HOME  |  CONTENTS  |  DISCUSSIONS  BLOG  |  QUICK-KITs|  STATES

Google

       Search WWW Search wifcon.com

FAR 15.404-1 (g):  Unbalanced pricing

Comptroller General - Key Excerpts

Unbalanced pricing exists where the prices of one or more line items are significantly overstated, despite an acceptable total evaluated price (typically achieved through underpricing of one or more other line items). See Federal Acquisition Regulation (FAR) sect. 15.404‑1(g)(1); Legacy Mgmt. Solutions, LLC, B‑299981.2, B-299981.4, Oct. 10, 2007, 2007 CPD para. 197 at 5; Triple H Servs., B-298248, B-298248.2, Aug. 1, 2006, 2006 CPD para. 115 at 2.

Here, JND has produced no definitive evidence that CJW's prices are significantly overstated. While higher than the IGE and JND's prices, CJW's price for line item No. 3 is lower than that of bidder Furby Construction Co., Inc. and its line item No. 9 price is lower than that of bidder Cutting Edge Concrete Services, Inc. See Reece Contracting, Inc., B‑285666, Aug. 21, 2000, 2000 CPD para. 135 at 4 (prices not overstated where they fall within range of government estimate and other bids). Similarly, JND has not shown that CJW's $.01 prices for line item Nos. 4 and 10 are understated. In this regard, the agency accepted CJW's explanation that its lower prices were based on its intent to cover its costs through sale of salvaged material. Agency Report (AR) at 5. Below-cost prices on fixed-price contracts are not prohibited, see Reece Contracting, Inc., supra, at 2 n.1, and whether a bidder can perform at its bid price is a matter of bidder responsibility, which is not reviewable by our Office absent circumstances not present here. See Bid Protest Regulations 4 C.F.R. sect. 21.5(c) (2009); Ventura Petroleum Servs., Inc., B‑281278, Jan. 21, 1999, 99-1 CPD para. 15 at 6.

In any case, even where a firm's pricing is found to be unbalanced, an agency need not reject the bid if, after conducting a risk analysis, it determines that award will not result in the government's paying an unreasonably high price for contract performance or otherwise present an unacceptable level of risk to the government. See FAR sect.15.404-1(g)(2), (3).

The record shows that the agency conducted a risk assessment, considering information from CJW, its prior experience with the bidder, and the anticipated order of work. For example, in response to the agency's inquiries, CJW confirmed its bid and its intent to perform all work in accordance with the IFB's specifications. Engineer's Memorandum para. 4. In connection with its $.01 prices for line item Nos. 4 and 10, CJW explained that it had a buyer for at least 177,000 CY of material (the amount identified in the IFB as salvageable and a cost benefit to bidders); that profit from the sale would cover its cost of re-handling the material; and that, even if it failed to sell all of the material, CJW expected that sale of a certain percentage would produce profits sufficient to cover re-handling of the remaining material. Id. As to other work, CJW had a history of good performance on a number of projects with another Corps district office, including a 2005 dredging job where CJW demonstrated its knowledge of the sediment market by successfully marketing all of the excavated sand. Id. para. 7. While the IFB did not specify the order of work, the agency's analysis showed that the contractor would have to excavate pond Nos. 4-7 (line item No. 3) in order to provide the necessary capacity to "store" the dredge material to be pumped from the lake (line item No. 9), and thus would have to re‑handle virtually all of the dry excavated material (line item No. 4) prior to dredging. AR at 7. Further, payment for dredging (line item No. 9) would not be made in a lump sum but, rather, would be based on the percentage of dredging completed, and the agency anticipated that a portion of the dredged material would have to be re-handled (line item 10) prior to completion of the dredging process. Engineer Declaration paras. 4, 6. At the time dredging is complete, the agency estimates that various aspects of the work--worth more than $1 million--will remain to be completed and paid for, including final excavation of pond Nos. 4-7, final levee construction, and riprap/crushed rock placement. Id. para. 7.

Based on its consideration of the above information, the agency concluded that CJW's bid did not pose a significant risk of non-performance or the payment of unreasonably high prices. Contracting Officer's Statement paras. 17-18; AR at 8. In our view, the agency's conclusion was reasonable, since CJW's plan to offset the cost of re-handling excavated and dredged material represented a plausible explanation for its low prices; its conclusion was based on prior experience with CJW in which the firm had successfully performed contracts involving the sale of salvage material; and the expected order of work will effectively prevent payment for all of the allegedly overstated line items prior to performance of much of the understated items and will include other contract line items providing incentive to continue performance.  (JND Thomas Company, Inc., B-402240, January 28, 2010) (pdf)

Noting that Wind River submitted significantly higher prices (than Cherokee’s) on 4 CLINs and significantly lower prices on 18, Cherokee asserts that Wind River’s proposed CLIN pricing is unbalanced, Protest at 3-8, and poses “a risk to Tinker Air Force Base which could cost the government additional funds during the life of this contract.” Protester’s Comments at 2. Cherokee concludes that Wind River’s proposal should have been rejected.

Unbalanced pricing exists where, despite a proposal’s low overall price, individual line item prices are either understated or overstated. Federal Acquisition Regulation (FAR) sect. 15.404-1(g); Semont Travel, Inc., B-291179, Nov. 20, 2002, 2002 CPD para. 200 at 3. While unbalanced pricing may increase risk to the government, agencies are not required to reject an offer solely because it is unbalanced. FAR sect. 15.404-1(g)(1). Rather, where an unbalanced offer is received, the contracting officer is required to consider the risks to the government associated with the unbalanced pricing in making the award decision, including the risk that the unbalancing will result in unreasonably high prices for contract performance. FAR sect. 15.404-1(g)(2). In the context of an ID/IQ contract, as here, a key consideration is the accuracy of the government’s quantity estimates; if the estimates are reasonably accurate, then evidence of mathematical unbalancing generally does not present a risk that the government will pay unreasonably high prices for contract performance. Accumark, Inc., B-310814, Feb. 13, 2008, 2008 CPD para. 68, at 4.

Cherokee does not challenge the accuracy of the agency’s estimated quantities. Moreover, we find nothing in the record to suggest that the agency was concerned about the accuracy of its estimated quantities. Where a protester does not challenge the estimated quantities used in the calculation of total item prices, there is no basis in the record for us to find a risk that the agency will pay unreasonably high prices for the items; it follows that, in such cases, there is no basis for us to object to mathematically unbalanced pricing. See Accumark, Inc., supra, at 4.

In any event, even if the estimates were in question, as noted above, the agency conducted a risk assessment and determined that the risk associated with Wind River’s pricing strategy was acceptable. In this regard, the CO analyzed the risk in two ways: by cost comparisons with recent delivery orders and by total maximum cost. AR, Tab 1, Memorandum of Law, at 8. Specifically, the CO compared each CLIN price with the corresponding IGE price and then conducted an analysis of five recent delivery orders under the current contract, which showed that Wind River’s prices would result in a lower cost than the IGE on four of the five. AR, Tab 12, Final Price Competition Memorandum, at 15 (not released to the protester). The CO also assessed the maximum possible liability to the Air Force by comparing the maximum cost under each IGE price with the maximum cost under each of Wind River’s CLIN prices. AR, Tab 1, Memorandum of Law, at 8. Other than asserting generally that Wind River’s pricing may pose a risk to the agency, Cherokee does not challenge this risk assessment, and we find no basis for questioning it. Thus, to the extent that Wind River’s pricing may be viewed as unbalanced, the agency has satisfied the FAR requirement by reasonably determining that the risks of any unbalancing were not significant enough to render its offer unacceptable. (Cherokee Painting LLC, B-311020.3, January 14, 2009) (pdf)


PEMCO's prices were not unbalanced, since any overstatement of its CLIN 0001 price was not significant. PEMCO's CLIN 0001 price was only 23 percent higher than the government's estimate; this is not an amount significant enough to require that the offer be considered unbalanced. Cf. Baxter Healthcare Corp.; Abbott Labs.--Recon. , B253455.3, B253455.4, May 10, 1994, 941 CPD 301 at 4, n.2 (base year price 44 percent above option year prices did not constitute impermissible frontloading). In any case, the agency fully discussed the CLIN 0001 pricing with PEMCO, and ultimately determined that it was reasonable; this satisfied the agency's obligation to ensure that the pricing did not pose an unacceptable risk. See PharmChem, Inc. , B-291725.3 et al., July 22, 2003, 2003 CPD 148 at 8. (Diversified Capital, Inc., B-293105.4; B-293105.8, November 12, 2004) (pdf)


There is no basis for concluding that STL’s pricing is unbalanced. PharmChem does not identify any specific prices that it believes are significantly overstated and the record does not indicate that any of STL’s prices are overstated. In this latter regard, for example, in the base year, STL’s line item prices exceed the government estimate under only 4 of 13 line items. Further, while STL’s proposal of $0.00 for [deleted] labor categories could be considered “understated,” such labor rate proposals alone do not establish that a bid is unbalanced. See SMC Info. Sys., B-224466, Oct. 31, 1986, 86-2 CPD ¶ 505 at 5. In any case, even if STL’s labor rate pricing evidenced unbalancing, it is clear that the agency considered the risk involved; it specifically inquired about STL’s $0.00 labor rate pricing, and had no concern that these rates would result in a higher contract price. Source Selection Decision at 6-7.  (PharmChem, Inc., B-291725.3; B-291725.4; B-291725.5, July 22, 2003)  (pdf)


While the agency here analyzed the unbalancing in terms of an "advance payment," that term does not appear in the discussion of unbalanced pricing in the revised Part 15 of the FAR, which applies to solicitations issued after January 1, 1998, such as the subject IFB. We believe, however, that the agency's analysis remains valid when couched in terms of the risk that IBI's pricing poses to the government.  (Industrial Builders, Inc., B-283749, December 29, 1999)


The Navy was satisfied, based on Phillips's response and Phillips's extensive experience performing housing maintenance contracts, that the rationale behind Phillips's pricing was sound, and that Phillips was aware of the risks involved in that strategy. The Navy also concluded from Phillips's explanation that its pricing was fair and reasonable. ARLS at 7. While Red River disagrees with the Navy's conclusions, in our view, the Navy could reasonably conclude that Phillips's pricing represented a legitimate business judgement that did not pose an unacceptable risk to the government, and that it would not pay an unreasonably high price for performance. Accordingly, the Navy was not required to reject Phillips's proposal.  (Red River Service Corporation, B-282634; B-282634.2, July 15, 1999)

Comptroller General - Listing of Decisions

For the Government For the Protester
JND Thomas Company, Inc., B-402240, January 28, 2010 (pdf)  
Cherokee Painting LLC, B-311020.3, January 14, 2009 (pdf)  
Diversified Capital, Inc., B-293105.4; B-293105.8, November 12, 2004) (pdf)  
PharmChem, Inc., B-291725.3; B-291725.4; B-291725.5, July 22, 2003  (pdf)  
Semont Travel, Inc., B-291179, November 20, 2002  
Weber Cafeteria Services, Inc., B-290085.2, June 17, 2002  
HSG Philipp Holzmann Technischer Service GmbH, B-289607, March 22, 2002  (PDF Version)  
Duke Engineering & Services, Inc., B-284605, May 17, 2000  
MG Industries, B-283010.3, January 24, 2000  (pdf)  
Industrial Builders, Inc., B-283749, December 29, 1999  
Red River Service Corporation, B-282634; B-282634.2, July 15, 1999  
J&D Maintenance and Service, B-282249, June 18, 1999  
Joppa Maintenance Company, Inc., B-281579; B-281579.2, March 2, 1999  

U. S. Court of Federal Claims - Key Excerpts

The first query in this review is to determine if the bid was mathematically unbalanced; i.e., a bid based upon prices that are significantly less than cost for some work and prices that are significantly overstated in relation to cost for other work. Anderson Columbia Envtl., 43 Fed. Cl.at 700. This does not close the matter, however, because an agency may award a contract based upon a bid that is mathematically unbalanced if it does not lead to unacceptable risk to the government. Anderson Consulting v. United States, 959 F.2d 929, 933 (Fed. Cir. 1992); Gracon Corp. v. United States, 6 Cl. Ct. 497, 498 (1984).

The Federal Circuit has held that the determination of whether a bid is materially unbalanced is “something that is best known by the agency, for it is dependant on projected ordering patterns, and we therefore give broad discretion to contracting officers in deciding whether material imbalance is present or not in a proposal.” SMS Data Prod. Group, Inc. v. United States, 900 F.2d 1553, 1557 (Fed. Cir. 1990) (quoting SMS Data, 89-1 BCA ¶ 21,567, at 108,615).  (Southgulf, Inc. v. U.S., No. 00-352C, June 20, 2001)


J&D next argues that Ashe's bid required advance payments on indefinite quantity line items as a condition of acceptance. That is, that Ashe would receive advance payments for indefinite quantity items before such items were performed. Bids that truly require advance payments are to be rejected. 48 C.F.R. 32.405(b); Riverport Indus., Inc., 64 Comp. Gen. 441 (1985), 85-1 CPD ¶ 364, aff'd B-18656.2 (1985), 85-2 CPD ¶ 108; Barnard-Slurry Walls, 97-1 CPD ¶ 23 (Low bid properly rejected as materially unbalanced where lump sum price for preparatory work line item was many multiples higher than reasonable value of work, such that bid was grossly front-loaded, and unit price for work was significantly less than government estimate and other bid prices).

J&D reasons that Ashe structured its bid so it would receive advance payments. The Court does not find J&D's logic persuasive given the structure of Ashe's bid. Ashe will not be prepaid for any non-FFP work because all of the FFP costs are properly associated with the fixed quantities. BFPE International, B-248783, 92-2 CPD ¶ 206 (1992). Indeed, one of the reasons the Navy preferred Ashe's bid was a benefit [it provided], which "justifies the fixed price." AR 1466. The Navy accepted Ashe's pricing rationale. J&D has not shown the Navy's determination in this regard was inappropriate.  (J&D Maintenance and Services, v. U.S. and S. D. Ashe Landscaping and Services, Inc., No. 99-484C, December 28, 1999)

U. S. Court of Federal Claims - Listing of Decisions
For the Government For the Protester
Southgulf, Inc. v. U.S., No. 00-352C, June 20, 2001   
CCL Service Corporation, v. U.S. and Federal Data Corporation, No. 00-361C, October 24, 2000  
J&D Maintenance and Services, v. U.S. and S. D. Ashe Landscaping and Services, Inc., No. 99-484C, December 28, 1999  
Legal

Protests

Bona Fide Needs Rule
Public Laws
Legislation
Courts & Boards


Rules & Tools
Workforce
Reading

Small Business
 

   
 
 

ABOUT  l CONTACT