New
Capture contends that it submitted a valid and enforceable bid
bond. In this regard, Capture argues that the letter attached to
its bid bond merely disclosed a third-party indemnification
arrangement, which Capture argues is a standard business
practice. Capture contends that the letter does not place any
restrictions or conditions on the government or limits the VA’s
rights against the surety. Protest at 3.
The determinative question in judging the sufficiency of a bid
guarantee such as a bid bond is whether it could be enforced if
the bidder subsequently fails to execute required contract
documents and to provide performance and payment bonds. TJ’s
Marine Constr. LLC, B-402227, Jan. 7, 2010, 2010 CPD ¶ 19 at 3.
The bid bond must clearly establish the liability of the surety;
when the liability is not clear, the bond is defective. BW JVI,
LLC, B-401841, Dec. 4, 2009, 2009 CPD ¶ 249 at 3.
Here, we find that the agency properly rejected Capture’s
proposal. The express language of the letter attached to
Capture’s bid bond indicated to the agency that the surety’s
obligation under the bond was based upon undisclosed conditions.
In this regard, the letter specifically stated that the surety
had been assured by Capture that the agency had been notified of
the conditions, the record shows that Capture had not informed
VA of any conditions (either prior to submitting its proposal or
along with the proposal). Thus, the VA could not know what
conditions had been placed upon the surety’s obligation or
whether the surety would be liable on the bond in the event of
Capture’s default. Given this, we agree with the agency that the
attached letter created uncertainty as to the obligation of the
surety to the government.
The protester has made various arguments attempting to explain
away the attached letter. For example, Capture essentially
contends that the agency should not have considered the attached
letter as conditioning the surety’s obligations where the face
of the bid bond, SF 24, stated that the surety would be bound.
The protester also parses the words of the attached letter to
argue that because the letter stated in the past tense that the
surety agreed to be bound, all of the conditions had been met.
None of these arguments has any merit. The fact remains that, in
its proposal, Capture provided a letter attached to its bid
bond, and the express language of the letter reasonably
indicated to the agency that the surety’s obligations were
conditioned upon unstated terms.
In short, the liability of Capture’s surety is uncertain, and
therefore the bid bond was properly rejected. (Capture,
LLC, B-406284, Mar 23, 2012) (pdf)
A bid guarantee is a form of security that ensures that a bidder
will not withdraw its bid within the period specified for
acceptance and, if required, will execute a written contract and
furnish required performance and payment bonds. Federal
Acquisition Regulation (FAR) sect. 28.001. The bid guarantee
secures the surety's liability to the government, thereby
providing funds to cover the excess costs of awarding to the
next eligible bidder in the event that the bidder awarded the
contract fails to fulfill these obligations. A.W. and Assocs.,
Inc., B-239740, Sept. 25, 1990, 90-2 CPD para. 254 at 2; General
Ship and Engine Works, Inc., B-184831, Oct. 31, 1975, 75-2 CPD
para. 269 at 2.. When required by a solicitation, a bid
guarantee is a material part of the bid and must be furnished
with it. Hostetter, Keach & Cassada Constr, LLC, B-403329, Oct.
15, 2010, 2010 CPD para. 246 at 3. Noncompliance with a
solicitation requirement for a bid guarantee generally renders
the bid nonresponsive and requires the rejection of the bid. FAR
sect. 28.101-4(a); A.W. and Assocs., Inc., supra.
Responsiveness of a bid is determined from an examination of the
face of the bid bond provided by a bidders' surety, and is
limited to whether the surety is clearly bound by the terms of
that bid bond. Stay, Inc., B-237073.2, Feb. 26, 1990, 90-1 CPD
para. 225 at 3. Thus, we have repeatedly held that a bid bond is
defective, rendering a bid nonresponsive, if it is not clear
that the bond will bind the surety. All Star Maint., Inc.,
B-234820, Mar. 24, 1989, 89-1 CPD para. 305 at 2. On the other
hand, when a required bid bond is found to be proper on its
face, the bond is acceptable and the bid responsive. Contract
Servs. Co., Inc., B-226780.3, Sept. 17, 1987, 87‑2 CPD para. 263
at 2-3. Specifically, where a corporate surety is designated, a
bid bond is proper "on its face" when it has been duly executed
by the surety's agent, the surety has agreed to be obligated for
the penal amount of the bond, and the surety appears on the
Treasury Circular list of acceptable sureties. See Stay, Inc.,
supra, at 3.
As indicated, the agency acknowledges that Shaka's bid bond is
proper on its face. AR at 4. Nonetheless, the agency claims that
it cannot be assured that the surety will honor the bid bond
since it appears to be contingent upon a continuing future
contractual relationship between Shaka and Fay. AR at 3. Thus,
the agency contends that Shaka's bid bond was reasonably deemed
to be defective because the surety's liability was limited by
Shaka's disclosure letter. AR at 5
We disagree with the agency's conclusion. Even assuming that the
principal on a bid bond (that is, the bidder) could
independently limit the liability of the surety under the bond,
the Shaka disclosure letter contains no such limits. Instead,
the letter simply advised the agency that it was obtaining its
bid bond from Liberty Mutual because of its subcontractor's
relationship with that surety. In addition, the letter requested
the agency to notify the surety if this arrangement created an
affiliation between the companies that could be seen as
violating certain rules and regulations applicable to small
business status. While the Corps asserts that this letter could
allow the surety not to honor the bid bond in the event that Fay
is no longer Shaka's subcontractor, this letter in no way alters
the surety's obligation to the Government under the bid bond,
which was executed without reservation or limitation. In this
regard, Shaka is the only principal named on the bond, Fay is
not mentioned in the bond, and the bond does not condition the
surety's liability on the relationship between Shaka and Fay.
Consequently, we find that the surety is clearly bound by the
terms of the bid bond and that Shaka's bid was responsive.
(Shaka, Inc., B-405552, November
14, 2011) (pdf)
IMC's proposal, 1 of 48 submitted, was evaluated as overall
satisfactory. However, the agency found that IMC's bid bond was
legally insufficient because it was not an original, lacked an
original surety agent's signature, and failed to demonstrate
that a duly authorized IMC officer had executed the bid bond.
The agency thus excluded IMC's proposal from further
consideration for award. The agency selected five contractors to
participate in the MATOC and awarded a seed task order for
construction of the Albritton Junior High School at Fort Bragg,
North Carolina. After notice of the awards and a written
debriefing, IMC filed this protest.
IMC protests the agency's rejection of its proposal as legally
insufficient, asserting that it submitted an original, duly
executed bid bond. Specifically, IMC maintains that, in
accordance with the RFP's instructions, it submitted both an
original proposal Volume I (stamped "original") which included
the original bid bond, and a copy which included a photocopy of
the bid bond. IMC speculates that the contracting officer
mistakenly furnished the attorney reviewing IMC's bid bond with
the copy instead of the original bid bond. Since the only
version of IMC's proposal Volume I retained by the agency is not
marked "original" and contains a photocopy of the bid bond,
Agency Response to Initial Comments para. 6, IMC further
speculates that the agency destroyed the original bid bond by
mistake. In support of its position, IMC has submitted
affidavits from the employees who prepared its proposal that
attest to the inclusion of the original bid bond, and a letter
from its surety attesting to its provision of an original bid
bond. Affidavits of Corporate Secretary and Program Manager;
Surety Letter. The contracting officer and specialist, on the
other hand, have submitted sworn statements that "to the best of
[their] knowledge," IMC submitted a photocopy and not an
original of its bid bond. Declarations of Contracting Officer
and Contract Specialist.
The determinative question in judging the sufficiency of a bid
guarantee such as a bid bond is whether it could be enforced if
the bidder subsequently fails to execute required contract
documents and to provide performance and payment bonds. TJ's
Marine Constr., LLC, B-402227, Jan.7, 2010, 2010 CPD para. 19 at
3. The bid bond must clearly establish the liability of the
surety; when the liability is not clear, the bond is defective.
BW JVI, LLC, B-401841, Dec. 4, 2009 CPD para. 249 at 3. In
general, copies of bid guarantee documents do not satisfy the
requirement for a bid guarantee since there is no way, other
than referring to the original documents, for the agency to be
certain that there had been no alterations to which the surety
had not consented and could use as a basis to disclaim
liability. TJ's Marine Constr., LLC, supra.
Here, the RFP expressly provided that photocopied bid guarantees
would not be acceptable. Further, where, as here, award is made
on the basis of initial proposals without discussions,
noncompliance with a solicitation requirement for a bid
guarantee requires rejection of the proposal as unacceptable,
except in situations not present here. FAR sect. 28.101-4. Since
the record indicates that at the time of review, IMC's bid bond
was determined to be a photocopy, the agency properly rejected
IMC's initial proposal.
IMC's assertion that the agency must have discarded IMC's
original bond, provides no basis for relief. Agencies have a
fundamental obligation to have procedures in place to receive
submissions from competitors under a solicitation, to reasonably
safeguard submissions received, and to fairly consider all
submission received. Safety and Health Consulting Servs., Inc.,
B‑290412, June 10, 2002, 2002 CPD para. 95 at 2. As a practical
matter, however, even with appropriate procedures in place, an
agency may lose or misplace a submission, and such occasional
loss generally does not entitle an aggrieved competitor to
relief. Joint Venture Penauillie Italia S.p.A, B‑298865,
B‑298865.2, Jan. 3, 2007, 2007 CPD para. 7 at 6.
This result is justified by the unique circumstances arising in
protests concerning lost information. The only means generally
available to establish the content of allegedly lost information
is for the offeror to reconstruct that information. However,
allowing the offeror to do so would be inconsistent with
maintaining a fair competitive system. Shubhada, Inc., B-292437,
Sept. 18, 2003, 2003 CPD para. 161 at 3-4. Here, there is
nothing in the record to independently establish the contents of
IMC's original proposal Volume I. In this regard, IMC's
corroborating evidence (employee affidavits and surety letter)
does not constitute independent corroborating evidence of the
original version's contents, including whether it contained an
original bid bond instead of a photocopy. See Jay-Brant Gen.
Contractors, B-274986, Jan. 10, 1997, 97‑1 CPD para. 17 at 4
(employee statement attesting to submission of original bid bond
is insufficient to establish submission of original bond); P.W.
Parker, Inc., B-190286, Jan. 6, 1978, 78-1 CPD para. 12 at 3
(evidence from surety, with substantial interest in procurement,
cannot be considered independent evidence).
Our office has recognized a limited exception to the rule that
negligent loss of proposal information does not entitle the
offeror to relief. The exception generally applies where the
loss was not an isolated act of negligence, but rather arises
out of a systematic failure in the agency's procedures that
typically results in multiple or repetitive instances of lost
information. Project Res., Inc., B-297968, Mar. 31, 2006, 2006
CPD para. 58 at 2; Shubhada, Inc., supra, at 4. The exception
does not apply here as there is no evidence--and IMC has not
suggested--that the agency has, for example, lost the proposal
information submitted by other offerors, or previously lost
proposal information.
In sum, even accepting the possibility that the agency lost or
destroyed the original bid bond, on this record, we believe the
agency reasonably rejected IMC's proposal as unacceptable.
(Islands Mechanical Contractor, Inc.,
B-404275, January 24, 2011) (pdf)
Hostetter argues that the discrepancies between its bid and bid
bond are minor informalities that do not cast into doubt that
the bidder and the bid bond principal are the same entity.
The VA disagrees that the discrepancy is a minor informality,
arguing that because the names of the bidder and the bid bond
principal are different, it is not clear that the bond would
bind the surety. The VA states that VA's Information Letter
049-05-11 provides guidance to the agency's contracting officers
regarding their review of surety bonds; this letter generally
informs contracting officers that the name of the bid bond
principal and the bidder must be the same, and that the type of
organization shown on the bid bond must be the same as that on
the bid or in ORCA. AR at 3‑4.
A bid guarantee is a form of security that ensures that a bidder
will not withdraw its bid within the period specified for
acceptance and, if required, will execute a written contract and
furnish required performance and payment bonds. FAR sect.
28.001. The bid guarantee secures the surety's liability to the
government, thereby providing funds to cover the excess costs of
awarding to the next eligible bidder in the event that the
bidder awarded the contract fails to fulfill these obligations.
A.W. and Assocs., Inc., B-239740, Sept. 25, 1990, 90-2 CPD para.
254 at 2. When required by a solicitation, a bid guarantee is a
material part of the bid and must be furnished with it. A.D. Roe
Co., Inc., B-181692, Oct. 8, 1974, 74-2 CPD para. 194 at 3.
Noncompliance with a solicitation requirement for a bid
guarantee generally renders the bid nonresponsive and requires
the rejection of the bid. FAR sect. 28.101-4(a); A.W. and
Assocs., Inc., supra, at 2.
The sufficiency of a bid guarantee depends on whether the surety
is clearly bound by its terms; when the liability of the surety
is not clear, the bond is defective. Techno Eng'g & Constr.,
Ltd., B-243932, July 23, 1991, 91-2 CPD para. 87 at 2. Under the
law of suretyship, no one incurs a liability to pay the debts or
perform the duties of another unless that person has expressly
agreed to do so. Andersen Constr. Co.; Rapp Constructors,
Inc., B‑213955, B-213955.2, Mar. 9, 1984, 84-1 CPD para. 279 at
4. Thus, generally, a bid bond which names a principal different
from the bidder is deficient, and the bid must be rejected
unless it can be established that the different names identify
the same entity. Goss Fire Protection, Inc., B-253036, Aug. 13,
1993, 93‑2 CPD para. 97 at 4; A.D. Roe Co., Inc., supra, at 4-5.
On the other hand, where the entity that submitted the bid and
that is identified as the bid bond principal are exactly the
same, any discrepancy between the bidder's and bid bond
principal's names is merely a matter of form that does not
require rejection of the bid. BW JV1, LLC, B-401841, Dec. 4,
2009, 2009 CPD para. 249 at 3. The proper question to be
considered is whether the nominal bidder and bid bond principal
are the same entity, such that it is certain that the surety
will be obligated under the bond to the government in the event
that that bidder withdraws its bid within the period specified
for acceptance or fails to execute a written contract or furnish
required performance and payment bonds. Harris Excavating,
B-284820, June 12, 2000, 2000 CPD para. 103 at 4.
Here, Hostetter's bid itself establishes that the bidder and the
bid bond principal are the same entity. Although the bid
identifies the bidder as "Hostetter, Keach & Cassada, LLC," the
bid also includes a DUNS number, ORCA representations and
certifications, and certified articles for incorporation that
identify the bidder to be "Hostetter, Keach & Cassada
Construction, LLC." Moreover, the address identified for the
bidder and bid bond principal is the same, and the bid and bid
bond are signed by the same individual, who identified himself
as vice-president. The record thus shows that the bidder and bid
bond principal are the same entity, despite the omission of
"Construction" from the name of the bidder. This minor
informality or irregularity should have been waived by the
contracting officer. See FAR sect. 14.405.
We recommend that the VA make award to Hostetter, as the entity
that submitted the lowest responsive bid, if the protester is
otherwise found to be responsible. We also recommend that the VA
reimburse the protester the reasonable costs of filing and
pursuing the protest, including attorneys' fees. 4 C.F.R. sect.
21.8(d)(1) (2010). The protester should submit its certified
claim for such costs, detailing the time expended and the costs
incurred, directly to the contracting agency within 60 days
after receipt of this decision. (Hostetter,
Keach & Cassada Construction, LLC, B-403329, October 15,
2010) (pdf)
The sufficiency of a bid bond relates to whether the government
will receive full and complete protection in the event that the
bidder fails to execute the required contract documents and
deliver the required performance and payment bonds. BW JVI, LLC,
B-401841, Dec. 4, 2009, 2009 CPD para. at 3. As such, a required
bid bond is a material condition of an IFB with which there must
be compliance at the time of bid opening; when a bidder submits
a defective bid bond or uncertainty exists at the time of bid
opening that the bidder has furnished a legally binding bond,
the bid itself is rendered defective and must be rejected as
nonresponsive. See Blakelee Inc., B-239794, July 23, 1990, 90-2
CPD para. 65 at 4; A & A Roofing Co., Inc., B‑219645, Oct. 25,
1985, 85-2 CPD para. 463 at 1-2.
The determinative question in judging the sufficiency of a bid
guarantee such as a bid bond is whether it could be enforced if
the bidder subsequently fails to execute required contract
documents and to provide performance and payment bonds. Southern
California Eng'g Co., Inc., B‑232390, Oct. 25, 1988, 88-2 CPD
para. 391 at 1. For the bid guarantee to be viewed as
enforceable, the surety must appear to be clearly bound based on
the information in the possession of the contracting officer at
the time of bid opening. Frank & Son Paving, Inc., B-272179,
Sept. 5, 1996, 96-2 CPD para. 106 at 1. Copies of bid guarantee
documents, whether transmitted electronically or hand-delivered,
generally do not satisfy the requirement for a bid guarantee
since there is no way, other than by referring to the original
documents after bid opening, for the contracting agency to be
certain that there had not been alterations to which the surety
had not consented and could use as a basis to disclaim
liability. Excel Bldg. & Dev. Corp., B-401955, Dec. 23, 2009,
2009 CPD para. __ at 3. See Jay‑Brant Gen. Contractors,
B-274986, Jan. 10, 1997, 97-1 CPD para. 17 at 3; G&A Gen.
Contractors, B‑236181, Oct. 4, 1989, 89-2 CPD para. 308 at 1.
Here, we find that the USACE properly rejected TJ's Marine's
bid. The bid bond submitted with the protester's bid did not
contain the surety's agent's original signature. Without
referring, after bid opening, to the document containing the
surety agent's original signature, the USACE cannot ascertain
whether or not there had been alterations to which the surety
had not consented and could use as a basis to disclaim
liability. Accordingly, TJ's Marine's bid guarantee cannot be
viewed as enforceable based on the information in the possession
of the contracting officer at the time of bid opening.
We do not agree with the protester that the E-SIGN Act requires
the USACE to accept the copy of the surety agent's signature on
TJ's Marine's bid bond. The E‑SIGN Act provides that a
governmental agency need not accept electronic signatures with
respect to a contract. See Excel Bldg. & Dev. Corp., supra, at
4, citing 15 U.S.C. sect. 7001(b)(2), FAR sect. 4.502. TJ's
Marine's arguments concerning the FRE are also without merit.
The FRE govern the admission of evidence in federal courts. They
do not, however, answer the issue here as to whether an agency
can ascertain at bid opening whether or not a copied document
has been altered from the original. See id. at 4 n. 3.
We also disagree with the protester's suggestion that extrinsic
evidence may be submitted after bid opening to establish the
enforceability of a bid bond that contained only a copy of the
surety agent's signature. Extrinsic evidence may be submitted
after bid opening to resolve any minor discrepancies between the
principals named on the bid and bid bond, BW JVI, LLC, supra, at
3-4, or to resolve questions regarding the authority of an agent
to bind the bidder or surety, Siska Constr. Co., Inc.--Recon.,
supra, at 4. The issue here, however, does not involve
discrepancies between named principals or the authority of
agents. Rather, as discussed above, the question in this case is
whether the contracting agency could be certain at the time of
bid opening that there had not been alterations to the copied
bid bond to which the surety had not consented and could use as
a basis to disclaim liability. In such cases, the bond's
deficiency may not be cured by requesting submission of the
original bond documents after bid opening because this would
essentially provide the bidder with the option of accepting or
rejecting the award by either correcting or not correcting the
bond deficiency, which is inconsistent with the sealed bidding
system. Bird Constr., B‑240002; B-240002.2, Sept. 19, 1990, 90-2
CPD para. 234 at 2. (TJ's Marine
Construction LLC, B-402227, January 7, 2010) (pdf)
Excel, which submitted the apparent low bid, provided a bid bond
that contained the original signature of the principal and a
copy of the surety agent’s signature and seal. The contract
specialist contacted the surety, who informed her that the
original bond would have an original seal affixed to it. The
contract specialist also contacted the surety’s agent, who
signed the bond, and he explained that he had emailed a copy of
the bond to Excel and that the original, which he sent by FedEx,
was received by the protester after bid opening. Agency Report
(AR), Tab 8, Contracting Specialist’s Memorandum, at 1. The
agency rejected the protester’s bid as nonresponsive and awarded
the contract to the second low bidder. Contracting Officer’s
Statement at 2. This protest followed.
Excel argues that it in fact submitted an original bid bond,
explaining that its submitted bid bond was an original print of
the bond emailed to it by the surety’s agent. Protest at 1. The
protester argues that “once the contents of the email were
printed and signed by Excel . . . an original bid bond was
created.” See Protester’s Comments at 2. The protester also
contends that the signatures and seals on the bond are clear and
legible and that the bond is binding regardless of whether the
signatures are in their original ink, and adds that the power of
attorney accompanying the bond expressly states that “[t]he
corporate seal is not necessary for the validity of any bonds .
. . [and t]he signature of any such officer and the corporate
seal may be printed by facsimile.” Protester’s Response to
Agency’s Dismissal Request at 1-2, citing Excel’s Bid Bond at 3.
According to the protester, signing, sealing, emailing, and then
physically mailing the bond is standard industry practice. See
Protester’s Comments at 1, 3. Moreover, the protester argues
that the Uniform Electronics Transactions Act (UETA) and the
Electronic Signatures in Global and National Commerce (E-SIGN)
Act have legitimized the use of email as a binding method of
conducting business, and the Federal Rules of Evidence (FRE)
recognizes a print-out of an email to be an original document.
Id. at 2-3, citing FRE Rule 1001(3).
The agency responds that the protester did not submit an
original bid bond, which raised questions as to whether the bid
document was altered. AR at 1. In this regard, the Forest
Service questions why the surety would send the original bond
document by FedEx if, as the protester argues, the emailed
version was the original. The agency adds that it is not
concerned with whether the power of attorney is binding because
photocopies or facsimile copies of powers of attorney are
permitted under the Federal Acquisition Regulation (FAR). See
FAR sect. 28.101-3 (2009). Citing the IFB’s incorporation of FAR
sect. 52.228-1(a), which provides that “[f]ailure to furnish a
bid guarantee in the proper form and amount, by the time set for
opening of bids, may be cause for rejection of the bid,” the
agency argues that it properly rejected the protester’s bid in
accordance with that provision and FAR sect. 14.404-2(j) (bid
shall be rejected where bidder fails to furnish bid guarantee in
accordance with requirements of IFB).
The sufficiency of a bid bond relates to whether the government
will receive full and complete protection in the event that the
bidder fails to execute the required contract documents and
deliver the required performance and payment bonds. BW JVI, LLC,
B-401841, Dec. 4, 2009, 2009 CPD para. at 3. As such, a required
bid bond is a material condition of an IFB with which there must
be compliance at the time of bid opening; when a bidder submits
a defective bid bond or uncertainty exists at the time of bid
opening that the bidder has furnished a legally binding bond,
the bid itself is rendered defective and must be rejected as
nonresponsive. See Blakelee Inc., B--239794, July 23, 1990,
90--2 CPD para. 65 at 4; A & A Roofing Co., Inc., B--219645,
Oct. 25, 1985, 85--2 CPD para. 463 at 1-2.
The determinative question in judging the sufficiency of a bid
guarantee such as a bid bond is whether it could be enforced if
the bidder subsequently fails to execute required contract
documents and to provide performance and payment bonds. Southern
California Eng’g Co., Inc., B‑232390, Oct. 25, 1988, 88-2 CPD
para. 391 at 1. For the bid guarantee to be viewed as
enforceable, the surety must appear to be clearly bound based on
the information in the possession of the contracting officer at
the time of bid opening. Frank & Son Paving, Inc., B-272179,
Sept. 5, 1996, 96-2 CPD para. 106 at 1. Copies of bid guarantee
documents, whether transmitted electronically or hand-delivered,
generally do not satisfy the requirement for a bid guarantee
since there is no way, other than by referring to the original
documents after bid opening, for the contracting agency to be
certain that there had not been alterations to which the surety
had not consented and could use as a basis to disclaim
liability. See Jay‑Brant Gen. Contractors, B-274986, Jan. 10,
1997, 97-1 CPD para. 17 at 3; G&A Gen. Contractors, B-236181,
Oct. 4, 1989, 89-2 CPD para. 308 at 1.
Moreover, a bond deficiency may not be cured by submitting the
original bond documents after bid opening because this would
essentially provide the bidder with the option of accepting or
rejecting the award by either correcting or not correcting a
bond deficiency, which is inconsistent with the sealed bidding
system. Bird Constr., B-240002; B-240002.2, Sept. 19, 1990, 90-2
CPD para. 234 at 2. For this reason, a surety’s post-bid opening
letter to the contracting officer cannot establish the liability
of the surety and responsiveness of the protester’s bid. A
nonresponsive bid cannot be made responsive after bid opening
through an explanation of what the bidder or surety intended.
Design for Health, Inc., B-239730, Sept. 14, 1990, 90-2 CPD para.
213 at 3.
Here, we find that the Forest Service properly rejected Excel’s
bid. The bid bond submitted with the protester’s bid did not
contain the surety’s agent’s original signature and seal.
Without referring, after bid opening, to the document containing
the surety agent’s original signature, the Forest Service cannot
ascertain whether or not there had been alterations to which the
surety had not consented and could use as a basis to disclaim
liability. Accordingly, Excel’s bid guarantee cannot be viewed
as enforceable based on the information in the possession of the
contracting officer at the time of bid opening.
We do not agree with Excel that the E-SIGN Act requires the
Forest Service to accept the copy of the surety agent’s
signature on Excel’s bid bond as an original signature. Rather,
the E-SIGN Act provides that a governmental agency need not
accept electronic signatures with respect to a contract. See 15
U.S.C. sect. 7001(b)(2). In this regard, the FAR provides that
agencies may accept electronic signatures and records in
connection with government contracts, see FAR sect. 4.502(d),
but also recognizes that in allowing the use of electronic
commerce, agencies may have to supplement electronic
transactions “by using other media to meet the requirements of
any contract action governed by the FAR (e.g., transmit hard
copy of drawings).” See FAR sect. 4.502(a). (Excel
Building & Development Corporation, B-401955, December 23,
2009) (pdf)
The protester's bid identified the bidder as "BW JV1" of 2735 S.
Krahn Road, New Berlin, Wisconsin, and was signed by Bruce Witt,
President, and Keith Harenda, Project Director. The accompanying
bid bond identified the principal as "BW JVI" of 1237 W. Bruce
Street, Milwaukee, Wisconsin, and contained signatures that
appeared to be those of Messrs. Witt and Harenda. The principal
on the bid bond was identified as a "joint venture" under the
"Type of Organization" section of the bid bond. Attached to the
bid bond was a notarized "Acknowledgement of Principal" that
identified the principal that executed the "foregoing
instrument" (that is, the bid bond) to be "KPH Construction
Corp."; this acknowledgment was signed by Keith P. Harenda as
President of KPH Construction Corp. AR, Tab 4, BW JV1 Bid.
(sections deleted)
The protester
contends that the bid and bid bond were submitted by the same
entity. In this regard, the protester explains that the bidder,
BW JV1, is a joint venture and that both members of the venture
signed the bid and bid bond as President and Project Director of
BW JV1. Protest at 2, 5. The different addresses, the protester
further explains, are mutually agreed upon offices provided
under the joint venture agreement. Id. at 4. Any discrepancy
between the names, the protester argues, is an insignificant
typographical error which the agency should waive as an
informality or minor irregularity under applicable provisions of
the FAR. Id. at 4, 7--8, citing FAR sections 14.301(a),
28.101-4(c)(7), 52.214-19(b). The protester also argues that the
additional acknowledgment of principal does not affect the
validity of the bid bond, because this acknowledgment was not
required by the IFB. Finally, the protester has provided a
letter from its surety, which states that it stands behind the
validity of bond.
The sufficiency of a bid bond relates to whether the government
will receive full and complete protection in the event that the
bidder fails to execute the required contract documents and
deliver the required performance and payment bonds. Martina
Enter./Tom Swenson Gen. Contractors, B-250766, Oct. 21, 1992,
92‑2 CPD para. 266 at 2 (holding that the bid of a joint
venture, which submitted a bid bond in the name of only one of
the corporations forming the joint venture, is nonresponsive).
Among other things, the terms of the bid bond must clearly
establish the liability of the surety at the time of bid
opening; when the liability is not clear, the bond is defective.
Design for Health, Inc., B-239730, Sept. 14, 1990, 90-2 CPD para.
213 at 2. A surety does not incur a liability to pay the debts
of another unless it expressly agrees to be bound. Mount Diablo
Corp., Inc., B‑228193, Nov. 10, 1987, 87-2 CPD para. 475. For
this reason, we rigidly apply the rule that the principal listed
on the bid bond must be the same as the nominal bidder. Opine
Constr., B-218627, June 5, 1985, 85-1 C.P.D. para. 645. If the
bid bond names a principal different from the nominal bidder, it
is deficient and may not be corrected after bid opening as a
minor informality. Atlas Contractors, Inc./Norman T. Hardee, a
Joint Venture, B-208332, Jan. 19, 1983, 83-1 CPD para. 69 at 3.
Where the entity that submitted the bid and that is identified
as the bid bond principal are exactly the same, any discrepancy
between the bidder's and bid bond principal's names is merely a
matter of form that does not require rejection of the bid.
Harris Excavating, B-284820, June 12, 2000, 2000 CPD para. 103
at 3, citing K-W Constr., Inc., B-194480, June 29, 1979, 79-1
CPD para. 475. Extrinsic evidence that is reasonably or publicly
available and in existence at the time of bid opening may be
provided to establish the identity of the bidder and bid bond
principal as the same entity. Gem Eng'g Co., B-251644, Mar. 29,
1993, 93-1 CPD para. 303 at 2 (award to second-low bidder
properly terminated where corporate records and Dun & Bradstreet
report resolved discrepancy in the name of the low bidder and
bid bond principal); Lamari Elec. Co., B-216397, Dec. 24, 1984,
84-2 CPD para. 689 at 2 (entity submitting the bid and
identified as the bid bond principal was the same, an individual
using different trade names); Jack B. Imperiale Fence Co., Inc.,
B-203261, Oct. 26, 1981, 81-2 CPD para. 339 at 2 (discrepancy in
corporate names used in bid and bid bond resolved through
submission of corporation records, tax forms, bid bonds,
insurance papers, loan documents, and contract documents); K-W
Constr., Inc., supra. (bidder's and bid bond principal's
identity established through submission of corporate documents).
Although extrinsic evidence available to the contracting officer
indicates that the different spellings of the bidder's name
(that is, BW JV1 and BW JVI) concern a discrepancy that appears
to be a mere matter of form, the identification of a corporation
as the entity that executed the bid bond calls into question the
liability of the surety with respect to the joint venture, thus
rendering the bid nonresponsive. Specifically, the bid bond's
notarized acknowledgment of the principal states that the person
executing the bid bond is Keith P. Heranda, as president of KPH
Construction Corp., and that this is "the corporation described
in and which executed the foregoing instrument," i.e., the bid
bond. AR, Tab 4, BW JV1 Bid. The principal identified on the
face of the bid bond, however, is BW JV1, a joint venture, and
not KPH Construction Corp. Moreover, although KPH Construction
is one of the two joint venture members, the protester's joint
venture agreement provides that the bid bond had to be executed
by both venture members. See Joint Venture Agreement at 6. We
find that the bid bond is unclear as to which entity executed
the bid bond and that this casts doubt on whether the surety
would be liable to the government in the event that the joint
venture failed to execute contractual documents after acceptance
of the bid.
In sum, we find that the agency properly rejected the
protester's bid as nonresponsive. See Dick Enter., Inc.,
B-259686, B-259686.2, June 21, 1995, 95-1 CPD para. 286 at 2-3
(surety's liability inconclusive where bid submission names
several legal entities and bid signed by vice president of one
corporation, but bond signed by joint venture member). Where a
protester submits a bid bond that creates an ambiguity in the
identity of the principal and the nominal bidder, the
contracting offcer is not obligated to reconcile the ambiguity
by deductions and inferences in order to make the bid
responsive. MKB Constructors, Inc., B-255098, Jan. 10, 1994,
94-1 CPD para. 10 at 3. The bidder's intention is established at
the time of bid opening and the bidder bears the primary
responsibility for properly preparing its bid documents in such
a fashion that the contracting officer may accept the bid with
full confidence that an enforceable contract conforming to all
the requirements of the IFB will result. See Outdoor Venture
Corp., B--235056, June 16, 1989, 89-1 CPD para. 571 at 2.
(BW JV1, LLC, B-401841, December
4, 2009) (pdf)
The IFB, issued on August 11, 2008, required a bid
guarantee in the form of a bid bond in the amount of 20 percent
of the bid. Mill City Partnership, the apparent low bidder at
$5,678,625, identified itself in the bid forms alternately as
Mill City Environmental Corp. (MCE), or Mill City Environmental
Corp. w/ Teaming Partner C.R.C. Co., Inc. (Mill City
Partnership). Agency Report (AR) Tab 13.
The accompanying bid bond identified its principal as C.R.C.
Company, Inc. AR, Tab 13, at 13. The principal was identified as
a "corporation" under the "Type of Organization" section of the
bid bond. Id. The signature block on the bond contained the
signature of CRC’s president. Id.
By letter dated September 29, the contracting officer notified
Mill City that its bid was nonresponsive because of a deficiency
in its bid bond. AR, Tab 7. The Corps awarded the contract to
the next low bidder, Green Seal Environmental, Inc., at
$5,793,221.45. Contracting Officer’s Statement at 2.
The sufficiency of a bid bond relates to whether the government
will receive full and complete protection in the event that the
bidder fails to execute the required contract documents and
deliver the required performance and payment bonds. Martina
Enter./Tom Swenson Gen. Contractors, B-250766, Oct. 21, 1992,
92‑2 CPD para. 266 at 2 (holding that the bid of a joint
venture, which submitted a bid bond in the name of only one of
the corporations forming the joint venture, is nonresponsive).
Among other things, the terms of the bid bond must clearly
establish the liability of the surety at the time of bid
opening; when the liability is not clear, the bond is defective.
Design for Health, Inc., B-239730, Sept. 14, 1990, 90-2 CPD para.
213 at 3. A surety does not incur a liability to pay the debts
of another unless he expressly agrees to be bound. Mount Diablo
Corp., Inc., B‑228193, Nov. 10, 1987, 87-2 CPD para. 475 at 2.
For this reason, the principal listed on the bid bond must be
the same legal entity as the nominal bidder. Reliable Elec.
Constr., Inc., B‑250092, Sept. 23, 1992, 92-2 CPD para.198 at 2.
If the bid bond names a principal different from the nominal
bidder, it is deficient and may not be corrected after bid
opening as a minor informality. Atlas Contractors, Inc./Norman
T. Hardee, a Joint Venture, B-208332, Jan. 19, 1983, 83-1 CPD
para. 69 at 3.
In the present case, the surety’s liability under the bid bond
is contingent upon the bid being in the name of the corporation
listed on the bid bond, i.e., "C.R.C. Company, Inc." While it is
not clear here whether the bidder was MCE or Mill City
Partnership, it is clear that the nominal bidder was not "C.R.C.
Company, Inc." Thus we agree with the contracting officer that
it is unclear that the surety would necessarily be bound in the
event that the joint venture failed to execute the contract upon
acceptance of its bid or declined to furnish acceptable
performance or payment bonds. (Mill
City Partnership, B-400712, December 16, 2008) (pdf)
In its protest,
Simont argues that the omission of the bid guarantee was in good
faith, and that it should be allowed to submit a bid guarantee
now. Simont states that it was misled by the deletion of “NFAS
sect. 5252.228-9302” and the failure to list the bid guarantee
as a required element of the bid in the “Instructions to
Bidders” section of the IFB. Protest at 2.
Simont also points to the IFB provision requiring prospective
bidders to pose any questions at least 10 days before the bid
opening. IFB at 5; Amend. 2 at 4. The protester explains that
since the bid opening was scheduled for July 24, and amendment 2
was posted electronically on July 16 (which was only 8 days
before the bid opening), Simont was prohibited from resolving
its confusion over the requirements of the amended IFB.
NAVFAC argues first that amendment 2 eliminated the conflict
between the 2 percent bid guarantee required by FAR sect.
52.228-1 and the 20 percent bid guarantee required by NFAS sect.
5252.228-9302 by deleting the NFAS provision.
The NAVFAC argument is complicated by the fact that the NFAS bid
guarantee provision was misidentified in the original IFB as
sect. 5254.201-9300. As a result, prospective bidders faced a
challenge in understanding what was being deleted. Since
amendment 2 did not explain that the provision being deleted had
a different label in the original IFB, the prospective bidders
(1) had to discern that the provision being deleted could be
found in the NAVFAC Contracting Manual (made more difficult
because its provisions are not part of the Navy FAR Supplement),
(2) locate a copy of the Manual (such as at the Internet address
noted previously), (3) look up sect. 5252.228-9302, and (4)
search the IFB for text that matched the provision in the
manual. Ultimately, bidders had to deduce that, notwithstanding
the discrepancy, NAVFAC’s intention was to delete the mislabeled
provision.
NAVFAC emphasizes that the amended IFB reiterated the
requirement for a two percent bid guarantee, the protester’s bid
did not include a bid guarantee of any type, and none of the
exceptions in FAR sect. 28.101-4 applies. Therefore, NAVFAC
argues, it was legally required to reject the protester’s bid.
See FAR sect. 28.101-4(a).
A bid guarantee assures that the bidder will, if required,
execute a written contract and furnish performance and payment
bonds. Curry Envtl. Servs., Inc., B-228214, Dec. 9, 1987, 87-2
CPD para. 570 at 2. Where a solicitation requires bidders to
submit bid guarantees with their bids, and a bidder fails to do
so (and no exception applies), the bid must be rejected.
Lawson’s Enters., Inc., B-286708, Jan. 31, 2001, 2001 CPD para.
36 at 2. Affording a bidder the opportunity to supply its bid
guarantee later provides the bidder the option of accepting or
rejecting the award by either correcting or not correcting a
deficiency, which would be inconsistent with the sealed bidding
system. Western Mgmt. Servs., Inc.; Mac-Bestos, Inc., B-266147,
B‑270153, Jan. 23, 1996, 96‑1 CPD para. 17 at 2-3.
In our view, amendment 2 confirmed the continuing validity of
the original bid guarantee provision, FAR sect. 52.228-1. We
believe that any ambiguity caused by NAVFAC’s errors was patent
and therefore had to be protested before the deadline for
submission of bids. 4 C.F.R. sect. 21.2(a)(1). Thus, even if the
error by Simont was subjectively in good faith, its bid was
properly rejected because it did not include the bid guarantee
required by the IFB, notwithstanding the confusion regarding
NAVFAC’s intent to delete the conflicting mislabeled bid
guarantee provision. (Simont
S.p.A., B-400481, October 1, 2008) (pdf)
The protester focuses on four passages from the FAR to support
its assertion that the contracting officer unreasonably
determined that its surety’s asset was unacceptable. First, it
argues that FAR sect. 28.203-2(a)--“The Government will accept
only cash, readily marketable assets, or irrevocable letters of
credit”--makes any “readily marketable asset” acceptable.
Second, the protester argues that paragraph (b) of FAR sect.
28.203-2 is not an all-inclusive list--“[a]cceptable assets
include,” (emphasis added)--and so the drafters of the FAR must
have intended for other assets, not included in the list, to
also be acceptable. Third, the statement in FAR sect.
28.203-2(c) that “[u]nacceptable assets include but are not
limited to. . .” suggests that there must be acceptable assets
other than those listed in paragraph (b). Finally, the protester
argues that the asset offered, mined coal, is nothing like the
assets that the FAR cites as examples of prohibited personal
property--jewelry, furs and antiques. The protester argues that
what distinguishes unacceptable assets from acceptable assets is
the latter’s identifiable value and ready marketability. Thus,
the protester argues, an antique, more difficult to appraise and
to liquidate, is unacceptable, while coal, which has an
ascertainable value and a ready market, is acceptable. We
disagree. The protester’s interpretation of the FAR to permit
the acceptance of coal as an asset reads out of the FAR the
indispensable guarantee that the government can collect on the
bond, namely, the fact that the personal property backing the
bond has been placed in escrow.[6] Thus, to be an acceptable
personal property asset under the FAR, an asset must be capable
of being placed in an escrow account. See FAR sect.
28.203-1(b)(1). As noted above, SF 28 requires individual
sureties to describe the escrow account into which the surety
will place the personal property being pledged in support of the
bond. The protester’s arguments are inconsistent with the
regulatory framework set forth in the FAR and the accompanying
SF 28. The protester also asserts that it had a right to
substitute assets under FAR sect. 28.203‑4. Comments on
Teleconference at 4. That provision gives a surety the right to
request asset substitution, not the right to the substitution.
See FAR sect. 28.203-4 (noting that an “individual surety may
request the Government to accept a substitute asset. . . . The
contracting officer may agree to the substitution of assets.”).
Furthermore, while agencies may not automatically reject a
bidder for unacceptable individual sureties because the SF 28
and supporting documentation contain minor defects that might
easily be remedied, Gene Quigley, Jr., B-241565, Feb. 19, 1991,
91-1 CPD para. 182 at 4, the wholesale substitution of assets is
not one of the minor document defects that are contemplated in
Quigley. (Tip Top Construction
Corporation, B-311305, May 2, 2008) (pdf)
When required by a solicitation, a bid bond or other bid
guarantee is a material part of the bid, noncompliance with
which renders the bid nonresponsive and generally requires
rejection of the bid. FAR sect. 28.101-4(a); Nova Group, Inc.,
B-220626, Jan. 23, 1986, 86-1 CPD para. 80 at 2. This is because
permitting correction of a bid guarantee after bid opening would
open the door to manipulation of the competitive bidding system
by permitting a bidder to decide after other bids have been
exposed whether to attempt to have its bid accepted or rejected.
Trans South Indus., Inc., B-224950, Dec. 19, 1986, 86-2 CPD para.
692 at 2. A bid bond submitted with an invalid power of attorney
certificate renders the bid nonresponsive. See, e.g., Big River
Constr. Co., B-250961, Oct. 26, 1992, 92-2 CPD para. 283 at 2;
Techno Eng’g & Constr., Ltd., B-243932, July 23, 1991, 91-2 CPD
para. 87 at 2-3. This is so because a power of attorney
authorizes an agent to act for the surety and only a valid power
of attorney would indicate that the surety expressly agreed to
be bound to pay the bond signed by the attorney-in-fact. E&R,
Inc., supra, at 4. A power of attorney is to be strictly
construed. The surety’s power of attorney must establish
unequivocally that the individual who signed the surety’s bond
was authorized to bind the surety, and we will not convert
ambiguous aspects of powers of attorney into mere matters of
form which can be explained away and waived. Id. Here, the
surety’s power of attorney attached to the bond listed only Ms.
Allen and Mr. Kingsbury as attorneys-in-fact authorized to bind
EMC, and did not also list Mr. Hixenbaugh, the individual who
signed the bond as attorney-in-fact on behalf of the surety. The
failure of EMC’s power of attorney to list Mr. Hixenbaugh thus
created an uncertainty as to whether Mr. Hixenbaugh was duly
authorized to bind EMC, thereby rendering the bond defective and
JMW’s bid nonresponsive under the regulations then in effect.
See Techno Eng’g & Constr., Ltd., supra. (Johnson
Machine Works, Inc., B-297115, October 20, 2005) (pdf)
The test in these cases is whether the government can enforce
the bond against the surety in the event the bidder fails to
execute the required contract documents and deliver the required
bonds. Professional Restoration Servs., Inc., supra. We find
that because the liability limit specified was inconsistent
with, and for a sum less than, the penal sum required by the IFB,
Armstrong’s bid guarantee was, at best, ambiguous concerning the
enforceable amount of the bid guarantee. Wagner Moving and
Storage, supra (bid is nonresponsive where bid bond included the
penal sum specified by the IFB, but surety’s liability
limitation was limited to an amount less than that required by
the IFB); cf. Professional Restoration Servs., Inc., supra (bid
bond is enforceable against a corporate surety that specifies an
intent to be bound to the penal sum by correctly completing the
liability limit portion of the bid bond form, even though the
penal sum was left blank).[1] Since none of the waiver
provisions in FAR § 28.101-4(c) were applicable, we find that
the agency properly rejected Armstrong’s bid as nonresponsive.
Armstrong’s later submission of a “corrected” bid bond raising
the surety’s liability limit does not alter the fact that the
bid was nonresponsive. The determination as to whether a bid is
acceptable must be based solely on the bid documents themselves,
as they appear at the time of bid opening. Drill Constr. Co.,
Inc., B-239783, June 7, 1990, 90-1 CPD ¶ 538 at 2. Thus, the
offer after bid opening to change the surety’s liability limit
could not cure the defect. As for Armstrong’s assertion that the
agency would realize a significant cost savings with the
acceptance of its bid, notwithstanding the defective bid bond,
we note that the public interest in strictly maintaining the
sealed bidding procedures required by law outweighs any monetary
advantage which the government might gain in a particular case
by a violation of those procedures. Cherokee Enters., Inc.,
B-252948, B-252950, June 3, 1993, 93-1 CPD ¶ 429 at 4. (Armstrong
Elevator Company, B-292864.2, April 13, 2004) (pdf)
Here, we find that GSA properly rejected McGhee’s bid because
the language “20% of the Attached Bid” in McGhee’s bid guarantee
created at least an ambiguity concerning the penal sum amount of
McGhee’s bid guarantee. Although it is true, as McGhee notes,
that we have found that where, as here, the penal sum amount is
expressed as a percentage of the bid price (and not as a
specific amount), the upward correction of the bid after bid
opening (due to a mistake in bid) did not render the bid
guarantee amount inadequate, because the penal sum amount of the
bid guarantee was increased by the bid correction. See Reynosa
Constr., Inc., B‑278364, Dec. 15, 1997, 97-2 CPD ¶ 165 at 2-3,
recon. denied, B‑278364.2, Apr. 28, 1998, 98-1 CPD ¶ 124 at 3.
Unlike Reynosa, however, the protester here, in addition to
stating its penal sum amount as a percentage of its bid price,
also limited its penal sum amount of its bid guarantee to a
percentage of the “attached bid.” As indicated by GSA, the bid
to which the bid guarantee was actually attached was not priced
but stated “no bid” for each CLIN. Thus, we agree with GSA that
McGhee’s limitation of its penal sum amount to a percentage of
the “attached” bid created significant doubts whether an upward
increase in the penal sum amount by reason of its bid
modification would be enforcible against the surety. This is so
because the language of the bid guarantee indicates that the
bidder intended to restrict its penal sum amount to a percentage
of the bid price expressed in the attached document without
providing for possible subsequent changes in the bid price.
Thus, at a minimum, McGhee’s bid guarantee is ambiguous
concerning the amount of the bid guarantee, and therefore must
be rejected as nonresponsive. See Johnston Eng’g, Inc.,
B‑258180, Dec. 16, 1994, 94-2 CPD ¶ 246 at 2-3; Cherokee
Enters., Inc. B-252948, B‑252950, June 3, 1993, 93-1 CPD ¶ 429
at 3. (McGhee Construction, Inc.,
B-293239, February 5, 2004) (pdf)
Horizon’s bid guarantee did not include SF 28, Affidavit of
Individual Surety, but instead included a document captioned
"Power of Attorney." This power of attorney was signed "Robert
Joe Hanson, Attorney-in-Fact, Global Bonding" and identified
"Global Bonding" as "attorney in fact" for Robert Joe Hanson.
The power of attorney also contained a representation of assets
identified as “Corporate Financial Debenture Note #2003-1,
$50,000,000.000 Hexagon Consolidated Companies of America." In
addition, Horizon’s bid bond included a document identifying
Hexagon Consolidated Companies of America as a "guarantor"
pledging $50 million in the form of "Corporate Debenture Number
Two Thousand Three dash One (2003-1), to back Global Bonding . .
. Attorney in Fact for Robert Joe Hanson . . . ." In sum,
given that the identity of the surety for Horizon’s bid bond was
unclear and the bid guarantee was materially deficient because
it did not include an SF 28 as required by the solicitation, we
see no basis to question the agency’s conclusion that Horizon’s
proposal was unacceptable. (Horizon
Shipbuilding, Inc., B-292992, December 8, 2003) (pdf)
In our view, the contracting officer reasonably imposed the bid
and performance bond requirement here. As the BLM explains, the
requirement is necessary to ensure completion before the
bicentennial celebration of the Lewis and Clark expedition ends
and protect against losses resulting from a defaulting
contractor's failure to meet this deadline. As noted above, the
timely completion of this project was “critical” to the agency,
given the project's “great historical significance.” Contracting
Officer's Statement at 1, 5. While AAP contends that the bond
requirement “does not guarantee” timely performance and was not
needed, Protester's Comments at 4, this disagreement with the
BLM's judgment does not render it unreasonable. D.J. Findley,
Inc., B-221096, Feb. 3, 1986, 86-1 CPD ¶ 121 at 4. Although a
bond requirement may restrict competition, and may even exclude
some small businesses, that possibility alone, absent a finding
of unreasonableness or bad faith, does not render a bond
requirement improper. Maintrac Corp., B‑251500, Mar. 22, 1993,
93-1 CPD ¶ 257 at 3. AAP has presented no evidence of bad faith
and, as discussed above, we find that the BLM's determination
was reasonable. (American
Artisan Productions, Inc., B-292380, July 30, 2003) (pdf)
CCI confuses the RFP's requirement to provide specified
information to establish "bonding capability" (the least
important of the four subfactors under the management and
organization factor) with a sealed bid requirement for a bid
bond. A bid bond requirement is a material condition of a sealed
bid procurement with which there must be compliance at the time
of bid opening; if the agency cannot determine definitely from
the documents submitted with the bid that the surety would be
bound, the bid is nonresponsive and must be rejected. Schrepfer
Indus., Inc., B‑286825, Feb. 12, 2001, 2001 CPD P: 23 at
2. There was no such stringent requirement here. In particular,
a bid bond was not required to establish bonding capability;
rather, the RFP required only that offerors *[p]rovide Bonding
Capability for projects of size and nature envisioned [in the
RFP] on surety's letterhead in amount of not less than
$10,000,000.00. Bonding capability shall be accompanied by a
document authenticating the agent's authority to sign bonds for
the surety company pursuant to FAC5252.228-9305 in Section
I.*[5] RFP at 91. The agency explains that these submissions
were considered representations as to the offerors' capability
to obtain appropriate bonds, and were not intended to obligate
the bonding companies.[6] Supplemental Agency Report at 2. Here,
all offerors, including the four challenged by CCI, provided the
requisite information on their surety's letterhead, indicating a
bonding capability of the $10 million minimum. Since the
agency's position--that this aspect of the evaluation was
intended only to assess offerors' prospective ability to obtain
bonding--is borne out by the language of the RFP, and the
offerors in question provided the requested information, we find
nothing unreasonable in the agency's determination that the
information furnished by the offerors met this requirement.
(C
Construction Co., Inc., B-291792; B-291792.2; B-291792.3,
March 17, 2003) (txt
version)
While we have recognized a power of attorney bearing
mechanically applied signatures as valid and binding where there
is evidence demonstrating that the surety intends to be bound by
such signatures, see Fiore Constr. Co., B-256429, June 23, 1994,
94-1 CPD ¶ 379 at 2-3, we conclude that, for a mechanically
applied signature to be recognized as valid and binding, it must
be affixed to the power of attorney after the power of attorney
has been generated. Where, as here, signatures are generated as
part of a document, as opposed to being affixed to the document
after its generation, they do not constitute an affirmation as
to the correctness of its contents and thus do not serve to
validate the document. In the absence of a validating signature,
there is no way to be certain at the time of bid opening that
the file from which a computer printer-generated power of
attorney/certification was created has not been altered, just as
there is no way to be certain that the original from which a
faxed or photocopied power of attorney/certification was created
has not been altered. While, as noted above, an original
certification from a current officer of the surety attesting to
its authenticity and continuing validity would have been
sufficient to validate the power of attorney that accompanied
All Seasons’ bid bond, the certification submitted by the
protester’s surety suffered from the same defect as the power of
attorney itself--i.e., it contained only a computer
printer-generated signature; thus, it did not serve to validate
the power of attorney. Moreover, the certification is itself of
questionable validity because it clearly had been
altered--through insertion of the date August 9, 2002-- after
being printed, and there is no evidence that the assistant vice
president whose computer printer-generated signature appears
beneath the certification was aware of or approved the
alteration. Because neither the power of attorney nor the
certification of continuing validity attached to the protester’s
bid bond bore signatures that had been applied to the document
after its creation, we think that the contracting officer
reasonably concluded that they did not establish unequivocally
at the time of bid opening that the bond would be enforceable
against the surety in the event that the bidder failed to meet
its obligations. Accordingly, she properly rejected All Seasons’
bid as nonresponsive. (All
Seasons Construction, Inc., B-291166.2, December 6, 2002)
Protester's bid was properly
rejected as nonresponsive where it contained a commercial bid
bond form that limited the surety's liability to the government
in the event of a default to the difference between the
protester's bid and the new award amount, contrary to the terms
of the solicitation, which required the surety to be liable for
all reprocurement costs, up to the penal amount of the bond.
(Paradise
Construction Company, B-289144, November 26, 2001)
Protest that agency was required
to reject bid for failure to satisfy bid guarantee requirement
is denied where the amount of the contested bid guarantee was
greater than the difference between that firm's bid and next low
bid and agency properly decided to waive the requirement; fact
that contested bid included inconsistent language regarding the
amount of the bid guarantee did not require rejection. (South
Atlantic Construction Company, LLC, B-286592.2, April 13,
2001)
Agency properly determined bid
bond accompanied by photocopied power of attorney unacceptable
because photocopied power of attorney does not establish
unequivocally at the time of bid opening that the bond would be
enforceable against the surety in the event that the bidder
fails to meet its obligations. (Schrepfer
Industries, Inc., B-286825, February 12, 2001)
Protester's bid is responsive,
despite a discrepancy in the name of the bidder as identified on
the bid and the name of the principal identified in the required
bid bond, where reasonably available extrinsic evidence in
existence at the time of bid opening establishes that the bidder
and principal are the same entity, such that there is no doubt
that the surety will be liable under the bond to the government
on the bidder's behalf. (Harris
Excavating, B-284820, June 12, 2000)
Photocopies of bid guarantee
documents generally do not satisfy the requirement for a bid
guarantee since there is no way, other than by referring to the
originals after bid opening, to be certain that there had not
been alterations to which the surety had not consented, and that
the government would therefore be secured. A faxed bid guarantee
document, which is an electronically transmitted copy, is
subject to the same uncertainty. (Kemper
Construction Company, Inc., B-283286.2, November 29, 1999)
|