Caddell next
argues that Framaco has not built any projects similar in
complexity, type of construction, and value to the three 2009
projects which, as identified above, ranged in value from $85 to
$150 million. As quoted above, subparagraph D of the Security
Act requires that an entity seeking contracts for diplomatic
construction projects over $10 million must have performed
construction services “similar in complexity, type of
construction, and value to the project being bid.” 22 U.S.C.
sect. 4852(c)(2)(D). In addition to having no experience with
projects of this magnitude, Caddell maintains that Framaco has
no experience whatsoever building embassies or working through
the challenges of performing “secure” work.
The agency acknowledges that it initially refused to pre-qualify
Framaco for any of its 2008 projects on the basis that Framaco
could not identify a single project that approached the value of
any of the 2008 projects. After Framaco protested this decision
to our Office, the agency elected not to defend its decision,
and adopted Framaco’s view that an offeror should be permitted
to establish that it has performed similar construction services
by identifying a number of projects it has performed, that, in
total, match or exceed the estimated value of the upcoming
project.
In this regard, in its 2008 submission--which, again, forms the
basis for the 2009 pre‑qualification decision--Framaco
identified the following projects that it contended should be
viewed as similar projects. In addition, it noted that it had
performed these projects for the agency in a joint venture with
two Turkish construction firms.
|
Name and Location of Project |
Value (US$) |
|
Interim
Embassy Renovation (Baghdad) |
$
41,656,220 |
|
500 Man Camp
(Kabul) |
$
14,915,379 |
|
Cafeteria-Health Center (Kabul) |
$
5,305,646 |
|
Existing
Office Renovation and Annex Construction (Kabul) |
$
9,994,125 |
|
Anti-Ram
Perimeter Wall (Mosul and Kirkuk) |
$
4,463,725 |
|
Geotechnical
Construction Services for NEC Baghdad, Iraq |
$
2,715,074 |
|
NOX Building
Construction (Bamako) |
$
15,825,748 |
|
NOX Building
Construction (Accra) |
$
17,749,994 |
|
Cantonment and
Facilities (Kabul) |
$
9,724,420 |
|
TOTAL |
$
122,350,332 |
AR, Tab 6, Letter from Framaco to the Agency, Mar. 17, 2008.
As a preliminary matter, we note that the agency report contains
no documentation of any review associated with pre-qualifying
offerors for the 2009 projects. Instead, the agency accepted as
qualified any contractor that was pre-qualified for 2008. AR,
Tab 3, TEP Pre-qualification for 2008 Projects, Feb. 15, 2008.
In our view, the agency’s failure to perform any type of
evaluation contradicts both the letter and spirit of the
Security Act, as well as the sources-sought announcement
published in FedBizOps. At a minimum, the 5-year period of
review anticipated by the Security Act, by definition, changes
each year. It appears from the record that Framaco submitted
only a letter of interest for the 2009 projects. Moreover, while
Framaco indicated in its letter that no changes had occurred in
Framaco’s or [DELETED] (its partner) structure or size status,
Framaco did indicate that it was adding another firm to its
team. Thus, we believe that some type of evaluation was
necessary to ensure that even previously qualified offerors
remained in compliance with the requirements of the Security
Act.
Turning to the analysis that was performed, we do not think the
aggregated list of projects provided by Framaco in its 2008
pre-qualification submission could form the basis for a
reasonable conclusion that Framaco has shown the requisite
experience performing services “similar in complexity, type of
construction and value to the project being bid,” as required by
22 U.S.C. sect. 4852(c)(2)(D). In our view, the Security Act’s
experience requirements anticipate a demonstration that an
offeror has completed at least one construction project of
similar complexity, size, and value as the 2009 embassy
construction projects. As shown above, considering simply the
value of Framaco’s projects, Framaco did not identify a single
completed project that reaches even half the value of the low
end of the estimated range for the Bujumbura construction
project (i.e., a $41.7 million project offered to show a
comparable value for a project estimated between $85 and 105
million); moreover, its largest identified project ($41.7
million) is less than one-third of the estimated value of the
Dakar project ($135 - $150 million). Since Framaco’s experience
consists of contracts of relatively low dollar values compared
to the estimated dollar values of the 2009 projects, we see no
basis for the agency’s conclusion that Framaco has the requisite
experience based on contract values. See Sytronics, Inc.,
B-297346, Dec. 29, 2005, 2006 CPD para. 15; J.A. Farrington
Janitorial Serv., B-296875, Oct. 18, 2005, 2005 CPD para. 187.
In addition, we think Framaco’s argument that the total value of
its list of smaller value projects equals the value of the 2009
embassy construction projects ignores the fact that combining
the values of a list of projects does not demonstrate the
necessary skills to complete and manage an entire embassy
construction project, as anticipated by the Security Act. See,
e.g., Marathon Constr. Corp., B-284816, May 22, 2000, 2000 CPD
para. 94 at 5-6. The identified projects mostly involved office
or building construction projects; none of them involved the
construction of an embassy (other than an interim renovation for
the embassy in Baghdad). In short, we conclude that the agency
has not provided a reasonable basis for its decision to
pre-qualify Framaco. (Caddell
Construction Company, Inc., B-401596; B-401597; B-401598,
September 21, 2009) (pdf)
Caddell argues that the agency’s approach of adding together 3
years of a company’s business receipts is not what the statute
intended. In fact, Caddell contends that the DOS interpretation
of the statute effectively reads out the term “3 years” because,
under the agency’s interpretation, if only 1 year of business
receipts provided sufficient business volume, and the remaining
2 years did not, the agency could still add together the 3 years
of business receipts and conclude that the offeror met the
requirement in 3 of the 5 years. In answer, the agency argues
that our Office should reject Caddell’s contentions and defer to
its interpretation, as it is the agency charged with
interpreting this statute. In matters concerning the
interpretation of a statute, the first question is whether the
statutory language provides an unambiguous expression of the
intent of Congress. If it does, the matter ends there, for the
unambiguous intent of Congress must be given effect. Chevron
U.S.A. Inc. v. Natural Res. Def. Council, Inc., 467 U.S. 837,
842-43 (1984). It is a fundamental canon of statutory
construction that words, unless otherwise defined by the
statute, will be interpreted consistent with their ordinary,
contemporary, common meaning. State of California v. Montrose
Chem. Corp., 104 F.3d 1507, 1519 (9th Cir. 1997); GAO,
Principles of Federal Appropriations Law, vol. 1, at 2-89 (3d
ed. 2004); see Mallard v. United States District Court for the
Southern District of Iowa, 490 U.S. 296, 301 (1989). Here,
the statute contemplates a significant restriction on an
offeror’s eligibility to compete for this type of contract.
Specifically, the statute seeks a showing that an entity must
have “achieved total business volume equal to or greater than
the value of the project being bid in 3 years of the 5-year
period” before the issuance of the solicitation. 22 U.S.C. sect.
4852(c)(2)(E). We think the ordinary and common meaning of these
words is that eligible offerors will have achieved a business
volume equal to or greater than the value of the project in each
of 3 years within the 5-year period. That said, given the
arguments raised by Caddell and State, we necessarily recognize
an element of ambiguity in this provision. When a statute
is silent or ambiguous with respect to the specific issue,
deference to the interpretation of an administering agency is
dependent on the circumstances. Chevron, 467 U.S. at 843-45; see
also United States v. Mead Corp., 533 U.S. 218, 227-38 (2001).
Where an agency interprets an ambiguous provision of the statute
through a process of rulemaking or adjudication, unless the
resulting regulation or ruling is procedurally defective,
arbitrary or capricious in substance, or manifestly contrary to
the statute, the courts will defer to this agency interpretation
(called “Chevron deference”). Mead, 533 U.S. at 227-31; Chevron,
467 U.S. at 843‑44. However, where the agency position reflects
only an informal interpretation, “Chevron deference” is not
warranted. In these cases, deference to an agency’s
interpretation is not mandatory, but rather the weight to be
accorded an agency’s judgment will depend on its relative
expertise, the thoroughness evident in its consideration, the
validity of its reasoning, its consistency with earlier and
later pronouncements, and all those factors which give it power
to persuade, though lacking power to control. Mead, 533 U.S. at
227-31; Skidmore v. Swift & Co., 323 U.S. 134, 140 (1944).
In our view, DOS’s interpretation of this statute is not
entitled to “Chevron deference,” as the interpretation arose in
the normal course of a procurement, and is not the result of
either a rulemaking or an adjudication. See, e.g., Intertribal
Bison Cooperative, B-288658, Nov. 30, 2001, 2001 CPD para. 195
at 4. In fact, while the agency suggests it has used this
interpretation before, it has given our Office no examples. In
any event, it has not promulgated this interpretation as part of
its extensive implementing regulations. Nor, as discussed below,
do we think the agency’s interpretation of this statute has the
persuasive weight deserving of deference. Our review leads us to
conclude that Caddell is correct in its argument that the
agency’s interpretation has the effect of rendering meaningless
the statute’s requirement for receipts at this level for 3 years
within the previous 5-year period. We also think the legislative
history of the Diplomatic Security Act does not support the
agency’s interpretation. (Caddell
Construction Company, Inc., B-298949.2, June 15, 2007) (pdf)
(NOTE:
This decision covers various sections of the law and covers them
in detail for this protest. If you work with the
Diplomatic Security and Antiterrorism Act, reading the entire .pdf
file may prove useful.)
In reviewing an agency’s source selection decision, we examine
the supporting record to determine whether the decision was
rational, consistent with the stated evaluation criteria,
consistent with applicable laws and regulations, and adequately
documented. Johnson Controls World Servs., Inc., B-289942, May
24, 2002, 2002 CPD para. 88 at 6; AIU N. Am., Inc., B-283743.2,
Feb. 16, 2000, 2000 CPD para. 39 at 7; Matrix Int’l Logistics,
Inc., B-272388.2, Dec. 9, 1996, 97-2 CPD para. 89 at 5. Where an
agency’s source selection decision is based on conclusions that
appear to be directly contrary to the contemporaneous record,
and where the agency’s evaluation record provides no explanation
regarding the apparent conflict, we cannot conclude that the
decision was reasonable. See AIU N. Am., Inc., supra. As
discussed above, the Security Act, and the agency’s stated
evaluation criteria regarding the procurement at issue here,
limited eligible offerors to “United States persons” or
“qualified United States joint venture persons.” The DOS
regulations implementing the statement of qualifications for the
Security Act provide that:
Organizations that wish to
use the experience or financial resources of any other legally
dependent organization or individual, including parent
companies, subsidiaries, or other related organizations, must
do so by way of a joint venture. A prospective bidder/offeror
may be an individual organization or a firm, a formal joint
venture in which the co-venturers have reduced their
arrangement to writing, or a de facto joint venture where no
formal agreement has been reached, but the offering entity
relies upon the experience of a related U.S. firm that
guarantees performance.
48 C.F.R. sect. 652.236-72.
Here, AICI-SP’s own
prequalification submission expressly stated: “The prospective
offeror . . . is not . . . a joint venture.” AR, Tab 2, AICI-SP
Prequalification Submission at 9. This statement appeared
directly beneath a definition of the term “joint venture,” which
stated the term “refers to a formal or de facto arrangement.”
Further, consistent with AICI-SP’s statement that it was not
seeking qualification on the basis of either a formal or de
facto joint venture, AICI-SP declined to provide any of the
necessary information regarding identification of the “U.S.
person participant” in the joint venture, nor did it identify
“all co-venturers,” as was specifically required. Finally, the
contemporaneous documentation supporting the agency’s summary
conclusion that AICI-SP was eligible to participate in this
procurement on the basis of a de facto joint venture provides no
explanation as to how the agency could reach this conclusion in
light of AICI-SP’s expressly contrary representation. On the
basis of the record here, we are unable to conclude that the
agency’s determination regarding AICI-SP’s eligibility for award
was reasonable. (Caddell Construction
Company, Inc., B-298949, January 10, 2007) (pdf) |