In its second supplemental protest, Colson further argued with
regard to the evaluation of its proposal under the technical
approach factor that the evaluators had incorrectly determined
in their evaluation report that its proposal had failed to
demonstrate compliance with the bonding, audit, and IT security
requirements set forth in section H of the RFP. The protester
also argued that the agency had treated the proposals of the two
offerors unequally in failing “to fully credit Colson for its
voluntary initiative to implement at its expense a
transformation initiative to upgrade, automate and modernize the
7(a) FTA system . . . , while giving RSG exceptional credit for
a similar system upgrade proposal . . . .” Second Supplemental
Protest at 5.
Regarding the former argument, the contracting officer explained
that she reviewed and considered the contents of both offerors’
proposals, as well as the evaluation team’s reports, in arriving
at her source selection decision, and thus was aware at the time
she made her decision that while Colson had not addressed the
bonding and audit requirements in its technical proposal,
leading to the finding of weakness by the technical evaluation
team, Colson had in fact addressed them in its business
proposal. That is, according to the contracting officer, she was
aware at the time of her source selection decision that the
weaknesses attributed to Colson’s proposal by the technical
evaluation team in these two areas were not in fact weaknesses,
and did not take them into consideration in her trade-off
determination. The contracting officer’s position is supported
by the contemporaneous source selection document, in which she
makes no mention of Colson’s non-compliance with the bonding and
audit requirements in summarizing the proposal’s strengths and
weaknesses. See AR Tab 32, Award Determination at 1.
The protester asserts that even though the contracting officer
was aware that Colson had in fact addressed the bonding and
audit requirements in its business proposal and took this
information into consideration in making her award decision, her
decision was nevertheless flawed in that it was based on a
defective technical evaluation. Thus, we understand the
protester to be arguing that although the contracting officer
was aware that two of the weaknesses identified by the technical
evaluation team were not in fact weaknesses and did not consider
them in making her source selection decision, her determination
was nonetheless flawed because it also took into consideration
the rating of green under the technical approach factor assigned
by the technical evaluators, which rating the evaluators had
arrived at taking the two weaknesses into consideration. We
disagree with the protester’s reasoning. It is clear from the
contracting officer’s source selection decision that she
considered the underlying basis for the evaluators’ rating of
green, i.e., the strengths and weaknesses in Colson’s technical
approach, and not simply the color rating assigned by the
evaluators, in making her tradeoff determination; accordingly,
we see no reasonable basis for the argument that her trade-off
determination was flawed. (Colson
Services Corporation, B-310971; B-310971.2; B-310971.3,
March 21, 2008) (pdf)
The best value tradeoff memorandum then adopted essentially
verbatim the language in the TET’s final evaluation report
regarding Nortel’s staffing levels. The memorandum also
characterized Nortel’s overall staffing levels as one of the
areas in which Nortel’s proposal offered a significant technical
advantage over AT&T’s proposal. Id., Tab 33, Final Technical
Evaluation Report, at 20, 23. The memorandum did not address the
TET’s finding that Nortel’s continued staffing of managers,
trainers, field engineers, and other personnel associated with
the TSRP system’s implementation beyond the deployment schedule
was an ineffective and uneconomical use of resources. AT&T
argues that both the TET’s final technical evaluation report and
the best value tradeoff memorandum are inconsistent with the
evaluators’ findings regarding Nortel’s staffing levels. The
protester argues that while the evaluators found that Nortel had
proposed excessive staffing levels throughout the entire
contract period--too many management and operations personnel in
the implementation period and too many implementation personnel
in the steady state period--the agency ignored these findings
and instead, without explanation, characterized Nortel’s
staffing levels as an unconditional strength. Protest, Sept. 20,
2007, at 27, 57-58. The agency does not dispute the TET’s
determination that Nortel’s final proposal contained “some
overstaffing,” nor deny that the best value tradeoff memorandum
considered Nortel’s higher staffing levels to be an unqualified
strength. Rather, SSA argues that under the RFP’s best value
evaluation scheme here, the agency set forth its preference for
a low risk technical solution and thus, could properly conclude
that a proposal that reduced risk by exceeding the staffing
requirements, even when there is a price premium, will better
satisfy the agency’s needs. AR, Oct. 1, 2007, at 13.
While source selection officials may reasonably disagree with
the evaluation ratings and results of lower-level evaluators,
Verify, Inc., B-244401.2, Jan. 24, 1992, 92-1 CPD para. 107 at
6-8, they are nonetheless bound by the fundamental requirement
that their independent judgments be reasonable, consistent with
the stated evaluation factors, and adequately documented. AIU N.
Am., Inc., B-283743.2, Feb. 16, 2000, 2000 CPD para. 39 at 8-9
(protest sustained because selection official did not document
the basis for concluding that proposals were technically equal,
after the evaluation panel concluded that one proposal was
superior to the other). As shown above, SSA’s best value
tradeoff determination reached conclusions regarding Nortel’s
staffing levels that were inconsistent with the underlying
evaluation findings. Further, the best value tradeoff memorandum
provides no explanation for its conclusion that Nortel’s higher
staffing levels represented an unqualified strength of
significant benefit to the agency, in contrast to the
evaluators’ determination that certain aspects of Nortel’s
staffing plan appeared to be an ineffective and uneconomical use
of resources. In fact, the best value tradeoff memorandum does
not indicate that the contracting officer, who prepared the
memorandum, considered or was even aware of the TET’s finding of
no apparent benefit in Nortel’s decision to continue
implementation staffing levels beyond the deployment schedule.
The record also reflects that this conclusion regarding the
benefits of Nortel’s staffing levels was material to the
agency’s source selection determination. We recognize that an
agency may properly conclude that a proposal with higher
staffing levels may reduce the offeror’s risk of performance.
The fact that a proposal has higher staffing levels does not
automatically mean reduced risk, however, and there has been no
showing or explanation offered here as to how Nortel’s
continuation of its implementation staffing personnel during the
managed services years would reduce the risk of performance
here. In sum, we cannot find SSA’s evaluation of Nortel’s
management approach to be reasonable when the agency reached a
conclusion regarding the offeror’s staffing plan that was
inconsistent with the underlying evaluation findings and
provided no explanation for this inconsistency, and then relied
on this conclusion as a material part of its best value tradeoff
determination.
AT&T
Corp., B-299542.3; B-299542.4, November 16, 2007) (pdf)
Karrar argues that the agency performed an unreasonable best
value determination. According to Karrar, its proposal was
substantially superior to BANC3’s under the most important
technical factor, while BANC3’s proposal was only slightly
superior to Karrar’s under the less important management factor.
Karrar concludes that, in selecting BANC3 for award, the agency
improperly gave more weight to the management factor than to the
more important technical factor. SSOs have broad discretion in
determining the manner and extent to which they will make use of
the technical and price evaluation results; their judgments are
governed only by the tests of rationality and consistency with
the stated evaluation criteria. Chemical Demilitarization
Assocs., B-277700, Nov. 13, 1997, 98-1 CPD para. 171 at 6. The
propriety of a tradeoff depends not on the mere difference in
technical scores or ratings, but on the reasonableness of the
SSO’s judgment concerning the significance of the difference.
Digital Sys. Group, Inc., B-286931, B-286931.2, Mar. 7, 2001,
2001 CPD para. 50 at 7. Here, while the SSO noted that the
Aberdeen Proving Ground management subfactor was the most
important subfactor, and that BANC3’s proposal was rated good
under this subfactor, SSD at 6, there is no basis to conclude
that she gave the management factor greater weight than the
technical factor. Rather, as discussed above, the SSO reviewed
the relative weights of the evaluation factors, the adjectival
ratings for each subfactor, and the underlying strengths and
weaknesses on which those ratings were based. The SSO’s
resulting conclusion that Karrar’s proposal was slightly
superior to BANC3’s under the technical factor, but that BANC3’s
proposal was superior to Karrar’s under the management factor,
formed the non-price side of the tradeoff equation. Balanced
against those considerations was Karrar’s $7.9 million (31
percent) higher price. In weighing the two, the SSO concluded
that any relative benefit offered by Karrar’s proposal was not
sufficient to offset its significantly higher price. Id. There
was nothing unreasonable in the agency’s methodology or
conclusion. (Karrar Systems
Corporation, B-310661.3; B-310661.4, March 3, 2008) (pdf)
Finally, the
protester contends that the selection decision here cannot
withstand scrutiny because of certain factual errors in the
document that have been acknowledged by the CO. We disagree.
As discussed above, the CO acknowledges that the selection
decision erroneously states that the record considered when
selecting JVP for award included evaluations by TEB and PEB
evaluators. Decl. of CO, Nov. 7, 2007, at 1. As the record
shows, the Navy used a TEB or PEB to evaluate offerors’
proposals for the initial award in 2006, but did not use these
teams in its reevaluation of proposals in 2007. Instead, all of
the 2007 reevaluations were conducted by the SSB. The CO
explains that the misstatements in the selection decision were
due to Navy personnel who assisted in the drafting of the
document using an outdated model document. Id. The CO further
states that he relied solely on the SSB reports produced during
the recompetition, and that he “did not rely . . . upon any
reports other than the SSB [reports] to reach my evaluation and
award decisions.” Id. The CO’s clarification is consistent
with the record. Although the selection decision refers to
“recommendations reported by the TEB and Price Evaluator,” AR
exh. 15, SSD, at 1, the source of the information relied upon in
the tradeoff determination clearly comes from the SSB report.
First, the technical ratings for JVP reflect the SSB’s
reevaluation of that offeror’s proposal that were conducted in
February 2007, following the Navy’s decision to take corrective
action in response to JVP’s COFC protest. See AR, BCM, Feb. 26,
2007. The record shows that the TEB, in contrast, had no input
as to technical evaluations after its final August 2006 report.
Next, the prices cited in the selection decision are clearly
those from the offerors’ final proposals, submitted during the
2007 recompetition. Both JVP’s and BOS’s revised prices, and the
differences between them, are cited in the selection decision
and reflect the 2007 proposals, rather than the initial
proposals which were evaluated by the PEB in 2006. In sum,
all of the information cited by or relied upon in the selection
decision for the award determination is clearly based on the
August 16, 2007, SSB report; conversely, none of the information
cited is based on the outdated TEB or PEB evaluations. In our
view this essentially cosmetic error--misidentifying the source
of the final assessments when the record clearly shows that the
assessments were drawn from different sources (which were
provided to protester’s counsel during the course of this
protest)--does not provide a basis to challenge the
reasonableness of the selection decision here. (Team
BOS/Naples--Gemmo S.p.A./DelJen, B-298865.3, December 28,
2007) (pdf)
With respect to UTT’s challenge to the SSA’s tradeoff decision,
we think selection officials have considerable discretion in
making price/technical tradeoffs. Their judgments in these
tradeoffs are by their nature subjective; nevertheless, the
exercise of these judgments must be reasonable and must bear a
rational relationship to the announced criteria upon which
competing offers are to be selected. Award may be made to a firm
that submitted a lower-rated, lower-priced proposal where the
decision is consistent with the evaluation criteria and the
agency reasonably determines that the premium involved in
awarding to the offeror with the higher-rated, higher-priced
proposal is not justified. Computer Tech. Servs., Inc.,
B-271435, June 20, 1996, 96-1 CPD ¶ 283 at 5. Here, the
SSA recognized UTT’s slight delivery advantage with respect to
the six FOB Destination trailers and concluded that the
advantage was not worth the price premium. In making this
decision, the SSA appropriately recognized the relative
importance of the solicitation’s evaluation factors, in
particular that the delivery factor was more important than the
price factor. AR, Tab 17, Source Selection Decision at 4.
Although UTT believes that its shorter delivery schedule for the
six FOB Destination trailers should have resulted in an award to
UTT, the protester’s disagreement with the SSA’s business
judgment does not show that that judgment is unreasonable. See
ACS State Healthcare, LLC et al., B-292981 et al., Jan. 9, 2004,
2004 CPD ¶ 57 at 44. Rather, we find that the decision reflects
a price/technical tradeoff assessment that is within the realm
of discretion given selection officials on these matters.
(Utility Tool & Trailer, Inc.
B-310535, January 3, 2008) (pdf)
The RFP here specifically informed offerors that award would be
made under Phase II of the evaluation on a price/technical
tradeoff basis, considering the evaluated advantages,
disadvantages and risks of each proposal under the delivery,
small business participation, and price factors. The RFP also
advised that offerors’ proposed delivery schedules for FOB
origin and FOB destination would be considered under the
delivery evaluation factor. RFP sect. M.2.2. Moreover, the RFP
advised that the delivery factor was the most important
evaluation factor. Based on our review of the record--and
contrary to the protester’s contention that had it known the
importance of the delivery factor in the evaluation of
proposals, it would have adjusted its delivery dates
accordingly--the record shows that the protester proposed
delivery dates that were significantly below the government’s
stated objectives. In this regard, the protester’s proposal, on
its face, suggests that the protester understood that the agency
needed these items sooner than later, and understood the
importance of an expedited delivery schedule. The record shows
that CKP simply did not propose a delivery schedule that was as
favorable as the delivery schedule proposed by Polaris.
CKP also challenges the SSA’s price/technical tradeoff
determination that Polaris’ offer of a shorter delivery schedule
was worth the $5.5 million price premium associated with
Polaris’ higher-priced proposal. In our view, selection
officials have considerable discretion in making price/technical
decisions. Their judgments in these tradeoffs are by their
nature subjective; nevertheless, the exercise of these judgments
must be reasonable and must bear a rational relationship to the
announced criteria upon which competing offers are to be
selected. Award may be made to a firm that submitted a
higher-rated, higher-price proposal where the decision is
consistent with the evaluation criteria and the agency
reasonably determines that the technical superiority of the
higher-priced offer outweighs the price difference. ACS State
Healthcare, LLC et al., B-292981 et al., Jan. 9, 2004, 2004 CPD
para. 57 at 44. Here, the SSA recognized CKP’s price advantage,
but concluded that Polaris’ shorter delivery schedule was worth
the price premium. In making this decision, the SSA
appropriately recognized the relative importance of the
solicitation’s evaluation factors, in particular that the
delivery factor was more important than the price factor. AR,
Tab 17, Source Selection Decision, at 4. The SSA noted that
there was an urgent need for these items and indicated that she
was willing to pay the price premium for faster deliveries with
lower risk. Although CKP does not believe that Polaris’ faster
delivery schedule was worth an additional $5.5 million, CKP’s
disagreement with the SSA’s business judgment does not show that
that judgment is unreasonable. See ACS State Healthcare, LLC et
al., supra, at 45. Rather, we find that the decision reflects a
price/technical tradeoff assessment that is within the realm of
discretion given selection officials on these matters. (Charles
Kendall & Partners, Ltd., B-310093, November 26, 2007) (pdf)
In a best-value procurement such as this, award may be made
based upon a higher-priced proposal where the award decision is
consistent with the evaluation criteria and the agency
reasonably determines that the technical superiority of the
higher-priced proposal outweighs the price difference. American
Material Handling, B‑297536, Jan. 30, 2006, 2006 CPD para. 28 at
4. The record demonstrates that the agency did undertake a
detailed comparison of the View One and Eggs & Bacon proposals,
from which it reasonably concluded that View One had a
significantly better technical proposal than Eggs & Bacon that
was worth the associated price premium and overcame Eggs &
Bacon’s price advantage. Agency Report, Tab 10, SSEB Report; Tab
11, Source Selection Decision Document. Specifically, the SSA
adopted View One’s proposal’s excellent ratings under all of the
evaluation factors. The SSA found that View One possessed
extensive experience organizing SOA events and other similar
productions, proposed personnel with extensive experience, had
an “immense pool of talent that would benefit this production,”
had a technical proposal that contained precise information that
addressed all aspects of the performance work statement (PWS),
and had excellent past performance reference evaluations. Agency
Report, Tab 11, Source Selection Decision Document, at 3-4.
While Eggs & Bacon also had excellent past performance reference
evaluations, its proposal was otherwise rated inferior to View
One’s. Eggs & Bacon’s prior experience, rated good, involved
similar type of productions but was based largely on trade shows
of short duration. Eggs & Bacon proposed experienced personnel,
but did not explain exactly how they would be organized for this
effort and there were indications that the proposed personnel
had not worked together as a group, and thus its proposal was
considered only acceptable under this factor. Eggs & Bacon’s
proposal was rated marginal under the technical capability
factor because there was insufficient detail and clarity as to
how and with what equipment the PWS requirements would be met,
including such requirements as local editing facilities and
certain specialized requirements, such as wide angle resolution,
digital imaging and the use of rear projection of at least 1,300
square feet. Id. at 2-3. Our review of the record, including the
proposals, provides us with no basis to question the
reasonableness of this evaluation, or the decision to select
View One’s higher-rated, higher-price proposal over Eggs &
Bacon’s lower-rated, lower-priced proposal since this result was
permitted by the evaluation scheme, particularly given price’s
lesser weight in the evaluation scheme. In fact, Eggs & Bacon
does not specifically question the agency’s evaluation of its
proposal despite having had access to this part of the record.
(Eggs & Bacon, Inc., B-310066,
November 20, 2007) (pdf)
The BVAC’s findings and recommendation were reported to the
source selection authority (SSA), who also received oral
briefings from the TERP and CAP chairs regarding their
respective findings. The SSA noted that the BVAC had found that
Earl’s “slight technical advantage” was attributable to “several
predominantly minor strengths” in Earl’s proposal that were not
found in MTJV’s proposal. In this regard, the SSA stated that
the BVAC’s report documented “that all of the offerors met the
requirements of the solicitation.” The SSA selected MTJV’s
proposal as reflecting the best value to the agency because “the
slight technical advantage inherent in [Earl’s proposal]” did
not warrant the payment of a [Deleted]-percent premium
associated with Earl’s higher evaluated cost. AR, Tab 18, Source
Selection Decision, at 1. Award was made to MTJV, and this
protest followed. Earl first complains that the Navy did not
reasonably assess the relative technical merit of its and MTJV’s
proposals. In this regard, Earl argues that the SSA’s conclusion
in his selection decision that Earl’s proposal reflected only a
“slight technical advantage” over MTJV’s proposal was not
consistent with the TERP’s evaluation and the solicitation
evaluation criteria.
(Section deleted.)
Here, the RFP provided for a comparative assessment of the
offerors’ management capability, resource capabilities, and past
performance. See RFP sect. M, at 178. With respect to the
resource capabilities factor, offerors were instructed to
identify resources committed to the work effort. See RFP sect.
L, at 159. The TERP found that Earl provided “the strongest
proposal to this solicitation in all areas because of their well
thought out plan and their strong current and past performance,
especially in the area of Resource Capabilities.” AR, Tab 15,
TERP Report, at 2. With respect to Earl’s proposed resource
capabilities, the TERP noted as a major proposal strength under
the resource capabilities factor that
Team Earl’s proposal clearly demonstrates that they have the
facilities and manning to execute the requirements of the
FFG7 . . . contract. Team Earl’s available resources are
unmatched in the Southeast region. Three team members--Earl
Industries and Atlantic Marine have significant facilities
located on Mayport Naval Station. They previously provided
significant industrial base support for the Navy in Mayport
for many years. Combined, they have almost six acres of land
and approximately 120,000 square feet of fully certified
facilities dedicated to the Navy. These facilities have
completed the overwhelming majority of maintenance on over
twenty surface ships and an aircraft carrier at Mayport
Naval Station. Team Earl has more than adequate resources
and manning to conduct multiple FFG7 availabilities
concurrently.
Id., encl. 3, Earl Evaluation, at 2.
MTJV’s final revised proposal, on the other hand, was found by
the TERP to be only satisfactory under the management
capability, resource capabilities, and past performance factors.
AR, Tab 15, TERP Report, at 3. As noted above, with respect to
the awardee’s resource capabilities, the TERP assessed MTJV’s
initial proposal as being “weak” because the firm had not
identified adequate resources to perform the contract, and
assigned a “marginal” rating to MTJV’s proposal under this
factor. In discussions, MTJV admitted that the “overwhelming
majority” of MTJV’s current resources were located in Norfolk,
Virginia, and not in Mayport, Florida. MTJV promised to augment
its existing Mayport facilities and resources with “new local
resources as required” and to solicit all local “master ship
repair agreement” and “agreement for boat repair” contractors
(such as Earl, Atlantic Marine, and QED) to execute various
tasks. See AR, Tab 3, MTJV Discussions Reponses, at 11; Tab 15,
TERP Report, encl. 4, MTJV Evaluation, at 3. In addition, MTJV
promised to provide the Navy with MTJV’s “Shipyard in a Box,”
which reflected shipyard resources that MTJV stated could be
shipped to Mayport, as required. Id. at 12. With little
explanation, the TERP changed MTJV’s rating for the resource
capabilities factor from marginal to satisfactory based upon
these promises. As noted above, the TERP concluded that Earl had
provided a superior proposal to that of MTJV, particularly in
the area of resource capabilities, under which the TERP
documented a major strength. The BVAC and SSA concluded,
however, that Earl’s higher technical ratings were attributable
to “several predominantly minor strengths” and that Earl’s
technical advantage was “slight.” Although source
selection officials may reasonably disagree with the ratings and
recommendations of evaluators, they are nonetheless bound by the
fundamental requirement that their independent judgments be
reasonable, consistent with the stated evaluation scheme and
adequately documented. DynCorp Int’l LLC, B-289863, B-289863.2,
May 13, 2002, 2002 CPD para. 83 at 4. Here, the SSA’s conclusion
with respect to Earl’s technical advantage is unsupported by any
meaningful explanation in either the contemporaneous record or
in response to the protest. That is, we have been provided with
no explanation supporting the BVAC’s and SSA’s judgment that
Earl’s proposal of significant resources in Mayport (which the
TERP termed “unmatched in the Southeast region”), as compared to
MTJV’s promise to obtain resources as necessary, represented
only a slight technical advantage, where the RFP provided for a
comparative evaluation of the offerors’ respective resource
capabilities. In this regard, there is no explanation for the
SSA’s and BVAC’s conclusion that Earl’s superior technical
ratings were attributable to minor strengths. Based upon this
record, we do not find that the SSA reasonably assessed, in
accordance with the solicitation’s evaluation criteria, the
relative technical merit associated with Earl’s and MTJV’s
proposals in his decision to select MTJV’s proposal on the basis
of its lower evaluated costs. Earl’s protest is sustained on
this basis. (Earl Industries,
LLC, B-309996; B-309996.4, November 5, 2007) (pdf)
An SSA may select a lower-priced, lower technically rated
proposal if he or she decides that the price premium involved in
selecting the higher-rated, higher-priced offer is not justified
given the acceptable level of technical competence available at
the lower cost. The determining element is not the difference in
technical merit, per se, but the contracting agency’s judgment
concerning the significance of the difference. In making this
determination, the SSA has broad discretion, and the extent to
which technical merit may be sacrificed for cost, or vice versa,
is limited only by the requirement that the tradeoff decision be
reasonable in light of the established evaluation and source
selection criteria. CVB Co., B-278478.4, Sept. 21, 1998, 98-2
CPD para. 109 at 8. As detailed above, the record shows that the
SSA was provided with a comprehensive briefing of the offerors’
proposals, which highlighted for the SSA significant strengths,
weaknesses, and discriminators in each proposal. Agency Hearing
Book, exhs. C-F, SSA Final Briefing Materials; Tr. at 17, 56.
During the briefing, the SSA “probed” behind the briefing
materials and asked questions of the expert evaluators and
“users.” Tr. at 18-21, 29. In reviewing the materials, the SSA
did not just “put blinders on,” but instead “went through [the
briefing chart] meticulously to find out if there was value in
those attributes above and beyond what’s listed on that chart.”
Tr. at 119. From this briefing, the SSA fully understood the
relative differences in capability between the EADS and AWI
proposals in terms of the mission and did not “trivialize” AWI’s
proposal strengths, as asserted by AWI. Tr. at 37-38, 227. In
fact, given the detailed, voluminous record in this case and the
complexities in this procurement, the SSA reasonably relied on
the expertise of the factor leads, LUH “users,” SSEB, and SSAC
to advise him of the value of exceeding, or failing to meet,
attributes relative to the mission.[50] Although it is true that
the SSA did not separately quantify the value for each element,
Tr. at 68, 180-81, this was not required and does not mean that
the SSA failed to perform any analysis of value as AWI appears
to argue. See FAR sect. 15.308 (SSA’s “documentation need not
quantify the tradeoffs that led to the decision”). Contrary to
AWI’s arguments, the SSA considered essentially all of the areas
where AWI’s aircraft capability exceeded EADS’s, including those
elements where both offers received the same rating.[51] He
considered the offerors’ proposed capabilities under the
technical elements “individually” and then “cumulatively” to
determine whether AWI’s technical superiority in the “totality”
was worth the additional cost. Tr. at 67, 117, 122-23. Although
the SSA did not discuss each and every element in the SSDD as
AWI would have liked, the record shows that the relative
differences between the proposals under each of these elements
were thoroughly documented in a well‑reasoned and rational SSEB
report, and a detailed summary of these findings was briefed to
the SSA and considered in his decision. Agency Hearing Book,
exhs. C-F, SSA Final Briefing Materials; Tr. at 17-21, 204. The
SSDD highlighted the key discriminators among offerors’
proposals, albeit not all of the elements that AWI would have
liked the SSA to agree were discriminators, and illustrates a
well‑reasoned and sufficiently detailed selection decision that
clearly credits AWI’s strengths and technical superiority, but
explains why its proposal was not worth $800 million over EADS’s
highly rated $3.9 billion proposal. (MD
Helicopters, Inc.; AgustaWestland, Inc., B-298502;
B-298502.2; B-298502.3; B-298502.4; B-298502.5, October 23,
2006) (pdf)
We
conclude that the agency’s evaluation of offerors’ proposals was
unreasonable because of the contradiction between the cost
evaluation and technical evaluation. See Honeywell Tech.
Solutions, Inc.; Wyle Labs., Inc., B-292354, B-292388, Sept. 2,
2003, 2005 CPD para. 107 at 7-8 (evaluation was unreasonable
where agency found that awardee was rated as “appropriate” under
technical evaluation, yet also concluded that awardee had
proposed insufficient staffing under cost realism analysis). The
agency argues that the technical evaluations were reasonable
because the evaluators relied upon numerous strengths in
concluding that each offeror warranted high technical scores.
The technical evaluation and source selection decision, however,
conclude that each offeror was “technically superior,” in part
because of each offerors’ “more than adequate” proposed staff.
The SSD makes no attempt to reconcile the clearly opposing views
of the technical evaluation and the cost evaluation. We conclude
that the agency’s evaluation that both offerors’ proposals were
“technically superior,” with near-perfect technical scores, is
unsupported in light of the patent contradiction in the record,
as discussed above. (Information
Ventures, Inc., B-297276.2; B-297276.3; B-297276.4, March 1,
2006) (pdf)
Based on our review, the source selection official could not
reasonably accept Badger’s proposed delivery schedule as the
basis for award. As indicated above, the “required” delivery
schedule, as specified by the RFP if FAT was waived, was
delivery of 3,000 units in 90 days (not the 150 days proposed by
Badger) with deliveries at 3,000 units per month until
completion (not the 1,800 units per month proposed by Badger).
While, as noted above, the RFP indicated that “earlier shipments
of smaller quantities, phased out longer may be accepted,” RFP
at 2, this provision had no applicability to Badger’s
noncompliant delivery proposal, which did not offer “earlier
shipments.” Indeed, while Badger’s proposed initial delivery of
3,000 units in 150 days was somewhat better than the
RFP-required delivery of 165 days if FAT was not waived--which
was the delivery proposed by Novex--Badger’s 1,800-unit monthly
rate of delivery for the rest of the contract was significantly
less advantageous than the RFP-required 3,000-unit monthly rate,
which was proposed by Novex. This means that, except for the
initial quantity, Novex’s proposed delivery schedule, which
would be completed in 315 days (initial delivery in 165 days and
five deliveries at 3,000-unit rate every 30 days), was
significantly better than Badger’s, which would not be completed
until 390 days (initial delivery in 150 days and eight
deliveries at 1,800-unit rate every 30 days). There is no
evidence in the award selection documentation that the agency
recognized Novex’s superiority with regard to delivery of the
bulk of the units, and the source selection official did not
reasonably explain why gaining earlier delivery of only 15 days
for the initial delivery was worth the additional cost,
considering that the rest of Badger’s proposed delivery was
significantly less advantageous than Novex’s. Cf. American
Material Handling, B‑297536, Jan. 30, 2006, 2006 CPD para. __ at
4 (agency reasonably focused on early initial delivery as award
discriminator where the delivery evaluation factor in the
solicitation expressly stated that such credit would be given).
While the award selection documentation indicates that up to 75
days would be needed to obtain and approve FAT before production
could begin, Novex’s proposal committed to supply the total
initial quantity in 165 days from date of award, including FAT,
which is only 15 days longer than the 150 days proposed for
delivery by Badger. The agency did not indicate that Novex’s
proposed delivery schedule was unrealistic. Instead, in a
supplemental agency submission made after the attorney from our
Office, in response to an agency request for alternate dispute
resolution, advised the agency of the reasons (set forth in this
decision) that our Office believed the award selection was
unreasonable, the agency for the first time argued that the
source selection official was actually considering the risk that
Novex might fail its FAT in determining that Badger offered
superior delivery because FAT had been waived for it and
therefore its offer represented the best value. However, the
contemporaneous documentation does not mention that any such
risk was considered. We give little weight to this argument
because it was made in the heat of litigation. See Boeing
Sikorsky Aircraft Support, B-277263.2, B‑277263.3, Sept. 29,
1997, 97‑2 CPD para. 91 at 15. (Novex
Enterprises, B-297660; B-297660.2, March 6, 2006) (pdf)
TruLogic first argues that the SSA failed to act with
“impartiality.”[12] It asserts that the SSA unreasonably ignored
the SSET majority view, instead relying on the minority view,
and “manipulated” the evaluation to support his selection of CTI
for award. TruLogic further contends that the SSA either ignored
or only mentioned in a cursory way TruLogic’s proposal
strengths, while dedicating several paragraphs of the SSD to
emphasize CTI’s proposal strengths. The record, however, shows a
well-documented, reasoned evaluation and award decision without
evidence of bias. Despite TruLogic’s insistence that the SSA
should have adopted the majority view, source selection
officials are not bound by the evaluation judgments of lower
level evaluators; they may come to their own reasonable
evaluation conclusions. MW-All Star Joint Venture, B-291170.4,
Aug. 4, 2003, 2004 CPD para. 98 at 3 n.3. Here, we find that the
SSA reasonably concluded that the minority view was a more
accurate assessment of CTI’s proposal. The record confirms that
CTI’s EN responses and final proposal revision adequately
address the functionality requirements at issue, and supports
the minority SSET report and the SSA’s conclusion that CTI’s
proposal met the functionality requirements of the RFP.[14] The
SSA did not “manipulate” the evaluation, as alleged, but
documented in detail his disagreement with the majority of the
SSET. To the extent that TruLogic complains that the SSD
contains more paragraphs discussing CTI’s proposal than
TruLogic’s, the agency explains that this was because the SSA
was explaining his disagreement with the majority of the SSET,
not because the SSA was ignoring the benefits of TruLogic’s
approach or over-emphasizing CTI’s proposal strengths. In sum,
our review of the record reveals that the SSD fairly considered
the benefits and drawbacks of both TruLogic’s and CTI’s proposal
features, and reasonably concluded that CTI’s proposal provided
the better value. (TruLogic, Inc.,
B-297252.3, January 30, 2006) (pdf)
AMH complains that TACOM unreasonably viewed JLG’s offer of a
shorter delivery schedule for the minimum quantity to be a
discriminator in the SSA’s price/technical tradeoff award
selection decision. In AMH’s view, the RFP only provided that
offerors’ proposals would be evaluated to determine whether the
proposed schedule was credible and would “beat or meet the 180
day delivery objective.” AMH argues that, because both it and
JLG offered an accelerated delivery schedule, the two firms’
proposals should have received the same evaluation rating for
this factor. We disagree with AMH’s view that the solicitation
did not allow TACOM to consider a shorter, credible delivery
schedule to be a proposal advantage. Here, the RFP specifically
informed offerors that award would be made on a price/technical
tradeoff basis, considering the evaluated advantages,
disadvantages and risks of each proposal under the delivery,
small business participation, and price factors, and the
delivery factor specifically stated that the offeror’s proposed
“single date for completion of delivery of the minimum
guaranteed quantity” would be considered. RFP at 68. We have
found that where, as here, a solicitation provides for award on
a best-value basis, an agency may reasonably assess as a
proposal advantage the manner in which a proposal exceeds the
minimum requirements of the solicitation. See, e.g., Preferred
Sys. Solutions, B-291750, Feb. 24, 2003, 2003 CPD para. 56 at
3-4; F2M-WSCI, B‑278281, Jan. 14, 1998, 98-1 CPD para. 16 at
7-8. AMH also challenges the SSA’s price/technical tradeoff
determination that JLG’s offer of a 29-day shorter delivery
schedule was worth the $286,873 price premium associated with
JLG’s higher-priced proposal. In this regard, AMH argues that
JLG’s accelerated delivery schedule was for only the minimum
guaranteed quantity and that the agency has not explained why an
earlier delivery schedule for the minimum quantity “is better
for the Iraq mission.” Protester’s Comments at 2. Selection
officials have considerable discretion in making price/technical
tradeoff decisions. Their judgments in these tradeoffs are by
their nature subjective; nevertheless, the exercise of these
judgments must be reasonable and must bear a rational
relationship to the announced criteria upon which competing
offers are to be selected. Award may be made to a firm that
submitted a higher-rated, higher‑priced proposal where the
decision is consistent with the evaluation criteria and the
agency reasonably determines that the technical superiority of
the higher‑priced offer outweighs the price difference. ACS
State Healthcare, LLC et al., B-292981 et al., Jan. 9, 2004,
2004 CPD para. 57 at 44. Here, the SSA recognized AMH’s price
advantage, but concluded that JLG’s shorter delivery schedule
was worth the price premium. In making this decision, the SSA
appropiately recognized the relative importance of the
solicitation’s evalutation factors, in particular that the
delivery factor (that focused on the guaranteed minimum
quantity) was more important than the price factor. AR, Tab 17,
Source Selection Decision, at 2. The SSA found that JLG’s
shorter delivery schedule for the guaranteed minimum quantity
provided a real benefit to the government, given that “early
delivery of this tactical forklift is critical to provide Iraqi
troops with the capability to off-load supplies from
containers.” Id. at 5. Although AMH does not believe that the
29-day shorter delivery schedule was worth the additional
$286,873, AMH’s disagreement with the SSA’s business judgment
does not show that that judgment is unreasonable. See ACS State
Healthcare, LLC et al., supra, at 45. Rather, we find that the
decision reflects a reasonable price/technical tradeoff
assessment. (American Material
Handling, Inc., B-297536, January 30, 2006) (pdf)
We
conclude that, on this record, YORK was competitively prejudiced
by the errors. Of particular significance, the record shows that
YORK’s proposal was scored higher than Obsi1’s proposal on the
most important evaluation factor, technical approach. The SSO’s
reliance on total scores (which themselves did not reflect the
RFP’s relative weighting of the factors) indicates that her
selection decision did not consider the significance of YORK’s
apparent technical advantage under the most important technical
evaluation factor. (YORK Building
Services, Inc., B-296948.2; B-296948.3; B-296948.4, November
3, 2005) (pdf)
The agency unfairly and unreasonably evaluated the proposals on
the feature of field control of inventory. Both offerors
proposed a capability that would permit field locations to have
full control of all types of inventory. Agency Report, Tab 26,
ReserveAmerica’s Final Revised Proposal, at 915-17; Tab 39,
Spherix’s Final Revised Proposal, at 1809‑12, 1969-70. The
agency stated that Spherix’s proposed inventory management
capability focused on campground inventory and did not address
tours and ticketing. Agency Report, Tab 16, Source Selection
Decision, at 474. That statement is inconsistent with the terms
of Spherix’s proposal, which states that its inventory
management capability applies to both recreation facilities and
recreation activities. Agency Report, Tab 39, Spherix’s Final
Revised Proposal, at 1809. The agency also stated that Spherix
did not quantify how much control would be granted to field
sites. Agency Report, Tab 16, Source Selection Decision, at 474.
This also is inconsistent with the terms of Spherix’s proposal,
which stated [DELETED].[5] Agency Report, Tab 39, Spherix’s
Final Revised Proposal, at 1969-70. These misstatements formed
the basis for inventory control being one of the discriminators
in the SSA’s tradeoff analysis. Agency Report, Tab 16, Source
Selection Decision, at 474. (Spherix,
Inc., October 20, 2005, B-294572.3; B-294572.4) (pdf)
In reviewing a protest against an agency’s evaluation of
proposals and award, including tradeoff determinations, we
examine the record to determine whether the agency’s judgment
was reasonable and consistent with the solicitation’s evaluation
criteria and applicable statutes and regulations. Ostrom
Painting & Sandblasting, Inc., B-285244, July 18, 2000, 2000 CPD
para. 132 at 4. An agency may properly select a lower-rated,
lower-priced proposal where it reasonably concludes that the
price premium involved in selecting a higher-rated proposal is
not justified in light of the acceptable level of technical
competence available at a lower price. Bella Vista Landscaping,
Inc., B-291310, Dec. 16, 2002, 2002 CPD para. 217 at 4. In its
comments on the agency report, which included the full
evaluation record and source selection decision documentation,
the protester does not persuasively refute the noted strengths
in the evaluation record of the awardee’s past performance, the
reasonableness of the SSA’s consideration of the two past
performance proposals as being essentially equal, or the SSA’s
concerns about the protester’s limited joint venture and
government contract experience (and the limited supporting
commentary for high past performance ratings). Rather, the firm
generally alleges that because the RFP provided that past
performance is the most important factor for award, and because
it received a higher past performance adjectival rating, it
should have been selected for award. We disagree. A protester’s
mere disagreement with the agency’s determinations as to the
relative merit of competing proposals and its judgment as to
which proposal offers the best value to the agency, does not
establish that the evaluation or source selection was
unreasonable. Weber Cafeteria Servs., Inc., B-290085.2, June 17,
2002, 2002 CPD para. 99 at 4. Our review of the record here
supports the reasonableness of the agency’s comparative review
of the merits of the proposals, its price/past performance
tradeoff, and the award decision. It is well-established that
adjectival ratings are merely guides to intelligent
decisionmaking; they do not mandate automatic selection of a
particular proposal. See Calspan Corp., B-255268, Feb. 22, 1994,
94-1 CPD para. 136 at 10. Rather, selection officials must
decide whether the different ratings show technical superiority
and what that difference may mean in terms of contract
performance in determining whether a price premium associated
with that superiority is warranted. See Computer Tech. Servs.,
Inc., B-271435, June 20, 1996, 96-1 CPD para. 283. Here, as
discussed above, the SSA performed a comprehensive integrated
assessment of the proposals and concluded that in terms of
performance risk, based on a comparative review of the offerors’
past performance, the proposals were essentially equal, making
price the determinative factor for award. Neither the protester,
nor our review of the record, provides a basis to question the
reasonableness of that determination. As set forth above, while
the protester’s past performance had noted strengths, the SSA
also noted its related weaknesses and the agency’s concerns
about the offeror’s limited relevant experience as a joint
venture and government contractor. Conversely, while the
awardee’s past performance was rated as very good, rather than
exceptional, the SSA noted the strengths of the firm’s past
performance and its direct relevance to the current SABER
contract. Moreover, the protester provides no basis to challenge
the reasonableness of the SSA’s determination that, given
NASCENT’s lower price, and the acceptable level of technical
competence and the high probability of successful performance by
this experienced SABER contractor, any technical superiority
that might be associated with the slightly higher adjectival
rating received by the protester does not justify the payment of
the price premium associated with an award to that offeror.
Therefore, whether the SSA viewed the proposals as essentially
technically equal, making price the proper basis of selection,
or concluded that the adjectival ratings of the proposals did
not warrant paying the price premium associated with the
Brewbaker White Sands proposal, we find nothing improper in the
SSA’s selection decision.Id. (Brewbaker
White Sands JV, B-295582.4,October 5, 2005) (pdf)
The protester argues that the source selection authority’s
price/technical tradeoff determination was [deleted] because it
took into account only the advantages in Coastal’s proposal that
resulted in quantifiable cost savings to the government. In a
best-value procurement, it is the function of the source
selection authority to perform a price/non-price factor(s)
tradeoff, that is, to determine whether one proposal’s
superiority under the non-price factor or factors is worth a
higher price. A.G. Cullen Constr., Inc., B-284049.2, Feb. 22,
2000, 2000 CPD para. 45 at 4. We will review the selection
decision to ensure that it was reasonable and consistent with
the evaluation scheme set forth in the solicitation. Id. Based
on our review of the record here, we agree with the protester
that the SSA’s tradeoff analysis was unreasonable. The SSA
concluded that Coastal’s proposal was not worth the cost
differential of approximately [deleted] that separated it from
MTCE’s proposal based on information furnished to her by the
program manager regarding the [deleted] identified in Coastal’s
technical proposal. The SSA mischaracterizes the information
furnished to her by the program manager, however. Contrary to
the SSA’s statement in the Negotiation Summary Memorandum at 14,
quoted above, the program manager’s analysis did not indicate
that only some of the [deleted] identified by the technical
evaluators “would be worth an additional cost to the
government”; instead, he identified those [deleted] that would
result in a cost benefit (i.e., cost savings) to the government.
The distinction is far more than a semantic one, since an
advantage in an offeror’s technical proposal need not result in
cost savings to the government to be of value to the government.
In our view, the SSA had an obligation to consider all of the
advantages of Coastal’s proposal in her tradeoff determination,
and not simply those that would effectively reduce the cost of
Coastal’s proposal. That is, the SSA had an obligation to
consider whether the [deleted] advantages that, according to the
Program Manager, would not result in cost savings to the
government nonetheless furnished sufficient additional value to
the government to make Coastal’s proposal a better value overall
than MTCE’s, despite [deleted]. Because the SSA failed to
perform such an analysis, we think that her determination lacked
a reasonable basis. The SSA’s analysis was further unreasonable
in that it failed to take into account the difference in the
ratings of the two proposals with regard to performance risk,
instead, as noted above, focusing exclusively on the [deleted].
Where a price/technical tradeoff is made, the source selection
decision must be documented, and the documentation must include
the rationale for any tradeoffs made. FAR sect. 15.308; Blue
Rock Structures, Inc., B-293134, Feb. 6, 2004, 2004 CPD para. 63
at 5. A tradeoff determination in favor of a lower-rated,
lower-priced proposal that fails to acknowledge significant
strengths of the higher-rated proposal and furnish an
explanation as to why they are not worth a price premium is not,
in our view, a sufficiently documented tradeoff determination.
See Blue Rock Structures, Inc., supra, at 6. (Coastal
Maritime Stevedoring, LLC, B-296627, September 22, 2005) (pdf)
With respect to the senior IQ personnel that the project
officers identified as lacking in experience, AR, Tab 72, at
2-3, the selection official expressed concerns that the project
officers appeared to be judging IQ's proposed personnel against
requirements not found in the RFP. In addition, and as indicated
above, the selection official noted that the experience of key
personnel had been reviewed and assessed by the evaluation
panel, and that the proposals of both URC and IQ had received
fairly high, and essentially equal ratings in this area. In our
view, there was nothing unreasonable in the selection official's
decision to look to the evaluators' assessment in this area as
the more reliable indicator of whether the personnel proposed by
URC and IQ had sufficient backgrounds to meet the requirements
of the solicitation. Moreover, the HHS regulations lend support
to the selection official's judgment about which of the two
panels to look to for an informed assessment about the
qualifications of proposed personnel. Specifically, our review
of the regulations leads us to conclude that they do not
anticipate that project officers will undertake the job of
reviewing the backgrounds of proposed key personnel.
Finally, we recognize that URC apparently views the project
officers' memorandum in this record as an attempt by agency
managers most familiar with the requirements of this effort to
ensure that this evaluation fairly assessed the capabilities of
these two offerors to perform this work. On the other hand, this
memorandum's unusual timing, its unusual scope, its unusual
level of detail, and the unusually high level of the agency
officials involved in ensuring its consideration, lend support
to other views. Specifically, evidence in this record supports a
view that this memorandum represents an effort by agency
officials resistant to installing a new contractor in the place
of a long-time incumbent, with a good performance history. Tr.
at 20-21, 23-27, 29, 34-37, 59-60, 100, 101. Looking at the
context of this procurement and the facts in the record, we
conclude that the selection official dealt reasonably with the
recommendations of the HHS project officers. (University
Research Company, LLC, B-294358.6; B-294358.7, April 20,
2005) (pdf)
At the end of the past performance evaluation memorandum, the
contracting officer prepared a three-page narrative summary of
her evaluation findings. Although the contracting officer found
that both Dismas's and Keeton's past performance warranted a
good overall adjectival rating, the summary identified only the
firms' respective average CEF point scores (4.24 for Dismas and
4.03 for Keeton (out of a possible 5 points)), as well as the
adjectival ratings on the BOP contracts considered in the
evaluation. Also in the summary, the contracting officer
identified numerous strengths but no weaknesses for Dismas,
whereas for Keeton the contracting officer identified a few
strengths and many weaknesses. Agency Report, Tab 17,
Contracting Officer's Past Performance Evaluation Memorandum, at
29-31. The contracting officer testified that although she
relied upon the individual adjectival ratings for each contract
derived from the firms' CEFs to determine that Dismas had better
overall past performance, she prepared the narrative summary of
the firms' strengths and weaknesses to justify the adjectival
past performance ratings. Tr. at 25354. In this regard, she
testified that she only identified strengths for Dismas and few
strengths and almost only weaknesses for Keeton because she
believed that this would point out the areas in which Dismas was
superior. Tr. at 255. The SSA testified that he relied upon this
summary of the firms' past performance and did not independently
assess the firms' past performance in making his source
selection decision. Tr.at3536. In this regard, the SSA further
testified that he did not know whether this summary accurately
reflected the contracting officer's past performance evaluation.
Tr. at 54. While the contracting officer testified that the past
performance evaluation summary she prepared was drafted to
highlight Dismas's superiority in past performance, this
explanation was not provided to the SSA or SSEP chairperson;
instead, the summary was presented and appeared as a significant
part of the basis for the source selection without the SSA being
apprised of, and considering, that there were actually numerous
weaknesses in Dismas's past performance and numerous strengths
in Keeton's past performance. Thus, we conclude that the source
selection decision was based upon a misapprehension of the
offerors' past performance evaluation and therefore the decision
lacks a reasonable basis. See Ashland Sales and Serv. Co. ,
supra , at 8-10. (Keeton Corrections,
Inc., B-293348, March 4, 2005) (pdf)
Moreover, the propriety of a cost/technical tradeoff turns not
on the difference in technical score, per se , but on whether
the contracting agency's judgment concerning the significance of
that difference was reasonable in light of the solicitation's
evaluation scheme. Where cost is secondary to technical
considerations under a solicitation's evaluation scheme, as
here, the selection of a lower-priced proposal over a proposal
with a higher technical rating requires an adequate
justification, i.e., one showing the agency reasonably concluded
that notwithstanding the point or adjectival differential
between the two proposals, they were essentially equal in
technical merit, or that the differential in the evaluation
ratings between the proposals was not worth the cost premium
associated with selection of the higher technically rated
proposal. Where there is inadequate supporting rationale in the
record for a decision to select a lower-priced proposal with a
lower technical ranking, notwithstanding a solicitation's
emphasis on technical factors, we cannot conclude that the
agency had a reasonable basis for its decision. Preferred Sys.
Solutions, Inc. , supra , at 7; MCR Fed., Inc. , B-280969,
Dec.14, 1998, 991 CPD 8 at 5. As noted above, the rationale
stated in the source selection decision for selecting McNeil's
proposal as the best value was the SSA's conclusion that all of
the competitive range proposals were technically substantially
equal. In making this decision, the SSA discussed certain
aspects of the proposals, in particular the evaluation of SOS's
proposal under the personnel and security plan subfactors and
the past performance factor, and the evaluation of McNeil's
proposal under the personnel subfactor. Although the SSA's
analysis documents the rationale for adjusting the adjectival
scores under these subfactors and factor, she does not discuss
or acknowledge SOS's evaluated advantage under the other two
technical evaluation factors, quality control plan and
transition plan, where SOS's proposal was assigned "outstanding"
ratings and McNeil's proposal received only "highly
satisfactory" ratings. The record shows that the TEP provided
detailed reasons for the proposals' respective ratings under
these subfactors. Agency Report, Tab 8, Final Consensus
Evaluation, McNeil's Evaluation, at10, 15; Final Consensus
Evaluation, SOS's Evaluation, at 10, 15; Initial Consensus
Evaluation, McNeil's Evaluation, at 8, 12; Initial Consensus
Evaluation, SOS's Evaluation at 8, 12. Because of SOS's
proposal's documented superiority under these factors and the
SSA's failure to consider this evaluated superiority in her
source selection decision, the SSA's statement that the
proposals were technically substantially equal is not reasonably
supported by the contemporaneous documentation. At the hearing,
the SSA also essentially repudiated her finding that McNeil's
and SOS's proposals were substantially technically equal, and
testified that she considered both the proposals to be
technically acceptable, rather than technically equal, and that
in reviewing the two proposals "[she] did not see anything that
was basically that superior to warrant paying [DELETED] extra in
costs." Tr. at 63-64. In our view, the inadequately supported
source selection decision and testimony of the SSA suggest that
the agency may have improperly converted the source selection to
one based upon technical acceptability and low price, instead of
one that emphasized relative technical superiority, as was
contemplated by the RFP's evaluation scheme here. An agency does
not have the discretion to announce in the solicitation that it
will use one evaluation plan, and then follow another; once
offerors are informed of the criteria against which their
proposals will be evaluated, the agency must adhere to those
criteria in evaluating proposals and making its award decision,
or inform all offerors of any significant changes made in the
evaluation scheme. See Preferred Sys. Solutions, Inc. , supra ,
at 10. (SOS Interpreting, LTD.,
B-293026; B-293026.2; B-293026.3, January 20, 2004) (pdf)
We find the agency's assessment of ReserveAmerica's offer of
dedicated staff problematic in a number of regards. First, the
SSA apparently believed that Spherix did not propose the
"dedicated" support that ReserveAmerica proposed. In this
regard, in the hearing conducted by our Office in this matter,
the SSA testified that he understood from the SSET's briefing
that Spherix's proposal had not committed to provide the level
of effort needed to provide the call center services. [13] Tr.
at97100. Both Spherix and ReserveAmerica addressed staffing in
their proposals. ReserveAmerica's proposal identified "[DELETED]
dedicated to serving the needs of the NRRS" that would include
[DELETED] agencyspecific program managers and [DELETED] contact
center agents. AR, Tab 92, ReserveAmerica Final Proposal
Revision, at 1491, 1500, 1526, 1541-42. As noted above, this
offer was assessed as a proposal strength for ReserveAmerica.
Spherix's proposal stated that Spherix would deliver [DELETED]
call center seats and "a dedicated staff of Reservation
Specialists and Customer Service Representatives" with
experienced management, and specifically proposed key personnel
that included [DELETED] dedicated to each major stakeholder
Agency." AR, Tab 112, Spherix Final Proposal Revision, at 2522,
2583. This aspect of Spherix's proposal was not discussed in the
SSET final consensus evaluation. See AR, Supplemental Documents,
Final Consensus Evaluation Worksheets for Spherix, 2995-96,
3003-04. From our review of the record, we find no reasonable
support for the agency's conclusion that ReserveAmerica's
promise of dedicated staff represented a significant proposal
advantage over Spherix's similar offer. As noted above, both
firms indicated in their proposals that dedicated staff would be
provided. Although it is true that Spherix's proposal did not
specifically identify the number of dedicated staff, as
ReserveAmerica's proposal did, this specific information was
neither requested by the RFP nor sought by the agency during
discussions. Moreover, the record does not show that the SSA
otherwise fairly considered Spherix's offer of dedicated staff.
The SSA stated that he had not reviewed Spherix's proposal and
the SSET's briefing left him with the understanding that
Spherix's proposal had not committed to provide the level of
effort needed to provide the call center services. Tr. at
97-100. This was neither a reasonable evaluation of Spherix's
proposal, nor a reasonable assessment of the difference between
ReserveAmerica's and Spherix's proposals. (Spherix,
Inc., B-294572; B-294572.2, December 1, 2004) (pdf)
FAR 15.308 requires documentation of source selection decisions,
and recognizes that while the selection official may rely on
reports and analyses prepared by others, the ultimate decision
reflects the selection official's independent judgment. The
independence granted selection officials, however, does not
equate to a grant of authority to ignore, without explanation,
those who advise them on selection decisions. See , e.g. ,
DynCorp Intl LLC , B-289863, B-289863.2, May 13, 2002, 2002 CPD
83 at 6-7 (protest sustained where selection official failed to
document the basis for rejecting the evaluation panels
conclusion that it was not possible to determine whether the
proposal included all required costs); AIU North America, Inc. ,
supra , at 8-9 (protest sustained, in part, because selection
official did not document the basis for concluding that
proposals were technically equal, after the evaluation panel
concluded that one proposal was superior to the other). In
response to the agency's arguments about the requirements in its
regulations, we recognize that there is no express requirement
in the HHSAR for selection officials to document their reasons
for rejecting the evaluation input received from project
officers. On the other hand, our review of the HHSAR
requirements reveals that the agency has anticipated the
possibility that project officers will provide significant
input, especially in the area of evaluated costs. See 48 C.F.R.
315.305(a)(1). While the permissive language of the regulation
does not require this input in every procurement, there is no
dispute that it was received here, it was detailed, and it was
mischaracterized by the CO in the Source Selection Determination
document. Given that HHS has elected to supplement the FAR with
a process for receiving input from agency project officers, and
given the detailed nature of the input provided in this
procurement and the importance all participants attached to it,
we think the CO here was required to document the existence of
these different views, and state her rational basis for either
accepting or rejecting those views. Even leaving aside a Source
Selection Determination document that misstates the input of
agency officials with a prescribed role in reviewing proposals,
there is still no statement in the record from the CO regarding
her rationale for rejecting the input of the project officers.
Without such a statement, the areas where the project officers
disagree with the technical evaluation panel have been elevated
to our Office for review, without having been first resolved by
the agency. (University Research
Company, LLC, B-294358; B-294358.2; B-294358.3; B-294358.4;
B-294358.5, October 28, 2004) (pdf)
As an initial matter, we note that many of the allegations share
a common challenge to the specific ratings that the agency
assigned a given proposal. These allegations identify various
terms of a given proposal and assert that the corresponding
rating assigned by the agency should have been higher or lower,
as the case may be. However, it is well established that
ratings, be they numerical or adjectival, are merely guides for
intelligent decision-making in the procurement process. Citywide
Managing Servs. of Port Washington, Inc. , B281287.12,
B281287.13, Nov. 15, 2000, 2001 CPD 6 at11. Where a source
selection decision reasonably considers the underlying bases for
the ratings, including advantages and disadvantages associated
with the specific content of competing proposals, in a manner
that is fair and equitable, and consistent with the terms of the
solicitation, the protesters' disagreement over the actual
adjectival ratings is essentially inconsequential, in that it
does not affect the reasonableness of the judgments made in the
source selection decision. See id. ; National Steel and
Shipbuilding Co. , B281142, B281142.2, Jan. 4, 1999, 99-2 CPD 95
at 15. As the remainder of our discussion of the evaluation
shows, rather than resting upon a superficial comparison of
ratings, the agency, as indicated by the source selection
decision, reasonably considered the specific content of the
proposals in weighing the relative merits of competing proposals
and determining which proposal represented the best value. (Mechanical
Equipment Company, Inc.; Highland Engineering, Inc.; Etnyre
International, Ltd.; Kara Aerospace, Inc., B-292789.2;
B-292789.3; B-292789.4; B-292789.5; B-292789.6; B-292789.7,
December 15, 2003) (pdf)
In any case, even where price is the least important evaluation
factor, an agency may properly select a lower-priced,
lower-rated proposal if it decides that the price premium
involved in selecting a higher-rated, higher-priced proposal is
not justified. NAPA Supply of Grand Forks, Inc., B-280996.2, May
13, 1999, 99-1 CPD ¶ 94 at 5. Based on our review of the record,
we find that the Air Force reasonably concluded that the
[REDACTED] percent price differential in price did not justify
award to SSL. As noted above, the agency found the differences
between the two firms’ past performance ratings to be
“marginal.” The grounds for that finding were, in our view,
reasonable: ATS’s lower past performance ratings were due to
limited, rather than negative, past performance information;
favorable customer ratings suggested to the agency that ATS
could satisfactorily perform; and SSL had only limited
performance information available concerning its performance as
a subcontractor on semi-relevant contracts, which caused the
agency to have “some doubt” as to SSL’s ability to successfully
perform as a prime contractor on this contract. Although SSL
disagrees with the agency’s judgment that the past performance
distinctions were “marginal,” it has not shown this judgment to
be unreasonable. UNICCO Gov’t Servs., Inc., B‑277658, Nov. 7,
1997, 97-2 CPD ¶ 134 at 7. (Specific
Systems, Ltd., B-292087.3, February 20, 2004) (pdf)
In a negotiated procurement, where the solicitation does not
provide for award on the basis of the lowest cost, technically
acceptable proposal, an agency has the discretion to make an
award to an offeror with a higher technical rating and a higher
cost where it reasonably determines that the cost premium is
justified and the result is consistent with the evaluation
criteria. ACC Constr. Co., Inc., B‑288934, Nov. 21, 2001, 2001
CPD ¶ 190 at 5-6. Here, the RFP stated that the mission
capability, proposal risk, and past performance evaluation
factors, when combined, were significantly more important than
the cost evaluation factor in determining the proposal
representing the best value to the government. The RFP also
stated that the agency reserved the right to award to an offeror
that submitted a higher technically rated, higher cost proposal.
The record shows that in making his best value determination,
the SSA was aware that Raytheon’s evaluated cost was higher (by
approximately 11 percent) than Northrop’s evaluated cost and
that both Raytheon and Northrop received the same significant
confidence ratings for past performance (thereby neutralizing
past performance in terms of the best value determination).
However, and as more completely set forth above, the SSA
concluded that Raytheon’s proposed technical approach reflected
a more open architecture than Northrop’s proposed technical
approach in terms of accommodating modifications, growth, and
system upgrades in a plug-and-play fashion. The SSA believed
that Raytheon’s exceptional, low risk architecture and design
approach would “best enable [his] customer to streamline
information flow so that operational decisions are made
logically and rapidly[,] providing the best value to the
Government, and it is well worth the premium.” AR, Vol. 131, Tab
16C, SSD, supra, at 10. In this respect, at the hearing, the SSA
testified that by awarding to Raytheon, the agency “was going to
get an architecture that the warfighter could fight with, that
streamlines information flow so the decision is made logically,
quickly and rapidly and, based on [his] lessons [learned] from
[Operation Iraqi Freedom], it was an important component. This
is why [he] chose [Raytheon].” Tr. at 382. The SSA continued by
stating that “the architectural approach that Raytheon was
offering was an opportunity to ensure the maximum combat
capability.” Id. at 394. While Northrop disagrees with the SSA’s
decision to pay a premium to Raytheon for its technically
superior approach, Northrop has failed to show that the SSA’s
best value determination was unreasonable or otherwise not in
accordance with the terms of the RFP. (Northrop
Grumman Systems Corporation, B-293036.5; B-293036.6;
B-293036.7, June 4, 2004) (pdf)
In our view, the SSA has failed to furnish an adequate rationale
for his tradeoff determination here, and thus we are unable to
conclude that the determination was reasonable. As the excerpt
from his selection decision quoted above shows, the SSA simply
concludes, without any mention of the technical advantages of
Blue Rock’s higher-rated proposal or a finding that despite its
higher rating, Blue Rock’s proposal was essentially equal to
those of Virtexco and C Construction in technical merit, that
the latter two proposals represent better value than the
protester’s because they are significantly lower in price. A
tradeoff analysis that fails to furnish any explanation as to
why a higher-rated proposal does not in fact offer technical
advantages or why those technical advantages are not worth a
price premium does not satisfy the requirement for a documented
tradeoff rationale, particularly where, as here, price is
secondary to technical considerations under the RFP’s evaluation
scheme. See Preferred Sys. Solutions, Inc., B-292322 et al.,
Aug. 25, 2003, 2003 CPD ¶ 166. In addition to failing to furnish
an adequate rationale for his selection of Virtexco and C
Construction for award, the SSA failed to furnish an adequate
rationale for his selection of Shaw Beneco. The SSA justified
his selection of Shaw on the grounds that it had “a technical
rating of Good+ and low competitive pricing.” SSA Memorandum for
the File, Sept. 25, 2003, at 1. Shaw’s technical rating of Good
Plus resulted from the SSB’s technical score adjustment scheme,
however; i.e., Shaw’s original technical rating (of Good) was
raised one step as credit for its low price. Accordingly, the
SSA in essence gave Shaw double credit for its low price by
considering both its adjusted rating and its price. Since Shaw’s
technical rating, as unadjusted, was lower than the technical
ratings of both Blue Rock and Sauer, and its price was higher
than the prices of Virtexco and C Construction, we think that it
was unreasonable for him to select Shaw for award without
comparing its combination of technical merit and price to those
of the other four offerors. (Blue Rock
Structures, Inc., B-293134, February 6, 2004) (pdf)
In evaluating the revised CIS proposal, four of the five
evaluators again prepared only cursory narrative materials. In
terms of scoring, three of these four evaluators raised CIS’s
score by [deleted] points; the agency’s final consensus
technical evaluation report states that two of the three
evaluators increased their scores based on their conclusion that
the CIS proposal now met the personnel experience requirements,
and that the third increased his score based on CIS’s providing
“additional information” in its revised proposal. AR, exh. 7, at
5-6. Among these four evaluators, two assigned a final overall
technical score of [deleted] points and two assigned a score of
[deleted] points. Id. at 7. The fifth evaluator scored CIS’s
revised proposal dramatically differently, reducing CIS’s score
from [deleted] total points initially to [deleted] points on
reevaluation. Unlike the other four evaluators, he prepared
extensive narrative materials during his rescoring of the
proposal, AR, exh. 4, at 25-26, and his unedited comments were
ultimately incorporated into the final consensus technical
evaluation report, along with a summary of the other evaluators’
limited comments. AR, exh. 7, at 5. The agency’s source
selection decision document, AR, exh. 18, does not reflect any
critical or independent analysis or evaluation of the proposals
by the source selection official (SSO); instead, it relies
entirely upon the numeric scores for purposes of the agency’s
source selection decision. This being the case, the comments of
the fifth evaluator regarding deficiencies in CIS’s proposal
represent the sole support in the evaluation record for the
relatively low ranking of CIS’s revised proposal. This is
problematic for the agency because we find that the conclusions
expressed by the fifth evaluator are unreasonable. (Computer
Information Specialist, Inc., B-293049; B-293049.2, January
23, 2004) (pdf)
As indicated, the agency also considered the underlying basis
for the scores. While LSA’s proposal had 36 identified strengths
and BGS’s 26, the TEP identified four risks posed by LSA’s
proposal and only one risk and two weaknesses posed by BGS’s.
The TEP considered these different strengths, weaknesses, and
risks in making its best value recommendation, and concluded
that, as the scores had indicated, the proposals were
technically equivalent. SSRR at 3-4, 9-10. Having made this
determination, and after finding no technical differences that
would justify the higher costs associated with other award
scenarios, the TEP concluded that an award under the
lowest-priced of the technically equivalent scenarios--BGS alone
(scenario 12)--represented the best value. While LSA asserts
that its proposal offered real benefits to the agency over BGS’s
at a minimal price premium, it does not identify any of those
alleged benefits but, rather, points only to the TEP’s
description of its proposal as “innovative,” “excellent,”
“outstanding,” and “comprehensive.” LSA Comments at 10. Having
failed to identify any particular benefit for which it did not
receive credit or that would call into question the agency’s
determination of technical equivalence, LSA’s assertions amount
to mere disagreement with the agency’s conclusions, which is not
sufficient to establish that the best value determination was
unreasonable. UNICCO Gov’t Servs., Inc., B‑277658, Nov. 7, 1997,
97-2 CPD ¶ 134 at 7. (Language
Service Associates, Inc., B-293041, December 22, 2003)
(pdf)
More specifically, in making her revised past performance/price
tradeoff, the record shows that the source selection authority
ignored, contrary to statute and regulation, as cited above,
Beautify’s significantly lower price vis-à-vis Southway’s higher
past performance rating, as well as the fact that Beautify,
which received a very good/significant confidence rating,
submitted the lowest price among all competitors. There is
nothing in the source selection document that suggests that the
source selection authority believed that Beautify’s
significantly lower price in this fixed‑price, commercial item
acquisition reflected any lack of understanding by Beautify of
the RFP requirements or that Beautify was otherwise incapable of
performing the requirements. On this record, we conclude that
the source selection authority’s revised tradeoff decision was
materially flawed because she inexplicably gave no consideration
to Beautify’s low price in relation to Southway’s higher past
performance rating (which was only one rating category higher
than Beautify’s rating) and, as a result, she failed to document
why it was worth paying a 25-percent price premium to Southway.
(Beautify Professional Services
Corporation, B-291954.3, October 6, 2003) (pdf)
Moreover, the propriety of a cost/technical tradeoff turns not
on the difference in technical score, per se, but on whether the
contracting agency’s judgment concerning the significance of
that difference was reasonable in light of the solicitation’s
evaluation scheme. Where cost is secondary to technical
considerations under a solicitation’s evaluation scheme, as
here, the selection of a lower-priced proposal over a proposal
with a higher technical rating requires an adequate
justification, i.e., one showing the agency reasonably concluded
that notwithstanding the point or adjectival differential
between the two proposals, they were essentially equal in
technical merit, or that the differential in the evaluation
ratings between the proposals was not worth the cost premium
associated with selection of the higher technically rated
proposal. Where there is inadequate supporting rationale in the
record for a decision to select a lower-priced proposal with a
lower technical ranking notwithstanding a solicitation’s
emphasis on technical factors, we cannot conclude that the
agency had a reasonable basis for its decision. MCR Fed., Inc.,
B-280969, Dec. 14, 1998, 99-1 CPD ¶ 8 at 5. Here, as noted
above, the SSA’s and SSAC’s source selection documents
reflecting the agency’s best-value analysis did not include any
meaningful analysis of the differentiating features of the two
proposals upon which the SSA based the cost/technical tradeoff.
Although the SSA and SSAC acknowledged PSS’s proposal’s
technical superiority under the task order competence factor,
there was no analysis as to why the well-documented technical
superiority of PSS’s proposal with its attendant advantages was
not worth the associated cost/price premium. Instead, the source
selection document simply concluded that the proposals had
“nearly equivalent ratings in non-cost areas,” with no analysis
discussing the SSEB report justifying PSS’s proposal’s superior
technical rating. The general statements in the SSAC’s and SSA’s
source selection documents as to why PSS’s technical superiority
did not offset the price/cost premium fall far short of the
requirement to justify cost/technical tradeoff decisions. See
Johnson Controls World Servs., Inc., supra, at 7. (Preferred
Systems Solutions, Inc., B-292322; B-292322.2; B-292322.3,
August 25, 2003) (pdf)
Contrary
to the source selection decision, nowhere in CBD's proposal does
it offer to provide an [DELETED] to develop a custom approach to
address technological weaknesses in the current database to meet
the current and future requirements, nor does CBD agree that it
would seek input from USAFWS instructors for this purpose. In
our view, a fairer reading of CBD's proposal to engage an
[DELETED] is that CBD recognized that it had no knowledge of the
USAFWS's current academic database and LAN, and that [DELETED]
was only to assist the [DELETED] CBD to “meet the contract
requirements.” We find no support for the SSA's conclusion that
CBD offered a “custom approach to address technological
weaknesses in the current database.” In fact, CBD's approach
(quoted above) for the most part either acknowledges, restates,
or generically responds to the SOW requirements with no
discussion or promise of a customized approach to satisfying
these requirements, except for some reference to employing
[DELETED] software. (SDS
International, Inc., B-291183; B-291183.2, December 2, 2002)
(pdf)
JWH asserts that it was improper for the source selection
authority (SSA) to serve as head of the price evaluation team,
since Federal Acquisition Regulation (FAR) § 15.308 provides
that “the source selection decision shall represent the SSA's
independent judgment.” This argument is clearly without merit.
While FAR § 15.308 requires the source selection decision to be
based on the SSA's exercise of independent judgment, it does not
expressly preclude the SSA from participating in the evaluation
process, and we see nothing in an SSA's doing so that is
inherently inconsistent with the exercise of independent
judgment. We are aware of no other applicable prohibition in
this regard. (J W Holding Group &
Associates, Inc., B-285882.3; B-285882.6, July 2, 2001)
(pdf)
Thus, when viewed in the overall scope of the procurement, the
SSA found the technical risk associated with the baseline
antenna approach to be narrow, isolated from the critical path,
and not of great concern to the overall cost and success of the
contract. Tr. at 172-76, 202-03, 217-19, 241-46, 259-60; Agency
Report, Tab 5B, Source Selection Decision, at 4. Considering
that antenna design was but one aspect of the architecture and
system performance subfactor, the developmental nature of this
procurement, and the fact that the SSA's rationale for changing
the risk evaluation is apparent in the source selection
decision, we find this rating change to be within the discretion
of the SSA and reasonable. See KPMG Consulting LLP, supra, at
13-14. As indicated above, this type of analysis by the SSA,
giving due consideration to the evaluation conclusions of the
lower-level evaluators, was entirely appropriate and reasonable.
See GTE Hawaiian Tel. Co., Inc., B-276487.2, June,
30, 1997, 97-2 CPD ¶ 21 at 18-19. (Raytheon
Company, B-291449, January 7, 2003) (pdf) (txt
version)
Thus, the record is clear that the SSA's tradeoff decision was
based on incorrect information concerning the relative timing of
Ashland's and Valley's delinquencies and a misstatement that a
contract was extended due to inexcusable rather than excusable
delay. Because of this, the decision's conclusion that
Valley had a superior timely record was unsupported by the
record. Moreover, the decision cast Ashland's proposal in
a more negative light than would be the case if the facts were
correctly stated, so that the evaluated advantage of Ashland
should be greater than what the SSA believed to be the case when
making the price/technical tradeoff. Since the SSA's
price/technical tradeoff decision favoring Valley's small price
advantage over Ashland's narrow technical advantage was
extremely close, correction of these errors could quite possibly
tip the tradeoff in favor of Ashland's higher-rated proposal.
In this regard, we note that as between Offeror A and Valley
that the SSA found a difference under the experience/past
performance factor that warranted payment of an even larger
price premium than existed between the proposals of Ashland and
Valley. (Ashland
Sales and Service Company, B-291206, December 5, 2002) (pdf)
(txt
version)
While adjectival ratings, like scores, may be useful as guides
to intelligent decision-making, they are not binding on the SSA,
who has discretion to determine the weight to accord them in
making an award decision. Porter/Novelli, B-258831, Feb. 21,
1995, 95-1 CPD ¶ 101 at 5. Of concern to our Office is
whether the record as a whole supports the reasonableness of the
evaluation results and the source selection decision. Orbital
Techs. Corp., B-281453 et al., 99-1 CPD ¶ 59 at 9. Here,
as discussed above, the record demonstrates the reasonableness
of the agency's evaluation of Campbell's proposal, and that the
SSA, in making the source selection, was aware of the TEB's
findings with regard to Campbell's proposal, the ratings
Campbell's proposal received under each of the evaluation
factors, and that the proposal was considered deficient with
regard to Campbell's approach to safety, quality control, and
experience of key personnel. As such, it is of little or no
significance whether the agency's overall rating of Campbell's
proposal as marginal was reasonable. (R.
L. Campbell Roofing Company, Inc., B-289868, May 10, 2002) (pdf)
(txt
version)
In a negotiated procurement with a "best value" evaluation plan
where selection officials reasonably regard proposals as being
essentially equal technically, price can become the determining
factor in making award, notwithstanding that the evaluation
criteria assigned price less importance than technical factors.
M-Cubed Info. Sys., Inc., B 284445; B-284445.2, Apr. 19, 2000,
2000 CPD P: 74 at 8. Here, the RFP evaluation scheme
explicitly provides that price would increase in importance as
the technical proposals become close to equal, and that price
may be the deciding factor between highly rated proposals.
At best, Vantage's technical proposal was evaluated as equal to
Raytheon's; in fact, the record reflects that the agency
consistently evaluated the Raytheon proposal as technically
superior, notwithstanding that the same *outstanding* ratings
were given to both proposals. Accordingly, Vantage's
objection that the agency improperly considered price to be
determinative is without merit because the agency's decision to
use low price as the determining factor between two equally
highly rated technical proposals was fully consistent with the
RFP award criteria. (Vantage
Associates, Inc., B-290802.2, February 3, 2003) (txt
version)
Here, there was no technical or price evaluation factor
providing for the evaluation of the offerors' understanding of
the requirements. The price evaluation factor provided only for
the evaluation of the “reasonableness” of the proposed price
(that is, whether the price was unreasonably high) and for
whether the price proposal was unbalanced, which is not
contended here. See RFP amend. 2, at 27-28. Moreover,
the RFP did not request cost or pricing information or any other
information that would allow the agency to determine that a low
proposed price reflected a lack of understanding of the contract
requirements. The agency's apprehension that CSE's price
was too low would appear to concern the firm's responsibility,
that is, whether CSE could satisfactorily perform at its
proposed price, Possehn Consulting, supra, at 4,
or whether CSE may have made a mistake in its proposed price.
Since CSE is a small business concern, if the agency believed
that CSE could not satisfactorily perform the contract at its
proposed price, the Corps was required to refer this finding of
non-responsibility to the Small Business Administration (SBA)
for that agency's review under its certificate of competency
procedures. Id. If the agency believed CSE had made a
mistake in its proposed price, it was required to request that
CSE verify its price. FAR § 15.306(b)(3)(i), which incorporates
the bid mistake rules of FAR § 14.407-3 (contracting officer
should obtain sufficient information to be reasonably assured
that the bid confirmed is without error). As noted above, the
agency did not request verification here. In any case,
here, the record establishes that CSE's proposal was not
considered for award by the SSA based primarily upon her
judgment that CSE's proposed price was unreasonably low and
reflected a lack of understanding of the contract requirements.
See Agency Report, Tab 9, Source Selection Decision, at
2. That is, although CSE was considered to be the “second best
qualified offeror,” CSE was not selected because of its two
marginal ratings and “unreasonably low” price. Id. In
performing the price/technical tradeoff required by the RFP, the
SSA did not consider CSE's significantly lower price to be an
advantage to be weighed against the awardee's higher technical
rating. We think that if CSE's price advantage had been
properly weighed in the agency's price/technical tradoff
analysis, it would have had a reasonable possibility of being
selected for award. Accordingly, we sustain CSE's protest on
this basis. (CSE
Construction, B-291268.2, December 16, 2002)
Furthermore, and perhaps more significantly, the SSA's
determination that the responses for |