|
1. Measurably Substantial Benefits
NEI argues that the Coast Guard’s bundling analysis is flawed in
several respects. The protester first argues that the Coast
Guard’s reliance on the Navy’s bundling justification is not
reasonable because the Coast Guard did not adequately explain
why it can expect the same efficiencies for the WHEC cutters the
Navy claimed for its destroyers. The protester further argues
that the Coast Guard unreasonably assumes that it will
experience the same level of savings as the Navy, and thus the
assumption of a similar 5.29 percent savings is not reasonable.
Our review of the Coast Guard analysis shows that the agency
does not directly compare the details of its maintenance and
repair operations to the Navy’s operations. Instead, the
analysis focuses on the benefits of adopting the phased
maintenance model to address inefficiencies in the current
practice of making single-contract awards. See AR, Tab 27,
Bundling Analysis, at 3-4. Based on our review, we think the
Coast Guard’s approach of identifying similar problems and
adopting similar solutions to those identified and adopted by
the Navy, was reasonable. Furthermore, the Coast Guard’s
analysis did not assume, as the protester argues, that the same
precise savings will result. Rather, the analysis relied on the
combination of the projected cost savings as well as other
benefits, discussed below, to conclude that the overall benefit
to the government would exceed 10 percent of the value of the
contract. See id. at 4. On this record, we believe that the
Coast Guard’s reliance on the Navy data was reasonable.
Next, NEI argues that the Coast Guard’s use of the Navy’s data
resulted in a double counting of “savings” by relying on both
the 5.29 percent cost savings and the 18 percent reduction in
the length of maintenance availabilities. The protester
correctly notes that the Navy’s justification relied on the 18
percent reduction in the length of maintenance availabilities as
a contributing factor to the overall 5.29 percent cost savings,
and argues that it would not be appropriate to conclude that a
transition by the Coast Guard to the phased maintenance model
would result in both a 5.29 percent cost savings plus an
additional 18 percent cost savings. The Coast Guard’s
justification did not, however, rely on the Navy’s data in this
way. Instead, as discussed below, while the 18 percent reduction
in maintenance time was a component of the 5.29 percent cost
savings for the Navy, it was also separately relied upon by the
Coast Guard as a basis to conclude that the WHEC cutters would
be available for more operational time. The Navy’s bundling
justification for the destroyers did not attempt to quantify the
benefit to the government from having additional operational
time for the ships as a result of the decreased length of
maintenance availabilities. Instead, the 18 percent savings in
the Navy’s analysis represented costs saved by avoiding 2 weeks
of maintenance costs; these savings were thus a component of the
overall 5.29 percent savings anticipated by the Navy. See AR,
Tab 22, Navy Small Business Justification, at 17. The
Coast Guard, however, chose to use the Navy’s data to quantify
an additional benefit to the government from the increased
operational time for the WHEC cutters. The Coast Guard’s
analysis notes that although the Navy was “reluctant to quantify
the benefits of returning a ship to operational status sooner,”
the agency believed that “the benefits to [the] Coast Guard of
increasing the available operational time for WHEC’s can be
quantified.” CO Statement para. 46. In this regard, the
intention of the new acquisition strategy was based on the
“central goal of reducing the period of time for performance of
maintenance tasks,” and thereby increasing “the number of days
that the WHEC’s are available to perform national defense and
homeland security missions.” Id. Thus, this benefit, although
quantified, was not a calculation of “cost savings.” Put
differently, the Coast Guard’s justification relied on two
different benefits to the government: decreased maintenance and
repair costs (quantified as a savings of 5.29 percent), and
increased time that the WHEC cutters will be performing their
duties (18 percent more time). The Coast Guard’s
identification of two benefits is consistent with the FAR, which
states that measurably substantial benefits “may include,
individually or in any combination or aggregate, cost savings or
price reduction, quality improvements that will save time or
improve or enhance performance or efficiency, reduction in
acquisition cycle times, better terms and conditions, and any
other benefits.” FAR sect. 7.107(b). NEI’s argument thus
incorrectly characterizes the Coast Guard’s identification of
benefits as a double-counting of “anticipated savings.”
Protester’s Comments on AR at 22. The two benefits identified by
the Coast Guard are, however, distinct, and each is an
appropriate measure under the FAR. We find no basis on this
record to challenge the reasonableness of the Coast Guard’s
determination.
Finally, NEI argues that the agency inappropriately relied on
the “reimbursable” rate of $178,488 per day to quantify the
benefit to the government from increased operational time of the
WHEC cutters. COMDIST 7310.1I states that the components of the
reimbursable rate “should not be used to calculate reimbursement
for [the Federal Emergency Management Agency] and foreseeable
costs related to contracting actions,” because the rate contains
“both fixed and variable components.” AR, Tab 27, COMDIST
7310.1I, at 2. Instead, the COMDIST states that “[r]ates for
these purposes shall be promulgated separately.” Id. As noted in
the facts above, the agency did separately promulgate rates for
“variable and foreseeable costs” for the cutters of $39,384 per
day. See AR, Tab 27, Coast Guard Variable Rate FY 06 Cost
Tables, encl. 1. The Coast Guard’s bundling analysis
calculated the benefit to the government of increased
operational time for the cutters based on the full reimbursable
rate of $178,488 per day. AR, Tab 27, Bundling Analysis at 4.
However, the analysis also noted that using the lower variable
rate still results in measurably substantial benefits to the
government that justifies bundling. AR, Tab 27, Bundling
Analysis, at 3. Thus, the analysis concludes, that even the rate
of $39,384 per day yields a benefit to the government of
$2,363,040--approximately 20 percent of the estimated contract
value. Although the protester only challenges the agency’s
reliance on the $178,488 per day rate, rather than the $39,384
rate, we think that neither of these rates on their own is a
reasonable measure of the benefit to the government for 1 day of
use of a WHEC cutter. In this regard, the variable rate
represents costs that the government will avoid during a
maintenance availability, such as fuel. See CO Statement para.
48; AR, Tab 27, Coast Guard Variable Rate FY 06 Cost Tables,
encl. 1. Thus, the variable rate of $39,384 per day represents
costs avoided, rather than the increased benefit to the
government from an additional day of operation for a cutter.
During the course of this protest, the CO conceded a better
calculation of the benefit to the government is achieved by
subtracting the variable rate from the full reimbursable rate.
CO Statement para. 48. Thus, in the CO’s view, the benefit to
the government of an increased day of use for a cutter is
$178,488 per day, less the variable costs of $39,384. Id. We
think that this approach appears reasonable because it captures
the quantifiable benefit to the government from the operation of
ship, less the costs of operation. Further, this approach is
consistent with COMDIST 7310.1I, which states that the
reimbursable rate should not be used to calculate foreseeable
costs relating to contracting actions because of its inclusion
of both fixed and variable costs. AR, Tab 27, COMDIST 7310.1I,
at 2. This calculation of a benefit to the government falls
between the two calculations cited in the Coast Guard’s bundling
analysis, but in any event well exceeds 10 percent of the value
of the contract. Id.
In sum, we conclude that even if the consolidation of the dry
dock and dockside requirements constituted bundling under the
Small Business Act, the Coast Guard reasonably justified any
such bundling by identifying measurably substantial benefits to
the government from the consolidation. Even allowing for some
margin of error in adopting the Navy’s estimates, the record
supports the Coast Guard’s determination that the consolidation
of the requirements will result in measurably substantial
benefits to the government equal to at least 10 percent of the
anticipated contract value.
B. Bundling in Violation of CICA
NEI argues that even if the Coast
Guard’s approach of consolidating the maintenance and repair
services does not violate the Small Business Act’s prohibitions
on bundling, the solicitation violates CICA’s prohibition on
improperly consolidating requirements. CICA generally requires
that solicitations permit full and open competition and contain
restrictive provisions and conditions only to the extent
“necessary to satisfy the needs of the executive agency.” 41
U.S.C. sect. 253a(a)(2)(B). Since bundled or consolidated
procurements may combine separate, multiple requirements into
one contract, they have the potential for restricting
competition by excluding firms that can furnish only a portion
of the requirement. Aalco Forwarding, Inc., et al., B-277241.12,
B-277241.13, Dec. 29, 1997, 97-2 CPD para. 175 at 6. In
interpreting CICA, we have looked to see whether an agency has a
reasonable basis for its contention that bundling is required,
and we have sustained protests only where no reasonable basis is
demonstrated. Phoenix Scientific Corp., B-286817, Feb. 22, 2001,
2001 CPD para. 24 at 10.
Here, the agency concluded that the combination of the dockside
and shipside maintenance and repair work will result in
measurably substantial benefits to the government. As discussed
above, we conclude that these benefits, including maintenance
and repair cost savings and increased operational time for the
WHEC cutters based on reduced duration of maintenance
availabilities, justified bundling under the Small Business Act.
In our view, these benefits also provide a reasonable basis to
justify the consolidation of the two requirements for purposes
of CICA. See Teximara, Inc., B-293221.2, July 9, 2004, 2004 CPD
para. 151 at 8-9. (Nautical
Engineering, Inc., B-309955, November 7, 2007) (pdf)
The protesters
first contend that this requirement violates the bundling
restrictions under the Small Business Act, and that the agency
failed to conduct appropriate market research to show that the
bundling was necessary; failed to reasonably justify the
bundling of requirements; and failed to timely notify the Small
Business Administration (SBA) of its decision to bundle the
requirements and provide a statement regarding its justification
for bundling. In response, the agency explains that the TMSS
routinely has been purchased as a packaged system under the
earlier DLA contract. The agency further explains that the TMSS
components cannot be purchased separately in a cost effective
manner but rather, must be procured as an integrated package.
The agency states that its market research consisted of
reviewing vendors’ literature, pamphlets, specifications, and
face-to-face briefings/meetings, as well as observing and
discussing vendors’ evolving capabilities and products at
exhibitions, symposiums, and trade shows. The agency also argues
that any challenge to bundling in this solicitation is untimely.
The Small Business Reauthorization Act of 1997, Pub. L. No.
105-135 (1997), provided that “to the maximum extent
practicable,” each agency shall “avoid unnecessary and
unjustified bundling of contract requirements that precludes
small business participation in procurements as prime
contractors.” 15 U.S.C. sect. 6319 (j)(3) (2000). Bundling, for
purposes of the Act means “consolidating 2 or more requirements
for goods or services previously provided or performed under
separate smaller contracts that is likely to be unsuitable for
award to a small-business concern.” 15 U.S.C. sect. 632(o)(2);
see FAR sect. 2.101. “Separate smaller contract . . . means a
contract that has been performed by 1 or more small business
concerns or was suitable for award to 1 or more small business
concerns.” 15 U.S.C. sect. 632(o)(3); see FAR sect. 2.101. Our
review of the record here shows that the SICPS/TMSS is currently
being purchased as a packaged system under a DLA contract with
DHS, and that the system has not been provided under separate
smaller contracts. Further, the record shows that the SBA and
the Small and Disadvantaged Business Utilization Specialist
agreed that this requirement was not suitable for award to 1 or
more small business concerns. Accordingly there is no
“consolidation” of two or more requirements in this procurement
as contemplated by the Small Business Act and the Small Business
Act requirements pertaining to bundling are therefore not
applicable here.
The protesters also argue that this solicitation represents an
improperly bundled or total package procurement in violation of
the Competition in Contracting Act of 1984 (CICA). 10 U.S.C.
sect. 2305 (a)(1) (2000). The protesters maintain that the Army
has consolidated these requirements for no reason other than
convenience, which, the protesters argue is not a sufficient
rationale for bundling. The reach of the restrictions against
total package or bundled procurements in CICA is broader than
the reach of restrictions against bundling under the Small
Business Act, Phoenix Scientific Corp., B-286817, Feb. 22, 2001,
2001 CPD para. 24 at 9-10. Specifically, CICA generally requires
that solicitations include specifications which permit full and
open competition and contain restrictive provisions and
conditions only to the extent necessary to satisfy the needs of
the agency. See 10 U.S.C. sections 2305(a)(1)(A), (B). Because
procurements conducted on a bundled or total package basis can
restrict competition, we will sustain a challenge to the use of
such an approach where it is not necessary to satisfy the
agency’s needs. Better Serv., B-265751.2, Jan. 18, 1996, 96-1
CPD para. 90 at 2. The determination of a contracting agency’s
needs and the best method for accommodating them are matters
primarily within the agency’s discretion. Specialty Diving,
Inc., B-285939, Oct. 16, 2000, 2000 CPD para. 169 at 3. Of
particular relevance here, where a requirement relates to
national defense or human safety, an agency has discretion to
define the solicitation requirements to achieve not just
reasonable results, but the highest possible reliability and
effectiveness. Tucson Mobilephone, Inc., B-250389, Jan. 29,
1993, 93-1 CPD para. 79 at 5, aff’d, B-250389.2, June 21, 1993,
93-1 CPD para. 472. The Army states that the SICPS/TMSS is a
mission critical system. CO’s Rebuttal Comments at 1- 3. It is
currently fielded for troops in Iraq and Afghanistan to provide
a quick and easy way to establish temporary battlefield
communication centers. Military commanders use these centers to
issue instructions and warn soldiers of approaching dangers.
Moreover, the agency explains that untested, unsafe, or
incompatible systems could cause delays and risks. As a result,
the Army contends it needs to be certain these items will
perform as a system, rather than as a collection of separate
parts. While the protesters disagree with the Army’s need for
the proven integration and compatibility of these systems, we
think the agency has met its burden of showing a reasonable need
for buying these items as a total system. We also see nothing
unreasonable in the Army’s rejection of the protesters’
contention that the agency could enter into a separate
integration contract. The Army responds that having a separate
contract for an additional company to integrate all the separate
components would not be time or cost effective, and that the
Army would run the risk of not being able to procure enough
systems in the event of a surge requirement. (Outdoor
Venture Corporation; Applied Companies, B-299675; B-299676,
July 19, 2007) (pdf)
When a proposed acquisition involves bundled requirements,
the agency must first conduct market research to determine
whether the bundling is necessary and justified, given the
potential impact on small business participation, by
ascertaining whether the government will derive measurably
substantial benefits from the bundling and quantifying these
benefits. FAR sect. 7.107(a), (b). In addition, the agency must,
at least 30 days before issuing a solicitation, provide its
acquisition package to the SBA procurement representative for
review and also provide a statement why the (1) proposed
acquisition cannot be divided into reasonably smaller lots for
small businesses, (2) delivery schedules cannot be established
that will encourage small business participation, (3) proposed
acquisition cannot be structured so to make it likely that small
businesses can compete for the prime contract, (4) consolidated
construction project cannot be acquired as separate discrete
projects, or (5) bundling is necessary and justified. FAR sect.
19.202-1(e). Furthermore, within the same 30 days, an agency
must notify any affected incumbent small business concerns of
the Government’s intention to bundle the requirement. FAR sect.
10.001(c)(2). However, the agency argues that FAR sections
7.107(a), (b); 10.001(c)(2); and 19.202-1 do not apply to the
task orders or the BPA issued under Sverdrup’s FSS contract
because these provisions applying bundling rules to FSS
contracts were implemented after TACOM had completed the
development of its acquisition plan. The requirements that
agencies perform a bundling analysis and notify the SBA when
requirements are bundled were specifically made applicable to
BPAs and orders placed against FSS contracts by a Federal
Register notice published October 20, 2003, with an "effective
date" of October 20, 2003. 68 Fed. Reg. 60,000 (Oct. 20, 2003);
FAR sect. 8.404(a). The FAR states that "[u]nless otherwise
specified . . . FAR changes apply to solicitations issued on or
after the effective date of the change.” FAR sect. 1.108(d)(1).
Since the solicitation that led to the award of the BPA was not
issued until December 5, 2003, which was after the effective
date of the revised bundling regulations, the agency was
required to comply with these regulations, even though at the
time the Army finished its acquisition planning the regulations
had not gone into effect. The Army next argues that these FAR
bundling requirements do not apply because the SETA services
previously performed by Sigmatech were not bundled with the
other requirements and were merely a “follow on” to the Camber
contract. However, the record shows that, for the past 15 years,
the SETA services for the RSJPO have been provided by small
businesses (including Sigmatech) under AMCOM contracts. These
services were not, as the agency contends, a “follow on” to the
Camber contract previously issued by TACOM because, although
SETA services were provided under the Camber contract, this
support for the RSJPO was not provided by Camber. Even after the
RSJPO came under the control of TACOM, the Army still procured
the RSJPO services from small businesses through the AMCOM
contracts and BPAs for example, through exercising options under
the ID/IQ contract as recently as 2004 (with performance into
2005) and through the BPA issued to Sigmatech in 2004, all as
part of small business reserves. Thus, the inclusion of the
RSJPO SETA services in Sverdrup’s BPA is a consolidation of two
or more procurement requirements that were previously performed
by small businesses under separate, smaller contracts. We also
find that the procurement appears to result in a single contract
(the Sverdrup BPA and resulting task orders) that is unsuitable
for award to small businesses due to its size and the aggregate
dollar amount of the anticipated award. In this regard, the
estimated contract value is approximately $130 million over a
5‑year period and only two large businesses (and no small
businesses) responded to the RFQ that resulted in the BPA award.
We thus conclude, under these circumstances, that the
consolidation of the SETA services for the RSJPO under the
Sverdrup BPA meets the definition of bundling under the Small
Business Act. However, the record shows that the Army failed to
perform a bundling analysis as required by FAR sect. 7.107(a),
(b), or comply with the requirements of FAR sect. 19.202-1 in
providing notice of bundling to the SBA. The record further
shows that the agency failed to provide notice to Sigmatech (the
incumbent small business concern) of its intent to bundle the
requirements and thus failed to comply with FAR sect.
10.001(c)(2). We sustain the protest on these bases. (Sigmatech,
Inc., B-296401, August 10, 2005) (pdf)
Although DLA initially identified 3,431 NSNs as F404 consumable
parts to be covered under the contract, DLA has since determined
that 665 of those NSNs were already being provided under a
separate Navy PBL contract, leaving 2,766 NSNs for which the
contractor will provide logistical support services. Of those,
DLA indicates that it will source and supply 312 "mainly
competitive small business NSNs," for which General Electric
will supply only logistical support, leaving 2,454 NSNs for
which General Electric will provide logistical support,
sourcing, and supply. CO Statement at 11. The record shows that
prior to proceeding with the solicitation, DLA fulfilled its
obligation to seek the views of the Small Business
Administration (SBA), through its procurement center
representative, regarding the anticipated bundling. See 15 U.S.C.
Section 644 (2000); FAR Section 7.107. Initially the SBA
objected to the bundling as unjustified, and pursued an appeal
to reverse the bundling. Ultimately, however, the SBA withdrew
its appeal and agreed to the bundling with certain conditions
intended to promote and preserve small business participation
for these parts, which were memorialized in writing between the
SBA and DLA. AR, Tab 14, Defense Department Form 70, at 2. (B.
H. Aircraft Company, Inc., B-295399.2, July 25, 2005) (pdf)
We find that there is no improper bundling here. Where there is
a consolidation of two or more agency requirements, the Small
Business Act, as amended, requires that agencies avoid bundling
them together where the result would be a single contract that
is likely to be unsuitable for award to a small business
concern. 15 U.S.C. 632(o)(2). On the other hand, where, as here,
the record shows that the agency has reserved its requirement
for small businesses, and there is an expression of interest in
the requirement by legitimate small businesses, there is no
basis to conclude that the consolidated requirement is
unsuitable for award to a small business within the meaning of
the Small Business Act. Phoenix Scientific Corp. , supra , at 9.
Here, the agency proceeded with the acquisition notwithstanding
the protest, and on October1, 2004, made award of a contract for
the consolidated requirement to a small business concern. Under
the circumstances, we have no basis to conclude that the
agency's consolidation of these requirements into a single
contract was improper or inconsistent with the Small Business
Act. (Health & Human Services Group,
B-294703, December 15, 2004) (pdf)
The agency explains that the
combined solicitation is necessary because Group Seattle
contains only one MLB (located at Station Bellingham), which may
not generate sufficient repair work to meet the $10,000 minimum
amount under the contemplated IDIQ contract. A separate contract
for Group Seattle also would deprive the agency of the potential
cost benefit from a single contractor’s economies of scale that
would result from repairs on more than one boat, and also would
unnecessarily increase contract administration costs. The agency
determined that, notwithstanding that Reedsport would not be
able to compete, combining the Groups would not result in a
limited competition, since 10 firms expressed interest in the
requirement as structured. The agency’s approach is
unobjectionable. We see no reason why the agency should not be
permitted to consider, in configuring the lots for solicitation
purposes, the amount of work that would be generated under
different combinations of groups, stations and boats, and the
potential effect on the prices for that work (due, for example,
to economies of scale), as well as whether the work generated
for the single MLB would satisfy the contract minimum. While
these considerations resulted in Reedsport’s exclusion from the
competition, it is clear that the Coast Guard gave due
consideration to the broader competitive impact of its approach.
In this regard, based on the numerous expressions of interest,
the agency concluded that it could achieve the operational
benefits of its approach while possibly receiving greater
competition than it did under IFB 003. In arguing that its
own inability to compete renders the solicitation restrictive,
Reedsport ignores other legitimate competitive considerations
that would lead to a different conclusion. For example, while
splitting the requirement would enable Reedsport to compete for
the Station Port Angeles MLBs, this might at the same time
result in little or no competition for the single MLB at Station
Bellingham. Similarly, Reedsport’s position fails to take into
account the possibility that combining the two groups could make
the requirement more attractive to some potential bidders, and
ultimately result in greater competition overall. We conclude
that the agency reasonably combined the two groups under Lot 5.
(Reedsport Machine & Fabrication,
B-293110.2; B-293556, April 13, 2004) (pdf)
The reasons that the agency has offered, however, for grouping
the travel locations by geographic region, and for issuing a
single consolidated procurement, are not solely based on
administrative convenience. As indicated previously, the
underlying purposes behind the agency's single procurement
included the legitimate requirement to reengineer the antiquated
and costly DoD travel process, in part by consolidating the
process, and structuring geographical groupings to allow for
more small business participation. Agency officials testified
that a major factor that was considered in structuring the RFP
into 28 travel areas, with 89 locations was whether there was
adequate sales volume to achieve effective competition. See Tr.,
June 11, 2003, at 12, 40-41. Moreover, this procurement approach
allowed more choices by potential small business offerors to
select the travel areas where they would be most competitive and
able to successfully perform the contracts. Finally, unlike the
protesters, DTS/PMO officials found, based on discussions with
the Army, that the MEPS travel needs were well suited for
support by small businesses because the travel services for MEPS
are relatively “cut and dry”; the protesters have not shown this
judgment was unreasonable. See Tr., June 6, 2003, at 41; Tr.,
June 9, 2003, at 105; Tr., June 11, 2003, at 12-15. Since
the agency had a legitimate requirement to reengineer DoD travel
processes by consolidating them, and the agency did reasonably
consider the impact on small businesses, we find the agency has
justified its approach to consolidating the agency's
requirements. In this regard, we have upheld the consolidation
of requirements where, as here, an agency has provided a
reasonable basis for using such an approach--e.g., a definitive
agency requirement that mirrors the agency's minimum needs and
necessitates the questioned consolidation. See The Sequoia
Group, Inc., supra. (AirTrak
Travel etal., B-292101; B-292101.2; B-292101.3; B-292101.4;
B-292101.5, June 30, 2003) (pdf)
We do not question the agency's decision to classify food
services as logistics support functions to be administered by
the DOL. Rather, our concern is whether the agency has provided
a reasonable justification of its needs in terms of including
food services in the same RFP with base, vehicle, and aircraft
maintenance services. In our view, the fact that the agency is
organized in a manner which results in the administration of the
performance of all of these functions by one particular office
(which may itself be reasonable) does not provide a basis for
insisting that all of these varied services be procured from one
source. In other words, Fort Riley could, consistent with its
view that food services are just as integral to the work of its
DOL as the other functions, continue to have the contract for
food services, as well as the contract for the other services,
administered by the DOL. Beyond the question of whether all of
the services are part of logistics and relate to supporting the
troops, the agency's reason for bundling them all in a
solicitation seems to merely reflect the belief that it is
administratively more convenient to manage one entity performing
all of the requirements--either the MEO or a private-sector
offeror--as opposed to two entities--either the MEO or a
private-sector offeror for the food services, and either another
MEO or another private-sector offeror for the other base,
vehicle, and aircraft maintenance requirements. Administrative
convenience is not a legal basis to justify bundling of
requirements, if the bundling of requirements restricts
competition, as we believe it does here. Vantex Serv. Corp.,
supra, at 4; National Customer Eng'g, supra, at 6. (EDPEnterprises, Inc.,
B-284533.6, May 19, 2003 (pdf))
This solicitation does not
represent a “consolidation” of two or more requirements,
inasmuch as the record establishes that all of the requirements
here were previously provided under the one predecessor contract
with IHS, a large business, and were not provided under separate
smaller contracts. Thus, the Small Business Act requirements
pertaining to bundling are not applicable to this solicitation.
USA also argues that this
solicitation represents an improperly bundled or total package
procurement in violation of the Competition in Contracting Act
of 1984 (CICA). The reach of the restrictions against total
package or bundled procurements in CICA is broader than the
reach of restrictions against bundling under the Small Business
Act. Phoenix Scientific Corp., B-286817, Feb. 22, 2001,
2001 CPD ¶ 24 at 9‑10. Specifically, CICA generally requires
that solicitations include specifications which permit full and
open competition and contain restrictive provisions and
conditions only to the extent necessary to satisfy the needs of
the agency. See 10 U.S.C. §§ 2305(a)(1)(A), (B) (2000).
Because procurements conducted on a bundled or total package
basis can restrict competition, we will sustain a challenge to
the use of such an approach where it is not necessary to satisfy
the agency's needs. Better Serv., B‑265751.2, Jan. 18,
1996, 96-1 CPD ¶ 90 at 2. The determination of a contracting
agency's needs and the best method for accommodating them are
matters primarily within the agency's discretion. Specialty
Diving, Inc., B-285939, Oct. 16, 2000, 2000 CPD ¶ 169 at 3.
Of particular relevance here, where a requirement relates to
national defense or human safety, an agency has discretion to
define the solicitation requirements to achieve not just
reasonable results, but the highest possible reliability and
effectiveness. Tucson Mobilephone, Inc., B-250389, Jan.
29, 1993, 93-1 CPD ¶ 79 at 5, aff'd, B-250389.2, June 21,
1993, 93-1 CPD ¶ 472. (USA Information Systems, Inc., B-291417,
December 30, 2002)
While
we recognize that there are instances where an agency awards
identical ID/IQ contracts so that it might be reasonable to
define what was solicited and awarded as one procurement
requirement (a question we need not resolve here), that is not
what occurred in this instance. In this case, although a single
solicitation (the MLA) was issued, it listed a variety of
equipment needed by the agency. The MLA thus was not a statement
of a single procurement requirement, as the agency suggests, but
instead functioned more as a list of a range of multiple
procurement requirements. As the protester notes, the nine
contracts awarded under the MLA were of varied scope and covered
varying lists of equipment. If the MLA referenced a single
requirement, as the agency contends, that would mean that the
contracting agency had awarded many (perhaps all) of the nine
contracts even though (since they did not cover the entire MLA)
they did not satisfy the agency's procurement requirement. The
fact that all of the containers and all of the related equipment
can be accurately described as intermodal container equipment
does not establish that they are simply elements in a large
unitary procurement requirement; otherwise, separate equipment
contracts for different types of furniture, or for identical
services in different regions of the country, would have to be
viewed as contracts for a single procurement requirement. In our
view, to define "procurement requirement" so broadly could
shield from meaningful review the very sort of arbitrary
consolidation of requirements that the Act's restrictions on
bundling are intended to prevent. (TRS
Research, B-290644, September 13, 2002) (pdf)
On the record before us, we find that the Army has not
adequately demonstrated that combining its requirements for
portable latrine and waste removal services was necessary to
satisfy the agency's needs. The agency has not adequately
explained why it chose to bundle the two kinds of work at Fort
Campbell, yet did not bundle two kinds of work at either of the
other two locations, and in fact structured the solicitation so
that services for the three locations can be obtained by
separate or combined awards, thus facilitating competition while
not excluding the possibility of a combined contract. The
agency's justification, quoted above, essentially amounts to
reliance on administrative convenience as the basis for the
bundling. However, the fact that the agency may find that
combining the requirements is more convenient administratively,
in that it has found dealing with one contract and contractor
less burdensome, is not a legal basis to justify combining the
requirements, if the combining of requirements restricts
competition. CICA and its implementing regulations require that
the scales be tipped in favor of ensuring full and open
competition, whenever concerns of economy or efficiency are
being weighed against ensuring full and open competition. See
Better Serv., supra; National Customer Eng'g, B-251135, Mar. 11,
93-1 CPD ¶ 225 at 6. (Vantex
Service Corporation, B-290415, August 8, 2002) (pdf)
Given the
fundamentally expanded scope and complexity of the agency's food
services requirement, we think USMC reasonably concluded that
there was no reasonable expectation that such small business
concerns, with primarily limited messhall contracts on the
installation level, possessed the capabilities, resources and
experience to satisfactorily perform the contemplated regional
contracts. (MCS
Management, Inc., B-285813; B-285882, October 11, 2000)
Treasury reports that
it projects achieving substantial technical benefits from
consolidating its IT requirements, including the requirement
here, under the Seat Management program. For example, Treasury
expects that having a single contractor responsible for all of
its desktop IT requirements--rather than continuing to rely on
the current fragmented approach of using different sources for
hardware/software and services--will result in significant
quality improvements as a result of (1) having a single
contractor responsible for infrastructure interoperability and
product compatibility, (2) eliminating the confusion, delays and
denials of responsibility for service interruptions or
installation problems, and (3) facilitating consistent, timely
upgrades and refreshment of technology. Treasury Reports, Apr.
2, 1999, at 25-26, Apr. 28, 1999, at 5-6, and Apr. 30, 1999, at
1-2; Agency Report, Tab 26, Acquisition Plan, Feb. 9, 1999, at
3, 9.
SKE has not rebutted
the basis for Treasury's determination to procure the services
in question under the Seat Management contract; it has made no
showing that Treasury in fact had no reasonable expectation of
achieving substantial technical benefits from consolidating
these IT requirements under the Seat Management contract. Thus,
there is no basis for finding that the agency's approach
violates the prohibition against improper bundling. (S&K
Electronics, B-282167, June 10, 1999) |