|
The protester
asserts that it was unreasonable for the agency not to have
considered OVC for this contract award.
The protester principally
asserts that it has less work than Camel and that, accordingly,
it also should have been considered for the award of a
mobilization base sole-source contract, especially in view of
the fact that this is the second such sole-source contract award
that recently has been made to Camel.
OVC also notes that Camel has three other production contracts
with DLA (noted above), and asserts that Camel had another Army
contract awarded to it in June, 2011.
Finally, the protester directs our attention to certain
anecdotal information that it suggests are evidence of Camel
being at a high rate of production, such as various Camel job
advertisements in local newspapers for experienced sewing
machine operators, and undated but apparently recent photographs
of numerous trailers in Camel's parking lot.
Agencies have
authority to conduct procurements using other than full and open
competition and may properly award sole-source contracts to a
particular concern for purposes of establishing or maintaining
industrial mobilization base sources of supply.
10 U.S.C. sect.
2304(c)(3);
Magnavox Elec. Sys., Co.; Ferranti Techs., Inc., B-247316.2,
B-247316.3, May 28, 1992, 92-1 CPD para. 475 at 4.
Where a military agency makes a sole-source award for purposes
of maintaining a particular supplier of an item, concern for
maximizing competition is secondary to the agency's industrial
mobilization needs. Outdoor
Venture Corp., B‑279777, July 17, 1998, 98-2 CPD para. 27 at
2. Decisions as to which
producers should be included in the mobilization base, and which
restrictions are required to meet the needs of industrial
mobilization, involve complex judgments that must be left to the
discretion of the military agencies.
We will question those decisions
only if the evidence convincingly shows that the agency has
abused its discretion.
Ridgeline Industries, Inc., B-402105, Jan. 7, 2010, 2010
CPD para. 22 at 3. OVC's protest
does not meet this standard.
OVC does not
challenge Camel's participation in the relevant industrial base
or assert that the agency's analysis of Camel's current MSR and
business condition is unreasonable or incorrect.
More importantly, although OVC
contends that it also would benefit from the award of a
contract, it nonetheless concedes that it is producing at its
MSR production capacity. As
noted, the record establishes that, without additional support,
Camel may cease its operations which, the agency has determined,
would seriously jeopardize the industrial base for MIL-SPEC
tents. The record also shows
that the agency gave specific consideration to whether OVC
required additional work in order to maintain its production
capability and concluded that it had adequate work at this time
to maintain its MSR. On this
record, we conclude that the agency reasonably exercised its
discretion in making award to Camel and in deciding not to make
award to OVC. (Outdoor Venture
Corporation, B-405423, October 25, 2011) (pdf)
The protester argues that the agency
improperly issued the short-term task order to Aquilent on a
sole-source basis without allowing STG an opportunity to compete
for the task order. Protest at 2.
The 4-month task order, which has a value of $1,958,752, was
placed against Aquilent's Federal Supply Schedule (FSS)
contract. Federal Acquisition Regulation (FAR) sect. 8.405-6[1]
exempts orders placed under the FSS from the competition
requirements of FAR Part 6, but requires that an ordering
activity "justify its action when restricting consideration of .
. . schedule contractors to fewer than required in [FAR
sections] 8.405-1 or 8.405-2."[2] FAR sect. 8.405-6(a)(1).
Circumstances justifying such a restriction include where an
urgent and compelling need exists and following the ordering
procedures would result in unacceptable delays. FAR sect.
8.405-6(b)(3). Where an ordering activity restricts competition
on the basis of an urgent and compelling need, the contracting
officer is required to document the circumstances in writing.
FAR sect. 8.405-6(c), (f). Where the proposed order is over
$550,000 but not over $11.5 million, the justification must be
approved by the competition advocate of the activity placing the
order. FAR sect. 8.405-6 (h)(2).
Here, the agency determined that it was critical that
maintenance and support services for the eCMS remain
uninterrupted and seamless during the time period in which the
agency reviews its requirements and resolicits the procurement.
Agency Report (AR), Tab 4, Urgency Statement, at 2. In support
of this determination, the agency explained that interrupted
service would have a "deleterious effect on the health and well
being of Veterans" who receive "vital" services from procurement
activities impacted by eCMS. Id. The agency concluded that "the
only reasonable and viable solution" to avoid an interruption in
the services was to award a short‑term task order, "which will
be solely for maintaining, not updating eCMS," to the current
incumbent, Aquilent, without competition, until a properly
competed task order can be awarded. Id.
To this end, the agency executed a justification and approval
(J&A) for a limited source award under the FSS on an urgent and
compelling basis. The agency reiterated that uninterrupted eCMS
maintenance and support was "critical to the [VA's] mission,"
and stated that the VA did not have the resources to provide
these services "in-house" while conducting a competition that
would likely take several months to complete. AR, Tab 7, J&A, at
2. The agency recognized that there were other sources available
for this requirement, including STG, but the agency concluded
that only Aquilent, the incumbent, possessed the specialized
experience specific to eCMS and the VA's needs necessary to
continue to provide the critical maintenance and support without
a break in service. Id. at 3. The agency stated that any new
contractor would most likely need to hire and train new
employees, as well as obtain the required security credentials.
Id. The agency also estimated that it would take a new
contractor at least 1 month to begin learning the processes and
the organization, a minimum of 2 weeks to provide new employees
with access to the VA network, and another 2 weeks to train the
new employees on eCMS and the various subsystems. Id. Based on
this record, we find the issuance of a task order to Aquilent to
be unobjectionable.
The protester disputes the agency's findings of "urgent and
compelling" circumstances. Comments at 2. However, the protester
has not shown that the agency's determination is unreasonable.
As noted above, the record supports the agency's determination
that conducting a competition for these interim services would
result in interrupted services that are critical to the VA's
mission. Furthermore, the agency has shown that, as the
incumbent, Aquilent is the only contractor capable of providing
immediate maintenance and support services. As noted above, FAR
sect. 8.405-6(b)(3) specifically authorizes restricting
competition where, as here, an urgent and compelling need exists
and following the FSS ordering procedures would result in
unacceptable delays. To the extent the protester is disputing
the agency's judgment as to the time period required to conduct
a competition for the interim services, a protester's mere
disagreement does not show that the agency's judgment was
unreasonable. Richard Bowers & Co., B-400276, Sept. 12, 2008,
2008 CPD para. 171 at 2. (STG,
Inc., B-405082; B-405082.2, July 27, 2011) (pdf)
The Competition in Contracting Act (CICA),
10 U.S.C. sect. 2304(c)(2), permits an agency to use other than
competitive procedures in acquiring goods or services where the
agency's requirement is of such an unusual and compelling
urgency that the government would be seriously injured unless
the agency is permitted to limit the number of sources from
which it solicits proposals. Moreover, while CICA requires that
agencies solicit offers from as many potential sources as is
practicable when using the unusual and compelling urgency
exception to limit competition, 10 U.S.C. sect. 2304(e), an
agency nonetheless may limit a procurement to the only firm it
reasonably believes can properly perform the work in the time
available. McGregor Mfg. Corp., B-285341, Aug. 18, 2000, 2000
CPD para. 151 at 6.
A military agency's assertion that there is a critical need that
is related to human safety and affects military operations
carries considerable weight. Id. at 7; Eclypse Int'l Corp.,
B-274507, Nov. 12, 1996, 96-2 CPD para. 179 at 3. Underlying
this policy is the simple fact that under wartime conditions,
the government must procure items quickly and urgently to meet
compelling military needs. Jay Dee Militarywear, Inc., B-243437,
July 31, 1991, 91-2 CPD para. 105 at 5. An agency need not risk
injury to personnel or property in order to conduct a
competitive acquisition. Signals & Sys., Inc., B‑288107, Sept.
21, 2001, 2001 CPD para. 168 at 10. Additionally, under
circumstances involving a critical need of items related to
human safety and affecting military readiness during wartime,
the agency need only consider those sources which can
immediately satisfy its requirements and not those which have
the potential to do so. Jay Dee Militarywear, Inc, supra. The
reasonableness of the contracting activity's judgments must be
considered in the context of the time when they were made and
the information that was available at that time. Equa Indus.,
Inc., B-257197, Sept. 6, 1994, 94-2 CPD para. 96 at 3 n.1.
The protester claims that it could "produce surveillance systems
to meet the [USMC's] needs," arguing that it could "deliver
G‑BOSS Lite systems" that "would not be different from, or
incompatible with, existing fielded systems." Protester's Supp.
Comments at 3. The protester also claims, apparently in the
alternative, that it could produce "compatible units on an
expedited basis," starting "with [DELETED]." Protester's
Comments at 9. With regard to its capability to produce and
deliver G‑BOSS Lite units, the protester has provided with its
comments on the agency report on this protest a declaration from
Argon's Director of Imaging Systems, stating that, "[b]ased on
[this individual's] understanding of G‑BOSS Lite," Argon,
starting "with [DELETED] which Argon is presently
manufacturing," could modify these units "to the G‑BOSS Lite
configuration" and deliver these units to "the Government within
[DELETED] of contract execution." Protester's Comments, exh. 1,
Declaration of Argon's Director of Imaging Systems (July 8,
2010), at 1. The protester provided with the declaration a
"technical proposal" describing the similarity between the
G‑BOSS Lite and [DELETED], and generally explaining how Argon
would modify or manufacture units to be delivered to the agency.
Protester's Comments, exh. 1, Technical Proposal. Argon adds in
its protest that during the Industry Day it had informed the
Navy that Argon "had been selected [by the Navy] to supply
Cerberus Tactical Long Range Systems and were currently building
units which are a very close variant to the [G‑BOSS Lite]
system," and "[DELETED]." Protest at 4.
Based upon our review of the record, we find the agency's
actions here to be reasonable. As an initial matter, there is no
basis on which to question the agency's position that there is a
critical and immediate need for additional G‑BOSS Lite units to
be used by USMC personnel in Operation Enduring Freedom, and
that this need is related to human safety and affects military
operations. The record reflects, and the protester does not
dispute, that at this time the agency does not have a technical
data package for the G‑BOSS Lite that could be made available to
Argon or any other firm for the manufacture of that system.
Further, as reasonably explained by the agency, the manufacture
of a fully functioning G‑BOSS Lite that is ready for use by the
warfighter is more complex than a simple assembly of various
components, and to date, ICx is the only vendor to have
manufactured, tested and delivered G‑BOSS Lite units.
Additionally, although Argon has provided a "technical proposal"
with its comments on the agency report generally describing how
it would manufacture "compatible units on an expedited basis,"
it conceded in describing its proposal that because the agency
lacks a technical data package for G‑BOSS Lite, the proposal was
prepared by Argon "without the benefit of even a basic
description of G‑BOSS Lite." Protester's Comments at 9. Also, as
pointed out by the agency, Argon has not manufactured and
delivered either a G‑BOSS Lite unit or a Cerberus unit to the
government. In this regard, the agency points out that Argon's
contract with the Navy for Cerberus Tactical Long Range Systems,
which Argon claims are a very close variant to the G‑BOSS Lite
system, was terminated by the agency prior to the delivery or
acceptance of any Cerberus units to agency.
In sum, while Argon claims that it could manufacture and deliver
G‑BOSS Lite units or another "compatible" system that could meet
the urgent needs of the warfighter, it has not shown that the
agency's differing view was unreasonable. That is, at the time
the J&A was executed as well as the time of award, ICx was the
only source that had already successfully manufactured and
delivered G‑BOSS Lite units and could move immediately into
production upon contract award, whereas Argon had not
demonstrated that it could provide the G‑BOSS Lite units to meet
the urgent requirements but only claimed that it could do so.
See FXC Corp., B-257697.2; B‑257973, Dec. 1, 1994, 94‑2 CPD para.
216 at 10.
Nor do we agree with Argon that the urgency of the requirement
that resulted in the sole-source award to ICx for 34 G‑BOSS Lite
units was the result of a lack of advance procurement planning.
As Argon points out, CICA mandates that noncompetitive
procedures not be used where agency contracting officials failed
to perform advance procurement planning. 10 U.S.C. sect. 2304
(f)(4); RBC Bearings Inc., B-401661; B‑401661.2, Oct. 27, 2009,
2009 CPD para. 207 at 6. Our Office has recognized that the
requirement for advance planning does not mean that such
planning be completely error-free, but, as with all actions
taken by an agency, the advance planning required must be
reasonable. RBC Bearings Inc., supra.
The record demonstrates that the G‑BOSS Lite program is
relatively new, and that the agency has been actively planning
for the competitive acquisition of G‑BOSS Lite units since
September 2009 and intends to issue an RFP in late 2010
providing for a awards on a competitive basis. Additionally, the
record further reflects that the urgent need for the G‑BOSS Lite
units was due to "unforeseen military requirements," that is, to
provide additional G‑BOSS Lite units to USMC personnel "in
support of protection of Forward Operating Bases in Afghanistan"
at a date earlier than could be accommodated through a
competitive procurement. AR, Tab 9, Joint Operational Needs
Prior Approval Reprogramming Action (Feb. 2, 2010), at 1-2.
Given the urgency of the unforeseen requirements being protested
here, Argon's complaints that the agency should have developed a
technical data package earlier or obtained one from ICx are
insufficient to show that the agency did not engage in advance
procurement planning under the circumstances present here.
The protester also argues that the J&A executed here is
defective. For example, the protester contends that the J&A is
inadequate because "it does not address when the G‑BOSS units
are required by the Government or even when they are required to
be delivered by ICx," and thus cannot justify an urgency
requirement. Supp. Protest at 3. The protester adds here that "[a]lthough
the J&A was executed on the basis of urgency, it confirms . . .
that the requirement was in development for a very long time,"
pointing out that the USMC's urgent statement of need was
executed in January 2010 and the J&A was executed in March 2010.
The protester concludes here that "[d]espite the purported
urgency, the Navy has been taking its time." Supp. Protest at 4.
Section 6.303-2 of the Federal Acquisition Regulation sets forth
the required content of a J&A. This section does not require
that a J&A based upon urgency specify the dates on which the
items being acquired will be delivered, or the date on which the
items are "required to be delivered," as asserted by the
protester. As such, we fail to see why the statement in the J&A
that the G‑BOSS Lite units are needed "as soon as possible" is
inadequate or inconsistent with an urgent requirement. We also
disagree with the protester that the agency, whose actions
include the research, preparation, vetting, and execution of the
J&A over a 2-month period, can reasonably be characterized as
"taking its time." In this regard, we believe that the agency's
actions, as well as those of ICx, support the characterization
of the requirement as urgent, given that the delivery of the
G‑BOSS Lite units commenced less than 7 months after the
agency's receipt of the urgency requirement, and 4 months after
the execution of the J&A, and will be completed shortly after
this decision is issued.
Although the protester is correct, and the agency concedes, that
the statement in the J&A that no other available surveillance
system incorporates "ground sensors" is inaccurate, this error
provides no basis on which to find the agency's actions
unreasonable, given that the rest of the J&A reasonably supports
the sole-source decision. The remainder of the alleged "errors"
in the J&A as identified by the protester, such as the J&A's
assertion that the acquisition of another system would "require
retraining the warfighter" reflect, in our view, the protester's
disagreement with the agency's judgment and not factual errors
in the J&A. Thus, we find that the J&A reasonably supports the
sole source determination. (Argon
ST, Inc., B-402908; B-402908.2, August 11, 2010) (pdf)
Missouri Machinery argues that the Coast Guard's requirement
that the vendor here must be an authorized Gould repair facility
unduly restricts competition. The record shows that the Coast
Guard limited competition to authorized repair facilities
because it lacks the data necessary to assure that
non-authorized repair facilities adequately perform the work,
assumes that only authorized repair facilities will have access
to OEM parts, and recognizes that only work completed by an OEM
authorized repair facility will be warranted by Gould.
The Competition in Contracting Act of 1984 requires full and
open competition in government procurements except where
otherwise specifically allowed by the statute. 10 U.S.C. sect.
2304(a)(1)(A) (2006). One exception to this competition
requirement is where the agency's requirements can be performed
by only one or a limited number of sources. 10 U.S.C. sect.
2304(c)(1); FAR sect. 6.302-1. However, where, as here, an
agency uses non-competitive procedures under 10 U.S.C. sect.
2304(c), it is required to execute a written J&A with sufficient
facts and rationale to support the use of the cited authority.
10 U.S.C. sect. 2304(f)(1); FAR sect. 6.302-1; Signals & Sys,
Inc., B-288107, Sept. 21, 2001, 2001 CPD para. 168 at 9. Our
review of the agency's decision to conduct a procurement under
the exceptions to full and open competition focuses on the
adequacy of the rationale and conclusions set forth in the J&A.
Pegasus Global Strategic Solutions, LLC, B-400422.3, Mar. 24,
2009, 2009 CPD para. 73 at 7.
Here, the record does not support the Coast Guard's decision to
limit this competition to Gould authorized repair facilities.
Although the Coast Guard contends that it lacks the data to
judge whether non‑authorized facilities, such as Missouri
Machinery, can adequately perform the overhaul and repair work,
the J&A also concedes that Missouri Machinery has in the past
successfully performed overhaul and repair work for the agency
on these Gould pumps. See AR, Tab 6, J&A, at 4. In this regard,
Missouri Machinery points to numerous examples, where the firm
has successfully repaired these pumps for the Coast Guard since
2003. See Protest at 1; Missouri Machinery Answers to GAO
Questions, Sept. 30, 2010, at 1-4. Missouri Machinery states
that these pumps, which have been on the market for many years,
are not complex, high‑technology items that require proprietary
data to perform repairs and overhaul. Comments at 2.
While the agency does not deny that Missouri Machinery has
successfully performed past contracts to repair and overhaul
these pumps, it suggests that Missouri Machinery will need more
time to repair and overhaul pumps than would an authorized
repair facility (allegedly 4 to 5 times the number of hours
according to the contracting officer and 7 times according to
the COTR). See CO's Statement at 4; COTR's Statement, Oct. 1,
2010, at 3. Even if this is true, the Coast Guard does not
explain--and neither the RFQ nor the J&A indicate--any need for
urgency. In this regard, the RFQ provides for a long time frame
for repair and overhaul, and further states that the repaired
pumps will be warehoused for as long as 2 years. See, e.g., RFQ
at 12, 17. In addition, while a longer repair time may well
cause Missouri Machinery's quote to be less likely to prevail in
a competition--for example, by increasing its labor costs--this
issue does not provide a basis for excluding the company before
the competition is underway.
The Coast Guard also argues that it must limit this competition
because it assumes that only a Gould authorized repair facility
will be able to provide the required OEM parts. CO's Statement,
at 3. Missouri Machinery does not dispute that OEM parts are
needed, but argues that it is untrue that only authorized repair
facilities can obtain them. In fact, the protester states that
it used OEM parts in its past contracts for these pumps.
Missouri Machinery Answers to GAO Questions, Sept. 30, 2010, at
5. Moreover, during the course of this protest, our Office asked
the Coast Guard for confirmation of Gould's position vis-à-vis
the OEM parts. In response, Gould stated that its authorized
repair facilities will willingly sell replacement OEM parts to
non‑authorized facilities. See COTR's Email to Agency Counsel,
Sept. 29, 2010, at 1. Thus, the record shows that the
assumptions underlying this reason for limiting competition are
unfounded.
Finally, the Coast Guard argues that only work completed at a
Gould authorized repair facility can receive a warranty from
Gould.[4] Legal Memorandum, at 3. In this regard, we note that
the RFQ requires vendors to provide a standard commercial
warranty at no additional cost. See RFQ at 83. Missouri
Machinery states that it warrants its service work in accordance
with the warranty terms in the RFQ, and in the same way that a
Gould authorized repair facility warrants this work. Missouri
Machinery Response, Oct. 8, 2010. We see nothing about the
warranty requirements here that justifies restricting this
competition to Gould authorized repair facilities.
In short, none of the reasons set forth by the Coast Guard in
the J&A justify the agency's decision to limit this competition
to Gould authorized repair facilities. Therefore, we find that
the agency's restriction of the competition to OEM authorized
repair facilities is not reasonable, and we sustain Missouri
Machinery's protest on this basis. (Missouri
Machinery & Engineering Company, B-403561, November 18,
2010) (pdf)
Ridgeline argues that the sole-source justification is
unreasonable because DLA did not consider Ridgeline for a
contract, and because Ridgeline too is at risk of having to
close its doors. Protest at 4. Ridgeline states that it has only
a handful of key employees with the knowledge and skills to
manufacture military specification tents, and is performing only
one small contract, for tent floors. Protest at 5.
In response, DLA acknowledges that Ridgeline has produced
military tent components (such as floors, liners, window
sections, and ductwork sections), but distinguishes Ridgeline's
experience producing tent components from the complete tent (or
"tent system" in DLA's terminology). DLA produced records
showing that Ridgeline last produced a complete military tent
system, as opposed to components, in 1985. DLA states that only
recently has Ridgeline even sought to compete under
solicitations for complete tent systems. Accordingly, DLA argues
that it appropriately did not consider Ridgeline as a part of
the relevant industrial base. DLA argues its effort to maintain
the existing industrial base does not require making award to a
firm that wishes to become a new supplier of tent systems, such
as Ridgeline. AR at 7.
In response, Ridgeline briefly asserts that DLA is incorrect,
but provides no facts to support its contentions. Protester's
Comments at 1-2. Thus, although Ridgeline argues that it should
have been considered an active participant in the market for
tent systems (as opposed to components), it has provided no
factual basis upon which our Office could reach such a
conclusion, given the detailed information submitted by DLA,
which shows that Ridgeline is not an established supplier of
tent systems.
Under the Competition in Contracting Act of 1984, agencies have
authority to conduct procurements to establish or maintain
sources of supply for a particular item in the interest of the
national defense, see 10 U.S.C. sections 2304(b)(l)(B) and
2304(c)(3). Agencies need not obtain full and open competition
where the procurement is conducted for industrial mobilization
purposes and may use other than competitive procedures where it
is necessary to award the contract to a particular source or
sources. Decisions as to which producers should be included in
the mobilization base, and which restrictions are required to
meet the needs of industrial mobilization, involve complex
judgments that must be left to the discretion of the military
agencies. We will question those decisions only if the evidence
convincingly shows that the agency has abused its discretion. Minowitz Mfg. Co., B‑228502, Jan. 4, 1988, 88-1 CPD para. 1 at
3.
In our view, Ridgeline has failed to meaningfully challenge the
agency's explanation for limiting this award to Camel. In
contrast with the factual support and reasoned explanation
provided in the agency report, Ridgeline's comments responding
to the agency report do not show that the sole-source
justification was unreasonable. (Ridgeline
Industries, Inc., B-402105, January 7, 2010) (pdf)
CDC challenges the sole-source justification, asserting that it
manufactures equipment that meets the agency's requirements.
Protest at 1. The protester asserts that, "Any systems can be
made compatible with the existing ironing system at VAMC
Canandaigua," id., and that it produces ironers that can meet or
exceed the performance requirements of the Braun equipment.
Protest at 1; Protester's Comments at 3. CDC indicates that it
has supplied other VA medical centers with ironing systems that
will communicate with applicable Braun equipment. Protest at 2;
Protester's Comments at 1.
The agency asserts that its market research indicated that only
an ironer manufactured by Braun could meet these requirements
and that the sole-source therefore was properly justified by the
contracting officer. AR at 3; Contracting Officer's Statement
(COS) at 3.
As a general matter, the Competition in Contracting Act (CICA)
mandates "full and open competition" in government procurements
obtained through the use of competitive procedures. 41 U.S.C.
sect. 253(c)(1) (2006). CICA, however, provides several
exceptions, including when an agency's requirements can only be
satisfied by one responsible source. 41 U.S.C. sect.
253(a)(1)(a). In this regard, we have recognized that an
agency's legitimate need to standardize the equipment it uses
may provide a reasonable basis for imposing restrictions on
competition. See, e.g., Sperry Marine, Inc., B-245654, Jan. 27,
1992, 92-1 CPD para. 111 (procurement of particular radar system
on sole-source basis was reasonable where record established
need for same system used in training program).
Here, the protester does not challenge the agency's stated
requirements for interoperability with installed Braun equipment
at VAMC Canandaigua but, rather, asserts that it can supply
equipment meeting those requirements. As a general matter, a
protester challenging an agency's sole-source determination on
the basis that its product meets the agency's needs has the
burden of showing that this is the case. See, e.g., eFedBudget
Corp., B‑298627, Nov. 15, 2006, 2006 CPD para. 159 at 7 (protest
against sole-source acquisition denied where protester did not
meet its burden of demonstrating that it could perform contract
without access to source code and without violating licensing
agreement).
CDC has not established that it can provide a flatwork ironer
meeting the agency's needs. Although the protester asserts,
generally, that its ironer can "be made compatible in that we
have installed other Chicago Dryer ironing, folding and feeding
systems with other ironing systems including GA Braun,"
Protester's Comments at 1, it has neither identified a model
that can meet all of the agency's identified requirements nor
provided product material that supports its assertions. Further,
as the agency points out (unrebutted by CDC), while the
protester generally asserts that it has provided equipment
compatible with Braun equipment at other VA medical centers--CDC
states that it has installed "equipment in concert with GA
Braun" at the VA facility at Oklahoma City and has also
"installed such systems at VA Perry Point," Protester's Supp.
Comments at 2--it has not provided any specific reference to an
actual customer for which it provided an ironer compatible with
the existing Braun system. Supp. AR at 1. We conclude that the
protester has not shown that it can supply a product that meets
the agency's needs. See, e.g., Container Prod. Corp.,
B‑270360.2, June 11, 1996, 96-1 CPD para. 275 (protest
challenging sole-source acquisition denied where protester's
submissions included only general technical information and
failed to identify exact equipment being offered). Consequently,
there is no basis for us to question the issuance of the
purchase order to Braun. (Chicago
Dryer Company, B-401888, December 8, 2009) (pdf)
The Competition in Contracting Act of 1984 (CICA) requires that
an agency obtain full and open competition in its procurements
through the use of competitive procedures. 10 U.S.C. sect.
2304(a)(1)(A). There are various exceptions to this requirement,
including a situation where only one responsible source is able
to meet the agency’s requirements. 10 U.S.C. sect. 2304(c)(1);
HEROS, Inc., B-292043, June 9, 2003, 2003 CPD para. 111 at 6. In
this regard, when a contracting agency restricts a contract to
an approved product or source, and uses a qualification
requirement, it must give other potential offerors a reasonable
opportunity to qualify; however, there is no requirement that an
agency delay a procurement in order to provide an offeror an
opportunity to demonstrate its qualifications. Lambda Signatics,
Inc., B‑257756, Nov. 7, 1994, 94-2 CPD para. 175 at 4; Advanced
Seal Tech., B‑250199, Jan. 5, 1993, 93-1 CPD para. 9 at 3; see
10 U.S.C. sect. 2319(b).
Here, as noted above, the record is clear that the complete
windshield kit was comprised of more than the two component
assemblies for which SBG sought source approval. Accordingly,
even if SBG had been properly approved to supply those
components, such approval would not qualify SBG to supply the
complete windshield kit for which the agency contracted. SBG’s
CEO expressly acknowledged that SBG did not submit a SAR1
for the complete windshield kit due to SBG’s uncertainty as to
the elements comprising that kit. Although SBG initially sought
to obtain the necessary information, through acquisition of a
sample kit and reverse design engineering, SBG did not
diligently pursue that information, waiting more than 5 months
after being advised that a kit was available to actually obtain
the kit.
On this record, we find no merit in SBG’s assertion that its
failure to qualify as an approved source for the items being
procured is attributable to the agency. To the contrary, SBG’s
failure to submit a SAR for the complete windshield kit, due to
its lack of knowledge coupled with its own inaction, was the
basis for its failure to obtain approval. To the extent SBG’s
protest is based on assertions that the agency improperly
withheld source approval for the procured items, the protest is
denied. (Standard Bent Glass
Corporation, B-401212, June 23, 2009) (pdf)
---------------------------------------
1
SAR - source approval request.
During the course of the procurement, the agency determined to
limit competition as provided for under the National Defense
Authorization Act for Fiscal Year 2008, Public Law (Pub. L.)
110-181. As relevant here,
section 886 of this act states that, for products or
services to be acquired in support of military operations or
stability operations in Iraq or Afghanistan, the Secretary of
Defense may determine that “it is in the national security
interest of the United States to limit competition, use
procedures other than competitive procedures, or provide a
preference” because such limitation, procedure, or preference
“is necessary to provide a stable source of jobs in Iraq or
Afghanistan” and “will not adversely affect military operations
or stability operations in Iraq or Afghanistan . . . .” Id. at
sect. 886(a) and (b)(2).
In this regard, the Secretary of Defense is authorized to
conduct a procurement in which, among other things, “procedures
other than competitive procedures are used to award a contract
to a particular source or sources from Iraq or Afghanistan.”
(Emphasis added.) Id. at sect. 886(a)(2). A source is defined as
being “from” Iraq or Afghanistan if it “is located in Iraq or
Afghanistan” and “offers products or services that are from Iraq
or Afghanistan.” Id. at sect. 886(c)(3). The regulations
implementing these provisions, found at Defense Federal
Acquisition Regulation Supplement (DFARS) sections
225-7703-1(a)(2) and (a)(3), allow for the use of “procedures
other than competitive procedures to award a contract to a
particular source or sources from Iraq or Afghanistan.” Id. at
sect. 225-7703-1(a)(3). A written determination must be executed
before competition may be limited. Id. at sect. 225‑7703-2.
On January 29, 2009, the Army prepared a determination and
finding (D&F) to support its decision to meet the requirement
through limited competition. The D&F states that the acquisition
will be conducted under section 886 and that “other than
competitive procedures” will be used “to award a contract to a
particular source or sources from Iraq or Afghanistan.” Agency
Request for Dismissal, encl. 7, D&F, at 1. The D&F also states,
among other things, that using the described procedures is
necessary to provide a stable source of jobs in Iraq, lists
Iraqi sources that expressed interest in the solicitation, and
states that, to implement the limited competition, the
solicitation will contain DFARS sect. 252-225-7026, Acquisition
Restricted to Products or Services from Iraq or Afghanistan. Id.
at 1. The solicitation, issued on February 17, contained this
clause, which states that “the contractor shall provide only
products or services from Iraq” (as defined in section 886(c)(1)
and (2)). RFP at 41.
The Army provided the
solicitation to several firms, but not to the protester because
it was aware that KLG is not an Iraqi company, but a Kuwaiti
company based in Kuwait. Agency Request for Dismissal, encl. 1,
at 1. KLG argues that it should have been permitted to compete
under the RFP. In this regard, KLG cites the language of DFARS
sect. 252-225-7026, included in the solicitation, which requires
only that contractors use services or products from Iraq or
Afghanistan in the performance of a contract, not that the
contractor be an Iraqi company. KLG also contends that the
statutory language “a particular source or sources from Iraq”
should be read to include firms “operating” in Iraq. Protester’s
Supplemental Response to Agency’s Dismissal Request at 1. KLG
concludes that, since it “operates” in Iraq and intends to
utilize Iraqi products and services, it meets the requirements
of DFARS sect. 252-225-7026, and thus should be permitted to
compete. Protester’s Response to Dismissal Request, at 2.
The Army maintains that it was authorized by the act to limit
the competition to Iraqi firms, and that the record clearly
shows that it intended to do so. In this regard, the Army
contends that the plain language of section 886 of Pub. L.
110-181 and DFARS sect. 225‑7703-1(a)(3) authorizes it to limit
competition to Iraqi companies, and cites the language in its
D&F as establishing its intent to invoke this authority to make
award to a source “from Iraq.” Agency Supplemental Dismissal
Request, at 3.
We agree with the protester that the language in the
solicitation does not expressly exclude non-Iraqi firms from
competing; the only provision incorporated in the solicitation
to limit competition--DFARS sect. 252-225-7026--requires that
the contractor provide Iraqi products and services, but does not
address the origin of the contractor. This conclusion
notwithstanding, we find no basis to object to the agency’s
actions, since we think the act confers authority to limit
competition to Iraqi companies, and the record shows that the
agency intended to do so. In this regard, as noted, under the
act a source is “from Iraq” if it is “located in Iraq” (and
offers products or services from Iraq). The agency interprets
this language as referring only to Iraqi companies, and we agree
with this interpretation. First, it is consistent not only with
the plain language of the act, but also with its underlying
purpose--because of its permanent connection to Iraq, an Iraqi
company reasonably may be viewed as more likely than a non-Iraqi
company to provide a stable source of jobs in Iraq. See Pub. L.
110-181, sect. 886(a) and (b)(2). Moreover, the protester’s
alternative interpretation--that “from Iraq” and “located in
Iraq” refer to sources operating in Iraq--is based on a
term--“operating”--that does not appear in the act. If this was
the intent underlying the act, it easily could have been
expressed by use of this term or other similar language. See,
e.g., AlliedBarton Sec. Servs. LLC, B‑299929 et al., Oct. 9,
2007, 2007 CPD para. 175 (the Stafford Act establishes
preference for firms “residing or doing business primarily in
the area affected . . . .”).
Accordingly, we conclude that the agency properly determined
that KLG is ineligible to compete because it is not a source
from Iraq. Requiring the agency to amend the solicitation to
make KLG’s exclusion clearer would serve no purpose; KLG would
remain ineligible for award. We will not recommend such a
useless act. See Arrow Eng’g, Inc., B-215585, Dec. 26, 1984,
84-2 CPD para. 702 at 3. (Kuwait
Leaders General Trading & Contracting Company, B-401015.2,
May 21, 2009) (pdf)
When an agency
uses noncompetitive procedures, it must execute a J&A with
sufficient facts and explanation to support the use of the
specific authority. See 10 U.S.C. sect. 2304(f). Our review of
an agency’s decision to conduct a sole-source procurement
focuses on the adequacy of the rationale and conclusions set
forth in the J&A. When the J&A sets forth reasonable
justifications for the agency’s actions, we will not object to
the award. Turbo Mechanical, Inc., B-231807, Sept. 29, 1988,
88-2 CPD para. 299 at 3-4. The protester’s disagreement with the
agency’s rationale does not provide a basis to sustain the
protest; rather, the protester must show that the agency’s
position is unreasonable. Allied-Signal Inc., B-247272, May 21,
1992, 92-1 CPD para. 461 at 10.
As stated above, the statutory exception relied on here is 10
U.S.C. sect. 2304(c)(1). Specifically, the agency asserts that
it reasonably determined that only LM MS2 could successfully
perform the 5110 hardware contract, and that only LM MS2 could
successfully develop and integrate the four new Aegis functions
that are the subject of solicitations 5121 and 5123. The
sole-source procurements are unobjectionable if the Navy
reasonably found that award to any source other than LM MS2
would likely result in either substantial duplication of cost to
the government that is not expected to be recovered through
competition, or unacceptable delays in fulfilling the agency’s
requirements. 10 U.S.C. sect. 2304(d)(1)(B); FAR sections
6.302-1(a)(2)(ii), (iii). Because either basis is sufficient
and, as discussed below, we find that the Navy reasonably
determined that acquisition from Raytheon IDS (or any source
other than LM MS2) would likely cause unacceptable delays, we
will not address the question of duplication of costs. Magnavox
Elec. Sys., Co., B-258076.2, B-258076.3, Dec. 30, 1994, 94-2 CPD
para. 266 at 7.
In certain circumstances, it is reasonable for an agency to
determine that overall knowledge of all of the critical
components of a system is essential. Kearfott Guidance &
Navigation Corp., B-292895.2, May 25, 2004, 2004 CPD para. 123
at 6. In procurements where the agency lacks a complete data
package, a contractor’s familiarity with the work to be
performed may justify a limited competition, because award to a
firm that lacks that experience may result in unacceptable delay
in fulfilling the agency’s requirements. Univox Cal., Inc. et
al., B-225449.2 et al., Dec. 9, 1987, 87-2 CPD para. 569 at 8-9.
This is the case when hands-on experience is needed to augment
an existing, inadequate TDP in order for the contractor to meet
the agency’s needs within the time prescribed. Id.
Where an agency does not possess a TDP adequate for competition,
the agency may procure its requirement on a sole-source basis
from a contractor whose prior experience reduces the risk to the
agency that its needs will not be timely met. Kollsman, A Div.
of Sequa Corp.; Applied Data Tech., Inc., B-243113, B-243113.2,
July 3, 1991, 91-2 CPD para. 18 at 8. This is so, even where,
given less stringent deadlines, other contractors might as ably
perform. Id. Where the protester is at a technical disadvantage
to the proposed sole-source recipient, and the record shows that
the protester could not remedy its technological deficit and
meet the time frame established by the agency, we will not
object to the proposed sole-source award. Id. at 9; Tri-Ex Tower
Corp., B‑239628, Sept. 17, 1990, 90-2 CPD para. 221 at 5. As
discussed below, the record supports the agency’s position that
Raytheon IDS has not shown that it can perform these contracts
without risk that the Navy’s needs will not be timely met.
(Raytheon Company-Integrated Defense
Systems, B-400610; B-400618; B-400619, December 22, 2008) (pdf)
The protester argues that this sole source procurement--as
originally proposed, and as modified--is improper because TLC
could have provided equivalent equipment had it been asked, and
because, in TLC’s view, the old fire alarm system could have
been repaired for half the cost of purchasing the new Monaco
system. Protest at 1; Protester’s Comments at 1. The protester
also appears to challenge the agency’s original procurement of
the central Monaco receiver and individual fire alarm
transmitters that the agency procured several years ago.
Protester’s Comments at 1. As set forth below, we think the
Army’s sole-source award was properly justified, and was a
reasonable exercise of its discretion to make such awards.
The overriding mandate of the Competition in Contracting Act (CICA)
is for “full and open competition” in government procurements,
which is obtained through the use of competitive procedures. 10
U.S.C. sect. 2304(a)(1)(A) (2008). Where an agency’s needs are
of such an unusual and compelling urgency that the government
would be seriously injured if the agency is not permitted to
limit the number of sources from which it solicits bids or
proposals, the agency may use noncompetitive procedures pursuant
to the authority set forth at 10 U.S.C. sect. 2304(c)(2). All
Points Int’l, Inc., B‑260134, May 22, 1995, 95-1 CPD para. 252
at 3. This authority is limited by 10 U.S.C. sect. 2304(e),
which requires agencies to request offers from as many sources
as practicable. An agency may limit a procurement to only one
firm if it reasonably determines that only that firm can
properly perform the work in the available time. Lundy Technical
Ctr., Inc., B‑243067, June 27, 1991, 91-1 CPD para. 609 at 3. We
will object to the agency's determination only where the
decision lacks a reasonable basis. Datacom, Inc.--Protests and
Request for Costs, B‑274175 et al., Nov. 25, 1996, 96-2 CPD para.
199 at 7.
As described in the facts above, and as referenced in the J&A,
immediate replacement of the failed fire alarms at Fort Meade
was necessary to prevent potential loss of life and/or property
due to undetected fires. In addition, despite TLC’s claims to
the contrary, the Army concluded that it would not be able to
repair the old system, as replacement parts for that system were
no longer being made. We see no basis in this record to question
that judgment. Moreover, because the testing of the Monaco
system had already been completed, and the Monaco central
receiver had already been installed, the Army concluded that
replacing the failed fire alarms with Monaco alarms was
necessary to achieve compatibility within its fire alarm system.
As a final matter, we note that in response to this protest the
agency reasonably elected to limit the size of the current
sole-source award to cover only the number of fire alarms needed
to replace those that had failed on June 11.
Given the severity of the potential harm if the government did
not replace the failed fire alarms, and the fact that, under
these exigent circumstances, where time was of the essence, only
the Monaco alarms could be immediately installed to work with
the central receiver without additional, and possibly extended,
testing, we think that the agency’s sole-source purchase of 51
fire alarms was properly justified, and a reasonable exercise of
its discretion to justify such awards. (T-L-C
Systems, B-400369, October 23, 2008) (pdf)
Eisenhower filed
an agency-level protest of the proposed sole-source award to the
incumbent claiming that, since Eisenhower has an acceptable
alternative property, it was unreasonable for the agency to
conclude that only one source exists that will satisfy the
agency’s requirements. In responding to that protest, the agency
explained to the protester that it decided to award a
sole-source lease to the incumbent based on the results of the
cost-benefit analysis which was performed pursuant to the GSA
regulations (GSAR) regarding succeeding leases, 48 C.F.R.
subpart 570.4. Specifically, under GSAR sect. 570.402-5(b), “if
the cost-benefit analysis indicates that the Government cannot
expect to recover relocation costs and duplication of costs
through competition, [the agency is to] prepare a justification
for approval in accordance with FAR 6.3 and 506.3.” The agency
further explained that a justification for the proposed
sole-source award was prepared pursuant to the exception to full
and open competition requirements at Federal Acquisition
Regulation (FAR) sect. 6.302-1 (which provision references as
statutory authority, the Competition in Contracting Act (CICA),
41 U.S.C. sect. 253(c)(1)), since the cost-benefit analysis
showed that only one responsible source will meet the agency’s
needs. Agency Report in Response to Agency-Level Protest, Nov.
1, 2007, at 2, 4. The agency-level protest official dismissed
the protest as an untimely challenge to the terms of the
presolicitation notices, and, to the extent the protest
questioned the proposed sole-source award of a succeeding lease
to the incumbent, denied the protest on the basis that the
agency had complied with the requirements of GSAR sect.
570.402-1(b)(2) for a cost-benefit analysis prior to making the
sole-source determination for the lease.
(Sections Deleted)
We have reviewed each of Eisenhower’s challenges to the
cost-benefit analysis and find that none of them provides a
basis to conclude the cost-benefit analysis lacks a reasonable
basis. For instance, Eisenhower initially alleges that its
rental rate is [deleted] per RSF lower than the rate paid by GSA
under the incumbent’s current lease; the protester estimates
that this difference gives it an almost [deleted] million
advantage in terms of cost savings to the government. The agency
reports, however, that Eisenhower’s initial rental rate of
[deleted] is in fact higher than the rates paid under the
incumbent’s lease, and that the subsequent rate information
provided by the two firms showed their properties are indeed
comparable in terms of rent. The record supports the agency’s
position. The protester next argues that since its expression of
interest noted that the firm would like to discuss paying for
the [deleted] costs, it should have received credit against the
[deleted] costs amount in the cost-benefit analysis. The record
supports the reasonableness of the evaluation, however, since,
despite the firm’s failure to quantify its claimed credit for
such costs, or confirm that it would pay all such costs rather
than just a portion, the agency applied an industry standard
amount for such costs [deleted]; the protester has not shown
that the standard amount is unreasonable. Moreover, Eisenhower
has not shown in any way that, given the substantial relocation
and duplication costs assessed against it in the cost-benefit
analysis, even if the full amount of the [deleted] costs
calculated here (approximately [deleted] million) had been
credited to the firm in the analysis, it would have made any
material change to the outcome of the analysis.
Eisenhower also claims that its lease location should be viewed
as presenting additional benefits exceeding the agency’s stated
minimum requirements, thus warranting cost credits in the
comparison of the expressions of interest; examples include the
ability to provide [deleted]; providing space in a newly
refurbished building capable of supporting state-of-the-art
equipment the agency may choose to purchase for its new space;
providing a convenient location, accessible by highways and
Metrorail, with more generous setback distances; and the ability
to design the layout of the space to consolidate office space or
accommodate growth. As a preliminary matter, to the extent that
the protester asserts that the value of the additional
intangible benefits its location allegedly offers was not
quantified by the agency, the protester itself has provided no
support for the dollar value associated with the claimed
benefits. Further, to the extent Eisenhower suggests that the
alleged benefits were ignored by the agency, as the agency
reports, these elements, while not quantified, were considered
in the cost-benefit analysis. For instance, while the agency
noted that Eisenhower could provide additional [deleted], it
considered the current amount [deleted] at the incumbent
location acceptable as it met the agency’s actual needs. While
Eisenhower asserts that the incumbent’s parking presents a
greater security risk because of its below-building location,
Eisenhower is essentially disagreeing with the agency’s judgment
that there is sufficient security at the incumbent site.
Similarly, while the protester’s location offers newly
refurbished space, the record shows that the agency’s space and
equipment needs are met at its current upgraded location.
Regarding the claimed convenience associated with the
protester’s location, the agency points out that the incumbent’s
location is also accessible by highways and Metrorail. As to the
additional setback distance for the protester’s property, since
the incumbent’s property has been government-approved for
setbacks and apparently otherwise meets the agency’s security
requirements, we do not find persuasive the protester’s general
contention that the shorter setback distance at DEA’s current
location presents a security risk, or one that has not been
resolved through other effective security measures. In short,
there is no showing in the record that the cost-benefit analysis
challenged by the protester was unreasonable. (Eisenhower
Real Estate Holdings, LLC, B-310941, March 18, 2008) (pdf)
Brinkmann objects to the proposed sole-source award to Mettler
principally on the ground that its own autotitrator, the Metohm
809 Titrando, which it claims is less expensive than the Mettler
autotitrator, is also technically and functionally equivalent or
superior to the Mettler unit. Accordingly, Brinkmann contends
that the Navy is required to compete the autotitrator
requirement. As a general matter, CICA mandates “full and
open competition” in government procurements obtained through
the use of competitive procedures. 10 U.S.C. sect.
2304(a)(1)(A). CICA, however, provides several exceptions to
this requirement, including when an agency’s requirements can
only be satisfied by one responsible source. 10 U.S.C. sect.
2304(c)(1). When, as here, an agency invokes this exception, it
is required to execute a written J&A with sufficient facts and
rationale to support the use of the cited authority. Our review
of an agency’s decision to conduct a sole-source procurement
focuses on the adequacy of the rationale and conclusions set
forth in the J&A; where the J&A sets forth a reasonable
justification for the agency’s actions, we will not object to
the award. Chapman Law Firm, B-296847, Sept. 28, 2005, 2005 CPD
para. 175 at 3. In this regard, our Office has held that an
agency’s legitimate need to standardize the equipment it uses
may provide a reasonable basis for imposing restrictions on
competition. See, e.g., Advanced Med. Sys., Inc., B-259010, Jan.
17, 1995 (agency’s need to standardize fetal monitors in order
to maximize patient care was reasonable); Sperry Marine, Inc.,
B-245654, Jan. 27, 1992, 92-1 CPD para. 111 (sole-source
acquisition of particular radar system was reasonable where
agency needed to utilize the same radar system it had already
deployed at training school). Based on our review of the record,
we conclude that the Navy had a reasonable basis for the
sole-source award to Mettler. The record shows that the ability
of the Brinkmann autotitrator to meet the Navy’s onboard
technical requirements was not an issue. Rather, the Navy’s
justification for the sole-source award to Mettler is based
upon, among other things, a reasonable need for standardization.
As explained by the Navy, the accuracy and reliability of the
chemical analyses by the autotitrators is essential for the safe
operation of a submarine’s nuclear reactor plant and having a
standard unit allows Navy personnel to operate the autotitrator
equipment without regard to the specific submarine to which they
are assigned. AR, Tab E, J&A at 2. Maintaining the operational
continuity of the autotitrators across submarines is especially
important since Navy personnel operating the units are not
professional chemists and there is “constant turnover” of
personnel between submarines. AR, Tab A, Declaration of
Director, Fleet Readiness Division, Naval Nuclear Propulsion
Program, Aug. 28, 2007, at 1. Because no other autotitrator is
“directly interchangeable in form fit and function” with the
currently fielded Mettler unit, AR, Tab E, J&A at 2, introducing
a different unit would undermine the advantage of having Navy
personnel operate a single standard unit, thereby “increas[ing]
the risk of incorrect chemical analyses,” and in turn increasing
the risk to the safety of Navy personnel and equipment. AR, Tab
A, Declaration of Director, Fleet Readiness Division, Naval
Nuclear Propulsion Program, Aug. 28, 2007, at 1. (Brinkmann
Instruments, Inc., B-309946; B-309946.2, October 15, 2007) (pdf)
As noted, this exception only allows an agency to “limit
the number of sources,” so that an agency may not simply ignore
the potential for competition. See Worldwide Language Res.,
Inc.; SOS Int’l Ltd., B‑296984 et. al., Nov. 14, 2005, 2005 CPD
para. 206 at 11. The mandate for agencies to effect some modicum
of competition is reiterated in 41 U.S.C. sect. 253(e), which
provides that when an agency utilizes other than competitive
procedures based on unusual and compelling urgency, the agency
“shall request offers from as many potential sources as is
practicable under the circumstance.” See also FAR sect.
6.302‑2(c)(2). In addition, CICA provides that under no
circumstances may noncompetitive procedures be used due to a
lack of advance planning by contracting officials or concerns
related to the amount of funds available to the agency. 41 U.S.C.
sect. 253(f)(5)(A); see also FAR sect. 6.301(c). The agency has
not demonstrated that it had a reasonable basis to make the
sole‑source orders here. While at least with respect to the VAMC
Albany facility, the agency has demonstrated that it had an
urgent need to replace the equipment due to the fact that
patients were getting eye infections as a result of the use of
the faulty medical equipment,[3] the agency has not reasonably
demonstrated why it could not have opened the requirement up to
an expedited limited competition among those firms that had
expressed interest in the acquisition. There is no evidence in
the record that the agency ever considered whether the cataract
medical equipment proposed by B&L, or any other firm, would meet
its urgent requirements. Moreover, B&L has responded in detail
to the agency’s sole-source justification by noting that its
Millennium equipment is “state of the art” cataract surgery
equipment and enjoys a significant market share, and by
providing many technical details as to why its equipment is the
best equipment available to meet VA’s requirements. While VA was
invited to respond to B&L’s comments, it has provided no
response to B&L’s detailed comments as to why its equipment
would satisfy VA’s requirements. (Bausch
& Lomb, Inc., B-298444, September 21, 2006) (pdf)
Generally, our Office will not question an agency’s
implementation of a statutory procurement requirement unless the
record shows that the implementation was unreasonable or
inconsistent with congressional intent--a matter best determined
by the words of the statute itself, or by the statute’s
legislative history. See Harris Corp. Broadcast Div., B-255302,
Feb. 10, 1994, 94-1 CPD para. 107 at 6. With respect to
statutory procurement preferences, we have held that where a
statute does not specify a particular way to give a provided
preference to a class of potential contractors, agency
acquisition officials have broad discretion in selecting the way
to effectuate the statutory mandate. American Multi Media,
Inc.--Recon., B-293782.2, Aug. 25, 2004, 2004 CPD para. 158 at 5
(preference for nonprofit institutions concerned with the blind
and other physically handicapped persons); HAP Constr., Inc.,
B‑280044.2, Sept. 21, 1998, 98-2 CPD para. 76 at 4 (preference
for firms doing business in a disaster area under the Stafford
Act); Appalachian Research Council, B-256179, May 20, 1994, 94-1
CPD para. 319 at 15-16 (preference for agencies with
demonstrated experience with the needs of youth in outreach
contracts under the Job Training Partnership Act); and U.S. Def.
Sys., Inc., B-251544 et al., Mar. 20, 1993, 93-1 CPD para. 279
at 4-5 (preference for U.S. firms in the award of contracts for
guard services at overseas embassies). As we noted in our
decision in HAP Constr., and as we have seen again here, neither
the language of the statute, nor the legislative history of the
Stafford Act, defines the terms “preference,” “feasible,” or
“practicable.” HAP Constr., Inc., supra, at 5. Without specific
definitions to guide our review, we look to whether the agency’s
interpretation is contradicted by the plain meaning of the words
used in the statute. In our view, it is not. The primary meaning
of the word “preference” in Black’s Law Dictionary 1217 (8th Ed.
2004) is “[t]he act of favoring one person or thing over
another….” Our review of the bid protest decisions above, and
other materials, shows that agencies have used a continuum of
possible preferences to implement statutes that provide one
class of contractor a preference over others. For example, in
the U.S. Def. Sys., Inc. decision, cited above, the agency
provided a preference in the form of five evaluation points to
be added to an offeror’s technical evaluation. In contrast, FEMA
has opted to implement the provision of the Stafford Act under
review here by providing a 30 percent price preference. 48 C.F.R.
sect. 4452.217-70. While we have not previously seen a protest
involving an agency decision to implement a preference using a
set-aside, we think a set-aside can be viewed as, in effect, an
absolute preference, located at one end of the continuum of
possible preferences an agency might adopt. In our view, we have
no basis for questioning the broader definition of “preference”
inherent in the agency’s position in this case. Moreover, we
think AshBritt misses the point when it argues that some form of
preference short of a set-aside also implements the Stafford
Act’s preference for using local businesses to clean up
disaster-related debris. The question here is not whether some
lesser form of preference might have satisfied the Act’s intent,
but whether the preference chosen was an abuse of agency
discretion. Since the language in the statute does not
specifically restrict the application of the preference, and
since the use of a set‑aside is consistent with the statutory
goal of assisting firms in the affected area, we do not view the
Corps’s decision to implement the Stafford Act preference with a
set‑aside as an abuse of the agency’s discretion to implement
this statutory scheme. See id. at 6; Appalachian Research
Council, supra, at 16. We turn next to AshBritt’s contention
that the Stafford Act does not envision providing a preference
(in this case, a set-aside) only to firms doing business in a
particular state, to the exclusion of firms located in other
states affected by the same natural disaster. As an initial
matter, it is fair to note that AshBritt’s interpretation of the
geographic reach of 42 U.S.C. sect. 5150 appears to be supported
by the portion of the statute that requires this preference be
provided to firms “residing or doing business primarily in the
area affected by such major disaster or emergency.” To conclude,
however, that the Corps abused its discretion by limiting the
competition here to firms within a single state would require us
to ignore the overall scheme of the Stafford Act, the
legislative history of the Act explaining what Congress was
trying to accomplish with this provision, and the simultaneously
enacted title of the preference provision in the Act (which is
now reflected in the U.S. Code). While we think an agency
reasonably might elect not to adopt the kind of restriction used
in this procurement, see, e.g., HAP Constr., Inc., supra, we do
not agree that the Corps acted improperly here by limiting this
competition to Mississippi firms. The entire scheme of the
Stafford Act contemplates a process by which states interact
with, and seek assistance from, the federal government; this
interaction does not cross state lines. For example, federal
assistance under the Stafford Act is triggered by a governor’s
finding that a major disaster has overwhelmed the state’s
ability to provide aid, assistance, and emergency services, and
to reconstruct and rehabilitate devastated areas. 42 U.S.C.
sections 5121, 5170. When a governor presents such a finding to
the President, and the President agrees, the President declares
that a major disaster exists. 42 U.S.C. sect. 5170. This
declaration identifies the specific areas within the state
eligible for disaster relief, and specifies the type of relief
available. 44 C.F.R. sect. 206.40; see also AR, Tabs 5a, 6a, 7a,
and 8a. In addition, the statute, on its face, identifies the
limits of federal cost-sharing available to the state for
different types of relief activities. See, e.g., 42 U.S.C.
sections 5170b(b), 5170c(a), 5173(d). Moreover, as shown by the
record in this protest, there are separate Presidential
declarations for each state, see AR, Tabs 5a (Florida), 6a
(Louisiana), 7a (Mississippi), and 8a (Alabama); there is no
unified disaster declaration addressing all damage done by
Hurricane Katrina, which would be more along the lines of the
scheme AshBritt posits. (AshBritt Inc.,
B-297889; B-297889.2, March 20, 2006) (pdf)
The Competition in Contracting Act (CICA), 10 U.S.C. sect.
2304(c)(2), permits an agency to use other than competitive
procedures in acquiring goods or services where the agency’s
requirement is of such an unusual and compelling urgency that
the government would be seriously injured unless the agency is
permitted to limit the number of sources from which it solicits
proposals. Moreover, while CICA requires that agencies solicit
offers from as many potential sources as is practicable when
using the unusual and compelling urgency exception to limit
competition, 10 U.S.C. sect. 2304(e), an agency nonetheless may
limit a procurement to the only firm it reasonably believes can
properly perform the work in the time available. McGregor Mfg.
Corp., B-285341, Aug. 18, 2000, 2000 CPD para. 151 at 6. In this
regard, a military agency’s assertion that there is a critical
need that is related to human safety and affects military
operations carries considerable weight. Id. at 7. The
reasonableness of the contracting activity’s judgments must be
considered in the context of the time when they were made and
the information that was available at that time. Equa Indus.,
Inc., B-257197, Sept. 6, 1994, 94-2 CPD para. 96 at 3 n.1.
Meggitt asserts that the agency improperly failed to engage in
adequate advance planning. In this regard, Meggitt asserts that,
after obtaining the responses to the RFI, the agency essentially
did nothing for a period of approximately 6 months before
eventually making its sole-source award to KDS. Meggitt
maintains that, among other things, the agency declined its
offer, included in its response to the RFI, to perform testing
of its product at the firm’s own expense, AR, exh. 8, at 5, and
also unreasonably declined its offer, in an April 28 e-mail, to
update its RFI response in April. AR, exh. 35, at 1. Although
the record shows that the agency did not respond to Meggitt’s
April 28 e‑mail, the agency’s Chief of the Marine Corps Program
Division testified that this was because, due to the lack of
funding at that time, the agency did not think it was
appropriate to cause any of the respondents to expend further
effort in preparing materials or information. Tr. at 63. In a
similar vein, he testified that he never specifically declined
Meggitt’s offer to perform testing at its own expense, but that,
again, the agency was reluctant to encourage additional
expenditures by Meggitt or other concerns in the absence of
program funding. Tr. at 109-11. We find nothing unreasonable in
the agency’s actions. Simply stated, the agency acted in a
manner that was prudent under the circumstances, since there
were no funds available and no firm basis for the agency to
conclude that it would be able to perform the upgrade. As noted,
the question for our Office is whether the contracting
activity’s judgments, considered in the context of the time when
they were made and the information that was available at that
time, appear reasonable. Equa Indus., Inc., supra. Further,
regarding Meggitt’s offer to perform testing at its own expense,
in the absence of agency direction not to perform such testing,
there is no basis to find that the agency somehow unreasonably
precluded Meggitt from conducting such testing. Meggitt has not
shown why it could not have performed such testing at its own
expense (and provided the agency with its results), and thereby
possibly positioned itself differently with respect to the
agency’s urgent requirement. In effect, Meggitt’s decision to
refrain from such testing was a matter of its own business
judgment, not improper agency action. We note that the agency’s
witness testified that he would have at least considered the
results of such testing. Tr. at 116‑17. (Meggitt
Safety Systems, Inc., B-297378; B-297378.2, January 12,
2006) (pdf)
Based on the factual context presented with regard to the
December 2004 award to OSS, it is evident that the agency’s
efforts--as described and explained by the agency itself--were
so fundamentally flawed as to indicate an unreasonable level of
advance planning, which directly resulted in the sole-source
award to OSS. In responding to the protesters’ challenges to the
December sole-source award, the Air Force suggests that its
actions and the justification underpinning the sole-source
determination should be evaluated based on the circumstances
faced by the contracting activity in November 2004 when it
received the requirement and took steps to expeditiously procure
the required BBE-SME services. For example, the Air Force
highlights the fact that when the J&A was prepared in support of
the award to OSS, the government was faced with the dilemma of
needing BBA-SME services in place to support the January 2005
elections in Iraq--then only 2 months away--and it did not have
a contractor to provide the services. AR, Tab 13, Supplemental
Legal Memorandum at 15; AR, Tab 1.b.2, J&A para. 3. We recognize
the abbreviated contracting schedule faced by the contracting
activity in its efforts to obtain a contract vehicle for the
BBA-SME requirement--a schedule driven by expectations and
mandates from higher echelons within the Department of Defense.
The record, however, clearly reflects the fact that this narrow
procurement window was the direct result of unreasonable actions
and acquisition planning by the Air Force and the Department of
Defense, to the extent these entities engaged in any acquisition
planning at all. Specifically, 2-3 months were lost as a result
of the initial plan to place the BBA-SME requirement under the
GEITA contract--even though the requirement was clearly outside
the scope of the GEITA contract. As noted above, the GEITA
contract was for advisory and assistance services in support of
AFCEE’s “continued excellence in the world environmental
stewardship market,” including support for AFCEE’s programs
involving environmental restoration, compliance, pollution
prevention, conservation and planning, fuel facility
engineering, base realignment and closure activities, and
military family housing initiatives, to include privatization
and outsourcing activities. AR, Tab 17, GEITA Contract,
Statement of Work, at 3, 4-5. The BBA-SME requirement, however,
was for Western-oriented individuals of Iraqi background, who
were committed to a democratic Iraq, and who would provide
services in Iraq such as advising government ministers, planning
for and implementing elections, drafting constitutional
documents, advising neighborhood, municipal, and national
councils, and training security forces and details. The plan to
use the GEITA contract was unreasonable on its face, given how
widely it diverged from the BBA-SME requirement. In fact, as
indicated above, a senior member within the Air Force,
responsible for acquisition, characterized the plan as requiring
a “sanity check” and indicated that it was the result of
individuals “leaning way forward in the saddle” in an effort to
support a customer because they were “not in the habit of saying
no to anyone.” AR, Tab 16.ss., E-mail, Subject: RE: GEITA
Services for Bilingual-Bicultural Support to Iraq, Nov. 10,
2004. It was this gross error that directly resulted in the Air
Force’s determination to pursue a sole-source award for the
BBA-SME requirement. After the Air Force cancelled the GEITA
plan, it initiated discussions with OSD regarding the option of
making a sole-source award based on urgency. See AR, Tab 16.kk.,
E-mail, Subject: Iraqi Contracting Debacle, Nov. 12, 2004
(stating “[the Air Force] has assured me that [it] should have a
contracting solution by COB today or Monday . . . specifically
mentioned ‘sole-sourcing’ and ‘urgent and compelling’ as options
on any new contract”). (WorldWide
Language Resources, Inc.; SOS International Ltd., B-296984;
B-296984.2; B-296984.3; B-296984.4; B-296993; B-296993.2;
November 14, 2005) (pdf)
Although the overriding mandate of the Competition in
Contracting Act of 1984 (CICA) is for full and open competition
in government procurements obtained through the use of
competitive procedures, 10 U.S.C. sect. 2304(a)(1)(A) (2000),
CICA permits noncompetitive acquisitions in certain
circumstances, such as when the services needed are available
from only one responsible source or when the agency’s need for
the services is of such an unusual and compelling urgency that
the agency would be seriously injured unless permitted to limit
the number of sources solicited. 41 U.S.C. sections 253(c)(1),
(c)(2) (2000). When an agency uses noncompetitive procedures
under sect. 253(c)(1) or (c)(2), it is required to execute a
written J & A with sufficient facts and rationale to support the
use of the cited authority. See 41 U.S.C. sect. 253(f)(1)(A),
(B); Federal Acquisition Regulation (FAR) sections
6.302-1(d)(1), 6.302‑2(c)(2), 6.303, 6.304. Our review of an
agency’s decision to conduct a sole‑source procurement focuses
on the adequacy of the rationale and conclusions set forth in
the J & A; where the J & A sets forth a reasonable justification
for the agency’s actions, we will not object to the award.
Global Solutions Network, Inc., B‑290107, June 11, 2002, 2002
CPD para. 98 at 6. However, noncompetitive procedures are not
justifiable where the agency created the need for the
sole-source award through a lack of advance planning. 41 U.S.C.
sect. 253(f)(5)(A). The justification for the sole-source award
here is reasonable, and there is no basis for finding a lack of
advance planning. As described in the facts above, and as
referenced in the J & A, Chapman’s protest of the award led to
the stay of contract performance. This stay prevented Greenleaf
from transitioning into contract performance as MCB’s contract
approached the end of its transition period, as had been
reasonably contemplated under the procurement scheme.
Consequently, the agency would shortly have no contractor
performing the M & M services. These circumstances together with
the agency’s determination that Chapman lacked the readiness to
perform the services, and not a lack of advance planning, led to
the agency’s decision to award the sole-source bridge contract.
(Chapman Law Firm Company, LPA,
B-296847, September 28, 2005) (pdf)
Total protests that the agency's award of the four contracts on
a noncompetitive basis for sandbags was improper. The
Competition in Contracting Act of 1984 (CICA) provides for the
use of noncompetitive procedures where an agency's need for the
property or services is of such an unusual and compelling
urgency that the United States would be seriously injured unless
the agency is permitted to limit the number of sources from
which it solicits proposals. 10 U.S.C. 2304(c)(2) (2000).
Although CICA requires that the agency request offers from as
many potential sources as is practicable under the
circumstances, 10U.S.C. 2304(e); see Federal Acquisition
Regulation (FAR) 6.302(c)(2), an agency may still limit the
procurement to the only firm it reasonably believes can properly
perform the work in the available time. McGregor Mfg. Corp. ,
B-285341, Aug. 18, 2000, 2000 CPD 151 at 6; Hercules Aerospace
Co. , B-254677, Jan. 10, 1994, 94-1 CPD 7 at 3. We will object
to the agency's determination only where the decision lacks a
reasonable basis. Signals & Sys., Inc. , B-288107, Sept. 21,
2001, 2001 CPD 168 at 12. In this regard, a military agencys
assertion that there is a critical need related to human safety
and which affects military operations carries considerable
weight. McGregor Mfg. Corp. , supra , at 7. The reasonableness
of the contracting officers judgments must be considered in the
context of the time when they were made and the information that
was available at that time. Equa Indus., Inc. , B-257197, Sept.
6, 1994, 94-2 CPD 96 at 3 n.1. We find the contracting officer
had a reasonable basis for the noncompetitive awards. The basic
undisputed facts known to the contracting officer at the time he
decided that it would be necessary to make noncompetitive
awards, providing for delivery of the sandbags in March 2005,
were: (1) the demand for sandbags had increased over the past
year in support of Operations Enduring Freedom and Iraqi
Freedom, (2) sandbags that were being used in Iraq were
deteriorating at an unexpectedly fast rate, (3) the contractor
that had received the largest share of the award under the
previous contract for sandbags--that is, Total--was delinquent
in its deliveries and its performance had been suspended because
of concerns about the compliance with the contracts HUBZone and
domestic manufacturing requirements, and (4) prior awards for
this item were set aside 100 percent for HUBZone firms by the
SBA. In view of the fact that the sandbags were reasonably found
critical to successful military operations, the contracting
officer reasonably determined that the requirement was urgent
and that the procurement process must be expedited through the
multiple noncompetitive awards. Total claims that the
urgency-based noncompetitive contracts were caused by a lack of
advance procurement planning and by the agency's decision to
obtain these sandbags only from HUBZone manufacturers. The
record does not establish that a lack of advance procurement
planning was the cause of this urgent requirement; instead, the
record shows that the urgency of the requirement was caused by
the unexpected rapid deterioration of sandbags, increased demand
for sandbags in Iraq, and the performance problems on Totals
current contract. The record also does not show that the urgency
here was caused by the agency's determination that the sandbag
requirement should be set aside for certified HUBZone firms,
given that four HUBZone firms have been found that are able to
satisfy the agencys urgent delivery requirements. In any case,
FAR 19.1306 provides express authority to make noncompetitive
awards to HUBZone concerns. (Total
Industrial & Packaging Corporation, B-295434, February 22,
2005) (pdf)
Our review of the agency's decision
to conduct a sole-source procurement focuses on the adequacy of
the rationale and conclusions set forth in the J&A. When the J&A
sets forth a reasonable justification for the agency's actions,
we will not object to the award. Global Solutions Network, Inc.,
supra, at 6; Diversified Tech. and Servs. of Virginia, Inc.,
B-282497, July 19, 1999, 99-2 CPD P: 16 at 3. Our review of the
record shows that several of the agency's reasons for concluding
that only IA's system can meet its needs constitute a reasonable
justification for the agency's decision to procure this system
on a sole-source basis. (McKesson
Automation Systems, Inc., B-290969.2; B-290969.3, January
14, 2003) (txt
version)
The agency’s actions here were reasonable. First, there is no evidence of a general
lack of advance planning. As noted, the agency initiated this procurement 18 months
ago, and anticipated acquiring the halfway-house services before the end of 2001.
This planning was thwarted by delays in the evaluation, the filing of two protests,
and the termination of the awarded contract due to irregularities in the procurement.
Thus, while the agency’s planning ultimately was unsuccessful, this was due to
unanticipated events, not a lack of planning. (Bannum,
Inc., B-289707, March 14, 2002; (pdf); (Exception 2))
Protest that agency improperly
awarded requirement on a sole-source basis because it determined
that only one firm could meet its requirements is sustained
where record shows that another potential vendor was given an
incorrect understanding of the agency's requirements; agencies
are required to provide potential sources an opportunity to
demonstrate their ability to meet the agency's requirements
based on an accurate portrayal of the agency's needs. (Lockheed
Martin Systems Integration--Owego, B-287190.2; B-287190.3,
May 25, 2001)
In this regard, a military agency's
assertion that there is a critical need related to human safety
and which impacts military operations carries considerable
weight. Id. at 3; see also BlueStar Battery Sys. Corp.,
B-270111.2, B-270111.3, Feb. 12, 1996, 96-1 CPD para. 67 at 3.
Here, the Army reasonably determined that it had an urgent need
for 273 deswirl ducts and reasonably limited the procurement to
GE, the only firm the Army believed could fulfill the
requirement within the available time. (McGregor
Manufacturing Corporation, B-285341, August 18, 2000)
Protest that agency purchase
order was, in effect, an improper sole-source award is sustained
where the record shows that the Federal Supply Schedule contract
against which the agency attempted to place its order had
expired, and no replacement contract was in place at the time of
the order. (DRS
Precision Echo, Inc., B-284080; B-284080.2, February 14,
2000)
In our view, the J&A
provides an adequate rationale and conclusions to support the
3-month contract extension with six 1-month options at issue.
Although Diversified argues that the agency has been moving too
slowly and that its current situation was caused by a lack of
advance planning, the record demonstrates that the delays have,
in fact, been caused in part by the agency's efforts to plan for
the long term rather than to opt for a short-term
"fix." (Diversified
Technology & Services of Virginia, Inc., B-282497, July
19, 1999) |