Resource
complains that the agency unreasonably evaluated its technical
quotation because the agency's assigned weaknesses in support of
its determination that Resource's quotation was technically
unacceptable were, in fact, adequately addressed in Resource's
presentation.
Simplified acquisition procedures are designed to, among other
things, reduce administrative costs, promote efficiency and
economy in contracting, and avoid unnecessary burdens for
agencies and contractors. FAR sect. 13.002; Sawtooth Enters.,
Inc., B-281218, Dec. 7, 1998, 98-2 CPD para. 139 at 3. When
using simplified acquisition procedures, an agency must conduct
the procurement consistent with a concern for fair and equitable
competition and must evaluate quotations in accordance with the
terms of the solicitation. In reviewing protests of an allegedly
improper simplified acquisition evaluation, we examine the
record to determine whether the agency met this standard and
executed its discretion reasonably. Computers Universal, Inc.,
B‑297552, Feb. 14, 2006, 2006 CPD para. 42 at 4-5; DOER Marine,
B-295087, Dec. 21, 2004, 2004 CPD para. 252 at 3. Moreover, even
for procurements under simplified acquisition procedures, it is
a fundamental principle of government accountability that an
agency be able to produce a sufficient record to allow for a
meaningful review where its procurement actions are challenged.
See e-LYNXX Corp., B-292761, Dec. 3, 2003, 2003 CPD para. 219 at
8; Checchi and Co. Consulting, Inc., B-285777, Oct. 10, 2001,
2001 CPD para. 132 at 6. In this regard, where an agency fails
to adequately document its actions, it bears the risk that there
may not be adequate supporting rationale in the record for us to
conclude that the agency had a reasonable basis for the source
selection decision. Southwest Marine, Inc.; American Sys. Eng'g
Corp., B-265865.3, B-265865.4, Jan. 23, 1996, 96‑1 CPD para. 56
at 10. Nevertheless, in reviewing an agency's procurement
actions, we do not limit our review to contemporaneous evidence,
but consider, as appropriate, hearing testimony and the parties'
arguments. Id.
Here, while Resource's 1-hour oral presentation was videotaped,
the Q&A session was not. Instead, this session was documented by
hand-written notes taken by acquisition personnel. The contract
specialist used these notes, and her own, to prepare a document
memorializing the session. When Resource asserted that the
contract specialist's account mischaracterized its answers, the
contract specialist permitted Resource to submit its version of
the answers, which with a few edits by the agency, was accepted
as an accurate memorialization of the session. AR, Tab 19f,
Email from Contract Specialist (Nov. 4, 2010). The accepted
revisions provided much more detailed answers to the questions
offered during the Q&A session of the oral presentation, for
example, in the areas of collaboration with federal bureaus and
methods. AR, Tab 19e, Resource's Final Q&A Document.
Because of the events surrounding Resource's Q&A session, this
was an issue at the hearing that our Office conducted on this
protest. At the hearing, a witness from the TEP was asked by the
hearing officer to provide her recollection of Resource's Q&A
session. The hearing officer read several of the questions from
the document memorializing Resource's answers during the Q&A
session to the TEP member, who testified that she had not seen
either the initial or finalized version of the document. Tr. at
30-31, 84. Although the TEP member testified that she was able
to recall some of the questions, she had limited recall of
Resource's answers; to the extent she recalled the answers, her
recollection seemed more consistent with the initial version of
the Q&A document, than with the final document that the agency
agreed more accurately reflected Resource's answers. Tr. at 93,
133, 135-36. Moreover, the initial, less detailed, version of
Resource's responses to the questions posed in the Q&A session
is more consistent with the technical consensus document
concluding that Resource's quotation was technically
unacceptable because it explained that the answers given by
Resource on October 14, particularly in the areas of
collaboration and methods, failed to provide sufficient detail
to convince the technical evaluators that its quotation was
technically acceptable. AR, Tab 21, Consensus of Resource, at
2-3.
Thus, despite receiving hearing testimony and the parties'
post-hearing arguments, we cannot find that the agency's
documentation in regard to Resource's Q&A session is sufficient
to allow us to review the reasonableness of the agency's
judgments. Because the final, mutually agreed-upon version of
the Q&A document addresses some of the weaknesses included in
the TEP's consensus report that supported Resource's
unacceptable rating, this document is at odds with the consensus
evaluation report. In addition, the final Q&A document, which
the agency accepted as an accurate memorialization of the
session, is inconsistent with the testimony of the TEP witness;
at a minimum, the final document provides more robust answers
than the TEP member recalled during her testimony. Compare AR,
Tab 19e, attach., Final Q&A Document for Resource's Oral
Presentation, at 3 with Tr. at 135-136. In view of these
discrepancies, it is unclear whether the TEP members reasonably
understood and considered Resource's answers at the oral
presentation. Accordingly, we cannot find that the agency's
documentation adequately supports its decision. See e-LYNXX
Corp., supra; Checchi and Co. Consulting, Inc., supra. (Resource
Dimensions, LLC, B-404536, February 24, 2011) (pdf)
Frontier argues that its quote was reasonable and that the CO
failed to properly evaluate its quoted price in accordance with
the terms of the RFQ. Frontier also argues that the IGE was
flawed and should not be used as a basis to determine price
reasonableness. The protester further argues that since it was
the only HUBZone small business vendor to submit a quote, the CO
could not evaluate its price by comparing it to the prices
quoted by other small business concerns.
As noted above, the procurement was conducted under simplified
acquisition procedures. Simplified acquisition procedures are
designed to, among other things, reduce administrative expenses,
promote efficiency and economy in contracting, and avoid
unnecessary burdens for agencies and contractors. Federal
Acquisition Regulation (FAR) sect. 13.002. These procedures
provide discretion to COs to use one or more of the evaluation
procedures in FAR Parts 14 and 15. See FAR sect. 13.106-2(b);
Finlen Complex, Inc., B-288280, Oct. 10, 2001, 2001 CPD para.
167 at 8-10. When using these procedures, an agency must conduct
the procurement consistent with a concern for fair and equitable
competition and must evaluate quotations in accordance with the
terms of the solicitation. In reviewing protests of an allegedly
improper simplified acquisition evaluation, we examine the
record to determine whether the agency met this standard and
exercised its discretion reasonably. Russell Enters. of N.
Carolina, Inc., B-292320, July 17, 2003, 2003 CPD para. 134 at
3.
The primary issue here is Frontier’s claim that the CO
improperly used an “unreasonable price” determination to reject
the quote of a HUBZone business concern. As stated above, the
RFQ specifically provided that a BPA would be issued to those
vendors who submitted a technically acceptable quote at a
reasonable price. RFP para. E.2. The RFQ further stated that
price would be evaluated in accordance with the FAR. Id. Under
simplified acquisition procedures price reasonableness is
determined by the CO. FAR sect. 13.106-3(a). The CO may make a
reasonableness determination based on a comparison to an IGE.
FAR sect. 13.106-3(a)(2)(vi). Here, the CO, in accordance with
the FAR, based her price reasonableness decision on an IGE that
was prepared using market research. Frontier’s quote was
significantly higher than the IGE and was therefore determined
to be unreasonably priced. We do not find this determination to
be unreasonable.
The protester also argues that the IGE used here was developed
after an inadequate evaluation of the market for the required
equipment. In calculating the IGE, the agency reports that it
contacted companies in Montana, Idaho and Washington who offered
mobile refrigerated units for rent and the prices from these
firms ranged from $125 through $175 with variations in pricing
schemes depending on length of rental. AR, Tab 2, CO Statement
at 6. The agency also did an internet search to establish a
price range for similar units meeting OSHA (Occupational Safety
and Health Administration) requirements. Finally, the IGE was
established by adding a premium amount to an average of the
market prices to take into consideration the excessive wear and
tear the equipment would experience. Id.
On this record, we have no basis to conclude that the IGE was
not reasonably based or that the market research was inadequate.
If anything, the adequacy of the agency’s market research was
vindicated by the quotes it received from numerous other small
business concerns. Frontier’s argument that the IGE was based on
an inadequate evaluation of the market reflects mere
disagreement with the agency’s assessment and provides no basis
for our Office to sustain a protest. (Frontier
Transportation, Inc., B-400345, September 9, 2008) (pdf)
In reviewing a protest against an agency’s evaluation of
quotations, we examine the record to determine whether the
agency’s judgment was reasonable and consistent with the stated
evaluation criteria and applicable statutes and regulations.
American Artisan Prods., Inc., B-286239, Nov. 29, 2000, 2000 CPD
para. 198 at 2. Here, we think that the agency reasonably
rejected the quotation as unacceptable based on the protester’s
failure to furnish an image demonstrating that the thumbdrive
that it was offering contained an external write-protect switch.
The RFQ required vendors to submit an image of the write-protect
switch, presumably, as noted, to demonstrate the switch’s
compliance with the requirement that it extend above the body of
the drive so as to be operable by finger (i.e., without the use
of a tool). It is the vendor’s responsibility to submit the
information requested by the agency for evaluation purposes, and
a vendor that does not do so runs the risk that its quotation
will be rejected as unacceptable. 3K Office Furniture
Distribution GmbH, B-292911, Dec. 18, 2003, 2003 CPD para. 231
at 4. Here, the only image that the protester furnished to the
contracting officer prior to the technical evaluation on July 13
was the image of the drive incorporating a biometric switch that
it proposed for the top secret drives. Even assuming that
this image satisfied the RFQ requirement for an image of a
finger-operated write-protect switch with regard to the top
secret drives, the fact remains that the protester furnished no
image of the switch that it was proposing for the unclassified
and secret drives. While the protester maintains that it had
previously furnished a color picture of a thumbdrive with an
appropriate switch in response to an earlier RFQ that was
cancelled, the protester made no reference to the previously
submitted image in the quotation that it submitted in response
to the RFQ here; given the lack of any reference to the previous
submission, we do not see how the evaluators should have been
expected to know of its existence and/or the fact that it was an
image of the product that Joint Systems intended to furnish
here. Accordingly, we think that the evaluators reasonably
rejected the protester’s quotation as technically unacceptable
for failing to furnish a picture of a write-protect switch
conforming to the solicitation requirements for the secret and
unclassified drives. (Joint Systems,
Inc., B-298573, October 6, 2006) (pdf)
When using simplified acquisition procedures under FAR Part 13,
an agency must conduct the procurement consistent with a concern
for fair and equitable competition. In reviewing protests
against an allegedly improper simplified award selection, we
examine the record to determine whether the agency met this
standard and exercised its discretion reasonably. Dew Drop
Sprinklers & Landscaping, B‑293963, July 15, 2004, 2004 CPD para.
171 at 3. The agency claims that telecommunications services
were necessary to test and demonstrate the operability of the
KVTS, and that it added the $7,000, which was taken from the
same price schedule containing CUI’s $20,000 quotation to make
the system operable, to account for these costs because “[t]he
government also had to identify the cost of telecommunications
within the CUI quotation in order to ensure [that] CUI had
presented a viable proposal of reestablishing operability and
testing of the KVTS,” given that CUI’s quotation did not
specifically indicate that such costs were included. Contracting
Officer’s Supplemental Statement at 3. CUI’s claim that the
costs for necessary telecommunications were included in its
$20,000 lump sum quotation is consistent with its e-mails and
quotation, given that the quotation expressly included the
acquisition of new cell phone lines and testing of the system,
which could not be done without an active telecommunications
service. In addition, CUI’s quotation clearly indicated that the
$7,000 figure used by the agency in the evaluation was not the
total monthly telecommunications charges, but was a proposed
increase to the monthly communications charges under CUI’s
maintenance contract, and that this proposed increase was not
related to CUI’s quotation to make the system operable. Our
review reveals no reasonable basis for the agency to assume that
the $7,000 increase referred to in CUI’s quotation represented
the cost of telecommunications that would be needed to make the
system operable under the purchase order. In any case, the
record evidences that the contracting officer did not ask CUI
whether the costs for necessary telecommunications were included
in its quotation or request CUI to separately price the
telecommunications charges. Instead, when its quotation was
solicited, CUI was asked to provide “a detailed proposal of what
work and costs would be required to reestablish KVTS
operability,” and for a “[p]roposed cost for the overall
effort,” to reestablish the operability of the KVTS. Contracting
Officer’s Supplemental Statement at 2; Agency Supplemental
Report, Tab H, E-mail from Contracting Officer to CUI (Sept. 9,
2006). Before adding this $7,000 charge to CUI’s quotation for
evaluation purposes, the agency, at a minimum, should have
requested CUI to verify whether or not the costs for necessary
telecommunications to accomplish the purchase order work were
included in its $20,000 quotation. In sum, the agency
unreasonably added CUI’s proposed $7,000 increase in its
telecommunications monthly charge in the KVTS maintenance
contract to CUI’s $20,000 quotation without first requesting
that CUI verify whether the necessary telecommunications costs
were already included in its quotation. On this record, CUI’s
$20,000 quotation was the lowest-priced one, and CUI should have
been issued the purchase order, if otherwise appropriate.
Because we are advised by the agency that the performance under
this purchase order has been completed, we recommend that CUI be
reimbursed its quotation preparation costs as well as the
reasonable costs of filing and pursuing the protest. 4 C.F.R.
sect. 21.8(d)(1), (2). CUI should submit its certified claim for
costs, detailing the time expended and costs incurred, directly
to the agency within 60 days of receiving this decision. (Computers
Universal, Inc., B-297552,February 14, 2006)
We find the source selection to be reasonable and in accordance
with the terms of the solicitation. Although Dew Drop asserts
that it was improper for the agency to consider the relative
experience of the two offerors as a discriminator, the RFQ
specifically stated that the agency would evaluate experience,
along with past performance, technical ability to meet the
requirements and price, and make award to the vendor whose
quotation provided the best value after considering these
factors. Further, while Dew Drop challenges the agency's
position that the technical evaluation factors were important,
arguing that the project was only a simple one, we note that the
RFQ did not make price more significant than the technical
factors. On the contrary, the RFQ did not specify the relative
importance of the individual evaluation factors and, in the
absence of any indication in the RFQ of the relative importance
among the individual evaluation factors, they are presumed to be
of equal importance. See Hyperbaric Techs., Inc. , B293047.2;
B-293047.3, Feb.11, 2004, 2004 CPD 87 at 4; Maryland Office
Relocators , B-291092, Nov. 12, 2002, 2002 CPD 198 at 5. Agency
officials have broad discretion in determining the manner and
extent to which they will make use of the technical and cost
evaluation results. Price/technical tradeoffs may be made, and
the extent to which one is sacrificed for the other is governed
by the test of rationality and consistency with the established
factors. See Structural Preservation Sys., Inc. , B-285085, July
14, 2000, 2000 CPD 131 at 7. An agency may properly select a
more highly rated quotation over one offering a lower price
where it has reasonably determined that the technical
superiority outweighs the price difference. See Sawtooth
Enters., Inc. , supra. , at4. As explained above, the
contracting officer determined that TML's non-price advantages
warranted payment of that firm's higher price. Dew Drop has
furnished no basis for our Office to question this
determination. (Dew Drop Sprinklers &
Landscaping, B-293963, July 15, 2004) (pdf)
Here, we find that the contracting officer failed to give any
meaningful consideration to e-LYNXX’s substantially lower
quotation price, given his inability to explain why Noosh’s
superiority was worth the more than 65 percent higher price.
More specifically, we question whether the contracting officer
had a sufficient basis to perform a rational price/technical
tradeoff where he testified that the open posting requirement
was a key consideration in his analysis but that he did not
understand the requirement or obtain any advice concerning it
from anyone that did. We fail to see how the contracting officer
can assign value for something he admittedly does not understand
and for which he did not seek any advice, and we sustain e-LYNXX’s
protest on this basis. (e-LYNXX
Corporation, B-292761, December 3, 2003) (pdf)
Under the circumstances, we find that the USDA's decisions to
rate Houston's quotation unacceptable under the weight and
balance factor and to not conduct discussions with that firm
were reasonable and not unfair. The RFQ informed offerors that
award would be made without discussions, RFQ § E.1(g), and it
does not appear from the record that the exchanges afforded
Commander an opportunity to revise its quotation. Given that
Houston failed to provide the required weight and balance sheet,
which rendered its quotation unacceptable under this factor, the
agency did not have to engage in discussions with Houston to
enable it to remedy this deficiency. CDS Network Sys., Inc.,
B‑281200, Dec. 21, 1998, 98-2 CPD ¶ 154 at 3. (Houston
Air, Inc., B-292382, August 25, 2003) (pdf)
We recognize that the agency may have reasonably desired, and
certainly could have required, that technical proposals include
a detailed plan, as well as evidence of the vendors'
understanding of the requirements and their qualifications and
experience. That would be altogether appropriate and within the
agency's discretion. Stating such desires and requirements is
the purpose of evaluation criteria in a solicitation, and it is
to provide transparency in our federal procurement process and
fairness for those competing for federal contracts that, as
explained above, agencies are required by procurement law to set
out in the solicitation the evaluation criteria, and then to
follow them. Here, the RFQ did not put vendors on notice of any
of the requirements that the agency has now identified. In our
view, it would be unfair for the agency, after the fact, to
evaluate technical proposals based on criteria that the agency
was required to identify before vendors submitted those
proposals. See FAR §§ 13.106-1(a)(2), 13.106‑2(a)(2). We
therefore sustain the protest. (SKJ
& Associates, Inc., B-291533, January
13, 2003) (pdf) (text
version)
Where an agency is not required to hold discussions or otherwise
communicate with vendors regarding past performance information,
as is the case where simplified acquisition procedures are
employed, see FAR § 13.106-2(b)(2), and the contracting officer
has no reason to question the validity of the past performance
information, we think that she can reasonably rely on the
information furnished without seeking to verify it or permitting
the protester an opportunity to rebut it. Lynwood Mach. &
Eng'g, Inc., B-285696, Sept. 18, 2000, 2001 CPD ¶ 113 at
7. Moreover, we note that an agency's past performance
evaluation may be based on a reasonable perception of inadequate
prior performance, even where the protester disputes the
agency's interpretation of the underlying facts. Quality
Fabricators, Inc., B-271431, B-271431.3, June 25, 1996, 96-2 CPD
¶ 22 at 7. Thus, we conclude the agency's actions were
unobjectionable. (John
Blood, B-290593, August 26, 2002)
Although
an agency is not required to establish a competitive range or
conduct discussions under simplified acquisition procedures, we
think that where an agency avails itself of these negotiated
procurement procedures, the agency should fairly and reasonably
treat quoters in establishing the competitive range and
conducting discussions. See Finlen Complex, Inc., B-288280, Oct.
10, 2001, 2001 CPD para. 167 at 8-10.
In sum, we find
unreasonable the Corps's competitive range determination that
included only Act II's quote. In making this judgment, the Corps
apparently mistakenly believed that Act II's quote satisfied all
the solicitation requirements and was acceptable. Instead, the
record shows that two firms' quotes suffered from similar
informational weaknesses that were susceptible of correction
through discussions. We sustain KHA's protest because the Corps
failed to treat the two firms fairly and equally with respect to
conducting discussions. (Kathryn
Huddleston and Associates, Ltd., B-289453, March 11, 2002)
Where an agency is not required to
hold discussions or to otherwise communicate with vendors
regarding past performance information, as is the case here
where simplified acquisition procedures were employed, see FAR
sect. 13.106-2(b)(2), and where the evaluators and selection
official have no reason to question the validity of the past
performance information, they can reasonably rely on the
information furnished without seeking to verify it or permitting
the protester an opportunity to rebut it. See A.G. Cullen Constr.,
Inc., B-284049.2, Feb. 22, 2000, 2000 CPD para. 45 at 5. (Ocean
Technical Services, Inc., B-288659, November 27, 2001)
In our view, it was inappropriate
for the agency, on the one hand, to request quotes from the
vendors for equipment for six locations and to issue a delivery
order based on the prices for all six locations, and, on the
other hand, for price evaluation purposes, to consider prices
for only five locations. Procuring agencies do not have the
discretion to announce one evaluation scheme and then follow
another in the actual evaluation. Technical Support Servs.,
Inc., B-279665, B-279665.2, July 8, 1998, 98-2 CPD para. 26 at
3. The record shows that, had the agency compared the quotes
based on the prices proposed for all six locations, as requested
by the agency, then the protester's quote would have been low.
Nonetheless, based on the record here, the selection of the
Solvetech system is unobjectionable. The agency solicited quotes
orally, which is allowed under FAR sect.13.106-1(c), and while
vendors were told that price would be the predominant
consideration in the selection decision, vendors were also
advised that other factors, such as life-cycle costs,
standardization and ease of data extraction would also be
considered. Telephone Hearing, Jan. 21, 2000. After evaluating
price and technical considerations, the agency reasonably
determined that the Solvetech system represented the better
value. (AudioCARE
Systems, B-283985, January 31, 2000)
Even under simplified
acquisition procedures, award decision is not reasonable where
the record does not provide any documentation or explanation
which supports the price/technical tradeoff, and the award
determination appears to be based entirely on a comparison of
total technical point scores without consideration of
protester's lower technically scored, but low priced proposal.
(Universal
Building Maintenance, Inc., B-282456, July 15, 1999) |