|
As a general rule, bidders are responsible for delivering their
bids to the proper place at the proper time, and late delivery
of a bid generally requires its rejection even if it is the
lowest bid. J.C.N. Constr. Co., Inc., B-270068,
B-270068.2, Feb. 6, 1996, 96-1 CPD para. 42 at 3; Aztec Dev.
Co., B-256905, July 28, 1994, 94-2 CPD para. 48 at 3. A bid
is late if it does not arrive at the office designated in the
solicitation by the time specified, Federal Acquisition
Regulation sect. 14.304(b)(1); Aztec Dev. Co., supra.,
and, normally, receipt at other places, such as a post office
box or the agency’s mailroom, is insufficient. Biones Constr.
& Equipment Co., Inc., B-279575, June 29, 1998, 98-1 CPD
para. 175 at 4-5. In this regard, bidders must allow a
reasonable time for bids to be delivered from the designated
point of receipt (such as in this case, a post office box) to
the bid opening room which is the ultimate destination for bid
opening. See Bay Shipbuilding Corp., B-240301, Oct. 30,
1990, 91-1 CPD para. 161 at 3, n.1. Our review of the record
shows that although the protester’s bid was received at the
agency’s mailroom, an intermediate stop for delivery of the
package, approximately 4 hours prior to bid opening, there is no
evidence that the bid was received by the contracting division
before the 2 p.m. bid opening. Further, the contracting
specialist to whom bids were to be addressed and who conducted
the bid opening did not receive the protester’s bid package
until approximately 2 hours after bid opening. Accordingly, we
find reasonable the agency’s determination that the bid was
late.
While a late hand-carried bid may be considered if it is
determined that the late receipt was due primarily to government
mishandling after receipt at the government installation, a late
bid should not be accepted if the bidder significantly
contributed to the late receipt by not acting reasonably in
fulfilling its own responsibility to submit its bid in a timely
manner. Comspace Corp., B-281067, Nov. 30, 1998, 98-2 CPD
para. 122 at 2. Where, as here, a bidder fails to record on its
bid’s sealed envelope required information as to the
solicitation number it is responding to, and the deadline for
its receipt, and, moreover, as here, also fails to address its
bid submission to the required point of contact at the address
provided in the IFB for bid submission, the bidder is usually
primarily responsible for any delay in its delivery. Boines
Constr. & Equipment Co., Inc., supra. In this case, the
protester failed to address its bid to the appropriate
individual, and failed to mark its bid package envelope in any
way to indicate that it contained time-sensitive bid
information, which caused the package to be sorted for standard
delivery to the contracting division, rather than under the
mailroom’s accelerated procedures for delivery of bid documents.
We agree with the agency that the firm here failed to do what it
reasonably could and should have done to ensure proper delivery,
and its failure to take the available steps to ensure timely
delivery was the paramount cause of the bid’s late receipt.
Since there has been no showing of government mishandling of the
bid package, the bid was properly rejected as late. (Aquaterra
Contracting, Inc., B-400065, July 14, 2008) (pdf)
We find nothing objectionable in the agency’s rejection of
Amigo’s second bid modification. The modification was plainly
late, since it did not reach the designated location for receipt
of bids prior to bid opening. To the extent that the protester
believes that government mishandling was the cause of the
modification’s being late or that Amigo did all it could
reasonably be expected to do to ensure timely delivery, see
Weeks Marine, Inc., supra, we believe that the record
establishes that the protester’s belief is unsupported. As
indicated, by the protester’s own account, the modification was
sent by facsimile at 1:51 p.m. and the transmission took 7.51
minutes to reach the agency’s facsimile machine, thereby
allowing one minute for agency personnel to retrieve, process,
and deliver this modification to the bid opening room. The
record shows that at the time the contract specialist was
notified that it was time to conduct the bid opening, the second
bid modification was not printed in its entirety--page 3 of the
four pages (containing the second page of the bid schedule) was
still printing. This being the case, it was primarily (if not
entirely) the protester’s tardy beginning of the transmission
that caused the failure of the modification to reach the bid
opening room on time. Nothing in the record suggests mishandling
of the modification by the government. Finally, the protester
alleges that the government was legally required to consider the
bid modification, since it was received in the memory of the
agency’s facsimile machine before 2 p.m. and was therefore
effectively in the Corps’s control before bid opening. We
disagree. At least in the circumstances of this case--where the
solicitation clearly placed the risk of facsimile transmission
problems on bidders and yet Amigo nonetheless began transmitting
its second bid modification within the final few minutes before
the start of bid opening--we do not believe that receipt in the
facsimile machine’s memory (assuming, arguendo, that the
modification was in the machine’s memory before bid opening)
qualifies as “under the Government’s control” prior to the time
for receipt of bids as contemplated by the clause at FAR §
52.214-7 so as to require the agency to consider the protester’s
late bid modification. (Amigo-JT Joint
Venture, B-292830, December 9, 2003) (pdf)
When evaluating the acceptability of a late bid outside the
strict confines of the late bid regulations, we are guided by
the general principle that where a bidder has done all it could
and should to fulfill its responsibility, it should not suffer
if the bid is untimely because the government failed in its own
responsibility, so long as acceptance of the bid would not cast
doubt on the integrity of the bidding process. See Palomar
Grading & Paving, Inc., B-274885, Jan. 10, 1997, 97-1 CPD ¶ 16
at 3-4. Accordingly, we have found late bids acceptable where
the government’s affirmative misdirection—such as erroneous
solicitation instructions--was the paramount cause of a bidder’s
untimely delivery of its bid since an agency has an affirmative
duty to establish procedures for the timely receipt of bids. See
id.; Select, Inc., B-245820.2, Jan. 3, 1992, 92-1 CPD ¶ 22 at 4.
In this case, the IFB listed the wrong room for delivery of
bids. This error, which was attributable solely to the
government, directly resulted in Great Lakes submitting its bid
1 minute late. Had the government provided for the receipt of
bids in the room identified in the IFB, there is no doubt that
Great Lakes’ bid would have been timely; the record clearly
demonstrates that Great Lakes was at the room designated for
receipt of bids approximately 5 minutes in advance of the time
set for bid opening. But, because Great Lakes was required to
make its way from the designated bid opening room to the actual
bid opening room, the government effectively caused Great Lakes’
bid to be received late. As a consequence, the misdirection by
the agency was the paramount cause of Great Lakes’ untimely
submission of its bid. As a final matter, it does not appear
that accepting Great Lakes’ bid compromised the integrity of the
procurement. When addressing this issue, the operative question
is whether the late bidder gained an unfair competitive
advantage over other bidders as a result of having submitted its
bid late. See Brazos Roofing, Inc., B-275113, Jan. 23, 1997,
97-1 CPD ¶ 43 at 5. In this regard, the protester emphasizes the
fact that the agency did not receive Great Lakes’ bid until
after approximately three of the protester’s 18 bid line items
had been disclosed. According to the protester, this provided
Great Lakes with the opportunity to decide not to furnish the
bid after bid opening. The protester’s concern, however, is
tempered by the fact that the position in which Great Lakes was
placed resulted from the actions of Corps personnel and was not
by its own design or choosing. Moreover, there is nothing in the
record to suggest that Mr. Inglis, who delivered Great Lakes’
bid, actually heard the prices when they were read. Mr. Inglis
had only a few minutes to go from the the 19th floor to the
actual bid opening room on the 18th floor; when he arrived,
Corps personnel noted that he appeared hurried and out of
breath. Agency personnel also indicated that they did not see
anyone outside the bid opening room when the contracting officer
called time. Under these circumstances, Mr. Inglis’ statement in
his declaration that he did not hear any prices being read prior
to handing Great Lakes’ bid to the agency, seems credible. (Weeks
Marine, Inc., B-292758, October 16, 2003) (pdf)
GPEA contends that the agency has not adequately shown that its
bid was received late. GPEA challenges the agency's reliance on
the log maintained by the security guards because the guards are
not government employees. In our view, the log is acceptable
evidence of the time of receipt. It is undisputed that the log
is a record maintained by the security guards in the regular
course of monitoring the loading dock for the agency, and there
is no reason to challenge its authenticity or reliability. The
fact that the log is compiled by security guards who are
contract employees rather than government employees does not
preclude reliance on the log. See J. L. Malone & Assocs.,
B-290282, July 2, 2002, 2002 CPD ¶ 116 at 5.
GPEA itself submitted a copy of a “customer cartage manifest”
from Airborne Express that purports to show that the bid package
was delivered to the loading dock at 11:49 a.m. on bid opening
day.2 Commercial carrier records, standing alone, however, do
not serve to establish the time of delivery to the agency, since
they are not evidence of receipt maintained or confirmed by the
agency. Valenzuela Eng'g, Inc., B-280984, Dec. 16, 1998, 98-2
CPD ¶ 145 at 3. In any event, to the extent that GPEA relies on
the Airborne Express document to establish that its bid was not
in fact late, receipt of a bid at a mailroom or other receiving
area does not constitute receipt at the office specified in the
IFB. Inland Marine Indus., supra. Thus, even assuming that GPEA
had established that the bid was received at the loading dock
before the closing time--which it has not--the bid nevertheless
properly would be considered late, since there is no evidence
showing receipt of the bid in the specified office by the time
set for receipt of bids in the IFB. (General Power
Engineering Associates, Inc., B-292170, May 28, 2003)
(pdf)
Although the contracting officer
was the official designated in the prospectus as the recipient
of mailed bids, the contracting officer was not present at his
desk or in his office prior to bid opening, and did not return
to his office prior to bid opening to determine whether any last
minute bids had been received. The bid opening official did
check the mailroom and the mail clerk's desk prior to bid
opening, but she too failed to check the contracting officer's
desk. This failure by the cognizant officials to check the desk
of the official designated for receipt of bids constituted
mishandling. (Carroll
Gene Brewer, B-285484, August 22, 2000)
In short, there is no acceptable
evidence which establishes that Cal Marine's bid was received at
the installation prior to bid opening, as required under the
test set forth in Pershield, Inc., supra, at 3, and it follows
that if timely receipt cannot be established by acceptable
evidence, then the second requirement of Pershield--i.e., that
the bid was in the government's sole custody from prior to bid
opening until discovered--is also not met. In this case, the
location of Cal Marine's bid at any time prior to its discovery
on January 14 remains unaccounted for. Accordingly, the bid
cannot be properly considered, Chelsea Clock Co., Inc.,
B-251348.2, May 24, 1993, 93-1 CPD para. 401 at 4, and the
protest is sustained. (Pacific
Tank Cleaning Services, Inc., B-279111.2, July 1, 1998)
However, a late bid should not
be accepted if the bidder significantly contributed to the late
receipt by not acting reasonably in fulfilling its
responsibility for ensuring delivery to the designated place for
receipt by the proper time. Aztec Dev. Co., supra, at 3; John
Holtman and Sons, Inc., B-246062, Feb. 13, 1992, 92-1 CPD para.
187 at 2; J.E. Steigerwald Co., Inc., supra, at 5. Where the
bidder fails to record required information as to the
solicitation number, deadline for receipt and ultimate
destination on the outside envelope provided by the commercial
carrier, the bidder is usually primarily responsible for any
delay in delivery. See Systems for Bus., B-224409, Aug. 6, 1986,
86-2 CPD para. 164 at 3-4. Here, Pierce's failure to mark its
commercial carrier-provided envelope as required by FAR sec.
52.214-5 was the paramount reason for the delay resulting from
the mailroom's "misrouting" of its bid. (Boines
Construction & Equipment Co., Inc., B-279575, June 29,
1998) |