|
FAR
28.101: Bid guarantees |
|
Comptroller
General |
The protester focuses on four passages from the FAR to support
its assertion that the contracting officer unreasonably
determined that its surety’s asset was unacceptable. First, it
argues that FAR sect. 28.203-2(a)--“The Government will accept
only cash, readily marketable assets, or irrevocable letters of
credit”--makes any “readily marketable asset” acceptable.
Second, the protester argues that paragraph (b) of FAR sect.
28.203-2 is not an all-inclusive list--“[a]cceptable assets
include,” (emphasis added)--and so the drafters of the FAR must
have intended for other assets, not included in the list, to
also be acceptable. Third, the statement in FAR sect.
28.203-2(c) that “[u]nacceptable assets include but are not
limited to. . .” suggests that there must be acceptable assets
other than those listed in paragraph (b). Finally, the protester
argues that the asset offered, mined coal, is nothing like the
assets that the FAR cites as examples of prohibited personal
property--jewelry, furs and antiques. The protester argues that
what distinguishes unacceptable assets from acceptable assets is
the latter’s identifiable value and ready marketability. Thus,
the protester argues, an antique, more difficult to appraise and
to liquidate, is unacceptable, while coal, which has an
ascertainable value and a ready market, is acceptable. We
disagree. The protester’s interpretation of the FAR to permit
the acceptance of coal as an asset reads out of the FAR the
indispensable guarantee that the government can collect on the
bond, namely, the fact that the personal property backing the
bond has been placed in escrow.[6] Thus, to be an acceptable
personal property asset under the FAR, an asset must be capable
of being placed in an escrow account. See FAR sect.
28.203-1(b)(1). As noted above, SF 28 requires individual
sureties to describe the escrow account into which the surety
will place the personal property being pledged in support of the
bond. The protester’s arguments are inconsistent with the
regulatory framework set forth in the FAR and the accompanying
SF 28. The protester also asserts that it had a right to
substitute assets under FAR sect. 28.203‑4. Comments on
Teleconference at 4. That provision gives a surety the right to
request asset substitution, not the right to the substitution.
See FAR sect. 28.203-4 (noting that an “individual surety may
request the Government to accept a substitute asset. . . . The
contracting officer may agree to the substitution of assets.”).
Furthermore, while agencies may not automatically reject a
bidder for unacceptable individual sureties because the SF 28
and supporting documentation contain minor defects that might
easily be remedied, Gene Quigley, Jr., B-241565, Feb. 19, 1991,
91-1 CPD para. 182 at 4, the wholesale substitution of assets is
not one of the minor document defects that are contemplated in
Quigley. (Tip Top Construction
Corporation, B-311305, May 2, 2008) (pdf)
When required by a solicitation, a bid bond or other bid
guarantee is a material part of the bid, noncompliance with
which renders the bid nonresponsive and generally requires
rejection of the bid. FAR sect. 28.101-4(a); Nova Group, Inc.,
B-220626, Jan. 23, 1986, 86-1 CPD para. 80 at 2. This is because
permitting correction of a bid guarantee after bid opening would
open the door to manipulation of the competitive bidding system
by permitting a bidder to decide after other bids have been
exposed whether to attempt to have its bid accepted or rejected.
Trans South Indus., Inc., B-224950, Dec. 19, 1986, 86-2 CPD para.
692 at 2. A bid bond submitted with an invalid power of attorney
certificate renders the bid nonresponsive. See, e.g., Big River
Constr. Co., B-250961, Oct. 26, 1992, 92-2 CPD para. 283 at 2;
Techno Eng’g & Constr., Ltd., B-243932, July 23, 1991, 91-2 CPD
para. 87 at 2-3. This is so because a power of attorney
authorizes an agent to act for the surety and only a valid power
of attorney would indicate that the surety expressly agreed to
be bound to pay the bond signed by the attorney-in-fact. E&R,
Inc., supra, at 4. A power of attorney is to be strictly
construed. The surety’s power of attorney must establish
unequivocally that the individual who signed the surety’s bond
was authorized to bind the surety, and we will not convert
ambiguous aspects of powers of attorney into mere matters of
form which can be explained away and waived. Id. Here, the
surety’s power of attorney attached to the bond listed only Ms.
Allen and Mr. Kingsbury as attorneys-in-fact authorized to bind
EMC, and did not also list Mr. Hixenbaugh, the individual who
signed the bond as attorney-in-fact on behalf of the surety. The
failure of EMC’s power of attorney to list Mr. Hixenbaugh thus
created an uncertainty as to whether Mr. Hixenbaugh was duly
authorized to bind EMC, thereby rendering the bond defective and
JMW’s bid nonresponsive under the regulations then in effect.
See Techno Eng’g & Constr., Ltd., supra. (Johnson
Machine Works, Inc., B-297115, October 20, 2005) (pdf)
The test in these cases is whether the government can enforce
the bond against the surety in the event the bidder fails to
execute the required contract documents and deliver the required
bonds. Professional Restoration Servs., Inc., supra. We find
that because the liability limit specified was inconsistent
with, and for a sum less than, the penal sum required by the IFB,
Armstrong’s bid guarantee was, at best, ambiguous concerning the
enforceable amount of the bid guarantee. Wagner Moving and
Storage, supra (bid is nonresponsive where bid bond included the
penal sum specified by the IFB, but surety’s liability
limitation was limited to an amount less than that required by
the IFB); cf. Professional Restoration Servs., Inc., supra (bid
bond is enforceable against a corporate surety that specifies an
intent to be bound to the penal sum by correctly completing the
liability limit portion of the bid bond form, even though the
penal sum was left blank).[1] Since none of the waiver
provisions in FAR § 28.101-4(c) were applicable, we find that
the agency properly rejected Armstrong’s bid as nonresponsive.
Armstrong’s later submission of a “corrected” bid bond raising
the surety’s liability limit does not alter the fact that the
bid was nonresponsive. The determination as to whether a bid is
acceptable must be based solely on the bid documents themselves,
as they appear at the time of bid opening. Drill Constr. Co.,
Inc., B-239783, June 7, 1990, 90-1 CPD ¶ 538 at 2. Thus, the
offer after bid opening to change the surety’s liability limit
could not cure the defect. As for Armstrong’s assertion that the
agency would realize a significant cost savings with the
acceptance of its bid, notwithstanding the defective bid bond,
we note that the public interest in strictly maintaining the
sealed bidding procedures required by law outweighs any monetary
advantage which the government might gain in a particular case
by a violation of those procedures. Cherokee Enters., Inc.,
B-252948, B-252950, June 3, 1993, 93-1 CPD ¶ 429 at 4. (Armstrong
Elevator Company, B-292864.2, April 13, 2004) (pdf)
Here, we find that GSA properly rejected McGhee’s bid because
the language “20% of the Attached Bid” in McGhee’s bid guarantee
created at least an ambiguity concerning the penal sum amount of
McGhee’s bid guarantee. Although it is true, as McGhee notes,
that we have found that where, as here, the penal sum amount is
expressed as a percentage of the bid price (and not as a
specific amount), the upward correction of the bid after bid
opening (due to a mistake in bid) did not render the bid
guarantee amount inadequate, because the penal sum amount of the
bid guarantee was increased by the bid correction. See Reynosa
Constr., Inc., B‑278364, Dec. 15, 1997, 97-2 CPD ¶ 165 at 2-3,
recon. denied, B‑278364.2, Apr. 28, 1998, 98-1 CPD ¶ 124 at 3.
Unlike Reynosa, however, the protester here, in addition to
stating its penal sum amount as a percentage of its bid price,
also limited its penal sum amount of its bid guarantee to a
percentage of the “attached bid.” As indicated by GSA, the bid
to which the bid guarantee was actually attached was not priced
but stated “no bid” for each CLIN. Thus, we agree with GSA that
McGhee’s limitation of its penal sum amount to a percentage of
the “attached” bid created significant doubts whether an upward
increase in the penal sum amount by reason of its bid
modification would be enforcible against the surety. This is so
because the language of the bid guarantee indicates that the
bidder intended to restrict its penal sum amount to a percentage
of the bid price expressed in the attached document without
providing for possible subsequent changes in the bid price.
Thus, at a minimum, McGhee’s bid guarantee is ambiguous
concerning the amount of the bid guarantee, and therefore must
be rejected as nonresponsive. See Johnston Eng’g, Inc.,
B‑258180, Dec. 16, 1994, 94-2 CPD ¶ 246 at 2-3; Cherokee
Enters., Inc. B-252948, B‑252950, June 3, 1993, 93-1 CPD ¶ 429
at 3. (McGhee Construction, Inc.,
B-293239, February 5, 2004) (pdf)
Horizon’s bid guarantee did not include SF 28, Affidavit of
Individual Surety, but instead included a document captioned
"Power of Attorney." This power of attorney was signed "Robert
Joe Hanson, Attorney-in-Fact, Global Bonding" and identified
"Global Bonding" as "attorney in fact" for Robert Joe Hanson.
The power of attorney also contained a representation of assets
identified as “Corporate Financial Debenture Note #2003-1,
$50,000,000.000 Hexagon Consolidated Companies of America." In
addition, Horizon’s bid bond included a document identifying
Hexagon Consolidated Companies of America as a "guarantor"
pledging $50 million in the form of "Corporate Debenture Number
Two Thousand Three dash One (2003-1), to back Global Bonding . .
. Attorney in Fact for Robert Joe Hanson . . . ." In sum,
given that the identity of the surety for Horizon’s bid bond was
unclear and the bid guarantee was materially deficient because
it did not include an SF 28 as required by the solicitation, we
see no basis to question the agency’s conclusion that Horizon’s
proposal was unacceptable. (Horizon
Shipbuilding, Inc., B-292992, December 8, 2003) (pdf)
In our view, the contracting officer reasonably imposed the bid
and performance bond requirement here. As the BLM explains, the
requirement is necessary to ensure completion before the
bicentennial celebration of the Lewis and Clark expedition ends
and protect against losses resulting from a defaulting
contractor's failure to meet this deadline. As noted above, the
timely completion of this project was “critical” to the agency,
given the project's “great historical significance.” Contracting
Officer's Statement at 1, 5. While AAP contends that the bond
requirement “does not guarantee” timely performance and was not
needed, Protester's Comments at 4, this disagreement with the
BLM's judgment does not render it unreasonable. D.J. Findley,
Inc., B-221096, Feb. 3, 1986, 86-1 CPD ¶ 121 at 4. Although a
bond requirement may restrict competition, and may even exclude
some small businesses, that possibility alone, absent a finding
of unreasonableness or bad faith, does not render a bond
requirement improper. Maintrac Corp., B‑251500, Mar. 22, 1993,
93-1 CPD ¶ 257 at 3. AAP has presented no evidence of bad faith
and, as discussed above, we find that the BLM's determination
was reasonable. (American
Artisan Productions, Inc., B-292380, July 30, 2003) (pdf)
CCI confuses the RFP's requirement to provide specified
information to establish "bonding capability" (the least
important of the four subfactors under the management and
organization factor) with a sealed bid requirement for a bid
bond. A bid bond requirement is a material condition of a sealed
bid procurement with which there must be compliance at the time
of bid opening; if the agency cannot determine definitely from
the documents submitted with the bid that the surety would be
bound, the bid is nonresponsive and must be rejected. Schrepfer
Indus., Inc., B‑286825, Feb. 12, 2001, 2001 CPD P: 23 at
2. There was no such stringent requirement here. In particular,
a bid bond was not required to establish bonding capability;
rather, the RFP required only that offerors *[p]rovide Bonding
Capability for projects of size and nature envisioned [in the
RFP] on surety's letterhead in amount of not less than
$10,000,000.00. Bonding capability shall be accompanied by a
document authenticating the agent's authority to sign bonds for
the surety company pursuant to FAC5252.228-9305 in Section
I.*[5] RFP at 91. The agency explains that these submissions
were considered representations as to the offerors' capability
to obtain appropriate bonds, and were not intended to obligate
the bonding companies.[6] Supplemental Agency Report at 2. Here,
all offerors, including the four challenged by CCI, provided the
requisite information on their surety's letterhead, indicating a
bonding capability of the $10 million minimum. Since the
agency's position--that this aspect of the evaluation was
intended only to assess offerors' prospective ability to obtain
bonding--is borne out by the language of the RFP, and the
offerors in question provided the requested information, we find
nothing unreasonable in the agency's determination that the
information furnished by the offerors met this requirement.
(C
Construction Co., Inc., B-291792; B-291792.2; B-291792.3,
March 17, 2003) (txt
version)
While we have recognized a power of attorney bearing
mechanically applied signatures as valid and binding where there
is evidence demonstrating that the surety intends to be bound by
such signatures, see Fiore Constr. Co., B-256429, June 23, 1994,
94-1 CPD ¶ 379 at 2-3, we conclude that, for a mechanically
applied signature to be recognized as valid and binding, it must
be affixed to the power of attorney after the power of attorney
has been generated. Where, as here, signatures are generated as
part of a document, as opposed to being affixed to the document
after its generation, they do not constitute an affirmation as
to the correctness of its contents and thus do not serve to
validate the document. In the absence of a validating signature,
there is no way to be certain at the time of bid opening that
the file from which a computer printer-generated power of
attorney/certification was created has not been altered, just as
there is no way to be certain that the original from which a
faxed or photocopied power of attorney/certification was created
has not been altered. While, as noted above, an original
certification from a current officer of the surety attesting to
its authenticity and continuing validity would have been
sufficient to validate the power of attorney that accompanied
All Seasons’ bid bond, the certification submitted by the
protester’s surety suffered from the same defect as the power of
attorney itself--i.e., it contained only a computer
printer-generated signature; thus, it did not serve to validate
the power of attorney. Moreover, the certification is itself of
questionable validity because it clearly had been
altered--through insertion of the date August 9, 2002-- after
being printed, and there is no evidence that the assistant vice
president whose computer printer-generated signature appears
beneath the certification was aware of or approved the
alteration. Because neither the power of attorney nor the
certification of continuing validity attached to the protester’s
bid bond bore signatures that had been applied to the document
after its creation, we think that the contracting officer
reasonably concluded that they did not establish unequivocally
at the time of bid opening that the bond would be enforceable
against the surety in the event that the bidder failed to meet
its obligations. Accordingly, she properly rejected All Seasons’
bid as nonresponsive. (All
Seasons Construction, Inc., B-291166.2, December 6, 2002)
Protester's bid was properly
rejected as nonresponsive where it contained a commercial bid
bond form that limited the surety's liability to the government
in the event of a default to the difference between the
protester's bid and the new award amount, contrary to the terms
of the solicitation, which required the surety to be liable for
all reprocurement costs, up to the penal amount of the bond.
(Paradise
Construction Company, B-289144, November 26, 2001)
Protest that agency was required
to reject bid for failure to satisfy bid guarantee requirement
is denied where the amount of the contested bid guarantee was
greater than the difference between that firm's bid and next low
bid and agency properly decided to waive the requirement; fact
that contested bid included inconsistent language regarding the
amount of the bid guarantee did not require rejection. (South
Atlantic Construction Company, LLC, B-286592.2, April 13,
2001)
Agency properly determined bid
bond accompanied by photocopied power of attorney unacceptable
because photocopied power of attorney does not establish
unequivocally at the time of bid opening that the bond would be
enforceable against the surety in the event that the bidder
fails to meet its obligations. (Schrepfer
Industries, Inc., B-286825, February 12, 2001)
Protester's bid is responsive,
despite a discrepancy in the name of the bidder as identified on
the bid and the name of the principal identified in the required
bid bond, where reasonably available extrinsic evidence in
existence at the time of bid opening establishes that the bidder
and principal are the same entity, such that there is no doubt
that the surety will be liable under the bond to the government
on the bidder's behalf. (Harris
Excavating, B-284820, June 12, 2000)
Photocopies of bid guarantee
documents generally do not satisfy the requirement for a bid
guarantee since there is no way, other than by referring to the
originals after bid opening, to be certain that there had not
been alterations to which the surety had not consented, and that
the government would therefore be secured. A faxed bid guarantee
document, which is an electronically transmitted copy, is
subject to the same uncertainty. (Kemper
Construction Company, Inc., B-283286.2, November 29, 1999)
|
|
|
Comptroller
General - Listing of Decisions |
|
For
the Government |
For
the Protester |
|
Tip Top Construction Corporation,
B-311305, May 2, 2008 (pdf) |
Apex
Support Services, Inc., B-288936; B-288936.2, December 12,
2001 |
|
Johnson Machine Works, Inc.,
B-297115, October 20, 2005) (pdf) |
Harris
Excavating, B-284820, June 12, 2000
|
|
Armstrong Elevator Company,
B-292864.2, April 13, 2004 (pdf) |
|
|
McGhee Construction, Inc.,
B-293239, February 5, 2004 (pdf) |
|
|
Horizon Shipbuilding, Inc.,
B-292992, December 8, 2003 (pdf) |
|
|
NVT Technologies, Inc.,
B-292302.3, October 20, 2003 (pdf) |
|
|
American Artisan Productions, Inc.,
B-292380, July 30, 2003 (pdf) |
|
|
C Construction Co., Inc., B-291792; B-291792.2; B-291792.3,
March 17, 2003 (txt
version) |
|
|
All
Seasons Construction, Inc., B-291166.2, December 6, 2002 |
|
|
Paradise
Construction Company, B-289144, November 26, 2001 |
|
|
South
Atlantic Construction Company, LLC, B-286592.2, April 13,
2001 |
|
|
Schrepfer
Industries, Inc., B-286825, February 12, 2001 |
|
|
Kemper
Construction Company, Inc., B-283286.2, November 29, 1999 |
|
|
U.
S. Court of Federal Claims |
The Government’s dispute is with the procedures
themselves. It is not for the trial court to devise a procedure that fills in a gap that the FAR does
not recognize as a critical interval. Specifically, the administrative record reveals that Arch
Insurance will not deliver the performance bond if the contract is awarded to plaintiff; that
plaintiff may or may not have been authorized to submit the surety’s bid bond; that plaintiff did not
have a surety in place; and that the one currently under consideration is suspect. The FAR
provides that the bid guarantee will be called on if the contractor cannot deliver the
performance bond when required. Were the court to rule that Contract Administrator Mitchell could
avert further delay by taking preemptive action, the door would open for any surety
after bid opening and upon further reflection to call in its disinclination not to make
good on an otherwise valid, authorized guarantee. The certainty and predictability of
reliance on surety guarantees would be hostage to the whims of the surety. Indeed, if a surety
notified the procuring official of its disinclination and the latter decided to proceed
nonetheless and hold the surety to its commitment, a new cause of action could be spawned.
Defendant’s position also cannot be sustained because it would require the court
to find the terms “firm commitment” and “reasonably acceptable to the Government”
to provide the regulatory authority for the procuring officer’s exercise of discretion
after bid opening and after receipt of an otherwise facially valid bid bond. Plaintiff’s admission
in the phone call between Mr. Mitchell and Mr. Williams appears in the handwritten Phonecon
Record as “[a]dmitted Arch won’t bond them. Looking for other sureties.” That does not
equate to an admission that the bid guarantee was invalid, i.e., that it was not an
enforceable contract. At most, it is a candid statement that the surety may be backing out of what was
a firm commitment. If this court were to allow the Government to interpret broadly the term “firm
commitment” to extend beyond what it means at the time of bid opening, procuring
officials would be able to inquire with the surety to learn if the surety will actually do
what it promised to do. The exception urged by defendant would swallow the rule. It
would also be impossible to determine what level of reliability of evidence a procuring
official could base such a decision on without basically legislating new procedure. That is not
this court’s role. While defendant urges expediently that the ruling it seeks would protect the
Government better than the regulation, the real protection would be accorded the
surety, which now would be able to back out of a “firm commitment” whenever it chooses
merely by giving word to the agency. Even bidders would reap a benefit from such a
ruling, for if a surety with second doubts creates a reasonable basis to justify rejection of a
bid, then the bidder itself could take advantage and assert the same basis to justify
withdrawal of its bid. (Aeroplate Corporation v. U.
S., No. 05-736C, August 5, 2005) (pdf)
Defendant and intervenors have argued that a
mechanically applied signature does not give adequate assurance that the
document has not been modified. All Seasons explained this rationale, as
follows:
While we have recognized a power of attorney
bearing mechanically applied signatures as valid and binding where there is
evidence demonstrating that the surety intends to be bound by such
signatures, [see Fiore, B-256429, 94-1 CPD ¶ 379, at 2-3, 1994 U.S. Comp.
Gen. LEXIS 553, at *4], we conclude that, for a mechanically applied
signature to be recognized as valid and binding, it must be affixed to the
power of attorney after the power of attorney has been generated. Where, as
here, signatures are generated as part of a document, as opposed to being
affixed to the document after its generation, they do not constitute an
affirmation as to the correctness of its contents and thus do not serve to
validate the document. In the absence of a validating signature, there is no
way to be certain at the time of bid opening that the file from which a
computer printer-generated power of attorney/certification was created has
not been altered, just as there is no way to be certain that the original
from which a faxed or photocopied power of attorney/certification was
created has not been altered.
Unlike the document in All Seasons, plaintiff
submitted powers of attorney with certificates restating board resolutions by
which the surety bound itself to facsimile signatures on a power of attorney or
any certificate relating to the power of attorney. This affirmation, combined
with a facially valid appointment and original corporate seal, in their totality
establish unequivocally that the surety intends to be bound. However, in
this regard a mechanical signature is not unique in any way compared with an
original wet signature. The risk of fraud or forgery is inherent in any executed
document. Since 1994 the GAO has recognized that mechanically applied
signatures can give the requisite unequivocal assurance. In the present case,
the surety went so far as to state unequivocally that facsimile signatures on
both the powers of attorney and certificates are valid and that, per the
certificates, it agrees to be bound by them. This may even be greater assurance
that the surety intends to stand behind the document than would be present if an
original wet signature were present without a statement that the surety intends
to be bound by any wet signature. Although the contracting officer’s
decision to reject plaintiff’s bids was unreasonable, it is not unreasonable
because he relied on GAO precedent. As discussed, contracting officers often
rely on GAO decisions for guidance. However, in this case the contracting
officer had to determine whether plaintiff’s powers of attorney documents were
sufficient to bind the surety. It is unreasonable for a contracting officer to
rely on unreasonable rationale when making such a decision. As applied by
the contracting officer, All Seasons would prevent all uses of facsimile
signatures because the contracting officer would not be able to tell if the
signature had been mechanically applied after the document was generated.
Mechanical signatures require additional indicia that the surety intends to be
bound. By including a statement that the surety intends to be bound by all
facsimile signatures, the surety has made it unequivocally clear that it intends
to be bound by mechanically applied signatures. (Hawaiian
Dredging Construction Co., Inc. v. U. S. and Nova Group, Inc., No. 03-2763C,
January 9, 2004.) (pdf)
As other commentators have noted, “bid bonds and
bid guarantees add an incredible amount of complexity and cost to sealed bid
procurement. It is extremely doubtful whether such cost and complexity is
justified by whatever benefits the Government receives from bonds and
guarantees.” JOHN CIBINIC JR., & RALPH C. NASH, JR., BID BONDS AND BID
GUARANTEES: THAT TAIL IS STILL WAGING, 16 NO. 3 NASH & CIBINIC REP. P. 12
(March, 2002). In the end, it is not for the Court to establish
procurement policy. Plaintiff’s remedy would be to seek an amendment to the FAR
that explicitly details the requirements for a valid power of attorney. This
would greatly serve to reduce confusion among the surety industry while ensuring
that the government pays the lowest-available price. Ultimately however,
the VA and the GAO decisions, that facsimile or photocopied powers of attorney
should be rejected based on the rationale that the documents could have been
manipulated without the alterations being apparent upon examination, cannot be
called irrational. Bid bonds provide a greater opportunity for fraud than
payment and performance bonds because bid bond sureties are rarely called upon
to reimburse the government. The bid bond surety’s obligations are satisfied
once payment and performance bonds are provided and the contract is executed. In
most situations, the bid bond becomes a moot issue and it is unlikely that any
fraud will be revealed. It was not irrational for the Comptroller General to
adopt a firm rule that a CO could easily apply to determine bid bond deficiency
instead of relying on a totality of the circumstances test. The CO would only be
able to determine if there had been any alterations by comparing the photocopy
to the original power of attorney. The fact that the IFB does not expressly
prohibit a photocopied power of attorney does not render the CO’s actions
irrational. In this case, other bidders such as Witherington submitted bid bonds
accompanied by an original power of attorney. The GAO decisions cannot be found
to be irrational and the CO did not act arbitrarily or capriciously in adopting
the GAO’s recommendations that photocopied power of attorneys render the bid
non-responsive. (All
Seasons Construction, Inc., v. U. S. and Withering Construction Corp., No.
02-1895 C, January 23, 2003)
As a result of the Government’s action in this case, the District of Columbia is
being forced to spend $312,653.00 more than initially expected to construct a public
school because of a technicality in a bid bond that was no longer in effect at the time the
agency protest that resulted in Plaintiff’s loss of the contract was filed, and where the
government suffered no injury. Furthermore, the protester, the lowest bidder, is a
minority contractor and one that is preferred by the Army Corps of Engineer’s client, the
District of Columbia Public Schools. AR 512. Nevertheless, the Court is constrained to hold that
Defendant’s decision to award the contract to Hess based on Division Counsel’s determination that Plaintiff’s bid was
non-responsive due to a defect in the bid bond discovered after expiration of the bid bond
was not arbitrary, capricious, or in violation of law. (Davis/HRGM
Joint Venture v. U. S., No. 01-414C, October 15, 2001) (pdf)
Clearly, the process of sealed bidding does not afford the opportunity for
each bidder that might submit a defective bid bond to manifest its intent post-bid
opening. Accordingly, Interstate’s failure to submit a properly executed bid guarantee rendered its bid
nonresponsive. The government is not permitted to
consider Interstate’s explanation concerning the defect in its bid bond, and Interstate is not entitled to alter its bid with additional documents following bid
opening. Interstate requested FHWA to declare its bid responsive on the basis of
Interstate’s explanation that (1) the omission of the penal sum was a clerical error;
and (2) it had previously executed a proper bid bond, but that it asked the surety to
execute a second bid bond because the first one was partially illegible. FHWA was entirely correct in rejecting this request.
(Interstate
Rock Products, Inc. v. U.S., No. 01-408C, September 17, 2001)
|
|
|
U.
S. Court of Federal Claims - Listing of Decisions |
|
For
the Government |
For
the Protester |
|
All Seasons Construction, Inc., v. U. S. and Withering Construction Corp.,
No. 02-1895 C, January 23, 2003 |
Aeroplate Corporation v. U. S., No. 05-736C,
August 5, 2005 (pdf) |
|
Davis/HRGM
Joint Venture v. U. S., No. 01-414C, October 15, 2001 (pdf) |
Hawaiian Dredging Construction Co.,
Inc. v. U. S. and Nova Group, Inc., No. 03-2763C, January 9,
2004 (pdf) |
|
Interstate
Rock Products, Inc. v. U.S., No. 01-408C, September 17, 2001 |
|
|
|