The protester
complains that the Corps did not evaluate its entire proposal in
determining that Outreach failed to identify three relevant
projects for its company experience. Specifically, Outreach
argues that it identified seven projects under the company
experience section of its proposal and informed the Corps that
this experience was detailed in the past performance section of
its proposal. Comments at 8; AR, Tab J, Outreach Proposal at 7.
Outreach also argues that its proposal identified 17 performance
awards that the firm had received for its work, which Outreach
argues demonstrates its relevant experience. Comments at 8.
Finally, the protester complains that both it and employees of
the Corps had attended the annual Association of State
Floodplain Managers Conference in May 2011, from which the
protester contends that the Corps was aware of Outreach's
experience. Id. at 4.
Our Office will review an agency's evaluation and exclusion of a
proposal from the competitive range for reasonableness and
consistency with the solicitation criteria and applicable
statutes and regulations. Int'l Med. Corps, B-403688, Dec. 6,
2010, 2010 CPD para. 292 at 7. Contracting agencies are not
required to retain in the competitive range proposals that are
not among the most highly rated or that the agency otherwise
reasonably concludes have no realistic prospect of being
selected for award. Federal Acquisition Regulation (FAR) sect.
15.306(c)(1); D&J Enters., Inc., B-310442, Dec. 13, 2007, 2008
CPD para. 8 at 2. In this regard, a protester's mere
disagreement with an agency's evaluation and competitive range
judgment does not establish that the agency acted unreasonably.
SPAAN Tech, Inc., B-400406, B‑400406.2, Oct. 28, 2008, 2009 CPD
para. 46 at 9.
Here, as noted above, the Corps found that Outreach's proposal
did not identify three projects that demonstrated the firm's
experience facilitating meetings related to national flood risk
management and levee/dam safety issues. AR, Tab K, Competitive
Range Memorandum, at 6. Although Outreach argues that it
identified seven projects under this section of its proposal,
the record shows that Outreach provided only general information
about the identified projects, noting little more than the
number of meetings it had set up and stating that these meetings
involved flood risk management and dam safety issues. See AR,
Tab J, Outreach Technical Proposal at 4-12. This very limited
information fails to demonstrate, for any of Outreach's
identified seven projects, the firm's experience in facilitating
meetings related to national flood risk management and levee/dam
safety issues. With respect to the protester's argument that the
17 performance awards listed in this section of Outreach's
proposal demonstrates its experience, the proposal does no more
than list a number of awards without supporting detail. See id.
at 4-5. This also does not demonstrate that Outreach has
relevant experience facilitating meetings related to national
flood risk management and levee/dam safety issues.
Outreach states that, although it provided limited information
about its projects in the section of its proposal addressing the
company experience factor, it provided more detailed information
in the section of its proposal addressing the past performance
factor. Comments at 8; see AR, Tab J, Outreach Proposal at 7. In
this regard, Outreach notes that although the RFP established
page limitations for offerors' responses to each evaluation
factor, the solicitation did not prohibit offerors from
cross-referencing sections in responding to the evaluation
factors. Comments at 3-4. Outreach contends that by
cross-referencing detailed information in its response to the
past performance factor, it adequately demonstrated its relevant
experience under the company experience factor. Id.
We disagree. Although the RFP may not have specifically
prohibited cross-referencing, the solicitation specified page
limitations for responses under each evaluation factor. As noted
above, the RFP limited responses to the company experience
factor to 10 pages, and responses to the past performance factor
to 25 pages. See RFP sect. L at 135. Allowing Outreach to
satisfy the requirements of the company experience factor by
referencing other parts of its proposal would improperly
increase the number of pages for addressing company experience,
without allowing other offerors the same opportunity. See North
Wind Inc.; Earth Res. Tech., Inc., B-404880.4 et al., Nov. 4,
2011, 2011 CPD para. at 12 (an agency improperly considered
portions of an awardee's proposal that were outside the
solicitation stated page limitations). It is a fundamental
principle of government procurement that competition must be
conducted on an equal basis; that is, offerors must be treated
equally and be provided with a common basis for the preparation
of their proposals. Electronic Design, Inc., B-279662.2 et al.,
Aug. 31, 1998, 98-2 CPD para. 69 at 10.
In sum, we find reasonable the Corps' determination that the
protester's proposal was technically unacceptable. The record
shows that Outreach failed to demonstrate that it satisfied the
company experience requirements within the page limitations
stated by the RFP. An agency's evaluation is dependent on the
information furnished in a proposal; thus, it is the offeror's
responsibility to submit an adequately written proposal for the
agency to evaluate. SC&A, Inc., B-270160.2, Apr. 10, 1996, 96-1
CPD para. 197 at 5. As we have often said, an offeror that does
not submit an adequately written proposal runs the risk of
having its proposal rejected as unacceptable. L-3 Communications
EOTech, Inc., B‑311453, B‑311453.2, July 14, 2008, 2008 CPD para.
139 at 4. Because Outreach's proposal was not among the most
highly-rated offers, the firm's proposal was reasonably excluded
from the competitive range. (Outreach
Process Partners, LLC, B-405529, November 21,
2011) (pdf)
The protesters
argue that NASA's re-evaluation of Navarro's proposal, and the
new source selection decision, were inconsistent with the stated
requirements of the solicitation. Specifically, the protesters
contend that the agency could not have reasonably determined
that Navarro's proposal, after removal of the 56 pages
containing [basis of estimate] BOE narrative, met the
solicitation's requirement to provide a BOE.
It is a fundamental principle of federal procurement law that a
contracting agency must evaluate all offerors' proposals against
the solicitation's stated evaluation criteria. See, e.g., Source
Diversified, Inc., B-403437.2, Dec. 16, 2010, 2010 CPD para. 297
at 6; Computer Prods., Inc., B-284702, May 24, 2000, 2000 CPD
para. 95 at 4-5. In reviewing protests against allegedly
improper evaluations, our Office examines the record to
determine whether the agency's evaluation was, in fact, in
accord with the stated evaluation factors. Computer Assocs.
Int'l, Inc., B-292077.3 et al., Jan. 22, 2004, 2004 CPD para.
163 at 6.
NASA maintains that it evaluated Navarro's proposal in
accordance with the solicitation criteria and did not consider
the 56-page BOE attachment that was removed as a result of its
initial evaluation, even though the same evaluators that had
viewed the 56 pages conducted the re-evaluation.[10] NASA
contends that it complied with the solicitation's requirements
because Navarro's proposal contained sufficient BOE narrative
within the remaining 50 pages of its mission suitability
proposal for the agency to determine that "[REDACTED], despite
the fact that Navarro did not explicitly state within its
50-page . . . [mission suitability proposal] that it
[REDACTED]." NASA's Post‑Hearing Comments at 1-2; Tr. at 103.
NASA states that its assumption that [REDACTED] was confirmed by
its integrated assessment of the rest of Navarro's proposal
(besides the 50-page mission suitability proposal).
Our review of the record reveals several problems with NASA's
position. First, while it is true that the RFP allowed offerors
to [REDACTED], Tr. at 78, they were nonetheless explicitly
required by section L of the solicitation to provide a BOE. The
BOE was required to include, among other things, "supporting
rationale for all labor resources (FTEs and skill mix) proposed"
to demonstrate that the resources are realistic for the proposed
technical and management approach. RFP at L-19. During the
hearing, NASA's SEB witness testified that the RFP [REDACTED].
Tr. at 79‑80.
The record here shows that both protesters and Navarro provided
BOEs with their initial mission suitability proposals. However,
as Navarro's proposal explained, Navarro did not address the BOE
level of detail within the mission suitability page limit
because it determined that this requirement was "outside of the
page count." AR, Tab 7, Navarro's Mission Suitability Proposal,
at 10.
In addition, during the hearing, the agency conceded that
Navarro's 50-page mission suitability proposal [REDACTED], as
Navarro was required to do if this was its intent. Tr. at 175.
In our view, without such a representation, the agency could not
reasonably conclude that the proposal contained "a discussion
regarding how the proposed FTEs were estimated" as required by
the BOE level of detail. See RFP at L‑19.
Furthermore, even if we accept that Navarro [REDACTED]. The RFP
specified that resources tables "shall agree with" the narrative
discussion (here, how the FTEs were estimated) required for the
BOE labor and non-labor resources. RFP at L-20. Our review of
Navarro's resource tables for task order 1 and task order 2
confirms the protesters' allegations that [REDACTED]. Compare
ERT AR, Tab 7, Navarro Mission Suitability Proposal, attach.,
Task Order 1 Resources Table, and Task Order 2 Resources Table
with RFP at L-26-28; see Tr. at 142-43, 169-70. While NASA
asserts that the differences were relatively minor and that a
review of the totality of the proposal confirms that [REDACTED],
Navarro did not state this, or provide the BOE required by the
RFP, in its 50‑page mission suitability proposal.
As indicated, while stipulating that inclusion of the BOE in the
technical approach section of the mission suitability proposal
was a requirement of the RFP, Tr. at 60, NASA nevertheless
contends that Navarro's proposal provided sufficient narrative
to meet the BOE requirements. In both its agency report, and at
the hearing, NASA provided examples that it contends show
Navarro's compliance with the BOE requirements, and [REDACTED].
We have reviewed of each of NASA's examples, the parties'
arguments, the hearing testimony, and Navarro's proposal; in our
view, Navarro's mission suitability proposal did not comply with
the RFP proposal preparation requirements. Specifically, the
proposal failed to provide adequate "supporting rationale for
all labor resources (FTEs and skill mix) proposed" to
demonstrate that the proposed resources are realistic for the
proposed technical and management approach. See RFP at L-19.
Furthermore, as indicated, Navarro's mission suitability
proposal did not "include a discussion regarding how the
proposed FTEs were estimated." See id. Navarro's mission
suitability proposal also failed to provide any narrative BOE
that explained its understanding of the required non-labor
resources. See id. (North
Wind, Inc.; Earth Resources Technology, Inc., B-404880.4;
B-404880.5; B-404880.6, November 4, 2011) (pdf)
PRA protests the
agency's rejection of its proposal for exceeding the page
limitation. Protest at 1. Specifically, PRA contends that the
subcontractor letter and SOW were supporting documentation for
the cost proposal and should not have been counted against the
page limit. Protest at 2; Comments at 2.
Offerors are required to prepare their proposals in the format
established by the solicitation, including page and other
limitations. Client Network Servs., Inc., B‑297994, April 28,
2006, 2006 CPD para. 79 at 6. If the solicitation provides that
a proposal exceeding a specified page limit will be rejected and
an offeror does not protest those terms, then rejection of a
proposal that exceeds the limit is unobjectionable. See
Macfadden & Assocs., Inc., B-275502, Feb. 27, 1997, 97-1 CPD
para. 88 at 2. In reviewing a protest against an agency's
evaluation of proposals, our Office will not reevaluate
proposals, but instead will examine the record to determine
whether the agency's judgment was reasonable and consistent with
the stated evaluation criteria and applicable procurement
statutes and regulations. Shumaker Trucking & Excavating
Contractors, Inc., B-290732, Sept. 25, 2002, 2002 CPD para. 169
at 3. A protester's mere disagreement with the agency's judgment
in its evaluation does not establish that the evaluation was
unreasonable. VT Griffin Servs., Inc., B-299869.2, Nov. 10,
2008, 2008 CPD para. 219 at 4.
First, PRA argues that the solicitation required offerors to
provide "detailed substantiation" of proposed subcontractor
costs. Protest at 2; Solicitation sect. 3.5.c(6). The protester
argues that the subcontractor SOW was a "cost substantiation,"
which was intended to enable the agency to understand the
proposed costs for the subcontractor. Comments at 4, citing
Solicitation sect. 3.5.c(6).
The Army contends that the subcontractor cover letter and SOW
related to the work to be performed by the subcontractor, rather
than a substantiation of the costs of performance. To the extent
that the protester contends that the solicitation required
"substantiation" of subcontractor costs in the form of technical
approach information, the agency notes that the solicitation
advised offerors that the level of detail for subcontractor
costs must be the same as that provided for the prime
contractor. AR at 7, citing Solicitation sect. 3.5.c(6). The
agency further notes that PRA did not provide details concerning
its own technical approach in its cost proposal, thus
undercutting the protester's interpretation that the
solicitation required subcontractor costs to be supported by
technical approach information in the cost proposal. AR at 7.
We think that the agency's conclusion was reasonable. The
solicitation did not state, as the protester contends, that
offerors were required or permitted to include technical
approach information in their cost proposals. See Comments at 2.
Consistent with the solicitation, all such information should
have been part of the technical proposal. Solicitation sect.
3.5.b(3)(1). Neither the subcontractor's cover letter nor the
SOW itself discuss the subcontractor's costs or how the
subcontractor plans to use the requested funds. See AR, Tab 4,
PRA Proposal, at 22-23; Solicitation sect. 3.5.c(6). Instead,
PRA separately provided details concerning the subcontractor's
proposed costs in the "Proposal Pricing Sheet." AR, Tab 4, PRA
Proposal, at 24. On this record, we conclude that the agency
reasonably found the cover letter and subcontractor SOW to be
part of the technical proposal.
Next, PRA argues that the "mere brevity" of the subcontractor
SOW is evidence that the page was not meant to provide "any
technical substance." Comments at 3, 4. Regardless of the
protester's intentions in submitting this information, the
record shows that the subcontractor SOW described the work
related to the tasks to be performed. For this reason, we do not
think that the protester's representations concerning its
intended purpose for the subcontractor SOW demonstrate that the
agency unreasonably found that the pages counted toward PRA's
technical proposal.
Finally, PRA argues that, in connection with other Army SBIR
solicitations, it has submitted similar subcontractor
information as part of its cost proposal, and that the Army did
not reject those proposals. Protest at 2; Comments at 3. For
this reason, the protester contends that the agency should not
have deviated from its prior practice. Even if the protester is
correct that the agency had not previously rejected other PRA
proposals that included similar subcontractor information--a
point not substantiated by the protester--we find no merit to
this argument. As our Office has long held, each federal
procurement stands on its own, and an agency's prior practices,
if independently reasonable, are not rendered improper by the
fact that the agency might have viewed a prior proposal
differently. See e.g., Gonzales-McCaulley Inv. Group, Inc.,
B-402544, May 28, 2010, 2010 para. 127 at 3 n.4; FR
Countermeasures, Inc., B-295375, Feb. 10, 2005, 2005 CPD para.
52 at 8.
In sum, we conclude that the agency reasonably found that the
subcontractor cover letter and SOW were part of PRA's technical
proposal, rather than its cost proposal. Thus, consistent with
the terms of the solicitation, the agency counted these pages
toward the technical proposal page limit. Because these two
pages resulted in the protester's proposal exceeding the
solicitation's 20-page limit, the agency reasonably rejected
PRA's proposal. (Propagation
Research Associates, Inc., B-405362, October 20, 2011)
(pdf)
F&S argues that
its proposal was acceptable, and therefore should have been
included in the competitive range. In particular, F&S argues
that its proposal complied with the 48-hour readiness
requirement, and that in any event it was improper for FEMA to
exclude F&S's proposal from the competitive range without
considering its price. Protest at 10-13. In two supplemental
protests, F&S challenges the geographic eligibility of the
awardee, JESCO Company, Supplemental Protest at 6-13, argues
that FEMA ignored favorable past performance of F&S, and argues
that F&S was treated unfairly compared to other offerors.
Comments & Second Supplemental Protest at 17‑23.
As explained below, we conclude that FEMA reasonably rated F&S's
proposal unacceptable based on its failure to comply with the
48-hour readiness requirement. We therefore conclude that FEMA
reasonably rejected F&S's proposal, rendering F&S's remaining
arguments regarding its evaluation, and the agency's ultimate
award, immaterial.
F&S first argues that its proposal met the 48-hour readiness
requirement. F&S points out that its proposal expressly
mentioned the availability of "qualified personnel" in five
Alabama locales, and "additional personnel . . . 'On-Call' and
ready to depart within [24] hours of award notification."
Comments & Second Supplemental Protest at 11. F&S argues that
the FEMA evaluators ignored or misinterpreted these statements
in its proposal, id. at 11-12, while improperly focusing on the
elements of the phase-in plan that reflected longer timelines.
Id. at 13.
FEMA does not dispute that F&S's proposal mentioned personnel in
position or ready to depart within 24 hours. Nevertheless FEMA
argues that F&S's proposal did not place the phase-in tasks in a
clear time-frame or otherwise provide that F&S was prepared to
begin performing contract maintenance services within 48 hours
after award. AR at 8-9. Rather, FEMA argues that F&S's phase-in
plan focused on the firm's internal planning for performance,
which included determining personnel requirements and hiring or
subcontracting, all of which were keyed to a FEMA‑hosted
kick-off meeting--that the agency describes as "nonexistent." AR
at 9. Ultimately FEMA argues that F&S's proposal failed to
provide any clear commitment to provide the required maintenance
activities throughout the contract performance
period--particularly by beginning such services within 48 hours
of award. Id. FEMA also notes that F&S's proposal lacked a
timeline with key dates (requested by the RFP), which could have
shown when F&S intended to begin performing THU maintenance. Id.
at 14‑15. Accordingly, FEMA maintains that its evaluation was
reasonable and that it properly rated F&S's proposal as
technically unacceptable. AR at 16.
We find FEMA's position reasonable. It is an offeror's
responsibility to submit a well-written proposal, with
adequately detailed information to clearly demonstrate
compliance with the solicitation requirements, to allow a
meaningful review by the procuring agency. CACI Techs., Inc.,
B-296946, Oct. 27, 2005, 2005 CPD para. 198 at 5. In this
regard, an offeror must affirmatively demonstrate the merits of
its proposal and risks the rejection of its proposal if it fails
to do so. HDL Research Lab, Inc., B‑294959, Dec. 21, 2004, 2005
CPD para. 8 at 5.
The phase-in plan submitted by F&S, as described above,
identifies two periods--the earlier of which, "project
mobilization," was described as taking place in a 72-hour period
measured from a kick-off meeting that the agency had not
committed to conduct. The tasks related to this "project
mobilization" phase were described as providing plans and making
decisions for performance (including hiring and subcontracting)
that were internal to F&S. Additionally, the second "project
alignment" period in the first 30 days involved F&S meeting with
its staff, transferring functions to itself, and assigning
technicians to newly created service zones. We agree with FEMA
that F&S's proposal did not provide any clear statement that the
firm would meet the 48-hour readiness requirement; rather, the
phase-in plan suggested that F&S would take significantly longer
than 48 hours after award to have staff in place to begin actual
performance of the required maintenance services. Based on this
record, FEMA's rating of F&S's proposal as unacceptable was
reasonable. (F&S Environmental,
LLC, B-405232; B-405232.2; B-405232.3, September 22, 2011)
(pdf)
GEA protests the
agency's rejection of its proposal for exceeding the page
limitation. Protest at 3. GEA contends that the additional
proposal pages were the result of unclear solicitation
instructions and a "partially defective" SBIR submission
website. Protest at 2; Comments, Aug. 21, 2011, at 1.
Offerors are required to prepare their proposals in the format
established by the solicitation, including page and other
limitations. Client Network Servs., Inc., B‑297994, April 28,
2006, 2006 CPD para. 79 at 6. If the solicitation provides that
a proposal exceeding a specified page limit will be rejected and
an offeror does not protest those terms, then rejection of a
proposal that exceeds the limit is unobjectionable. See
Macfadden & Assocs., Inc., B-275502, Feb. 27, 1997, 97-1 CPD
para. 88 at 2.
Here, the solicitation's terms regarding the cover sheets and
the company commercialization report were unambiguous. Contrary
to the protester's assertion that "[n]owhere in the instructions
does it say that a signature is not required on the form,"
Comments, Aug. 21, 2011, at 1, the solicitation and cover sheets
clearly stated that signatures were not required at the time
offerors submitted proposals. Solicitation at sect. 6.1; AR, exh.
9, DOD SBIR FY11.2 Forensic, at 1-2; see AR, exh. 2, GEA
Proposal, at 2 of 2. The protester also ignored explicit
solicitation instructions warning offerors not to duplicate the
electronically-generated cover sheets, and that duplicated cover
sheets would count against the page limit. AR, exh. 7, Army SBIR
Proposal Submission Instructions, at 1, 9; see Solicitation at
sections 3.2, 3.4.
Additionally, with regard to the company commercialization
report section, the solicitation permitted offerors to include
additional explanation at the end of the
electronically-generated report. Solicitation at sect. 3.5.d.
However, uploading documents for the report was neither
authorized by the solicitation, nor provided for in the relevant
section of the website. See AR, exh. 9, DOD SBIR FY11.2
Forensic, at 2.
In sum, the protester has not presented any evidence to
substantiate that the website was defective. See Protest at 1.
Instead, the record shows that the protester disregarded clear
solicitation instructions when it duplicated the cover sheets
and uploaded documents to support its company commercialization
report. As a result, the agency appropriately counted the
duplicate cover sheets and two-page brochure against GEA's
proposal's page count. Because the inclusion of these extra
pages resulted in the protester's proposal exceeding the
solicitation's 20-page limit, the agency properly rejected GEA's
proposal. (GEA Engineering, P.C.,
B-405318, October 13, 2011) (pdf)
The agency
provided each offeror with discussion questions and requested
final revised proposals (FPR). As discussed in greater detail
below, offerors were instructed to provide an FPR that addressed
the agency's discussion questions. The request for FPRs stated
that the original 30-page limit for technical proposals had been
increased to 35 pages. AR, Tab 10, Request for DPK FPR, at 4.
Offerors were also required to provide a letter to "accompan[y]"
the FPR that "outlines" the offeror's response to the agency's
discussion questions. AR, Tab 10, Agency Email Forwarding
Request for DPK FPR, at 1 (July 16, 2010).
AID provided discussion questions
for DPK that identified weaknesses under the technical approach,
staffing and key personnel, and management approach factors,
including, as relevant here, notice that three of its proposed
key personnel did not meet the solicitation requirements. DPK
submitted an FPR that consisted of a 49‑page cover letter, a
35-page technical proposal, and several appendices; DPK's
specific responses to the agency's discussion questions were
contained in its cover letter, rather than in its revised
technical proposal. Chemonics also submitted a cover letter,
revised technical proposal, and appendices.
The agency did not evaluate the detailed responses to the
discussion questions contained in DPK's 49-page cover letter.
AR, Tab 19, Revised Technical Evaluation, at 2. In this regard,
the agency concluded that the protester's approach of addressing
the discussion questions outside of its 35-page technical
proposal did not comply with the instructions in the request for
FPRs, and that evaluation of this information would result in an
"unfair competitive advantage" for DPK. Id. In contrast, the
agency concluded that Chemonics' proposal complied with the
request for FPR instructions, and evaluated the entirety of its
FPR.
(table and
section deleted)
The RFTOP [request
for task order proposals] required offerors to submit its
technical proposal with a limit of 30 pages. Offerors were also
permitted to submit appendices to their technical proposal that
addressed certain RFTOP requirements, such as key personnel
resumes and letters of commitment, and past performance
information; these appendices were not subject to a page
limitation. RFTOP sect. L.5 at 59. The request for FPRs
instructed offerors to address the discussion questions by
revising their technical proposals as follows:
Addressing these
technical weaknesses and/or deficiencies will require a
significant revision of the proposal. This revision may also
directly result in major changes to the cost proposal.
The [FPR] should
clarify and document DPK's understandings of both the
technical proposal and the cost/business proposal. Please make
sure that your responses to USAID's comments and
clarifications are complete yet concise.
* * * * *
The FPR should
not exceed thirty-five (35) pages, exclusive of annexes and
other pages not subject to this page limitation as specified
in Section L of the subject RFTOP.
AR, Tab 10,
Request for DPK FPR, at 4. In addition to these instructions,
the email transmitting the discussion questions and request for
FPRs stated that the revised proposals "should be accompanied
with a letter that outlines DPK's response to USAID's"
discussion questions. AR, Tab 10, Agency Email Forwarding DPK
FPR, at 1.
As discussed above, DPK's FPR consisted of a 49-page cover
letter, a 35-page revised technical proposal, and a number of
additional appendices. Rather than specifically addressing the
agency's discussion questions in its revised technical proposal,
DPK addressed these questions in the cover letter. Chemonics'
response included a 15‑page cover letter, a 35-page revised
technical proposal, and a number of appendices.
AID reviewed DPK's revised technical proposal and noted that the
protester had addressed some concerns regarding its technical
approach. AR, Tab 19, Revised Technical Evaluation, at 2. The
agency concluded, however, that the protester's revised proposal
did not address other concerns identified during discussions,
including the experience of its proposed key personnel. With
regard to DPK's cover letter, the agency noted that it contained
"additional information on key personnel, management capacity,
sub-partner relationship, and other matters (including
alternative candidates for three positions)," but stated that
this information "was not evaluated as it would have constituted
an unfair competitive advantage over the 35‑page limit for the
FPR." Id. In this regard, the agency notes that the solicitation
specifically instructed offerors that although offerors were
allowed to use appendices for information, such as resumes and
performance information, "[a]ll critical information from
appendices must be summarized in the technical proposal." See
RFTOP sect. L.5.b at 59.
DPK argues that AID unreasonably failed to evaluate the
responses to discussion questions contained in the cover letter
to the protester's revised proposal. Specifically, the protester
argues that the instructions to the request for revised
proposals instructed offerors to respond to the discussion
questions, and that the cover letter did not have a page limit.
In our view, the request for revised proposals did not instruct
offerors to "respond" to the discussion questions in the cover
letter. Instead, the instructions explained that "[a]ddressing
these technical weaknesses and/or deficiencies will require a
significant revision of the proposal," AR, Tab 10, Request for
DPK Final Proposal Revisions, at 4, and that the revised
proposals "should be accompanied with a letter that outlines
DPK's response to USAID's" discussion questions. AR, Tab 10,
Agency Email Forwarding DPK FPR, at 1. (emphasis added).
Although the protester repeatedly argues that offerors were
instructed to "respond" to the discussion questions in the
letter, see Supp. Protest at 4, Protester's Supp. Comments at
4-5, the instructions make clear that an offeror was required to
revise its technical proposals to account for the agency's
discussions, and could only "outline[]" its response to the
discussion questions in the "accompany[ing]" letter. Because the
protester chose to include its detailed responses to the
discussion questions in its 49-page cover letter, rather than in
its 35-page revised proposal, we think that the agency
reasonably excluded consideration of DPK's responses that were
not otherwise contained in its revised proposal. (DPK
Consulting, B-404042; B-404042.2, December 29, 2010) (pdf)
The agency
advised Adelaide in its debriefing that, while its corporate
experience was a strength, its technical proposal did not
provide sufficient details regarding its management approach,
did not include a proposed schedule, and did not provide an
adequate staffing plan. Adelaide challenges the evaluation in
this regard.
Our Office reviews challenges to an agency's technical
evaluation to determine whether the agency acted reasonably and
in accord with the solicitation's evaluation criteria and
applicable procurement statutes and regulations. Integrate,
Inc., B-296526, Aug. 4, 2005, 2005 CPD para. 154 at 3. Here, we
find that the technical evaluation was reasonable.
Adelaide has furnished no basis to question the agency's
determination that its management plan lacked adequate detail to
evaluate the likelihood of successful performance. In this
regard, the RFQ provided as follows:
Management Approach: At a minimum, the offeror should develop
a plan showing an understanding of the tasks to be covered and
the schedule for the required services. The plan should show
how the work will be managed to ensure the success of the
contract from a professional, cost and time perspective and
should include a staff plan that among other items shows
availability of staff and subcontractors to complete
multi-tasked jobs.
RFQ at 3.
Adelaide notes that in describing its corporate experience, it
listed in its proposal the various tasks performed under four
prior VA contracts for asbestos surveys. The solicitation here,
however, required vendors to furnish a "'plan . . . show[ing]
how the work will be managed to ensure the success of the
contract." Id. Simply listing tasks completed under prior
contracts does not describe a plan for successful performance.
Likewise, while Adelaide points to a flow chart in its proposal
identifying the stages in the required work‑‑"'Need Identified
and Project Manager Assigned"; "'Work Request Received by
Environmental Consultant"; "'Brewster Office"; "'Team/Client
Pre-job Briefing and Planning"; "'Data Gathered Analyzed";
"'Detailed Reporting"‑‑we find reasonable the agency's position
that simply identifying a few general stages in the work,
without including any narrative describing each stage, did not
furnish an adequate basis for the agency to evaluate its
management approach. Further, while Adelaide furnished a generic
Quality Assurance and Quality Control Manual, the agency
reasonably determined that the manual did not constitute a
detailed, overall management approach to performing the specific
required work under this solicitation. Furthermore, while
Adelaide entered in the solicitation schedule a completion date
for each VA facility, we disagree with the protester that this
shows the agency was unreasonable in downgrading its proposal
for lack of a performance schedule. Rather, we find reasonable
the agency's position that an overall completion date for each
VA facility is not the sort of detailed, task-by-task schedule
that was to be furnished under the management approach subfactor
and which was necessary in order to evaluate the vendor's
likelihood of successful, timely performance.
Regarding the staffing plan, Adelaide notes that it identified
in its proposal its president/contract administrator, senior
vice president/program manager, director of technical and field
operations/field supervisor, and an industrial hygienist.
Adelaide Proposal at 9-13. In contrast, however, the awardee
identified in its proposal its proposed project manager,
assistant project manager, quality manager, a number of lead
industrial hygienists, and a number of industrial hygienists.
Furthermore, the awardee also indicated in its proposal its
staffing approach for each stage of performance. Aerosol
Proposal at 2-3, 7, 14-22. In these circumstances, we conclude
that the agency reasonably viewed the protester's staffing
approach as less detailed, and less likely to result in
successful performance than the awardee's.
Having considered all of Adelaide's challenges to the
evaluation, we find that none furnish a basis for questioning
the issuance of a task order to Aerosol.
The protest is denied. (Adelaide
Environmental Health Associates, Inc., B-404164, January 13,
2011) (pdf)
The agency
received nine quotations by the September 20 closing date for
the receipt of quotations, including four quotations from
HUBZone small businesses. In accordance with the cascading
set‑aside procedures established by the RFQ, only the four
quotations from HUBZone vendors were considered for selection.
Of these four quotations, 1-A Construction & Fire's was the
lowest-priced (at $19,950). The agency, however, rejected the
protester's quotation. The evaluators found that the protester's
quotation identified limited reservoir experience for the firm
and provided limited information about that experience. The
evaluators also found that 1-A's limited response under the
benefit to the local community factor, which stated only that
the reservoir project would provide water sources for cows and
all other wildlife, was insufficient to explain how the firm
planned to benefit the local area. The agency selected Hayden
Brothers for the task order at that firm's quoted price of
$42,680. After learning of the agency's decision, 1-A filed this
protest.
In its protest, 1-A contends, among other things, that the
agency unreasonably concluded that its quotation was
unacceptable under the benefit to the local community evaluation
factor; 1-A contends it was sufficient for the firm to have
noted in its quotation that the pond project will provide water
for cows and wildlife. 1-A suggests, in its comments submitted
in response to the agency's report on the protest, that the pond
project's benefits in providing water to local wildlife will
ultimately benefit the community, by supporting, among other
things, hunters who, in turn, will spend money in the county.
In reviewing a protest against the propriety of an evaluation,
it is not our function to independently evaluate proposals and
substitute our judgment for that of the contracting activity.
Barents Group, L.L.C., B-276082, B-276082.2, May 9, 1997, 97-1
CPD para. 164 at 6. Rather, we will review an evaluation to
ensure that it was reasonable and consistent with the evaluation
criteria in the solicitation and applicable procurement statutes
and regulations; a protester's mere disagreement with the
evaluation does not show it lacked a reasonable basis. Id. On
the record here, we see no basis to question the evaluation of
the protester's quotation or the source selection decision.
Here, the RFQ specifically instructed vendors to address how
they planned to benefit the local community in carrying out the
project, for example, through local hiring, local equipment
rentals, and the use of local housing and meal facilities. To
the extent 1-A generally noted that the reservoir project itself
would provide a benefit, since it would serve as a water source
for cows and wildlife, 1‑A's response was not meaningful, since
the RFQ clearly required vendors to establish how their own
planned activities in performance of the project would provide a
direct economic benefit to the local community. Given 1-A's
failure to adequately address this fundamental solicitation
requirement, the agency acted reasonably in finding 1‑A's
quotation unacceptable under the benefit to the local community
evaluation factor, which provided a reasonable basis for the
agency's rejection of 1-A's quotation.
The protest is denied. (1-A
Construction & Fire, LLP, B-404128, January 7, 2011) (pdf)
Tetra Tech argues
that it submitted a subcontracting plan, and that the plan's
disappearance is the Navy's responsibility. Tetra Tech submitted
sworn statements from its employees, explaining that they made
multiple checks of the proposal before submitting it, to ensure
that all parts of the proposal were present. Protest, exh. A,
Affidavit of Proposal Manager, at 1-2; exh. B, Affidavit of
Contract Administrator, at 1. Additionally, Tetra Tech maintains
that a copy of the proposal retained for the firm's own files
does contain the subcontracting plan, which, the protester
contends, means the plan was also present in the original
proposal and the copies submitted to the Navy. Id. at 2.
Accordingly, Tetra Tech argues that if the subcontracting plan
was no longer with the proposal when the Navy began its
evaluation, the Navy lost it.
In response, the Navy denies losing the subcontracting plan and
asserts that Tetra Tech's proposal did not include it. The Navy
has provided a statement from the contract specialist who
received the proposal, delivered the technical proposal volumes
to the evaluation panel, and opened the price proposal volumes.
The contract specialist reports that when he opened Tetra Tech's
price proposal, he found no subcontracting plan in either the
original or copy provided to the agency. AR, Tab 10, Statement
of Contract Specialist, at 2. The contract specialist brought
Tetra Tech's technical and price proposal to the contracting
officer, who verified that the subcontracting plan was not
contained in either the technical or price proposals. Id. The
contract specialist also checked his office, where the other
offerors' subcontracting plans were located, and Tetra Tech's
plan was not there. Id. The Navy argues that Tetra Tech's
proposal submission did not contain a subcontracting plan, and
therefore the Navy properly assigned a deficiency and rated the
proposal poor under the subcontracting plan factor, which
renders the proposal ineligible for award.
In its comments in response to the agency report, Tetra Tech
argues that not only have its employees sworn that the plan was
submitted with the proposal, the contemporaneous record
acknowledges that the proposal contained a subcontracting plan
section. Specifically, Tetra Tech points out that the Navy's
evaluation report states that "[a]ll proposals were received on
time" and were "reviewed for compliance with the RFP submission
requirements." Protester's Comments at 7 (quoting AR, Tab 8,
Source Selection Evaluation Report, at 4). According to the
protester, this statement means that no proposal--and
specifically, Tetra Tech's proposal--was missing any
information.[4] Tetra Tech also argues that the Navy's efforts
to ensure that the subcontracting plan had not been mislaid
actually demonstrate that the plan was lost by the Navy; that
is, if the Navy had not lost Tetra Tech's subcontracting plan,
it would not have needed to search for it. Protester's Comments
at 7 n.6. Neither of these arguments is persuasive evidence that
Tetra Tech submitted a subcontracting plan with its proposal,
but that the Navy lost it.
An offeror bears the burden of submitting an adequately written
proposal and it runs the risk that its proposal will be
evaluated unfavorably where it fails to do so. Beck's Spray Serv.,
Inc., B-299816, Aug. 9, 2007, 2007 CPD para. 149 at 3. Although
Tetra Tech argues that the Navy lost the firm's subcontracting
plan, the protester has not convincingly established that the
subcontracting plan was included with the submitted proposal.
Furthermore, the record demonstrates that, upon receipt of the
protester's proposal, the Navy handled the proposal with
appropriate care, noticed that the subcontracting plan was
missing when the evaluation began, and used diligence to confirm
that the plan had not been mislaid by the Navy or misfiled in
the other proposal materials. Based on this record, we find
reasonable the agency's conclusion that Tetra Tech had not
submitted a subcontracting plan with its proposal, and the
agency's assignment of a deficiency and poor rating to the
proposal under the subcontracting plan factor as a result. See
Nevada Real Estate Servs., Inc., B‑293105, Feb. 3, 2004, 2004
CPD para. 36 at 4 (even though protester claimed agency had lost
the missing proposal contents, proposal was reasonably found
unacceptable).
In addition, Tetra Tech argues that the Navy should have
informed Tetra Tech that the subcontracting plan was missing,
and should have allowed the firm to submit the plan as a
clarification or through discussions.
Clarifications are limited exchanges with an offeror that
agencies may use to allow the firm to clarify certain aspects of
its proposal or resolve minor or clerical mistakes, while
discussions are undertaken with the intent of allowing the
offeror to revise its proposal. FAR sect. 15.306(a), (d). The
submission of a proposal section, omitted entirely from the
initial proposal, the content of which was required for
evaluation, could not have been resolved as a clarification and
would have constituted discussions. Environmental Quality Mgmt.,
Inc., B-402247.2, Mar. 9, 2010, 2010 CPD para. 75 at 5. However,
the Navy was not required to hold discussions simply because
Tetra Tech needed to correct a material omission from its
proposal. Kiewit Louisiana Co., B‑403736, Oct. 14, 2010, 2010
CPD para. 243 at 4. Accordingly, the protester's argument does
not provide a basis to sustain this protest. (Tetra
Tech Tesoro, Inc., B-403797, December 14, 2010) (pdf)
TechStart
provided an explanatory letter and product literature with its
quotation to demonstrate the claimed equivalence of the IPCallCo
system. In reviewing the quotation, the agency found that the
product literature did not indicate whether strobe and Bluestar
locator light assemblies were included in the IPCallCo system.
Nor did Techstart indicate whether the assemblies were included
in its quoted price. The agency also discovered that, while the
quotation stated that it was priced FOB Destination, its price
schedule listed shipping and handling charges. Further, the
payment terms of TechStart's quotation required a 25 percent
initial deposit, which the contracting officer concluded the
agency could not properly pay.
Rather than reject TechStart's quotation immediately, according
to the agency, the contracting officer made several attempts to
contact TechStart for clarification. The agency states that
after phone calls made to TechStart on July 22 and July 23 were
not returned, the contracting officer contacted IPCallCo
directly, and was informed that strobe and Bluestar locator
light assemblies were an available option on IPCallCo call
boxes. The agency further states that the contracting officer
then attempted to contact TechStart via email on July 27, using
an email address previously used successfully to contact the
firm. The record shows that in this email the contracting
officer sought to confirm that the strobe and Bluestar locator
light assemblies were included in the quotation at no extra
charge, that the shipping and handling charges would be
eliminated, and that the 25 percent deposit provision would be
removed. The email requested a response by July 28.
When no response was received by July 29, the contracting
officer determined that TechStart's quotation was ambiguous and
not responsive to the RFQ, and that the award should be made to
ITA. The award notice was posted on August 2. This protest
followed on August 6.
TechStart asserts that the alleged ambiguities in its quotation
were insignificant, and that a reasonable review of the
quotation should have led the contracting officer to regard the
issues as minor discrepancies. TechStart argues that, even
including shipping and handling charges, its quotation was
significantly lower in price than the awardee's, that the
contracting officer should have realized that the deposit
requirement was not applicable to a federal customer, and that
the issue of the strobe and Bluestar locator light assemblies
was resolved through the contracting officer's communication
with IPCallCo. TechStart also alleges that it did not receive
telephone calls or messages from the contracting officer on July
22 or 23, and did not receive the contracting officer's July 27
email.
We have reviewed the record here and agree with the contracting
officer's conclusion that TechStart's quotation was unacceptable
under the RFQ. Even considering the contracting officer's
conversation with IPCallCo, the contracting officer could not
determine whether TechStart had included the cost of the strobe
and Bluestar locator light assemblies in its quotation, or
whether the shipping and handling charges stated in the price
schedule applied. Additionally, the payment terms set forth in
Techstart's quotation explicitly stated that a 25 percent
deposit was required, which the agency could not properly pay.
See Federal Acquisition Regulation sect. 32.202-2 (an agency may
not pay more than 15 percent of the contract price as a
pre-performance deposit in a commercial item purchase).
With regard to TechStart's argument that it did not receive the
July 22 and 23 telephone calls placed by the contracting
officer, or the email sent on July 27, we note that the
contracting officer had no obligation to seek to resolve the
issues with TechStart's quotation. Rather, it is the vendor's
responsibility to submit a well-written quotation, with
adequately detailed information, that clearly demonstrates
compliance with the solicitation requirements. Domain Name
Alliance Registry, B-310803.2, Aug. 18, 2008, 2008 CPD para. 168
at 10. Here, at the time the contracting officer determined to
make the award, on July 29, TechStart's quotation remained
ambiguous as to whether the strobe and Bluestar locator light
assemblies were included and whether the shipping and handling
charges applied, and required a 25 percent pre-performance
deposit that the agency was not authorized to pay. Under these
circumstances, the contracting officer properly concluded that
TechStart's quotation was unacceptable and that award should be
made to ITA. (TechStart, LLC,
B-403515, November 10, 2010) (pdf)
MCSI asserts that
it submitted the required experience/past performance data
sheets, and that its proposal was improperly evaluated by GSA
under the experience evaluation factor. The agency acknowledges
that MCSI submitted five experience/past performance data
sheets, but, as noted above, argues that in four cases the data
sheets failed to demonstrate that the referenced projects
included grounds maintenance responsibilities, and therefore did
not meet the solicitation's definition of "Similar Work" as
required for evaluation under the experience factor. We agree.
The evaluation of proposals is a matter within the discretion of
the contracting agency. In reviewing an agency's evaluation, we
will not reevaluate proposals; instead, we will examine the
agency's evaluation to ensure that it was reasonable and
consistent with the solicitation's stated evaluation criteria
and applicable procurement laws and regulations. MAR, Inc.,
B-246889, Apr. 14, 1992, 92-1 CPD para. 367 at 4. An offeror's
mere disagreement with the agency's evaluation does not render
the evaluation unreasonable. McDonnell Douglas Corp.,
B-259694.2, B-259694.3, June 16, 1995, 95-2 CPD para. 51 at 18.
As stated above, the solicitation required offerors to
demonstrate experience in performing similar work, and defined
similar work as projects including grounds maintenance services.
The record shows that, despite this instruction, only one of
MCSI's experience/past performance data sheets even arguably
referenced any aspect of grounds maintenance. Specifically,
MCSI's first data sheet stated, in the description of work,
"complete janitorial and related services, policing grounds,
carpets, floor maintenance 10 buildings." Comments, July 8,
2010, Exh. 2, at 1 (emphasis added). The remaining data sheets
specifically identified the services provided for each project,
but made no reference to any grounds maintenance services. For
example, MCSI's second data sheet stated, "[c]omplete janitorial
and related services, carpet, floor maintenance, window
cleaning," and its fifth data sheet stated, "[c]omplete aseptic
cleaning/janitorial service, related services, carpet and floor
maintenance, window cleaning, blood borne pathogen procedures (OSHA)."
Id. at 2, 5. Based on this record, we find GSA's determination
that MCSI's data sheets did not demonstrate experience within
the solicitation's definition of similar work to be reasonable
and consistent with the solicitation.
MCSI contends that the grounds maintenance services under its
prior projects were included within the "related services"
referenced in its data sheets. Given that MCSI specifically
listed certain janitorial services in its experience/past
performance data sheets, but failed to list grounds maintenance,
we do not consider it unreasonable for GSA to have concluded
that grounds maintenance services were not included in the
projects. Since an agency's evaluation is dependent on the
information furnished in a proposal, it is the offeror's
responsibility to submit an adequately written proposal for the
agency to evaluate. LOGMET, B-400535, Oct. 30, 2008, 2008 CPD
para. 199 at 3. An offeror that fails to do so runs the risk
that its proposal will be evaluated unfavorably. Recon Optical,
Inc., B-310436, B-310436.2, Dec. 27, 2007, 2008 CPD para. 10 at
6. (Moura's Cleaning Service,
Inc., B-402741.4,September 7, 2010) (pdf)
JBlanco complains
that its proposal met most of the solicitation's requirements
and that, to the extent it did not, its noncompliance was minor
and should have either been waived or corrected through
clarifications.
An offeror has the responsibility to submit a well-written
proposal, with adequately detailed information which clearly
demonstrates compliance with the solicitation requirements and
allows a meaningful review by the procuring agency. CACI Techs.,
Inc., B–296946, Oct. 27, 2005, 2005 CPD para. 198 at 5. In this
regard, an offeror must affirmatively demonstrate the merits of
its proposal, and risks the rejection of its proposal if it
fails to do so. HDL Research Lab, Inc., B–294959, Dec. 21, 2004,
2005 CPD para. 8 at 5.
The purpose of the technical proposal's demonstration project
was for offerors to demonstrate their task order proposal
preparation capability. Offerors were informed that, among other
things, the agency would review offerors' calculations for a
complete and reasonable task order price proposal complying with
the project specifications and drawings. RFP amend. 1 at 6-7.
Thus, it was incumbent upon the protester to submit a technical
proposal that clearly demonstrated its ability to satisfactorily
calculate prices as instructed. JBlanco essentially concedes
that it did not do so in its technical volume.
We do not agree with JBlanco that its failure to demonstrate its
capability to properly prepare task order proposals could be
waived as a minor error or corrected through clarifications.
Unlike a clerical or mathematical error in a price proposal,
which could be susceptible to correction through clarifications,
the error here implicates the protester's ability to properly
prepare its task order proposals. We think the agency could
reasonably conclude that allowing the protester to correct the
prices or change the pricing method in its technical proposal,
after the agency explained what errors the protester had made,
would defeat the purpose of the project demonstration. On this
record, we find no basis to question the reasonableness of the
agency's determination that JBlanco's proposal failed to meet
this pass/fail solicitation requirement.
The protest is denied. (JBlanco
Enterprises, Inc., B-402905, August 5, 2010) (pdf)
Richcon Federal
Contractors, Inc., of Wellington, Florida, protests the
rejection of its quotation by the Department of Agriculture,
Forest Service, under request for quotations (RFQ) No.
R3-6-10-007 for roofing services. The protester argues that the
agency should have accepted its quotation, which was submitted
by facsimile, notwithstanding the fact that the RFP incorporated
a Federal Acquisition Regulation (FAR) clause that prohibited
submission of quotations by this method.
We deny the protest.
The RFQ was issued on June 11, 2010, and sought quotations to
replace the roof of the Glenwood shop in the Gila National
Forest, New Mexico. Section L of the RFQ included the text of
FAR sect. 52.252-1, which states in relevant part: "This
solicitation incorporates one or more solicitation provisions by
reference, with the same force and effect as if they were given
in full text." Among the clauses incorporated by reference was
"Instructions to Offerors--Competitive Acquisition," which
states, as relevant here, "[u]nless other methods (e.g.,
electronic commerce or facsimile) are permitted in the
solicitation, proposals and modifications to proposals shall be
submitted in paper media in sealed envelopes or packages . . .
." FAR sect. 52.215-1(c)(1). The RFQ did not advise vendors that
any method other than paper media was acceptable for submission
of quotations.
Richcon submitted its quotation via facsimile on June 29, 1 day
before the solicitation closing date. The agency rejected
Richcon's quotation because it was delivered by facsimile,
rather than on paper, as required under the RFQ. Contracting
Officer's Statement para. 10.
Richcon argues that the Forest Service improperly rejected its
quotation because the RFQ did not specifically state that quotes
could not be submitted by facsimile. In this regard, the
protester contends that the RFQ did not expressly include
language that prohibited facsimile submission. As discussed
above, however, the RFQ advised vendors that the clause at
52.215-1 was incorporated into the solicitation. It is a
well-accepted principle of contract law that when an item is
incorporated by reference into a contract or other document, it
is not necessarily to bodily insert the text of the item into
the contract or document. Staker & Parsons Cos., B-402404.2,
Mar. 1, 2010, 2010 CPD para. 74 at 2-3; see also Northrop
Grumman Info. Tech., Inc., 535 F.3d 1339, 1343-46 (Fed. Cir.
2008). On this record, we conclude that vendors were advised
that facsimile submissions were prohibited, and that the
contracting officer acted reasonably by rejecting Richcon's
quotation. See G.D. Searle & Co., B-247077, Apr. 30, 1992, 92-1
CPD para. 406 at 3. (Richcon
Federal Contractors, Inc., B-403223, August 12, 2010) (pdf)
URS argues that
it fully complied with all RFP requirements and maintains that
it did demonstrate that it possessed a facility with a top
secret safeguarding clearance prior to the due date for receipt
of proposals, namely its facility with CAGE code 1RD04.
In reviewing protests of alleged improper evaluations, our
Office examines the record to determine whether the agency's
judgment was reasonable and in accord with the stated evaluation
criteria and applicable procurement laws. L-3 Commc'ns Westwood
Corp., B-295126, Jan. 19, 2005, 2005 CPD para. 30 at 5. It is an
offeror's responsibility to submit a well-written proposal, with
adequately detailed information which clearly demonstrates
compliance with the solicitation and allows a meaningful review
by the procuring agency. CACI Techs., Inc., B-296946, Oct. 27,
2005, 2005 CPD para. 198 at 5. In this regard, an offeror must
affirmatively demonstrate the merits of its proposal and risks
the rejection of its proposal if it fails to do so. HDL Research
Lab, Inc., B-294959, Dec. 21, 2004, 2005 CPD para. 8 at 5.
URS argues that the EPA misunderstood URS's corporate structure,
and that URS fully complied with the requirements of the RFP
because the proposal identified the specific CAGE code of the
facility that maintains a top secret safeguarding clearance. URS
explains that URS Group, Inc., is composed of multiple
facilities existing as a single entity, referred to as a
"Multiple Facility Organization." According to the protester,
the facilities that comprise URS Group, Inc., have different
CAGE codes; the facility with CAGE code 1N5H4 (which was listed
in the SF 33 as the offeror) is the headquarters and does not
have a top secret safeguarding clearance, but the facility with
CAGE code 1RD04 (which was listed in the technical proposal) is
a subordinate facility of the headquarters and does have a top
secret safeguarding clearance. Protest at 4. URS maintains that
the headquarters facility can use the security clearance of its
subordinate facility without the two facilities entering into a
written agreement because the two facilities are the same legal
entity operating out of the same physical location. URS asserts
that its identification of different CAGE codes in the SF 33 and
its technical proposal is irrelevant. Id. at 4-6.
We do not agree that the identification of different CAGE codes
is irrelevant, or that two entities with different CAGE codes
are the same for purposes of this procurement. CAGE codes are
assigned by the Defense Logistics Agency and are assigned to
discrete business entities for purposes of executing payments
under government contracts and to track the ownership of
technical data. National Found. Co., B-253369, Sept. 1, 1993,
93-2 CPD para. 143 at 2 n.1. Similarly, the DUNS numbering
system is established by Dunn & Bradstreet Information Services,
and discrete 9‑digit numbers are assigned for purposes of
establishing the precise identification of an offeror or
contractor. See FAR sections 4.605(b); 4.607. On an SF 33, the
CAGE code and DUNS number are used to identify the entity that
is the offeror for a given procurement. On the SF 33 here, those
numbers for the offering entity are different than the numbers
in the proposal for the entity with the top secret safeguarding
clearance.
As stated above, the RFP required offerors to have the
appropriate security clearance by the due date for receipt of
proposals. RFP sect. L.27. The RFP stated that the agency would
confirm that the offeror had the appropriate clearance in place
by the due date, and that offerors without the proper clearance
would not be considered for award. RFP attach. 9, at 9-7. After
determining that the URS entity that submitted the proposal in
response to the RFP, listed on the SF 33 with CAGE code 1N5H4,
did not have the appropriate clearance, the agency rejected
URS's proposal. Based on our review of the record, we find this
action unobjectionable.
In further support of its argument that the agency improperly
rejected its proposal, URS asserts that its technical proposal
committed the resources of the subordinate facility with CAGE
code 1RD04, which possesses a top secret safeguarding clearance,
to perform the contract. Comments at 3. However, the record
shows that URS failed to submit a complete demonstration of its
security clearance relative to the DD254, as required by the
RFP. Not only do the SF 33 and technical proposal identify two
different entities with different CAGE codes and DUNS numbers,
but also URS never explained in its proposal the relationship
between the two entities. Moreover, URS, in its proposal,
identified another entity that would be aiding the firm in its
performance of the safeguarding requirements; and it never
identified its relationship with this firm, provided the CAGE
code or DUNS number for this firm, or provided any evidence of
this firm's ability to handle and possess top secret
information.
In summary, the protester failed in its responsibility to
clearly demonstrate compliance with the RFP security
requirements. The record supports the reasonableness of the
agency's decision to find the proposal unacceptable for failure
to demonstrate that it satisfied the RFP security requirements.
(URS Group, Inc., B-402820, July
30, 2010) (pdf)
Xtreme questions
the agency's evaluation of its proposal and argues that the
agency improperly issued the task orders to two offerors with
higher evaluated costs.
In reviewing protests of alleged improper evaluations and source
selections, our Office examines the record to determine whether
the agency's judgment was reasonable and in accord with the
stated evaluation criteria and applicable procurement laws. See
ABT Assocs., Inc., B-237060.2, Feb., 26, 1990, 90-1 CPD para.
223 at 4. It is an offeror's responsibility to submit a
well-written proposal, with adequately detailed information
which clearly demonstrates compliance with the solicitation and
allows a meaningful review by the procuring agency. CACI Techs.,
Inc., B-296946, Oct. 27, 2005, 2005 CPD para. 198 at 5. In this
regard, an offeror must affirmatively demonstrate the merits of
its proposal and risks the rejection of its proposal if it fails
to do so. HDL Research Lab, Inc., B-294959, Dec. 21, 2004, 2005
CPD para. 8 at 5. A protester's mere disagreement with the
agency's evaluation provides no basis to question the
reasonableness of the evaluators' judgments. See Citywide
Managing Servs. Of Port Washington, Inc., B-281287.12,
B-281287.13, Nov. 15, 2000, 2001 CPD para. 6 at 10-11.
In addressing Xtreme's protest, we have reviewed the record,
including the agency's evaluation materials, Xtreme's proposal,
and its arguments challenging the agency's evaluation and
selection decision. While we only address the protester's
primary challenges, we have considered all of Xtreme's arguments
and conclude that none of them have merit. In short, we think
the record supports the ratings given the protester's proposal
and the agency's selection decisions.
Initially, we note that, although the agency report specifically
addresses the protester's challenge to the evaluation of the
firm's proposal and provides a detailed analysis of the
evaluated weaknesses and deficiencies in that proposal, the
protester's comments do not substantively challenge the agency's
evaluation results. Rather, the protester argues in a general
fashion that it has the knowledge and personnel to perform the
requirement. The TOPR, however, required that offerors
demonstrate their abilities to perform the requirements in their
proposals, and, in our view, Xtreme simply failed to do so.
With respect to CLIN 4020, the TOPR required offerors to
identify a specific number and category of employees all of
which were considered key. The TOPR further stated that resumes
must be provided for all key personnel. The protester does not
contend that it proposed sufficient key staff to perform the
CLIN (or that it provided resumes for these key personnel), but
instead argues that it has the ability to obtain staff and will
provide sufficient staff in contract performance. See Protest at
1-2; Comments at 3. This response, however, does not show that
the agency's concerns about Xtreme's staffing plan were
unreasonable. In short, the TOPR required offerors to detail the
personnel to be provided under the contract and to demonstrate a
commitment to assign appropriately skilled and experienced
personnel.
With respect to CLIN 4030, the protester also failed to address
a number of TOPR requirements, including identifying sufficient
staff to perform and addressing how it will accomplish contract
tasks. Again, the protester does not specifically challenge the
agency's evaluation conclusions concerning Xtreme's proposal but
simply argues that it has the ability to provide the required
services. As noted above, however, this does not demonstrate
that the agency's evaluation concerns are unreasonable.
For both CLINs, the agency received no completed past
performance questionnaires from any of the protester's
references, and found no past performance information for Xtreme
in the PPIRS database. The protester contends that it is not
listed in the PPIRS because several prime contractors, which
subcontracted work to the protester, failed to provide past
performance information to the PPIRS, despite repeated requests
that they do so. Although Xtreme complains that it was
prejudiced by these prime contractors' failure to provide past
performance information, Xtreme does not contend that the agency
was involved in any way. Xtreme's complaints in this regard
simply do not show that the Navy acted unreasonably, or in
violation of law or regulation.
The protester also argues that the agency was biased against
Xtreme, a small veteran-owned business. The protester, however,
presents no evidence supporting this allegation other than its
own inference based upon an alleged comment by a procurement
official that this requirement was not for small businesses.
Rather, as noted above, the record supports the reasonableness
of the agency's evaluation of Xtreme's proposal. We find no
basis to conclude that the evaluation of Xtreme's proposal was
the result of the agency favoring large business concerns, or
was otherwise motivated by bias or bad faith on the part of the
agency. In this regard, government officials are presumed to act
in good faith, and we will not attribute unfair or prejudicial
motives to procurement officials on the basis of inference or
supposition. See Shinwha Elecs., B-290603 et al., Sept. 3, 2002,
2002 CPD para. 154 at 5 n.6.
In sum, given the protester's failure to demonstrate its ability
to satisfy the agency's requirements, we find that the agency's
evaluation was reasonable and consistent with the evaluation
criteria. Furthermore, given the reasonableness of the
evaluation, the record provides no basis to question the
agency's decision not to select Xtreme for these task orders.
Because the agency found the protester's proposals to be
unacceptable in both instances, the agency was not required to
consider Xtreme's lower costs in its tradeoff decisions, since
it is well established that a technically unacceptable proposal
cannot be considered for award. EMSA Ltd. P'ship, B-254900.4,
July 26, 1994, 94-2 CPD para. 43 at 5. (XtremeConcepts
Systems, B-402438, April 23, 2010) (pdf)
The protester
challenges the agency's evaluation of both proposals. With
regard to TeAM's proposal, IBA contends that the evaluators
could not reasonably have assigned a rating of [deleted] under
the management approach factor given that once the pages in
excess of the solicitation limitations were excluded from the
TeAM proposal, the proposal did not include a transition plan or
required project milestones. With regard to its own proposal,
IBA argues that it should have received ratings of higher than
[deleted] under the experience, technical approach, and
management approach factors.
In reviewing an agency's evaluation, we will not reevaluate
proposals; instead, we will examine the record to determine
whether the agency's judgment was reasonable and in accord with
the solicitation evaluation criteria and applicable procurement
statutes and regulations. ESCO Marine, Inc., B-401438, Sept. 4,
2009, 2009 CPD para. 234 at 9. Based on our review of the record
here, we agree with the protester that the agency's evaluation
of both proposals was unreasonable. Accordingly, we sustain
IBA's protest.
Evaluation of TeAM proposal
The TOPR required offerors to provide a 60-day plan for incoming
transition as part of their proposals. The TOPR furnished a
great deal of detail regarding the required content of this
plan, instructing that it was to address the following topics:
-
Coordination with Government representatives,
-
Review, evaluation and transition of current support services,
-
Transition of historic data to new contractor system,
-
Government-approved training and certification process,
-
Transfer of hardware warranties and software licenses,
-
Transfer of all System/Tool documentation to include, at a
minimum: user manuals, system administration manuals, training
materials, disaster recovery manual, requirements traceability
matrix, configuration control documents and all other
documents required to operate, maintain and administer systems
and tools,
-
Transfer of compiled and uncompiled source code, to include
all versions, maintenance updates and patches,
-
Orientation phase and program to introduce Government
personnel, programs, and users to the Contractor's team,
tools, methodologies, and business processes,
-
Distribution of Contractor purchased Government owned assets,
including facilities, equipment, furniture, phone lines,
computer equipment, etc.,
-
Transfer of Government Furnished Equipment (GFE) and
Government Furnished Information (GFI), and GFE inventory
management assistance,
-
Applicable TMA briefing and personnel in-processing
procedures,
-
Coordinate with the Government to issue and account for
government keys, ID/access cards, and security codes.
TOPR at 2-3. In addition, the TOPR instructed offerors to
include a draft Program Management Plan (PMP) as an attachment
to their proposals. The solicitation identified four items that
"at a minimum" were to be addressed in the draft PMPs; of
relevance to this protest, one of the required items was "[i]dentification
of milestones where Government information/activity is required
and timeline dependencies for subsequent Contractor activities."
TOPR at 4.
TeAM included a [deleted] incoming transition plan as an
attachment to its non-price proposal; because the TOPR provided
that the transition plan was to be submitted as part of the
non-price proposal subject to the page limitations imposed
thereon, the contracting officer states that she removed the
attachment from the copy of TeAM's proposal that she provided to
the evaluators for reevaluation. Similarly, the contracting
officer states that she removed the final 10 pages of TeAM's
[deleted] PMP because the solicitation placed a limitation of 10
pages on this attachment. In their reevaluation, the evaluators
attributed [deleted] weaknesses and [deleted] weakness to the
TeAM proposal under the management approach factor; [deleted].
The evaluators noted that [deleted]. Evaluation Panel Report,
Dec. 10, 2009, at 20. Despite this finding, the evaluators
assigned the proposal an overall rating of [deleted] under the
management approach factor.
IBA argues that the rating of [deleted] is unreasonable given
that TeAM's proposal did not include a transition plan and did
not identify project milestones. In response to the first point,
the agency maintained that while TeAM's proposal lacked a full
transition plan, it did address transition issues and thus
merited an [deleted] rating. In particular, the agency pointed
to language in the proposal addressing TeAM's [deleted];
acknowledging the phases of the [deleted] to be supported under
the task order; discussing TeAM's approach to [deleted]; and
referring to TeAM's experience in [deleted]. The protester
responded that these references could not reasonably be
considered an adequate response to the solicitation requirement
for a transition plan addressing the 10 items summarized above.
We agree with the protester. As noted above, the TOPR required
contractors to furnish a plan addressing a number of aspects of
transition, including the offeror's plans for ensuring that
existing data, documentation, source code, and equipment would
be successfully transferred to it. The language from TeAM's
proposal cited by the agency [deleted]. Because the pared-down
version of the TeAM proposal that the evaluators considered
during their reevaluation not only failed [deleted], but also
failed to otherwise address the required elements [deleted], we
do not think that the evaluators could reasonably have
considered the proposal to satisfy the solicitation requirement
for a transition plan. Absent a basis for finding that the
proposal had demonstrated an approach to meeting the
requirement, we do not think that it was reasonable for the
evaluators to have assigned the TeAM proposal a rating of
[deleted] under the management approach factor, because the TOPR
provided for the assignment of a rating of [deleted].
The protester also complains that TeAM's draft PMP failed to
identify project milestones, as required by the TOPR, and thus
failed to reflect an acceptable management approach. In
response, the agency argues that while the table in which TeAM
identified its project milestones was not considered in the
reevaluation (due to enforcement of the solicitation's page
limitations), the proposal otherwise adequately identified the
milestones [deleted]. Based on our review of the record, we fail
to see how the proposal passages cited by the agency adequately
identified the project milestones [deleted]. For example, the
agency points to TeAM's statement in its PMP that [deleted],
TeAM Proposal, Attach. 3 (PMP), at 4. In our view, this
statement is not sufficient to incorporate the milestones into
the proposal; where, as here, a solicitation requires offerors
to furnish detailed information to demonstrate compliance with
solicitation requirements, [deleted] is not sufficient to
demonstrate that a proposal meets the requirements. VT Griffin
Servs., Inc., B‑299869.2, Nov. 10, 2008, 2008 CPD para. 219 at
5.
In sum, in addition to lacking a reasonable basis for concluding
that the TeAM proposal complied with the TOPR requirement for a
transition plan, we think that the evaluators lacked a
reasonable basis for finding that TeAM complied with the
solicitation requirement for a PMP setting forth project
milestones. Accordingly, we agree with the protester that it was
unreasonable for the evaluators to assign TeAM's proposal a
rating of [deleted] under the management approach factor.
(Irving Burton Associates, Inc.,
B-401983.3, March 29, 2010) (pdf)
Kiewit first
contends that it was unreasonable for the agency to reject its
proposal on the basis that the protester’s proposed preliminary
schedule for performance included what the agency perceived as
an unreasonably late date for the issuance of the notice to
proceed and start of performance. Since the agency’s anticipated
notice to proceed date was not shared with the competitors prior
to proposal submission, Kiewit contends that the agency applied
an unstated criterion in evaluating its proposal; that its
experience supports its schedule’s notice to proceed/
performance start date; and that the firm’s proposal, in any
event, included a statement of the firm’s intention to comply
with all solicitation requirements. As discussed below, our
review of the record provides no basis to question the agency’s
evaluation of the proposal.
An offeror has the burden of submitting an adequately written
proposal with sufficiently detailed information to clearly
demonstrate the merits of its proposal and risks the rejection
of its proposal if it fails to do so. See HDL Research Lab,
Inc., B‑294959, Dec. 21, 2004, 2005 CPD para. 8 at 5. As stated
above, the RFP required evaluation of, among other things, the
timeliness of the proposed performance, and offerors were to
demonstrate the “ability to schedule and successfully perform
the work and to satisfy all solicitation requirements.” RFP at
00110-3. Kiewit’s schedule assumed a notice to
proceed/performance start date approximately 3 months from when
the agency states that it anticipated issuing the task order
(and more than 2 months from the date Kiewit itself assumed the
task order would be issued). The protester provided no
information in its proposal to explain or support the proposed
schedule’s assumption that the notice to proceed and start of
performance would not occur until months after issuance of the
task order. While the firm argues that it intended the dates it
submitted on its proposed schedule to be placeholders for the
actual notice to proceed and performance start dates, our review
of the record shows there is no explanatory narrative or
notation in its proposal to support that intention. Likewise,
the proposal does not explain what experience the firm relies on
in supporting its anticipation of a delay by the agency in
issuing the notice to proceed.
We find reasonable the agency’s evaluation of Kiewit’s
unexplained, later than anticipated performance start date and
the uncertainty presented by the proposed schedule, in relation
to the agency’s anticipated dates for issuance of the task order
and the notice to proceed with performance. Although Kiewit
contends the agency applied an unstated evaluation criterion in
this regard, timeliness of proposed schedule and ability to
schedule and successfully perform the work were areas for
evaluation. As the agency points out in its report, in light of
the delay Kiewit’s proposal assumed between issuance of the task
order and start of performance, if the agency promptly issued
the task order and notice to proceed, it was uncertain from
Kiewit’s proposal whether performance would be completed within
the required period. Based on our review of the record, given
the insufficiency of the firm’s blanket statement of compliance
in light of the uncertainty introduced by Kiewit’s proposed
start of performance months after issuance of the task order,
and the failure of the firm to demonstrate in its proposal that
its proposed dates were mere placeholders for the actual dates
the agency’s notice to proceed would trigger, we have no basis
to question the reasonableness of the agency’s concerns and its
conclusion that the proposal was technically unacceptable.
The protest is denied. (Kiewit
Texas Construction L.P., B-402090; B-402090.2, January 12,
2010) (pdf)
The RFQ expressly
required technical submissions from each vendor demonstrating
the ability to perform based on the vendor's qualifications,
experience, past performance, and work plan and schedule
information. The record shows that a substantial amount of
required information was not submitted by John Blood; the
protester does not refute the agency's item-by-item list of
missing information in his quotation. Rather, the protester
generally contends the agency should have concluded that his
ability to perform was demonstrated by this quotation's
reference to 30 years of thinning experience, and because the
protester allegedly showed an understanding of the requirements
in speaking with agency personnel about the work prior to
submitting a quotation.
A vendor is responsible for demonstrating affirmatively the
merits of its quotation and risks rejection if it fails to do
so. See HDL Research Lab, Inc., B‑294959, Dec. 21, 2004, 2005
CPD para. 8 at 5. Further, no matter how competent a vendor may
be, the technical evaluation must be based on information
included in the firm's quotation. See Watson Indus., Inc.,
B-238309, Apr. 5, 1990, 90-1 CPD para. 371 at 3-4. Since the RFQ
here required the vendors to include specific technical
information for evaluation, we consider reasonable the agency's
determination that the protester's failure to submit the
information rendered its quotation technically marginal, at
best, and presented substantial performance risk. Given these
agency findings, we have no basis to question the reasonableness
of the agency's selection of the higher-priced, but technically
superior, lower risk quotation from Lara Brothers. (John
Blood, B-402133, January 15, 2010) (pdf)
Argon argues that
the agency unreasonably determined that its proposal did not
establish compliance with the MTBOMF1 requirement. In
considering protests challenging the evaluation of proposals, we
will not reevaluate proposals; rather, we will examine the
record to determine whether the agency’s evaluation conclusions
were reasonable and consistent with the terms of the
solicitation and applicable procurement laws and regulations.
Engineered Elec. Co. d/b/a/ DRS Fermont, B‑295126.5, B-295126.6,
Dec. 7, 2007, 2007 CPD para. 4 at 3-4. We find the agency
reasonably concluded that Argon’s proposal did not establish
compliance with the MTBOMF requirement.
It is undisputed that Argon’s initial proposal contained no
information whatsoever relating to the ability of its CPS to
meet the solicitation’s MTBOMF1 requirement. Argon’s
response to the ensuing discussion questions included an
estimate of MTBOMF expressed in terms of hours ([deleted]), but
was silent as to the temperature at which the estimate could be
achieved. The agency appears to have considered this information
sufficient, but any such conclusion was unwarranted, since
MTBOMF was not expressed in terms of number of hours at the
specified temperature of 25C. The information thereafter
provided by Argon in its FPR was similarly noncompliant with the
requirements of the RFP; the MTBOMF hourly figure ([deleted])
failed to meet the minimum requirement of 15,000 hours, and was
expressed at a temperature (55C) that was outside the specified
operating parameters for the CPS.
Argon asserts that the agency should have applied the “Arhenius”
model or equation, which allegedly has led to a rule of thumb
that a 10C change in operating temperature results in a doubling
(or halving) of reliability predictions; according to the
protester, using this approach would have allowed the agency to
project the MTBOMF of Argon’s proposed CPS at 25C using the data
provided for MTBOMF at 55C. Protest, May 11, 2009, exh. 4, at
2-3. This argument is without merit. The agency has produced
evidence both that its evaluators were unaware of this rule of
thumb, and that the model’s reliability is both suspect, and
dependent upon having various data that were not included in
Argon’s proposal. AR, exh. 13, at 2-4. Argon has not shown
otherwise. In any case, an offeror is responsible for submitting
an adequately written proposal and bears the risk that, if it
fails to do so, its proposal may be rejected as unacceptable.
L-3 Communications EOTech, Inc., B-311453, B-311453.2, July 14,
2008, 2008 CPD para. 139 at 4. Argon could not provide
inadequate MTBOMF information in response to the specific RFP
requirement and then rely on the agency to evaluate the
information based on an approach not referenced in the RFP (or,
for that matter, in the protester’s proposal). (Argon
ST, Inc., B-401387, August 6, 2009) (pdf)
---------------------------
1 mean time between operation mission failure.
The TOPR1
provided for the issuance of a task order to the vendor
whose proposal provided the “best value” to the government
considering technical support (with subfactors for technical
expertise, services, and quality control) and price. TOPR at 6.
As relevant here, under the technical expertise subfactor
vendors were required to address staffing levels, including a
detailed description of the staffing outline for all positions.
Id. The solicitation, as issued, included historical workload
data to assist vendors in developing their staffing plans, but
after receiving and evaluating initial quotations the agency
provided vendors with the government’s estimated minimum
staffing. Army E-mail, Mar. 17, 2009. The Army also sent each
vendor discussion questions concerning specific weaknesses in
their proposals. Following the receipt and evaluation of final
proposal revisions, both Altech’s and GC&E’s proposals were
rated acceptable for each non-price factor. Altech proposed a
price of $15,386,930.68, and GC&E a price of $18,933,348.40. The
agency selected Altech’s proposal for issuance of the task
order.
GC&E asserts that the agency misled it into increasing its price
unnecessarily. Specifically, the protester states that it
initially offered to perform with a staff of 40, but that it
increased its staff to 51 after the agency provided the minimum
staffing estimate showing a staff of 51. GC&E states it believed
the estimate reflected the agency’s minimum requirements, and
that it only learned after award that the estimate was not
intended to establish a minimum. GC&E asserts that this increase
in its proposed staffing resulted in a substantial increase in
its price, and concludes that, had it not increased its
staffing, it would have received the task order.
This argument is without merit. The e-mail transmitting the
staffing estimate advised vendors that, “The staffing provided
is not the solution, but represents the Government’s minimum
staffing to perform the requirements of the PWS.” Army E‑mail,
Mar. 17, 2009. Vendors questioned this statement, and the Army
responded to all vendors that, “The minimum staffing provided is
only an estimate. It is the contractor’s responsibility to
determine how to staff to support the requirements of the PWS.”
Questions and Answers, Mar. 20, 2009. Since the response
expressly stated that the minimum staffing was only an estimate,
and provided that vendors were to determine their own staffing,
there was no reasonable basis for GC&E to treat the estimate as
a minimum requirement; if GC&E believed that its initially
proposed staffing was adequate to perform the requirements of
the task order, it should have been clear that it was free to
leave its staffing unchanged. (GC&E
Systems Group, Inc., B-401315; B-401315.2, July 9, 2009)
(pdf)
-----------------------------
1 task order
proposal request.
SPAAN challenges
the agency’s evaluation of the firm’s proposal under the
technical understanding/approach, management approach, and past
performance factors and contends that its proposal should have
been found to be one of the most highly rated and included in
the competitive range. With respect to the evaluation of its
proposal under the technical understanding/approach factor,
SPAAN disagrees that it did not adequately discuss how the firm
would ensure technical quality in performing the contract and
that it had not adequately discussed its quality assurance plan.
In this regard, SPAAN cites certain pages of its proposal as
assertedly demonstrating the firm’s approach to ensuring
technical quality. See Protester’s Comments at 12-13. SPAAN also
argues that, as it indicated in its proposal, SPAAN, as the
incumbent contractor, had successfully integrated its quality
assurance plan with the agency’s quality control and quality
assurance requirements, which SPAAN contends satisfies the RFP’s
requirement to describe how the firm would ensure technical
quality. SPAAN concludes that, absent DOE’s allegedly
unreasonable evaluation, the firm’s proposal would have received
more than the two points it received under this factor.
DOE contends that SPAAN’s proposal addressed a “traditional
program management-based approach to the work (e.g.,
implementing internal project controls, schedule control,
tracking performance indicators)” and identified the work to be
performed but did not substantively address how the firm would
ensure technical quality. See AR, Tab 5, Initial SEB Report at
43. In this regard, DOE also notes that, despite the
solicitation’s explicit instructions, SPAAN failed to provide an
outline or summary of its quality assurance plan and that it is
an offeror’s obligation to prepare a proposal that adequately
addresses the solicitation’s requirements.
We agree with DOE that an offeror bears the burden of submitting
an adequately written proposal, and that it runs the risk that
the firm’s proposal will be evaluated unfavorably when it fails
to do so. See American Ordnance, LLC, B-292847 et al., Dec. 5,
2003, 2004 CPD para. 3 at 4. Here, we find from our review of
SPAAN’s technical proposal, including those parts to which SPAAN
cites in its comments, that SPAAN provided little discussion of
how it would ensure technical quality (that is, little
discussion of how SPAAN would ensure the “appropriateness,
accuracy, completeness” of its work products, as required by the
RFP). We also find that SPAAN did not provide an outline or
summary of its quality assurance plan, although this too was
required by the RFP. Given these shortcomings in SPAAN’s
proposal, we cannot say that DOE acted unreasonably in assessing
these failures to be a significant proposal weakness.
Although its true that SPAAN referenced in its proposal the
firm’s incumbent performance, including its integration of a
quality assurance plan, we disagree with SPAAN’s apparent belief
that, because the firm, as the incumbent contractor, had
successfully implemented a quality assurance plan in its prior
contract, DOE should accept SPAAN’s experience in this regard in
lieu of an adequately written proposal addressing all of the
solicitation’s requirements. See HealthStar VA, PLLC, B‑299737,
June 22, 2007, 2007 CPD para. 114 at 2; Interactive Commc’n
Tech., Inc., B‑271051, May 30, 1996, 96-1 CPD para. 260 at 2. In
this regard, offerors’ past performance was evaluated under
another evaluation factor, for which SPAAN’s proposal received
credit for its performance of the incumbent contract. (SPAAN
Tech, Inc., B-400406; B-400406.2, October 28, 2008) (pdf)
Sauer essentially
argues that the agency unreasonably evaluated its proposal.
Specifically, Sauer contends that the RFP only required offerors
to describe in narrative form how the offeror could meet the
contract requirements and that the RFP permits the AWS
certification requirement to be met through a narrative
description and that Sauer did mention in its narratives that
AWS standards were used on prior projects.
In reviewing a protest against an agency’s proposal evaluation,
our role is limited to ensuring that the evaluation was
reasonable and consistent with the terms of the solicitation and
applicable statutes and regulations. National Toxicology Labs.,
Inc., B-281074.2, Jan. 11, 1999, 99-1 CPD para. 5 at 3. An
offeror is responsible for submitting an adequately written
proposal, and runs the risk that its proposal will be evaluated
unfavorably where it fails to do so. Carlson Wagonlit Travel,
B-297016, Mar. 6, 2001, 2001 CPD para. 49 at 3. Based on our
review of the record, the agency’s evaluation of Sauer’s
proposal as a “No Go” was reasonable given Sauer’s lack of
documentation demonstrating its performance of projects
involving AWS certification.
Although the RFP allowed offerors to describe in narrative form
their ability to satisfy the RFP’s requirements, the RFP
emphasized the importance of providing information sufficiently
detailed to clearly describe the offeror’s capabilities to
successfully complete the project. The RFP also warned that
proposals that did not include substantial evidence of the
offeror’s experience, qualifications and production capability
would be considered unacceptable. With respect to the welding
and weld testing experience requirements, the RFP clearly
required offerors to provide “documentation showing AWS
certification for this type of work.” Moreover, the RFP
specifically provided that offerors providing documentation of
completion of projects similar in scope and size and AWS
certification for similar work would be considered to have
satisfied the minimum requirements of the RFP.
Sauer’s proposal did not provide any documentation to
demonstrate that its prior experience involved welding work that
required AWS certifications. Rather, Sauer merely described its
prior projects and stated that “[w]eldment required certified
welders and weld testing of full pen welds to AWS standards.”
Sauer Proposal Section 2, Experience at 1. Sauer’s explanation
that it performed weld testing to AWS standards is not the same
as establishing that it performed welding work that required AWS
certifications or documentation to that effect. In contrast,
other offerors provided copies of the AWS certification for the
individual employees that performed the work on their prior
contracts. Given that the RFP was very specific concerning the
requirement for documentation showing AWS certification on prior
projects, the agency reasonably concluded that Sauer’s proposal
was unacceptable based on Sauer’s lack of documentation
concerning AWS certification with respect to any of its prior
projects. (Sauer, Incorporated,
B-400709, December 22, 2008) (pdf)
In its pre-oral
presentation evaluation, the AEEB assigned a notable weakness to
the protester’s submission under factor 6, stating that the
“Offeror did not clearly explain [how] it would adapt to
increasing capacity of this contract. The Offeror stated that
they would be operating at 50% capacity in 6 months and 80%
capacity in 12 months.” AR, Tab 6, AEEB Report, at 6.
As noted above, offerors were provided at the oral presentations
with a list of questions to which they should respond. The last
of HGL’s questions stated: “The proposal includes an estimate
that key staff will have 50% availability in 6 months and 80%
availability at the end of the year. Please describe the
personnel and companies included in this estimate.” Id. at 4. In
its post-oral presentation analysis, the AEEB stated that
“during the oral presentation, HGL was asked to explain a
statement in the written document regarding capacity (that HGL
would be able to provide service at 50% at 6 months, 80% in 12)
and did not satisfactorily explain how this would work to the
AEEB.” AR, Tab 11, AEEB Final Report, at 3.
The protester argues that the agency unreasonably took one
sentence in its submission out of context, when the submission,
read as a whole, repeatedly asserted that HGL would be prepared
to fulfill the contract requirements at the inception of
contract performance. We disagree.
An offeror has the responsibility to submit a well-written
proposal, with adequately detailed information, which clearly
demonstrates compliance with the solicitation requirements and
allows a meaningful review by the procuring agency, CACI Techs.,
Inc., B-296946, Oct. 27, 2005, 2005 CPD para. 198 at 5, and that
contains all the information that was requested or necessary to
demonstrate its capabilities in response to the solicitation.
HealthStar VA, PLLC, B-299737, June 22, 2007, 2007 CPD para. 114
at 2. A protester’s mere disagreement with the evaluation, as
noted above, provides no basis to question the reasonableness of
the evaluators’ judgments. See CH2M Hill, Ltd., supra.
In our view, based on the reference in HGL’s submission to “50%
availability in six months and up to 80% availability within 12
months” of its “key personnel and technical staff,” it was not
unreasonable for the agency to seek confirmation from HGL
regarding the availability of the personnel proposed for the
contract. To that end, four of the 15 oral presentation
questions presented to HGL by the agency concerned staffing,
including the last question, quoted above, which was
specifically directed at obtaining clarification of the
statement in the protester’s SF 330 regarding staffing
availability. The record shows, however, that the protester
failed to persuade the agency that it would have the key
individuals with which it intended to staff the contract ready
at the inception of performance, and that it was prepared to
deal with the staffing contingencies that might arise. Because
HGL did not provide the confirmation the agency was seeking, it
was reasonable for the agency to characterize this area as a
notable weakness and ultimately rely on it as the primary
discriminator between the two strong submissions from HGL and
ITSI. (HydroGeoLogic, Inc.,
B-311263; B-311263.2, May 27, 2008) (pdf)
The evaluation of proposals is a matter within the discretion of
the procuring agency, since the agency is responsible for
defining its needs and deciding on the best methods of
accommodating them. We will question the agency’s technical
evaluation only where the record shows that the evaluation does
not have a reasonable basis or is inconsistent with the RFP.
Pacifica Servs., Inc., B-280921, Dec. 7, 1998, 98-2 CPD para.
137 at 3. Since an agency’s evaluation is dependent upon the
information furnished in a proposal, it is the offeror’s
responsibility to submit an adequately written proposal for the
agency to evaluate. Id. Here, based upon our review of the
record, we find that the agency’s evaluation of LOGMET’s
proposal as unacceptable was reasonable and consistent with
terms of the RFP.
As noted above, LOGMET submitted documentation pertaining to two
individuals for the SCBA technician position. The resume of one
of the proposed individuals (Technician A) listed as one of his
qualifications that he was “SCBA (self contained breathing
apparatus) Trained.” AR, Tab 13. Technician A’s resume also
furnished a summary of his work experience (positions held, job
duties, and supervisors’ names) and the names of three
references. Technician B’s resume consisted of a job description
for an SCBA technician position at a local fire department, with
his name inserted at the top. In other words, rather than a
typical resume summarizing the candidate’s qualifications,
training, and experience, this “resume” furnished only a
description of the essential functions to be performed and the
skills/knowledge required for performance of a particular SCBA
technician position.
The Air Force explains that it could not determine from the
proffered documentation that the proposed individuals had the
requisite work experience or certifications to perform the SCBA
technician position. With regard to Technician A, the agency
explained that the evaluators could not assume that “SCBA
trained” meant that the individual had received training in the
maintenance of SCBA equipment since “SCBA trained” could
reasonably be interpreted as signifying simply that the
individual had received training in the use of SCBA gear. The
agency further noted that none of Technician A’s work experience
was in positions that required the performance of duties similar
to those of an SCBA technician. With regard to Technician B, the
agency explained that while the position description was a
reasonably accurate summary of the skills and training required
of an SCBA technician, there was no evidence that the proposed
individual actually possessed those skills and training. In this
connection, the “resume” furnished no information regarding the
employee’s experience and/or training that would qualify him for
the position.
In response to the agency’s argument that the evaluators could
not reasonably assume that the phrase “SCBA trained” in
Technician A’s resume indicated that he was trained in
maintenance of SCBA equipment, the protester contends that the
solicitation did not furnish any explanation as to the services
to be provided--or the equipment to be maintained--by an SCBA
technician. To the extent that the protester is arguing that the
RFP did not make clear that the SCBA technician would be
performing maintenance on SCBA equipment--and thus that
experience in performing and/or certification to perform
maintenance on SCBA equipment was required--we think that, given
that this was a solicitation for maintenance services, offerors
reasonably should have understood that one of the functions to
be performed by an SCBA technician was maintenance of SCBA
equipment.
The protester also argues that if the evaluators had questions
regarding the nature of Technician A’s SCBA training, they
should have contacted one of the references listed on his
resume, who was identified as a “Firefighter/EMT--Paramedic.” We
disagree. First, as noted above, it is the offeror’s
responsibility to submit an adequately written proposal, and
contracting agencies are not obligated to go in search of needed
information that the offeror has omitted or failed to present.
Delphinus Eng’g, Inc., B-296902, B-296902.2, Sept. 20, 2005,
2006 CPD para. 7 at 8. Second, there was nothing in Technician
A’s resume to suggest that the firefighter/EMT whom he listed as
a reference had any involvement in furnishing him with SCBA
training. In fact, there was no indication in the resume that
the firefighter/EMT had been associated with the proposed
technician in any professional capacity.
With regard to Technician B, the protester argues that the
documentation that it submitted demonstrates that the candidate
secured employment with a local fire department as an SCBA
technician, and thus he may be presumed to possess the
qualifications, training, and experience necessary for such a
position. We do not think that it is apparent from the
documentation furnished by the protester that Technician B in
fact secured or performed the job described. Further, even
assuming that he did fill the position described, there is no
information confirming that he had the experience or
qualifications for it, nor is there any information regarding
the tenure of his employment at the job.
In sum, we think that the agency had a reasonable basis for
finding that the protester failed to demonstrate that it had a
qualified individual to fill the position of SCBA technician,
and, as a consequence, for determining the protester’s proposal
technically unacceptable. (LOGMET,
B-400535, October 30, 2008) (pdf)
Our Office has long recognized that, as a general matter, it is
an offeror’s responsibility to submit an adequately written
proposal with sufficient information for the agency to evaluate
and determine compliance with the solicitation’s requirements.
Interstate Gen. Gov’t Contractors, Inc., B-290137.2, June
21, 2002, 2002 CPD para. 105 at 5; Better Serv.,
B-256498.2, Jan. 9, 1995, 95-1 CPD para. 11 at 2. With regard to
the role of the agency, our Office has held that in evaluating a
proposal, an agency is under no obligation “to decipher a poorly
organized proposal,” Shumaker Trucking and Excavating
Contractors, Inc., B-290732, Sept. 25, 2002, 2002 CPD para.
169 at 5, or to reach favorable conclusions regarding the merits
of a proposal or the compliance of the proposal with a
solicitation’s requirements where the information supporting
such conclusions is “not readily apparent,” DATEX, Inc,
B-270268.2, Apr. 15, 1996, 96-1 CPD para. 240 at 6, “not clearly
delineated,” Joint Mgmt. & Tech. Servs., B-294229;
B-294229.3, Sept. 22, 2004, 2004 CPD para. 208 at 5, or not set
forth with the requisite degree of precision required by the
RFP. Ace Info. Sys., B-295450.2, Mar. 7, 2005, 2005 CPD
para. 75 at 8; United Def. LP, B-286925.3 et al., Apr. 9,
2001, 2001 CPD para. 75 at 19. Nor is an agency required to
“deduce[]” that a proposal meets certain requirements where the
proposal lacks the level of detail the RFP requires, SOS
Interpreting, Ltd., B-287505, June 12, 2001, 2001 CPD para.
104 at 11-12, or accept a proposal that the agency finds is
unclear or ambiguous regarding its merits or compliance with the
solicitation’s requirements. Ace Info. Sys., supra at 7;
Innovative Commc’s Techs., Inc., B-291728; B-291728.2,
Mar. 5, 2003, 2003 CPD para. 58 at 5-7; JAVIS Automation &
Eng’g, Inc., B-290434; B-290434.2, Aug. 5, 2002, 2002 CPD
para. 140 at 6 (it is not the agency’s obligation to fill in
gaps in an offeror’s proposal during the evaluation process).
As indicated above, the RFP advised that in completing the
functional requirements matrix, which included the
solicitation’s provisions regarding intellectual property/data
rights, offerors were to “provide a description of how the
proposed solution meets the requirements stated.” RFP at 69. As
recognized by the agency in evaluating the protesters’
proposals, the protesters did not do this. That is, the
protesters, rather than providing “a description” of how their
proposals evidenced compliance with the solicitation’s
provisions regarding intellectual property/data rights, chose to
state simply that “[d]ata rights are governed by the applicable
provisions of the Avue Master Subscription Agreement,” and then
set forth certain provisions of the Avue Master Subscription
Agreement. This approach left it to the agency to “deduce”
whether the Avue Master Subscription Agreement evidenced
compliance with the solicitation provisions regarding
intellectual property/data rights.
As set forth above, the agency found that the provisions of the
Avue Master Subscription Agreement included in the proposals
were unclear in a number of areas with regard to data rights, or
too narrowly defined the intellectual property/data that would
be considered the agency’s, and that it appeared from the Master
Subscription Agreement that the intellectual property/data
rights provisions in the RFP would not be met. Although the
protester clearly disagrees with the agency’s determinations,
based upon our review of the record, we have no basis to
question the reasonableness of the agency’s evaluation. Simply
put, it was the protesters’ obligation to submit proposals with
adequately detailed information in such a manner as to allow for
a meaningful review by the agency, Shumaker Trucking and
Excavating Contractors, Inc., supra, and the protesters, who
did not provide any explanation in their proposals regarding the
proposals’ compliance with the solicitation’s intellectual
property/data rights provisions, failed to do so. (Avue
Technologies Corp.; Carahsoft Technology Corp., B-298380.4,
June 11, 2007) (pdf)
As we have often stated, an offeror must submit an adequately
written proposal or it runs the risk of having its proposal
rejected as unacceptable. Dynamic Mktg. Servs., Inc.,
B-279697, July 13, 1998, 98-2 CPD para. 84 at 6. Here, the
complaint raised by L-3 concerning the endurance-live fire test
was the result of its failure to identify how its locking nut
was to be tightened, and not because of agency error. Under
these circumstances, we cannot find the agency’s testing
approach unreasonable.
L-3 nevertheless asserts that its test failure was not design
related, but was the result only of a “minor informational
deficiency” that could have been corrected easily by asking L-3
whether a tool was required to properly tighten the nut. L-3
contends that given this minor issue and the fact that this was
the only one of the “essential criteria” that its sample failed
to satisfy, the agency should allow L‑3 to correct the
informational deficiency and repeat the pass/fail test,
especially because the failure to do so resulted in the
establishment of a competitive range of one. Supp. Protest and
Comments at 9.
Federal Acquisition Regulation (FAR) permits an agency to limit
the competitive range to only the “most highly rated proposals”
and does not require that discussions be held with offerors that
are not included in the competitive range. FAR sections
15.306(c)(1), (d)(1). We have held that there is nothing
inherently improper in a competitive range of one where the
agency has a reasonable basis for its competitive range
determination. M&M Investigations, Inc., B‑299369.2,
B-299369.3, Oct. 24, 2007, 2007 CPD para. 200 at 3. As indicated
above, this RFP clearly established the ground rules for testing
the samples as well as the consequences--“elimination from
further consideration for award”--for offerors whose proposed
bid sample failed any one of the 15 “essential criteria.” Given
these ground rules, we cannot find unreasonable the agency’s
decision to exclude L-3’s proposal and bid sample from the
competitive range where, as here, the proposal failed an
“essential criteria” test and the only complaint about this
failure is related to L-3’s inadequately drafted proposal, and
not because of agency error or flawed testing. See California
Microwave, Inc., B-229489, Feb. 24, 1988, 88-1 CPD para. 189
at 6. (L-3
Communications EOTech, Inc., B-311453; B-311453.2, July 14,
2008) (pdf)
As explained in detail below, we find that HHS’s evaluation of
PPDG’s proposal, and the subsequent decision to exclude the
proposal from the competitive range, were reasonable and
consistent with the solicitation. The record reflects that the
proposal, in large part, either parroted back in whole or part
the RFP’s requirements, with a statement of PPDG’s intent to
meet the requirements, or simply lacked the required information
or detail for the agency to determine that PPDG understood the
RFP’s requirements. Although it is true that proposals were
limited to 35 pages in length, and therefore exhaustive detail
could not be provided, our review of the record confirms the
reasonableness of the agency’s judgment that PPDG failed to
provide the level of detail that reasonably could be expected,
within the page limitation stated in the RFP. Although we do not
specifically address here all of the protester’s arguments
concerning the evaluation of its proposal, we have fully
considered all of them and find that they afford no basis to
question the agency’s evaluation. (Professional
Performance Development Group, Inc., B-311273; B-311273.2,
June 2, 2008) (pdf)
Mangi asserts
that, although it did not propose a solution like that
envisioned in RFP sect. 2, its proposal addressed all RFP
requirements. It notes, for example, that its proposal set forth
Mangi’s extensive experience, including the preparation of some
350 EAs and EISs, and explained its analytical process. This
process included developing a description of the proposed action
and alternatives; identifying connected and cumulative actions,
potential types of effects, priorities, and allocations;
determining data, study needs, scoping issues, and alternatives
and public involvement; conducting its analyses in accordance
with its analytic process, documenting the results, and
providing an innovative concordance analysis to show the ways in
which each EA differs from the other ones in structure,
analysis, schedule, and conclusions. Mangi Supplemental Comments
at 4-5. With regard to its proposed subcontractors, Mangi notes
that it clearly proposed that it would be responsible for the
EAs and that the subcontractors would serve as specialty
consultants; this recognized that performance would be based
mainly on existing knowledge, literature reviews, and other
appropriate material. Id. at 5-6. Since Mangi itself, not its
subcontractors, was to be responsible for producing the 20 EAs,
Mangi asserts that it was improper for the agency to criticize
its proposal for failing to provide evidence of adequate
management oversight of its subcontractors with regard to
production of the EAs.In considering a protest of an agency’s
proposal evaluation, our review is confined to determining
whether the evaluation was reasonable and consistent with the
terms of the solicitation and applicable statutes and
regulations. United Def. LP, B‑286925.3 et al., Apr. 9, 2001,
2001 CPD para. 75 at 10‑11. This aspect of the evaluation
was unobjectionable. While the agency was well aware that Mangi
itself had extensive NEPA experience, as noted, the agency was
concerned with the number of completed projects and its proposed
subcontractors’ apparent lack of NEPA experience. Further, while
the agency recognized that the proposal stated that Mangi would
perform the bulk of the work, it found that this was not so
clear from a complete reading of the proposal. For example,
immediately after stating that Mangi and its personnel would
play a “major role in the centralized planning, conduct and
documentation of the EAs,” Mangi’s proposal stated that its
“[s]ubcontractors and their personnel familiar with each state
will substantially assist with the state-by-state scoping,
planning, data gathering and analysis within the systematic [Mangi]
approach.” Mangi Proposal at 23. This language led the agency to
question whether Mangi might rely heavily on its proposed
subcontractors, which was problematic because it appeared that
they lacked NEPA experience. Here, as with the other areas of
its proposal evaluated as weak or deficient, while Mangi may
have attempted to cover the requirements of the RFP, the agency
found that its proposal failed to do so in a clear and
understandable manner. We think the agency’s conclusion was
reasonable, and that it reasonably downgraded Mangi’s proposal
on this basis. See HDL Research Lab, Inc., B-294959, Dec. 21,
2004, 2005 CPD para. 8 at 5 (an offeror is responsible for
affirmatively demonstrating the merits of its proposal and risks
rejection of its proposal if it fails to do so).
(B-299721.4, The Mangi Environmental Group, Inc., January 24,
2008. (The Mangi Environmental
Group, Inc., B-299721.4, January 24, 2008) (pdf)
In responding to
the sample task orders, offerors were asked to identify the
composition of the contractor team that would be used to perform
the task. This required listing the prime contractor, the lead
subcontractor (if not the prime) and all other companies that
would be involved. Offerors were then instructed to describe how
the proposed contractor team would perform the sample task by
indicating which company would perform which parts of the team
effort. In addition, the RFP required that the proposal describe
up to three team examples of experience. VetTech in its response
to Task Order 1, listed itself, Cepeda Systems & Software
Analysis, Inc. (CSSA) and Sparta, Inc. as the team members
VetTech proposed to support this task order, however, the
task-related experience examples provided by VetTech identified
the experience of individuals employed by Computer Sciences
Corporation, MagnaCom and CSSA. VetTech Proposal, Vol. IV, at
IV-1-2. The agency found VetTech’s response deficient because
VetTech failed to provide the related experience of individuals
employed by team members proposed to support the task orders.
Consequently, the agency could not determine whether VetTech’s
proposed team members themselves had the required task-related
experience. Likewise, with Task Order 2, VetTech listed
CSC, Sparta and VetTech as the team members to support this task
order, however, VetTech only identified the experience examples
as those of the “VetTech team member” and did not identify which
specific team member possessed the task-related experience. Id.
at IV-2-2. In its protest to our Office, VetTech argues that
there was no requirement that the proposed individuals with
task-specific experience had to be employed by the companies
designated to support the tasks, and thus its proposal met the
RFP requirement. We disagree with VetTech’s assertion. While
VetTech argues that there was no requirement to provide this
information, the RFP did require that the offeror identify at
least three team examples of task-related experience. VetTech’s
proposal was unclear as to which team members would be
performing the work and failed to provide the task specific
experience of the team member.
It is incumbent upon the protester to submit a response to the
sample task orders that clearly demonstrated that it understood
the requirement and proposed a plan, with appropriate team
members, that detailed its ability to satisfactorily perform the
task. An offeror has the responsibility to submit a well-written
proposal, with adequately detailed information, which clearly
demonstrates compliance with the solicitation requirements and
allows a meaningful review by the procuring agency. CACI Techs.,
Inc., B-296946, Oct. 27, 2005, 2005 CPD para. 198 at 5. In this
regard, an offeror must affirmatively demonstrate the merits of
its proposal, and risks the rejection of its proposal if it
fails to do so. HDL Research Lab, Inc., B-294959, Dec. 21, 2004,
2005 CPD para. 8 at 5. Where a protester challenges an agency’s
evaluation of a proposal’s technical acceptability, our review
is limited to considering whether the evaluation is reasonable
and consistent with the terms of the RFP and applicable
procurement statutes and regulations. National Shower Express,
Inc.; Rickaby Fire Support, B‑293970, B-293970.2, July 15, 2004,
2004 CPD para. 140 at 4-5. On this record, we find no basis to
question the reasonableness of the agency’s determination that
VetTech’s proposal failed to meet the solicitation requirements.
(Veterans Technology, LLC,
B-310303.2, January 7, 2008) (pdf)
Benchmade also
challenged the agency’s use of SF 26 to make a split award. The
protester argues that because the agency did not obtain the
awardee’s consent to use SF 26 and its signature on it, there
was no legally binding agreement between those two parties. The
language of the RFP, noted above, put prospective offerors on
notice that the agency considered it proper to make a split
award using the SF 26; in fact, Benchmade’s own contract for the
other knife under the RFP was issued using SF 26 as well.
Benchmade raised this challenge to the terms of the RFP in a
supplemental protest filed May 29, 2007, well past the
solicitation closing date of November 17, 2006; this protest
ground is therefore untimely. See 4 C.F.R. sect. 21(a)(1)
(2007). Benchmade’s argument that the language of the RFP was
too speculative to form the basis of a protest is unpersuasive,
given the agency’s clearly stated position in the RFP that it
reserved the option to make a split award using SF 26. (Benchmade
Knife Co., Inc., B-299366.3, B-299366.4, July 16, 2007) (pdf)
The agency
explains that Beck’s proposal was downgraded--it received 10 of
the 50 available points--for a number of weaknesses, only one of
which was its failure to propose any use of helicopters. In this
regard, the RFP notified offerors that some of the project sites
were in very rugged terrain with deep drainages and steep
slopes, RFP sect. C.1.4.1, and called for offerors to inspect
the sites prior to submitting proposals. RFP sect. L, para.
52.237-1. The agency explains that its policy is not to specify
the type of aircraft to be used, and the RFP clearly provided
that the tools and equipment used for application of herbicides
was at the contractor’s discretion. RFP sect. C.5.1.2. The
agency considered fixed-wing aircraft appropriate for some of
the applications here, but believed that helicopters would be
better suited to others. Beck’s maintains that it can accomplish
all of the work with fixed-wing aircraft, and that it thus was
improper to downgrade its proposal for this reason. However,
Beck’s brief technical proposal--a cover letter and list of
references--did not address in any detail the firm’s experience
or ability to make fixed-wing applications over all types of
terrain to be encountered under the contract. Further, as noted
by the agency, Beck’s proposal was downgraded for a variety of
weaknesses--not just the failure to propose the use of
helicopters--including its overall lack of detailed information.
The RFP required offerors to provide evidence of their ability
to perform the project, cautioning them that sufficient
information had to be presented to enable the agency to evaluate
the firms’ qualifications. RFP sections L.1.1, L.1.2. In this
regard, it called for offerors to submit resumes that included a
narrative description of the offeror’s noxious weed control
background, experience and performance on its three most recent
jobs, and related work experience. RFP sect. L.2.3. While Beck’s
proposal identified, for example, experience with various
noxious weeds, it included no resumes or other narrative
describing Beck’s noxious weed control background. Likewise,
while the proposal stated that Beck’s pilot was qualified to
read maps, and proposed to use the global positioning system
(GPS)--as required by RFP sect. C.3.6--it included no
information explaining how its GPS would translate ground
information or who would operate it. We find nothing
unreasonable in the agency’s conclusion that applications by
helicopter may be necessary under the contract--and its
downgrading of Beck’s proposal accordingly. Likewise, since
Beck’s did not address other areas of the RFP in its limited
proposal, there is no basis for us to object to the agency’s
downgrading the proposal on that basis under the technical
capabilities factor. An offeror has the burden of submitting an
adequately written proposal and runs the risk that its proposal
will be evaluated unfavorably where it fails to do so. Carlson
Wagonlit Travel, B‑287016, Mar. 6, 2001, 2001 CPD para. 49 at 3,
6. (Beck's Spray Service, Inc.,
B-299816,August 9, 2007) (pdf)
Throughout
Wizdom’s protest, there appear express and implicit assertions
that the agency should have considered information that Wizdom
believes is, or should have been, general knowledge regarding
Wizdom’s experience, capabilities, or how Wizdom intended to
perform this contract. In this regard, an offeror/vendor bears
the responsibility to submit an adequately written
proposal/quotation that includes sufficiently detailed
information to affirmatively demonstrate that the offeror/vendor
will comply with the solicitation requirements. ADC, Ltd.,
B-297061, Oct. 14, 2005, 2005 CPD para. 178 at 5. To the extent
Wizdom’s protest is based on the premise that the agency should
have considered information that was not provided within
Wizdom’s quotation, the protest is without merit. (Wizdom
Systems, Inc., B-299829, August 3, 2007) (pdf)
GTI argues that
the TEC’s determination that its proposed IP telephones were not
currently available in the United States was improper. The
protester contends that its proposal made no representation with
respect to the availability dates for its OpenStage
telephones,[5] and, as a result, the agency evaluators could not
reasonably conclude that GTI’s proposed telephones were
unavailable without first confirming the matter with either GTI
or the telephone’s manufacturer. Comments, May 14, 2007, at 9.
GTI’s argument here reflects a fundamental misunderstanding of
the proposal process. It is an offeror’s responsibility to
submit a well-written proposal, with adequately detailed
information, which clearly demonstrates compliance with the
solicitation requirements and allows for a meaningful review by
the procuring agency. CACI Techs., Inc., B-296946, Oct. 27,
2005, 2005 CPD para. 198 at 5. An offeror is responsible for
affirmatively demonstrating the merits of its proposal and risks
the rejection of its proposal if it fails to do so. HDL Research
Lab, Inc., B-294959, Dec. 21, 2004, 2005 CPD para. 8 at 5. Here,
since it was GTI’s responsibility to establish the timely
availability of its proposed IP telephones--not, as the
protester argues, the evaluators’ responsibility to establish
unavailability--and GTI admittedly failed to do so, we find the
agency’s evaluation to be entirely reasonable. (Government
Telecommunications, Inc., B-299542.2, June 21, 2007) (pdf)
Our review of HealthStar’s proposal indicates that the
assignment of these two weaknesses was well-founded.
Nevertheless, HealthStar, the incumbent contractor, complains
that it was not evaluated in a reasonable manner because the
agency should have considered its knowledge of its incumbent
contract performance in evaluating these areas. In its protest
filings addressing the patient-focused care weakness, HealthStar
details in its protest a plethora of patient-focused services,
which were admittedly not identified in its proposal due to page
constraints. With regard to the other significant weakness,
HealthStar asserts that its proposal stated that all
professional staff were licensed, in good standing, credentialed
in the Veterans Administration system, and that copies, while
not included in its proposal, were available on file in the
Central Arkansas Veterans Healthcare System or would be provided
upon request; again, HealthStar asserts that the agency was
aware of these licenses because of its incumbent status, which
were not submitted due to the page limitations. An offeror’s
technical evaluation is dependent upon the information
furnished; there is no legal basis for favoring a firm with
presumptions on the basis of its incumbent status. It is the
offeror’s burden to submit an adequately written proposal; an
offeror, including an incumbent contractor, must furnish, within
its proposal, all information that was requested or necessary to
demonstrate its capabilities in response to the solicitation.
Computerized Project Mgmt. Plus, B-247063, Apr. 28, 1992,
92-1 CPD para. 401 at 3. Based on this record, the agency’s
assignment of the two weaknesses to HealthStar’s proposal
because it did not provide the information requested by the RFP
was reasonable. (HealthStar VA,
PLLC, B-299737, June 22, 2007) (pdf)
Mathews Associates, Inc. protests the rejection of its proposal
submitted in response to request for proposals (RFP) No.
W15P7T-06-R-N204, issued by the Department of the Army’s
Communications-Electronics Life Cycle Management Command to
procure loudspeakers and battery boxes for use in the Single
Channel Ground and Airborne Radio System. Mathews argues that
the Army unreasonably rejected its proposal after concluding
that every page of the proposal exceeded the solicitation’s
specified margin limitations. The solicitation instructions
limited proposals to 25 pages, specified the margin settings and
font sizes to be used, and required that proposals be submitted
electronically. As the Army notes, there is no dispute here that
every page of the protester’s proposal exceeded the margin
limitations in the solicitation, and that the solicitation
clearly advised that no page that exceeded the margin, font, or
page limitations would be read. In addition, while conceding the
relative technical ease with which reformatting could be
accomplished, the Army raises several concerns about the impact
of a decision holding that it was required to reformat the
protester’s proposal, or allow the protester to do so. Among the
concerns the Army raises is the potential dispute between it and
Mathews about how the reformatting should be accomplished. In
the Army’s view, any reformatting should only involve a change
to the margin settings in the electronic document, which, it
claims, would add four pages to the proposal. In the protester’s
view, the Army should not only change the margins in its
submission, but should make some additional changes to spacing
and headings that would allow the proposal to meet the 25-page
deadline. Alternatively, the protester argues that the Army
should change the margins and simply not read the portion of the
proposal that exceeds the page limitation. In our view, the
protest here is rendered a closer call than it might have been
several years ago because of the nature of electronic
submissions. For example, in 1991 our Office considered a
protest from an offeror that had disregarded both a
solicitation’s page limitation and the requirement that
proposals be double-spaced. After 59 pages of the protester’s
117-page submission were not read--with the expected negative
result on its competitive posture--the protester argued that it
“could retype the proposal using double space in a few days.”
Our Office held that the agency was not required to give the
protester a few more days to retype its proposal. All Star Maint.,
Inc., B-244143, Sept. 26, 1991, 91-2 CPD para. 294 at 4. In
contrast, the agency here would not be required to wait for a
reformatted proposal, and could, in fact, complete the
reformatting itself in a matter of minutes, without the
offeror’s involvement. The question before us, however, is not
what the agency could do, but what it was required to do. Viewed
in this light, we do not think the Army was required to
reformat, or allow Mathews to reformat, the proposal. We note
first that, as in All Star Maint., Inc., the solicitation
requirements at issue in this protest are clear, and were not
contested by the protester. In addition, there is no dispute
about the facts of this case--the proposal here did not contain
a single page that complied with the solicitation’s margin
requirements. Simply put, we know of no reason why an agency
should be required to allow an offeror to reformat its proposal
when the solicitation’s requirements were so clear. While the
protester asserts that reformatting--or allowing the protester
to reformat--its proposal does not appear to pose a significant
risk of unfairness to other offerors, that view does not
translate into a requirement that the agency take such action,
given the RFP’s clear instructions regarding formatting and the
consequences of not complying with those instructions. In
addition, we think the record here supports the agency’s
contention that the approach urged by Mathews raises the
possibility of further disputes about the manner in which the
reformatting is accomplished. In our view, the agency should not
be forced to assume the risk of such potential disruptions to
the procurement due to the reformatting made necessary by
Mathews’ failure to comply with the unequivocal requirements of
the RFP. Finally, we recognize that many of our prior cases,
cited by both the Army and the protester, involve situations
where agencies took less severe action than in this case. See,
e.g., Client Network Servs., B-297994, Apr. 28, 2006, 2006 CPD
para. 79 at 8 (agency reasonably downgraded proposal for failing
to comply with the solicitation’s formatting requirements). On
balance, however, we think there is nothing unfair, or unduly
burdensome, about requiring offerors to assume the risks
associated with submitting proposals that do not comply with
clearly stated solicitation formatting requirements. Id.;
Coffmann Specialties, Inc., B-284546, B‑284546.2, May 10, 2000,
2000 CPD para. 77 at 3. (Mathews
Associates, Inc., B-299305, March 5, 2007) (pdf)
It is an offeror’s responsibility to submit a well-written
proposal, with adequately detailed information, which clearly
demonstrates compliance with the solicitation requirements and
allows a meaningful review by the procuring agency. Ace Info.
Solutions, Inc., B-295450.2, Mar. 7, 2005, 2005 CPD para. 75 at
8; Communications Data Sys. Assocs., B-223988, Oct. 29, 1986,
86-2 CPD para. 491. Procuring agencies have considerable
discretion in evaluating technical proposals and, in reviewing
protests challenging an agency’s evaluation of technical
requirements, our Office will not reevaluate offerors’
proposals; rather, our review is limited to considering whether
the agency’s evaluation of competing proposals was reasonable,
consistent, and in accord with law, regulation and the terms of
the solicitation. L-3 Communications Westwood Corp., B-295126,
Jan. 19, 2005, 2005 CPD para. 30 at 5. A protester’s mere
disagreement with an agency’s judgment is not sufficient to
establish that the agency acted unreasonably. Purification
Indus., Inc., B-261984, Sept. 20, 1995, 95-2 CPD para. 143 at 5.
Here, the portion of CACI’s proposal responding to the “E.5”
requirement only addressed “reconstruction” efforts on a
particular contract performed at Andersen Air Force Base, Guam.
In pursuing this protest, CACI expressly recognizes that the
“reconstruction” efforts described in its proposal necessitated
the engineering and professional service that the solicitation
sought, acknowledging that “an engineering firm had to design
this work and make sure that it was environmentally safe, that
necessary permits were obtained, and that health risks were
minimized.” Protester’s Comments, Sept. 6, 2005, at 15. Rather
than discussing the capabilities the solicitation sought, CACI’s
proposal merely referred to construction activities
(installation of generators, replacement of blast doors, and
burial of electrical lines)--work the PWS expressly provided
could only be “incidental” to contract performance. On this
record, we find no basis to question the reasonableness of the
agency’s determination that CACI’s proposal failed to meet the
solicitation requirements. (CACI
Technologies, Inc., B-296946, October 27, 2005) (pdf)
Offerors bear the responsibility to submit an adequately written
proposal with sufficiently detailed information to establish
that their proposals will meet the solicitation requirements.
G&M Indus., B-290354, July 17, 2002, 2002 CPD para. 125 at 4. An
offeror is responsible for affirmatively demonstrating the
merits of its proposal and risks the rejection of its proposal
if it fails to do so. Knoll, Inc.; Steelcase, Inc., B-294986.3,
B-294986.4, Mar. 18, 2005, 2005 CPD para. 63 at 3. Based on our
review of ADC’s proposal, we conclude that the agency reasonably
determined that ADC did not specifically address how it would
meet the required human resource requirements in the SOO. ADC’s
proposal does not explain in detail its approach to performing
the SOO requirements; at most, ADC’s proposal affirms that it
has the capability to meet the agency’s needs, citing as
evidence its experience in performing background clearance work,
which ADC now contends should have been considered analogous to,
or encompassed within, the scope of human resource requirements
in the SOO. See AR, Tab 16, ADC Proposal, at 7-9; Protest at
8-9. Accordingly, we believe that the agency reasonably
determined that ADC’s proposal was technically unacceptable. (ADC,
Ltd., B-297061, October 14, 2005) (pdf)
With regard to the descriptive information not considered by
DOE, as noted above, Sayres provided this information as an
attachment to its proposal. Because these pages exceeded the
proposal page limit established by the RFP, the agency did not
consider them. Sayres contends that the RFP contemplated that
descriptive information such as this would be excluded from the
proposal page limit as it was contemplated by the Reference
Information Sheets. Although the Reference Information Sheets
did in fact contain a block where offerors were to provide a
"description of work," Sayres completed this block. The pages
not considered, about which Sayres complains, were separate from
these forms and contained information such as how Sayres' past
performance satisfied the past performance subfactors, which
information was required by the RFP to be contained within the
20 pages of the proposal. See RFP L.16(b)(2), (c)(3).
Furthermore, in an amendment to the RFP, offerors were advised
that past performance descriptions were to be part of the
proposal and were subject to the proposal page limit. RFP amend.
1, Q&A 28 ("Are past performance descriptions included in the 20
page limit for Vol. 2? . . . Yes"). Since the agency's failure
to consider this information was consistent with the RFP's
requirement, and consistent with how it treated other offerors
whose proposals exceeded the page limit, we find no basis to
question DOE's evaluation in this regard. See Centech Group,
Inc. , B-278904.4, Apr. 13, 1998, 98-1 CPD 149 at 5. (Sayres
& Associates Corporation, B-295946; B-295946.2, April 25,
2005) (pdf)
LB&B's proposal under the staffing and authority factor by
failing to take into account awardee's failure submit all
required information for its proposed [deleted]. In this regard,
the RFP instructed offerors to submit an organizational chart
showing the names and titles of proposed key managerial and
supervisory personnel and describing their respective
authorities and responsibilities, as well as their
qualifications and experience. RFP at 247, 2.B.1. In addition,
offerors were to submit resumes for the on-site project manager
and all other on-site supervisors, as well as indicate if those
persons were in the offeror's employ or "if not, what
commitments have been made to hire them." RFP at 248-250.
Offerors were required to furnish a dedicated [deleted], who
were considered "supervisory employees," Statement of Work,
12.1.A.1, 12.1.B.4.A. LB&B's revised proposal did not name its
proposed [deleted], and did not identify their authorities or
responsibilities, describe their qualifications, resumes, or
include employment commitment information. However, LB&B
proposed to hire the [deleted] under the current contract, and
GSA was acquainted with these individuals and their job
performance, and possessed their resumes from the protester's
and another offeror's proposals. GSA found LB&B's proposal
acceptable based on this information. The protester maintains
that this was improper. An agency is not bound by the "four
corners" of an offeror's proposal in the evaluation of proposals
and may use other information of which it is aware. Forest
Regeneration Servs. LLC , B-290998, Oct. 30, 2002, 2002 CPD 187
at 6. Since the agency here was aware of the resumes and
qualifications and experience information omitted from LB&B's
proposal, those omissions were of no import. While LB&B's
proposal also did not include a description of the [deleted]
responsibilities, LB&B's organizational chart did show
[deleted]. AR, Tab 15, at B-2. Park Tower's proposal went
further than LB&B's, specifically stating [deleted] (AR, Tab 11
at SP 7; Tab 14, 3.B), and that [deleted] (AR, Tab 11 at SP 9;
Tab 14, 3.B). In our view, the listed responsibilities are
fairly self-evident from the nature of the contract and the
titles of the positions, and reasonably could be viewed by the
agency as adding little substantive value relative to LB&B's
proposal, particularly given that LB&B was proposing the
individuals who were currently performing the [deleted]
responsibilities. This being the case, even had the evaluators
downgraded LB&B's proposal for omitting this information, there
is no reason to believe it would have had any significant impact
on LB&B's score or the source selection. (Park
Tower Management Ltd., B-295589; B-295589.2, March 22, 2005)
(pdf)
In sum, HUD found that DIY's proposal was disorganized and
contained insufficient detail to demonstrate that DIY fully
understood the requirements. AR, Tab 4, Initial TEP Report, at
192-193, 203, 206. While DIY disagrees with the agency's
conclusions, it does not in any meaningful way rebut them, and
has not otherwise shown that the evaluation was unreasonable.
Under these circumstances, we have no reason to object to the
agency's evaluation. Since the evaluation is unobjectionable,
and DIY's standing relative to the other offerors therefore
remains the same as when the agency made its competitive range
determination, we have no reason to question the agency's
excluding DIY's proposal from the competitive range. Wahkontah
Servs., Inc., B-292768, Nov. 18, 2003, 2003CPD 214 at 7. (DIY,
Inc., B-293105.13, February 7, 2005) (pdf)
In evaluating HDL's proposal, the evaluators found seven
weaknesses and eight deficiencies, including five deficiencies
under the design subfactor. The deficiencies, and many of the
weaknesses, were principally based on the firms failure to
satisfy various informational requirements in its proposal. For
example, despite the RFP's requirement for detailed information,
HDL's proposal lacked any information on its parts obsolescence
program; did not address the required stacking requirement; did
not address expedited returns; and did not make clear its
maximum/available facilities production capacity or identify the
labor force necessary for support of full production. An offeror
is responsible for affirmatively demonstrating the merits of its
proposal and risks the rejection of its proposal if it fails to
do so. Arctic Slope World Servs. , B-284481, B-284481.2, Apr.
27, 2000, 2000 CPD 75; DBA Sys., Inc., B241048, Jan.15, 1991,
911 CPD 36 at 4. In our view, the agency reasonably concluded
that these and other deficiencies and weaknesses were sufficient
to render HDL's proposal unacceptable under the technical factor
and only susceptible to being made acceptable under the
management factor. Since the RFP provided that proposals must be
found acceptable under all subfactors in order to be in line for
award, the agency properly rejected HDL's proposal. HDL suggests
that the agency should have conducted discussions to provide HDL
an opportunity to correct the identified deficiencies. However,
there generally is no obligation for an agency to conduct
discussions where, as here, the RFP specifically instructs
offerors of the agency's intent to award a contract on the basis
of initial proposals. FAR 15.306(a)(3); Colmek Sys. Engg ,
B291931.2, July 9, 2003, 2003CPD 123 at 7. The contracting
officers discretion in deciding not to hold discussions is quite
broad. Our Office will review the exercise of that discretion
only to ensure that it was reasonable based on the particular
circumstances of the procurement. Id. We find no circumstances
here that call into question the agency's decision not to engage
in discussions. (HDL Research Lab,
Inc., B-294959, December 21, 2004) (pdf)
Carpetmasters proposal listed nine experience/past performance
references; of those, only six listed janitorial and/or grounds
keeping, and of those six, only two were within the 3-year time
frame. AR, ex. 6, Carpetmaster Proposal, at 12-13. Those two
references within the time frame were for janitorial and
campground cleanup for the U.S. Army Corps Of Engineers, and
various janitorial contracts for the City of Las Vegas. Id. at
13. Neither of these references, however, listed all of the
information required under the RFP, omitting contract numbers,
dates of performance other than years, contract values, and
details regarding the work, other than general descriptions (
e.g. , janitorial work). See id. at 15. The agency determined
that the Corps and Las Vegas references were relevant and
credited Carpetmaster with providing two of the three required
experience references. SAR, attach. 4, Technical Ratings
Summaries; SAR, attach. 3, Technical Proposal Notes, at 2-3.
Based on Carpetmasters failure to provide three relevant
experience references, the agency severely downgraded its
proposal. SAR, attach. 2, Technical Evaluation Team Report, at
2. The protester primarily argues that its reference for various
janitorial contracts with the City of Las Vegas should have been
interpreted and credited as more than a single experience
reference. We disagree. It is an offerors responsibility to
submit a proposal with adequately detailed information to allow
a meaningful review by the agency. Interstate Gen. Govt
Contractors, Inc. , B-290137.2, June 21, 2002, 2002 CPD 105 at
5. Here, Carpetmasters reference for various janitorial
contracts with the City of Las Vegas did not provide the
information requested under the RFP. Although the agency found
that the reference to the various Las Vegas janitorial contracts
merited credit as a single reference, we do not believe that the
agency acted unreasonably, given the lack of detailed
information, in declining to credit the reference as multiple,
relevant contracts. (Carpetmaster,
B-294767, November 4, 2004) (pdf)
The solicitation here provides for a best-value-type evaluation;
therefore, it is the vendor's burden to submit a quotation that
is adequately written and establishes the merits of the
quotation, or run the risk of the agency rejecting the quotation
as technically unacceptable. RVJ Int'l, Inc. , supra , at 6; see
Cybernet Sys. Corp. , B292600, Sept. 30, 2003, 2003 CPD 171 at
3-4. An agency may exclude from further consideration a response
to a solicitation that contains significant informational
deficiencies, whether the deficiencies are attributed to omitted
information or merely inadequate information addressing
fundamental factors. Cybernet Sys. Corp. , supra. We
conclude that the agency reasonably determined that Verizon's
technical quotation was unacceptable for failure to include
adequate evidence as required under the RFQ demonstrating the
qualifications of the staff that would perform the contract.
We further find that the Marine Corps reasonably determined that
Verizon's quotation did not satisfy the RFQ requirement to
demonstrate the qualifications of its staff. The SOW estimate
for total labor hours per year would require more than one FTE
in 3 of the 11 labor categories, i.e. , fiber technician, inside
plant technician and outside plant technician. Verizon, however,
furnished only 10 resumes for 11 labor categories. Verizon did
not submit a resume for the CAD drafter labor category, and it
submitted only 1 resume for each of the 3 labor categories that
would require multiple FTEs. In addition, the 10 resumes
submitted did not identify names of staff members. Although the
resumes did identify employment histories, they generally lacked
depth of detail, with 7 of the 10 resumes submitted including
only a half page or less of text. Verizon Technical Quotation at
43-55. (Verizon Federal, Inc.,
B-293527, January 15, 2004) (pdf)
It is incumbent on an offeror to submit a complete and
adequately detailed technical proposal for the agency to
evaluate. Dimensions Int'l/QSOFT, Inc. , B-270966, B270966.2,
May 28, 1996, 96-1 CPD 257 at 5. No matter how competent an
offeror's past performance may have been, an agency may
reasonably base an offeror's technical evaluation entirely on
the information submitted with the proposal. Id. This is
particularly true where the requirements for the contract being
competed differ from requirements that were previously
performed. Here, the fact that CHS's past performance was rating
"outstanding does not eliminate CHS's obligation to provide
adequate explanation and detail substantively addressing the
agency's various concerns regarding performance of the contract
requirements being competed here. To the extent CHS is
protesting that the agency was required to consider its past
performance as, in essence, a proxy for providing the
otherwise-required information in its proposal, the protest is
without merit. (Comprehensive Health
Services, Inc., B-292858.3; B-292858.6; B-292858.7, April
27, 2004) (pdf)
Where protester submitted proposal
that failed to comply with requirement that type be no smaller
than 12 pitch, agency's reformatting of the proposal into
required type size--as a result of which, proposal exceeded the
30-page limit--was unobjectionable, where agency's reformatting
approach was reasonable. (Integrated
Technology Works, Inc.-Teltara, Inc., B-286769.5, August 10,
2001)
Agency reasonably downgraded
proposal that failed to comply with solicitation's formatting
requirements, including limits on the number of pages and
projects to address particular evaluation subfactors. (Coffman
Specialties, Inc., B-284546; B-284546.2, May 10, 2000)
|