|
WorldWide
challenges the modification of MEP's contract to increase the
contract ceiling by $679 million, arguing that the modification
was outside the scope of MEP's underlying contract and therefore
constitutes an improper noncompetitive award in contravention of
the competition requirements established by CICA, specifically,
10 U.S.C. sect. 2304(f)(1)(C) (2006). To the extent the agency
has justified its actions based on a finding that only MEP can
meet the agency's interim need for linguists--a conclusion
disputed by the protester--WorldWide asserts that the
noncompetitive extension of MEP's existing contract was
attributable to a lack of advance procurement planning, which is
also precluded by CICA. 10 U.S.C. sect. 2304(f)(5).
CICA requires that an agency obtain full and open competition in
its procurements through the use of competitive procedures. 10
U.S.C. sect. 2304(a)(1)(A). Exceptions are provided under CICA,
however, where (among other specified exceptions) there is only
one responsible source able to meet the agency's requirements,
10 U.S.C. sect. 2304(c)(1). CICA also provides that
noncompetitive procedures may not be used where agency
contracting officials failed to perform advance planning. 10
U.S.C. sect. 2304(f)(5); HEROS, Inc., B-292043, June 9, 2003,
2003 CPD para. 111 at 6; New Breed Leasing Corp., B-274201,
B-274202, Nov. 26, 1996, 96-2 CPD para. 202 at 6. Our Office has
recognized that the requirement for advance planning does not
mean that such planning must be completely error-free, but, as
with all actions taken by an agency, the advance planning
required under CICA must be reasonable. Barnes Aerospace Group,
B-298864, B-298864.2, Dec. 26, 2006, 2006 CPD para. 204 at 4-5.
Here, WorldWide is challenging the modification of MEP's
existing contract, not the award of a sole-source contract per
se. As a general rule, our Office will not consider protests
against contract modifications, since they involve matters of
contract administration and are beyond the scope of our bid
protest function. See 4 C.F.R. sect. 21.5(a) (2010); DOR
Biodefense, Inc.; Emergent BioSolutions, B-296358.3, B-296358.4,
Jan. 31, 2006, 2006 CPD para. 35 at 6. An exception to this
general rule is where a protester alleges that a modification is
beyond the scope of the original contract, as WorldWide argues
in this case, since, absent a valid sole‑source justification,
the work covered by the modification would be subject to the
competition requirements established under CICA. Engineering &
Prof'l Servs., Inc., B-289331, Jan. 28, 2002, 2002 CPD para. 24
at 3.
In determining whether a modification triggers CICA's
competition requirements, we look to whether there is a material
difference between the modified contract and the contract that
was originally awarded. Engineering & Prof'l Servs, Inc., supra,
at 4. Evidence of a material difference between the modification
and the original contract is found by examining changes in the
type of work, performance period, and costs between the contract
as awarded and as modified. Atlantic Coast Contracting, Inc.,
B-288969.2, June 21, 2002, 2002 CPD para. 104 at 4.
The agency and the intervenor argue that modifying MEP's
contract to increase the contract ceiling by $679 million is not
outside the scope of MEP's underlying contract. In this regard,
they principally assert that the increase in the ceiling level
does not change the type of work required under the contract and
offerors could have reasonably anticipated a modification to
increase the contract ceiling. WorldWide maintains that the
magnitude of the increase in the dollar ceiling implicitly
reflects a change in the nature of the agency's original
requirement and the basis of the original competition, and
therefore renders the modification outside the scope of the
original award.
As discussed below, we do not need to decide the question of
whether the modification is within the scope of MEP's contract
because, even assuming that it was not, the agency properly
supported the modification with a reasonably based J&A under 10
U.S.C. sect. 2304(c)(1).
In challenging the agency's decision to increase the ceiling
under MEP's linguist contract, WorldWide does not in any way
contest the vital role that the linguists play in support of the
U.S. mission in Afghanistan. Rather, WorldWide argues that the
need for a noncompetitive modification was the result of the
agency's failure to adequately plan for the award of a
competitive contract. According to WorldWide, it should have
been "obvious" to the agency by April 2009 that there would be a
need for additional linguists as of that time given that the
military was requesting additional troops and support services
for the efforts in Afghanistan, yet the agency waited until 2010
to take any action to ensure that it could meet the increased
need for linguists. Protester's Opposition to Dismissal Request,
June 8, 2010, at 2, 9; Protester's Comments, supra, at 2.
WorldWide also suggests that the agency's planning for the award
of a competitive contract was unreasonable given the length of
time scheduled for the procurement, approximately 22 months.
According to WorldWide this time period should have been
significantly reduced and can still be shortened further so as
to minimize the period needed for the noncompetitive
modification.
The record reflects that the agency initiated the process of
planning for a competitive award in May 2009. When the need for
greater numbers of linguists became apparent in August 2009, and
was further defined as a consequence of the surge decision in
December 2009, the agency took steps to set an expedited
schedule for the award of a competitive linguist contract--a
process requiring numerous steps, reviews, and milestones.
While WorldWide believes that this period of time could be
greatly compressed, the record does not support its opinion in
this regard. As discussed in the May 3 J&A, the linguist
services are vitally important to the U.S. war effort in
Afghanistan. Further, the anticipated size of the award at issue
is very large; it will be a contract with a value likely in
excess of $1 billion, involving performance by thousands of
contractor personnel at remote locations throughout Afghanistan.
In light of the complexity, scope, and criticality of the
requirements, we have no basis to conclude that the procurement
planning for the competitive linguist award reflects
unreasonable delay or a lack of diligence by the agency. On the
contrary, the record shows that, beginning in May 2009, the
agency has engaged in appropriately deliberate efforts to ensure
a competitive award of a new long-term contract by March 2011.
As noted above, an agency's procurement planning need not be
error-free, it need only be reasonable. Based on the record in
this case, we think that WorldWide's challenge to the agency's
procurement planning efforts are without merit.
We next turn to WorldWide's assertion that the agency's decision
not to compete the interim linguist requirement was
unreasonable. WorldWide challenges the agency's conclusion that
MEP was the only source capable of providing the required
linguist services, arguing that INSCOM's determination was based
on incomplete and flawed market research regarding the
capabilities of potential offerors--WorldWide declares that it
can meet the Army's urgent short-term needs without any
degradation of service. In representing that it is capable of
meeting the agency's requirements, WorldWide relies on its own
linguist assets, as well as those of its potential "teammates"
which are currently performing linguist contracts for U.S. and
coalition forces in Afghanistan and Iraq. Protester's Opposition
to Dismissal Request, supra, at 4.
WorldWide's challenge to the agency's decision is flawed in
several respects. As an initial matter, WorldWide does not
address the agency's determination that even if there were firms
capable of meeting the linguist requirements, conducting a
limited competition among such firms was not a practicable
alternative. As noted above, the J&A expressly found that
conducting a limited competition was not a viable option given
that the award would be for a very short duration (approximately
3 to 5 months), coupled with the fact that conducting such a
competition would undermine the agency's ability to timely award
the long-term linguist contract, and would introduce multiple
transitions during a period of high stress for U.S. forces in
Afghanistan.
The agency has set forth in its J&A, and in its response to the
protest, the challenges associated with awarding and
transitioning a contract of this importance to the military
mission and magnitude--one involving thousands of contractor
personnel operating at over 200 locations throughout
Afghanistan. In this regard, the agency reasonably questioned
the advisability of awarding, and transitioning to, an interim
contract of this size, based on limited competition, only to
have it displaced shortly thereafter by a long-term competitive
contract requiring the same type of large-scale contractor
transition; as indicated by the J&A, the agency reasonably was
concerned that multiple large-scale transitions for these vital
services would increase risk and disruption to U.S. military
capabilities and thereby endanger the military mission and the
lives of U.S. troops. See, e.g., Vertol Sys. Co., Inc.,
B-293644.6 et al., July 29, 2004, 2004 CPD para. 146 at 3 (where
requirement relates to national defense, agency has the
discretion to seek not just reasonable results, but the highest
possible effectiveness). Given this context, we find the agency
reasonably weighed and balanced the impact of conducting a
limited competition against the relatively short duration of any
resulting award, and reasonably concluded that conducting such a
competition was not a viable option. Under these circumstances,
the agency had no alternative other than modifying MEP's
contract so that it could continue providing linguist services
until the agency is able to award the follow-on competitive
contract.
We likewise are not persuaded by WorldWide's challenges to the
market research underlying the J&A prepared by INSCOM. The
record reflects that the agency considered the capabilities of
numerous firms, to include WorldWide, and solicited specific
information regarding the capabilities of GLS, which apparently
is the largest provider of linguist services to the military and
was then operating in Iraq. The agency concluded that none of
the firms, including GLS, was a viable alternative to having MEP
continue providing linguists in Afghanistan. In reaching this
conclusion, the agency reasonably gave paramount consideration
to military operations in Afghanistan, noting that they were at
a critical juncture given the implementation of the U.S. troop
surge. As explained in the J&A, the surge presents a period of
logistical strain and "high operational stress." AR, Tab 6, J&A,
May 3, 2010, at 6. Given the underlying military considerations,
the agency did not believe any contractor could transition the
contract--which, as explained in the J&A and discussed above,
presents unique and difficult challenges, entails providing more
than 6,000+ linguists at 200 locations throughout Afghanistan,
during the surge--without an adverse impact on U.S. forces and
potentially compromising the military's ability to execute its
mission in Afghanistan.
WorldWide maintains that the agency's transition concerns are
overstated, arguing that any transition would have limited
impact since its "team" has a presence in Afghanistan, and the
vast majority of linguist personnel would simply transition to
the new vendor. In this regard, WorldWide cites the J&A, which
states that experience shows that approximately 90 percent of
the incumbent's workforce transitions to the new contractor, and
notes that the agency transitioned GLS's Iraq contract, which
was actually larger, without any difficulty. The record reflects
that the agency considered each of these points, yet concluded
that continuing to obtain linguist services from MEP was the
only viable option given the state of military operations in
Afghanistan.
First, it is important to recognize that this contract involves
more than simply providing a particular number of qualified
linguists. It requires transporting, billeting, feeding, and
paying these individuals at over 200 locations throughout
Afghanistan. While the transition thus must address these
requirements as well, WorldWide focuses almost exclusively on
transitioning the linguist assets themselves. In any event, to
the extent WorldWide complains that the agency did not give
sufficient consideration to its own capabilities, the record
shows that the agency had no basis to believe that WorldWide was
capable of performing the large-scale requirement at issue,
particularly since WorldWide did not provide the agency with any
information regarding its capabilities in response to the RFI
and WorldWide has never performed a contract of this magnitude
in the past. In this regard, the agency expressly concluded that
WorldWide was not a viable source for the current requirements
in view of the small size of its prior Afghanistan linguist
contract, which involved providing approximately 100 linguists,
all of whom had transitioned to MEP's contract when it was
concluded in March 2010. Nor should the agency be faulted for
its failure to have considered WorldWide's "team," given that
the agency did not know, or have reason to know, that any such
team existed. Under these circumstances, the agency did not act
unreasonably in not contacting WorldWide or further
investigating its capabilities or interest. See Chicago Dryer
Co., B-401888, Dec. 8, 2009, 2009 CPD para. 253 at 2 (denying
challenge to an agency's market research in support of a
sole-source award and explaining that an agency is not required
to contact all potential sources when conducting market research
regarding the feasibility of sole-source procurement).
Further, the agency specifically considered the difficulty
associated with transitioning the incumbent workforce, and
expressly noted that a 90 percent transition rate for the
incumbent's linguists would result in an immediate loss of 500
linguists, thereby increasing operational risk at a time of
significant stress on the military due to the surge. AR, Tab 6,
J&A, May 3, 2010, at 4. Moreover, WorldWide's reference to the
alleged ease of the transition under GLS's Iraq linguist
contract is misplaced since the J&A describes the greater
challenges posed by the requirement for linguist services in
Afghanistan. As noted above, the J&A explains that establishing,
managing, and sustaining linguist support services in
Afghanistan is particularly difficult due to the country's
widely dispersed population, which can be located in remote and
isolated regions; literacy problems within the population; the
fact that there are dozens of languages and dialects, and few
locals capable of acting as linguists; and the fact that the
national infrastructure and central government remain limited,
and the economy is rudimentary. Id. Given this record, we have
no basis to question the reasonableness of agency's actions.
In sum, we find that the J&A supports the reasonableness of the
agency's decision to increase the ceiling under MEP's contract,
thereby allowing MEP to continue providing vitally important
linguist services to U.S. forces in Afghanistan, until the time
when the agency can award a competitive contract for these
services. (WorldWide Language
Resources, Inc., B-299315.7; B-299315.8, August 12, 2010)
(pdf)
In determining
whether a modification triggers the competition requirements
under CICA, we look to whether there is a material difference
between the modified contract and the contract that was
originally awarded. Engineering & Prof'l Servs., supra, at 4;
AT&T Commc'ns, Inc. v. Wiltel, Inc., 1 F.3d 1201, 1205 (Fed.
Cir. 1993). Evidence of a material difference between the
modification and the original contract is found by examining
changes in the type of work, costs, and performance period
between the contract as awarded and as modified. Overseas Lease
Group, Inc.,
B-402111, Jan. 19, 2010, 2010 CPD para. 34 at 3; Atlantic Coast
Contracting, Inc.,
B-288969.2, June 21, 2002, 2002 CPD para. 104 at 4. We also
consider whether the solicitation for the original contract
adequately advised offerors of the potential for the type of
changes found in the modification, and thus whether the
modification would have materially changed the field of
competition. See DOR Biodefense, Inc.; Emergent BioSolutions,
supra; Atlantic Coast Contracting, Inc., supra.
As detailed below, we conclude that the record demonstrates that
the scope of the original contract was not substantially changed
by modification 0018, and thus the changes to the contract would
not have had a substantial impact on the field of competition
for the original contract award.
The RFP and resulting Phase 2 contract called for a research and
development (R&D) effort. Unlike contracts for supplies and
services, most R&D contracts are directed toward objectives for
which the work or methods cannot be precisely described in
advance; it is difficult to judge the probabilities of success
or required effort for technical approaches, some of which offer
little or no early assurance of full success. FAR sect. 35.002.
Our decisions have recognized that additional latitude for
modifying a contract may exist where the contract is for R&D
work, noting that the scope of such contracts is often flexible
because of unanticipated changes due to the lack of
definitiveness of the government's requirements. DOR Biodefense,
Inc.; Emergent BioSolutions, supra, at 7; Everpure, Inc.,
B-226395.4, Oct. 10, 1990, 90-2 CPD para. 275 at 4-5.
Additionally, the scope of work of the RFP and original
PharmAthene Phase 2 contract was a broadly-defined one: the
continued advanced development, testing, and production of rPA
anthrax vaccine suitable for FDA licensure, as well as specific
objectives and milestones that were to be accomplished in
support thereof. Given this broad scope of work, we think the
RFP and original contract reasonably contemplated that there
would be developmental changes and setbacks during performance,
including, as here, those resulting from changes in FDA
guidance, manufacturing facility changes, technology transfer
requirements, and additional studies. See AT&T Comm'cns, Inc. v.
Wiltel, supra, at 1205-06 (a broad original scope of work may
validate a broader range of later modifications without further
competition).
The record also reflects that the original objectives of
PharmAthene's Phase 2 contract have not changed, and that
modification 0018 continues rather than alters the original
contract objectives. As stated by the HHS project officer, "[t]he
steps in [the] process have changed over time, but the end
result has remained the same." Tr. at 293. We agree. Where the
type of work under a contract as modified remains substantially
unchanged, we do not view modifications of the technical
requirements of performance to be outside the scope. Atlantic
Coast Contracting, Inc., supra. Furthermore, a technical change
to a contract should be viewed in the context of the
contractor's obligations "as a whole." AT&T Comm'cns, Inc. v.
Wiltel, supra, at 1206. Quite simply, given the broadly-defined,
developmental nature of the PharmAthene Phase 2 contract
requirements, we conclude that modification 0018 does not
represent a material difference in the type of work from the
original contract.
Further, we think that the solicitation for the original
contract adequately advised offerors of the potential for the
type of changes that occurred during the course of contract
performance (i.e., changes in processes and activities but not
objectives), and that in the context of the type of R&D work at
issue here, modification 0018 encompasses changes which the
field of competitors could reasonably have anticipated. DOR
Biodefense, Inc.; Emergent BioSolutions, supra, at 7;
Engineering & Prof'l Servs., supra, at 4.
Emergent argues that the work requirements of modification 0018
are beyond the scope of work of the original contract in one
particular regard. Specifically, the protester contends that the
RFP expressly provided that the original contract would not fund
animal aerosol challenge studies, yet modification 0018 now
funds such studies. Emergent argues that, as a result, this work
is out-of-scope and needs to be competitively procured.
The original solicitation stated, in relevant part,
A critical component of an rPA vaccine database and licensure of
any rPA vaccine will be controlled animal efficacy data and
aerosol challenge data in relevant animal models. However, there
is a worldwide shortage of Biosafety Level 3 aerosol challenge
capacity . . . so it is therefore essential that this capacity
be used as efficiently as possible to generate these crucial
data. . . . Accordingly, [HHS] intends to directly fund the
conduct of the aerosol animal challenge studies associated with
this advanced rPA vaccine development effort through a separate
contract with a separate contractor. . . . This close
government/contractor relationship will enable efficient
implementation of a comprehensive core of well-designed aerosol
challenge studies that should provide quality data to support
product licensure using the animal rule.
AR, Tab 5, RFP at 4.
Thus, while the objectives and milestones in the RFP required a
successful offeror to design, construct, and analyze the animal
aerosol challenge studies necessary for FDA product licensure,
the offeror did not have to perform the actual studies itself.
As HHS essentially made itself a subcontractor to a successful
offeror with regard to the performance of the animal aerosol
challenge studies, tr. at 242-44, the RFP informed offerors that
they did not need to budget for the performance of animal
aerosol challenge studies. By contrast, as part of modification
0018, PharmAthene is to perform such animal aerosol challenge
studies.
In our view PharmAthene's performance of animal aerosol
challenge studies does not materially change the nature of the
original rPA anthrax vaccine development contract. The RFP and
original contract already required PharmAthene to design and
construct animal aerosol challenge studies, receive and evaluate
the resulting data, and submit the data to the FDA as part of
product licensure. What modification 0018 changed was who--PharmAthene
or HHS--was to perform such animal aerosol challenge studies. We
see no basis to conclude that this change materially altered the
type of work required under the original contract, or would have
affected the original field of competition. (Emergent
BioSolutions Inc., B-402576, June 8, 2010) (pdf)
OLG contends that
ANHAM’s contract was limited to armored vehicles, and that
adding unarmored vehicles under the modification exceeded the
scope of the contract and therefore constituted an improper
sole-source award. The Army asserts that the RFP in fact
included unarmored vehicles, stating that in “military parlance,
a non-tactical vehicle (NTV) connotes a commercially available
vehicle that is not armored . . . . Soft-skinned, unarmored and
non-tactical vehicles are adjectives used interchangeably to
denote commercial vehicles without any form of armor.” AR at 2
n.1.
As a general rule, our Office will not consider protests against
contract modifications, since they involve matters of contract
administration and are beyond the scope of our bid protest
function. 4 C.F.R. sect. 21.5(a) (2009); DOR Biodefense, Inc.;
Emergent BioSolutions, B-296358.3, B-296358.4, Jan. 31, 2006,
2006 CPD para. 35 at 6: Engineering & Prof’l Servs., Inc.,
B-289331, Jan. 28, 2002, 2002 CPD para. 24 at 4. An exception to
this general rule is where, as here, a protester alleges that a
modification is beyond the scope of the original contract,
since, absent a valid sole‑source justification, the work
covered by the modification would be subject to the statutory
requirement for competition. Engineering & Prof’l Servs., Inc.,
supra, at 4; Atlantic Coast Contracting, Inc., B-288969.2, June
21, 2002, 2002 CPD para. 104 at 4.
In determining whether a modification triggers the competition
requirements in the Competition In Contracting Act of 1984, 10
U.S.C. sect. 2304(a)(1)(A), we look to whether there is a
material difference between the modified contract and the
contract that was originally awarded. Engineering & Prof’l Servs,
Inc., supra, at 4. Evidence of a material difference between the
modification and the original contract is found by examining
changes in the type of work, performance period, and costs
between the contract as awarded and as modified. Atlantic Coast
Contracting, Inc., supra, at 4. Here, the record is clear that
the purpose and nature of the original contract were not changed
by the modification.
The determinative consideration here is, simply, whether the
requirement as described in the RFP (and resulting contract)
included unarmored vehicles. While the RFP does not refer to
“unarmored” vehicles, per se, in describing the requirement, we
think it nevertheless was sufficiently clear that unarmored
vehicles were encompassed by the RFP. In this regard, in
describing the requirement, as noted, the RFP differentiated
between “non-tactical vehicles” (NTV) and “up‑armored”
vehicles.” It is undisputed in the record that an NTV may be
either armored or unarmored. However, since the RFP here
specifically called for both NTV and “up-armored” vehicles, we
think it should have been clear to the protester that the term
NTV was intended to refer to unarmored NTV. If the protester
were correct that NTV referred only to NTV with armor, there
would have been no logical reason for the RFP to refer to NTV at
all, since up-armored vehicles reasonably would have included
armored NTVs. Moreover, the RFP nowhere defined NTV as armored
vehicles and, while OLG contends that the Army’s definition of
NTV is “flat‑out wrong,” Protester Comments at 2, it has
provided no definitive evidence refuting the agency’s assertion
that the term NTV generally is used to refer to unarmored
vehicles.
OLG maintains that the fact that the RFP and contract specified
“five specific configurations of ‘hard’ (armored) vehicles,” and
no unarmored vehicles, shows that the contract was not meant to
include the ordering or delivery of unarmored vehicles. Protest
at 3. However, the agency made clear from the outset that the
VLPL [Vehicle Lease Price List] was not all-inclusive, and could
be modified in the future. In this regard, as noted above, the
RFP advised offerors that “The [VLPL] will be incorporated into
the contract and may change in accordance with the available
market. . . .” RFP at 77. Consistent with this language,
amendment 5 to the RFP, issued January 9, 2009, included answers
to questions, including the following:
Q4: I am curious if only one brand of transport would be
acceptable?, such as the specified Ford Truck and Van units?
A4: The list of vehicles in the solicitation is representative
of what we have been using and will continue to be diversified.
RFP amend. 5, at 3. In response to another question regarding
the vehicles, the agency advised that the “list of vehicles will
be amended, if required, after award of the contract. Please
quote on the list as provided.” Id. In view of the cited RFP
language, as clarified by the amendment, the listing of only
armored vehicles in the RFP did not preclude the purchase of
unarmored vehicles under the contract.
The protest is denied. (Overseas
Lease Group, Inc., B-402111, January 19, 2010) (pdf)
Sallie Mae argues that the CSB contract, as originally competed
and awarded, did not contemplate the servicing of non-defaulted
FFELP loans, and that modification of the contract to encompass
the servicing of the non-defaulted FFELP loans “put” to the
government pursuant to the loan purchase program is accordingly
beyond its original scope.
The Competition in Contracting Act (CICA) requires “full and
open competition” in government procurements as obtained through
the use of competitive procedures. 41 U.S.C. sect. 253a(a)(1)(A)
(2000). Once a contract is awarded, however, our Office will
generally not review modifications to that contract, because
such matters are related to contract administration and are
beyond the scope of our bid protest function. Bid Protest
Regulations, 4 C.F.R. sect. 21.5(a) (2008); DOR Biodefense,
Inc.; Emergent BioSolutions, B‑296358.3; B-298358.4, Jan. 31,
2006, 2006 CPD para. 35 at 6. An exception to this rule is where
it is alleged that a contract modification is beyond the scope
of the original contract because, absent a valid sole-source
determination, the work covered by the modification would be
subject to the statutory requirements for competition.
Engineering & Prof’l Servs., Inc., B-289331, Jan. 28, 2002, 2002
CPD para. 24 at 3.
In determining whether a modification triggers the competition
requirements in CICA, we look to whether there is a material
difference between the modified contract and the contract that
was originally awarded. MCI Telecomms. Corp., B‑276659.2, Sept.
29, 1997, 97-2 CPD para. 90 at 7. Evidence of a material
difference between the modification and the original contract is
found by examining any changes in the type of work, performance
period, and costs between the contract as awarded and as
modified. Atlantic Coast Contracting, Inc., B-288969.4, June 21,
2002, 2002 CPD para. 104 at 4. We also consider whether the
solicitation for the original contract adequately advised
offerors of the potential for the type of change found in the
modification, and thus whether the modification would have
changed the field of competition. DOR Biodefense, Inc.; Emergent
BioSolutions, supra.
In support of its argument that the servicing of non-defaulted
FFELP loans is beyond the scope of ACS’s CSB contract, the
protester notes that the Statement of Objectives (SOO) in the
CSB solicitation did not describe the servicing of non-defaulted
FFELP loans and that the Student Credit Management Volumes chart
provided as an appendix to the SOO did not furnish a figure for
non-defaulted FFELP loans. Sallie Mae maintains that offerors
could not possibly have contemplated that the CSB contract would
include the servicing of the non-defaulted FFELP loans that are
expected to be put to the government given that the legislation
authorizing the loan purchase program was not enacted until May
2008. The protester also points out that the ECASLA authorizes
the Secretary of Education to contract with eligible lenders for
the servicing of the loans purchased from them and argues that
there would have been no need for the statute to include such
authorization if it were intended that the loans put to the
government be serviced under ACS’s CSB contract.
In response, the agency maintains that the SOO in the CSB
solicitation described the kinds of obligations that the
contractor would be responsible for servicing quite broadly,
providing that “[t]he CSB solution will have the capability to
manage all types of student aid obligations,” and that “[t]hese
obligations include Direct Loans, defaulted debts assigned to
the Department of Education from [FFEL] or other lenders,
rehabilitated loans, and any other type of Title IV student loan
obligation.” SOO, sect. 1.2, as cited in AR at 3-4. (Emphasis
added by agency.)
While we agree with the protester that at the time the CSB
contract was awarded, agency officials and offerors could not
have anticipated that the government would acquire the number of
FFELP loans that lenders now have the option to put to it
pursuant to the loan purchase program, we do not think that this
leads to the conclusion that modification of the CSB contract to
encompass the servicing of these loans would be beyond the
contract’s scope. In our view, the SOO in the CSB solicitation
clearly placed offerors on notice that the agency intended to
award a contract for the management--i.e., the servicing, the
consolidating, and the collecting--of all types of Title IV
student loans, including the types of FFELP loans that the
ECASLA has authorized the government to purchase from lenders,
i.e., Stafford subsidized, Stafford unsubsidized, and PLUS
loans. In this connection, we note that not only did the SOO
state that the CSB solution was to be capable of managing “all
types of student aid obligations,” including direct, defaulted
FFELP, and rehabilitated loans and “any other type of Title IV
student aid obligation,” but it also specifically identified the
Stafford and PLUS loan programs as among the Title IV programs.
Furthermore, the SOO specifically instructed that the CSB
solution was to be flexible enough to handle new requirements
generated by Congress and to respond to legislative mandates and
policy changes. SOO at 33.
We also disagree with the protester’s argument that the
inclusion in the ECASLA of language authorizing the Secretary of
Education to contract with lenders for the servicing of loans
that they sell to the government demonstrates that Congress
contemplated that these loans would not be serviced under the
CSB. We simply have no basis to conclude that this language may
reasonably be interpreted as signaling that Congress intended to
preclude the Secretary from contracting for the services from a
source or sources other than the lenders.
Sallie Mae further argues that the modification of ACS’s CSB
contract to encompass the servicing of the FFELP loans that the
agency will acquire represents an out-of-scope change in the
original contract because it will dramatically increase the
scope of the loan portfolio that ACS is servicing for the
government.
As previously noted, the agency reported to us that ACS expects
to service approximately [deleted]. According to the agency, if
all of the loans that lenders were vested with the option to put
to the government in mid-September are in fact put, about
[deleted] new borrowers would be added to the ACS portfolio, and
the projected cost of servicing these additional borrowers in
2009 would be approximately [deleted]. AR at 3. These figures
were substantially decreased by the agency decision to take
corrective action, however. As previously noted, the agency
expects to award a new contract for servicing of the FFEL loans
by March or April of 2009, and anticipates that the contractor
will be able to begin servicing the loans by August or September
2009. According to the chart summarizing the loans to be put to
the government by borrower and month included in the agency
report at Tab O, [deleted] loans that lenders have a vested
option to put to the government during fiscal year 2009 are to
be put in August, and [deleted] are to be put in September 2009.
In other words, [deleted] of the loans will potentially be
serviced by the new contractor. The addition of the remaining
[deleted] that may be put to the government prior to August
represents an increase of only approximately [deleted] to ACS’s
existing portfolio of [deleted] loans. Such an increase clearly
cannot be characterized as--to use the protester’s
wording--dramatic. Moreover, even assuming that all [deleted]
loans do end up being serviced under ACS’s CSB contract, this
represents an increase of approximately [deleted] percent to
ACS’s existing portfolio. Such an increase in workload volume
does not, in and of itself, signal a modification beyond the
scope of the original contract. See Caltech Serv. Corp.,
B‑240726.6, Jan. 22, 1992, 92-1 CPD para. 94 at 5 (30 percent
increase in workload volume not beyond scope of original
contract). (Sallie Mae, Inc.,
B-400486, November 21, 2008) (pdf)
The protesters argue that the contract was improperly modified
to require delivery of a bivalent serotype A/B vaccine, a
product that was not listed among the optional RFP CLINs. The
RFP identified optional CLINS for monovalent vaccine serotypes A
through G, and a multivalent vaccine for serotypes A, B, D and
F. RFP at B-1. The RFP advised offerors, however, that “[t]he
government reserves the right to change the list above to add or
delete products as need may arise.” RFP at B-1. Where the type
of work under a contract as modified remains substantially
unchanged, we do not view modifications of the technical
requirements of performance to be outside the scope. Atlantic
Coast, supra. Our decisions have acknowledged that additional
latitude for changing a contract may exist where the contract is
for research and development, noting that the scope of such
contracts is often flexible because of unanticipated changes due
to the lack of definitiveness of the government’s requirements.
Everpure, Inc., B-226395, B-226395.4, Oct. 10, 1990, 90-2 CPD
para. 275 at 4-5. Furthermore, a technical change to a contract
should be viewed in the context of the contractor’s obligations
“as a whole.” AT&T Communications, Inc., 1 F.3d at 1206. Here,
the RFP made clear that decisions regarding the specific
vaccines to be developed and produced would be made after award,
and that the agency could add or delete vaccines based on the
government’s needs. RFP at B-1. The RFP and contract, in our
view, anticipated addition and deletion of optional botulinum
vaccines, and thus the change from the RFP’s requirement under
CLIN 0016 for a pentavalent vaccine to a bivalent vaccine that
incorporates two of the serotypes under the pentavalent vaccine
does not fundamentally alter the type of work required under the
contract. See Engineering & Prof’l Servs., supra. (DOR
Biodefense, Inc.; Emergent BioSolutions, B-296358.3;
B-296358.4, January 31, 2006) (pdf)
The agency characterizes the contract modification as a
reasonable effort to ensure that the agency remains in
compliance with EPA regulations for handling of the SBM. The
agency contends that, due to UST's subcontractor's failure to
properly recycle the SBM, UST's ability to comply with the
contract's recycling component was called into question. Thus,
the agency states that in the absence of a viable recycling
option, it modified the contract to allow for disposal
consistent with EPA regulations. The agency argues that the
government's ultimate need for plastic media and the obligation
to comply with EPA regulations regarding the handling of the SBM
have not changed and, thus, the modification was proper. We
disagree with the agency's view that the modification does not
materially change the requirements of the contract or result in
a fundamental change to the nature of the work. The original
solicitation sought proposals that required offerors to both
lease plastic media and recycle the resulting SBM in compliance
with regulations, and offerors were thus required to propose
technical solutions and pricing for both the lease and recycling
components of the work. The fact that the agency still requires
plastic media for its equipment needs and still requires removal
of the SBM from its facilities does not afford the agency
unlimited latitude to modify the way in which it contracts to
meet those requirements. An agency may not modify a contract by
changing or relaxing requirements where the resulting work is
fundamentally different from the work anticipated by the
original solicitation. Marvin J. Perry & Assoc. , supra , at
4-5; Avtron Mfg., Inc. , supra , at 4-5. Here, the RFP did not
anticipate that the contractor could be relieved of the
recycling requirement or that a disposal effort could be ordered
in lieu of recycling. Furthermore, Poly-Pacific contends, and
the agency does not dispute, that the costs of leasing plastic
media with no recycling requirements is as much as 50 percent
less than the costs of leasing plastic media with recycling
requirements. There also appear to be at least 4 approved
sources for providing type V plastic media, including
Poly-Pacific and UST, without the recycling requirement.
Comments, exh. 8, "Media Approved for Air Force Use." Evidence
suggesting that proposals submitted on the basis of a modified
contract's relaxed requirements could result in more competition
and lower prices generally weighs in favor of finding that the
contract modification was improper. Avtron Mfg., Inc. , supra ,
at 5. In sum, the agency's suspension of the recycling
requirement relaxed the performance requirements and modified
the contract beyond the scope of work anticipated by the
underlying solicitation and unmodified contract. In our view,
the modification resulted in a material and fundamental change
to the nature of the work that changed the field of competition
and that work, therefore, should have been competed on a full
and open basis, unless the agency followed the steps required to
conduct the procurement without full and open competition. (Poly-Pacific
Technologies, Inc., B-296029, June 1, 2005) (pdf)
As noted above, the competitive award to Saltwater was based
upon a 1-year contract extending through June 30, 2004 with a
1-year option to June 30, 2005. However, the award to NWO was
for a 6-month contract period from July 1, 2004 toDecember 31,
2004, with an option to extend the contract 1 year, i.e. , to
December31, 2005, which Commerce has exercised. Because the
period of performance under NWO's contract extends beyond June
30, 2005, it is inconsistent with the basis for the competition
and therefore improper. See Tennessee Valley Serv. Co. ,
B188771, Dec. 8, 1977, 77-2 CPD 442. That is, the extension of
NWO's contract beyond June30, 2005 constitutes an improper
sole-source, since it was not supported by a J&A. Since the
contract with NWO now is in its option year, we recommend that
Commerce meet its needs after June 30 competitively (through
limited competition if full and open competition is not
feasible) and terminate NWO's contract as of that date if NWO is
not the successful offeror. We further recommend that the agency
reimburse Saltwater for the costs of filing and pursuing its
protests, including reasonable attorneys' fees. Saltwater's
certified claim for costs, detailing the time spent and cost
incurred, must be submitted to the agency within 60 days of
receiving this decision. 4 C.F.R. 21.8(f)(1) (2004). (Saltwater
Inc.--Reconsideration and Costs, B-294121.3; B-294121.4,
February 8, 2005) (pdf)
CECOM's FedBizOps synopsis explained that the primary
justification for restricting the acquisition to one source was
that deliveries by a source other than MAI would be delayed
unacceptably due to the time required for testing. Lyntronics
failed to substantively address this concern in its April 2
proposal, instead merely asserting, without supporting
explanation or information, that it could have a first article
ready in 3-4 weeks, and the first shipment ready in an
additional month. In light of CECOM's stated concern and
projected 1-year timeframe, it was incumbent upon Lyntronics to
provide specific information detailing its alternative FAT
schedule; absent such information, CECOM had no basis to
determine that Lyntronics would be able to perform the required
tests and deliver batteries within CECOM's timeframe. See Litton
Computer Servs., supra. We conclude that CECOM reasonably
determined that only MAI could satisfy its requirements for the
BA-3547/U battery within the time required, and that the
sole‑source modification of that firm's contract was
unobjectionable. (Lyntronics Inc.,
B-292204, July 22, 2003) (pdf)
Accordingly, the critical question is whether the change in the location of the site for
the construction of the awarded building space is so material to the overall effort
required under the SFO as to be outside of the scope of the lease
awarded here. In answering this question, we look to the purpose and nature of the lease, which here
required much more than an amount of space located at a particular address.
As noted above, the lease here incorporates numerous work performance
requirements ranging from the provision of specific, architecturally defined areas of
building space, highly specialized for the needs of a medical treatment facility, to the
provision of specified management, custodial, and security services. In our view, the
level of detail provided describing the required configuration and provision of the
building space reflects the relative importance to the agency of obtaining space
meeting specific design and functional requirements. In contrast, the SFO’s property
location requirements are only general in nature and scope--wide location
boundaries were provided in the SFO and only general transportation accessibility
was required, reasonably indicating that specific location within the cited area
simply was not a critical factor to the agency, as long as the property was within the
delineated area and reasonably accessible. In other words, we think it is apparent
that the location of the specific site offered--as long as it was within the identified
geographic boundaries and otherwise met all SFO requirements--was not
of particular importance under the SFO. (HG
Properties A, LP, B-290416; B-2904162, July 25, 2002 (pdf))
In determining whether a modification triggers the competition
requirements in the Competition in Contracting Act of 1984, 10
U.S.C. § 2304(a)(1)(A) (2000), we look to whether there is a
material difference between the modified contract and the
contract that was originally awarded. Evidence of a
material difference between the modification and the original
contract is found by examining any changes in the type of work,
performance period and costs between the contract as awarded and
as modified. The question for our review is whether the
original nature and purpose of the contract is so substantially
changed by the modification that the original and modified
contract would be essentially different and the field of
competition materially changed. Engineering &
Professional Servs., Inc., B-289331, Jan. 28, 2002, 2002 CPD
¶ 24 at 4. Here, the Army's modification did not make any
changes to the original nature and purpose of the contract.
First, the front-loading refuse collection service is but one of
multiple refuse collection services to be performed under the
contract, the bulk of which were to be performed using the
contractor's trucks. Contract § C.4. Moreover, the
contract specifically included as one of the multiple line items
the requirement that the contractor would perform the very
front-loading refuse collection services that were the subject
of this modification, albeit with government furnished vehicles.
As noted, the decision to modify the requirement to have the
contractor perform this task with its own vehicles and
containers--as the contractor does on other contract line
items--rather than with government-furnished equipment--as
originally required by the contract--came about only because of
the condition of the government's equipment (and at Atlantic's
suggestion). Since the essence of the requirement was for
the contractor to provide front-loading refuse collection, the
Army's modification, merely shifting the responsibility for the
vehicles and the containers needed to carryout the service to
the contractor, did not substantially change the contract, nor
make it essentially different. (Atlantic Coast Contracting, Inc,
B-288969.4, June 21, 2002
)
In determining whether a
modification triggers the competition requirements in the
Competition in Contracting Act of 1984, 10 U.S.C. sect.
2304(a)(1)(A) (Supp. IV 1998), we look to whether there is a
material difference between the modified contract and the
contract that was originally awarded. Neil R. Gross & Co.,
Inc., supra, at 2-3; see AT&T Communications, Inc. v. Wiltel,
Inc., 1 F.3d 1201, 1205 (Fed. Cir. 1993). Evidence of a material
difference between the modification and the original contract is
found by examining any changes in the type of work, performance
period, and costs between the contract as awarded and as
modified. Access Research Corp., B-281807, Apr. 5, 1999, 99-1
CPD para. 64 at 3-4; MCI Telecomms. Corp., B-276659.2, Sept. 29,
1997, 97-2 CPD para. 90 at 7-8. The question for our review is
whether the original nature or purpose of the contract is so
substantially changed by the modification that the original and
modified contract would be essentially different, and the field
of competition materially changed. Everpure, Inc., B-226395.4,
Oct. 10, 1990, 90-2 CPD para. 275 at 4. The RFP thus clearly
described the CHS-2 program as dynamic, and contemplated that
the contractor would incorporate new technologies as they became
available. Where, as here, a contractor provides more
technologically advanced equipment pursuant to a modification
within the scope of the basic contract--i.e., the fundamental
nature and purpose of the underlying contract remains
unchanged--the modification is not improper. See Hewlett Packard
Co., B-245293, Dec. 23, 1991, 91-2 CPD para. 576 at 3-4. (Engineering
& Professional Services, Inc., B-289331, January 28,
2002)
ARC's argument here overlooks the
fact that with each modification, the terms of MERC's basic
contract were changed to accommodate the agency's overall need,
as reflected in modification No. 06, to digitize the entire TO
warehouse. Accordingly, a comparison of modification No. 16 to
delivery order No. 0005, without regard to the impact of the
intervening modifications--especially modification No. 06, which
contemplated the digitization of the entire TO warehouse--on the
terms of MERC's basic contract, would not be appropriate, since
such a comparison would disregard the new contract
requirements.
The protester has not
established that the fundamental nature and purpose of MERC's
contract, as modified, were materially changed by modification
No. 16 so as to require a separate competition. (Access
Research Corporation, B-281807, April 5, 1999) |