|
The protester generally contends that the agency unreasonably
rated its proposal as unacceptable under the safety evaluation
factor. OER maintains that "it was not given a clear direction
on exactly what information [the agency] was looking for in
regards to requirements for safety measures" and that its
proposal was "not reviewed at the same level as other firms."
Protester's Comments at 1. OER also challenges the agency's
evaluation of FCC's proposal under the safety factor.
In reviewing protests objecting to an agency's technical
evaluation, our role is limited to ensuring that the evaluation
was reasonable and consistent with the terms of the
solicitation. CMI Mgmt., Inc., B-402172, B-402172.2, Jan. 26,
2010, 2010 CPD para. 65 at 2. It is an offeror's responsibility
to submit an adequately written proposal that establishes its
capability and the merits of its proposed technical approach in
accordance with the evaluation terms of the solicitation. See
Verizon Fed., Inc., B-293527, Mar. 26, 2004, 2004 CPD para. 186
at 4. The protester's mere disagreement with the agency's
judgment does not establish that an evaluation was unreasonable.
Akal Security, Inc., B-401469 et al., Sept. 10, 2009, 2009 CPD
para. 183 at 3. Based on our review of the record, the agency's
finding that OER's initial and revised proposals failed to
adequately address the safety evaluation factor was reasonable
and supports the agency's decision to exclude OER's proposal
from further consideration.
Here, in order for a proposal to be evaluated as technically
acceptable, the RFP required that an offeror provide detailed
narratives that addressed each of the four identified elements
of the safety evaluation factor. While OER may have taken a
limited view as to what information was necessary to address the
question of safety--the protester states that "safety is black
and white" and "the rules and regulations have absolutely no
gray area," id. at 1-2--we note that simply citing the
applicable OSHA and/or ANSI rules or regulations in its proposal
did not comport with the RFP's specific requirement for a
detailed narrative describing the offeror's safety procedures
for itself and its subcontractors, as well as the safety program
and procedures employed by the offeror under similar projects it
performed over the last 5 years. Because OER did not furnish all
of the information required by the RFP, we have no basis to
question the agency's determination that OER's proposal was
technically unacceptable.
Moreover, during two rounds of discussions, the agency
specifically questioned the protester with regard to its
approach to managing and implementing safety procedures for
itself and its subcontractors. Yet, it still failed to submit a
response addressing the agency's concerns; indeed, OER provided
essentially no information for the agency to evaluate regarding
the firm's compliance with this evaluation factor. To the extent
OER contends that the agency failed to inform OER of the level
of detail sought by the agency during the two rounds of
discussions, its contention is without merit. Agencies are not
required to "spoon-feed" offerors during discussions, but rather
need only lead offerors into the areas of their proposals that
require amplification or revisions. Martin Elecs., Inc., AMTEC
Corp., B-404197, et al., Jan. 19, 2011, 2011 CPD para. 25 at 6.
The agency clearly advised OER during both rounds of discussions
that OER needed to provide greater detail regarding its safety
program. (OER Services, LLC,
B-405273, October 7, 2011) (pdf)
We find that JRS's quotation was properly found unacceptable. In
this regard, the RFQ's plain language required vendors to submit
supporting documentation to show that the instructor candidate
possessed the required qualifications and experience. RFQ at 25.
Although the protester's quotation generally described the
candidate's experience, the quotation did not include sufficient
details (such as where the individual worked) for the agency to
verify the experience. Furthermore, JRS failed to provide the
information when repeatedly requested by the agency. Since the
quotation did not contain any supporting documentation showing
that the instructor candidate possessed the requisite
experience, and JRS failed to provide the documentation when
requested by the agency, we find reasonable the agency's
determination that JRS' quotation was technically
unobjectionable. (JRS Management,
B-405361; B-405361.2; B-405361.3, October 3, 2011) (pdf)
Orion asserts that its proposal included sufficient information
for the agency's evaluation, and, therefore, the agency's
determination to eliminate the proposal from consideration for
award was unreasonable. Protest at 8. The agency responds that
because certain information regarding Orion team member costs
was not included in Orion's proposal or submitted by the team
members to the agency, as required by the solicitation, the
agency could not evaluate the proposal for cost realism as
contemplated by the solicitation's evaluation scheme and the
Federal Acquisition Regulation (FAR). Contracting Officer
Statement para. 15, at 4-5. According to the agency, examples of
missing but required and necessary information include the
direct labor rates, indirect cost rates, and ODCs of five Orion
team members that were to perform work under the task order
scenario PWS. Id. at 5. The agency also asserts that the missing
information precluded a determination as to whether Orion team
member ODCs were included in Orion's proposal. Id.
In its comments on the agency's report, Orion argues that the
agency could have evaluated the realism of Orion team member
costs using information contained in Orion's proposal. Comments
at 6. As described above, the information regarding team member
labor in the labor cost table of Orion's cost/price proposal was
limited to the number of hours to be performed under a given
labor category for a PWS paragraph, and the total cost, with
fee, for the work. AR, Tab 7, Orion Proposal, Vol. IV, Labor
Cost Table. Orion contends that the agency could have derived
Orion team member labor rates by dividing the number of hours by
the total cost, with fee, and then used the derived rates for
its cost realism analysis. Comments at 7.
In reviewing protests challenging allegedly improper
evaluations, or, as here, the rejection of a proposal based on
the agency's evaluation, it is not our role to reevaluate
proposals; rather, our Office examines the record to determine
whether the agency's judgment was reasonable, and in accordance
with the solicitation criteria and applicable procurement
statutes and regulations. Ira Wiesenfeld & Assocs., B- 293632.3,
June 21, 2004, 2004 CPD para. 132 at 2. A protester's mere
disagreement with the agency's judgment does not establish that
an evaluation, or rejection, was unreasonable. Id.
It is an offeror's responsibility to submit a well-written
proposal, with adequately detailed information which clearly
demonstrates compliance with the solicitation and allows a
meaningful review by the procuring agency. CACI Techs., Inc.,
B-296945, Oct. 27, 2005, 2005 CPD para. 198 at 5. Any proposal
that fails to conform to material terms of the solicitation may
be considered unacceptable and not form the basis for an award.
Gordon R.A. Fishman, B-257634.3, Nov. 9, 1995, 95-2 CPD para.
217 at 2. Even where individual deficiencies may be susceptible
to correction though discussions, the aggregate of many such
deficiencies may preclude an agency from making an intelligent
evaluation, and the agency is not required to give the offeror
an opportunity to rewrite its proposal. Jack Faucett Assocs.,
B-253329, Sept. 7, 1993, 93‑2 CPD para. 154 at 4, aff'd, Jack
Faucett Assocs.-Recon., B-253329.2, Apr. 12, 1994, 94‑1 CPD para.
250. Further, communications with offerors before the
establishment of the competitive range "shall not be used to
cure proposal deficiencies or material omissions, or materially
alter the technical or cost elements of the proposal." FAR sect.
15.306(b)(2).
As discussed above, the solicitation here provided that offerors'
task order scenario cost/price proposals would be evaluated for
cost realism and that proposed costs would be evaluated for
reasonableness using cost analysis techniques. RFP sections
M.1.1.2, M.4.0. The FAR describes cost analysis as follows:
Cost analysis is the review and evaluation
of any separate cost elements and profit or fee in an offeror's
or contractor's proposal, as needed to determine a fair and
reasonable price or to determine cost realism, and the
application of judgment to determine how well the proposed costs
represent what the cost of the contract should be, assuming
reasonable economy and efficiency.
FAR sect. 15.404-1(c)(1). With respect to
cost realism analysis, the FAR provides as follows:
Cost realism analysis is the process of
independently reviewing and evaluating specific elements of each
offeror's proposed cost estimate to determine whether the
estimated proposed cost elements are realistic for the work to
be performed; reflect a clear understanding of the requirements;
and are consistent with the unique methods of performance and
materials described in the offeror's technical proposal.
Id. sect. 15.404-1(d)(1). The FAR also
provides that cost realism analyses "shall be performed on cost
reimbursement contracts." Id. sect. 15.404-1(d)(2)
Although application of the methodology
advocated by Orion would have permitted the agency to derive the
fully loaded labor rates of the Orion team members for which
cost information was missing, such methodology would not have
permitted the agency to review the specific elements of the team
members' costs to determine whether those elements were
realistic or reasonable. For example, using Orion's methodology,
the agency could not have derived the team members' direct labor
rates or indirect costs, such as fringe benefit or G&A costs.
Accordingly, application of Orion's methodology would not have
permitted the agency to evaluate Orion's proposed costs as
contemplated by the FAR. See FAR sect. 15.404-1(c)(2)(i)(A),
(d)(1). Further, the informational deficiencies in Orion's
proposal relate to specific and detailed cost evaluation
criteria in the solicitation, RFP sections M.1.1.2, M.4.0, and
the solicitation expressly cautioned offerors that failure to
submit the information in question could result in the
elimination of a proposal from consideration for award, id.
sect. L.4.4.6.1.1(d). We therefore conclude that the agency
reasonably excluded Orion's proposal from the competition. See
Robotic Sys. Tech., B‑278195.2, Jan. 7, 1998, 98-1 CPD para. 20
at 9-10; Jack Faucett Assocs., supra; see also FAR sect.
15.306(b)(2). (Orion Technology,
Inc., B-405077, August 12, 2011) (pdf)
AC4S protests that the agency's assessment of a deficiency under
the mission support subfactor was improper because the
"inadvertent omission" of the phrase "in subcontracting" from
one metric did not change AC4S's intent to meet the SOO's
objective to increase small business subcontracting. AC4S argues
that its intent to meet the objective was apparent from Table 1
and from its proposal throughout, in which AC4S repeatedly
discussed its intent to subcontract 30 percent of the work to
other small business subcontractors. AC4S also argues that the
agency should have corrected the missing phrase through
clarifications. We disagree.
Clearly stated RFP requirements are considered material to the
needs of the government, and a proposal that fails to conform to
such material terms is unacceptable and may not form the basis
for award. National Shower Express, Inc.; Rickaby Fire Support,
B-293970, B-293970.2, July 15, 2004, 2004 CPD para. 140 at 4-5.
It is a fundamental principle in a negotiated procurement that a
proposal that fails to conform to a material solicitation
requirement is unacceptable. See TYBRIN Corp., B-298364.6,
B-298364.7, Mar. 13, 2007, 2007 CPD para. 51 at 5. Here, we
conclude that the government-specified performance metrics were
material requirements of the RFP, that the agency reasonably
determined that AC4S improperly modified the performance metrics
in a manner that did not conform to the terms of the RFP, and
that the error was not subject to correction via clarifications.
Under a performance based contracting arrangement, such as we
have here, performance metrics are more than mere proposal
evaluation tools. Rather, the metrics become the measurable
performance standards used to assess the contractor during
performance, and to determine the application of performance
incentives and disincentives. Indeed, the measures, metrics, ALQ,
and incentives/disincentives establish the performance levels
that are required to meet the objectives specified by the SOO,
and are critical aspects of the resulting performance-based
contract. In this case, the agency provided certain
government-specified performance metrics reflecting the level of
performance that the government required, and the agency
repeatedly cautioned the offerors that these metrics were not to
be revised in any way. Such clearly stated RFP terms are
undoubtedly material to the needs of the government, and failure
to conform to such terms renders a proposal unacceptable.
Next, based on our review of the RFP and AC4S's proposal, it is
readily apparent that AC4S's modification of the performance
metric at issue did, in fact, materially alter the metric's
meaning. The agency explains that, based on its past experience,
the awardees will likely outgrow their small business status
over the course of the contract, leaving few firms to compete
for future set-asides. COSF, at 10. The objective "[e]ffectively
use small businesses to assure achievement of subcontracting
targets allowing for mentorship of small businesses" was
therefore included in the SOO to encourage awardees to "mentor
and grow other small businesses, that would obtain relevant
experience, and . . . enhance the competition for the next
generation of small business set-asides of this kind." Id.
The applicable government-provided performance metric, "usage of
SBs in subcontracting," was specified to provide a common,
clearly understandable and measurable basis for monitoring
awardee's success in meeting the above objective during
performance. The metric, "usage of SBs," as modified by AC4S,
however, fails to reflect the intent of the SOO objective to
assure achievement of subcontracting targets and allow for
mentorship of small businesses, or the intent of the provided
metrics, because it captures AC4S's own efforts as a small
business along with those of its small business subcontractors.
The extent to which AC4S's modified performance metric deviated
from the SOO objective and government-specified metric is
apparent when it is considered that AC4S also included its own
efforts as a small business in its proposed percentage small
business usage in ALQ 1.d, contrary to the RFP's instructions.
In Volume IV of its proposal, AC4S stated that "AC4S is
retaining 80% of the contract towards small businesses. The 80%
includes 50% for AC4S." On the same page of the proposal, in
Table 3 – Subcontracting Participation Goals, AC4S confirms that
30 percent of the contract will be subcontracted to small
businesses. However, rather than enter the 30 percent figure
from Table 3 into ALQ 1.d, as instructed, AC4S entered "80
percent."
The overall effect is that, by including its own efforts in the
small business utilization percentage of ALQ 1.d, and by
omitting the phrase "in subcontracting" from metric 1.d, AC4S
made it possible to compensate for failure to meet its
subcontracting objective by increasing its own share of contract
performance. For example, if AC4S were to fall 10 percent short
of its small business subcontracting target during performance,
but increase its own portion of contract performance to 60
percent, AC4S would meet its modified performance metric of 80
percent small business usage and avoid performance-based
disincentives, despite failing to meet the small business
subcontracting target. Therefore, the omission of the phrase "in
subcontracting" had a material effect on AC4S's commitment to
conform to the specified small business usage metric required by
the RFP.
AC4S also suggests that the omission of the phrase "in
subcontracting," and the inclusion of its own efforts in the
small business usage percentage should have been corrected
through clarifications. We disagree. Clarifications are limited
exchanges between the agency and offerors that may occur where,
as here, contract award without discussions is contemplated. FAR
sect. 15.306(a). An agency may, but is not required to, engage
in clarifications that give offerors an opportunity to clarify
certain aspects of proposals or to resolve minor or clerical
errors. Id. However, clarifications may not be used to cure
proposal deficiencies or material omissions, materially alter
the technical or cost elements of the proposal, or revise the
proposal. Superior Gunite, B-402392.2, Mar. 29, 2010, 2010 CPD
para. 83 at 4. Because the omission of the phrase "in
subcontracting" in this case was both a material omission and a
deficiency, the error was not subject to correction via the
clarifications process. (AC4S,
Inc., B-404811.2, May 25, 2011) (pdf)
EXCEPTION TO FIXED PRICE REQUIREMENT
Solers argues that BAH's price proposal improperly took
exception to the RFQ requirement to propose a fixed price. We
agree.
The requirement to propose fixed prices is a material term or
condition of a solicitation requiring such pricing. Marine
Pollution Control Corp., B-270172, Feb. 13, 1996, 96-1 CPD para.
73 at 2-3. Where a solicitation requests proposals on a
fixed-price basis, a price offer that is conditional and not
firm cannot be considered for award. Id.; SunEdison, LLC,
B-298583, B-298583.2, Oct. 30, 2006, 2006 CPD para. 168 at 5
(protest sustained where the awardee conditioned its fixed price
on the successful completion of a financial transaction between
the awardee and a third party).
Here, the RFQ required offerors to submit proposals on a
fixed-price basis. RFQ at 3. Offerors were also required to
provide pricing information regarding the basis for their fixed
price, including fully-loaded labor hourly rates for personnel,
and information concerning the offeror's GSA schedule labor
rates. Id. The contractor was to be paid fixed monthly payments
based on a delivery schedule set forth in the solicitation. Id.
Additionally, as relevant here, the PWS stated that the agency
would provide space for contractor personnel at the government
worksite as follows:
Place of Performance. The contractor shall perform the majority
of work for this contract at its own facilities. The government
may provide space for up to seven (7) personnel to perform work
under other tasks at its office space currently located at 5600
Columbia Pike, Falls Church, VA. In early 2011, the government's
office space will relocate to Fort Meade, Maryland.
RFQ, PWS sect. 9.1.
With regard to the place of performance requirement, BAH stated
it "will comply with all items in PWS Section 9.0 and 9.1." AR,
Tab J, BAH Revised Proposal, vol. 1, at 25.
In its cost proposal, BAH stated that its price was based on
labor rates in its GSA schedule 70 contract. AR, Tab J, BAH
Revised Proposal, vol. 2, at 8. The awardee further explained
that its price "includes both Contractor and Government site
rates." Id. BAH explained that the government site rates were
provided at a lower rate as compared to the contractor-site
rates, and that their use "presents a significant discount or
savings, to the Government, in excess of $[deleted] over the
life of the contract." Id. BAH explained that it was able to
offer the discount for the following reasons:
Government site rates are offered when the
Government provides suitable work facilities and related
equipment (e.g.: telephone, copier, parking, furniture desktop
computer, and other standard equipment and office supplies) for
a period of no less than [deleted] work days at a Government
site. [BAH] maintains the lower overhead rates on which the
Government site labor prices are based as these [sic] or similar
facilities are provided on a continuing basis throughout the
task period and as long as sufficient tasking is provided to
perform assignments on a full-time basis at these work sites.
Id. (emphasis added). BAH also stated,
however, that in the event the conditions for the
government-site work spaces set forth in its proposal did not
occur, different rates could be applied:
Additionally, Booz Allen understands that a
number of our engineering and development staff will spend the
majority of their time working out of Government lab spaces and
as such we are offering Government site rates on those staff
members which represent[s] a significant discount of over
$[deleted] to the Government. In the event that these conditions
are not met, contractor site rates may need to be applied.
Id. (emphasis added).
In addition to the language above, Solers
notes that BAH's price proposal reflects [deleted] labor hours
for the base year and each option year of performance. AR, Tab
J, BAH Proposal, vol. 2, attach. A, at 17-19. For the base
period, the protester calculates that BAH proposed [deleted]
hours at government site rates; based on BAH's calculation of
[deleted] hours of labor per year per FTE, this translates to
[deleted] FTEs at the government-site rates, out of the
[deleted] FTEs proposed. Protester's Supp. Protest at 4-5,
citing AR, Tab J, BAH Proposal, vol. 2, attach. A, at 22-35. For
the 4 option years, Solers contends that BAH used
government-site rates for [deleted] of the total [deleted] FTEs
proposed. Id., citing AR, Tab J, BAH Proposal, vol. 2, attach.
A, at 36-111. Solers contends that because these assumptions
were built into BAH's price, and because the RFQ stated that the
government would provide space at the government site for no
more than seven personnel, BAH's price contained a exception to
the fixed price that could result in BAH seeking a price high
than it offered.
DISA and BAH contend that the language in the awardee's proposal
was not an exception to the fixed-price requirement, and was
instead merely a suggestion that BAH might request an adjustment
to its fixed price in the future. The agency argues that BAH
proposed a fixed price, and that regardless of what BAH stated
concerning its calculation of its fixed price, the awardee was
required to perform for that price. SAR at 13.
We disagree. We think that a fair reading of BAH's proposal
shows that the awardee took exception to the requirement to
propose a fixed price. In this regard, as stated above, BAH
stated that it had based its price on government-site and
contractor-site rates, and that use of the government-site rates
permitted the offeror to offer "a significant discount or
savings" to the agency. AR, Tab J, BAH Revised Proposal, vol. 2,
at 8. With regard to the lower government-site rates, BAH stated
that these rates "are offered when the Government provides
suitable work facilities and related equipment . . . for a
period of no less than ninety (90) continuous work days at a
Government site." Id. (emphasis added). BAH's proposal also
stated that it was able to offer these rates because the offeror
experiences lower overhead rates when its personnel are provided
space and were working full-time at the government site. Id. As
noted above, BAH's price proposal was premised on its personnel
performing significantly more work at the government site than
was contemplated by the solicitation. Finally, BAH stated, in
the event that the conditions set forth in its price proposal
concerning the availability of space at the government site, the
higher contractor-rates "may need to be applied." Id. The
collective effect of these statements in BAH's proposal amount
to BAH conditioning its offered price on a greater use of
government facilities than contemplated or authorized by the
solicitation, such that its offered price was conditional not
firm.
On this record, we find that DISA improperly issued the task
order to BAH, based on a proposal that took exception to the
solicitation requirement to propose a fixed price. SunEdison,
LLC, supra; Marine Pollution Control Corp., supra. Because DISA
cannot accept BAH's proposal that did not offer a fixed price
for award, and because Solers, which did offer a fixed price,
was the only other offeror who submitted a proposal, we conclude
that Solers was prejudiced by DISA's error, and sustain the
protest on this basis. (Solers,
Inc., B-404032.3; B-404032.4, April 6, 2011)
ATS challenges HUD's determination that its proposal was
technically unacceptable under the licensing/insurance factor.
Protest at 2. With respect to the protester's ability to legally
conduct real estate closings in California, ATS argues that
there is no clear restriction under California law prohibiting a
joint venture comprised of a licensed California firm and a
non-licensed, Colorado firm, from conducting real estate
closings in California. Comments at 4. Although ATS acknowledges
that the joint venture agreement provided that American Title
Services Company would have complete authority and control of
the ATS joint venture, it argues that this did not affect
Fresno's ability to conduct closings in California. See id. at
3. Accordingly, ATS contends that HUD's unacceptability
determination is unreasonable, because HUD has not demonstrated
that ATS will be unable to legally perform real estate closings
in California.
In reviewing protests of alleged improper evaluations and source
selections, our Office examines the record to determine whether
the agency's judgment was reasonable and in accord with the
stated evaluation criteria and applicable procurement laws. See
ABT Assocs., Inc., B-237060.2, Feb., 26, 1990, 90-1 CPD para.
223 at 4. It is an offeror's responsibility to submit a
well-written proposal, with adequately detailed information
which clearly demonstrates compliance with the solicitation and
allows a meaningful review by the procuring agency.
International Med. Corps, B-403688, Dec. 6, 2010, 2010 CPD para.
292 at 7. A protester's mere disagreement with the agency's
evaluation provides no basis to question the reasonableness of
the evaluators' judgments. See Citywide Managing Servs. of Port
Washington, Inc., B‑281287.12, B‑281287.13, Nov. 15, 2000, 2001
CPD para. 6 at 10-11.
The RFP here required offerors to affirmatively demonstrate
their ability to legally perform real estate closings in
California. In this regard, offerors were required to identify
in their proposals applicable California law. See RFP sect.
L.7(1). The TEP found that ATS had not made such an affirmative
showing in its proposal with respect to the joint venture.
Specifically, the evaluators were concerned that ATS had not
provided any information in its proposal "'regarding how a
Colorado joint venture member can legally manage its California
joint venture partner with regard to performing closing services
under a California license."' See AR, Tab 18, TEP Evaluation
Report, at 8.
We find HUD's evaluation of ATS's proposal to be reasonable.
Although ATS argues that HUD did not demonstrate that the joint
venture would be unable to legally perform closings in
California, it was the protester's responsibility under the RFP
to affirmatively establish that the joint venture could comply
with California law in performing the contract. ATS did not do
so in its proposal. That is, despite the fact that Fresno may be
licensed to perform closings in California, the joint venture
agreement provided that the joint venture (which submitted the
offer here) would be controlled and managed by American Title
Services Company. ATS did not show in its proposal or in its
protest submissions that this business arrangement would be
permitted under state law to perform closings in California. In
short, ATS merely disagrees with the agency's evaluation, which
does not demonstrate that the evaluation was unreasonable.
(American Title Services, a Joint
Venture, B-404455, February 4, 2011) (pdf)
Brown protests the agency’s determination that its quotation was
technically unacceptable. It argues that its quotation meets the
requirements of the statement of work, and contends that any
questions the agency had about the quotation could have been
resolved through discussions.
Our Office reviews challenges to an agency’s technical
evaluation to determine whether the agency acted reasonably and
in accord with the solicitation’s evaluation criteria and
applicable procurement statutes and regulations. System Eng’g
Int’l, Inc., B-402754, July 20, 2010, 2010 CPD para. 167 at 4. A
vendor’s mere disagreement with the agency’s evaluation is not
sufficient to demonstrate that the evaluation is unreasonable.
Trinity Tech. Group, Inc., B-403210, Sept. 23, 2010, 2010 CPD
para. 235 at 2. Furthermore, it is a vendor’s burden to submit
an adequately written quotation and it runs the risk that its
quotation will be evaluated unfavorably where it fails to do so.
System Eng’g Int’l, Inc., supra.
On the record before us, we find no basis to object to the
agency’s evaluation. As noted above, the RFQ required that the
selected vendor provide “full turn key” webcasting that meets
the requirements of eight specific tasks, including providing a
link to the NIST/ITL/CSD web cite and providing a webcast page
with the same look and feel as the current ISPAB page with the
capability to allow viewers to send, post, and tag questions to
posted agenda items. RFQ at 3. The record shows that Brown’s
quotation did not meet these requirements because its login
requirement violated the NIST privacy policy, its webcast page
did not have the same look and feel as the ISPAB page, and the
quotation did not demonstrate with certainty that Brown would
meet the requirement to send, post, and tag questions without
further action from the agency. AR, Tab 6, Technical Evaluation,
at 1-2; AR Tab 3, Statement of Evaluator, paras. 9, 11‑12, 14,
17-18.
Brown disagrees with these conclusions. It contends that its
login feature can be turned off, and that the quotation’s
commitment to “create the portal page for design consistency and
functional compatibility with the NIST home page” satisfies the
requirement to provide the same look and feel as the ISPAB page.
Comments at 2, 4. Brown also denies that there is any ambiguity
in its quotation that should have led to a rating of technical
unacceptability. Id. at 4. It contends that, if the agency had
any questions, it should have raised them during discussions.
Id. at 3, 5.
However, as noted above, the RFQ advised vendors that
discussions would not be conducted. RFQ at 8. Because the agency
had no obligation to engage Brown in discussions about its
quotation, it was imperative that Brown provide a clear and
adequately written quotation. Brown’s quotation did not make
clear that the login feature was an option that could be turned
off, or that it was firmly committing to meet the requirements
without further direction from the agency. Although Brown
continues to disagree with the agency’s evaluation conclusions,
it has not shown them to be unreasonable.
Based on the reasonable determination that Brown’s quotation was
technically unacceptable, we find unobjectionable the agency’s
issuance of the purchase order to a vendor with a higher-priced,
technically-acceptable quotation. (George
T. Brown Associates, Inc., B-404398, January 26, 2011) (pdf)
HDT Tactical Systems, Inc., of Solon, Ohio, protests the
elimination of its proposal from further consideration during a
downselection procedure conducted by the Department of the Army
in connection with its acquisition of variously-sized improved
environmental control units (IECUs), under request for proposals
No. W909MY-08-R-0014. HDT maintains that its IECUs were
misevaluated during a testing phase of the acquisition, that the
agency treated it and its competitor, Mainstream Engineering,
Inc., of Rockledge, Florida, disparately, and that the agency
unreasonably failed to engage in discussions.
(sections deleted)
The record shows that Mainstream's IECUs
passed all applicable tests. AR, exh. C, at 4. However, during
the testing of HDT's units in March 2010, its 9,000 BTU IECU
failed the high temperature operational limit test, and its
18,000 BTU IECU failed the sensible cooling capacity test.
Specifically, the 9,000 BTU IECU was unable to operate
uninterrupted for 1 hour at a temperature of 125° Fahrenheit
(F), as required; it was only able to pass the test at a
temperature of 123° F. AR, exh. B, at 60. With respect to HDT's
18,000 BTU IECU, the unit was required to have a sensible
cooling capacity of 13,100 BTUs per hour, but was only able to
achieve a sensible cooling capacity of 12,774 BTUs per hour. Id.
at 63.
Based on the results of the testing, as well as the agency's
evaluation of the firms' downselection proposals, the agency
made award to Mainstream at a cost/price higher than HDT's
($63,085,456 versus $41,388,969), concluding that HDT was
ineligible for award based on its failure to pass all of the
required tests. AR, exh. F5. After being advised of the agency's
downselection decision and receiving a debriefing, HDT filed
this protest.
HDT argues that the agency's evaluation of its 9,000 BTU IECU
was unreasonable. According to the protester, when its unit was
subjected to the high temperature operational limit test, it was
connected to the wrong power source for an interval of time
prior to the test; this caused the unit's compressor to
overheat, thereby preliminarily predisposing it to fail the high
temperature operational limit test.
In reviewing an agency's evaluation of proposals, we will not
reevaluate proposals; rather, we examine the record to determine
whether the agency's evaluation conclusions were reasonable and
consistent with the terms of the solicitation (or, as in this
case, the underlying contracts), as well as applicable
procurement laws and regulations. Engineered Elec. Co. d/b/a/
DRS Fermont, B-295126.5, B-295126.6, Dec. 7, 2007, 2008 CPD para.
4 at 3-4.
We have no basis to object to the evaluation here. Even if we
agreed with HDT regarding the propriety of the high temperature
operational limit test, as discussed, HDT's 18,000 BTU IECU
independently failed the sensible cooling capacity test, and HDT
does not take issue with the manner in which that test was
conducted. Since, as discussed, the express contract terms
required passage of all tests in order for a proposal to be
considered for award, HDT's proposal was properly excluded from
further consideration based on this failure, notwithstanding the
outcome of the high temperature operational limit test.
HDT asserts that the agency engaged in disparate treatment in
connection with the conducting of the testing described above.
According to the protester, the record shows that Mainstream was
permitted to postpone its testing for a period of approximately
5 weeks; HDT explains that it, too, would have benefited from
postponement of its official testing. HDT maintains that, had
its testing been postponed, it could have implemented a design
change to its 18,000 BTU IECU that would have enabled it to pass
the sensible cooling test. HDT maintains, in this regard, that
it had already devised the engineering change necessary to
improve the performance of its unit, but that it chose not to
activate the feature during testing because it believed a
malfunctioning part needed replacing, and HDT did not believe it
could effect the repair before its scheduled testing time. HDT
concludes that it was unreasonable for the agency to allow
Mainstream to postpone its official testing without advising HDT
that it could postpone its testing.
We have no basis to object to the agency's actions here. The
record shows that the agency did not advise any offeror that it
could postpone its testing. Rather, Mainstream approached the
agency and, on its own initiative, requested an opportunity to
reschedule its official testing to a later date within 350 days
after contract award (offerors were free to establish any
testing date in their test plans, so long as the date was within
the 350 day period). In this regard, in an affidavit submitted
by the contracting officer's representative (COR) for the
Mainstream contract, the COR states:
In my capacity as COR on Mainstream's
contract, I received a phone call from . . . [the cognizant
Mainstream representative] on March 5, 2010. He informed me that
Mainstream wanted to postpone all of its official tests because
Mainstream's own unofficial tests conducted at Intertek [an
independent testing concern used by both firms] had gone poorly
and revealed the need for further design changes. After
determining that the rescheduled testing would still occur
within the required 350 days after contract award (DAC) per SOW
[statement of work] Para. 4.6, I granted the request. All of
Mainstream's official tests were postponed to later dates, not
just the official testing to be performed at ITS [Intertek]. No
change was made to Mainstream's test plan except to postpone the
tests for a five-week period.
Supplemental Agency Report, exh. D.
HDT did not ask to reschedule its testing
date. In this connection, HDT's representative submitted an
affidavit in which he states:
HDT did not believe, at the time of
downselection testing, that it was a realistic option for HDT to
reschedule its downselection testing for a future date, because
(1) we believed that Mainstream had already tested its IECUs
before HDT in early March, and that delay would reflect poorly
on HDT, and (2) we believe[d] the Army would either not permit
[the] delay or would hold [the] delay against HDT in its
evaluation.
HDT's Supplemental Comments, Nov. 10, 2010,
attach. B, at 2. However, notwithstanding HDT's subjective
beliefs, nothing in the contracts specified when, within the 350
day period, testing should occur, and nothing precluded offerors
from rescheduling their testing--within the larger window
allowed for testing--to a later date. In addition, nothing in
the contracts suggested that an offeror's decision to reschedule
its testing would have a negative evaluation impact, since, as
noted, offerors were free to select their own testing dates
within the 350 day post-award period. Moreover, the COR for the
HDT contract submitted an affidavit in which he states:
Had HDT requested that I (as COR) grant a
postponement of all its scheduled official downselection testing
to allow them to make additional improvements to its test units,
I would have granted the request as long as test completion was
not delayed beyond the contractually required date of 350 days
after contract award.
Supplemental Agency Report, exh. C, at 1.
In our view, both firms made a business judgment concerning
whether or not to request an extension of time to perform their
official testing. In granting Mainstream's request, the agency
did not waive or relax any contract requirement, or provide
Mainstream an opportunity it would not also have provided to HDT
had it made the same request, which it was free to do.
Correspondingly, the agency was not under any legal obligation
to spontaneously offer to reschedule HDT's testing, simply
because Mainstream had rescheduled.
Finally, HDT asserts that the agency abused its discretion in
not initiating discussions in connection with its downselection
decision. Specifically, the record shows that, after determining
that the HDT proposal failed to meet all of the official testing
requirements and therefore was unacceptable, the agency
considered proposed solutions to the deficiencies identified
during the testing that were outlined in HDT's downselection
proposal, but concluded that they were too vague. According to
HDT, at that point, the agency was legally obligated to engage
in discussions in order to afford HDT an opportunity to provide
additional information that would demonstrate the soundness of
its proposed solutions.
This argument is without merit. The contracts specifically
advised, consistent with the requirements of the Competition in
Contracting Act, 10 U.S.C. sect. 2305(a)(2(A)(ii)(I) (2006), and
Federal Acquisition Regulation sect. 15.209(a), that the agency
intended to make its downselection decision without engaging in
discussions. AR, exhs. D1, D2, at 130. Given the terms of the
contracts, and in light of the fact that HDT has neither alleged
nor demonstrated circumstances that would lead us to consider a
possible abuse on the part of the agency in exercising its
discretion not to open discussions, this argument provides no
basis for questioning the award. Kiewit Louisiana Co., B-403736,
Oct. 14, 2010, 2010 CPD para. 243 at 3-4. (HDT
Tactical Systems, Inc., B-403875,December 14, 2010) (pdf)
The solicitation, a section 8(a) set-aside, contemplated the
award of a time-and-materials/labor-hour contract for a base
year, with four 1-year options. RFP at L-1, F-1. The successful
offeror was to be determined based on a "best value" evaluation
of initial proposals. RFP at M-1. Because some members of the
technical evaluation panel (TEP) were former employees of the
contractors and subcontractors competing for award, the agency
structured the procurement to insure anonymity of offerors, in
order to achieve an unbiased evaluation. Agency Report (AR) at
2. Specifically, offerors were required to submit one original
and three redacted copies of their technical proposals. RFP at
L-3. The solicitation, at section L.6, stated that the redacted
copies "shall not contain the name of the offeror's company,
logos, markings, or photos associated with the company or the
names of personnel." RFP at L-3. This requirement was
essentially repeated at section L.6.c. Id. at L-4. Additionally,
section L.6.d(i) stated in bold type that
Redacted proposal copies must be completely
redacted of all identifying information. Failure to submit
properly redacted copies may result in the offeror being
excluded from further consideration.
(sections deleted)
The TEP chair explains that, because SNAP
stated that its team included the incumbent contractor, which,
he was aware, had "graduated" from the section 8(a) program and
therefore could not be the prime contractor, he deduced that the
incumbent was one of SNAP's proposed subcontractors. AR, Tab 38,
Declaration of TEP Chair, at 1. The TEP chair further states
that, based on this knowledge, he also could deduce the identity
of the proposed personnel. Id. Based on its conclusion that SNAP
had violated the identifying information redaction requirement,
the agency rejected SNAP's proposal as unacceptable. AR, Tab 36,
Memorandum of Law, at 8; AR, Tab 37, CO Statement, at 2. In
notifying SNAP of its determination, the agency noted that SNAP
had included "identifying information" in its technical proposal
in violation of section L.6.d(i), and had violated "the spirit,
if not the letter" of RFP sections L.6 and L.6.c. Id.
SNAP asserts that it was improper for the agency to reject its
proposal based on the identifying information redaction
requirement, arguing that the agency's interpretation of the
requirement as established by the RFP is incorrect. Protest at
5. Specifically, SNAP maintains that the term "identifying
information" in section L.6.d(i) is specifically defined in
sections L.6 and L.6.c as the name of the offeror's company,
logos, marking or photos that are associated with the offeror's
company, or the names of proposed key personnel. Protester
Comments at 3. SNAP contends that, if DOL intended a more
expansive definition, the RFP should have so indicated, by, for
example, adding "and all other identifying information" to the
end of those clauses. Id. Similarly, the protester argues that
DOL's statement that "all references to key personnel's names
must be redacted" required only that names be redacted, not all
identifying information, including incumbency-related
information. Protester Comments at 6-7.
Where a protester and agency disagree over the meaning of
solicitation language, we will resolve the matter by reading the
solicitation as a whole and in a manner that gives effect to all
of its provisions; to be reasonable, and therefore valid, an
interpretation must be consistent with the solicitation when
read as a whole and in a reasonable manner. Alluviam LLC,
B-297280, Dec. 15, 2005, 2005 CPD para. 223 at 2; Fox Dev.
Corp., B-287118.2, Aug. 3, 2001, 2001 CPD para. 140 at 2.
We find that only the agency's interpretation of the RFP is
reasonable. The solicitation contained the explicit, mandatory
requirement at section L.6.d(i) that "[r]edacted proposal copies
. . . be completely redacted of all identifying information."
While sections L.6 and L.6.c identified specific types of
information to be redacted, nothing in the RFP indicated that
the identifying information listed in these sections was
intended to be exclusive, so as to relax the unequivocal general
prohibition against identifying information set forth in section
L.6.d(i). Absent such an express exception to the unequivocal
requirement that all identifying information be redacted, there
was no reasonable basis for SNAP to ignore section L.6.d(i) and
interpret the requirement more loosely. Further, we note that
SNAP's interpretation would render the prohibition meaningless,
since, as with SNAP's proposal, offerors would be permitted to
include information that could enable the evaluators to
associate a proposal--directly or by deduction--with a
particular firm or its subcontractors; this is the result the
identifying information prohibition was intended to avoid. Since
the agency's interpretation of the requirement is the only
reasonable reading, and that the agency properly rejected SNAP's
proposal for failing to comply with the RFP requirement. (SNAP,
Inc., B-402746, July 16, 2010) (pdf) See (LS3
Incorporated, B-401948.11, July 21, 2010) (pdf)
Douglass/Kenny contends that the evaluation
of its proposal was unreasonable. In reviewing an agency's
technical evaluation, we consider whether it was reasonable and
in accord with the evaluation criteria listed in the
solicitation. An offeror has the obligation to affirmatively
demonstrate that its proposal will meet the government's needs,
and has a duty to establish that what it is proposing will meet
the solicitation requirements where required to do so. See TRS
Research, B-274845, Jan. 7, 1997, 97‑1 CPD para. 6 at 3;
Discount Machinery & Equip., Inc., B-253094, Aug. 2, 1993, 93‑2
CPD para. 68 at 4. Where, as here, a solicitation requires
offerors to furnish information necessary to establish
compliance with the specifications, an agency may reasonably
find a proposal that fails to include such information
technically unacceptable. Discount Machinery & Equip., Inc.,
supra.
Douglass/Kenny does not dispute that its concept drawings did
not meet the express RFP dimension requirements for the carports
and otherwise did not provide the detail required by the agency
in various areas, such as landscaping, mounting systems, and
storm water drainage. Instead, the protester argues that the
concept drawings were simply a sample depiction, which were not
intended for use in construction or to take exception to the
requirements. In this regard, Douglass/ Kenny asserts that
because its drawing specifically referenced another project, it
should have been obvious that the drawing was not intended for
this project. Douglass/ Kenny also states that it could not have
provided any more meaningful detail regarding landscaping and
storm water drainage because the site was still undergoing
modifications.
While it may be that Douglass/Kenny did not intend for its
concept drawing to illustrate the dimensions of the carports it
would build, the fact remains that the drawings did not meet the
material requirements of the solicitation, which required the
concept drawing to meet the carport design guidelines, including
the specific dimensions. Since the drawing showed dimensions
that did not meet the design guidelines, the agency here
reasonably found that the proposal was unacceptable in this
respect, and could not be selected for award without
discussions. In addition, based on our review of
Douglass/Kenny's proposal, the agency could reasonably conclude
that it did not include required details about other aspects of
the design, such as landscaping.
Douglass/Kenny nevertheless argues that the agency unreasonably
disregarded the commitment in its offer to comply with the
material requirements of the solicitation, as evidenced by its
submission of standard form (SF) 1442. Douglass/Kenny argues
that by simply signing the SF-1442 a party agrees to and is
obligated to perform, all material requirements of the RFP.
However, simply submitting an SF-1442 is insufficient to comply
with an RFP requirement to provide the detailed technical
information necessary for evaluation purposes. See Sabre
Commc'ns Corp., B‑233439, Mar. 2, 1989, 89‑1 CPD para. 224 at 5.
Where a proposal contains a blanket offer of compliance to meet
specifications, such as by signing an SF-1442, and also contains
conflicting provisions which call that offer of compliance into
question, the offer is ambiguous and may properly be rejected as
technically unacceptable. TRS Research, supra. Under such
circumstances, there is no requirement that the agency conduct
discussions so as to allow the offeror to correct the
deficiencies in its proposal, where, as here, the solicitation
expressly advised that it intended to make award without
discussions. See DynCorp Int'l LLC, B-294232, B-294232.2, Sept.
13, 2004, 2004 CPD para. 187 at 8. (Douglass
Colony/Kenny Solar, JV, B-402649, June 17, 2010) (pdf)
The RFP also stated that "The Contractor
shall comply with all applicable Federal, State and local laws,
executive orders, rules and regulations applicable to its
performance under this contract."
Id. at 11.The RFP also stated that "The Contractor shall
comply with all applicable Federal, State and local laws,
executive orders, rules and regulations applicable to its
performance under this contract." Id. at 11.
(sections deleted)
Compliance with FCC Requirements
Freedom asserts that the award to Enhanced was improper because
its products do not comply with FCC technical requirements, and
thus do not comply with "all applicable Federal, State and local
laws," as required under the solicitation. Protest at 7.
Specifically, Freedom argues that Enhanced's 19-inch monitor
does not comply with the FCC's emissions requirements and that
its products violate the FCC's labeling requirements.
This argument is without merit. The RFP did not expressly
require that offered products comply with FCC requirements as a
precondition to award. Rather, the RFP clause requiring
compliance with all federal, state, and local laws is included
in the solicitation under "Section C - Contract Clauses" and, by
its terms, applies to "the contractor." General solicitation
provisions mandating that "the contractor" comply with federal,
state, and local laws do not require that an offeror demonstrate
compliance prior to award. Rather, compliance is a performance
requirement that may be satisfied during contract performance
and does not affect the award decision (except, possibly, as a
general responsibility matter). Further, whether Enhanced
ultimately complies with the provision is a matter of contract
administration that we will not review. 4 C.F.R sect. 21.5(a)
(2009); Solar Plexus, LLC, B-402061, Dec. 14, 2009, 2009 CPD
para. 256 at 2-3. (Freedom
Scientific, Inc., B-401173.3, May 4, 2010) (pdf)
Sletten challenges the agency's evaluation of its technical
proposal, arguing that the identified concerns were not
deficiencies and could, in any event, have been corrected
through clarifications or discussions. Sletten also complains
that GSA did not consider the firm's lower proposed priced in
selecting Mortenson's proposal for award.
Where a protester challenges an agency's evaluation of a
proposal's technical acceptability, our review is limited to
considering whether the evaluation is reasonable and consistent
with the terms of the RFP and applicable procurement statutes
and regulations. National Shower Express, Inc.; Rickaby Fire
Support, B-293970, B-293970.2, July 15, 2004, 2004 CPD para. 140
at 4-5. Clearly stated RFP technical requirements are considered
material to the needs of the government, and a proposal that
fails to conform to such material terms is technically
unacceptable and may not form the basis for award. Id.; Outdoor
Venture Corp., B-288894.2, Dec. 19, 2001, 2001 CPD para. 13 at
2-3.
Here, the record shows that Sletten's proposal did not comply
with a number of solicitation requirements, which the SSEB found
to be proposal deficiencies. For example, the SSEB found that
Sletten had failed to provide required drawings, that Sletten's
floor plans were not the plans utilized for the BOMA
calculations, that Sletten's BOMA calculations did not represent
the solicitation's requirements, and that Sletten's design did
not satisfy the minimum space requirements (such as for the
district judges' chambers). See AR, Tab 12, SSEB Evaluation
Report, at 6-7.
Sletten does not contend that its proposal satisfies these
requirements, but instead argues that these deficiencies do not
render its proposal technically unacceptable. We disagree.
First, GSA found that Sletten's failure to provide required
information in its proposal, such as scalable drawings and BOMA
calculations, prevented the SSEB from being able to evaluate
properly Sletten's proposal. Sletten has not shown that the
agency's judgment in this regard was unreasonable. Moreover, the
solicitation's space and allocation requirements can only be
viewed as material requirements, which Sletten failed to
satisfy. In fact, Sletten's actions throughout the procurement
demonstrate its recognition of the materiality of the
solicitation requirements, given its repeated attempts to revise
its proposed design after the closing date for receipt of
proposals.
We also disagree with Sletten that, to the extent the agency
wanted to avoid holding discussions, these deficiencies could
easily be corrected through clarifications. "Clarifications" are
limited exchanges between the government and offerors that may
occur when award without discussions is contemplated. Such
communications with offerors, however, may not be used to cure
proposal deficiencies or material omissions, materially alter
the technical or cost elements of the proposal, or otherwise
revise the proposal. FAR sect. 15.306(b)(2). The evaluated
deficiencies in Sletten's proposal could only be corrected
through discussions, as this would require a material revision
of its proposal.
With respect to conducting discussions with Sletten, we have
found that a contracting agency is generally not required to
conduct discussions where, as here, the RFP specifically
instructs offerors of the agency's intent to award a contract on
the basis of initial proposals. See FAR sect. 15.306(a)(3);
Colomek Sys. Eng'g., B‑291931.2, July 9, 2003, 2003 CPD para.
123 at 7. In this regard, the CO's discretion in deciding not to
hold discussions is quite broad. Our Office will review the
exercise of such discretion only to ensure that it was
reasonably based on the particular circumstances of the
procurement. Colomek Sys. Eng'g., supra. The fact that the
protester in its initial proposal failed to comply with the RFP
requirements does not give rise to an obligation on the agency's
part to hold discussions, where discussions are not otherwise
necessary. (Sletten Companies/Sletten
Construction Company, B-402422, April 21, 2010) (pdf)
BOSS Construction, Inc., of Bellingham, Washington, protests the
award of a contract to Mowat Construction Company, Inc., of
Woodinville, Washington, by the Department of the Interior,
Bureau of Reclamation (BoR), under solicitation No. 09SP101729
for construction services on the Weber Siphon Project, as part
of the Columbia Basin Project in Grant County, Washington. BOSS
argues that its proposed schedule was misevaluated as
unacceptable, and that Mowat also proposed an unacceptable
schedule.
(sections deleted)
BOSS argues that
its proposal was improperly downgraded under the CPM schedule
factor and attempts to justify its decision to propose a
schedule that exceeded the completion deadline:
BOSS
intentionally placed a one month lag in the start of
hydroseeding and site restoration work after completion of the
physical structures [by the deadline] . . . because, given the
locale and seasonal weather conditions at the project site,
seeding should not practically and effectively be commenced as
of [the required completion date].
Protest at 5.
Accordingly, BOSS argues that it was unreasonable to downgrade
its proposal based on what it argues was the only proper way to
complete the work.
BoR argues that the specification clearly required completion
within 18 months, and specified that schedules would be
evaluated on this basis, among others. By failing to meet the
18-month completion, BoR argues that the rating of BOSS as
unacceptable under the CPM factor was proper.
In reviewing a protest of an agency's evaluation of proposals,
our review is confined to a determination of whether the agency
acted reasonably and consistent with the terms of the
solicitation and applicable statutes and regulations.
Cooperativa Maratori Riuniti-Anese, B-294747, Oct. 15, 2004,
2004, CPD para. 210 at 2. A firm delivery schedule or completion
date set forth in a solicitation is a material requirement,
precluding acceptance of any proposal not offering to meet that
date. In a negotiated procurement, any proposal that fails to
conform to material terms and conditions of the solicitation is
unacceptable and may not form the basis for an award. Id. at 3.
BOSS emphasizes certain provisions of the solicitation that
indicated that the schedule in the offeror's proposal would not
be final, and did not need to be "contract quality," and
therefore the fact that its schedule exceeded the time permitted
should not have been treated as a significant failure. We
disagree. There is no dispute on this record that BOSS's
proposed schedule exceeded the limit specified in the
solicitation, and as noted above, such requirements are
material. Accordingly, we cannot conclude that the agency acted
improperly in rating BOSS unacceptable under the CPM schedule
factor.
To the extent that BOSS argues that Mowat's proposed schedule
did not show that the construction of the new siphon would be
completed to allow the start of the irrigation season in
mid-March, as specified in the solicitation, Supp. Protest at 1,
the record does not support its claim.
BoR responds that a review of the detailed tasks within Mowat's
schedule show that the firm would be able to complete testing of
joints in the siphon construction on March 14 or within a day or
two after, at which time water flow for irrigation could begin.
Thus BoR argues it reasonably concluded that Mowat's schedule
meets the requirement of making the siphon usable by the start
of the irrigation season in "mid‑March."
The solicitation does not define the term "mid-March," or
provide any other basis on which offerors should have understood
that term to imply an exact date. Accordingly, since BoR's
construction of "mid-March" to include March 14 (or a few days
after that) is a reasonable one, we have no basis to question
it. Even though BOSS argues that BoR should have interpreted
Mowat's schedule to provide for completion of joint testing as
late as March 25, BoR has pointed out that a detailed analysis
of the underlying tasks (or "fragmentary networks") within
Mowat's schedule undermine BOSS's interpretation. In our view,
BoR has shown that its interpretation of Mowat's proposed
schedule is supported by the record and is a reasonable one.
(BOSS Construction, Inc.,
B-402143.2; B-402143.3, February 19, 2010) (pdf)
With regard to the agency's finding that its quotation lacked
necessary detail, CDI asserts that the agency "never specified
what specific[ ] processes [it] was interested in" regarding
integration; thus, since its quotation addressed integration of
the existing flat iron, speed controls, and interfacing of
equipment and controls, with no exception to the requirements,
it should not have been rejected. Protest at 1-2.
CDI's assertions are without merit. The RFQ provided sufficient
guidance for preparing quotations, including requirements for
both a detailed installation plan covering the proposed
equipment's ability to interface and integrate with existing
equipment "within the space available," and a modification plan
describing how vendors would make each proposed module fully
operational with the existing flat iron, including how new or
existing equipment would be modified for electrical wiring,
circuitry, or reprogramming. RFQ at 5, 7.
While CDI's quotation included some general statements, it
failed to provide the detailed information called for. For
example, the quotation stated that CDI's equipment would "easily
integrate" with the existing flat iron; that speed controls of
"either the feeder or folder" offered "[would] require
integration"; that CDI would install a stop circuit so that the
feeder would stop when the flat iron stopped; that CDI's
equipment could be "interfaced by interlocking and providing an
interface between all components"; and that CDI would provide
its "high intelligent controls" for "smooth operation."
Quotation Narrative at 1-2. The quotation further stated that
"some control circuits [would] be modified allowing the feeder,
ironer and folder and stackers to communicate," and that CDI
considered these to be "minor modifications." Id. at 2. However,
the quotation did not explain why these modifications would be
minor, and did not address the specific power requirements.
Further, apart from stating that various items would be
accomplished by "retro‑fitting the systems in order to make one
complete system," CDI's quotation lacked any detailed
installation and modification plans, and did not otherwise
describe "how" it would integrate and modify the proposed and
existing equipment to ensure successful inter-operation. Given
the absence of the required detailed plans and explanations, the
TET reasonably found that it could not evaluate whether CDI's
equipment would meet the stated requirements. Ervin & Assocs.,
Inc., B‑280993, Dec. 17, 1998, 98-2 CPD para. 151 at 6 (blanket
offers of compliance with stated requirements are not an
adequate substitute for detailed information necessary to
establish how vendor proposes to meet agency requirements).
With regard to whether its equipment would fit within the
available space, CDI cites its quotation's statements that "[a]ll
systems offered [would] easily fit in the space made available
and [would] provide the necessary clearances as specified," and
also asserts that its drawing "clearly indicated" that CDI's
equipment would fit in the current space. Quotation Narrative at
1; Protest at 2. However, the agency considered these broad
statements inadequate and found CDI's drawing and brochures to
be conflicting and confusing. In this regard, the TET found that
the quotation did not specify complete dimensions for CDI's
proposed folder/stacker, and noted that CDI's product brochures
stated that "[s]pecifications [were] subject to change without
notice." Quotation, attachs. 5-7. By its own estimate, based on
CDI's brochure information, the TET determined that the quoted
equipment, once integrated, would exceed the available length by
18 inches. SSER, Tab 10 at 3. Further, the TET inferred that,
because CDI's drawing showed its stacker at a "cocked" angle,
CDI was attempting to force the equipment to meet the RFQ's
16‑inch column clearance requirement, and noted that the
quotation did not address whether the machine would even operate
in that position. Quotation, attach. 7; SSER, Tab 10, at 2. The
drawing also depicted a centerline for the existing flat iron,
which suggested to the TET that CDI intended to reposition it
even though the RFQ prohibited relocation of the machine. RFQ at
4. (Consistent with the TET's concern, CDI's cover letter
suggested that the agency amend the RFQ, in part, to permit
relocation of the flat iron. Quotation Letter at 1.) Based on
the conflict between the quotation's claim that CDI's equipment
would fit within the available space and the other indications
that it would not, we find the TET reasonably concluded that
CDI's quotation did not adequately establish that its equipment
would meet the agency's requirements. We conclude that the
agency reasonably rejected the quotation as unacceptable.
(Chicago Dryer Inc., B-402340,
February 16, 2010) (pdf)
A source selection evaluation board (SSEB) evaluated the
proposals. Gohman's price was low at $11,125,266; Holte's was
second low at $11,157,587. AR, Tab 15, Source Selection
Decision, at 3. However, the SSEB determined that Gohman had
qualified its offer by stating that its price did not include
SAC/WAC fees1. AR, Tab 14, SSEB Report, at 10. Due to
omission of this required pricing element, the agency determined
that Gohman had not agreed to be responsible for SAC/WAC fees,
and that its proposal therefore was ineligible for award. AR at
7; AR, Tab 14, SSEB Report, at 10. By letter dated July 29, the
Army notified Gohman that its proposal was found not to be the
best value because its price was incomplete based on its
exclusion of SAC/WAC fees, and that award was made to Holte. AR,
Tab 9, Notice of Award, at 1.
Following a debriefing, Gohman filed an agency-level protest,
arguing that the SAC/WAC fees were not required. The agency
dismissed the protest, citing the language of RFP section 00800,
advising offerors that they were responsible for all charges
related to temporary utilities. AR, Tab 10, Contracting Officer
Response to Agency Protest, at 2. On September 8, Gohman filed
this protest with our Office.
Gohman asserts that, contrary to the Army's determination, it
"bid everything that was required to be bid under the terms" of
the RFP. Protest at 3.
Where a protest challenges an agency's technical evaluation, we
will review the evaluation record to determine whether the
agency's judgments were reasonable and consistent with the
stated evaluation criteria and applicable procurement statutes
and regulations. Government Acquisitions, Inc., B-401048 et al.,
May 4, 2009, 2009 CPD para. 137 at 8. It is well-settled that a
proposal that fails to conform to a solicitation's requirements
cannot form the basis for an award. Id.
The evaluation and rejection of Gohman's proposal were
unobjectionable. The solicitation clearly provided that the
contractor would be responsible for all costs related to
providing temporary utilities, that is, utilities necessary
during the construction of the center. There is no dispute that
sewer and water service constitute utilities--and, as noted
above, the list of utilities in the Design Submittal, at
paragraph 1.3, included sewer and water. It likewise is
undisputed that Gohman's proposal specifically provided that its
price excluded SAC/WAC fees. Under these circumstances, the
agency reasonably determined that Gohman had not agreed to be
responsible for the costs of SAC/WAC during construction,
contrary to the RFP's express requirements, and that its
proposal therefore was unacceptable.
In challenging the agency's determination, Gohman cites
paragraphs 1.29 and 1.31 of the Design Submittal, and asserts
that the only costs associated with utilities are those related
to obtaining permits, installing temporary utilities (and
returning them to their original configuration), and gaining
access to the utilities. Protest at 5-6. Gohman claims that
"Nowhere, however, in the Solicitation does it mention utility
fees generally or SAC/WAC fees particularly," which, it asserts,
"makes sense" because these fees "are not determinable until a
plan is submitted to the Metropolitan Council by the Army
Architect," id. at 6, and that, indeed, there may be no SAC/WAC
fees assessed against the Army. Protester Comments at 2.
Gohman's argument that it properly excluded the SAC/WAC fees
because the RFP did not specifically identify those fees as
among the utility costs to be borne by the contractor is without
merit because it ignores the plain language of RFP section
00100, paragraph 10. As noted above, that provision stated that
the contractor "will pay all charges (hook up fees, metering,
monthly usage, etc.) resulting from temporary utilities." This
language was sufficiently inclusive that, in the absence of an
exception for SAC/WAC fees, it should have been clear that these
fees were among the utility charges that were to be the
responsibility of the contractor. The language cited by the
protester as well as the language in RFP section 00100,
paragraph 10 make it clear that the contractor is responsible
for all utility charges. The fact that utility fees ultimately
may not be assessed is irrelevant, particularly since Gohman
concedes that it does not know conclusively that such fees will
not be assessed under any circumstances. Protest at 6; Protester
Comments at 2. (W. Gohman
Construction Co., B-401877, December 2, 2009) (pdf)
-----------------------------
1 Sewer and water
accessibility charges (SAC/WAC).
DeVal's protest is based on a flawed premise, namely, that the
RFQ did not require quotations to include any specific
information apart from welding experience. Here, the RFQ advised
vendors that their quotations would be evaluated under certain
criteria, including experience with welding standards and a
technical assessment. RFQ at 34. To this end, the RFQ, as
amended, specifically advised vendors that "[p]art of the review
for your quote to be considered technically responsive, is that
you must include your past experience in meeting the welding
standards in the SOW and Drawings" and that lack of past
experience would not be counted against a quotation. RFQ, amend.
0001 at 2 (emphasis added). However, the RFQ's instructions also
included the requirement that, "[a]s a minimum," vendors show
"[a] technical description of the items being offered in
sufficient detail to evaluate compliance with the requirements
in the solicitation." RFQ at 33, incorporating by reference FAR
sect. 52.212-1. The RFQ's technical requirements were set forth
in the SOW and, in addition to welding standards, included
requirements that the skids be fabricated based on specified
drawings, specifications, and standards listed in the SOW,
nondestructive test inspection load testing, applicable test
reports, marking and packaging, and delivery. RFQ at 7. The SOW
also provided that the contractor's facility "shall be . . . in
compliance with ISO 9001: 2008 Quality Management Systems." RFQ
at 6. We think the RFQ provision requiring that vendors provide
sufficient information to permit the agency to "evaluate
compliance with the requirements," together with the provision
for a technical assessment as part of the technical
acceptability determination, were sufficient to put DeVal on
notice that all RFQ requirements had to be addressed in its
quotation, and that the agency would evaluate the information
provided in determining acceptability.
DeVal's quotation did not include information addressing all of
the RFQ requirements. Rather, it only included a copy of the RFQ,
with pricing and representations, a copy of DeVal's limited
warranty, and welding process information. This left the agency
unable to assess whether DeVal intended to meet all
requirements. For example, the RFQ's SOW required fabrication of
complete skids, with all constituent fabricated and procured
parts and assemblies produced in accordance with the specified
government drawings, Department of Defense (DoD) standards, and
industry specifications and standards listed in the SOW. RFQ at
7. In this regard, the SOW identified the primary drawing (No.
3967AS100, major assembly), along with 11 revised drawings and
four DoD standards. RFQ at 6. Without information from DeVal
regarding its plan to fabricate the skids, the agency could not
perform the technical assessment called for under the RFQ to
determine that DeVal would provide items meeting these
requirements. See West Coast Research Corp., B‑281359,
B-281359.2, Feb. 1, 1999, 99-1 CPD para. 27 at 3 (where vendor
fails to address specifically identified requirements, agency
need not presume vendor's acceptance of those requirements).
Likewise, while DeVal now asserts that it is compliant with ISO
9001 requirements, the failure of its quotation to address this
requirement in any way made it impossible for the agency to
determine that DeVal met it. We conclude that the agency
reasonably evaluated DeVal's quotation as technically
unacceptable. See Carlson Wagonlit Travel, B‑287016, Mar. 6,
2001, 2001 CPD para. 49 at 3 (offeror is responsible for
submitting an adequately written proposal); West Coast Research
Corp., supra.
The protest is denied. (DeVal
Corporation, B-402182, December 17, 2009) (pdf)
The SFO at issue here was published in November 2008, and
contemplated the award of a long-term operating lease to support
the activities of NOAA’s MOC-P. Among other things, the
solicitation sought offers to provide 31,000 square feet of
office, warehouse and related space, 1,960 linear feet of pier
space, and 20,000 square feet of equipment laydown space. Agency
Report (AR), Tab 7, SFO, at 5. The solicitation provided that
the lease award would be based on the offer determined to be
most advantageous to the government based on application of the
following evaluation factors: location of site; site
configuration and management; quality of building and pier;
availability; past performance and project financing; quality of
life; and price. AR, Tab 7, SFO amend. 3, at 2. The solicitation
also provided that: “An award of contract will not be made for a
property located within a base flood plain or wetland unless the
Government has determined that there is no practicable
alternative.” SFO at 7.
(sections deleted)
Bellingham
protests that the agency failed to comply with the SFO provision
that stated: “An award of contract will not be made for a
property located within a base flood plain or wetland unless the
Government has determined that there is no practicable
alternative.” See SFO at 7. More specifically, Bellingham
protests that Newport’s proposed pier was clearly within a
designated floodplain area; that the agency had no reasonable
basis to conclude otherwise; and that the agency was, therefore,
required to make a determination as to whether there was a
practicable alternative to Newport’s offer.
The agency responds that it “properly concluded that Newport’s
offered property is not located within the base floodplain,” and
that, having so concluded, that the agency “was not required to
and properly did not conduct a practicable alternative
analysis.” AR, Tab 2, at 15. In maintaining that Newport did not
propose property within the designated floodplain area, the
agency refers to the fact that the “finished level” of Newport’s
proposed pier is projected to be higher than 9 feet NGVD (the
applicable BFE) asserting: “[I]f the finished level of the pier
were built below 9 NGVD it would be located within the base
floodplain and likely impacted by flooding; if it were built
above 9 NGVD it would not be in the base floodplain.” Agency
Response to Protester’s Comments, Oct. 16, 2009, at 2. The
agency also references Newport’s conclusory representation,
provided in response to the agency’s discussion question, quoted
above, that “all proposed facilities and structures will be
designed above the BFE.” On this basis, the agency maintains
that it reasonably concluded that Newport’s proposed pier was
outside the designated floodplain area and, accordingly,
maintains the agency had no obligation to--and did not--consider
whether there was any practicable alternative.
Our Office has previously considered whether, in leasing real
property, an agency has properly considered the particular
floodplain requirements that are at issue here. See, e.g.,
Ronald Brown, B-292646, Sept. 20, 2003, 2003 CPD para. 170; Vito
J. Gautieri, B‑261707, Sept. 12, 1995, 95-2 CPD para. 131;
Alnasco, Inc., B-249863, Dec. 22, 1992, 92-2 CPD para.430; Wise
Inv., Inc., B-247497, B-247497.2, 92-1 CPD para. 480; Oak Street
Distribution Ctr., Inc., B-243197, July 2, 1991, 91-2 CPD para.
14; Western Div. Inv.; Columbia Inv. Group, B-213882,
B-213882.2, Sept. 5, 1984, 84‑2 CPD para. 258. In this regard,
we have noted that the floodplain requirements flow from
Executive Order (EO) No. 11988, 42 Fed. Reg. 26,951 (1977),
which precludes a federal agency from providing direct or
indirect support of flood plain development when there is a
practicable alternative. We have further noted that the purpose
of EO No. 11988 is to minimize the impact of floods on human
health and safety, as well as to minimize the impact on the
environment. See Vito J. Gautieri, supra., at 2-3. In
considering compliance with these floodplain requirements, we
have held that an agency must, at a minimum, consider whether a
proposed structure will be located within a designated
floodplain area. See, e.g., Ronald W. Brown, supra., at 1-2
(agency reasonably concluded that floodplain provisions did not
bar award of lease where proposed building was not located
within the floodplain area, even though the periphery of the
site was within the floodplain); see also Oak Street
Distribution Ctr., supra., at 3-4 (agency properly awarded lease
where proposed building was not within floodplain); cf. Wise
Inv., Inc., supra., at 2-4 (award of lease not prohibited where
ground level of site had been elevated by filling).
Here, based on the record discussed above, there can be no
reasonable doubt that Newport’s offer proposed to build its pier
structure within the designated floodplain area. Further, as
noted above, Newport’s construction of the pier was a
significant aspect of its offer in that the solicitation
required offerors to provide a minimum of 1,950 linear feet of
pier space. AR, Tab 7, at 7. Finally, it is clear that the pier
structure may have an environmental impact on the floodplain
area within which it is to be located.
As discussed above, Newport’s proposed pier construction within
the designated floodplain area was expressly presented to the
agency by the very engineering firm the agency retained to,
among other things, inform the agency on floodplain matters.
Consistent with that notification, in conducting discussions
with Newport, the agency requested that Newport address the
floodplain issue in the context of the location of its proposed
pier; yet, Newport did not. Finally, the fact that the “finished
level” of the pier may be above the BFE has no bearing on the
clearly apparent fact that the pier structure itself is to be
constructed within the designated floodplain area, which will,
among other things, require Newport to drive hundreds of
concrete piles “approximately 15 feet below the mudline.” See
AR, Tab 20 at 4-18. In this regard, neither Newport’s proposal
nor the agency’s contemporaneous evaluation documents, address
the specific environmental issues identified in the EA report,
including the potential for debris to be trapped against the
concrete pier piles or the pier’s alteration of the way
floodwaters circulate and flow within the bay.
On this record, there was no reasonable basis for the agency to
conclude that Newport’s proposal did not fall within the scope
of either the solicitation’s express floodplain limitations or
EO No. 11988’s limitations regarding potential environmental
impacts. Accordingly, the agency was required to consider the
environmental impact of Newport’s proposed pier structure and to
determine whether there was a practicable alternative to
Newport’s offer; the record is clear it did not. (Port
of Bellingham, B-401837, December 2, 2009) (pdf)
The RFP, which
contemplated the award of a cost-reimbursement contract for a
3-year base period with four 1-year option periods, provided
that cost would be evaluated by adding the total proposed cost
for the base period and all option periods. RFP at 72. The RFP
also stated that the agency intended to make award on the basis
of initial proposals, without discussions. Id. at 65. Manthos
submitted a cost proposal for the base period, but did not
include any pricing for the option periods. Protest at 5; Agency
Report at 4. The agency did not reject the proposal but,
instead, attempted to calculate option prices from the
information included in the proposal. The agency ultimately
determined that TEC's proposal, not Manthos's, represented the
"best value," and thus made award to TEC. Manthos challenges the
evaluation and selection decision on several grounds.
The protest is without merit. While the agency did not reject
Manthos's proposal for failure to include option prices, this
omission rendered the proposal unacceptable. In this regard,
since offerors were required to provide option year prices and
those prices were to be evaluated for purposes of determining
the total evaluated price, option prices were a material
solicitation requirement. Robotic Sys. Tech., B‑271760, May 14,
1996, 96-1 para. 229 at 4. In a negotiated procurement, a
proposal that fails to conform to the material terms and
conditions of the solicitation is considered unacceptable and
may not form the basis for award. Cajar Def. Support Co.,
B‑239297, July 24, 1990, 90-2 CPD para. 76. Since Manthos did
not provide the required option year prices, its proposal did
not conform to the material terms of the RFP, and therefore
could not be accepted for award. See Joint Venture Penauillie
Italia S.p.A; Cofathec S.p.A; SEB.CO S.a.s; CO.PEL.S.a.s.,
B-298865, B-298865.2, Jan. 3, 2007, 2007 CPD para. 7 at 6.
Manthos argues that the agency should have permitted Manthos to
provide its missing option year prices through clarifications.
We disagree. In this regard, clarifications are "limited
exchanges" agencies may use to allow offerors to clarify certain
aspects of their proposals or resolve minor or clerical
mistakes. Federal Acquisition Regulation (FAR) sect.
15.306(a)(2). As is relevant here, an agency may allow an
offeror to correct a mistake or clerical error in a cost or
price proposal through clarifications only where both the
existence of the mistake and the amount intended by the offeror
are apparent from the face of the proposal. Joint Venture
Penauillie, supra, at 8. Here, while it was clear from Manthos's
proposal that the option year pricing had been omitted, the
proposal specifically stated that "Option Years 1 through 4 will
also be priced upon request." Cost Proposal at 8. Based on this
statement, it is clear that the omission was not a
mistake--despite the clear requirement in the RFP for option
year prices, Manthos purposely omitted them from its proposal.
Under these circumstances, the option prices could not be added
through clarifications. (Manthos
Engineering, LLC, B-401751, October 16, 2009) (pdf)
OLCR Inc. of
Chester, Pennsylvania, and Revolutionize of Las Vegas, Nevada,
protest the rejection of their proposals under request for
proposals (RFP) No. DJD-09-R-0017, issued by the Drug
Enforcement Administration (DEA), Department of Justice, for
basic cable television service at DEA's Training Academy in
Quantico, Virginia. OLCR and Revolutionize, which provide
satellite television service, argue that the RFP did not require
the contractor be a cable service provider.
(sections deleted)
In sum, we
conclude that the protesters knew, or should have known, that
satellite service would not be permitted under this RFP for
basic cable service. In this regard, we do not agree with the
protesters that the inclusion of NAICS code 517110 indicated
that satellite service providers would be permitted to compete
under this RFP. Although the NAICS code does include both cable
and satellite television services, it also includes other types
of services such as telephone, broadband Internet, and Voice
over Internet Protocol services that are not being solicited
here. As the agency explains, the RFP did not solicit proposals
for a wired telecommunications carrier generally, which could
include any number of the services listed under the code, but
specifically solicits cable video programming. Apart from the
reference to satellite service in the NAICS code, the RFP, read
as a whole, reasonably informed vendors that the agency was
seeking basic cable service, not service from satellite
providers. (OLCR Inc.;
Revolutionize, B-401575; B-401575.2, September 24, 2009)
(pdf)
Controlled
Systems argues that MCPA's quotation does not comply with a
material term of the solicitation, and should have been found to
be technically unacceptable. Specifically, the protester
contends that by including the term--"FOB Point: Shipping Point"
in its quotation--MCPA took exception to the solicitation
requirement for "FOB Destination."
A quote that fails to conform to the material terms and
conditions of the solicitation should be considered unacceptable
and may not form the basis for an award. See, Muddy Creek Oil
and Gas, Inc., B-296836, Aug. 9, 2005, 2005 CPD para. 143 at 2.
Here, we find that MCPA's quote did conform to the RFQ's
material terms and conditions. With respect to the delivery
terms, although MCPA's quotation stated that delivery would be
"FOB Shipping Point," the firm quoted a price for delivery, "FOB
Destination" to Fort Sill, which was part of MCPA's total price.
Given that MCPA quoted complete pricing for the supply, delivery
and installation of the power converters on a turnkey basis, as
contemplated by the RFQ, we think that the Army reasonably
concluded that the inclusion of the "FOB shipping point" term,
which was inserted below the firm's quoted prices and was not
specifically associated with any of the priced CLINs, was a
minor error. The purchase order issued to MCPA by the Army
provided for delivery to Fort Sill at the price quoted by MCPA.
Agency Report, Tab 22, Purchase Order, at 4. (Controlled
Systems, B-401208.2, July 8, 2009) (pdf)
Ashbury maintains
that, while Horus offered in its FPR to provide an alternate
reticle that purported to meet the requirements and objective of
the RFP, in fact, its proposal did not provide the agency with a
reasonable basis for finding it acceptable. More specifically,
Ashbury maintains that the agency improperly failed to test
Horus's replacement reticle, as contemplated under the RFP,
instead accepting Horus's mere promise to provide a compliant
reticle. Ashbury asserts that this promise could not reasonably
form the basis for the agency to find that the replacement
reticle met the objective of the RFP of being similar to the
reticle currently in use in the USMC Scout Sniper Day Scope, or
that it was technically equivalent to the one offered by Ashbury.
Agencies are required to evaluate proposals in a manner that is
consistent with the terms of the solicitation. Contingency Mgmt.
Group, LLC; IAP Worldwide Servs., Inc., B-309752 et al., Oct. 5,
2007, 2008 CPD para. 83 at 10. Our review of the record shows
that the agency improperly failed to obtain a telescope from
Horus that was configured with its alternate reticle and,
consequently, did not evaluate and test the alternate reticle
proposed by Horus in accordance with the requirements of the
RFP.
As quoted above, the solicitation provided that the agency "will
subject production samples to any and all of the examinations
and tests specified in the detailed performance Specification."
RFP at 68. The record shows, however, that, after receiving
Horus's proposal revision, the agency neither required Horus to
identify a specific model nor did anything to examine or test
Horus's proposed alternate reticle. The record contains no
indication that the agency obtained a sample telescope with the
alternate reticle installed, or that it in any way critically
evaluated the change in the firm's proposed reticle, despite the
fact that this was a key attribute of the telescopes. Instead,
the agency accepted Horus's unsubstantiated representation that
its alternate reticle was [deleted] and, in apparent reliance on
that representation, concluded that its alternate reticle was
not only acceptable, but also met the performance specification
objective of being similar to the reticle in the USMC Scout
Sniper Day Scope. In this regard, the agency's second technical
evaluation report simply notes, without elaboration, that the
alternate reticle meets the objective requirement of the
performance specification of being similar to the reticle in the
USMC Scout Sniper Day Scope. Technical Evaluation Report, Nov.
26, 2008, at 3.
The agency's actions were unreasonable in view of the fact that
Horus's originally‑proposed reticle was found technically
unacceptable. In contrast, as noted, the reticle offered by
Ashbury was shown through the agency's testing procedures to
have met both the threshold requirements and the objective of
the performance specification of being similar to the reticle in
the USMC Scout Sniper Day Scope. The agency's acceptance of the
alternate Horus reticle was unreasonable because doing so was
inconsistent with the stringent testing requirements that the
RFP stated would be applied to establish technical
acceptability. Moreover, the agency's actions constituted an
improper waiver of the testing requirements for Horus, but not
Ashbury. As a result of the waiver, although Horus's proposal
was higher priced than Ashbury's, it is not clear whether Horus
submitted a technically acceptable proposal. Contingency Mgmt.
Group, LLC; IAP Worldwide Servs., Inc., supra. We therefore
sustain this aspect of Ashbury's protest. (Ashbury
International Group, Inc., B-401123; B-401123.2, June 1,
2009) (pdf)
The RFP's
statement of work established the following requirement:
The contractor shall have a facility within 15 miles of CMS
for the duration of this contract. The contractor's Project
Management staff shall be located at this facility. The
facility must accommodate contractor staff working on this
contract and provide for meeting space.
RFP sect. C.1.2. NGIT asserts that CGI's proposal did not comply
with this provision because CGI proposed to perform the majority
of its work at a facility more than 15 miles away from CMS
headquarters, in Woodlawn, Maryland. The agency responds that
its evaluation was reasonable because this provision required
only that project management staff--not all staff--perform at
the nearby facility, and CGI met this requirement.
To be reasonable, the interpretation of solicitation language
must be consistent with the solicitation when read as a whole
and in a manner that gives effect to all of its provisions.
BellSouth Telecomm., Inc., B--258321, Jan. 6, 1995, 95--1 CPD
para. 10 at 6. NGIT's assertions here simply are not reasonable.
Reading the quoted provision as a whole, while it is plain that
offerors were required to have a facility within 15 miles of CMS
headquarters, it is just as plain, contrary to NGIT's
interpretation, that the provision does not require all staff to
be located there; rather, only project management staff is
specified. The remainder of the provision only generally calls
for accommodation of staff working on the contract and provision
of meeting space; it does not require that all other contractor
personnel be located at the facility. To read the provision
otherwise would make the requirement specifying the location of
project management personnel redundant and the provision, at
best, patently ambiguous; the protester was obligated to
challenge any such ambiguity prior to submitting its proposal.
Bid Protest Regulations, 4 C.F.R. sect. 21.2(a)(1) (2009); see,
e.g., Poly‑Pacific Techs., Inc., B‑293925.3, May 16, 2005, 2005
CPD para. 100 at 3. We conclude that there was no basis for the
agency to reject or downgrade CGI's proposal for proposing to
locate non-project management staff more than 15 miles from CMS.
Our conclusion is not changed by NGIT's reliance on the RFP's
requirement that the contractor "interact" with CMS personnel
(RFP sect. C.2) and to work "closely" with CMS personnel on
numerous tasks listed in RFP section C.3. These provisions do
not require that the interaction or work occur at a facility
within 15 miles of CMS. Likewise, NGIT's assertion that, under
its incumbent contract for a portion of this requirement,
members of its technical staff were "routinely" called upon to
attend impromptu face-to-face meetings (Response to Motion to
Dismiss at 3) is not a basis for finding that the RFP here
required offerors to propose to locate all staff at the nearby
facility. Each federal procurement stands on its own; prior
practice involving meetings at a nearby facility does not
establish the same requirement here. See Sabreliner Corp.,
B-275163 et al., Dec. 31, 1996, 96-2 CPD para. 244 at 2 n.2. In
fact, the provision calls for the facility to include meeting
space, but does not mandate that all staff work be performed at
the site. (Northrop Grumman
Information Technology, Inc., B-401198; B-401198.2, June 2,
2009) (pdf)
The RFP, which
contemplated award of up to 10 fixed-price,
indefinite-delivery/indefinite-quantity contracts, contained the
Federal Acquisition Regulation (FAR) Rights in Data-Special
Works clause, which states in part that the “Government shall
have unlimited rights in all data delivered under this
contract.” FAR sect. 52.227-17(b)(1).
(Sections
deleted)
The protester’s initial proposal made no mention of the Rights
in Data clause; its final revised proposal contained the
following language: “All materials will be cleared for
educational and museum presentation use for the life of the
programs, up to twenty years.” Agency Report (AR), Tab 11,
Protester’s Final Proposal Revisions at 17. The protester’s
proposal received 95.64 points, including seven out of ten
points under the comprehensive plan factor. Nonetheless, the
contracting officer (CO) found the proposal unacceptable,
however, because it took exception to the Rights in Data clause
and the clause regarding ownership of products, quoted above, by
restricting the nature and the duration of the agency’s use of
the materials to be produced under the contract.
The protester argues that an offeror’s understanding of the
Rights in Data clause was but one portion of the comprehensive
plan factor, which was worth a maximum of ten points, and that
the failure of the protester’s proposal to comply with that
clause was properly considered in the comprehensive plan factor
scoring. Having considered this aspect of the proposal under the
criterion announced in the RFP, the CO’s subsequent
determination that the protester’s proposal was unacceptable was
inconsistent with the RFP, the protester asserts, given the
overall high score that the proposal received. We disagree.
In negotiated procurements, a proposal that fails to comply with
the material terms[2] of the solicitation should be considered
unacceptable and may not form the basis of award. Nordic Air,
Inc., B-400540, Nov. 26, 2008, 2008 CPD para. 223 at 3. We will
not disturb an agency’s determination of the acceptability of a
proposal absent a showing that the determination was
unreasonable, inconsistent with the terms of the solicitation,
or in violation of procurement statutes or regulation. Id.
Further, when a dispute exists as to the exact meaning of a
solicitation requirement, our Office will resolve the matter by
reading the solicitation as a whole and in a manner that gives
effect to all provisions of the solicitation. Id. Here, it is
unclear what purpose was served by the agency’s inclusion of an
offeror’s understanding of the Rights in Data clause as one
aspect of the comprehensive plan evaluation factor. But the
protester’s interpretation--that the agency was restricted to
the comprehensive plan evaluation factor when considering a
proposal’s understanding of that clause--negates both the text
of the clause, which is included in full in the solicitation, as
well as the Ownership of Products provision in the RFP, quoted
above, requiring offerors to grant to the agency unrestricted
use of the materials produced under the contract. When read as a
whole, then, the only reasonable interpretation of the RFP is
that it requires proposals to offer the agency unrestricted data
rights. Because the protester’s proposal failed to do so, we see
no reason to question the agency’s decision to exclude it from
the competition as unacceptable.
The protester argues that, because its proposal contained no
explicit deviations or exceptions, under the RFP’s standard
“deviations and exceptions” clause,[3] the agency could not
reasonably conclude that the proposal offered the agency less
than unrestricted rights in the materials produced under the
contract. The protester’s proposal restricted the agency’s
manner and duration of use of the materials created under the
contract. To say that such a statement may not be deemed a
deviation from the terms of the RFP because it was not in a
proposal section labeled “deviations and exceptions” is an
unpersuasive attempt to elevate form over substance. The plain
language of the protester’s proposal clearly took exception to a
material term of the RFP.
Even if its proposal had taken such an exception to the RFP, the
protester argues, “this would not have afforded the government
the right to find the offer ‘unacceptable’, under the explicit
terms of the very contract clause that the NPS itself drafted.”
Comments on AR at 2. We disagree. The deviations and exceptions
clause merely states that deviations from the terms of the RFP
will not automatically render a proposal unacceptable, and the
record in this case does not support an allegation that the
protester’s proposal was “automatically” deemed unacceptable.
Rather, the CO determined that the protester’s final proposal
revisions failed to comport with a material term of the
solicitation, and she therefore determined that the proposal was
unacceptable. (Northern Light
Productions, B-401182, June 1, 2009) (pdf)
Spectrum first
protests that the products offered by MTM do not have a Federal
Information Processing Standards (FIPS) 140-2 validation, and as
such do not meet a mandatory requirement set forth in the
solicitation. The protester's argument here is based upon
Spectrum's analysis of publicly-available information concerning
MTM's quoted product, and Spectrum's understanding of the FIPS
validation process.
The record reflects that in evaluating MTM's quotation the
agency found that MTM had responded "yes" to the requirement set
forth in the RFQ's Vendor Solution Matrix that the "[c]ryptographic
module in the product is NIST [National Institute of Standards]
FIPS 140-2 compliant," and that MTM's quotation also expressly
provided that MTM "uses a FIPS 140-2 Certified Cryptographic
module in all products." Agency Report (AR), Tab 2, MTM
Quotation, at 14.
Based upon our review of the record, the agency reasonably found
that MTM's quotation provided the information requested by the
solicitation, and agreed without exception to furnish a product
in accordance with the terms of the solicitation. While Spectrum
contends that the agency could not accept MTM's quotation
representation without further investigation, an agency may
accept a quotation's representation that indicates compliance
with the solicitation requirements, where there is no
significant countervailing evidence reasonably known to the
agency evaluators that should create doubt whether the offeror
will or can comply with the requirement. Alpha Marine Servs.,
LLC, B-292511.4, B-292511.5, Mar. 22, 2004, 2004 CPD ¶ 88 at 4.
Here, notwithstanding the detailed arguments by Spectrum as to
why MTM's quotation will not provide a product that meets the
FIPS 140-2 certification requirement, the record does not
indicate there was any countervailing evidence reasonably known
to the agency evaluators before award that should have created
doubt that MTM would or could honor its quotation. Whether MTM
actually delivers a product compliant with the terms of the
solicitation is a matter of contract administration, which is
for consideration by the contracting agency, rather than our
Office. Standard Mfg. Co., Inc., B‑236814, Jan. 4, 1990, 90‑1
CPD ¶ 14 at 3. GAO does not review matters of contract
administration under our bid protest function. 4 C.F.R. §
21.5(a) (2008); Nilson Van & Storage, Inc. B‑310485, Dec. 10,
2007, 2007 CPD ¶ 224 at 4. (Spectrum
Systems, Inc., B-401130, May 13, 2009) (pdf)
KBR argues that
the agency's determination that its proposal was unacceptable
was unreasonable. The protester first argues that its force
protection "assumption is consistent with the terms of the RFP,"
and "merely describes certain circumstances KBR anticipates may
occur during the course of performance and states KBR's
understanding of the manner in which the Army would respond."
Protest at 10. The protester continues here by providing a
lengthy explanation as to why, in its view, the force protection
assumption set forth in its proposal "was nothing more than a
brief encapsulation of those solicitation provisions" pertaining
to force protection. Protester's Comments at 14. The protester
argues that "[n]owhere does the Assumption state or suggest that
KBR would determine what constitutes 'necessary force
protection,'" and that "[i]t is clear to KBR . . . that a
contractor cannot issue orders to the military regarding the
deployment of military forces for force protection." Protester's
Comments at 3, 17.
The protester further argues that the Army's determination that
KBR's force protection assumption rendered its proposal
unacceptable was unreasonable because "[n]owhere in KBR's
proposal is there any explicit or implicit statement by KBR that
its performance is contingent upon the [force protection
assumption]," and that the "assumption can have no effect on the
cost that KBR would ultimately charge to the Army" because of
other RFP provisions that require Army approval under
"stringently defined conditions" before the contractor can incur
force protection costs. Protest at 11. The protester also points
out that it "included a nearly identical assumption in its
proposal for this same work under the LOGCAP III proposal, and
the solicitation and task order for this work under the LOGCAP
III contract contains similar force protection provisions." Id.
at 11 n.1.
The evaluation of proposals is a matter within the discretion of
the contracting agency, and in reviewing protests against
allegedly improper evaluations, it is not our role to reevaluate
proposals. Rather, our Office examines the record to determine
whether the agency's judgment was reasonable, in accord with the
evaluation factors set forth in the solicitation, and whether
the agency treated offerors equally in its evaluation of their
respective proposals and did not disparately evaluate proposals
with respect to the same requirements. Contingency Mgmt. Group,
LLC; IAP Worldwide Servs., Inc., B-309752 et al., Oct. 5, 2007,
2008 CPD para. 83 at 10. A protester's mere disagreement with
the agency's judgment does not render the evaluation
unreasonable. Landoll Corp., B-291381 et al., Dec. 23, 2002,
2003 CPD para. 40 at 8.
The agency explains that "there is perhaps no more crucial issue
in a contract for the provision of services on the battlefield,
than the level of force protection to be provided by the
military to the contractor." Contracting Officer's Statement at
7. The agency's overriding concern with KBR's force protection
assumption was that "the entire assumption implies that KBR will
be the one determining what 'necessary force protection' it will
require." AR at 4; see Contracting Officer's Statement at 4; AR,
Tab 9, Decision by Task Order Determining Official to Remove KBR
from Consideration for Award (Oct. 29, 2008), at 2. The agency
explains that this is in direct conflict with the provisions of
the applicable contract clauses, and, as incorporated by
reference, chapter 6 of Army Field Manual 3-100.21 and the
"Applicable Theater Anti-Terrorism/Force Protection Guidelines,"
which provide that determinations as to whether force protection
is needed and at what level rest with the combatant commander
and are to be made in accordance with those publications. AR at
4-5; Contracting Officer's Statement at 4-5;
The agency also points to several specific clauses in KBR's
assumption that cause the agency concern. For example, the
second sentence of KBR's force protection assumption states that
the provision of "necessary" force protection "includes, but is
not limited to, the security at the KBR work site and movement
throughout the Area of Operations, to include between work
sites, living/messing areas and ingress/egress to the Area of
Operation." See AR, Tab 13, KBR Proposal, Proposal Narrative, at
3. The agency argues that the requirement that force protection
be provided to KBR personnel "between work sites, living/messing
areas and ingress/egress to the Area of Operation" is "an overt
augmentation of the solicitation provisions." Contracting
Officer's Statement at 5. The agency adds that, in its view,
KBR's force protection assumption, through the use of the phrase
"includes, but is not limited to," in describing the force
protection to be provided, "establishes a minimum level of force
protection to be provided by the military, and then goes on to
subject the Government to indeterminate responsibility for the
provision of force protection." Id.
The agency also argues that the last sentence of KBR's force
protection assumption, which states that "[i]t is assumed
soldiers will be positioned in over watch of the site and where
KBR personnel encounter a hostile threat, it is further assumed
that U.S. Army personnel will intervene without delay,"
constitutes an "augmentation of the force protection provisions
of the solicitation." Contracting Officer's Statement at 6; see
AR, Tab 13, KBR Proposal, Proposal Narrative, at 3. In this
regard, the agency contends that KBR's assumption that
"'soldiers will intervene without delay' imposes a requirement
that impinges upon the combatant commander's latitude in
determining the appropriate course of action in hostile
circumstances." Id. at 6.
Finally, with regard to KBR's argument that its force protection
assumption should not cause the agency concern because "KBR
included a nearly identical assumption in its proposal for this
same work under the LOGCAP III proposal, and the solicitation
and task order for this work under the LOGCAP III contract
contains similar force protection provisions," see Protest at 11
n.1., the agency notes that "force protection has been a
contentious issue" under that contract. Contracting Officer's
Statement at 8; see AR at 7. The agency specifically states
here, and the protester does not argue otherwise, that KBR has
requested "reimbursement for costs of force protection, and when
denied KBR submitted a claim of $19 [million]." AR at 7.
The agency concluded that the acceptance of KBR's proposal would
subject "the Government to increased risk of a contractor claim,
or refusal to perform in the event of a dispute concerning what
constitutes the appropriate level of force protection," and thus
the agency rejected KBR's proposal as unacceptable. Contracting
Officer's Statement at 8.
Our review of the record provides no basis to find the agency's
evaluation and rejection of KBR's proposal unreasonable or
otherwise objectionable. As explained by the parties and set
forth in chapter 6 of Army Field Manual 3-100.21, "[p]rotecting
contractors and their employees on the battlefield is the
commander's responsibility," and "[t]he mission, threat, and
location of contractor operations determine the degree of force
protection needed." AR, Tab 4, Army Field Manual 3‑100.21, ch.
6, at 6-2. With regard to the agency's primary concern, we
believe that KBR's force protection assumption is, considered
most favorably to the protester, unclear as to who determines
what force protection is necessary. That is, although KBR's
assumption does not specifically state that KBR assumes that it
will be able to determine or be required to have input in
determinations concerning force protection, it nevertheless
provides no guidance in this regard, and is thus ambiguous as to
whether the assumption is consistent with, or is taking
exception to, the RFP's force protection provisions. Given that
the solicitation provided that force protection would be
provided in accordance with, among other things, chapter 6 of
Army Field Manual 3-100.21, which provides that the combatant
commander determines, based upon the terms of the manual, the
force protection needed for contractor personnel, we find the
agency's rejection of KBR's proposal because of the ambiguity
introduced by KBR's assumption to be unobjectionable. Nu-Way,
Inc., B-296435.5; B-296435.10, Sept. 28, 2005, 2005 CPD para.
195 at 5; Rel‑Tek Sys. & Design, Inc., B-280463.3, Nov. 25,
1998, 99‑1 CPD para. 2 at 4. (Kellogg
Brown & Root Services, Inc., B-400614.3, February 10, 2009)
(pdf)
In a nutshell,
the dispute between the protester and the agency arises over the
method used to calculate an offeror’s compliance with the
solicitation’s small business subcontracting goals. Simply put,
the solicitation established goals for various types of small
businesses, which were stated in terms of a percentage of total
subcontracted dollars. In calculating compliance with the stated
goals, Granite first subtracts the value of its major electrical
subcontractor, which is a large business, and then calculates
its compliance with the solicitation’s goals. In contrast, the
agency includes the value of this significant subcontract, and
calculates the goals using the larger total.
Granite’s approach of deducting the value of the work to be
provided by its large business electrical subcontractor before
calculating its compliance with the RFP goals using the much
smaller resulting number, means that Granite erred in two ways.
First, its claimed percentages of the amount of total
subcontracted dollars going to the various categories of small
businesses were significantly overstated because they are not
based on the total amount of Granite’s subcontracting dollars.
In addition, because Granite overstated the resulting
percentages, it failed to take the opportunity to explain why it
could not meet the solicitation-required minimums. Finally, even
if the agency wanted to accept Granite’s representation about
why it could not meet the solicitation’s overall small business
subcontracting goal--i.e., 76.07 percent of subcontracted
dollars--Granite’s FPR says nothing about the other applicable
small business goals--i.e., the goals applicable to WOSBs, SDBs,
HUBZone small businesses, VOSBs, or SDVOSBs. In short, Granite’s
proposed approach to subcontracting does not do either of the
two things this solicitation required with respect to these
other categories of small businesses--i.e., either meet the
applicable goals, or explain why the goals could not be met.
To the extent that Granite asserts that its subcontracting plan
was a draft plan that could have been revised prior to award if
the agency was not satisfied, we disagree. As quoted previously,
the RFP clearly indicates that the agency would evaluate an
offeror’s small business subcontracting plan as part of the
non-price evaluation and would then evaluate further only those
proposals rated acceptable under each non-price factor.
Consistent with that evaluation scheme, the agency would again
review and approve the subcontracting plan of the technically
acceptable offeror whose proposal was deemed the lowest-priced.
This approach does not mean the agency acted improperly when it
decided not to accept a proposal that did not address the
requirements of the solicitation and give Granite a third
opportunity to address the situation (since this matter was
clearly raised during discussions) after the selection decision.
Under the circumstances here, we think the agency acted
reasonably when it concluded that Granite had not responded
adequately to the small business subcontracting requirements set
forth in this solicitation. (Granite
Construction Company, B-400706, January 14, 2009) (pdf)
When an agency
evaluates proposals for the award of a cost-reimbursement
contract, an offeror’s proposed estimated cost of contract
performance is not considered controlling since, regardless of
the costs proposed by an offeror, the government is bound to pay
the contractor its actual and allowable costs. Hanford Envtl.
Health Found., B-292858.2, B-292858.5, Apr. 7, 2004, 2004
CPD para. 164 at 9; PADCO, Inc.--Costs, B-289096.3, May
3, 2002, 2002 CPD para. 135 at 5; see Federal Acquisition
Regulation (FAR) sect. 16.301. As a result, a cost realism
analysis is required to determine the extent to which an
offeror’s proposed costs represent the offeror’s likely costs in
performing the contract under the offeror’s technical approach,
assuming reasonable economy and efficiency. FAR sections
15.305(a)(1), 15.404-1(d)(1), (2); The Futures Group Int’l,
B-281274.2, Mar. 3, 1999, 2000 CPD para. 147 at 3. A cost
realism analysis involves independently reviewing and evaluating
specific elements of each offeror’s cost estimate to determine
whether the estimated proposed cost elements are realistic for
the work to be performed, reflect a clear understanding of the
requirements, and are consistent with the unique methods of
performance and materials described in the offeror’s proposal.
FAR sect. 15.404-1(d)(1); Advanced Commc’ns. Sys., Inc.,
B-283650 et al., Dec. 16, 1999, 2000 CPD para. 3 at 5. Based on
the results of the cost realism analysis, an offeror’s proposed
costs should be adjusted when appropriate. FAR sect.
15.404-1(d)(2)(ii).
The evaluation of competing cost proposals requires the exercise
of informed judgment by the contracting agency. We review an
agency’s judgment in this area only to see that the agency’s
cost realism evaluation was reasonably based and not arbitrary.
Jacobs COGEMA, LLC, B-290125.2, B-290125.3, Dec. 18,
2002, 2003 CPD para. 16 at 26. An agency’s cost realism analysis
need not achieve scientific certainty; rather, the methodology
employed must be reasonably adequate and provide some measure of
confidence that the agency’s conclusions about the most probable
costs under an offeror’s proposal are reasonable and realistic
in view of other cost information reasonably available to the
agency as of the time of its evaluation. See Metro Mach.
Corp., B-295744, B-295744.2, Apr. 21, 2005, 2005 CPD para.
112 at 10-11.
The protester argues that NAVSEA unreasonably accepted Metro’s
unrealistically low capped indirect rates and failed to consider
the risk presented by these low capped rates in determining that
Metro’s proposal represented the best value to the government.
According to the protester, this was contrary to the terms of
the solicitation, which expressly stated that the agency would
perform a cost realism evaluation and admonished offerors not to
submit unrealistically low costs. In support of this allegation,
the protester highlights the fact that Metro proposed indirect
rates (overhead and G&A) at levels below its forward pricing
rates, as well as the then-current information the agency had
regarding Metro’s indirect rates. Because Metro capped its
indirect rates at such unrealistically low levels, the protester
alleges that Metro will be operating at a loss under the
contract and that the agency failed to properly consider this
risk in its selection of Metro for award.
The agency essentially argues that because Metro capped its
indirect rates, upward adjustment to Metro’s rates was not
warranted; any decision about Metro’s ability to perform at the
rates capped below actual costs is solely a matter concerning
Metro’s responsibility; and it in fact considered Metro’s
ability to perform at the capped rates as part of its
affirmative responsibility determination.
As a general matter, the contractor bears the risk of cost
overruns for a particular category or type of work in a
cost-reimbursement contract when the contractor agrees to a cap
or ceiling on its reimbursement for that category or type of
work. Thus, when offerors propose such caps, and no other issue
calls into question the effectiveness of the cap, upward
adjustments to capped costs are improper. Vitro Corp.,
B-247734.3, Sept. 24, 1992, 92-2 CPD para. 202 at 7. Here, there
is nothing in the record to suggest that the rate caps proposed
by Metro were in any way illusory; thus, we agree with the
agency’s contention that it was not required to upwardly adjust
Metro’s capped indirect rates, notwithstanding the fact that the
agency itself found Metro’s capped rates to be “significantly”
lower than its then-current rates.
Nevertheless, the agency could not simply ignore the risk
presented by these capped rates in concluding that Metro’s
proposal was the best value. As noted previously, the
solicitation expressly admonished offerors not to propose
unrealistically low costs because of NAVSEA’s concern that a
proposal with unrealistically low costs due to an offeror’s
decision to submit a proposal below its anticipated costs “may
cause problems for the Navy as well as the contractor during
contract performance.” RFP at 138. Recognizing that the capped
indirect rates proposed by Metro shifted the risk of cost
overruns for those rates entirely to Metro, the imposition of
the cap in fact exacerbated the issues identified by DCAA
regarding Metro’s financial condition [Deleted], and thereby
further hampering its ability to perform under its government
contracts--the very concern articulated in the RFP. While NAVSEA
was clearly aware of the concerns regarding Metro’s financial
situation, and the fact that the rate caps would potentially
place Metro [Deleted], thereby potentially affecting its
performance under the contract, the agency failed to consider
the risks posed by Metro’s low rates.
NAVSEA argues that the issue of Metro’s ability to perform at
its capped rates was solely a matter concerning Metro’s
responsibility, a matter which the protester did not challenge,
and was expressly considered as part of that determination.
While we agree that, as a general matter, a decision about an
awardee’s ability to perform a contract at rates capped below
actual costs is a matter of an offeror’s responsibility, see,
e.g., Vitro Corp., supra, at 7; Halifax Tech. Serv.,
Inc., B-246236.6 et al., Jan. 24, 1994, 94-1 CPD para. 30
at 9, where, as here, the solicitation expressly instructs
offerors not to submit unrealistically low costs or prices, the
risk stemming from an offeror’s decision to propose
unrealistically low capped rates is a matter for the agency’s
consideration in the context of its evaluation of proposals and
source selection decision process. The agency’s failure to
consider Metro’s capping of its rates in that context was
inconsistent with the terms of the solicitation. We therefore
sustain the protest in this regard.
(MCT JV, B-311245.2; B-311245.4, May 16, 2008) (pdf)
The sole issue before us is the interpretation of GSAR
552.270-1(c)(7).
Plaintiff argues that the inclusion of this clause in the SFO
obligated GSA to
consider on the merits all offers, even those deviating
materially from the
stated requirements. In effect, plaintiff suggests that, even
though its offer did
not make use of the site which formed the basis of the SFO, this
clause means that there can be no non-conforming offers and that
the failure to include Tin Mills in the competitive range could
only be effected after a full examination of the advantages and
disadvantages of its offer. It contends that the particular site
on which the building was located was not, in any event, a
material requirement and that Tin Mills could not be left out of
the competitive range without a substantive explanation which
must pass muster under an Administrative Procedures Act style
review.
Defendant argues that GSAR 552.270-1(c)(7) permits GSA to
consider
offers that depart from solicitation requirements but does not
obligate it to do
so. The failure to justify a refusal to consider changing the
solicitation terms,
it contends, is not subject to court review. Although not
strictly necessary to
its argument, defendant also contends that if GSA had been
interested in Tin
Mills’ offer, the agency would have had to amend the
solicitation and notify
all bidders. The SFO process, defendant contends, should be
interpreted in the
context of the statutory requirement for full and open
competition, 41 U.S.C.
§ 253, and the background principle set out in FAR 15.206, which
requires the
government to amend the solicitation if a proposal of interest
deviates from the
stated solicitation requirements.
We must first examine what, if any, obligation the GSAR clause
imposes on the government to consider an offer that departs from
the stated
solicitation requirements. If we find that this clause imposes
an obligation on
the agency to consider non-conforming offers, we must then
examine whether
the failure to open the sale to offers which deviate from what
the agency seeks
is subject to court review. Only if that determination is
subject to court
review, need we also consider whether the government had to
amend the
solicitation before awarding a nonconforming offer.
We begin by noting the obvious: Nothing in the language of the
clause
(“Offerors may submit proposals that depart from stated
requirements.”)
compels plaintiff’s reading. GSAR 552.270-1(c)(7). There is
certainly no
explicit promise to consider non-conforming proposals. And, as
we explain
below, there is good reason not to imply such a promise.
In negotiated procurements, “the court will take a more
deferential view
of whether an agency’s actions were rational or reasonable than
it will in
sealed bidding.” John Cibinic, Jr. & Ralph C. Nash, Jr.,
Formation of Government Contracts 1554 (3rd ed. 1998) (citing Logicon, Inc. v. United
States, 22 Cl. Ct. 776 (1991)); see also Cincom Sys. v. United
States, 37 Fed. Cl. 663, 672 (1997) (“[contracting officials’] discretion is
especially broad in
negotiated procurements”); 126 Northpoint Plaza Ltd. P’ship v.
United States,
34 Fed. Cl. 105, 107 (1995) (“In negotiated procurements,
contracting officials
possess ‘broad discretion in the process of obtaining the
contract most
beneficial to the government.’”) Here, the CO eliminated Tin
Mills’ offer
from the competitive range because it was “nonresponsive.” AR
1203.
Although the concept of responsiveness or “an unconditional
promise to
comply with the terms of a solicitation,” does not apply
directly to negotiated
procurements, offers must comply with the material terms and
obligations in
a SFO to merit consideration. Gardiner, Kamya & Assocs., P.C.,
1995 WL
19599, B-258400, 95-1 CPD ¶ 191, *2 n.1. Stated inversely, “[a]
proposal that
fails to satisfy a material solicitation term is unacceptable
and may not form
the basis for an award.” Integrated Business Solutions, Inc. v.
United States,
58 Fed. Cl. 420, 428 (2003) (citing Marisco, Ltd., 1989 U.S.
Comp. Gen.
LEXIS 719, B-235773, 89-2 CPD ¶ 8; Minigraph, Inc.-Recon., 1990
U.S.
Comp. Gen. LEXIS 1350, B-237873.3, 90-2 CPD ¶ 492).
Consistent with this general approach, GSAR 570.303-4, “Changes
to
SFOs,” provides that, if the government’s requirements change,
“either before
or after receipt of proposals, issue an amendment.” Similarly,
GSAR 570.306,
“Evaluating offers,” instructs COs that they “must evaluate
offers solely in
accordance with the factors and subfactors stated in the SFO.”
This strongly
suggests, not only that the agency has no obligation to consider
nonconforming
offers on the merits, but that it would be improper to do so
without
first changing the solicitation and notifying other bidders.
We also take note of FAR 15.206(d), which applies to negotiated
procurements and specifically addresses when the agency must
amend the
solicitation. Although that regulation was not specifically
incorporated in the SFO here, it reflects general background principles applicable
to negotiated
procurements:
If a proposal of interest to the Government involves a departure
from the stated requirements, the contracting officer shall
amend
the solicitation, provided this can be done without revealing to
the other offerors the alternate solution proposed or any other
information that is entitled to protection [].
48 C.F.R. §
15.206(d). In short, only proposals of interest to the
government
need to be pursued, and, because they imply a departure from the
advertised
terms of the SFO, other bidders must be notified.
Plaintiff suggests that GSAR 552.270-1(c)(7) is an exception to
this
approach; that by soliciting non-conforming offers, any proposal
submitted in
response is per se responsive. Although Tin Mills takes the
position that the
alternate site it offered was not a material deviation, it
argues that, even if
plaintiff’s deviation from the terms of the SFO had been
material, GSAR
552.270-1(c)(7) required GSA to consider and evaluate its offer.
The agency
could only reject it after weighing the advantages and
disadvantages suggested
by Tin Mills and explaining its reasoning to plaintiff and to
the court.
According to plaintiff, if GSA did not want to evaluate
alternative proposals,
it should have either not included the GSAR clause or stated
that the location
of the building was a mandatory requirement, exempt from this
clause.
Such an interpretation would lead to a scenario for bid protests
which
is completely untethered to the requirements of the SFO. It
would effectively
make all solicitation requirements optional. The agency could be
called upon
to justify its stated requirements to any offeror. We cannot
adopt this
interpretation.
Instead, we agree with defendant that Tin Mills’ offer could be
excluded from the competitive range because it materially
departed from the
solicitation requirements. Tin Mills had every reason to know
that a
fundamental predicate of the solicitation was the site selected
by the
government for the building. The solicitation specified that the offerors should
use the 1550 Earl Core Road site in submitting proposals for the
building. The
executed option to purchase that site was included with the
solicitation. The
three amendments made to the SFO were all specific to the
Glenmark site.
These events left no room for plaintiff to doubt defendant’s
commitment to
construct a building on the Glenmark site. (Tin
Mills Properties, LLC v. U. S. and Glenmark Holding, LLC,
No. 08-375C, July 15, 2008) (pdf)
Product Support Subfactor Evaluation
Boeing also complains that the Air Force misevaluated Northrop
Grumman’s proposal under the product support subfactor. This
subfactor required the agency to evaluate the “offeror’s
proposed product support approach for an efficient, effective
and comprehensive support program for the service life of the
KC-X fleet.” RFP sect. M.2.2.3. Specifically, Boeing contends
that the Air Force improperly ignored Northrop Grumman’s refusal
to commit to providing the required support necessary to allow
the agency to achieve initial organic depot-level maintenance
capability within the time required by the RFP, namely, within 2
years after delivery of the first full-rate production aircraft.
Boeing’s Post-Hearing Comments at 84. The Air Force evaluated
Boeing’s and Northrop Grumman’s proposals to be essentially
equal under the product support subfactor. See AR, Tab 54,
Source Selection Decision Document, at 10; Tab 55, PAR, at 34.
Offerors were informed that the long-term support concept for
the KC-X program was for two levels of organic maintenance:
organization level and depot level, and that a program objective
was a product support approach that effectively addressed all
the integrated support elements, including “[t]imely, cost
effective transition to organic support.” RFP, SOO for KC-X SDD,
at 1-2. One of the specific minimum program tasks required by
the SOO with regard to “logistics” was for the contractor to
[p]lan for and support the Government to achieve an initial
organic [depot]-level maintenance capability in accordance
with the [Source of Supply Assignment Process] for
core-designated workloads, at a minimum, within two years
after delivery of the first full-rate production aircraft.
Id. at 14; see also RFP, SOO for KC-X LRIP and Full-Rate
Production, at 1. The RFP instructed offerors to ensure that
their proposed contractual statements of work (SOW) would
“conform to the Government’s SOO” and that “[t[he proposed SOWs
shall define the tasks required for the KC-X program, ensuring
all minimum requirements of the Government provided SOOs and
preliminary [work breakdown structure] have been addressed.” See
RFP sections L.2.1, L.8.3.7.2.
The Air Force recognized in its evaluation that, although
Northrop Grumman promised to provide the necessary planning and
support for the agency to achieve an initial depot-level
maintenance capability, the firm did not commit to providing
this required support within 2 years after delivery of the first
full-rate production aircraft, as required by the RFP. Thus, at
the mid-term briefing, Northrop Grumman was informed that the
timing of the firm’s proposed depot level maintenance support
was “unclear,” see AR, Tab 199, Northrop Grumman’s Mid-Term
Briefing, at 134, and then again at the pre-final proposal
briefing, Northrop Grumman was informed that the agency had
assigned it a weakness for its failure “to include the time
frame for initial organic depot standup in Offeror’s Production
SOW (SOO states within two years after delivery of the first
full-rate production aircraft).” See AR, Tab 205, Northrop
Grumman’s Pre-Final Proposal Revision Briefing, at 141. Northrop
Grumman did not resolve its failure to commit to the 2-year
timeframe for this product support requirement during the
procurement. In the firm’s final proposal revision, Northrop
Grumman stated in one place that resolution of this “timing
issue will be determined in coordination with the Government at
contract award” and, in another place, that action to “resolve
government identified weaknesses” would occur “after contract
award.” See AR, Tab 187, Northrop Grumman’s Final Proposal
Revision, KC-X Program Summary Document, at 2-3.
In its final evaluation, the SSET evaluated Northrop Grumman’s
refusal to commit to providing these product support services
within the 2-year timeframe as a weakness. AR, Tab 46, SSET
Final Briefing to SSAC and SSA, at 360, 362. The SSAC concluded
that this was an “administrative documentation oversight”
because Northrop Grumman had promised to provide the required
services and its “cost/schedule documentation is consistent with
standing up depot capability within two years of delivery of the
first full-rate production aircraft.” AR, Tab 55, PAR, at 34.
The SSA concurred with the SSAC that this was “merely an
administrative oversight.” AR, Tab 54, Source Selection
Decision, at 10.
We agree with Boeing that Northrop Grumman’s refusal to commit
to the required 2‑year timeframe within which to provide these
depot-level maintenance planning and support services cannot be
reasonably viewed as an administrative or documentation
oversight. As noted above, Northrop Grumman was clearly informed
several times by the Air Force of the agency’s concern that the
firm had not committed to the required timeframe, and Northrop
Grumman responded that it was not resolving this failure before
award. Although throughout the protest and during the hearing,
the agency steadfastly asserted that Northrop Grumman’s failure
to so commit was an “oversight,” see, e.g., Air Force’s
Memorandum of Law at 151-53, in its post-hearing rebuttal
comments, the agency admitted for the first time that Northrop
Grumman’s “omission” appeared to be a conscious decision. See
Air Force’s Post‑Hearing Rebuttal Comments at 9. Northrop
Grumman also finally admits in its rebuttal comments that its
decision to not commit to the 2-year timeframe was
“intentional.” Northrop Grumman’s Post‑Hearing Rebuttal Comments
at 29 n.13.
The Air Force and Northrop Grumman argue, however, that, apart
from Northrop Grumman’s refusal to commit to the 2-year
timeframe, Northrop Grumman committed generally and specifically
to performing the planning and support services solicited by the
RFP in its proposal and proposal revisions, and that the firm
would otherwise be obligated to perform the required services
under whatever schedule the agency chooses. See, e.g., Air
Force’s Post-Hearing Rebuttal Comments at 11; Northrop Grumman’s
Post-Hearing Rebuttal Comments at 29. The parties disagree as to
whether Northrop Grumman’s proposal demonstrates the ability to
provide the required services within 2 years of delivery of the
first full-rate production aircraft, and based on our review of
Northrop Grumman’s proposal and revisions, we find that it is
far from clear whether or not Northrop Grumman’s proposed
schedule establishes that it would perform these services within
the 2-year time frame.
Whether or not Northrop Grumman’s proposed schedule accommodates
providing these product-support services within the 2-year
timeframe misses the point, however. By explicitly refusing to
contractually commit to the 2-year timeframe for providing these
services in the SOW as it was repeatedly requested to do, we
think that Northrop Grumman has taken exception to this
solicitation requirement. See C‑Cubed Corp., B-272525, Oct. 21,
1996, 96-2 CPD para. 150 at 3. It is a fundamental principle in
a negotiated procurement that a proposal that fails to conform
to a material solicitation requirement is technically
unacceptable and cannot form the basis for award. See TYBRIN
Corp., B‑298364.6; B‑298364.7, Mar. 13, 2007, 2007 CPD para. 51
at 5.
The Air Force and Northrop Grumman also argue that the 2-year
requirement is not a material solicitation provision. However,
their arguments in this regard are belied by the agency’s
contemporaneous actions during the procurement and the testimony
of the SSET product support subfactor team chief. As noted
above, the agency repeatedly raised this matter with Northrop
Grumman during discussions in an unsuccessful effort to have the
firm commit to this solicitation requirement, and Northrop
Grumman just as steadfastly refused to commit. Moreover, the
SSET product support subfactor team chief identified the purpose
or intent of this particular SOO requirement as follows: “It was
a binding function to bind it to a specific time line,” see HT
at 1216, and that this 2-year requirement was “an important
requirement.” HT at 1245. We find, from our review of the
record, that the requirement to plan for and support the
agency’s achieving an initial organic depot‑level maintenance
capability within 2 years after delivery of the first full-rate
production aircraft was a material requirement.
In sum, the Air Force improperly accepted Northrop Grumman’s
proposal, where that proposal clearly took exception to a
material solicitation requirement.
(The
Boeing Company, B-311344; B-311344.3; B-311344.4;
B-311344.6; B-311344.7; B-311344.8; B-311344.10; B-311344.11,
June 18, 2008) (pdf)
On July 25, 2007, the Air Force issued the RFP for certain air
conditioning units (units capable of both cooling and heating)
to be installed at locations surrounding Aviano Air Base, Italy.
The RFP required the units to meet various specifications,
including that they be “EUROVENT certified” in a certain class,
and that the air conditioner data be available at the website
www.eurovent-certification.com. AR, Tab 18, at 1. In response to
the RFP, the agency received six proposals, including the
protester’s and the awardee’s. While the protester proposed one
item at a single price, the awardee proposed six different
brands of air conditioner at different prices, with four priced
lower than the protester’s. The other four proposals were
eliminated from the competition for reasons not relevant here.
The agency then sought information from C&H and Sanson Bruno
regarding their proposed items’ Eurovent certification.
Contracting Officer’s (CO) Statement at 1. The agency
determined that the awardee’s four lowest-priced items were not
Eurovent certified. With regard to the fourth lowest priced
item, the agency requested product information from Sanson
Bruno, and ultimately concluded that this item was not listed on
the Eurovent website. The agency then requested information from
C&H. The protester responded with a statement from another
firm--apparently the supplier of the units to C&H--that the
units were “from Bonaga Italia, brand Sermond, Model SRF 12 H
registered with Eurovent under the serial number MSH 12HRN1.”
AR, Tab 13, B, at 3. The agency subsequently searched the
Eurovent website and discovered that the brand name associated
with this model number actually was Midea, manufactured by GD
Midea Air Conditioning Company, Ltd. There was no mention of the
brand name Sermond on the website. Legal Memorandum at 3. The
agency then questioned C&H about its product a second time, and
the protester responded with two more certifications, one from
itself and one from Bonaga Italia. Both certifications stated
that the proposed unit was marketed with the brand Sermond by
Bonaga Italia, and was certified under the code MSH 12HRN1 of GD
Midea Air Conditioning Equipment Company, Ltd. on the Eurovent
certification website. Based on this exchange, the agency
concluded that the protester’s proposal was ineligible for award
because there was no item under the Sermond brand listed on the
Eurovent website. The agency thus made award to Sanson Bruno for
its fifth lowest-priced unit, which was listed on the Eurovent
website, at a price higher than C&H’s. Upon learning that the
agency had determined that its product was ineligible for award,
C&H filed this protest. C&H primarily asserts that it
should have received the award because its proposed unit
actually was listed on the Eurovent website. In this regard, the
protester asserts that its unit was in fact the Midea unit
listed on the website, the only difference between the two units
being the marketing name. Clearly stated RFP requirements
are considered material to the needs of the government, and a
proposal that fails to conform to such material terms is
unacceptable and may not form the basis for award. Gear Wizzard,
Inc., B‑298993, Jan. 11, 2007, 2007 CPD para. 11 at 2. The
procuring agency has primary responsibility for evaluating the
technical information supplied by an offeror and determining the
acceptability of the proposed item; we will not disturb such a
determination unless it is shown to be unreasonable. Alpha
Marine Servs., LLC, B‑292511.4, B‑292511.5, Mar. 22, 2004, 2004
CPD para. 88 at 4. The agency’s determination that C&H’s
proposed product was unacceptable for failing to meet the
Eurovent listing requirement was reasonable. It is undisputed
that C&H’s proposed Sermond brand product was not listed on the
Eurovent website under the brand as stated in C&H’s proposal.
This led the agency to seek information from C&H clearly
establishing that its proposed Sermond product in fact was
listed on the website. In response, C&H provided only statements
from itself and a supplier that the Sermond product was actually
a Midea product, with no independent information supporting the
claim. C&H provided no supporting information from the
manufacturer or from Eurovent, and the agency’s search of the
website under “Midea Manufacturing” did not yield any items with
the Sermond brand. Legal Memorandum at 6. We note that, in
connection with its protest, C&H has provided a letter from GD
Midea Air Conditioning Equipment Company, Ltd. stating that the
proposed unit is in fact identical to the listed Midea unit.
Protester’s Comments, Dec. 17, 2008, exh. 1. However, given
C&H’s failure to provide this information in response to the
agency’s request during the evaluation process, the agency
reasonably concluded at that time that the protester had failed
to demonstrate that its product was listed on the Eurovent
website. (C&H SERVICE Srl,
B-310790, February 5, 2008) (pdf)
Connectec submitted its proposal on August 9, but did not
include a proposed delivery schedule. CO Statement at 2. UNICOR
awarded the contract to Teutech on August 20, and posted a
notice of the award on August 29. Id. Subsequently, Connectec
contacted UNICOR requesting an explanation of the decision to
award the contract to Teutech at a higher price. Connectec
Letter, Sept. 5, at 1. UNICOR explained that Connectec’s
proposal was rejected because it failed to include a proposed
delivery schedule. CO Statement at 2. Connectec filed an
agency-level protest, which UNICOR denied. CO Letter, Sept. 17.
Subsequently, Connectec filed this protest. Connectec does
not disagree that it failed to provide delivery information.
Instead, it contends that UNICOR should not have excluded its
proposal from consideration for award because the agency has, in
the past, awarded contracts based on proposals that did not
contain delivery information. Generally, a delivery
schedule or time of performance requirement is regarded as a
material requirement of a solicitation. See, e.g., Muddy Creek
Oil and Gas, Inc., B‑296836, Aug. 9, 2005, 2005 CPD para. 143 at
2. A proposal that fails to conform to material solicitation
requirements is technically unacceptable and cannot form the
basis for award. Bannum, Inc., B-291847, Mar. 17, 2003, 2003 CPD
para. 74 at 3. Here, the RFP provided for a delivery date,
stated that delivery was one of three evaluation factors, and
noted twice that delivery and past performance were
significantly more important than price. RFP at 6, 9. Therefore,
information about an offeror’s ability and intent to make timely
deliveries was a material part of each proposal, and UNICOR
reasonably determined that the lack of delivery information
rendered Connectec’s proposal technically unacceptable and
ineligible for contract award. The protester argues that
it has been awarded contracts in the past without a proposed
delivery schedule. Protest at 1. To support this assertion, the
protester provided a prior solicitation under which it claims to
have received award without providing delivery terms.
Protester’s Comments, Nov. 5, 2007, exh. 1. Our review of this
solicitation shows that it does not use the same evaluation
scheme as here; delivery was not a separate evaluation factor.
Id. Furthermore, even if this assertion is true, the protester
cannot rely on past practices to excuse its failure to satisfy
the requirements of the RFP here, as each procurement stands
alone. GM Indus., Inc., B‑231998, Oct. 25, 1988, 88-2 CPD para.
388 at 5. In our view, the RFP clearly indicated that
offerors must identify a delivery date in order to be considered
for award. Therefore, UNICOR reasonably excluded Connectec from
consideration when the company failed to include the required
delivery information in its proposal. (Connectec
Company, Inc., B-310460, November 27, 2007) (pdf)
The Air Force reasonably rejected
CMC’s proposal. While the protester’s argument is focused on
whether the items labeled deficiencies met (or exceeded) the RFP
requirements or could be corrected through minor revisions, we
note that the number of words affected and the ease of
correction are not the defining considerations. Rather, even
where proposal deficiencies could be corrected without lengthy
revisions, the need for numerous corrections and revisions may
provide a reasonable basis for an agency to conclude that the
proposal evidenced an inherent lack of understanding or
awareness of the current RFP’s requirements. See Pace Data Sys.,
Inc.; Senior Care Storage Co., B‑236083, B‑236083.2, Nov. 6,
1989, 89‑2 CPD para. 429 at 5 (even where proposal deficiencies
may be viewed as minor in nature taken individually, the
cumulative effect of the deficiencies is sufficient to support
the agency’s conclusion that the proposal was unacceptable).
Such was the case here. CMC’s proposal was not responsive to
numerous aspects of the RFP, did not correspond to other
aspects, and contained extraneous information. CMC does not
dispute that evaluated deficiencies existed, and given the
number and nature of those deficiencies--which suggested that
CMC may have submitted information from an old proposal without
updating various aspects of the requirements--we think the
agency reasonably could conclude that CMC lacked an
understanding or awareness of the RFP requirements. Further,
while CMC’s proposed 50-day maintenance rotation (and other
proposal features) may have exceeded the RFP requirements, the
agency could view this in the context of the proposal as a
whole; rather than an intended enhancement, the agency
apparently considered this to be another example of the
proposal’s failure to correspond to the requirements of the
current RFP, reinforcing its concern that CMC did not
understand, or was unaware of, the actual requirements. Again,
given the nature and number of the identified deficiencies, this
conclusion was unobjectionable. (C.
Martin Company, Inc., B-299382, April 17, 2007) (pdf)
Here, as noted above, the solicitation specifically required
that, to be evaluated as technically acceptable, an offeror’s
proposed management plan must “ensure timely, professional and
high quality performance.” RFP at 65. Particularly in light of
the requirements at issue here, the length of an offeror’s
proposed workweek is clearly encompassed within the stated
requirement for high quality performance. Further, in conducting
discussions with WII regarding this matter, the agency
explicitly advised WII that the agency considered WII’s proposed
[DELETED] workweek to be “excessive,” and that such a management
approach would “exhaust and demoralize a guard force.”
Notwithstanding this explicit language indicating that the
proposed workweek was unacceptable to the agency, WII neither
provided a meaningful response to the agency’s concerns, nor
revised its proposed management approach. Procuring agencies are
generally in the best position to determine their actual
requirements and the best method for meeting them. In reviewing
protests challenging an agency’s assessments with regard to a
particular performance approach, our Office will not substitute
our judgment for that of the agency; rather, we will review the
record to determine whether the judgments are reasonable and
consistent with the solicitation criteria. See, e.g., RMS
Indus., B-247233, B-247234, May 1, 1992, 92-1 CPD para. 412.
Here, based on our review of the entire record, we find no basis
to question the agency’s determination that WII’s proposed
[DELETED] workweek was excessive, that it would exhaust and
demoralize WII’s guard force and, therefore, that it rendered
WII’s proposal unacceptable for failure to comply with the
solicitation requirement that an offeror’s proposed management
approach would “ensure timely, professional and high quality
performance.” Although WII continues to express disagreement in
this regard, it has provided nothing to demonstrate that the
agency’s determination was unreasonable. (Wackenhut
International, Inc., Wackenhut Puerto Rico, Inc., Wackenhut
Jordan, Ltd.--a Joint Venture, B-299022; B-299022.2, January
23, 2007) (pdf)
Here, as discussed above, the solicitation defined the
acceptable level of performance in terms of the maximum percent
of defective work that will be allowed. RFP, Performance Work
Statement, at 31. More specifically, the solicitation provided
that “[l]aundry is clean, dry, free of lint and odor, spots and
stains removed,” and that the acceptable level of deviation from
this standard was limited to “5% per month.” Similarly, with
regard to damaged items, the solicitation’s “Performance
Standard” specified that, “[l]aundered items are not physically
damaged due to improper processing or carelessness,” and that
the acceptable deviation from this standard was limited to “2.5%
per month.” RFP at 50-51. The agency concluded that, contrary to
the solicitation’s specified requirements, Stewart’s proposal
effectively provided that virtually every laundered item could
permissibly contain holes and stains--provided the holes were
limited in size and number to the alternative standards that
Stewart identified, and provided the stains were similarly
limited in size and number and/or were sufficiently “light.”
Accordingly, the agency concluded that Stewart’s proposal did
not offer to meet the solicitation’s stated performance
requirements. Stewart complains that the agency should
have interpreted the quality standards identified in its
proposal as applying only to the portion of items that the
solicitation permitted to deviate from the stated
requirements--that is, 5 percent per month with regard to
stained items and 2.5 percent per month with regard to damaged
items. However, nothing in its proposal advised the agency
regarding this purported interpretation and intent to comply
with the solicitation’s specified quality standards. Here,
Stewart’s inclusion of quality standards that conflicted with
the solicitation’s stated standards--even if viewed in a light
most favorable to Stewart--created an ambiguity regarding
Stewart’s intention to comply with the RFP’s requirements. Since
the agency selected Balfurd’s proposal for award without
discussions, as contemplated by the solicitation, the agency
properly rejected Stewart’s proposal as technically unacceptable
for failure to clearly meet the solicitation’s stated
requirements. On the record here, we have no basis to question
the agency’s actions. (Stewart
Distributors, B-298975, January 17, 2007) (pdf)
The agency’s rejection of GWI’s proposal was unobjectionable.
DLA explains, citing Defense Federal Acquisition Regulation
Supplement sect. 204.7201, that a CAGE code is a “contractor
identification code” assigned to a contractor’s name and
address, so as to avoid any confusion regarding the entity
identified. Letter from DLA to GAO, Dec. 15, 2006, at 1. CAGE
codes are assigned to discrete business entities for a variety
of purposes (e.g., facility clearances and pre-award surveys) to
dispositively establish the identity of a legal entity for
contractual purposes. See Perini/Jones, Joint Venture, B-285906,
Nov. 1, 2000, 2002 CPD para. 68 at 5. Here, the RFP included a
CAGE code for Dana’s part that identified the manufacturing
entity as “Dana Corp. Spicer Universal Joint Div.,” at an
address in Holland, Ohio. The agency states, and GWI does not
dispute, that GWI’s proposed parts were to be manufactured by [DELTED],
not by Dana’s Spicer Universal Joint Division in Holland, Ohio,
and Dana has advised the agency that it is not aware of any
approved sites to manufacture this part outside the United
States. Agency Motion to Dismiss, exh. 2, at 2. The agency
advises that [DELETED] is not included under the specified CAGE
code; as a foreign entity, it would be assigned a different
code, specifically, a North Atlantic Treaty Organization
commercial and government entity code. Thus, while GWI appears
to be proposing the specified Dana part, the information
subsequently developed by the agency indicates that the part
would be manufactured by [DELETED] that was not contemplated by
the agency’s source approval. We think this was a legitimate and
reasonable basis for the agency’s action here, that is,
rejecting GWI’s proposal as unacceptable. (Gear
Wizzard, Inc., B-298993, January 11, 2007) (pdf)
The record here shows that Prudent failed to follow the detailed
instructions set forth in section M of the RFP requesting
experience information and explaining how that information would
be reviewed. As set forth above, the RFP required offerors to
provide sufficient information to establish that the offeror (or
its key personnel, or its subcontractors) had relevant (“same or
similar”) experience within the past 3 years; to make this
showing, offerors were asked to identify up to five contracts
for review by the agency. For these five contracts, offerors
were to describe “the type and quantity of service provided, the
value of those services, the contract award date, the contract
completion date, and the name and title, address, telephone
number, fax number, and email address (if available) of a person
familiar with the offeror’s performance.” RFP at M-3. Although
Prudent’s proposal broadly claims to meet the RFP’s experience
requirements in a brief two-paragraph discussion titled
"Experience and Past Performance," Agency Report (AR), Tab 7, at
15, there is no place in its proposal where it provides the
information requested by the RFP so that HUD evaluators could
verify for themselves whether the company meets the experience
requirement. Specifically, there is also no place in the
proposal where Prudent identifies five contracts for review by
the agency; there is no description of any kind about the work
performed; and there is no indication of when the relevant work
might have occurred. At best, the proposal identifies seven
entities as references--two for Prudent, and five others, one
for each of five subcontractors--and provides for each a point
of contact, mailing address, and telephone number. AR, Tab 7, at
18-19. In our view, given the detailed instructions in section M
of the solicitation about the information the agency needed to
make its assessment, these omissions alone provide a reasonable
basis for the agency to conclude that the proposal was
unacceptable. See, e.g., Interstate Gen. Gov’t Contractors,
Inc., B-290137.2, June 21, 2002, 2002 CPD para. 105 at 5 (it is
the responsibility of the offeror to provide sufficient
information about the projects in its proposal to ensure they
will be assessed as relevant). (Prudent
Technologies, Inc., B-297425, January 5, 2006) (pdf)
Nothing in Marine Industries’ proposal establishes that a
company can implement a QA system based on ISO 9001-2000 only as
an upgrade to an existing QA system. Further, Marine Industries
has provided no evidence that implementation of a plan based on
ISO 9001-2000 necessarily implies the existence of a precursor
plan, such that the agency should have evaluated the proposal
based on such an assumption. Accordingly, because the protester
failed to represent that its new QA plan would be in place by
the time of contract award and failed to furnish any description
of an already implemented QA plan, we think that the evaluators
reasonably determined that it had failed to comply with the RFP
requirement for a description of its company QA plan for
certifying completed work. (Marine
Industries NW, B-297207, December 2, 2005) (pdf)
A quotation that fails to conform
to material terms and conditions of the solicitation should be
considered unacceptable and may not form the basis for an award.
CAMS Inc., B-292546, Oct. 14, 2003, 2003 CPD para. 191 at 2; L.S.
Womack Inc., B-244245, Sept. 30, 1991, 91-2 CPD para. 309 at 2.
Material terms of a solicitation are those which affect the
price, quantity, quality, or delivery of the goods or services
offered. Seaboard Elecs. Co., B-237352, Jan. 26, 1990, 90-1 CPD
para. 115 at 3. Here, Muddy Creek’s quotation altered several
material terms of this solicitation. Specifically, Muddy Creek’s
quotation altered the location of deliveries, limited the type
of modified meals available, and added terms regarding the
advance notice of the number of meals to be provided. Since
Muddy Creek’s quotation failed to conform to material terms of
the solicitation, the agency correctly deemed the quotation
unacceptable. As a final matter, we recognize that certain
conversations between Muddy Creek and Bureau employees may have
led the company to expect that it would be awarded a sole-source
contract, and that Muddy Creek apparently thought the RFQ here
was that sole-source contract, and not a competitive
solicitation. Once Muddy Creek received the RFQ, however, the
protester’s continued expectation that it was receiving a
sole-source contract was unreasonable. The solicitation
indicated it was a request for quotations on its face, and it
included a description of the basis for award, which listed the
factors of past performance, ability to meet schedule, price,
and responsiveness. Muddy Creek, therefore, should have realized
the agency was not negotiating a sole-source contract, but was
conducting a competition, and cannot now prevail in its protest
that it was treated unreasonably when the agency rejected its
quotation because of the changes Muddy Creek made to the
material terms and conditions of the solicitation. (Muddy
Creek Oil and Gas, Inc., B-296836, August 9, 2005) (pdf)
Before leaving this topic, we recognize that the agency and
Titan argue that since this was a performance-based procurement
the agency was evaluating technical solutions, not staffing
levels. They also point out, correctly, that there was no
requirement for any particular staffing approach, and that this
means the changes made by Titan in response to the reopened
competition should not be seen as affecting the nature of
Titan's performance-based offer. We cannot agree with this
assertion. The solicitation's evaluation scheme contained a
management/technical evaluation factor which was supposed to
include a review of the evidence of an offeror's technical
proficiency. RFP amend. 3, at 6. In addition the final
memorandum of the source selection evaluation board (SSEB)--which
was based on Titan's earlier technical proposal, since revised
technical proposals were not submitted here--expressed the view
that Titan's approach allowed "[reduced] staffing levels in the
out years while maintaining a highly skilled technical staff."
AR, Tab 23, at 25. Given the changes Titan made to the mix of
technical staff in its final FRP, we are not sure this
observation remains valid for this proposal. In our view, the
situation here is similar to the situation we encountered in
DynaLantic Corp. , supra . In DynaLantic , after originally
making award, but then finding it necessary to terminate that
contract for default, an agency requested an additional round of
best and final offers (BAFO) from the remaining offerors,
limiting them to price and delivery schedule revisions. The
successful offeror in the recompetition included in its revised
BAFO a list of six changes which allowed it to reduce its
earlier price by 48 percent. In our decision, we concluded that
the awardee's reduced price, in fact, reflected changes to its
technical proposal, contrary to the ground rules established for
the submission of revised BAFOs. Here, we think Titan has
essentially done the same thing. In changing the staffing mix of
labor categories overall, and in offering a completely different
staffing approach for off-site work, Titan did not follow the
ground rules set by the agency in this reopened competition. As
a result, offerors that followed the agency's instructions were
placed at a disadvantage, and did not have the same opportunity
to achieve the price reduction Titan was able to achieve. (Resource
Consultants, Inc., B-293073.3; B-293073.5; B-293073.6, June
2, 2004) (pdf)
Gold Cross next asserts that the agency improperly eliminated
its quotation from the competition based on price alone, without
considering the high quality of its technical submission. This
argument is without merit. While the RFQ provided for a best
value evaluation based on comparative technical and price
considerations, the agency also was required to consider whether
the protester's quoted price was too high in an absolute sense.
In this regard, before awarding a fixed-price contract, an
agency is required to determine that the price offered is fair
and reasonable. Federal Acquisition Regulation (FAR) 15.402(a).
Here, the agency states that it rejected Gold Cross's quotation
pursuant to the contracting officer's determination that the
quoted price was so high that award to the firm would not be in
the public interest, no matter the quality of its technical
submission. Contracting Officer's Statement of Facts at 2. This
was tantamount to finding that Gold Cross's price was
unreasonably high. A price reasonableness determination may be
based on various price analysis techniques, including comparison
of prices received among themselves and to an independent
government estimate (IGE). FAR 15.4041(b)(2). A price
reasonableness determination is a matter of administrative
discretion that we will question only where it is clearly
unreasonable or there is a showing of bad faith or fraud. The
Right One Co. , B-290751.8, Dec. 9, 2002, 2002 CPD 214 at 5. The
contracting officer considered the prices received and the IGE,
and concluded that Gold Cross's price was so high--approximately
20 times the awardee's price, 8 times the third vendor's price,
and 10 times the IGE--that award could not be made to the firm.
Given this great disparity in pricing, there was nothing
improper in the contracting officer's determining that Gold
Cross's price was unreasonable and eliminating it from the
competition on this basis. See , e.g. , Rhimco Indus., Inc. ,
B-247600, June 8, 1992, 92 CPD 499 at 2 (a price 42 percent
higher than government estimate constitutes an unreasonable
price). Since Gold Cross could not receive the award due to its
unreasonable price, the results of any technical evaluation the
agency may have subsequently performed were immaterial; even if
Gold Cross's technical submission received the highest possible
rating, it could not receive the award due to its unreasonable
price. Consequently, there was nothing improper in the agency's
failure to evaluate Gold Cross's technical submission. (Gold
Cross Safety Corporation, B-296099, June 13, 2005) (pdf)
In proposing a keyboard that has 107 keys, ITG's proposal failed
to meet the mandatory requirement of the solicitation that the
keyboard have 104 keys, and therefore could not be accepted for
award. See White Storage & Retrieval Sys., Inc. , B-250245, Jan.
19, 1993, 93-1 CPD 70 at 3. Although the agency assigned ITG's
proposal a rating of acceptable under this factor, the record
shows that the agency recognized the proposal's non-compliance
with this solicitation requirement in eliminating its proposal
from the competitive range. (Integration
Technologies Group, Inc., B-295958; B-295958.2, May 13,
2005) (pdf)
We turn then to the protester's argument that it included a
pricing contingency in its proposal and deviated from the
required delivery schedule based on its understanding that the
Navy was seeking an improved CNVD, and that it would have
offered a lesser quality system without the pricing contingency
and delivery schedule deviation if it had been apprised that the
Navy was willing to consider systems that were not an
improvement over its "baseline" CNVD. [8] While the protester
contends that "[i]n order to exceed the performance of the
Baseline unit, OSTI was required to incorporate an expensive
high-performance image intensifier into its device whose cost
and delivery could not be guaranteed by the manufacturer," the
solicitation did not require the protester to incorporate the
particular tube in question into its product. The protester
elected to do so itself. Moreover, even assuming for the sake of
argument that the RFP had required this particular tube and that
the supplier of the tube would not guarantee its price, this did
not require the protester to pass any risk of a price increase
on to the government. Solicitations frequently require offerors
to bear pricing risks, and the bottom line is that where an RFP
requires fixed prices and a proposal does not offer fixed
prices, the proposal as submitted cannot be considered for
award. Georgetown University--Recon. , B-249365.3, June 7, 1993,
93-1 CPD 434 at 5. Similarly, award generally cannot be made on
the basis of a proposal that takes exception to a required
delivery schedule. American Fuel Cell & Coated Fabrics Co. ,
B-293020, Jan. 12, 2004, 2004 CPD 13 at 5. (Optical
Systems Technology, Inc., B-292743.2, November 12, 2004) (pdf)
The agency reasonably rejected TJLs proposal as unacceptable.
One of the factors for which TJLs proposal received a no go
rating was experience building castinplace concrete structures,
under which offerors were to provide documentation of at least
two projects, with no time frame limits, that demonstrate
experience building cast-in-place concrete structures. RFP at
21. In response to this requirement, TJLs proposal stated only
that [TJL] does not self perform the actual cast in place
concrete. However, TJL does perform the excavation and backfill
for the subcontractor for this work. TJL Proposal, Vol.1,3.7.
The proposal made no mention of projects--performed by TJL or a
subcontractor--involving castin-place concrete structures, and
did not include any other information--such as the name of the
subcontractor with which it previously had performed--that might
give the agency further guidance in evaluating the protesters
experience in this area. Given TJLs manifest failure to present
the required information establishing that it possessed the
required experience, the agencys no go rating was reasonable.
(T. J. Lambrecht Construction, Inc.,
B-294425, September 14, 2004) (pdf)
Here, SuccessTech’s proposal failed to meet a material RFP
requirement, and therefore was unacceptable. A firm delivery or
service commencement date set forth in a solicitation is a
material requirement, precluding acceptance of any proposal not
offering to meet that date. Hawaiian Tel. Co., B-187871, May 2,
1977, 77‑1 CPD ¶ 298 at 9. In a negotiated procurement, any
proposal that fails to conform to material terms and conditions
of the solicitation is unacceptable and may not form the basis
for an award. Plessey Elec. Sys. Corp., B‑236494, Sept. 11,
1989, 89-2 CPD ¶ 226 at 2; Telenet Communications Corp.,
B‑224561, Feb. 18, 1987, 87‑1 CPD ¶ 181 at 3. The RFP stated
that the performance period (contract term) “shall be for a
period of 12 months commencing or within 15 days after
notice/date of award.” RFP § F.2. The RFP’s statement of work
provided that within “15 calendar days after award, the
Contractor shall begin work for the Contract period.” RFP §
C.9.b. SuccessTech’s initial startup plan did not include any
identifiable time frames or schedule. When permitted to
supplement its plan in discussions, SuccessTech stated that it
assumed “at least thirty days advanced notice of contract award”
and provided a 30‑day transition schedule leading up to a start
date when transition was to be completed and the firm would
“assume all duties.” Protest attach. 9, at 2-3. Since
SuccessTech’s plan did not call for contract performance to
begin within the required 15 days of award, it could not be
accepted for award. (SuccessTech
Management & Services, B-294174, July 6, 2004) (pdf)
The Federal Acquisition Regulation (FAR) authorizes the
contracting officer to exclude proposals from the competitive
range that are not among the “most highly rated.” FAR §
15.306(c)(1). Further, an agency is not generally required to
include a proposal in the competitive range when, in order to be
selected for award, the offeror would have to essentially
rewrite its entire proposal. See, e.g., Source AV, Inc.,
B-234521, June 20, 1989, 89-1 CPD ¶ 578. Finally, agencies are
not required to retain a proposal in the competitive range
simply to avoid a competitive range of one, since conducting
discussions and requesting final revised proposals from offerors
with no reasonable chance of award would benefit neither the
offerors nor the government. SDS Petroleum Prods., Inc.,
B-280430, Sept. 1, 1998, 98-2 CPD ¶ 59 at 5. (Fiserv
NCSI, Inc., B-293005, January 15, 2004 (pdf)
As indicated above, SOCOM relied upon the tests performed by an
ISO-certified and accredited laboratory testing facility to
conclude that USIA's material did not meet the abrasion
requirement. SOCOM explains that testing of USIA's material was
performed by one of Natick's evaluators, who has a 4-year degree
in textile technology and over 15 years of experience in
performing the test. Although USIA has presented test results
purportedly performed by Thor-Tex's manufacturer showing
compliance with the abrasion requirement, the submitted
documentation is not on its face designated as a test by the
manufacturer and does not identify the product number of the
tested material, and does not reflect that the tests were
performed by an ISO‑certified and accredited laboratory
facility. Thus, the protester has provided no basis to question
the independent tests of the ISO-certified facility. While USIA
argues that the varying test results suggest that the agency may
have mishandled the storage and/or rushed the testing of the
fabric, we find no credible evidence of mishandling or improper
testing by this ISO‑certified facility, to which the offerors
directly delivered their samples. Given the test results, we
find that the agency properly eliminated USIA's proposal from
the competition prior to the full technical proposal evaluation.
(USIA Underwater Equipment Sales
Corporation, B-292827.2, January 30, 2004) (pdf)
DSCC’s argument does not address the problem with Flinchbaugh’s
quotation. To be reasonable, and therefore valid, an
interpretation must be consistent with the solicitation when
read as a whole and in a reasonable manner. Fox Dev. Corp.,
287118.2, Aug. 3, 2001, 2001 CPD ¶ 140 at 2. Here, although it
is true that the RFQ did not expressly preclude the possibility
of subcontracting the packaging, Flinchbaugh’s quotation
provided for both the inspection and acceptance at the packaging
facility, instead of at the actual manufacturing facility as
required by the provisions in section B. The fact that the
solicitation allows multiple inspection points does not mean
that acceptance can be anywhere but at the manufacturing
facility, as required by the RFQ. There is only one “final
acceptance” under a contract for supplies. That is, acceptance
is acknowledgment by the agency that the supplies conform with
applicable contract quality and quantity requirements, and title
to supplies passes to the government upon formal acceptance,
regardless of when or where the government takes physical
possession; this is the point where the government obtains title
to the supplies and assumes the risk of loss. See FAR §§ 46.501,
46.505. Accordingly, compliance with the requirement that
acceptance be at the manufacturing facility was a material term,
which Flinchbaugh’s quotation did not satisfy; thus, an order
could not be issued based on Flinchbaugh’s quotation. See
Rel-Tek Sys., & Design, Inc., supra; Scientific-Atlanta, Inc.,
B-255343.2,B-255343.4, Mar. 14, 1994, 94-1 CPD ¶ 325 at 9.
(CAMS Inc., B-292546, October 14,
2003) (pdf)
By placing language in its proposal which stated that providing
the required capacity was subject to availability, Americom made
both its technical offer and its fixed pricing contingent, in
response to a solicitation which required fixed prices for the
specific proposed technical solution. This is an impermissible
deviation from a material RFP term that renders the proposal
unacceptable and ineligible to form the basis for award. SWR,
Inc., B-284075, B-284075.2, Feb. 16, 2000, 2000 CPD ¶ 43 at 6-7;
Beckman Coulter, B-281030, B-281030.2, Dec. 21, 1998, 99-1 CPD ¶
9 at 6. Americom’s protest characterization of this contingency
as standard language that it was willing to remove from its
proposal is without consequence or legal effect. This
impermissible contingency rendered Americom’s proposal
technically unacceptable and properly subject to elimination
from the competitive range; an agency is under no obligation to
conduct discussions with an offer to permit it to cure the
noncompliance which provided the basis for the proposal’s
exclusion. SOS Interpreting, Ltd., B-287505, June 12, 2001, 2001
CPD ¶ 104 at 12. (Americom
Government Services, Inc., B-292242, August 1, 2003) (pdf)
It is true that Anteon's proposal did not satisfy the minimum
water depth requirement so that the agency essentially waived
the requirement when it concluded that the 1-inch shortfall was
acceptable. Nevertheless, we find no prejudice to the protester
in the agency's actions, as the water depth shortfall was
reasonably determined to be “negligible” and the protester has
not shown how it would have altered its proposal to improve its
competitive standing had it been given an opportunity to respond
to the relaxed requirements. Absent prejudice to the protester,
we deny this ground of protest. See 4-D Neuroimaging,
B-286155.2, B‑286155.3, Oct. 10, 2001, 2001 CPD ¶ 183 at 10-11;
see also Magnaflux Corp., B‑211914, Dec. 20, 1983, 84-1 CPD ¶ 4
at 3-4 (agency permitted to waive deviation from specification
which was minor and did not result in prejudice). (Gulf
Copper Ship Repair, Inc., B-292431, August 27, 2003) (pdf)
An agency is not required to include an offeror in the
competitive range when the proposal, to be acceptable, would
have to be revised to such an extent that it would be tantamount
to a new proposal. Source AV, Inc., B-234521, June 20, 1989,
89-1 CPD ¶ 578. Even where individual deficiencies may be
susceptible to correction through discussions, the aggregate of
many such deficiencies may preclude an agency from making an
intelligent evaluation, and the agency is not required to give
the offeror an opportunity to rewrite its proposal.
Ensign-Bickford Co., B-211790, Apr. 18, 1984, 84-1 CPD ¶ 439.
Accordingly, on the basis of the record here, we find no basis
to question the agency's exclusion of Austin's proposal from the
competitive range. (The
Austin Company, B-291482, January 7, 2003) (txt
version)
While exclusion of technically unacceptable proposals is
frequently permissible, it is not generally required. More
specifically, the significance of the weaknesses and/or
deficiencies in an offeror's proposal, within the context of a
given competition, is a matter for which the procuring agency
is, itself, the most qualified entity to render judgment.
(Albert
Moving & Storage, B-290733; B-290733.2, September 23, 2002)
(txt
version)
We conclude that the agency
reasonably rejected CSWI's proposal. As quoted above, in
describing its proposed program/project manager, CSWI duplicated
the narrative from the RFP for the contract manager position and
inserted a per-hour ceiling labor rate. It is this duplication
of contract manager requirements, plus the insertion of an
hourly rate, that caused CSWI's proposal to be considered, at
best, ambiguous with respect to whether the firm intends to
provide contract management services at no direct cost to the
government in accordance with the terms of the RFP or whether
the firm intends to charge an hourly rate as contained on page
B-69 of its proposal for the required management services. On
this record, where CSWI's intentions are not clear and
unambiguous from the face of its proposal in terms of providing
contract management services at no direct cost to the
government, we have no basis to question the reasonableness of
the agency's rejection of the firm's proposal. (Consolidated
Services Worldwide, Inc., B-290751.7, October 21, 2002)
(pdf)
Further, although SHBS's proposal
identifies more than 20 architects and engineers and includes
their resumes and professional certificates, it fails to specify
which of these personnel will be used to perform the rapid
response design work. Based on SHBS's failure to indicate
which of its professional personnel would perform the design
work, the agency reasonably concluded that its proposal was weak
under the technical capability subfactor.
It was incumbent on the protester
to provide adequate information, beyond mere promises to hire
qualified subcontractors when the need arises, to permit the
agency to evaluate the firm's capability under this element. See
DynCorp Int'l LLC, B‑289863, B‑289863.2, May 13,
2002, 2002 CPD P: 83 at 9. Given SHBS's failure to provide the
required information, the agency reasonably concluded that its
proposal was weak in this area. (Sayed
Hamid Behbehani & Sons, WLL, B-288818.6, September 9,
2002)
Our Office has found no reason to question similar cascading
set-aside preference provisions used by HUD for certain real
estate services. HUD has explained that such an approach
promotes the interests of small business concerns and also
provides the agency with an efficient means to continue the
procurement in the event that sufficient small business
participation is not realized. HUD explains that the cascading
set-aside approach was formulated in conjunction with, and has
been endorsed by, the SBA. See The Urban Group, Inc.; McSwain
and Assocs., Inc., B-281352, B-281353, Jan. 28, 1999, 99-1 CPD ¶
25 at 7. The cascading set-aside preference provision used in
the RFP here reasonably put large businesses on notice that, if
the agency receives a sufficient number of eligible small
business offers, large business proposals received simply would
not be considered for award. See id. As such, the cascading
set-aside preference terms establish, at best, only a potential
for participation of large businesses in the competition for
award. (Carriage
Abstract, Inc., B-290676; B-290676.2, August 15, 2002) (pdf)
The Navy reasonably determined
that G&M's management plan consisted largely of conclusory
statements and lacked supporting documentation. For
example, while acknowledging that its proposal did not expressly
address the management of subcontractors, G&M contends that its
proposal did specify having an International Organization for
Standardization (ISO) 9000 quality program, which includes a
subcontractor management program. Notwithstanding this
claim (which itself was unsupported), it was G&M's
responsibility to demonstrate in its proposal how it intended to
successfully accomplish and manage all PWS requirements; it was
not the agency's obligation during the evaluation process to
fill in the gaps or to perform a “leap of faith.” Since
G&M had the burden of submitting an adequately written proposal,
yet failed to do so, we have no basis to question the
reasonableness of the agency's evaluation. Quality
Elevator Co., Inc., B-271899, Aug. 28, 1996, 96-2 CPD ¶ 89
at 4. (G&M Industries,
B-290354, July 17, 2002)
Our analysis begins with the
premise that an offeror may elect not to charge for a certain
item and if it indicates a commitment to furnish the item in
question, for example, by inserting "$0" in its proposal, its
proposal is compliant. GTSI Corp., B-286979, Mar. 22,
2001, 2001 CPD ¶ 55 at 6; Integrated Protection Sys., Inc.,
B-229985, Jan. 29, 1988, 88-1 CPD ¶ 92 at 2. Here, while under
the terms of the RFP, offerors were requested to insert a
"service fee" for each period of performance, the RFP did not
prohibit a firm from proposing a fee of zero, or even a negative
fee, and such a fee was not inconsistent with the terms of the
RFP. Under N&N's pricing scheme, where the firm inserted on the
RFP schedule a service fee of "$zero" for the base period and a
fee of zero plus an incentive (discount fees/rebates) for the
option periods, the firm committed to provide the required
services for no cost to the government in any of the performance
periods. N&N did not take exception to the RFP requirement to
identify its proposed service fees; rather, N&N elected not to
charge the agency for providing the required services in any of
the performance periods, plus it proposed discount fees/rebates
in the option periods. We have no basis to object to N&N's
pricing scheme. (SatoTravel,
B-287655, July 5, 2001)
The agency maintains that there
was no difference between Petchem's initial proposal and its
final proposal revision in terms of the firm's commitment to
satisfy the RFP's transit speed requirement, especially since
under the predecessor contract, Petchem's vessel was required to
satisfy the same transit speed requirement. Memorandum from CO
to GAO (Mar. 8, 2001). The agency notes that the reference to "@
80%" in Petchem's initial proposal had been inserted by hand to
the vessel characteristic sheet completed by Petchem for the
"Christine S"; the agency viewed the failure of Petchem to add
that handwritten notation to the same sheet in its final
proposal revision and the failure of the agency to include "@
80% rated horsepower" in Petchem's contract as clerical errors.
Here, there is no dispute that the RFP's minimum transit speed
requirement, as quoted above, was material. Although Petchem
stated in its initial proposal that its proposed vessel would
meet this material requirement, in its final proposal revision,
Petchem did not state that its proposed vessel would transit at
9 knots in moderate weather "@ 80% rated horsepower." Since
Petchem's final proposal revision did not satisfy the RFP's
minimum transit speed requirement, the agency's acceptance of
the firm's proposal meant that the agency waived this
requirement for Petchem. The award to Petchem on the basis of
its nonconforming proposal was improper. (Universal
Yacht Services, Inc., B-287071; B-287071.2, April 4, 2001)
Here, it is undisputed that the
solicitation specifically mandated submission of a letter of
intent for any proposed project manager who was not employed by
the offeror at the time the proposal was submitted. Further the
solicitation identified the project manager as the only "key
personnel," and described the role of the project manager as
"essential to the work to be performed." RFP at 20. Clearly, in
light of the essential nature of this position, submission of
the required assurance that a non-employee proposed as project
manager would, in fact, be available to serve as such
constituted a material solicitation requirement. Indeed,
Triumph's ultimate inability to provide the sole "key personnel"
it proposed, and on which its proposal was evaluated,
demonstrates the significance of this requirement. Accordingly,
Triumph's failure to comply with this requirement rendered its
proposal technically unacceptable and, thus, could not form a
valid basis for contract award. (Special
Operations Group, Inc., B-287013; B-287013.2, March 30,
2001)
Where an offeror proposes a
particular individual for a key position with the intention of
removing that individual from the position after an unspecified
transition period under the contract, and the agency relies on
the offeror's representation that the individual will be
performing the work in evaluating its proposal, the agency
reasonably rejected the proposal once the agency learned of the
offeror's actual intent. (S.
C. Myers & Associates, Inc., B-286297, December 20, 2000)
Agency reasonably rejected as
technically unacceptable a proposal that was noncompliant with
material solicitation requirements that proposed service
engineers possess current training certifications issued by
specified equipment manufacturers. (Techseco,
Inc., B-284949, June 19, 2000)
Agency's rejection of the
protester's proposal on a construction project as technically
unacceptable is unobjectionable where the proposal's project
schedule failed to address demobilization, which was reasonably
considered to be a material solicitation requirement; the fact
that neither the protester's nor the awardee's proposals
addressed final inspection does not render the agency's
rejection improper, because final inspection was the agency's
responsibility, so that the offerors' failure to address this
item was immaterial. (Encorp-Samcrete
Joint Venture, B-284171; B-284171.2, March 2, 2000)
Any proposal that does not
conform to material terms and conditions of the RFP should be
considered unacceptable and may not form the basis for an award.
Integrated Sys. Group, B-272336, B-272336.2, Sept. 27, 1996,
96-2 CPD para. 144 at 6. When an agency relaxes its
requirements, either before or after receipt of proposals, it
must issue a written amendment to notify all offerors of the
changed requirements. CNA Indus. Eng'g, Inc., supra, at 4. We
will sustain a protest where an agency, without issuing a
written amendment, relaxes an RFP specification to the
protester's possible prejudice (e.g., where the protester might
have altered its proposal to its competitive advantage had it
been allowed to respond to the relaxed requirements). Id.
(SWR,
Inc., B-284075; B-284075.2, February 16, 2000)
In a negotiated procurement, a
proposal that fails to conform to material solicitation
requirements is technically unacceptable and cannot form the
basis for award. See International Sales Ltd., B-253646, Sept.
7, 1993, 93-2 CPD para. 146 at 2. Here, the record shows that
the protester clearly took exception to material solicitation
requirements, thus rendering its proposal technically
unacceptable. (Wellco
Enterprises, Inc., B-282150, June 4, 1999)
The record indicates that the
agency established the competitive range on the basis that the
three proposals included in the competitive range were
considered the most highly rated proposals and that Spectrum's
proposal was evaluated as unacceptable and therefore not among
the most highly rated proposals. The record shows that at the
time of this evaluation, the TET determined a variety of areas
in Spectrum's proposal that were unacceptable primarily because
of perceived manning shortages. The agency now admits that its
evaluation of Spectrum's proposal that served as the basis for
the competitive range determination was defective because
several of concurrently stated reasons for finding Spectrum's
proposal unacceptable were unsupported, and that only the
security aspect of Spectrum's proposal is now regarded as
unacceptable. None of the proposals included in the competitive
range was found to be technically acceptable, but all were rated
susceptible of being made acceptable (the same rating that was
initially assigned to Spectrum's proposal). Thus, we cannot find
from this record that Spectrum would not have been among the
most highly rated proposals on the procurement, which
contemplated award to the low-priced acceptable offeror. (Spectrum
Sciences & Software, B-280700, November 9, 1998)
Based on our review, we agree
with the protester that the three deficiencies in Nations'
proposal cited by the agency for its elimination from the
competitive range did not provide a reasonable basis to reject
Nations' proposal, as they were either the result of
misevaluation, or readily correctable, or similar to features in
the competitive range proposals. Furthermore, although, as
noted, the agency states that Nations' deficiency under the
staffing sub-subfactor was less important than the other
deficiencies, we find that the contracting officer could not
reasonably conclude that Pulau's staffing approach was better
justified and more detailed than Nations' as the stated basis
for distinguishing the two proposals. (Nations,
Inc., B-280048, August 24, 1998) |