The Navy was to make its award “to the responsible offeror who
submits the lowest total price, technically acceptable offer
with acceptable or neutral past performance.” The RFP
incorporated by reference FAR § 52.212-1, “Instructions to
Offerors-Commercial Items,” which includes the following clause:
(h) Multiple awards. The Government
may accept any item or group of items of an offer, unless the
offeror qualifies the offer by specific limitations. Unless
otherwise provided in the Schedule, offers may not be
submitted for quantities less than those specified. The
Government reserves the right to make an award on any item for
a quantity less than the quantity offered, at the unit price
offered, unless the offeror specifies otherwise in the offer.
FAR § 52.212-1. The final paragraph of
the RFP quoted the following NAVSUP clause:
Single Award For All Items (JAN 1999) (NAVSUP):
Due to the interrelationship of
supplies and/or services to be provided hereunder, the
Government reserves the right to make a single award to the
offeror whose offer is considered in the best interest of the
Government, price and other factors considered. Therefore,
offerors proposing less than the entire requirement may be
determined to be unacceptable.
(sections deleted)
B. Did the RFP Authorize Split
Awards?
The basic issue in this case is
relatively straightforward – did the RFP authorize the Navy to
make a split award here – or not? Plaintiff asserts that the RFP
unambiguously indicates that the award will be made to a single
offeror for all four ports. It argues that the Navy deviated
from the RFP’s terms when it made the split award. Defendant,
however, contends that the RFP provided the Navy with an option
– allowing it to make either an award to a single offeror or to
split the award, depending on which was in the best interests of
the Navy. Defendant argues that while the Navy originally
intended to issue a single contract, it changed its mind – as it
was permitted to do under the RFP – based on the CO’s
recognition that considerable savings could be realized by
splitting the award. The latter approach, defendant asseverates,
did not vary from the terms of the RFP.
“It is hornbook law that agencies must
evaluate proposals and make awards based on the criteria stated
in the solicitation.” Banknote Corp., 56 Fed. Cl. at 386; see
also NEQ, 88 Fed. Cl. at 47; PGBA, LLC v. United States, 60 Fed.
Cl. 196, 207, aff’d, 389 F.3d 1219 (Fed. Cir. 2004). This
requirement is rooted in the Competition in Contracting Act (CICA)
and the FAR, both of which indicate that an agency shall
evaluate proposals and assess their qualities solely based on
the factors and subfactors specified in the solicitation. See 10
U.S.C. §§ 2305(a)(2)(A)-(3)(A); 48 C.F.R. §§ 15.303(b),
15.305(a); see also NEQ, 88 Fed. Cl. at 47; ManTech Telecomms. &
Info. Sys. Corp. v. United States, 49 Fed. Cl. 57, 66 (2001),
aff’d, 30 Fed. Appx. 995 (Fed. Cir. 2002). If the agency changes
any evaluation criterion after issuing the solicitation, it must
amend the solicitation and notify the offerors of the changed
requirement. See 48 C.F.R. § 15.206(a); see also id. §
15.206(d); Elec. Data Sys., LLC v. United States, 93 Fed. Cl.
416, 430 (2010); SP Sys., Inc. v. United States, 86 Fed. Cl. 1,
18 (2009). Consistent with these precepts, in a case such as
this, a protestor must show that: (i) the procuring agency used
a significantly different basis in evaluating the proposal than
was disclosed; and (ii) the protestor was prejudiced as a result
– that it had a substantial chance to receive the contract award
but for that error. Elec. Data Sys., 93 Fed. Cl. at 430;
Banknote Corp., 56 Fed. Cl. at 386-87.
So what does the RFP here disclose about the number of contracts
to be awarded? We begin, as we must, with the RFP’s plain
language. Banknote Corp., 365 F.3d at 1353; see also Coast Fed.
Bank, FSB v. United States, 323 F.3d 1035, 1038 (Fed. Cir. 2003)
(en banc). “If the provisions of the [RFP] are clear and
unambiguous,” the Federal Circuit has stated, “they must be
given their plain and ordinary meaning; we may not resort to
extrinsic evidence to interpret them.” Banknote Corp., 365 F.3d
at 1353. In addition, a RFP should be interpreted in a manner
that harmonizes and gives reasonable meaning to all its parts.
Id. “Provisions of a contract must be so construed as to
effectuate its spirit and purpose.” Gould, Inc. v. United
States, 935 F.2d 1271, 1274 (Fed. Cir. 1991); see also Metric
Constructors, Inc. v. NASA, 169 F.3d 747, 752 (Fed. Cir. 1999).
An interpretation that gives a reasonable meaning to all
provisions of a solicitation thus is preferable to one that
leaves a portion of it useless or inexplicable. Gould, Inc., 935
F.2d at 1274; see also Fulcra Worldwide, LLC v. United States,
2011 WL 286250, at *15 (Fed. Cl. Jan. 31, 2011); Linc Gov’t
Servs., LLC v. United States, 2010 WL 4484021, at *32 (Fed. Cl.
Nov. 5, 2010). Context thus defines the meaning of any given
term or provision in a government solicitation. Linc Gov’t Servs.,
2010 WL 4484021, at *32 (citing Metric Constructors, 169 F.3d at
752); see also Fulcra Worldwide, 2011 WL 286250, at *15.
In the court’s view, the plain language
of the RFP demonstrates that defendant reserved the right to
award either a single contract covering all four ports, or
multiple contracts covering one to three ports. In particular,
the RFP included the clause found at FAR § 52.212-1,
Instructions to Offerors – Commercial Items, which provides in
relevant part:
(h) Multiple awards. The Government
may accept any item or group of items of an offer, unless the
offeror qualifies the offer by specific limitation. Unless
provided otherwise in the Schedule, offers may not be
submitted for quantities less than those specified. The
Government reserves the right to make an award on any item for
a quantity less than the quantity offered, at the unit prices
offered, unless the offeror specifies otherwise.
Numerous cases have held that this
clause authorizes an agency to award either a single contract or
multiple contracts.
Principal among these decisions is Emeco
Indus., Inc. v. United States, 485 F.2d 652 (Ct. Cl. 1973).
There, the solicitation sought a contractor to manufacture
31,896 boxes. Id. at 654. Upon receiving an award to manufacture
2,713 boxes, the plaintiff assumed that it had won the contract
and that this was the first of many box orders. Id. Later,
however, it found that another contractor had received a
contract to manufacture the remaining 29,183 boxes. Id. The
plaintiff filed suit in the Court of Claims, asserting that the
solicitation, as written, obliged the defendant to purchase the
entire quantity of boxes from a single contractor and did not
authorize a split award. This court’s predecessor rejected this
argument, finding that “[a] careful reading” of the clause
quoted above permitted a split award. Id. at 655. It focused, in
particular, on that portion of the clause in which the
Government “‘reserves the right to make an award . . . for a
quantity less than the quantity offered . . . unless the offeror
specified otherwise in his offer.” It noted that the “plaintiff
placed no conditions on its bid,” and that, as a result, the
award of only 2,713 boxes, rather than the entire quantity of
31,896, was proper. Id. A phalanx of cases has construed the
multiple awards clause of FAR § 52.212-1 (or like-worded
predecessor provisions) to similar effect.
Plaintiff attempts to bring this case
outside this line of authority by citing several cases that have
held that the mere presence of FAR § 52.212-1(h) does not
authorize a split award where a solicitation otherwise
anticipates an aggregate award. See Int’l Code Servs., Inc.,
97-1 C.P.D. ¶ 216 (1997); Knoxville Glove Co., 93-1 C.P.D. ¶ 339
(1993); Gen. Aero Prods. Corp., 78-2 C.P.D. ¶ 70 (1978). It
bravely insists that the latter is the case here, centering its
claim on the evaluation mechanism in the RFP. In this regard,
plaintiff trumpets that portion of the RFP which states that
“the Government will award a contract resulting from the
solicitation to the responsible offeror who submits the lowest
total price, technically acceptable offer with acceptable or
neutral past performance.” It asserts that there can only be one
“lowest total price” under the RFP, a price that must
necessarily correspond to all four of the ports in question.
But, this interpretation of the “total
price” clause makes no sense. For one thing, it would render the
multiple awards clause an absurdity, because the Navy could not
sensibly make an award under that clause of “less than the
quantity offered,” i.e., an award for one to three ports, if
that decision had to be based upon the “total price” for all
four ports. Any reliance on the latter approach would almost
certainly run afoul of the CICA and FAR provisions that require
agencies to include price as an evaluation factor, all of which,
one would hope, require the agency to evaluate the price of what
it is buying, as opposed to the “price of tea in China.”6 See 41
U.S.C. § 253a(c)(1)(B); FAR § 15.304(c)(1); see also Serco, Inc.
v. United States, 81 Fed. Cl. 463, 491 (2008). It makes far more
sense to read the “total price” clause as authorizing multiple
awards, provided each award meets the evaluation criteria – that
is, the award must go to the otherwise qualified contractor
which submits the lowest total price for the lot in question.
This approach, unlike plaintiff’s strained reading, preserves
the integrity of both the “multiple awards” and “total price”
provisions, a result consistent with familiar canons of
construction. See Gould, 935 F.2d at 1274 (“an interpretation
which gives a reasonable meaning to all of its parts will be
preferred to one which leaves a portion of it useless,
inexplicable, inoperative, void, insignificant, meaningless,
superfluous, or achieves a weird and whimsical result.” (quoting
Arizona v. United States, 575 F.2d 855, 863 (1978))); see also
Spectrum Sciences & Software, Inc. v. United States, 84 Fed. Cl.
716, 735 (2008). Indeed, in analogous circumstances, several
cases have held that the presence of “total price” clause in a
RFP or solicitation does not prevent an agency from awarding
multiple contracts. See Gichner Mobile Sys., 85-1 C.P.D. ¶ 534
(1985); Granite State Mach., 80-2 C.P.D. ¶ 396; see also SKS
Group, Ltd., 82-1 C.P.D. ¶ 574 (1982).
That the Navy had the option of awarding
more than one contract accords with two other provisions in the
RFP. The first of these is found in the PWS, which stated that
“[t]he contract is sub-divided into Lots. Lots may be for
individual ports or they may include several ports under one
Lot.” This language, which provides for the variable grouping of
ports, makes sense only if the Navy could award more than one
contract under the RFP, i.e., could “sub-divide[]” the work; it
makes utterly no sense if the Navy could award only a single
contract. That the RFP envisioned the former, and not the latter
situation, is suggested by yet another clause in the RFP, to wit
–
SINGLE AWARD FOR ALL ITEMS (JAN 1999)
(NAVSUP)
Due to the interrelationship of supplies and/or services to be
provided hereunder, the Government reserves the right to make
a single award to the offeror whose offer is considered in the
best interest of the Government, price and other factors
considered. Therefore, offerors proposing less than the entire
effort specified herein may be determined to be unacceptable.
Of course, it would be passing odd to
“reserve the right to make a single award” if, as plaintiff
contends, the RFP only authorized the agency to make a single
award. Given the common understanding of the word “reserve,” it
makes eminent sense to read this provision as preserving the
Navy’s option to award a single contract in the face of other
RFP provisions authorizing the award of multiple contracts
Viewing the RFP as affording the Navy this flexibility accords
with Congress’ expectation, manifested in the CICA, that
agencies will award contracts to “the responsible source whose
proposal is most advantageous to the United States, considering
only cost or price and the other factors included in the
solicitation.” 10 U.S.C. § 2305(b)(4)(C); see also Lockheed
Missiles & Space Co., Inc. v. Bentsen, 4 F.3d 955, 959 (Fed.
Cir. 1993); Friend v. Lee, 221 F.2d 96, 100 (D.C. Cir. 1955).
Various cases have interpreted this legislative command to mean
that “if multiple awards will be most advantageous to the
Government, and they are not prohibited by the solicitation,
multiple awards should be made.” Rocky Mountain Trading Co.,
87-2 B.C.A. ¶ 19,725. Here, of course, the multiple awards were
advantageous to the Navy in yielding the lowest cost for the
husbanding services in question. And those awards were not
prohibited by the RFP. (Glenn
Defense Marine (Asia), PTE, LTD v. U. S., No. 10-852c, March
1, 2011) (pdf) |