCI is created when a contractor’s judgment and
objectivity in performing a contract’s requirements may be
impaired due to the fact that the substance of the contractor’s
performance has the potential to affect other interests of the
contractor. FAR sections 9.505, 9.508; PURVIS Sys., B-293807.3,
B-293807.4, Aug. 16, 2004, 2004 CPD para. 177; Science
Applications Int’l Corp., B-293601 et al., May 3, 2004, 2004 CPD
para. 96; Aetna Govt. Health Plans, Inc.; Foundation Health Fed.
Servs., Inc., B‑254397.15 et al., July 27, 1995, 95-2 CPD para.
129 at 13. In reviewing this protest, we considered the
description of contract requirements reflected in the
solicitation, as well as the basis for the agency’s conclusion
that “the maximum potential for impaired objectivity OCI
occurrences is 15%” of the total contract requirements. We also
considered the information provided by ITT with its OCI plan,
which included its 2004 annual report, along with other publicly
available information, including information contained on ITT’s
Internet website. The publicly available information we reviewed
leaves no doubt that ITT has multiple financial interests with
regard to manufacturing and marketing of spectrum-dependent
products to the U.S. government, to foreign governments, and to
commercial customers worldwide.[10] Further, ITT’s public
statements make clear that its financial interests and the
success of its company are affected by a variety of factors,
including both domestic and foreign government regulations,
ITT’s ability to continue to win contracts, and ITT’s
development and marketing of new products. Overall, our review
of the record leads us to conclude that the agency’s assessment
of potential impaired-objectivity OCI’s created by ITT’s
performance of the anticipated contract activities is not
adequately supported by the record.[14] Specifically, in light
of the significant spectrum-related interests of ITT, ITT’s
competitors, and ITT’s customers, that may well be affected by
ITT’s contract performance, the agency’s failure to meaningfully
consider the scope and extent of such spectrum-related interests
requires the conclusion that the agency’s assessment of the
“maximum potential” for impaired-objectivity OCIs is not, on the
record here, reasonably supported. In short, the record shows
that the agency failed to reasonably identify and evaluate
potential OCIs associated with ITT’s performance of this
contract and, accordingly, failed to reasonably evaluate the
effect that such OCIs will have on ITT’s contract performance. (Alion
Science & Technology Corporation, B-297022.3, January 9,
2006) (pdf)
As a general rule, OCIs may be broadly categorized into three
situations: impaired objectivity, unequal access to information
and biased ground rules. American Mgmt. Sys., Inc. , B-285645,
Sept. 8, 2000, 2000 CPD 163 at 4. GSS has not articulated which
of the three situations it believes is present here. However, we
find that none applies. The unequal access to information and
biased ground rules situations clearly are not applicable to
this aspect of the protest. In an unequal access to information
situation, there must be some showing that the allegedly
conflicted entity has had access to information not available to
the other competitors, while in a biased ground rules situation
there must be some showing that the entity had an opportunity
(such as in preparing the solicitation) to influence the ground
rules for the competition. Id. Under the third situation,
impaired objectivity, the concern is that, because of the nature
of a firm's actual or potential work under another government
contract, it may be unable to provide objective advice or
judgments to the government. Id. Here, because the CV contractor
is not called upon by the terms of its contract to provide
objective judgments regarding the disposition of property as
useable versus scrap (such judgments are contractually the
responsibility of DRMS), it follows that there can be no issue
of an impairment of LSI's objectivity. In the final analysis,
GSS does not allege that LSI's objectivity will be impaired;
rather, it alleges that, because of the additional potential
profit available under the SV contract, LSI will have an
incentive to act deliberately, in concert with SAV, to maneuver
property offered to SAV under the CV contract to the SV
contract. This amounts to an allegation that LSI may potentially
engage in bad faith in its performance of the two contracts.
However, there simply is no basis to deny a firm an award due to
bad faith that has not occurred but, rather, is a mere
theoretical possibility. (Government
Scrap Sales, B-295585, March 11, 2005) (pdf)
Lucent argues that the contracting officer's OCI determination
was flawed because Lucent did not provide "complete
specifications" for the TETRA devices, as that term is used in
FAR 9.505-2(a). Specifically, Lucent contends that it developed
the specifications in Schedule D in conjunction with the agency,
and that the agency further altered or revised the
specifications in Schedule D when it issued the revised RFP. As
a preliminary matter, the FAR does not define the term "complete
specifications." A reasonable interpretation of the term
suggests that a firm that provides specifications that are
necessary and sufficient to inform the solicitation has provided
"complete specifications." Based on our review of the record, we
agree with the agency that Lucent's Schedule D was the source
for the technical specifications in the revised RFP and that the
specifications provided by Lucent are nearly identical to those
listed in the amended RFP. Compare RFP, Amend. 2, at 3-10 with
AR, Tab 18, Lucent Schedule D. Lucent characterizes its work on
Schedule D as a collaboration with the agency, and thus argues
it did not provide complete specifications. FAR
9.505-2(a)(1)(ii) provides that the OCI exclusion rule does not
apply where contractors prepare specifications under the
supervision and control of government representatives. Lucent's
references to the record do not, however, conclusively establish
that the agency played a joint role in developing the TETRA
device specifications, or one that would rise to the level of
supervision and control by the agency. At best, correspondence
cited by Lucent suggests that the agency was kept apprised of
Lucent's progress on the Schedule D specifications, participated
in some discussions regarding Lucent's development of the
specifications, and provided some comments or feedback prior to
the final version of the specifications. See Protester's
Comments, Exh. 9, E-mail Correspondence Between Agency Technical
Representatives for IRCS Contract and Lucent; id. , Exh. 1, Decl.
of Lucent Technical Manager, at 1; id. , Exh. 2, Decl. of Lucent
Technical Consultant, at 1. The record clearly shows that Lucent
provided technical specifications for the TETRA devices under
IRCS Task Order 2, and that the agency incorporated those
specifications into the revised RFP. (Lucent
Technologies World Services Inc., B-295462, March 2, 2005) (pdf)
In response to our decision, the agency requested, received and
considered additional information regarding Lockheed Martin's
past and ongoing environmentally-regulated activities.
Thereafter, the agency performed and documented an analysis
regarding whether such activities would reasonably affect the
objectivity with which Lockheed Martin will perform the work
contemplated by this contract. In a memorandum dated June 9,
2004, the agency summarized the additional information it had
considered and concluded: "[I]t has been determined that no
actual or potential conflicts of interest exist due to Lockheed
Martin's environmentally-regulated activities in the context of
the entire scope of work to be performed under [this contract]."
Agency Report, Tab 9, Conflict of Interest Analysis Memorandum,
at 2. Despite the agency's assertion that "no . . . potential
conflicts of interest exist," the agency's analysis,
nonetheless, provides that, prior to issuing any task order
under this contract, the agency's project officer will
"ascertain that no [conflicts of interest] exist within the
assigned tasks, or that adequate mitigation strategies are in
place and have been discussed with the contracting officer." Id.
at 8. By letter to our Office dated June 10, with a copy to
SAIC's counsel, the agency stated that, as a result of its
analysis and conclusions, it was proceeding with contract
performance by Lockheed Martin. This protest followed. Here,
notwithstanding the agency's broad assertion that "no . . .
potential conflicts of interest exist," the record clearly
demonstrates that the agency recognizes the potential that
conflicts may arise during contract performance, and has in
place procedures to safeguard against such occurrences. As noted
above, the agency states that, prior to issuing each task order
under this contract, the agency project officer will
independently consider whether that task order's requirements
create a conflict of interest for Lockheed Martin. Specifically,
the project officer will "[either] ascertain that no [conflicts
of interest] exist within the assigned tasks, or that adequate
mitigation strategies are in place and have been discussed with
the contracting officer." Agency's Conflict of Interest
Analysis, June 9, 2004, at 8. In summary, the record establishes
that the agency has requested and received information regarding
Lockheed Martin's environmentally-regulated activities, has
reasonably considered that information in the context of the
solicitation's anticipated requirements, and has accepted
responsibility for performing an independent and ongoing
assessment of potential conflicts of interest each time a task
order is issued. On this record, we deny SAIC's protest that the
agency's corrective actions regarding potential conflicts of
interest were inadequate. (Science
Applications International Corporation, B-293601.5,
September 21, 2004) (pdf) (NOTE:
See B-293601 below)
As noted
above, the solicitation's SOW lists numerous activities that
either expressly or inherently involve analysis, evaluation, and
judgment on the part of the contractor. For example, under the
task area exercise planning and preparation, the SOW establishes
that the contractor is responsible for drafting scenarios to
test specific tactics and recommending settings for mine
simulators. Agency Report, Tab 3, RFP at 80-81 (italics added).
With regard to the task area conducting and observing an
exercise, the contractor is required to present
first-impression reports. Id. at 81 (italics added). Under
the task area exercise reconstruction and analysis, the
contractor is required to conduct in-depth analysis of exercise
data to include detection capability evaluation , sensor
effectiveness assessment, and tactical effectiveness
assessment. Id. at 81 (italics added). Under the task area
program analysis, the contractors responsibilities include
evaluating and comparing data and selecting and analyzing
MOEs [measures of effectiveness]. Id. at 81 (italics added).
Finally, under the task area program intermediary and longrange
planning, the contractor is responsible for assisting the SHAREM
and MIREM officers in devising, presenting and
implementing their 6-year plans. Id. at82 (italics added). We
view all of the above activities as requiring varying amounts of
subjective analysis and judgment on the part of the contractor
that go beyond objectively measuring data. The agency record
regarding the evaluation of Northrop Grumman's proposal further
supports the conclusion that contract performance will
require--and that the agency values--subjective contractor input
and judgment. For example, in evaluating Northrop Grumman's
technical performance plan with regard to the task area,
[deleted], the agency rated Northrop Grumman's proposal
[deleted], specifically noting that, in their proposal,
[deleted]. Agency Report, Tab 36, at6. Similarly, in evaluating
Northrop Grumman's technical performance plan with regard to the
task area [deleted], the agency concluded that Northrop Grumman
specifically proposed [deleted], and further noted that Northrop
Grumman's proposed performance approach includes [deleted]. Id.
at 9. We view the agency's evaluation assessments identified
above as reflecting the agency's expectation--and desire--that
the contractor will provide subjective input and judgment in
performing the contract.
Despite recognizing that Northrop Grumman is the manufacturer of
a significant portion of the systems to be tested and that the
vast majority of the remaining systems are manufactured by
companies with whom Northrop Grumman competes, Northrop Grummans
OCI plan concludes: we have determined that an actual OCI .. .
does not currently exist for the envisioned work to be performed
under the Contract, adding that [m]ature, fielded USW systems in
use in the fleet do not pose an OCI issue. Agency Report, Tab
24, Northrop Grumman OCI Plan, at8. Northrop Grumman's
conclusion that no OCI issues are created by Northrop Grumman's
evaluation of its own mature, fielded systems--or similar
systems manufactured by potential competitors--appears to be
based on the premise that the work performed under this contract
is not part of the procurement process. Even if Northrop
Grumman's assertion, that the work performed and reports
produced under this contract are not part of the procurement
process, was factually accurate--which it is not --we reject
Northrop Grumman's apparent assumption that impaired objectivity
OCIs can arise only within the procurement process. To the
contrary, we view a situation where, as here, a company is
responsible for assessing the performance of systems it has
manufactured as a classic example of an impaired objectivity OCI--without
regard to whether the evaluation occurs as part of the
procurement process. See, e.g. , Engineered Air Sys., Inc.,
supra , at 3 (contract to test and evaluate products that
awardee manufactured was improper). In such situations, the firm
risks having its objectivity impaired by a bias in favor of its
own system's performance. Similarly, a company manufacturing
systems that are, as a practical matter, competing with similar
systems produced by other manufacturers, risks having a negative
bias regarding the performance of the competing systems. This is
particularly true where, as here, the contract requirements
clearly anticipate comparisons between the performance of
similar systems manufactured by competing firms. (PURVIS
Systems, Inc., B-293807.3; B-293807.4, August 16, 2004) (pdf)
As discussed above, the record unambiguously establishes that
the agency gave no consideration to Lockheed’s past and ongoing
performance of environmentally-regulated activities and,
similarly, gave no consideration to the impact those activities
could have on Lockheed Martin’s judgment and objectivity in
performing certain tasks that are reasonably within the scope of
the contract. Our concern with the agency’s failure to consider
the potential conflicts of interest is heightened by the fact
that both the agency and Lockheed Martin are intent on
experiencing substantial “growth” in the contract--increasing
both the volume of tasks to be performed and the customer base
that relies on this contract, specifically expressing the intent
to expand the base to EPA’s “clients” and “partners,” including
“other Federal and state agencies” and “local governments,
contractors, and researchers.” RFP at C-2, C-4; Agency Report,
Tab 4, Lockheed Martin Proposal, at III.2-1. (Science
Applications International Corporation, B-293601;
B-293601.2; B-293601.3, May 3, 2004) (pdf)
We find that TSMO reasonably viewed with concern RAM’s failure
to describe an approach to avoiding OCI issues in the event that
it entered into new, contractual relationships for outside
technical assistance. As asserted by the agency, it was
unreasonable for RAM to assume that it would not need to look
outside the company (and RAM’s pool of surge personnel) for
technical expertise sometime during the potential 15-year period
of the contract. Given the reasonable possibility that RAM would
require recourse to outside technical expertise sometime during
the potential 15-year period of the contract, and given the
possibility that such assistance might carry with it OCI
concerns, it was not unreasonable for the agency to expect that
RAM’s mitigation plan would address the OCI implications of such
an eventuality. However, we also find that the agency failed to
apply the same strict standard in evaluating NGTS’s mitigation
plan as acceptable and its risk as low. In this regard, NGTS’s
OCI plan contemplated a number of possible responses when faced
with a potential OCI, including (depending on the nature of the
potential OCI) [DELETED]. NGTS OCI Plan, attach. 2, at 3-4. TSMO
concluded that OCIs would be rare and that NGTS’s mitigation
plan would effectively eliminate OCIs that did arise. In this
regard, TSMO states that, in the event it is faced with an
actual OCI, it will either, as it has in the past, ask other
military services or the intelligence community to provide
operators, or award a short-term contract to another firm
[DELETED]. Given the availability of operators from other
military services or the intelligence community, TSMO expects to
have to award a short‑term, limited contract for support
services no more than 3-5 times over the potential 15-year
period of the contract. TSMO Comments, Oct. 23, 2003, at 4-5;
Declaration of TSMO Operations Team Leader, Oct. 23, 2003, at
4-6. Even if TSMO reasonably concluded that the OCIs resulting
from award to NGTS could be avoided or mitigated such that award
to NGTS was not precluded, it does not follow that there were no
OCI concerns that had to be reflected in the evaluation, at
least in light of the strict standard applied in evaluating
RAM’s mitigation plan. It is clear from the record that the
agency was fully aware during the evaluation that, in some
limited number of instances, an award to NGTS likely would
require TSMO to proceed outside the terms of NGTS’s contract and
have contract work performed by some other contractor or
government entity. This likely outcome does not appear to have
been factored into the agency’s evaluation of NGTS’s proposal,
despite the agency’s view during its evaluation of RAM’s
proposal that RAM’s failure to plan for a merely potential OCI
warranted downgrading RAM for performance risk. We conclude that
the agency did not evaluate the proposals on an equal basis, and
that the evaluation in this regard therefore was unreasonable.
Symplicity Corp., B‑291902, Apr. 29, 2003, 2003 CPD ¶ 89 at 5. (Research
Analysis & Maintenance, Inc.; Westar Aerospace & Defense Group,
Inc., B-292587.4; B-292587.5; B-292587.6; B-292587.7;
B‑292587.8, November 17, 2003) (pdf)
We have no basis on the record before us to find that [deleted]
has an impaired objectivity OCI. Contrary to TDS's position,
there is nothing inherently improper in a firm's monitoring the
activities of a team member such as Northrop here (or its own
activities); monitoring, standing alone, does not necessarily
create the potential for impaired objectivity. Rather, as noted
above, an impaired objectivity conflict typically arises where a
firm is evaluating its own activities because the objectivity
necessary to impartially evaluate performance may be impaired by
the firm's interest in the entity being evaluated. See Johnson
Controls World Servs., B-286714.2, Feb. 13, 2001, 2001 CPD ¶ 20
at 11-12. While we do not exclude the possibility in a different
context of monitoring activities resulting in an impaired
objectivity OCI, here there is no evidence that [deleted] will
be evaluating the performance of the help desk contractor, and
there is nothing otherwise objectionable in the
interrelationship of activities performed by [deleted] on the
two contracts. Instead, the record shows that the help desk
contractor's performance must at least meet the minimum
standards outlined in the RFQ and that the contracting officer's
technical representative will be responsible for evaluating the
adequacy of the firm's performance for purposes of assessing the
firm's overall performance, deciding whether or not to award
option year requirements, and determining the firm's
compensation under the SLA. SOO at 8-9. We find no indication in
the record--and TDS has not directed our attention to any
information--showing that [deleted] will have any input
whatsoever into the evaluation of the help desk contractor's
performance. Under these circumstances, we have no basis to find
that the awardee, or its subcontractor, has an impaired
objectivity OCI. (TDS, Inc.,
B-292674, November 12, 2003) (pdf)
The situations in which OCIs arise, as addressed in FAR subpart
9.5 and the decisions of our Office, can be broadly categorized
into three groups. The first group consists of situations in
which a firm, as part of its performance of a government
contract, has in some sense set the ground rules for the
competition for another government contract by, for example,
writing the statement of work or the specifications. In these
biased ground rules cases, the primary concern is that the firm
could skew the competition, whether intentionally or not, in
favor of itself. FAR §§ 9.505-1, 9.505-2. These situations may
also involve a concern that the firm, by virtue of its special
knowledge of the agency’s future requirements, would have an
unfair advantage in the competition for those requirements.
Aetna Gov’t Health Plans, Inc.; Found. Health Fed. Servs., Inc.,
B‑254397.15 et al., July 27, 1995, 95-2 CPD ¶ 129 at 13. The
second group consists of “unequal access to information”
situations in which a firm has access to nonpublic information
as part of its performance of a government contract and where
that information may provide the firm an unfair competitive
advantage in a later competition for a government contract. FAR
§ 9.505-4; Aetna Gov’t Health Plans, Inc.; Found. Health Fed.
Servs., Inc., supra, at 12. The third group comprises cases
where a firm's work under one government contract could entail
its evaluating itself or a related entity, either through an
assessment of performance under another contract or an
evaluation of proposals. FAR § 9.505-3. In these “impaired
objectivity” cases, the concern is that the firm’s ability to
render impartial advice to the government could appear to be
undermined by the relationship with the entity whose work
product is being evaluated. Aetna Gov’t Health Plans, Inc.;
Found. Health Fed. Servs., Inc., supra, at 13. As noted by
the protester, while a firewall arrangement may resolve an
“unfair access to information” OCI, it is virtually irrelevant
to an OCI involving potentially impaired objectivity. See Aetna
Gov’t Health Plans, Inc.; Found. Health Fed. Servs., Inc.,
supra, at 16. Likewise, due to the ultimate relationship of one
entity to another, a firewall would not resolve an
organizational conflict of interest involving biased ground
rules. However, the record indicates that the OCI mitigation
approach relied upon by DCC‑W in determining to issue an order
to CACI extended beyond CACI’s proposed firewall. According to
testimony at the hearing our Office conducted in this matter,
the most important feature of the plan was CACI’s proposal to
notify the agency of procurements under which CACI was
interested in competition, which would allow DCC-W to act to
avoid an OCI. Hearing Transcript (Tr.) at 29, 131. Specifically,
contracting officials testified, and the then Acting Director of
Contracting confirmed, that potential OCIs on the part of CACI
would be handled in the same manner where a government employee
has an interest in a matter; CACI contracting specialists would
not be assigned to a procurement for which CACI was expected to
submit an offer or to a CACI contract, and if CACI submitted an
offer for a procurement that already was assigned to a CACI
contracting specialist, the procurement would be reassigned to a
government contracting specialist. Tr. at 32, 37, 39-40, 61-62,
121‑124, 138-40, 148, 183-84, 193, 196-97, 212-13; Agency
Comments, September 4, 2003; Agency Comments, September 5, 2003,
Statements of Contracting Officer and Former Acting Director of
Contracting.[1] As a result, the mitigation approach addresses
the unfair access to information and impaired objectivity OCIs
by ensuring that CACI contracting specialists would not be in
potential conflict positions. (The
LEADS Corporation, B-292465, September 26, 2003) (pdf)
An impaired objectivity OCI exists where a firm’s work under one
government contract could entail its evaluating itself, either
through an assessment of performance under another contract or
an evaluation of a proposal submitted to obtain another
contract. Id. at 13. The concern in such situations is that the
firm’s ability to render impartial advice to the government
could appear to be undermined by its relationship with the
entity whose work product is being evaluated. Id. CUI’s
allegation that Critel will be unable to render impartial
judgments because of conflicting obligations under different
government contracts involves impaired objectivity. We find no
prohibited OCI here. Under its equipment contract, Critel is
required to provide preventative and corrective maintenance and
an inspection system covering the required services, and also
must maintain and make available to the government records of
all inspection work performed. While the IMS contractor is
required to develop a quality assurance program to provide
surveillance of--that is, to monitor--the required scheduled
maintenance, it is not responsible for making judgments as to
what maintenance is required or how well the maintenance is
being performed. We note in this regard that monitoring,
standing alone, does not necessarily create the potential for
impaired objectivity. Rather, as noted above, an impaired
objectivity OCI typically arises where a firm is evaluating its
own (or a related firm’s) activities, because the objectivity
necessary to impartially evaluate performance may be impaired by
the firm’s interest in the entity being evaluated. See Johnson
Controls World Servs., Inc., B‑286714.2, Feb. 13, 2001, 2001 CPD
¶ 20 at 11-12. Since the IMS contractor’s responsibilities are
not based on subjective judgments or evaluations, there is no
basis for finding that the objectivity of the IMS contractor
will be impaired under the circumstances here. Cf. Ktech Corp.,
B-285330, B‑285330.2, Aug. 17, 2002, 2002 CPD ¶ 77 (prohibited
OCI found where subcontractor was to establish requirements for
tests it or its prime contractor would perform). (Computers
Universal, Inc., B-292794, November 18, 2003) (pdf)
Protest that awardee had unfair
competitive advantage due to organizational conflict of interest
is sustained where awardee's proposed subcontractor possessed
information through its work as a government contractor, the
information was not available to other offerors, the agency took
no steps to identify or mitigate the conflict in advance, and
there were no meaningful procedures in place to prevent
interaction between the employees possessing the information and
the employees preparing the proposal. (Johnson
Controls World Services, Inc., B-286714.2, February 13,
2001)
Agency reasonably excluded
protester from participating in procurement where protester has
an organizational conflict of interest arising from its
preparation of the statement of work and cost estimates used by
the agency in the procurement. (SSR
Engineers, Inc., B-282244, June 18, 1999)
An offeror may not have an
unfair competitive advantage over other competitors and, in
order to protect the integrity of the procurement system, an
agency may go so far as to exclude an offeror from the
competition because of the likelihood that it has obtained an
unfair competitive advantage. See Compliance Corp., B-239252,
Aug. 15, 1990, 90-2 CPD ¶ 126 at 5; Holmes and Narver Servs.,
Inc./Morrison-Knudson Servs., Inc., a joint venture; Pan Am
World Servs., Inc., B-235906, B-235906.2, Oct. 26, 1989, 89-2
CPD ¶ 379 at 8. In seeking competition, however, an agency is
not required to construct its procurements in a manner that
neutralizes the competitive advantage that some potential
offerors may have over others by virtue of their own particular
circumstances, such as prior or current government contracts,
where the advantages did not result from unfair motives or
action on the part of the government. See MCA Research Corp.,
B-276865, July 29, 1997, 97-2 CPD ¶ 33 at 2-3; Optimum Tech.
Inc., B-266399.2, Apr. 16, 1996, 96-1 CPD ¶ 188 at 7; Validity
Corp., B-233832, Apr. 19, 1989, 89-1 CPD ¶ 389 at 6; Ross
Bicycles, Inc., B-217179, B-217547, June 26, 1985, 85-1 CPD ¶
722 at 3. EDI has failed to establish that an unfair competitive
advantage existed here. (Electronic
Design, Inc., B-279662.5, May 25, 1999) |