FAR
6.001: Competition: Modifications, beyond the scope |
Comptroller
General - Key Excerpts |
New
In determining whether a
modification to a contract or task order is beyond the scope of
the contract or order, and thereby triggers applicable
competition requirements, we look to whether there is a material
difference between the modified order and the order that was
originally awarded. Booz Allen Hamilton Eng’g Servs., supra, at
6-7; see also MCI Telecomms. Corp., B-276659.2, Sept. 29, 1997,
97-2 CPD ¶ 90 at 7. Evidence of a material difference between
the modification and the original order is found by reviewing
the circumstances attending the original procurement, and any
changes in the type of work, performance period, and costs
between the order as issued and as modified. See Erickson
Helicopters, Inc., B-415176.3, B-415176.5, Dec. 11, 2017, 2017
CPD ¶ 378 at 7; see also Western Pilot Serv., et al., B‑415732
et al., Mar. 6, 2018, 2018 CPD ¶ 104 at 6. We also consider
whether the solicitation for the original order adequately
advised offerors of the potential for the type of change found
in the modification, and thus whether the modification could
have changed the field of competition. Western Pilot Serv. et
al., supra; see also DOR Biodef., Inc.; Emergent BioSols.,
supra. Here, we find that the [technical direction letter] TDL
is out of scope of the task order it purports to clarify.
The TDL was issued in order to assist [Naval Air Warfare Center
Aircraft Division] NAWCAD “in establishing operations in a
Commercial Cloud Com[p]uting facility.” AR, Tab 4, TDL, at 2.
GSA confirms that “[t]he TDL scope of work pertains to
supporting [NAWCAD’s] move to the Cloud environment,” but
contends that “the scope of requirements contained in the TDL
was entirely consistent with the scope” of the RRTS task order.
MOL at 8-9; see also Intervenor Comments at 13 (concurring with
agency that TDL is within scope). However, the RRTS task order
makes only limited reference to cloud services, i.e., that
“[t]he contractor shall provide research and analysis support .
. . necessary to assess systems in areas such as Cloud, Big Data
. . . .” AR, Tab 3, RRTS Task Order, at C-10.
More specifically, the agency asserts that establishment of a
commercial cloud facility is within scope of the RRTS task
order, specifically section C.5.3(b). COS ¶ 12, citing AR Tab 3,
RRTS Task Order, at C-10; AR Tab 4, TDL. Section C.5.3(b)
instructs the RRTS contractor to “[p]rovide support to C4ISR and
Big Cloud system technology insertion initiatives, including
transfer and transition of existing and emerging technologies.”
AR, Tab 3, RRTS Task Order, at C‑10. However, section C.5.3
instructs the contractor to provide “research and analysis
support . . . by developing custom identification, collection,
interpretation and evaluation systems necessary to asses systems
in areas such as the Cloud, Big Data . . . .” Id. Thus, the RRTS
subsection (b) “insertion initiatives” are provided as part of
research and analysis support for the RRTS task order, not
enterprise-wide cloud migration and operations as contemplated
by the TDL.
The agency also argues that section C.5.4 of the [Rapid Response
Technical Services] RRTS task order requires the contractor to
“provide general requirements support, to include providing
logistics support, software and hardware support, operations and
maintenance support, operator procedures, systems integration
and demonstration, and exercise preparation support,” and that
these tasks encompass the TDL work. MOL at 9. However, the
contractor’s responsibilities here are project-based and,
importantly, relate to information assurance for classified
material and must be performed according to certain guidance
applicable to classified systems and classified material. AR,
Tab 3, RRTS Task Order, at C-11. In contrast, the TDL scope of
work does not mention work on classified systems. Thus, this
task order section does not reasonably encompass any TDL work.
Overall, we find that the TDL’s work in supporting the migration
to and operation of a cloud facility differs materially from the
RRTS’s scope of work, i.e., providing research and analysis
support for systems assessment. For example, under the heading
of information assurance support, the RRTS task order requires
the contractor to support risk management certification and
accreditation with regard to intelligence community classified
information technology systems. On the other hand, the TDL
requires the contractor to “[e]ducate and develop an organic
understanding of” DoD guidance relating to unclassified data as
part of its information assurance support. Further, under the
TDL the contractor must “[e]ducate and develop an organic
understanding of” DoD’s “cloud first policy, and how to best
utilize that to our advantage, to reduce time to Approval to
Operate” the new cloud-based IT systems. Compare AR, Tab 3, RRTS
Task Order, at C-11 with AR, Tab 4, TDL, at 4-5. The work
related to establishing an unclassified cloud environment under
the TDL is substantively different from tasks supporting
certification and accreditation related to classified
environments under the RRTS task order.
Similarly, the TDL asks the contractor to perform work that goes
beyond the RRTS task order scope of work. For example, the TDL
scope of work requires the contractor to “[p]rovide IT support
services to manage the Government’s enterprise-wide IT server
and storage computing environments,” and “manage delivery of all
enterprise IT services.” AR, Tab 4, TDL, at 5. However, the RRTS
statement of work never uses the phrases “enterprise” or “IT
server” and does not anticipate the contractor performing
ongoing management. See generally AR, Tab 3, RRTS Task Order.
As to whether any TDL work falls within the scope of the RRTS
task order, we note that the TDL makes no reference to the Rapid
Response Project Office (RRPO) and its scope of work does not
refer to ISR work. The TDL seeks support for NAWCAD, not the
RRPO, and is thus broader in scope than the RRTS task order. GSA
contends that the TDL can be used to support offices other than
the RRPO because “the [RRPO] supports other DoD and Non-DOD
agencies, and this [t]ask [o]rder is being used to support these
[unspecified] agencies.” MOL at 8. This argument, however, that
the RRPO work can be used as a foundation upon which to
cantilever broad support for both DoD and non-DoD work misreads
the express terms of the RRTS task order. On this record, we
conclude that the TDL’s instructions to provide services to
offices other than the RRPO, as well as new services for cloud
migration and operations, represent a material departure from
the RRPO ISR services competed among Alliant GWAC contract
holders and awarded to Smartronix.
Furthermore, although the RRTS task order prohibits the use of
TDLs for “assign[ing] new work, direct[ing] a change to the
quality or quantity of supplies and/or services delivered . . .
or chang[ing] any other conditions” of the task order, and
despite GSA’s argument that “the TDL is not a modification to
the Task Order at all,” the GSA and Navy considered the TDL to
encompass new work. AR, Tab 3, RRTS Task Order, at H‑15; MOL at
10, citing AR, Tab 3, RRTS Task Order, at H-14 and H-15. In this
regard, the Navy confirmed to GSA that, “[i]n regards to your
inquiry as to whether this [TDL] work is being provided for on
another [contracting] vehicle, it is not.” AR, Tab 8, Navy Email
to GSA, Jan. 16, 2018, at 2.
The record also shows why the Navy elected to put the cloud
migration and operations work on the RRTS task order.
Smartronix’s RRTS task order was chosen as the vehicle for the
Navy’s migration to a “cloud-based Managed Service Organization”
due to the Navy’s “critical need for a contract vehicle to
accommodate an emergent rapid requirement to stand up a
proof-of-concept demonstration for a cloud-based infrastructure
environment.” AR, Tab 8, Navy Email to GSA, Jan. 11, 2018, at 1.
The Navy concluded that “[t]he symbiotic relationship between
the two hosting environments (on-premise/legacy and cloud) and
the associated migration activities necessitate all work
performed be under one contract.” Id. The Navy justified its
decision to put the new TDL work on the RRTS task order on the
basis that the Alliant GWAC “is IT[‑]focused . . . and of course
the scope of this vehicle covers all things IT and any
corresponding Task Orders and TDLs would follow suit.” Id. at 1.
The Navy’s desire for the work to start quickly under “one
contract” appears to have taken precedence over a critical
analysis by GSA and the Navy as to whether the TDL work was
within the existing scope of the RRTS task order.
The record shows that the TDL’s scope of work is broader than
the RRTS task order in terms of offices served and subject
matter. Based on this record, we conclude that the TDL work is a
material departure from the scope of the RRTS task order and we
sustain the protest. See Western Pilot Serv., supra, at 7-8; see
also Makro Janitorial Servs., Inc., B‑282690, Aug. 18, 1999,
99-2 CPD ¶ 39 at 3 (sustaining protest where contract
modification and task order were beyond the scope of the
underlying IDIQ contract). (Alliant
Solutions, LLC B-415994, B-415994.2: May 14, 2018)
When a protester alleges that the
issuance of a task or delivery order under an IDIQ contract is
beyond the scope of the underlying contract, and thus falls
within CICA’s competition requirement, our Office examines
whether the order is materially different from the original
contract, as reasonably interpreted. DynCorp Int’l LLC, supra;
Floro & Assocs., B‑285451.3, B-285451.4, Oct. 25, 2000, 2000 CPD
¶ 172 at 6. Evidence of a material difference is found by
reviewing the circumstances attending the original procurement;
any changes in the type of work, performance period, and costs
between the contract as awarded and the order as issued; and
whether the original solicitation effectively advised offerors
of the potential for the type of orders issued. Symetrics
Indus., Inc., B‑289606, Apr. 8, 2002, 2002 CPD ¶ 65 at 5.
Additionally, we consider whether the agency itself has
historically procured the task order services under a separate
contract, such that it appears that the agency itself has viewed
the task order services as separable and essentially different
in nature. Data Transformation Corp., B‑274629, Dec. 19, 1996,
97-1 CPD ¶ 10 at 6. The overall inquiry is whether the order is
of a nature which potential offerors reasonably would have
anticipated. DynCorp Int’l, LLC, supra, at 7-8 (sustaining
protest of out-of-scope task order where services required under
a TORP [task order request for proposals] were not reasonably
contemplated when the IDIQ contracts were awarded, even though
there was some overlap in the services requested in the TORP and
those required under the IDIQ contracts).
Here, we find that SEAT [single engine air tanker] flight
services for guaranteed periods of at least 75 days at
predetermined locations are beyond the scope of the protesters’
on-call contracts. At the outset, we recognize that both the
IDIQ contracts and the TORP at issue involve the acquisition of
SEAT flight services to assist BLM in the suppression of
wildland fires. Our analysis on scope issues, however, does not
focus solely on a comparison of the specific services being
procured. In this respect, as explained above, a variety of
factors are pertinent to our Office’s assessment of whether an
order (or solicitation for an order) falls within the scope of
an underlying contract. As discussed below, we agree with the
protesters that the obligations of the contractors under the
on-call contract, as compared to what is contemplated by the
TORP, are materially different. Consequently, the protesters
could not have anticipated a task order competition for
extended, guaranteed periods of performance at the time they
submitted proposals. We sustain the protest on this basis.
The TORP essentially converts the on-call contracts into
exclusive-use procurement vehicles; the agency’s contentions
otherwise are unavailing. The two types of SEAT flight services,
however, rely on fundamentally different service models. As
noted above, the on-call orders provide for SEAT flight services
for emergencies or surge requirements: services are sought when
needed, on a daily basis, for ostensibly shorter periods of
time, with the aircraft transitioning from and mobilizing to
various locations throughout the wildfire season, depending on
the emergent wildfire conditions. See AR, exh. 12,
Representative On-Call Contract, at 6-9; exh. 3, On-Call
Acquisition Plan, at 1, 4. The exclusive-use TORP, on the other
hand, contemplates that aircraft will be prepositioned at one
location by a predetermined date for an extensive period of 75
days or more, reserved exclusively for BLM use during the full
performance period. TORP at 1-2. We agree with the protesters
that the structure of how the SEAT flight services will be
performed under the TORP, which generally mirrors what was
contemplated under the exclusive-use procurement, is notably
different than what was anticipated pursuant to the on-call
contracts.
Similarly, the on-call solicitation and the subsequently awarded
contracts make no reference whatsoever to any long-term,
guaranteed performance period for SEAT flight services. Indeed,
as elaborated further below, the protesters prepared and
submitted their proposals based on their reasonable assumption
that the agency would be conducting separate procurements for
the different types of SEAT flight services, as it had done for
decades. Therefore, we conclude that the TORP’s guaranteed,
extended periods of performance at predetermined locations
represent a material departure from the on-call IDIQ contracts
as competed and awarded. See Ervin & Assocs., Inc., B‑278850,
Mar. 23, 1998, 98-1 CPD ¶ 89 at 8-9 (sustaining protest alleging
out of scope task order even though the ordered accounting
services were “quite similar” to what was required under the
contract, but potential offerors could not have reasonably
anticipated an order for the services at issue).
In addition, the manner in which the agency typically
administers the on-call contracts evidences the uniqueness of
the TORP. While the on-call contracts generally advise that task
orders would be issued on a best-value tradeoff basis,
historically the agency actually procured its on-call needs
under a somewhat unconventional methodology. AR, exh. 12,
Representative On-Call Contract, at 43. Specifically, promptly
after contract award in April 2017, the agency issued two task
orders to the awardees: one covered on-call SEAT flight services
for DOI/BLM and the other for the U.S. Forest Service. See id.;
see also, e.g., AR, exh. 17, WPS Orders and Modifications, Order
No. D17PD00510, at 1-3 (task order for BLM fire suppression);
id., WPS Orders and Mods., Order No. D17PD00511, at 1-2 (task
order for Forest Service fire suppression). Then, as requests
for services--referred to as dispatches--were accepted by the
SEAT contactor, DOI would modify the applicable, previously
issued task order to include the new work. See, e.g., AR, exh.
17, WPS Orders and Mods., Order No. D17PD00510, Modification
Nos. 1-22; COS at 5; WPS Comments at 4. Although permitted to do
so under the on‑call contracts, the agency does not conduct a
best-value task order competition resulting in the issuance of
new task orders for each on-call dispatch. See AR, exh. 3,
On‑Call Acquisition Plan, at 4 (explaining that task orders
under the on‑call contract would not be competed due to the
unpredictable nature of wildland fires).
Instead, in determining which vendor to utilize for a specific,
urgent need for SEAT aircraft, the protesters explain that DOI
generally first focused on the firm with the available aircraft
closest to the fire at the lowest price. See WPS Protest at 3;
ATA Protest at 8, 14; GBAA Protest at 6. If that contractor’s
crew and aircraft were unavailable or the vendor declined the
tasking, the agency would move to the next lowest-priced
contractor until one accepted the work. See ATA Protest at 8. At
that point, a written or verbal resource order was provided and
the previously issued task order was modified to add the effort.
E.g., ATA Protest, exh. D, ATA Sample Resource Orders, at 1-4.
Of significance here, the contracts’ ordering procedures, and
the methodology actually utilized by DOI, did not (1) discuss or
otherwise provide for revised pricing or (2) refer to the
contract rates as ceiling prices for a subsequent task order
competition.
The protesters represent that the dispatch methodology utilized
by the agency during the 2017 wildfire season was consistent
with DOI practice for at least the past 20 years, a point not
contested by the agency. ATA Protest, exh. E, Dec. of ATA
President, ¶ 6. In this respect, and significantly, DOI has not
previously issued a TORP to on-call contractors to solicit new
pricing for extended, guaranteed periods of performance at
predetermined locations, as DOI is attempting to do here. ATA
Comments at 3-4; Evergreen Comments, exh. 1, Dec. of Evergreen
President, ¶ 2. Similarly, neither the terms of the contracts
nor the agency’s action placed the on-call offerors on notice
that their proposed pricing would be treated as ceiling prices
for later-competed exclusive‑use work. See Evergreen Protest at
29; GBAA Protest at 11.
Indeed, given the agency’s prior practice in how dispatches were
determined and administered, we agree with the protesters that
they could not have anticipated at the time they submitted
offers in response to the on-call solicitation that the on-call
contracts would become the vehicles through which the agency
would compete and award the long-term, guaranteed period SEAT
flight services that separately were being solicited under the
exclusive-use solicitation. In our view, the on‑call
solicitation simply did not effectively advise offerors of the
potential for the type of orders contemplated by the TORP. See
Data Transformation Corp., supra, at 6-7 (sustaining protest of
task order as outside the scope of the underlying contract where
services provided under the order were beyond the contemplation
of offerors when the underlying contract was awarded).
In addition, the agency’s own historical procurement record
demonstrates that DOI understood the character of these SEAT
flight services to be distinct. In this respect, we consider it
significant that DOI has for decades procured its SEAT flight
services under two separate contracts: one for extended,
guaranteed periods at specific locations and the other for surge
or emergency on-call needs. Indeed, DOI remained faithful to its
historical preference for separate procurements in 2016, when
the agency prepared two distinct acquisition plans, issued two
solicitations for the different types of SEAT flight services,
and awarded separate contracts for the different services.
That the agency solicited for and awarded contracts under
separate tracks for the different types of SEAT flight services
further supports our view that exclusive-use services under the
on-call contract were beyond the contemplation of offerors when
the on-call contracts were awarded. See Sprint Communications
Co., B-278407.2, Feb. 13, 1998, 98-1 CPD ¶ 60 at 10 (sustaining
protest of an out-of-scope contract modification where the
agency previously solicited for the different services under
separate procurements, demonstrating that the agency itself
viewed the services as separable); Neil R. Gross & Co., Inc.,
B-237434, Feb. 23, 1990, 90-1 CPD ¶ 212 at 3-4 (sustaining
protest of modification of contract where agency itself viewed
the services being added to the contract as separable); see also
Makro Janitorial Servs., Inc., B-282690, Aug. 18, 1999, 99-2 CPD
¶ 39 at 4 (sustaining protest alleging out-of-scope task order
where contemporaneous letters and memorandum from agency
officials regarding the intent and purpose of the underlying
IDIQ contract supported that the ordered services were not
contemplated under the original contract).
In sum, following its decision to cancel the exclusive-use
procurement in April 2017, the agency was left without a
stand-alone contract vehicle to procure SEAT flight services for
guaranteed, extended periods of time, as it anticipated it would
have in place. However, the agency’s attempt to obtain the
exclusive-use flight services under the current on-call
procurement simply does not withstand scrutiny. In this respect,
given the distinguishing characteristics of how the SEAT flight
services are provided under the different models, the pre‑award
perceptions and expectations of the protesters, as well as
taking into account the agency’s decades of procurement
practice, we conclude that the type of SEAT flight services
sought under the TORP are materially different than those
encompassed under the on-call IDIQ contracts. For this reason,
we sustain the protests. (Western
Pilot Service; Aerial Timber Applicators, Inc.; Evergreen Flying
Services, Inc.; G.B. Aerial Applications, Inc. B-415732,
B-415732.2, B-415732.3, B-415732.4: Mar 6, 2018)
Zodiac argues that modification
P00004 improperly relaxed the original solicitation’s
performance requirements, which changed the scope of work
anticipated by the RFP. Zodiac contends that the resulting work
should therefore be subject to competition pursuant to CICA and
Zodiac should have the opportunity to compete under a new
solicitation based on the relaxed requirements. Further, Zodiac
contends that such a change was not anticipated at the time the
original solicitation was issued, and the field of competition
would have changed had the agency relaxed the specifications in
the original solicitation. As detailed below, we conclude that
the record demonstrates that the scope of the original contract
was not substantially changed by modification P00004, the
changes to the contract could reasonably have been anticipated
by competitors for the initial solicitation, and the changes to
the contract would not have had a substantial impact on the
field of competition for the original contract award.
CICA requires “full and open” competition in government
procurements as obtained through the use of competitive
procedures. 10 U.S.C. § 2304(a). Once a contract is awarded,
however, our Office will generally not review modifications to
that contract because such matters are related to contract
administration and are beyond the scope of our bid protest
function. 4 C.F.R. § 21.5(a); Poly-Pacific Techs., Inc.,
B-296029, June 1, 2005, 2005 CPD ¶ 105 at 3. An exception to
this rule arises where a protest alleges that a contract
modification changes the work from the scope of the original
contract, since the work covered by the modification would
otherwise be subject to the statutory requirements for
competition absent a valid determination that the work is
appropriate for procurement on a sole-source basis. Anteon
Corp., B-293523, B-293523.2, Mar. 29, 2004, 2004 CPD ¶ 51 at 4.
Although challenges to the relaxation of contract requirements
are less common than challenges to contract modifications that
enlarge a contract’s scope of work, our Office recognizes that
both fall within the scope of this exception, and we will
consider whether modification of performance requirements result
in work that should be subject to competition. Poly-Pacific
Techs., Inc., supra at 3-4.
In determining whether a modification triggers the competition
requirements in CICA, our Office looks to whether there is a
material difference between the modified contract and the
contract that was originally awarded. Engineering & Prof’l Servs.,
Inc., B-289331, Jan. 28, 2002, 2002 CPD ¶ 24 at 4. To assess
whether a contract is so substantially changed by the
modification that the original and modified contracts are
essentially and materially different, we consider such factors
as the extent of any changes in the type of work, performance
period, and costs between the modification and the original
contract, as well as whether the original solicitation
adequately advised offerors of the potential for the change or
whether the change was the type that reasonably could have been
anticipated, and whether the modification materially changed the
field of competition for the requirement. Marvin J. Perry &
Assocs., B-277684, B-277685, Nov. 4, 1997, 97-2 CPD ¶ 128 at 3.
Zodiac first argues that modification P00004 so substantially
relaxed the contract requirements that the Army will be
procuring “dramatically different boats and motors than the
boats and motors that the Army had solicited.” Protest at 1.
More specifically, the protester alleges that the 10 percent
propelled weight reduction will alter the intended use of the
boats such that in an operational situation, the boats will not
be able to accommodate the payload (motor, fuel, all of the
equipment and number of soldiers it was originally intended to
carry). Id. at 5. Zodiac also argues that the increased working
pressure will cause the boats to take longer to inflate and will
have a corresponding impact on the durability of the fabric of
the boats, affecting safety. Id. Further, Zodiac argues that
increasing the size of the storage bag for the 7-person I-CRC by
three inches will limit the means by which these boats can be
transported and deployed in platforms with size restrictions,
and elimination of the airborne transportability requirement in
its entirety further eliminates the Army’s ability to utilize
the boat in conjunction with airborne operations. Id. at 5-6.
The Army responds that modification P00004, executed almost two
years into contract performance, made minor changes to the
technical specifications that are within the scope of the
contract, and contests the protester’s allegations that the
changes will have any impact on mission performance. Combined
Contracting Officer’s Statement of Facts/Memorandum of Law
(COS/MOL) at 9-11. As explained by the Army, although the motors
are now required to accommodate 10 percent less weight when
reaching 16 knots during sea state 1 (calm water) within two
minutes, the payload weight requirements for the boats
themselves remain unchanged. Id. at 13-14. In other words, the
deliverables will still function as 7-person I-CRCs and
15-person I-CACs and the agency will not be forced to leave
behind anyone or anything as a result of the decreased propelled
weight requirement. AR, Tab 8, Decl. from Director, Requirements
Determination Division, Army Maneuver Support Center of
Excellence, ¶ 2.
Further, the Army states that the increase in working pressure
will not impact the safety of the boats because testing has
already demonstrated (during a 300 percent overpressure/psi
test) that the fabric of the boats can withstand the increased
pressure. COS/MOL at 16; AR, Tab 8, Decl. from Director,
Requirements Determination Division, Army Maneuver Support
Center of Excellence, ¶ 3. Additionally, the Army notes that
modification P00004 did not change the required inflation time
for the boats (15 minutes for the 7-person I-CRC and 25 minutes
for the 15-person I-CAC) and any increase in inflation time
caused by the increased working pressure is insignificant
because it did not exceed the Army’s requirements for inflation
time. COS/MOL at 16. Finally, the Army states that a larger
storage bag and elimination of airborne transportability
requirements for the 7-person I-CRC will not will impact how the
boats can be transported or what platforms they can be deployed
from, and will not prevent the Army from performing airborne
operations with the boats. Id. at 17-18; AR, Tab 8, Decl. from
Director, Requirements Determination Division, Army Maneuver
Support Center of Excellence, ¶¶ 4-5.
In our view, the agency did not improperly relax the
specifications because the original nature and purpose of the
solicitation and contract has not been changed by modification
P00004. The capabilities and missions of the 7-person I-CRC and
15-person I-CAC set forth in the solicitation and contract
remain the same after the modification to the contract. The
changes to the purchase descriptions of the boats and motors are
relatively minor when viewed against the entirety of all of the
contract specifications and performance requirements. Defense
Systems Group; Warren Pumps, Inc.; Dresser Indus., Inc.,
B-240295 et al., 1990 U.S. Comp. Gen. LEXIS 1182, Nov. 6, 1990
(protest denied where modifications involved substantial cost
and affect first article test requirements, delivery schedule,
and performance specification but did not change the nature and
purpose of the original contract).
Moreover, modification P00004 did not change the performance
period of the contract. The contract remains a five-year
contract as awarded in 2013, and will expire on September 24,
2018. AR, Tab 3, ADS Contract W56HZV-13-D-0151, at 3. In
addition, the downward equitable adjustment extending the option
year ordering prices to the following year’s prices for the
remaining years of the contract is relatively small, and is a
function of the contract’s first article approval clause
operating precisely as the contract intended. Id. at 72-73; see
also RFP at 74. On this record, we agree with the Army that
modification P00004 did not materially change the contract. See
Emergent BioSolutions, Inc., B-402576, June 8, 2010, 2010 CPD ¶
136 at 10-11 (modification to contract did not change the
original objectives of the contract given the broadly defined
developmental nature of the requirement for an anthrax vaccine).
Zodiac next argues that the original solicitation did not
adequately advise offerors of the potential for the change. We
disagree and find that the changes made by modification P00004
are changes to the requirements that competitors could have
reasonably anticipated. As discussed, the RFP and the resulting
contract included the requirement that the boats and motors pass
first article testing. Under the terms of the first article
approval clause, the contractor is afforded an opportunity to
“make any necessary changes, modifications, or repairs to the
first article or select another first article for testing” in
the event it did not receive first article approval. RFP at 74.
The inclusion of the first article test requirements in the RFP
itself indicates the potential for changes, such as those made
by modification P00004, to be made to the technical
specifications of the boats and motors. See Engineering & Prof’l
Servs., Inc., supra at 4-5 (modification to incorporate
technological advances in ruggedized handheld computers was
within scope of original contract where RFP contemplated
advances could be incorporated into the requirement as they
became available).
Zodiac also contends that the modification would have materially
changed the field of competition had the agency relaxed the
specifications in the original solicitation. However, Zodiac has
not demonstrated that the changes made by modification P00004
would have materially changed the field of competition. Zodiac
has not alleged that other or different competitors would have
participated in the procurement. Instead, Zodiac repeatedly
states that it would have proposed different, less expensive
boats than the boats it proposed under the original
solicitation. Protest at 2, 4, and 6-7; Comments at 1 and 3.
Zodiac’s proffer of how it would have altered its original offer
in response to the changed requirements does not show that the
field of competition would have otherwise changed.
Finally, Zodiac argues that its boats met the original
solicitation requirements, since it was found technically
acceptable, and therefore it has been prejudiced by the agency’s
actions. However, Zodiac has failed to establish that it was
prejudiced by the changes made to the specifications by
modification P00004. Competitive prejudice is an essential
element of a viable protest, and where the protester fails to
demonstrate prejudice, our Office will not sustain a protest.
Emergent BioSolutions, Inc., supra at 14. Here, the modification
in requirements had no impact on Zodiac’s ability to compete for
the contract originally. More importantly, Zodiac has not even
alleged that the boats it would have proposed in response to the
modified requirements, even if lower-priced than the offer it
originally submitted in response to the RFP, would have been
lower than those proposed by ADS in this lowest-price
technically acceptable procurement, such that it would have been
awarded the contract. See Armed Forces Hospitality, LLC,
B-298978.2, B-298978.3, Oct. 1, 2009, 2009 CPD ¶ 192 at 9-10.
Accordingly, there is no basis for finding that the modification
in the specifications for the boats and motors and in the
overall performance requirements resulted in any prejudice to
Zodiac. (Zodiac of North
America, Inc. B-414260: Mar 28, 2017)
Chase challenges the modifications
the DLA made to PO-1464 and PO-1620, which waived some or all
[first article test] FAT requirements. The protester primarily
argues that the modifications were unreasonable because they
changed the fundamental nature of the purchase orders. As a
result, Chase contends that the modification was outside the
scope of the orders, and should have required a new competition.
(deleted sentences)
With respect to the scope
argument, the Competition in Contract Act generally requires
“full and open competition” in government procurements as
obtained through the use of competitive procedures. 41 U.S.C. §
3301. Our Office generally will not review modifications to
contracts, because such matters are related to contract
administration and are beyond the scope of GAO’s bid protest
function. 4 C.F.R. § 21.5(a); MCI Telecomms. Corp., B‑276659.2,
Sept. 29, 1997, 97-2 CPD ¶ 90 at 7. An exception to our rule
about reviewing modifications to a contract is where it is
alleged that the modification is outside the scope of the
contract originally awarded. Id. This is because the work
covered by the modification would otherwise be subject to the
statutory requirement for competition, absent a valid
determination that the work is appropriate for procurement on a
sole-source basis. Id.
In determining whether a modification is beyond the scope of an
underlying contract (or in this case a purchase order), our
Office considers whether there is a material difference between
the modification and the contract. DynCorp Int’l LLC, B‑402349,
Mar. 15, 2010, 2010 CPD ¶ 59 at 6; MCI Telecomms. Corp., supra.
Evidence of a material difference is found by reviewing the
circumstances attending the procurement that originally was
conducted, examining any changes in the type of work,
performance period, or costs between the contract as awarded and
as modified, and considering whether the original solicitation
adequately advised offerors of the potential for the type of
work contemplated by the modification. See Anteon Corp.,
B-293523, B-293523.2, Mar. 29, 2004, 2004 CPD ¶ 51 at 5. The
overall inquiry is whether the modification is of a nature that
potential offerors reasonably would have anticipated competing
for the goods or services being acquired through issuance of the
modification. Id.
In its protest, Chase argues that the agency’s waiver of FAT
will result in fundamentally different products from those that
pass FAT without waivers. In this regard, the protester contends
that the FAT requirements will influence decisions about the
materials, construction, and design of the products. In
addition, Chase contends that even if the agency could waive
FAT, Flexfab is not eligible for the waiver.
Contrary to Chase’s arguments, we find that decision to waive
FAT under PO-1464 and PO-1620 did not materially change the
orders because the waiver of test requirements does not modify
the underlying substantive requirements for the air duct hose
assemblies. AR (B-411528.2), Tab 13, Modification P00001, at 2;
AR (B‑411529.2), Tab 17, Modification P00002, at 2. In this
regard, every air duct hose assembly supplied by Flexfab must
still meet the product requirements imposed under the original
purchase orders, irrespective of the FAT waivers. AR (B‑411528),
Tab 3, PO-1464, at 3; AR (B-411529), Tab 7, PO‑1620, at 3. As
the DLA explains, “waiver of FAT does not change any of the
requirements under th[e] specification” since “FAT is used to
ensure that the contractor has the ability to make an item that
meets the contractual requirements” and even “[i]f FAT is
waived, the contractual requirements still have to be met.” AR
(B-411528.2), Tab 13, Quality Assurance Specialist Memorandum,
at 1; AR (B‑411529.2), Tab 14, Quality Assurance Specialist
Memorandum, at 1.
Since we conclude that waiving the testing requirement does not
mean that the agency will be ordering a fundamentally different
product, Chase’s assertions fail to demonstrate that the
modification was beyond the scope of the order.
We also find misplaced the protester’s assertion that Flexfab
was not eligible to obtain a waiver. Chase asserts that the
agency’s waiver of FAT was improper because Flexfab’s air duct
has never passed FAT. As previously discussed, PO‑1464 and
PO-1620 each contain FAR clause 52.209-3. FAR clause 52.209-3
does not make the agency’s decision to waive FAT contingent on
whether a vendor previously passed the FAT being waived, but
rather contemplates that an agency may waive FAT where supplies
identical or similar to those called for have been previously
furnished by the vendor and have been accepted by the
government. See FAR clause 52.209-3(h).
Here, the agency based its waiver under PO-1464 on Flexfab
previously furnishing these air duct hose assemblies under prior
government contracts, which were accepted by the government
within three years of when PO-1464 was issued, and because the
tests that were waived were not impacted by the exception to the
wire specification. AR (B-411528.2), Tab 23, Engineer’s
Affidavit, at 1. The record also demonstrates that the DLA
waived all FAT requirements under PO‑1620 because Flexfab
received FAT approval under PO-1464. AR (B-411529.2), Tab 17,
Modification P00002, at 2. Based on this record, we have no
basis to find that Flexfab’s air duct hose assemblies were not
eligible for FAT waiver.
In sum, since we conclude that the modifications to waive FAT
were not outside the scope of the underlying purchase orders, we
view the modifications at issue as purely a matter of contract
administration within the discretion of the agency.
(Chase Supply, Inc. B-411528.2,
B-411529.2: Dec 7, 2015 (pdf)
Onix maintains that the modification of the En Pointe delivery
order is outside the scope of the original requirements that the
agency was purchasing. For the reasons discussed below, we agree
with Onix.
(sections deleted)
Onix alleges that the agency’s
modification of the En Pointe delivery order amounts to an
impermissible, out-of-scope, sole-source modification. Onix
maintains that the original En Pointe delivery order was for the
provision of software update services (along with technical
support) for the Peace Corps’ existing software products
installed on the Peace Corps’ IT enterprise system. The
protester argues that the acquisition of an [e-mail as a
service] EaaS product--a cloud based service rather than
maintenance/update services for existing, installed,
software--is fundamentally different from what the agency
originally had acquired under the En Pointe delivery order. Onix
therefore argues that the agency is either required to conduct a
competition for its EaaS requirement, or to execute a
sole-source justification for acquiring its EaaS product from En
Pointe, or any other authorized Microsoft reseller.
The agency argues that its modification is within the scope of
En Point’s original delivery order, and therefore, proper. The
Peace Corps principally argues that the modification is within
scope because the delivery order contemplated the acquisition of
cloud based services, and that acquisition of an EaaS product is
merely the next logical step in updating the agency’s existing
computing environment. The agency points out that the delivery
order included a table entitled “future pricing.” AR, exh. 16,
En Pointe Delivery Order Future Pricing Chart. According to the
agency, this table was included in the En Pointe delivery order
to “lock in” prices for future products that the Peace Corps
might want to purchase throughout the performance period of the
delivery order. Contracting Officer’s Statement of Facts at 4.
The agency also identifies various sections of the delivery
order’s statement of work that it maintains allow the agency to
add products to the delivery order throughout the period of
performance. Id. at 4-5.
The Competition in Contracting Act generally requires “full and
open competition” in government procurements as obtained through
the use of competitive procedures. 41 U.S.C. § 3301. Our Office
generally will not review modifications to contracts, because
such matters are related to contract administration and are
beyond the scope of GAO’s bid protest function. 4 C.F.R. §
21.5(a); MCI Telecomms. Corp., B‑276659.2, Sept. 29, 1997, 97-2
CPD ¶ 90 at 7. An exception to our rule about reviewing
modifications to a contract is where it is alleged that the
modification is outside the scope of the contract originally
awarded. Id. This is because the work covered by the
modification would otherwise be subject to the statutory
requirement for competition, absent a valid determination that
the work is appropriate for procurement on a sole source basis.
Id.
In determining whether a
modification is outside the scope of an underlying contract (or
in this case, a delivery order), our Office considers whether
there is a material difference between the modification and the
contract. DynCorp Int’l LLC, B-402349, Mar. 15, 2010, 2010 CPD ¶
59 at 6; MCI Telecomms. Corp., supra. Evidence of a material
difference is found by reviewing the circumstances attending the
procurement that originally was conducted, examining any changes
in the type of work, performance period, or costs between the
contract as awarded and as modified, and considering whether the
original solicitation adequately advised offerors of the
potential for the type of work contemplated by the modification.
See Anteon Corp., B-293523, B-293523.2, Mar. 29, 2004, 2004 CPD
¶ 51 at 5. The overall inquiry is whether the modification is of
a nature that potential offerors reasonably would have
anticipated competing for the goods or services being acquired
through issuance of the modification. Id.
We agree with Onix that the modification of the En Pointe
delivery order is an improper, out-of-scope, sole-source
modification. As an initial matter, we note that there is a
fundamental flaw in the agency’s logic. As noted, the original
competition for the En Pointe delivery order was limited to
authorized Microsoft resellers because the agency concluded that
only Microsoft products would meet its requirements. The
agency’s subsequent actions in connection with acquiring an EaaS
product--notably its pilot program that tested the Google EaaS
product, and its issuance of an RFI to sources other than
Microsoft authorized resellers[4]--explicitly recognize that
there are firms other than Microsoft authorized resellers, and
products other than Microsoft’s EaaS product, that are available
to meet the agency’s requirement.
Since the agency essentially concedes by its actions that there
are EaaS products that potentially can meet its requirements,
and since the competition for the En Pointe delivery order was
confined to firms capable of providing Microsoft products and
services, it necessarily follows that firms--such as Onix--could
not reasonably have anticipated that the agency would acquire an
EaaS product using the originally-competed delivery order. For
this reason alone, we conclude that the modification is outside
the scope of the original delivery order.
We also agree with the protester
that, substantively, neither the original competition for the
delivery order, nor the delivery order as issued, ever
contemplated the acquisition of a cloud-based EaaS product or
service. Specifically, a review of the RFQ and delivery order
demonstrate that the agency was acquiring a renewal of its
existing enterprise agreement with Microsoft for a discrete list
of software products already owned by the Peace Corps. The
statement of work in the RFQ (as well as the En Pointe delivery
order) provides, in its entirety, as follows:
The Peace Corps requires renewal
of its Microsoft EA [enterprise agreement] which provides
software and maintenance services that cover the following:
• Licensing for required Microsoft
software products authorized for use by Peace Corps;
• Software Assurance for authorized/licensed products, as
appropriate;[5]
• Media sets, as appropriate;
• Access to Technical Support Assistance services to provide
remote or onsite support to Peace Corps;
• Access to Problem Resolution services;
• Access to Technical Training on Microsoft products;
• Technical Account Manager services to track assets and
utilization of the technical support resources on the contract;
• Authorization for home use of Microsoft products for Peace
Corps staff based on the “Home Use Program.”
The Peace Corps requires supply of its existing inventory of
Microsoft licensed software under this Enterprise Agreement,
according to the quantities required, as detailed in Appendix A.
In addition, the Peace Corps requires technical support hours,
problem resolution hours, and days of technical training, as
detailed in Appendix B.
AR, exh. 3, Delivery Order RFQ, at
2 (emphasis supplied). Simply stated, there is nothing in this
statement of work that contemplates the provision of an entirely
new product or service, such as an EaaS product.
Based on our review, it is clear that the original delivery
order did not include any cloud based services such as the EaaS
product being acquired by the Peace Corps. Rather, it was for
maintenance and upgrade of the agency’s existing inventory of
software products already installed in the agency’s IT
environment.
As a final matter, we note that the agency appears to suggest
that the original RFQ (and, correspondingly, the En Pointe
delivery order) essentially contemplated the issuance of an
indefinite-delivery, indefinite-quantity (IDIQ) type delivery
order under which the agency may purchase, without limitation,
new software licenses not already owned by the Peace Corps.
Contracting Officer’s Statement at 4-5. We disagree.
The terms of the RFQ (as well as the En Pointe delivery order)
are expressly limited to a discrete list of software
products--identified by part number, and specified by
quantity--already owned by the Peace Corps. AR, exh. 3, RFQ at
appendix A; exh. 2, En Pointe Delivery Order, at 5-9. There is
nothing in either the RFQ or the delivery order that suggests
that the agency intended to (or did, in fact) issue an IDIQ-type
delivery order. In fact, the RFQ specifically contemplates the
award of a firm-fixed-price delivery order, AR, exh. 3, RFQ at
1. In addition, firms were required to provide pricing in two
line-item tables, appendix A (listing the software products and
quantities owned by the agency) and appendix B (listing the
technical support services required and the number of hours to
be provided). Firms were required to provide lump-sum prices for
each line item. The record therefore shows, contrary to the
agency’s suggestion, that the En Pointe delivery order was a
firm-fixed-price instrument to acquire a discrete, enumerated,
quantity of services.
In sum, we conclude that the modification to the En Pointe
delivery order is an improper, out-of-scope, sole-source
modification, for which the agency never conducted a
competition, and for which the agency has not prepared the
necessary justification and approval. We therefore sustain
Onix’s protest.
RECOMMENDATION
We recommend that the agency either meet its requirement for an
EaaS product through the use of full and open competitive
procedures, or execute the necessary justification and approval
to acquire the EaaS product through other than full and open
competitive procedures. Should the agency decide to meet its
requirements using full and open competition (or some form of
limited competition), we recommend that the agency terminate the
modification issued to En Pointe’s delivery order for the
convenience of the government, and make award for its
requirement to the firm the agency determines can best meet its
requirements. Finally, we recommend that the agency reimburse
Onix the costs associated with filing and pursuing its protest,
including reasonable attorneys’ fees. (Onix
Networking Corporation B-411841: Nov 9, 20150 (pdf)
In determining whether a modification triggers the competition
requirements under CICA, we look to whether there is a material
difference between the modified contract and the contract that
was originally awarded. Engineering & Prof’l Servs., B-289331,
Jan. 28, 2002, 2002 CPD ¶ 24 at 4; see AT&T Commc’ns, Inc. v.
Wiltel, Inc., 1 F.3d 1201, 1205 (Fed. Cir. 1993). Evidence of a
material difference between the modification and the original
contract is found by examining changes in the type of work,
costs, and performance period between the contract as awarded
and as modified. Overseas Lease Group, Inc., B-402111, Jan. 19,
2010, 2010 CPD ¶ 34 at 3. We also consider whether the
solicitation for the original contract adequately advised
offerors of the potential for the type of changes found in the
modification, and thus whether the modification would have
materially changed the field of competition. Atlantic Coast
Contracting, Inc., B-288969.2, June 21, 2002, 2002 CPD ¶ 104 at
4.
Here, Cornishe argues that modification No. 39 is outside the
scope of the underlying LSF contract because it requires
performance of aircraft overhauls, which the protester argues
are not within the scope of the LSF contract. The protester also
argues that performance of requirements outside the Continental
United States is not within the scope of SES’s LSF contract.
The Army argues that the SOW for modification No. 39 is
expressly within the scope of the LSF contract. We agree. As
noted above, the SOW for the LSF contract specifically addresses
aircraft repairs, overhauls and related logistics support. It
does not limit the type of aircraft for performance, and instead
broadly addresses the following categories of work:
(1) Repair, update, integrate, overhaul or modify various items
of Communications-Electronics (C-E), navigational fire control,
aircraft and . . . associated hardware.
(2) Repair, update, overhaul or modify end items (example:
aircraft, shelters, tooling) that contain, use or transport
other Class VII (Major End Items), e.g., mobile communication or
aircraft systems as required.
* * * * *
(6) Perform modification and repair on designated aircraft and
on components at locations in and outside of the continental
United States. This includes aircraft engine overhaul, aircraft
refurbishment, transmission overhaul, etc.
AR, Tab E, Contract No. 0130 SOW, at 1-2.
The record here shows that overhauls were clearly within the
scope of the LSF contract. The record further shows that the SOW
clearly anticipated performance of work “at locations in and
outside of the continental United States.” Id. at 2. For this
reason, we find no merit to the protester’s argument that the
requirements of modification 39 are outside the scope of the LSF
contract.
The protester also argues that the requirements of modification
39 are outside the scope of work authorized by the November 2011
J&A, in that the J&A did not mention overhauls of Mi-17
helicopters. In this regard, the protester notes that the
November 2011 J&A stated that the agency anticipated ordering
cockpit modifications for Mi-17 helicopters, but not overhauls.
The protester also contends that the 2011 J&A authorized work in
support of the Pakistan government, but not the Afghanistan
government.
As the Army contends, however, the purpose of the J&As was to
increase the ceiling value of the LSF contract, and while each
J&A cited estimates of work to be performed, the work estimates
did not modify the scope of the LSF or otherwise restrict the
scope of work under the LSF contract. We agree, and conclude
that the LSF contract, rather than the 2011 J&A, is the relevant
document for determining whether modification No. 39 was an
in-scope modification. On this record, we deny Cornishe’s
argument that modification No. 39 is outside the scope of the
LSF contract. (Cornische
Aviation & Maintenance, LTD, B-405013.4, Jan 25, 2013)
(pdf)
WorldWide
challenges the modification of MEP's contract to increase the
contract ceiling by $679 million, arguing that the modification
was outside the scope of MEP's underlying contract and therefore
constitutes an improper noncompetitive award in contravention of
the competition requirements established by CICA, specifically,
10 U.S.C. sect. 2304(f)(1)(C) (2006). To the extent the agency
has justified its actions based on a finding that only MEP can
meet the agency's interim need for linguists--a conclusion
disputed by the protester--WorldWide asserts that the
noncompetitive extension of MEP's existing contract was
attributable to a lack of advance procurement planning, which is
also precluded by CICA. 10 U.S.C. sect. 2304(f)(5).
CICA requires that an agency obtain full and open competition in
its procurements through the use of competitive procedures. 10
U.S.C. sect. 2304(a)(1)(A). Exceptions are provided under CICA,
however, where (among other specified exceptions) there is only
one responsible source able to meet the agency's requirements,
10 U.S.C. sect. 2304(c)(1). CICA also provides that
noncompetitive procedures may not be used where agency
contracting officials failed to perform advance planning. 10
U.S.C. sect. 2304(f)(5); HEROS, Inc., B-292043, June 9, 2003,
2003 CPD para. 111 at 6; New Breed Leasing Corp., B-274201,
B-274202, Nov. 26, 1996, 96-2 CPD para. 202 at 6. Our Office has
recognized that the requirement for advance planning does not
mean that such planning must be completely error-free, but, as
with all actions taken by an agency, the advance planning
required under CICA must be reasonable. Barnes Aerospace Group,
B-298864, B-298864.2, Dec. 26, 2006, 2006 CPD para. 204 at 4-5.
Here, WorldWide is challenging the modification of MEP's
existing contract, not the award of a sole-source contract per
se. As a general rule, our Office will not consider protests
against contract modifications, since they involve matters of
contract administration and are beyond the scope of our bid
protest function. See 4 C.F.R. sect. 21.5(a) (2010); DOR
Biodefense, Inc.; Emergent BioSolutions, B-296358.3, B-296358.4,
Jan. 31, 2006, 2006 CPD para. 35 at 6. An exception to this
general rule is where a protester alleges that a modification is
beyond the scope of the original contract, as WorldWide argues
in this case, since, absent a valid sole‑source justification,
the work covered by the modification would be subject to the
competition requirements established under CICA. Engineering &
Prof'l Servs., Inc., B-289331, Jan. 28, 2002, 2002 CPD para. 24
at 3.
In determining whether a modification triggers CICA's
competition requirements, we look to whether there is a material
difference between the modified contract and the contract that
was originally awarded. Engineering & Prof'l Servs, Inc., supra,
at 4. Evidence of a material difference between the modification
and the original contract is found by examining changes in the
type of work, performance period, and costs between the contract
as awarded and as modified. Atlantic Coast Contracting, Inc.,
B-288969.2, June 21, 2002, 2002 CPD para. 104 at 4.
The agency and the intervenor argue that modifying MEP's
contract to increase the contract ceiling by $679 million is not
outside the scope of MEP's underlying contract. In this regard,
they principally assert that the increase in the ceiling level
does not change the type of work required under the contract and
offerors could have reasonably anticipated a modification to
increase the contract ceiling. WorldWide maintains that the
magnitude of the increase in the dollar ceiling implicitly
reflects a change in the nature of the agency's original
requirement and the basis of the original competition, and
therefore renders the modification outside the scope of the
original award.
As discussed below, we do not need to decide the question of
whether the modification is within the scope of MEP's contract
because, even assuming that it was not, the agency properly
supported the modification with a reasonably based J&A under 10
U.S.C. sect. 2304(c)(1).
In challenging the agency's decision to increase the ceiling
under MEP's linguist contract, WorldWide does not in any way
contest the vital role that the linguists play in support of the
U.S. mission in Afghanistan. Rather, WorldWide argues that the
need for a noncompetitive modification was the result of the
agency's failure to adequately plan for the award of a
competitive contract. According to WorldWide, it should have
been "obvious" to the agency by April 2009 that there would be a
need for additional linguists as of that time given that the
military was requesting additional troops and support services
for the efforts in Afghanistan, yet the agency waited until 2010
to take any action to ensure that it could meet the increased
need for linguists. Protester's Opposition to Dismissal Request,
June 8, 2010, at 2, 9; Protester's Comments, supra, at 2.
WorldWide also suggests that the agency's planning for the award
of a competitive contract was unreasonable given the length of
time scheduled for the procurement, approximately 22 months.
According to WorldWide this time period should have been
significantly reduced and can still be shortened further so as
to minimize the period needed for the noncompetitive
modification.
The record reflects that the agency initiated the process of
planning for a competitive award in May 2009. When the need for
greater numbers of linguists became apparent in August 2009, and
was further defined as a consequence of the surge decision in
December 2009, the agency took steps to set an expedited
schedule for the award of a competitive linguist contract--a
process requiring numerous steps, reviews, and milestones.
While WorldWide believes that this period of time could be
greatly compressed, the record does not support its opinion in
this regard. As discussed in the May 3 J&A, the linguist
services are vitally important to the U.S. war effort in
Afghanistan. Further, the anticipated size of the award at issue
is very large; it will be a contract with a value likely in
excess of $1 billion, involving performance by thousands of
contractor personnel at remote locations throughout Afghanistan.
In light of the complexity, scope, and criticality of the
requirements, we have no basis to conclude that the procurement
planning for the competitive linguist award reflects
unreasonable delay or a lack of diligence by the agency. On the
contrary, the record shows that, beginning in May 2009, the
agency has engaged in appropriately deliberate efforts to ensure
a competitive award of a new long-term contract by March 2011.
As noted above, an agency's procurement planning need not be
error-free, it need only be reasonable. Based on the record in
this case, we think that WorldWide's challenge to the agency's
procurement planning efforts are without merit.
We next turn to WorldWide's assertion that the agency's decision
not to compete the interim linguist requirement was
unreasonable. WorldWide challenges the agency's conclusion that
MEP was the only source capable of providing the required
linguist services, arguing that INSCOM's determination was based
on incomplete and flawed market research regarding the
capabilities of potential offerors--WorldWide declares that it
can meet the Army's urgent short-term needs without any
degradation of service. In representing that it is capable of
meeting the agency's requirements, WorldWide relies on its own
linguist assets, as well as those of its potential "teammates"
which are currently performing linguist contracts for U.S. and
coalition forces in Afghanistan and Iraq. Protester's Opposition
to Dismissal Request, supra, at 4.
WorldWide's challenge to the agency's decision is flawed in
several respects. As an initial matter, WorldWide does not
address the agency's determination that even if there were firms
capable of meeting the linguist requirements, conducting a
limited competition among such firms was not a practicable
alternative. As noted above, the J&A expressly found that
conducting a limited competition was not a viable option given
that the award would be for a very short duration (approximately
3 to 5 months), coupled with the fact that conducting such a
competition would undermine the agency's ability to timely award
the long-term linguist contract, and would introduce multiple
transitions during a period of high stress for U.S. forces in
Afghanistan.
The agency has set forth in its J&A, and in its response to the
protest, the challenges associated with awarding and
transitioning a contract of this importance to the military
mission and magnitude--one involving thousands of contractor
personnel operating at over 200 locations throughout
Afghanistan. In this regard, the agency reasonably questioned
the advisability of awarding, and transitioning to, an interim
contract of this size, based on limited competition, only to
have it displaced shortly thereafter by a long-term competitive
contract requiring the same type of large-scale contractor
transition; as indicated by the J&A, the agency reasonably was
concerned that multiple large-scale transitions for these vital
services would increase risk and disruption to U.S. military
capabilities and thereby endanger the military mission and the
lives of U.S. troops. See, e.g., Vertol Sys. Co., Inc.,
B-293644.6 et al., July 29, 2004, 2004 CPD para. 146 at 3 (where
requirement relates to national defense, agency has the
discretion to seek not just reasonable results, but the highest
possible effectiveness). Given this context, we find the agency
reasonably weighed and balanced the impact of conducting a
limited competition against the relatively short duration of any
resulting award, and reasonably concluded that conducting such a
competition was not a viable option. Under these circumstances,
the agency had no alternative other than modifying MEP's
contract so that it could continue providing linguist services
until the agency is able to award the follow-on competitive
contract.
We likewise are not persuaded by WorldWide's challenges to the
market research underlying the J&A prepared by INSCOM. The
record reflects that the agency considered the capabilities of
numerous firms, to include WorldWide, and solicited specific
information regarding the capabilities of GLS, which apparently
is the largest provider of linguist services to the military and
was then operating in Iraq. The agency concluded that none of
the firms, including GLS, was a viable alternative to having MEP
continue providing linguists in Afghanistan. In reaching this
conclusion, the agency reasonably gave paramount consideration
to military operations in Afghanistan, noting that they were at
a critical juncture given the implementation of the U.S. troop
surge. As explained in the J&A, the surge presents a period of
logistical strain and "high operational stress." AR, Tab 6, J&A,
May 3, 2010, at 6. Given the underlying military considerations,
the agency did not believe any contractor could transition the
contract--which, as explained in the J&A and discussed above,
presents unique and difficult challenges, entails providing more
than 6,000+ linguists at 200 locations throughout Afghanistan,
during the surge--without an adverse impact on U.S. forces and
potentially compromising the military's ability to execute its
mission in Afghanistan.
WorldWide maintains that the agency's transition concerns are
overstated, arguing that any transition would have limited
impact since its "team" has a presence in Afghanistan, and the
vast majority of linguist personnel would simply transition to
the new vendor. In this regard, WorldWide cites the J&A, which
states that experience shows that approximately 90 percent of
the incumbent's workforce transitions to the new contractor, and
notes that the agency transitioned GLS's Iraq contract, which
was actually larger, without any difficulty. The record reflects
that the agency considered each of these points, yet concluded
that continuing to obtain linguist services from MEP was the
only viable option given the state of military operations in
Afghanistan.
First, it is important to recognize that this contract involves
more than simply providing a particular number of qualified
linguists. It requires transporting, billeting, feeding, and
paying these individuals at over 200 locations throughout
Afghanistan. While the transition thus must address these
requirements as well, WorldWide focuses almost exclusively on
transitioning the linguist assets themselves. In any event, to
the extent WorldWide complains that the agency did not give
sufficient consideration to its own capabilities, the record
shows that the agency had no basis to believe that WorldWide was
capable of performing the large-scale requirement at issue,
particularly since WorldWide did not provide the agency with any
information regarding its capabilities in response to the RFI
and WorldWide has never performed a contract of this magnitude
in the past. In this regard, the agency expressly concluded that
WorldWide was not a viable source for the current requirements
in view of the small size of its prior Afghanistan linguist
contract, which involved providing approximately 100 linguists,
all of whom had transitioned to MEP's contract when it was
concluded in March 2010. Nor should the agency be faulted for
its failure to have considered WorldWide's "team," given that
the agency did not know, or have reason to know, that any such
team existed. Under these circumstances, the agency did not act
unreasonably in not contacting WorldWide or further
investigating its capabilities or interest. See Chicago Dryer
Co., B-401888, Dec. 8, 2009, 2009 CPD para. 253 at 2 (denying
challenge to an agency's market research in support of a
sole-source award and explaining that an agency is not required
to contact all potential sources when conducting market research
regarding the feasibility of sole-source procurement).
Further, the agency specifically considered the difficulty
associated with transitioning the incumbent workforce, and
expressly noted that a 90 percent transition rate for the
incumbent's linguists would result in an immediate loss of 500
linguists, thereby increasing operational risk at a time of
significant stress on the military due to the surge. AR, Tab 6,
J&A, May 3, 2010, at 4. Moreover, WorldWide's reference to the
alleged ease of the transition under GLS's Iraq linguist
contract is misplaced since the J&A describes the greater
challenges posed by the requirement for linguist services in
Afghanistan. As noted above, the J&A explains that establishing,
managing, and sustaining linguist support services in
Afghanistan is particularly difficult due to the country's
widely dispersed population, which can be located in remote and
isolated regions; literacy problems within the population; the
fact that there are dozens of languages and dialects, and few
locals capable of acting as linguists; and the fact that the
national infrastructure and central government remain limited,
and the economy is rudimentary. Id. Given this record, we have
no basis to question the reasonableness of agency's actions.
In sum, we find that the J&A supports the reasonableness of the
agency's decision to increase the ceiling under MEP's contract,
thereby allowing MEP to continue providing vitally important
linguist services to U.S. forces in Afghanistan, until the time
when the agency can award a competitive contract for these
services. (WorldWide Language
Resources, Inc., B-299315.7; B-299315.8, August 12, 2010)
(pdf)
In determining
whether a modification triggers the competition requirements
under CICA, we look to whether there is a material difference
between the modified contract and the contract that was
originally awarded. Engineering & Prof'l Servs., supra, at 4;
AT&T Commc'ns, Inc. v. Wiltel, Inc., 1 F.3d 1201, 1205 (Fed.
Cir. 1993). Evidence of a material difference between the
modification and the original contract is found by examining
changes in the type of work, costs, and performance period
between the contract as awarded and as modified. Overseas Lease
Group, Inc.,
B-402111, Jan. 19, 2010, 2010 CPD para. 34 at 3; Atlantic Coast
Contracting, Inc.,
B-288969.2, June 21, 2002, 2002 CPD para. 104 at 4. We also
consider whether the solicitation for the original contract
adequately advised offerors of the potential for the type of
changes found in the modification, and thus whether the
modification would have materially changed the field of
competition. See DOR Biodefense, Inc.; Emergent BioSolutions,
supra; Atlantic Coast Contracting, Inc., supra.
As detailed below, we conclude that the record demonstrates that
the scope of the original contract was not substantially changed
by modification 0018, and thus the changes to the contract would
not have had a substantial impact on the field of competition
for the original contract award.
The RFP and resulting Phase 2 contract called for a research and
development (R&D) effort. Unlike contracts for supplies and
services, most R&D contracts are directed toward objectives for
which the work or methods cannot be precisely described in
advance; it is difficult to judge the probabilities of success
or required effort for technical approaches, some of which offer
little or no early assurance of full success. FAR sect. 35.002.
Our decisions have recognized that additional latitude for
modifying a contract may exist where the contract is for R&D
work, noting that the scope of such contracts is often flexible
because of unanticipated changes due to the lack of
definitiveness of the government's requirements. DOR Biodefense,
Inc.; Emergent BioSolutions, supra, at 7; Everpure, Inc.,
B-226395.4, Oct. 10, 1990, 90-2 CPD para. 275 at 4-5.
Additionally, the scope of work of the RFP and original
PharmAthene Phase 2 contract was a broadly-defined one: the
continued advanced development, testing, and production of rPA
anthrax vaccine suitable for FDA licensure, as well as specific
objectives and milestones that were to be accomplished in
support thereof. Given this broad scope of work, we think the
RFP and original contract reasonably contemplated that there
would be developmental changes and setbacks during performance,
including, as here, those resulting from changes in FDA
guidance, manufacturing facility changes, technology transfer
requirements, and additional studies. See AT&T Comm'cns, Inc. v.
Wiltel, supra, at 1205-06 (a broad original scope of work may
validate a broader range of later modifications without further
competition).
The record also reflects that the original objectives of
PharmAthene's Phase 2 contract have not changed, and that
modification 0018 continues rather than alters the original
contract objectives. As stated by the HHS project officer, "[t]he
steps in [the] process have changed over time, but the end
result has remained the same." Tr. at 293. We agree. Where the
type of work under a contract as modified remains substantially
unchanged, we do not view modifications of the technical
requirements of performance to be outside the scope. Atlantic
Coast Contracting, Inc., supra. Furthermore, a technical change
to a contract should be viewed in the context of the
contractor's obligations "as a whole." AT&T Comm'cns, Inc. v.
Wiltel, supra, at 1206. Quite simply, given the broadly-defined,
developmental nature of the PharmAthene Phase 2 contract
requirements, we conclude that modification 0018 does not
represent a material difference in the type of work from the
original contract.
Further, we think that the solicitation for the original
contract adequately advised offerors of the potential for the
type of changes that occurred during the course of contract
performance (i.e., changes in processes and activities but not
objectives), and that in the context of the type of R&D work at
issue here, modification 0018 encompasses changes which the
field of competitors could reasonably have anticipated. DOR
Biodefense, Inc.; Emergent BioSolutions, supra, at 7;
Engineering & Prof'l Servs., supra, at 4.
Emergent argues that the work requirements of modification 0018
are beyond the scope of work of the original contract in one
particular regard. Specifically, the protester contends that the
RFP expressly provided that the original contract would not fund
animal aerosol challenge studies, yet modification 0018 now
funds such studies. Emergent argues that, as a result, this work
is out-of-scope and needs to be competitively procured.
The original solicitation stated, in relevant part,
A critical component of an rPA vaccine database and licensure of
any rPA vaccine will be controlled animal efficacy data and
aerosol challenge data in relevant animal models. However, there
is a worldwide shortage of Biosafety Level 3 aerosol challenge
capacity . . . so it is therefore essential that this capacity
be used as efficiently as possible to generate these crucial
data. . . . Accordingly, [HHS] intends to directly fund the
conduct of the aerosol animal challenge studies associated with
this advanced rPA vaccine development effort through a separate
contract with a separate contractor. . . . This close
government/contractor relationship will enable efficient
implementation of a comprehensive core of well-designed aerosol
challenge studies that should provide quality data to support
product licensure using the animal rule.
AR, Tab 5, RFP at 4.
Thus, while the objectives and milestones in the RFP required a
successful offeror to design, construct, and analyze the animal
aerosol challenge studies necessary for FDA product licensure,
the offeror did not have to perform the actual studies itself.
As HHS essentially made itself a subcontractor to a successful
offeror with regard to the performance of the animal aerosol
challenge studies, tr. at 242-44, the RFP informed offerors that
they did not need to budget for the performance of animal
aerosol challenge studies. By contrast, as part of modification
0018, PharmAthene is to perform such animal aerosol challenge
studies.
In our view PharmAthene's performance of animal aerosol
challenge studies does not materially change the nature of the
original rPA anthrax vaccine development contract. The RFP and
original contract already required PharmAthene to design and
construct animal aerosol challenge studies, receive and evaluate
the resulting data, and submit the data to the FDA as part of
product licensure. What modification 0018 changed was who--PharmAthene
or HHS--was to perform such animal aerosol challenge studies. We
see no basis to conclude that this change materially altered the
type of work required under the original contract, or would have
affected the original field of competition. (Emergent
BioSolutions Inc., B-402576, June 8, 2010) (pdf)
OLG contends that
ANHAM’s contract was limited to armored vehicles, and that
adding unarmored vehicles under the modification exceeded the
scope of the contract and therefore constituted an improper
sole-source award. The Army asserts that the RFP in fact
included unarmored vehicles, stating that in “military parlance,
a non-tactical vehicle (NTV) connotes a commercially available
vehicle that is not armored . . . . Soft-skinned, unarmored and
non-tactical vehicles are adjectives used interchangeably to
denote commercial vehicles without any form of armor.” AR at 2
n.1.
As a general rule, our Office will not consider protests against
contract modifications, since they involve matters of contract
administration and are beyond the scope of our bid protest
function. 4 C.F.R. sect. 21.5(a) (2009); DOR Biodefense, Inc.;
Emergent BioSolutions, B-296358.3, B-296358.4, Jan. 31, 2006,
2006 CPD para. 35 at 6: Engineering & Prof’l Servs., Inc.,
B-289331, Jan. 28, 2002, 2002 CPD para. 24 at 4. An exception to
this general rule is where, as here, a protester alleges that a
modification is beyond the scope of the original contract,
since, absent a valid sole‑source justification, the work
covered by the modification would be subject to the statutory
requirement for competition. Engineering & Prof’l Servs., Inc.,
supra, at 4; Atlantic Coast Contracting, Inc., B-288969.2, June
21, 2002, 2002 CPD para. 104 at 4.
In determining whether a modification triggers the competition
requirements in the Competition In Contracting Act of 1984, 10
U.S.C. sect. 2304(a)(1)(A), we look to whether there is a
material difference between the modified contract and the
contract that was originally awarded. Engineering & Prof’l Servs,
Inc., supra, at 4. Evidence of a material difference between the
modification and the original contract is found by examining
changes in the type of work, performance period, and costs
between the contract as awarded and as modified. Atlantic Coast
Contracting, Inc., supra, at 4. Here, the record is clear that
the purpose and nature of the original contract were not changed
by the modification.
The determinative consideration here is, simply, whether the
requirement as described in the RFP (and resulting contract)
included unarmored vehicles. While the RFP does not refer to
“unarmored” vehicles, per se, in describing the requirement, we
think it nevertheless was sufficiently clear that unarmored
vehicles were encompassed by the RFP. In this regard, in
describing the requirement, as noted, the RFP differentiated
between “non-tactical vehicles” (NTV) and “up‑armored”
vehicles.” It is undisputed in the record that an NTV may be
either armored or unarmored. However, since the RFP here
specifically called for both NTV and “up-armored” vehicles, we
think it should have been clear to the protester that the term
NTV was intended to refer to unarmored NTV. If the protester
were correct that NTV referred only to NTV with armor, there
would have been no logical reason for the RFP to refer to NTV at
all, since up-armored vehicles reasonably would have included
armored NTVs. Moreover, the RFP nowhere defined NTV as armored
vehicles and, while OLG contends that the Army’s definition of
NTV is “flat‑out wrong,” Protester Comments at 2, it has
provided no definitive evidence refuting the agency’s assertion
that the term NTV generally is used to refer to unarmored
vehicles.
OLG maintains that the fact that the RFP and contract specified
“five specific configurations of ‘hard’ (armored) vehicles,” and
no unarmored vehicles, shows that the contract was not meant to
include the ordering or delivery of unarmored vehicles. Protest
at 3. However, the agency made clear from the outset that the
VLPL [Vehicle Lease Price List] was not all-inclusive, and could
be modified in the future. In this regard, as noted above, the
RFP advised offerors that “The [VLPL] will be incorporated into
the contract and may change in accordance with the available
market. . . .” RFP at 77. Consistent with this language,
amendment 5 to the RFP, issued January 9, 2009, included answers
to questions, including the following:
Q4: I am curious if only one brand of transport would be
acceptable?, such as the specified Ford Truck and Van units?
A4: The list of vehicles in the solicitation is representative
of what we have been using and will continue to be diversified.
RFP amend. 5, at 3. In response to another question regarding
the vehicles, the agency advised that the “list of vehicles will
be amended, if required, after award of the contract. Please
quote on the list as provided.” Id. In view of the cited RFP
language, as clarified by the amendment, the listing of only
armored vehicles in the RFP did not preclude the purchase of
unarmored vehicles under the contract.
The protest is denied. (Overseas
Lease Group, Inc., B-402111, January 19, 2010) (pdf)
Sallie Mae argues that the CSB contract, as originally competed
and awarded, did not contemplate the servicing of non-defaulted
FFELP loans, and that modification of the contract to encompass
the servicing of the non-defaulted FFELP loans “put” to the
government pursuant to the loan purchase program is accordingly
beyond its original scope.
The Competition in Contracting Act (CICA) requires “full and
open competition” in government procurements as obtained through
the use of competitive procedures. 41 U.S.C. sect. 253a(a)(1)(A)
(2000). Once a contract is awarded, however, our Office will
generally not review modifications to that contract, because
such matters are related to contract administration and are
beyond the scope of our bid protest function. Bid Protest
Regulations, 4 C.F.R. sect. 21.5(a) (2008); DOR Biodefense,
Inc.; Emergent BioSolutions, B‑296358.3; B-298358.4, Jan. 31,
2006, 2006 CPD para. 35 at 6. An exception to this rule is where
it is alleged that a contract modification is beyond the scope
of the original contract because, absent a valid sole-source
determination, the work covered by the modification would be
subject to the statutory requirements for competition.
Engineering & Prof’l Servs., Inc., B-289331, Jan. 28, 2002, 2002
CPD para. 24 at 3.
In determining whether a modification triggers the competition
requirements in CICA, we look to whether there is a material
difference between the modified contract and the contract that
was originally awarded. MCI Telecomms. Corp., B‑276659.2, Sept.
29, 1997, 97-2 CPD para. 90 at 7. Evidence of a material
difference between the modification and the original contract is
found by examining any changes in the type of work, performance
period, and costs between the contract as awarded and as
modified. Atlantic Coast Contracting, Inc., B-288969.4, June 21,
2002, 2002 CPD para. 104 at 4. We also consider whether the
solicitation for the original contract adequately advised
offerors of the potential for the type of change found in the
modification, and thus whether the modification would have
changed the field of competition. DOR Biodefense, Inc.; Emergent
BioSolutions, supra.
In support of its argument that the servicing of non-defaulted
FFELP loans is beyond the scope of ACS’s CSB contract, the
protester notes that the Statement of Objectives (SOO) in the
CSB solicitation did not describe the servicing of non-defaulted
FFELP loans and that the Student Credit Management Volumes chart
provided as an appendix to the SOO did not furnish a figure for
non-defaulted FFELP loans. Sallie Mae maintains that offerors
could not possibly have contemplated that the CSB contract would
include the servicing of the non-defaulted FFELP loans that are
expected to be put to the government given that the legislation
authorizing the loan purchase program was not enacted until May
2008. The protester also points out that the ECASLA authorizes
the Secretary of Education to contract with eligible lenders for
the servicing of the loans purchased from them and argues that
there would have been no need for the statute to include such
authorization if it were intended that the loans put to the
government be serviced under ACS’s CSB contract.
In response, the agency maintains that the SOO in the CSB
solicitation described the kinds of obligations that the
contractor would be responsible for servicing quite broadly,
providing that “[t]he CSB solution will have the capability to
manage all types of student aid obligations,” and that “[t]hese
obligations include Direct Loans, defaulted debts assigned to
the Department of Education from [FFEL] or other lenders,
rehabilitated loans, and any other type of Title IV student loan
obligation.” SOO, sect. 1.2, as cited in AR at 3-4. (Emphasis
added by agency.)
While we agree with the protester that at the time the CSB
contract was awarded, agency officials and offerors could not
have anticipated that the government would acquire the number of
FFELP loans that lenders now have the option to put to it
pursuant to the loan purchase program, we do not think that this
leads to the conclusion that modification of the CSB contract to
encompass the servicing of these loans would be beyond the
contract’s scope. In our view, the SOO in the CSB solicitation
clearly placed offerors on notice that the agency intended to
award a contract for the management--i.e., the servicing, the
consolidating, and the collecting--of all types of Title IV
student loans, including the types of FFELP loans that the
ECASLA has authorized the government to purchase from lenders,
i.e., Stafford subsidized, Stafford unsubsidized, and PLUS
loans. In this connection, we note that not only did the SOO
state that the CSB solution was to be capable of managing “all
types of student aid obligations,” including direct, defaulted
FFELP, and rehabilitated loans and “any other type of Title IV
student aid obligation,” but it also specifically identified the
Stafford and PLUS loan programs as among the Title IV programs.
Furthermore, the SOO specifically instructed that the CSB
solution was to be flexible enough to handle new requirements
generated by Congress and to respond to legislative mandates and
policy changes. SOO at 33.
We also disagree with the protester’s argument that the
inclusion in the ECASLA of language authorizing the Secretary of
Education to contract with lenders for the servicing of loans
that they sell to the government demonstrates that Congress
contemplated that these loans would not be serviced under the
CSB. We simply have no basis to conclude that this language may
reasonably be interpreted as signaling that Congress intended to
preclude the Secretary from contracting for the services from a
source or sources other than the lenders.
Sallie Mae further argues that the modification of ACS’s CSB
contract to encompass the servicing of the FFELP loans that the
agency will acquire represents an out-of-scope change in the
original contract because it will dramatically increase the
scope of the loan portfolio that ACS is servicing for the
government.
As previously noted, the agency reported to us that ACS expects
to service approximately [deleted]. According to the agency, if
all of the loans that lenders were vested with the option to put
to the government in mid-September are in fact put, about
[deleted] new borrowers would be added to the ACS portfolio, and
the projected cost of servicing these additional borrowers in
2009 would be approximately [deleted]. AR at 3. These figures
were substantially decreased by the agency decision to take
corrective action, however. As previously noted, the agency
expects to award a new contract for servicing of the FFEL loans
by March or April of 2009, and anticipates that the contractor
will be able to begin servicing the loans by August or September
2009. According to the chart summarizing the loans to be put to
the government by borrower and month included in the agency
report at Tab O, [deleted] loans that lenders have a vested
option to put to the government during fiscal year 2009 are to
be put in August, and [deleted] are to be put in September 2009.
In other words, [deleted] of the loans will potentially be
serviced by the new contractor. The addition of the remaining
[deleted] that may be put to the government prior to August
represents an increase of only approximately [deleted] to ACS’s
existing portfolio of [deleted] loans. Such an increase clearly
cannot be characterized as--to use the protester’s
wording--dramatic. Moreover, even assuming that all [deleted]
loans do end up being serviced under ACS’s CSB contract, this
represents an increase of approximately [deleted] percent to
ACS’s existing portfolio. Such an increase in workload volume
does not, in and of itself, signal a modification beyond the
scope of the original contract. See Caltech Serv. Corp.,
B‑240726.6, Jan. 22, 1992, 92-1 CPD para. 94 at 5 (30 percent
increase in workload volume not beyond scope of original
contract). (Sallie Mae, Inc.,
B-400486, November 21, 2008) (pdf)
The protesters argue that the contract was improperly modified
to require delivery of a bivalent serotype A/B vaccine, a
product that was not listed among the optional RFP CLINs. The
RFP identified optional CLINS for monovalent vaccine serotypes A
through G, and a multivalent vaccine for serotypes A, B, D and
F. RFP at B-1. The RFP advised offerors, however, that “[t]he
government reserves the right to change the list above to add or
delete products as need may arise.” RFP at B-1. Where the type
of work under a contract as modified remains substantially
unchanged, we do not view modifications of the technical
requirements of performance to be outside the scope. Atlantic
Coast, supra. Our decisions have acknowledged that additional
latitude for changing a contract may exist where the contract is
for research and development, noting that the scope of such
contracts is often flexible because of unanticipated changes due
to the lack of definitiveness of the government’s requirements.
Everpure, Inc., B-226395, B-226395.4, Oct. 10, 1990, 90-2 CPD
para. 275 at 4-5. Furthermore, a technical change to a contract
should be viewed in the context of the contractor’s obligations
“as a whole.” AT&T Communications, Inc., 1 F.3d at 1206. Here,
the RFP made clear that decisions regarding the specific
vaccines to be developed and produced would be made after award,
and that the agency could add or delete vaccines based on the
government’s needs. RFP at B-1. The RFP and contract, in our
view, anticipated addition and deletion of optional botulinum
vaccines, and thus the change from the RFP’s requirement under
CLIN 0016 for a pentavalent vaccine to a bivalent vaccine that
incorporates two of the serotypes under the pentavalent vaccine
does not fundamentally alter the type of work required under the
contract. See Engineering & Prof’l Servs., supra. (DOR
Biodefense, Inc.; Emergent BioSolutions, B-296358.3;
B-296358.4, January 31, 2006) (pdf)
The agency characterizes the contract modification as a
reasonable effort to ensure that the agency remains in
compliance with EPA regulations for handling of the SBM. The
agency contends that, due to UST's subcontractor's failure to
properly recycle the SBM, UST's ability to comply with the
contract's recycling component was called into question. Thus,
the agency states that in the absence of a viable recycling
option, it modified the contract to allow for disposal
consistent with EPA regulations. The agency argues that the
government's ultimate need for plastic media and the obligation
to comply with EPA regulations regarding the handling of the SBM
have not changed and, thus, the modification was proper. We
disagree with the agency's view that the modification does not
materially change the requirements of the contract or result in
a fundamental change to the nature of the work. The original
solicitation sought proposals that required offerors to both
lease plastic media and recycle the resulting SBM in compliance
with regulations, and offerors were thus required to propose
technical solutions and pricing for both the lease and recycling
components of the work. The fact that the agency still requires
plastic media for its equipment needs and still requires removal
of the SBM from its facilities does not afford the agency
unlimited latitude to modify the way in which it contracts to
meet those requirements. An agency may not modify a contract by
changing or relaxing requirements where the resulting work is
fundamentally different from the work anticipated by the
original solicitation. Marvin J. Perry & Assoc. , supra , at
4-5; Avtron Mfg., Inc. , supra , at 4-5. Here, the RFP did not
anticipate that the contractor could be relieved of the
recycling requirement or that a disposal effort could be ordered
in lieu of recycling. Furthermore, Poly-Pacific contends, and
the agency does not dispute, that the costs of leasing plastic
media with no recycling requirements is as much as 50 percent
less than the costs of leasing plastic media with recycling
requirements. There also appear to be at least 4 approved
sources for providing type V plastic media, including
Poly-Pacific and UST, without the recycling requirement.
Comments, exh. 8, "Media Approved for Air Force Use." Evidence
suggesting that proposals submitted on the basis of a modified
contract's relaxed requirements could result in more competition
and lower prices generally weighs in favor of finding that the
contract modification was improper. Avtron Mfg., Inc. , supra ,
at 5. In sum, the agency's suspension of the recycling
requirement relaxed the performance requirements and modified
the contract beyond the scope of work anticipated by the
underlying solicitation and unmodified contract. In our view,
the modification resulted in a material and fundamental change
to the nature of the work that changed the field of competition
and that work, therefore, should have been competed on a full
and open basis, unless the agency followed the steps required to
conduct the procurement without full and open competition. (Poly-Pacific
Technologies, Inc., B-296029, June 1, 2005) (pdf)
As noted above, the competitive award to Saltwater was based
upon a 1-year contract extending through June 30, 2004 with a
1-year option to June 30, 2005. However, the award to NWO was
for a 6-month contract period from July 1, 2004 toDecember 31,
2004, with an option to extend the contract 1 year, i.e. , to
December31, 2005, which Commerce has exercised. Because the
period of performance under NWO's contract extends beyond June
30, 2005, it is inconsistent with the basis for the competition
and therefore improper. See Tennessee Valley Serv. Co. ,
B188771, Dec. 8, 1977, 77-2 CPD 442. That is, the extension of
NWO's contract beyond June30, 2005 constitutes an improper
sole-source, since it was not supported by a J&A. Since the
contract with NWO now is in its option year, we recommend that
Commerce meet its needs after June 30 competitively (through
limited competition if full and open competition is not
feasible) and terminate NWO's contract as of that date if NWO is
not the successful offeror. We further recommend that the agency
reimburse Saltwater for the costs of filing and pursuing its
protests, including reasonable attorneys' fees. Saltwater's
certified claim for costs, detailing the time spent and cost
incurred, must be submitted to the agency within 60 days of
receiving this decision. 4 C.F.R. 21.8(f)(1) (2004). (Saltwater
Inc.--Reconsideration and Costs, B-294121.3; B-294121.4,
February 8, 2005) (pdf)
CECOM's FedBizOps synopsis explained that the primary
justification for restricting the acquisition to one source was
that deliveries by a source other than MAI would be delayed
unacceptably due to the time required for testing. Lyntronics
failed to substantively address this concern in its April 2
proposal, instead merely asserting, without supporting
explanation or information, that it could have a first article
ready in 3-4 weeks, and the first shipment ready in an
additional month. In light of CECOM's stated concern and
projected 1-year timeframe, it was incumbent upon Lyntronics to
provide specific information detailing its alternative FAT
schedule; absent such information, CECOM had no basis to
determine that Lyntronics would be able to perform the required
tests and deliver batteries within CECOM's timeframe. See Litton
Computer Servs., supra. We conclude that CECOM reasonably
determined that only MAI could satisfy its requirements for the
BA-3547/U battery within the time required, and that the
sole‑source modification of that firm's contract was
unobjectionable. (Lyntronics Inc.,
B-292204, July 22, 2003) (pdf)
Accordingly, the critical question is whether the change in the location of the site for
the construction of the awarded building space is so material to the overall effort
required under the SFO as to be outside of the scope of the lease
awarded here. In answering this question, we look to the purpose and nature of the lease, which here
required much more than an amount of space located at a particular address.
As noted above, the lease here incorporates numerous work performance
requirements ranging from the provision of specific, architecturally defined areas of
building space, highly specialized for the needs of a medical treatment facility, to the
provision of specified management, custodial, and security services. In our view, the
level of detail provided describing the required configuration and provision of the
building space reflects the relative importance to the agency of obtaining space
meeting specific design and functional requirements. In contrast, the SFO’s property
location requirements are only general in nature and scope--wide location
boundaries were provided in the SFO and only general transportation accessibility
was required, reasonably indicating that specific location within the cited area
simply was not a critical factor to the agency, as long as the property was within the
delineated area and reasonably accessible. In other words, we think it is apparent
that the location of the specific site offered--as long as it was within the identified
geographic boundaries and otherwise met all SFO requirements--was not
of particular importance under the SFO. (HG
Properties A, LP, B-290416; B-2904162, July 25, 2002 (pdf))
In determining whether a modification triggers the competition
requirements in the Competition in Contracting Act of 1984, 10
U.S.C. § 2304(a)(1)(A) (2000), we look to whether there is a
material difference between the modified contract and the
contract that was originally awarded. Evidence of a
material difference between the modification and the original
contract is found by examining any changes in the type of work,
performance period and costs between the contract as awarded and
as modified. The question for our review is whether the
original nature and purpose of the contract is so substantially
changed by the modification that the original and modified
contract would be essentially different and the field of
competition materially changed. Engineering &
Professional Servs., Inc., B-289331, Jan. 28, 2002, 2002 CPD
¶ 24 at 4. Here, the Army's modification did not make any
changes to the original nature and purpose of the contract.
First, the front-loading refuse collection service is but one of
multiple refuse collection services to be performed under the
contract, the bulk of which were to be performed using the
contractor's trucks. Contract § C.4. Moreover, the
contract specifically included as one of the multiple line items
the requirement that the contractor would perform the very
front-loading refuse collection services that were the subject
of this modification, albeit with government furnished vehicles.
As noted, the decision to modify the requirement to have the
contractor perform this task with its own vehicles and
containers--as the contractor does on other contract line
items--rather than with government-furnished equipment--as
originally required by the contract--came about only because of
the condition of the government's equipment (and at Atlantic's
suggestion). Since the essence of the requirement was for
the contractor to provide front-loading refuse collection, the
Army's modification, merely shifting the responsibility for the
vehicles and the containers needed to carryout the service to
the contractor, did not substantially change the contract, nor
make it essentially different. (Atlantic Coast Contracting, Inc,
B-288969.4, June 21, 2002
)
In determining whether a
modification triggers the competition requirements in the
Competition in Contracting Act of 1984, 10 U.S.C. sect.
2304(a)(1)(A) (Supp. IV 1998), we look to whether there is a
material difference between the modified contract and the
contract that was originally awarded. Neil R. Gross & Co.,
Inc., supra, at 2-3; see AT&T Communications, Inc. v. Wiltel,
Inc., 1 F.3d 1201, 1205 (Fed. Cir. 1993). Evidence of a material
difference between the modification and the original contract is
found by examining any changes in the type of work, performance
period, and costs between the contract as awarded and as
modified. Access Research Corp., B-281807, Apr. 5, 1999, 99-1
CPD para. 64 at 3-4; MCI Telecomms. Corp., B-276659.2, Sept. 29,
1997, 97-2 CPD para. 90 at 7-8. The question for our review is
whether the original nature or purpose of the contract is so
substantially changed by the modification that the original and
modified contract would be essentially different, and the field
of competition materially changed. Everpure, Inc., B-226395.4,
Oct. 10, 1990, 90-2 CPD para. 275 at 4. The RFP thus clearly
described the CHS-2 program as dynamic, and contemplated that
the contractor would incorporate new technologies as they became
available. Where, as here, a contractor provides more
technologically advanced equipment pursuant to a modification
within the scope of the basic contract--i.e., the fundamental
nature and purpose of the underlying contract remains
unchanged--the modification is not improper. See Hewlett Packard
Co., B-245293, Dec. 23, 1991, 91-2 CPD para. 576 at 3-4. (Engineering
& Professional Services, Inc., B-289331, January 28,
2002)
ARC's argument here overlooks the
fact that with each modification, the terms of MERC's basic
contract were changed to accommodate the agency's overall need,
as reflected in modification No. 06, to digitize the entire TO
warehouse. Accordingly, a comparison of modification No. 16 to
delivery order No. 0005, without regard to the impact of the
intervening modifications--especially modification No. 06, which
contemplated the digitization of the entire TO warehouse--on the
terms of MERC's basic contract, would not be appropriate, since
such a comparison would disregard the new contract
requirements.
The protester has not
established that the fundamental nature and purpose of MERC's
contract, as modified, were materially changed by modification
No. 16 so as to require a separate competition. (Access
Research Corporation, B-281807, April 5, 1999) |
|
Comptroller
General - Listing of Decisions |
For
the Government |
For
the Protester |
Zodiac
of North America, Inc. B-414260: Mar 28, 2017 |
New
Alliant
Solutions, LLC B-415994, B-415994.2: May 14,
2018 |
Chase
Supply, Inc. B-411528.2, B-411529.2: Dec 7, 2015 (pdf) |
Western
Pilot Service; Aerial Timber Applicators, Inc.; Evergreen Flying
Services, Inc.; G.B. Aerial Applications, Inc. B-415732,
B-415732.2, B-415732.3, B-415732.4: Mar 6, 2018 |
Cornische Aviation & Maintenance, LTD,
B-405013.4, Jan 25, 2013 (pdf) |
Onix Networking Corporation
B-411841: Nov 9, 20150 (pdf) |
WorldWide Language Resources, Inc.,
B-299315.7; B-299315.8, August 12, 2010 (pdf) |
Poly-Pacific Technologies, Inc.,
B-296029, June 1, 2005 (pdf) |
Emergent BioSolutions Inc.,
B-402576, June 8, 2010 (pdf) |
Saltwater Inc.--Reconsideration and
Costs, B-294121.3; B-294121.4, February 8, 2005 (pdf) |
Overseas Lease Group, Inc.,
B-402111, January 19, 2010 (pdf) |
MCI Telecommunications Corporation, B-276659.2, September 29,
1997 (pdf) |
Sallie Mae, Inc., B-400486,
November 21, 2008 (pdf) |
|
DOR Biodefense, Inc.; Emergent
BioSolutions, B-296358.3; B-296358.4, January 31, 2006 (pdf) |
|
Lyntronics Inc., B-292204, July
22, 2003 |
|
HG
Properties A, LP, B-290416; B-2904162, July 25, 2002 (pdf)
|
|
Atlantic Coast Contracting, Inc,
B-288969.4, June 21, 2002
|
|
Engineering
& Professional Services, Inc., B-289331, January 28,
2002 (print
pdf)
|
|
Paragon
Systems, Inc., B-284694.2, July 5, 2000 |
|
Parmatic
Filter Corporation, B-283645; B-283645.2, December 20, 1999 |
|
Access
Research Corporation, B-281807, April 5, 1999 |
|
U.
S. Court of Federal Claims - Key Excerpts |
New This is a protest of a decision by the Department of Veterans Affairs
(“VA”) to modify four existing contracts for the distribution of medical and
surgical supplies. The contracts were modified to expand the scope of work
to include supply as well as distribution. The plaintiffs are suppliers of
medical and surgical items and allege that the change will result in loss of
opportunity to compete to sell their products to the VA. We denied a motion
for a preliminary injunction on July 13, 2018. The case is now presented on
fully-briefed cross-motions for judgment on the administrative record. Oral
argument was held on September 13, 2018. As announced at the conclusion
of oral argument, because the balance of the harms favors the government, we
cannot grant an injunction.
Background
The VA awarded contract No. VA119-16-D-002 to Kreisers, Inc.
(“Kreisers”), No. VA119-16-D-0004 to American Medical Depot (“AMD”),
No. VA119-16-D-0005 to Cardinal Health 200, Inc., and No. VA119-16-D0006
to Medline Industries, Inc. (“Medline”) on February 24, 2016. The VA
refers to these companies as the “Prime Vendors” or “PVs” of its Medical Surgical-Prime
Vendor-Next Generation program (“MSPV-NG” or “MSPV”
generally). Each contract covers a geographical area and requires the PVs to
stock, store, and distribute the medical supplies that are available on the
“Master List” against which VA hospitals can place orders. The agency also
refers to this as the “formulary.” An item on the list comes from a specific
supplier and is available for a set price. The VA local centers place orders
with the PVs, which then ship those items to the hospitals and bill the VA for
them. The dispute in this case concerns who should populate the Master List
with particular items, suppliers, and prices. It is worth noting up front that
plaintiffs do not contend that they are able to do the precise work sought by the
modifications–populating the Master List. Rather, they are able to furnish
some of the end-product supplies which will appear on the Master List.
The MSPV program has been in existence for over a decade. It is
intended to further standardize and expedite the buying process by “narrowing
the range of items purchased to meet a given need in order to improve buying
power, simplify supply chain management, and provide clinical consistency.”
AR 1972. The goal of the VA was to establish a “national strategic sourcing
solution that combines a Government-provided capability for ordering a wide
range of medical and surgical supplies via a master listing with electronic
cataloging (e-catalog) and ordering capability.” Id. VA medical centers
around the country have used the legacy MSPV program to order frequentlyused
medical and surgical supplies. In 2016, the Government Accountability
Office (“GAO”) issued a report about the program. It stated that the former
version of the MSPV was not fully realizing its purpose of “standardizing
items used across [the VA’s] medical centers” nor had it achieved cost savings
that ought to follow from the buying power generated by a standardized
ordering process. AR 408.2 The VA hoped to improve outcomes with the new
MSPV.
(sections deleted)
By March 2018, the Master List contained only 7800 out of the 80,000
that the VA anticipated as necessary to support its national healthcare network.
This failure was untenable in the view of the VA, thus it sought rapidly to
enlarge the number of items on the Master List by outsourcing to the PVs the
selection for items to be included on the formulary. In order to do so, it
modified the four PV contracts, allowing the PVs “to assist the Government
in sourcing thousands of new items quickly. This will be accomplished by
allowing the PVs to leverage their existing commercial networks in order to
propose sources and prices for items identified by the MSPV Program Office.”
AR 1974 (Class Justification and Approval). VA retained the ultimate
authority to place items on the Master List, but it no longer bothered to go
through the acquisition-like process of identifying sources and setting prices
through competing BPAs and the like (or other legal non-competitive
alternatives).
(sections deleted)
DISCUSSION
We are fully sympathetic with plaintiffs’ challenge to this
“procurement.” The VA appears to have thrown up its hands in its decade
long effort to develop an efficient system for the procurement of high volume
items by its many field hospitals using competitive or quasi-competitive
methods. It frankly concedes now that using competition is too time
consuming, too fraught with challenges, and too subject to inefficiencies
triggered by the myriad set-asides required by Congress. Having failed
abjectly in prior efforts, what it proposes here is tantamount to a wholesale
outsourcing of a large portion of its management of procurement to a few
private companies. And yet, we are sympathetic. And as we explain below,
we are unwilling to question the agency’s assessment that anything less
dramatic will jeopardize patient care.
Plaintiffs challenge the decision to modify the contracts and hand the
task of identifying suppliers to the PVs for five reasons: lack of competition,
failure to consider VA’s statutorily mandated preferences for service disabled
veteran-owned small businesses, improper bundling of distribution with supply
requirements, inherent conflict of interest due to the PVs also being suppliers
of some items, and an illegal outsourcing of inherently governmental
functions. Plaintiffs ask the court to enjoin the contract modifications and
require the VA to continue under its prior system of soliciting suppliers
through BPA solicitations and other competition-substitutes.
Defendant responded by moving to dismiss, arguing that plaintiffs lack
standing because the modifications were within the scope of the original
contracts, meaning that the change is not a protestable event. Defendant also
moved to dismiss for lack of standing on the basis that the plaintiffs are not
distributors of medical supplies and thus are not eligible for the work being
added to the PV contracts. Lastly, on the merits, the government cross-moved
for judgment, arguing that the J&A reasonably justifies the change, that any
harm to plaintiffs is merely hypothetical, that the VA will be significantly
harmed by any further delay in populating the list, and that the public interest
favors timely provision of healthcare to veterans as enabled by this
modification. Intervenors join in these arguments by filing their own cross
motions and, in one case, an independent motion to dismiss.
(sections deleted)
A. The Contracts’ Modifications Are an End-Run Around CICA
CICA requires that, except as otherwise provided by law, agencies
procuring goods or services must use “full and open competition through the
use of competitive procedures in accordance with the requirements of this
division and the Federal Acquisition Regulation.” 41 U.S.C. § 3301(a)(1)
(2012). CICA itself provides a number of exceptions to the full and open
competition requirement in section 3304. As detailed above, the VA availed
itself of subsection (a), which allows an agency to select a single source and
buy from that source when the agency determines that the goods or services
needed “are available from only one responsible source and no other type of
property or services will satisfy the needs of the executive agency.” Id. §
3304(a)(1). The agency found that only the four PVs were in a position to
quickly identify sources and prices for the items the VA wanted on the Master
List.
It justified the sole-source award of the modifications for that reason.
The inquiry does not end there, however.
Neither we nor the plaintiffs question the government’s conclusion that
the PVs are well, and perhaps critically, positioned to rapidly populate the
VA’s national formulary for medical supplies. The contract modifications may
indeed be justified as sole-source changes in scope, but CICA applies to the
purchase of all goods and services unless otherwise exempted by law.
Plaintiffs’ point is that their loss is at the supplier level, the level of the sales
of the individual items to the government. Neither the government nor the
intervenors answer this question other than to suggest that this problem preexisted
the change and thus this challenge comes too late.
Defendant points to the fact that both pre and post-modification the
actual sale of supply items to the government was and is between the PVs and
the VA. Although competition or competition substitutes were used prior to
the modification, avers defendant, it was always and still is the PVs selling to
the VA. Plaintiffs are thus too late, urges the government and intervenors.
We agree with plaintiffs, however, that this fact is not dispositive
because a new non-trivial competitive harm results from the modifications,
which is the loss of competition. Prior to the modifications, VA solicited and
entered into purchase agreements with vendors or justified sole-source
arrangements (as the case most frequently was). Competition was had and the
right to protest attached even when the vendor was a sole-source selection.
The subsequent purchase at those prices from those vendors by the PVs and
then resale to VA does not change the fact that the government competed or
otherwise lawfully avoided competition for each item placed and then
purchased off the Master List. The intermediary step provided by the PVs
makes no difference.
After the modification, the VA has foresworn competition as unwieldy
and impractical. By outsourcing the selection of suppliers to the PVs entirely,
the government has avoided the multitude of legal and regulatory requirements
appurtenant to a federal procurement. The change is obvious. Plaintiffs are
not in the same situation today as they were when the MSPV-NG contracts
were competed and originally awarded. Thus neither waiver nor laches
applies. CICA has been violated unless the J&A provides legal cover for the lack
of competition. As we explain next, it does not.
B. The J&A Does Not
Justify the Lack of Competition at the Supply Level
As plaintiffs rightly
point out, the J&A is silent as to the availability of
suppliers for the many thousands of items that have been and
still will be placed on the Master List. 30,000 new items have
been placed on the
formulary since this protest was filed. The record does not indicate whether
any items have been ordered from those 30,000, but regardless, when they are,
those sales will not have been competed. The law requires a justification and
approval for that purchase without competition. It is no answer to hide behind
the PVs’ role in adding to the list of items in the formulary. That aspect of the
modification is inseparable from the associated work of picking vendors. By
eliminating the price and vendor competitions or competition substitutes, the
VA has no-doubt bought itself significant expediency. But it has not bought
itself legal cover.
The J&A is silent as to the purchase of any particular item on the now
much-expanded list. Neither the government nor the intervenors have
provided a lawful reason why CICA is satisfied by this arrangement. Section
3304(a) allows agencies to forego full competition when they conclude and
explain that only one source can provide what they are purchasing, but that is
a far different circumstance than that provided by this case. We understand the
attraction; expediency is undoubtedly key when it comes to purchasing medical
supplies, but Congress has made no such particular exception to the
competition mandate. We are thus left to conclude that the law has been
violated.
C. The Modifications Ignore the VA’s Rule of Two Requirement
Plaintiffs’ second merit-based challenge regards the VA’s unique
requirement that it must consider whether a service-disabled veteran-owned
small business (“SDVOSB”) or, failing that, veteran-owned small business
(“VOSB”) could provide the goods it wishes to procure. If two or more such
entities could provide the items, the VA is required by law to attempt to buy
from those sources by running a competition limited to only those concerns.
This is the “rule of two.” 38 U.S.C. § 8127(d) (2012); Kingdomware Techs.,
Inc. v. United States, 136 S. Ct. 1969, 1976-77 (2016). The four plaintiffs are
SDVOSB companies and argue that, not only does the new PV-provided
sourcing violate CICA’s competition requirements, but it also robs them of
their entitlement to a competition limited to only them and other similarly
situated VOSBs.
The Supreme Court has left no doubt that the Veterans Benefits, Health
Care, and Information Technology Act of 2006, codified at sections 8127 and
8128 of title 38, requires that the “rule of two” be applied to every purchase
possible made by the VA with limited exceptions. Kingdomware, 136 S. Ct at 1977. Plaintiffs allege that they stand ready to provide many of the goods
needed by the government here, and there are more than two of them.
According to Kingdomware, VA must consider awarding to them. The PVs,
on the other hand, as private businesses, are not under such constraints and
thus plaintiffs are harmed. We agree.
The government again provides no legal cover for this arrangement.
Defendant and intervenors instead suggest that the PVs will be bound by their
small-business participation plans, which will protect the rights of VOSBs, and
thus the court should be unconcerned. We are not so sanguine. There is no
legal requirement that the PVs consider whether two VOSBs can provide an
item that they source for the Master List nor is there any requirement that they
limit their consideration to such businesses. Further, plaintiffs would not have
any right to challenge the selection of non-VOSBs by the PVs should they
ignore this requirement. The government might attempt to hold the
intervenors’ feet to the fire in this regard, as a contract administration issue,
but plaintiffs have lost valuable procurement rights in the process. The PVs
are private purchasers untethered to the FAR, VA regulations, and
procurement statutes.
The bevy of protests filed in this court and at GAO since the Supreme
Court’s decision in Kingdomware are evidence enough that these requirements
are strict and difficult to follow in the mean and no doubt doubly so when the
law requires that they be applied without fail or exception. And yet the law
remains. Only Congress has the kill switch. Plaintiffs are correct that 38
U.S.C. § 8127 is violated by the VA’s outsourcing of its selection of supply
vendors.
(sections deleted)
CONCLUSION
In this case, the VA is
hamstrung by the myriad requirements and preferences layered
onto the process of federal purchasing, and especially the
preferences unique to the VA. The complaint here is exhibit A.
Plaintiffs are correct that Congress has granted to them and
bidders generally a variety of rights when it comes to selling
things to the VA. It is for Congress and the voters to weigh
the merits of the benefits and burdens imposed by such a
labyrinth of legal and regulatory hoops and hurdles. This case
presents a circumstance in which the VA could not timely clear
the hurdles. The result is danger to veterans’ healthcare and
increased cost to the government. The agency found a detour
around the obstacles and tried to legally justify it. It could
not do so, but the court is in no position to restore the
status quo ante by enjoining a process aimed at protecting and
improving the management of the VA’s supply chain for medical
and surgical supplies. The equities do not favor the
plaintiffs: the harm to the plaintiffs is somewhat
speculative, while the harm to the agency is real and
potentially grave. The public interest favors avoiding those
harms. The protest must therefore be denied. (Electra-Med,
et al., v. U. S. and American Medical Depot, et al., No.
18-927C, October 3, 2018.)
Plaintiff challenges two aspects of the procurement. Plaintiff’s
primary challenge is directed at the modifications to OSG’s
contract after the Agency discovered that OSG was delivering
nonconforming windows. Plaintiff contends that the modifications
lacked a rational basis because the Agency unreasonably accepted
OSG’s contention of an alleged latent ambiguity in the
solicitation, allowing OSG to supply products that did not
conform to the required technical specifications. According to
plaintiff, this decision violated the Competition in Contracting Act (“CICA”)6 in that it thwarted full and open
competition. (Sentence deleted)Plaintiff’s first argument, that the contract modifications lacked a
rational basis, rests on plaintiff’s belief that OSG never intended to supply a
conforming product under the contracts, and that DLA’s acceptance of
nonconforming products as part of the modifications effectively eliminated any
competition. In its reply brief it argues that the contract modification brought
the contracts outside the scope of the solicitation, and therefore, under CICA,
a new procurement was required in order to preserve the competitive bidding
process. See 10 U.S.C. § 2304 (a)(1)(A) (2011) (“[T]he head of an Agency in
conducting a procurement for property or services . . . shall obtain full and
open competition through the use of competitive procedures . . . .”); CCL, Inc.
v. United States, 39 Fed. Cl. 780, 791 (1997) (explaining that CICA’s
requirements “cannot be avoided by using the device of contract
modification”).
As support for its position that OSG never intended to supply
conforming products, plaintiff relies on an April 15, 2015 letter from OSG’s
President and CEO to DLA setting out an analysis of the misunderstanding
between the parties. See CT(DLA)-367-70. This letter suggests that after OSG
was approved as a source, it discovered some risks regarding the availability
of M-ATV raw materials, which would lead it unable to produce composition
[ ]. As a result, OSG began testing other compositions of the formula for
the transparent armor, and developed a different composition, [ ]. Plaintiff
does not accept the truth of OSG’s responses to the Army, and suggests that
OSG had always intended to supply composition [ ], in violation of the MATV
Solicitations, which specified the correct NSNs and which explicitly
disallowed substitution. Schott argues that it was unreasonable and prejudicial
to it to allow OSG to rely on a supposed alleged latent ambiguity to deliver
substitute products because it was inconsistent with the terms of the original
solicitation and thus precluded Schott from competing.
Defendant recognizes in its response that there were serious errors with
OSG’s performance under the contracts, but maintains that these issues are not the proper subject for a bid protest. It argues that Schott cannot rest a bid
protest on what amounts to a matter of post-award contract performance,
something beyond the reach of the court’s bid protest jurisdiction under 28
U.S.C. § 1491(b). Relying on the affidavit of DLA’s Contracting Officer,[
], defendant contends that the award to OSG cannot be faulted, because
it proposed to supply the exact product. It was only after the awards were
made and well after performance had commenced that the government became
aware that OSG was providing nonconforming products.
Defendant also argues that Schott’s argument is factually unfounded,
in that the Agency rejected OSG’s interpretation of the contract. It never
knowingly accepted non-conforming product and merely devised a solution for
a serious problem after it was discovered. Because a majority of the deliveries
had been accepted and paid for by the time DLA discovered that they were
nonconforming, the agency’s rights were governed by FAR 52.246-2(k) and
(l). This regulation stipulates that the government’s acceptance of an item
“shall be conclusive, except for latent defects, fraud, [or] gross mistakes
amounting to fraud.” FAR 52.246-2(k) (2014). The regulation further provides
that following non-conclusive acceptance, the government may elect to have
the awardee “repay such portion of the contract as is equitable under the
circumstances if the Contracting Officer elects not to require correction or
replacement,” FAR 52.246-2(l) (2014), which defendant contends is exactly
what the Agency did. We agree with defendant. The agency never endorsed the
manner in which OSG proceeded with these contracts and instead devised a
practical solution to a problem of OSG’s making. Schott’s CICA rights, in
other words, were not compromised by anything the agency did.
We note, moreover, that in exercising jurisdiction over a bid protest,
“the courts shall give due regard to the interests of national defense and
national security and the need for expeditious resolution of the action.” 28
U.S.C. § 1491(b)(3). The [ ] affidavit makes clear the agency’s concern
that the military not be delayed in getting armored windows for its vehicle for
use in a combat zone. Returning the parties to the position they were in prior
to contracting would require pulling the M-ATV fleet out of service until
replacement transparent armor windows could be obtained through a new
procurement. Id.
We do not mean to suggest that circumstances could not arise in which
a contract modification might depart materially from the contract’s original
scope so as to trigger this court’s bid protest jurisdiction. See, e.g., Glob. Computer Enter.’s, Inc. v. United States, 88 Fed. Cl. 359, 452 (2009);
Cardinal Maint. Serv., Inc. v. United States, 63 Fed. Cl. 98, 108 (2004). In this
case, however, given the passage of time, the security concerns involved, and
the agency’s insistence on compensation for non-performance, we are
persuaded that concerns reflected in other cases are not triggered here. (Schott
Government Services, LLC v. U. S. and Oran Safety Glass,
Nos. 15-616C, 15-617C, 15-618C, 15-619C, 15-620C, September
17, 2015) (pdf)
A. Evolving Missions Are Anticipated in the Solicitation
The court’s first task is to determine whether the scope of the
Solicitation, as described by the Solicitation’s terms and its
Changes clause, would have led bidders to expect that the
Afghan airlift services disputed here could reasonably be
included within the State Contract. See AT & T, 1 F.3d at 1205
(“A modification generally falls within the scope of the
original procurement if potential bidders would have expected it
to fall within the contract’s changes clause.”). Plaintiff
advises that in solicitation interpretation, as in contract
interpretation, the court must give meaning to all of a
solicitation’s terms. Pl.’s Mot. at 49-50. The court agrees with
plaintiff’s view of contract interpretation. Even more apt
advice comes from the Federal Circuit, however, which suggests
that in bid protests alleging that a cardinal change has
occurred, the court must focus on the “the [challenged contract]
modification in the context of the contract as a whole.” AT & T,
1 F.3d at 1207. It is necessary, therefore, to begin with an
analysis of the context of services described in the
Solicitation.
1. The Solicitation’s Context
Here, the Solicitation noted that contract services “are currently performed
in Colombia, Bolivia, Peru, and Pakistan, and are anticipated in Mexico and
Afghanistan in the near future.” AR at 104. The court observes, first, that there is
no limit to the number of countries that could be served, or to the specific countries
that could be served under the State Contract. Thus, unless each of the country-specific
tasks enumerated in the Solicitation are identical, a bidder would have
realized that services to be performed in newly-added countries might well be
different from those provided in Bolivia or Peru, for example.
Upon a close reading of the Solicitation, there are, as it happens, significant
differences in the types of services provided in Colombia or Pakistan, for example,
from those provided in Bolivia and Peru. Of particular interest here, in Colombia
the awardee would be responsible for “Air Assault/Aerial Transportation of
Personnel and Cargo.” AR at 187. Two separate provisions of the Solicitation,
specific to Colombia in this regard, are relevant:
The Contractor routinely supports multiple-ship
helicopter air assault operations, which involves troop
transport helicopters and armed escort helicopters. The
Contractor shall maintain the capability to perform
special mission tasks to include but not limited to fast
rope and rappel operations. At least twice per month, the
Contractor will support air assault movement of one counter-narcotics battalion
(up to 500 personnel strength) and other units.
. . .
The Contractor will be required to
transport cargo and personnel to meet mission support
requirements in country. Currently, the average monthly movement
is 1,500 passengers and 120,000 pounds of cargo. This support is
currently provided with the C-27 and supplemented by leased
aircraft.
Id. It would be reasonable to interpret the
first cited provision as describing Air Assault and the second
cited provision as describing Aerial Transportation of Personnel
and Cargo; it is also reasonable to view or interpret these two
provisions as describing similar but not identical aviation
support services under the State Contract.
The operations in Bolivia and Peru are not
described as including Air Assault services. Furthermore, in
Bolivia, no country-specific provision is included for Aerial
Transportation of Personnel and Cargo. See AR at 194. In Peru,
the Aerial Transportation of Personnel and Cargo
country-specific provision states that
The Contractor will be required to
transport an average of 30 passengers and up to 6000 pounds of
cargo (or a combination thereof) at least three times a week
between Lima [and contract performance locations].
Id. at 200. Because operations in Colombia, Bolivia and Peru all differ in the type
of Aerial Transportation of Personnel and Cargo services to be provided, a bidder
on the State Contract could not assume that aviation support services in a newly-added
country would be the same as those described in the Solicitation
for these three countries. In the court’s view, a bidder would
have assumed that different types of aviation support services
could well be required under the contract in Afghanistan.
The court turns its focus to Pakistan. The
Solicitation includes a markedly different description of
missions to be performed in Pakistan, as opposed to the missions
described for the operations in Bolivia and Peru. Here are
perhaps the most relevant Pakistan-specific terms of the
Solicitation, in the “Mission Overview” description:
The Bureau for International Narcotics and Law
Enforcement Affairs, Office of Aviation (INL/A) is
primarily responsible to support the U.S Embassy
Country Team and NAS, Islamabad to assist the
Government of Pakistan (GOP) in the Border Security
Project. Under the auspices of the US Country Team, the
Narcotics Affairs Section (NAS) is primarily responsible
to assist host nation government to gain and maintain
control of the Pakistan-Afghanistan border through the
surveillance and interdiction of terrorists, narcotics, arms
and other unlawful cross-border activities. INL/A
supports this mission with the Huey IIs and C-208
Cessna Caravans.
AR at 203.
In Pakistan, the State Contract’s
primary focus is to assist Pakistan “to gain and maintain
control of the Pakistan-Afghanistan border.” Id. In Bolivia, in
contrast, the “Mission Overview” states that:
The Bureau for International Narcotics and Law
Enforcement Affairs, Office of Aviation (INL/A) is
primarily responsible to support the U.S Embassy
Country Team and NAS, La Paz to assist the Government
of Bolivia (GOB) to curtail the supply of illegal drugs
from Bolivia to the United States. INL/A performs this
mission through the Bolivia Air Program in support of
the NAS.
Id. at 192. The operations in Bolivia
differ in many respects from the operations in Pakistan.
Similarly, for Peru the “Mission Overview” states that the
primary focus of the State Contract will be the “curtailment of
the supply of illegal drugs from Peru into the United States.”
Id. at 198. Reasonable bidders would assume from these
country-specific descriptions of contract services that the
missions to be accomplished in Afghanistan would differ from
those in Bolivia and Peru, just as the missions to be
accomplished in Pakistan are different from those in Bolivia and
Peru.
As the court reads the Solicitation, aviation support services in each country
served, and the country-specific primary and secondary missions of INL/A, would
differ. This context is crucial to the determination of the scope of the State
Contract. The court now turns to the parties’ dispute as to the scope of the
Solicitation.
2. The Solicitation’s Scope
Plaintiff and defendant fundamentally
disagree as to the scope of the Solicitation. To summarize
plaintiff’s argument, five main points appear to provide the
foundation upon which plaintiff’s reading of the Solicitation
rests. First, the Solicitation must be narrowly construed as
seeking, at bottom, a counter-narcotics contractor for counter-narcotics missions. See, e.g., Pl.’s Mot. at 4 n.2
(suggesting that the primary and secondary missions noted in the Solicitation could
be referenced by the term “counternarcotics mission”); 46 (“The Counter-Narcotics
Solicitation was precisely that: a solicitation for aviation services in support of
designated counternarcotics missions.”). Second, all references in the Solicitation
to flexibility, additional tasks or evolving missions must be construed to include a
significant limitation – that all services added to the State Contract would
necessarily have a counter-narcotics focus. See id. at 49 (arguing that the
Solicitation’s reference to flexibility must be interpreted as stating that “flexibility
must be exercised within the confines of the Counternarcotics Solicitation and does
not authorize INL/A to acquire wholesale new airlift requirements materially
different from the services solicited in the original competion”); Pl.’s Reply at 9
(arguing that “broad-based air carriage of personnel or cargo . . . unrelated to
counternarcotics activities was beyond the scope of the contract’s counternarcotics
support mission”). Third, the Solicitation’s lack of a broad catch-all category of
services, or reference to any specific passenger-related services such as ticketing or
reservations, would have led offerors to assume that passenger service was beyond
the scope of the State Contract. Pl.’s Mot. at 47-48. Fourth, aerial transportation
of personnel and cargo, a category of services described in the Solicitation, cannot
be interpreted to include airlift services that do not have an emergency or military
nature, or that do not have a counter-narcotics purpose. Id.; Pl.’s Reply at 14-15.
Fifth, the Solicitation must be viewed as imbued with a strong nationalization mission, where the contractor would provide training to host country nationals in
furtherance of achieving a transition to counter-narcotic aviation support services
being provided by the host countries and not by the United States. Pl.’s Mot. at 51-
52; Pl.’s Reply at 9-10, 14. Because DynCorp’s performance of airlift services in
Afghanistan includes no training component, plaintiff argues, these services must
be beyond the expectations of offerors responding to a Solicitation
characterized by a strong nationalization mission. Pl.’s Mot. at
51-52.
Defendant, on the other hand, views the
Solicitation as denoting a procurement for a broad range of
aviation support services. Defendant points to language listing
a multitude of services to be provided under the State Contract,
such as this introductory statement of technical requirements:
This document provides the technical requirements for
the Bureau for International Narcotics and Law
Enforcement Affairs, Office of Aviation (INL/A)
Contractor Logistical Support (CLS) services for
eradication and interdiction of illicit drugs, training of
Contractor and host nation personnel, movement of
personnel and equipment, reconnaissance, search and
rescue, medical evacuation and ferrying of aircraft.
AR at 168. The government also points to terms of the Solicitation that are
expansive and broad, rather than narrow and specific. See Def.’s Mot. at 19.
Finally, defendant argues that the mention of “‘extremely hostile’” and “‘very
austere’” conditions in the Solicitation would have led offerors to presume that
contract missions would evolve as conditions required. Id. at 20 (quoting AR at
168).
Although both plaintiff’s and defendant’s positions reflect, at times,
somewhat extreme interpretations of the Solicitation, the court cannot disagree
with the government’s ultimate conclusion that aerial transportation of passengers
and cargo, at least in the context of protecting the interests of the United States in
Afghanistan, is within the scope of the Solicitation. First, as noted supra, different
types of aerial transportation are required in the country-specific portions of the
Solicitation, and different missions are required to be accomplished in different
nations. Second, there is enough flexibility in the Solicitation’s terms to support
aerial transportation of passengers and cargo in hostile environments. See, e.g.,
AR at 166 (“Secondary missions include pipeline security, border patrol, and other
related activities.”); id. (“The anticipated annual contract value is approximately
$170M, but could vary greatly depending upon how the mission evolves over the
performance period.”); id. at 167 (“Flexibility: Due to the evolving nature of the
mission, the contractor must be able to react to changing conditions quickly, with
minimal impact to steady state operations.”); id. at 169 (“The Department of State
anticipates expansion of the program, to include other aircraft types and or
quantity, and additional missions (counter-narcotics and expanded authorities) into
other countries.”). Third, the court finds that the provisions in the Solicitation
governing Aerial Transportation of Personnel and Cargo, alongside reference to
other operations of considerable variety, provide notice to reasonable offerors that
airlift support services in Afghanistan are contemplated under the terms and the
Changes clause of the Solicitation.
Plaintiff argues that “references” to the Aerial Transportation category of
services in the Solicitation are determinative of the expectations of offerors as to
airlift support services:
The issue before the Court, then, is whether the
references in the Counternarcotics Solicitation to “aerial
transportation of personnel and cargo” would have
sufficiently alerted prospective offerors to the possibility
that the government would use the resulting contract as a
vehicle to obtain from its counternarcotics contractor
full-scale commercial-equivalent passenger and cargo
services, including an online ticketing/reservation system, under which the contractor would serve all the
in-country air transportation needs of diplomacy and
development personnel, regardless of any connection to
the specific counternarcotics missions identified in the
Solicitation.
Pl.’s Reply at 14 (emphasis removed). The court does not agree with plaintiff’s
framing of the decisive issue for the merits of this protest. It is the Solicitation as a
whole, and especially the comparison of the context of the Solicitation with the
contract modification challenged here, that must be weighed by the court. See AT
& T, 1 F.3d at 1207. The Solicitation, aside from its important references to Aerial
Transportation of Personnel and Cargo, exhibited variety in the description of the
operations in Colombia, Bolivia, Peru, and Pakistan, and significant references to
flexibility and anticipated changes. Thus, although the Aerial Transportation
category of services is indeed important in the court’s analysis, the court must
construe the Solicitation as a whole.
The court has reviewed the relevant sections of the Solicitation and cannot
agree with plaintiff that secure air transportation of passengers and cargo, in the
hostile and austere conditions found in countries such as Afghanistan, was not
included within the Solicitation’s scope. The Technical Requirements Document
(TRD) describes “Aerial Transportation of Personnel and Cargo,” in relevant part,
in this manner:
Aerial transportation is defined as the
movement of personnel and cargo via rotary and/or fixed wing
aircraft. . . . The Contractor shall provide mission capable
aircraft and mission qualified crews to perform the
transportation mission.
AR at 171. Other operations, or
missions,16 include search and rescue, medical evacuations, and
VIP missions. AR at 171-72. As an introduction to these
operations, the Solicitation states that
[t]he types of missions the Contractor will be required to
perform are listed below. We anticipate that mission
profiles may change and the Contractor shall be capable
of adapting to these changes.
AR at 170. The court has considered: (1)
the performance period of more than ten
years for the State Contract; (2) the types of operations
specified in the TRD; (3)
the variety of missions described in the Solicitation; (4) the
differences in the
country-specific portions of the Solicitation; (5) the multiple
and prominent
references to flexibility, adaptation and change; and, (6) the
unique challenges of
protecting the interests of the United States in Afghanistan. In
view of the context
of the State Contract set forth in the Solicitation, the court
finds that a reasonable
offeror would have anticipated that in a country such as
Afghanistan, secure air
transportation of passengers and cargo would be within the scope
of the State
Contract.
There has been, therefore, no cardinal change effected by the
addition of
airlift support services in Afghanistan to the State Contract.
Thus, even if
plaintiff’s bid protest were not barred by laches [The court
finds that ACS unreasonably delayed its protest and that the
government was economically prejudiced as a result. Plaintiff’s
bid protest is barred by laches, and must be dismissed on these
grounds.], the protest
filed by ACS has not
succeeded on the merits. Because plaintiff has not shown that a
cardinal change of
the State Contract occurred, the court need not consider whether
ACS was
prejudiced by Mod 12 and the addition of airlift support
services in Afghanistan to
the State Contract. See Bannum II, 404 F.3d at 1351 (stating
that the prejudice
inquiry is triggered by the plaintiff’s success on the merits of
its protest). (Aircraft Charter
Solutions, Inc. v. U. S. and DynCorp International LLC, No.
13-9C, March 8, 2013) (pdf)
CICA generally directs executive agencies, “in conducting a
procurement for
property or services” to “obtain full and open competition
though the use of competitive
procedures.” 41 U.S.C. § 3301(a)(1) (Supp. V 2011) (formerly 41
U.S.C. § 253(a)(1)(A)
(2006)). As stated by the United States Court of Appeals for the
Federal Circuit:
CICA, however, does not prevent modification of a contract by
requiring
a new bid procedure for every change. Rather only modifications
outside the scope of the original competed contract fall
under the statutory
competition requirement. CICA sets forth no standard for
determining
when modification of an existing contract requires a new
competition or
falls within the scope of the original competitive
procurement.
AT & T Commc’ns, Inc. v. Wiltel, Inc., 1 F.3d 1201, 1204-05 (Fed. Cir.) (footnote
removed), reh’g denied, en banc suggestion declined (Fed. Cir.), suggestion for reh’g
declined (Fed. Cir. 1993). Contract modification for changes beyond the scope of the
original procurement, however, should not be utilized as a way to avoid competition.
See HDM Corp. v. United States, 69 Fed. Cl. 243, 253 (2005) (citation omitted); CESC
Plaza Ltd. P’ship v. United States, 52 Fed. Cl. 91, 93 (2002). Modifying an existing
contract so that it materially departs from the scope of the original procurement violates
CICA by preventing potential bidders from participating in or competing for what should
be a new procurement. See HDM Corp. v. United States, 69 Fed. Cl. at 253; see also
AT & T Commc’ns, Inc. v. Wiltel, Inc., 1 F.3d at 1205; VMC Behavioral Healthcare
Servs. v. United States, 50 Fed. Cl. 328, 332 (2001). A modification that is within the
scope of the original procurement “does not raise a viable protest under [28 U.S.C.]
§ 1491(b)(1).” See Distrib. Solutions, Inc. v. United States, 539 F.3d at 1346; See also
Ceradyne, Inc. v. United States, 103 Fed. Cl. 1, 12-13 (2012) (citing AT & T Commc’ns,
Inc. v. Wiltel, 1 F.3d at 1204-05) (“If the modification materially departs from the scope,
then a new competition may be required and jurisdiction will stand. . . . If the
modification was, however, within the scope of the solicitation, the protest must be
dismissed.”); RhinoCorps Ltd. Co. v. United States, 87 Fed. Cl. 481, 489 (2009) (citing
AT & T Commc’ns, Inc. v. Wiltel, 1 F.3d at 1205) (“[T]o sustain a bid protest stemming
from a change or modification to a contract, the protestor must allege facts that
establish that the modification falls outside the scope of the original contract, thereby
triggering the statutory competition requirement. If any change made to a procurement
is within the scope of work originally contemplated, no competition is required, and
jurisdiction is not present.”).
The United States Court of Appeals for the Federal Circuit, accordingly, has
recognized that modifications of an existing contract are permissible to procure products
or services, as long as the modification is “within the scope of the original competitive
procurement.” See AT & T Commc’ns, Inc. v. Wiltel, Inc., 1 F.3d at 1205; see also
Krygoski Constr. Co. v. United States, 94 F.3d 1537, 1543 (Fed. Cir.) (citation omitted),
reh’g denied, en banc suggestion declined (Fed. Cir. 1996), cert. denied, 520 U.S. 1210
(1997) (relying on AT & T Communications, Inc. v. Wiltel, Inc. in its analysis of a
necessary change to a contract’s scope); Golden Mfg. Co., Inc. v. United States, No.
12-317C, 2012 WL 4479422, at *10 (Fed. Cl. Oct. 1, 2012) (relying on AT & T
Communications, Inc. v. Wiltel, Inc. when discussing an amendment to a contract
solicitation); Solute Consulting v. United States, 103 Fed. Cl. 783, 792 (2012) (applying
AT & T Communications, Inc. v. Wiltel, Inc. to the issue of the in-scope contract
modification); Ceradyne, Inc. v. United States, 103 Fed. Cl. at 12 (analyzing AT & T
Communications, Inc. v. Wiltel, Inc. to determine whether the contract modification was
within the scope of the original procurement); RN Expertise, Inc. v. United States, 97
Fed. Cl. 460, 473 (using AT & T Communications, Inc. v. Wiltel, Inc. as a basis for the
court’s analysis of the contract modification), reconsideration denied (2011).
Because CICA itself does not define whether a modification of an existing
contract is “within the scope of the original competitive procurement,” the Federal Circuit
has relied on the “cardinal change” doctrine by analogy as the test to ascertain whether
the modification is in-scope or violates the competition requirements of CICA. See
AT & T Commc’ns, Inc. v. Wiltel, Inc., 1 F.3d at 1205 (“The cardinal change doctrine
asks whether a modification exceeds the scope of the contract’s changes clause; this
case asks whether the modification is within the scope of the competition conducted to
achieve the original contract. In application, these questions overlap.”); see also
Ceradyne, Inc. v. United States, 103 Fed. Cl. at 12 n.9; Cardinal Maint. Serv., Inc. v.
United States, 63 Fed. Cl. 98, 106 (2004). “‘[A] cardinal change . . . occurs when the
government effects an alteration in the work so drastic that it effectively requires the
contractor to perform duties materially different from those originally bargained for.’”
AT & T Commc’ns, Inc. v. Wiltel, 1 F.3d at 1205 (quoting Allied Materials & Equip. Co. v.
United States, 215 Ct. Cl. 406, 409, 569 F.2d 562, 563-64 (1978)); see also Krygoski
Constr. Co. v. United States, 94 F.3d at 1543. “Just as the cardinal change doctrine
prohibits an agency from compelling a contractor to perform contract terms that are not
within the scope of the original bargain, the CICA prevents an agency from modifying a
contract to such an extent that the modified contract is ‘materially different’ from the
contract for which a competition was held.” GraphicData, LLC v. United States, 37 Fed.
Cl. 771, 781 (1997) (citing AT & T Commc’ns, Inc. v. Wiltel, Inc., 1 F.3d at 1205); see
also Mgmt. Solutions & Sys., Inc. v. United States, 75 Fed. Cl. 820, 830 (2007); cf.
Solute Consulting v. United States 103 Fed. Cl. at 793 (discussing the merits of the
GAO’s application of the “material difference standard” to multiple-award contracts and
its conclusion that “‘[t]he analysis of whether a task order is outside the scope of a
multiple-award contract is the same as the analysis of whether a contract modification is
outside the scope of a single-award contract’” (alteration in original) (quoting DynCorp
Int’l LLC, B-402349, 2010 CPD ¶ 59, 2010 WL 893517, at *4 (Comp. Gen. Mar. 15,
2010))).
In determining whether a contract, as modified, is “materially different,” a court
should “first focus on the modification in the context of the original procurement” and
then determine “the expectations of potential offerors.” See RN Expertise, Inc. v. United
States, 97 Fed. Cl. at 473-74 (citing AT & T Commc’ns, Inc. v. Wiltel, Inc., 1 F.3d at
1205, 1207). The analysis of whether a contract modification “materially departs from
the scope of the original procurement. . . . focuses on the scope of the entire original
procurement in comparison to the scope of the contract as modified.” AT & T
Commc’ns, Inc. v. Wiltel, Inc., 1 F.3d at 1205. “Thus a broad original competition may
validate a broader range of later modifications without further bid procedures.” Id. at
1205. To determine whether a modification is within the scope of the original
procurement, a court should consider whether the modification “substantially changes
‘the type of work, performance period, and costs as between the original contract and
the modified contract.’” CESC Plaza Ltd. P’ship v. United States, 52 Fed. Cl. at 93
(quoting CCL, Inc. v. United States, 39 Fed. Cl. 780, 791 (1997)); see also Cardinal
Maint. Serv., Inc. v. United States, 63 Fed. Cl. at 106 (noting that the question of
whether “the contract, as modified, is materially different from the contract that was
originally competed . . . turns on whether the original contract, as modified, calls for
‘essentially the same performance’” (quoting Exec. Bus. Media, Inc. v. United States
Dep’t of Defense, 3 F.3d 759, 763 n.3 (4th Cir. 1993))); Northrop Grumman Corp. v.
United States, 50 Fed. Cl. 443, 466 (2001) (describing factors that courts have
considered under the cardinal change doctrine, including “[c]hanges in the type of
product or service that were not anticipated due to their lack of resemblance to the
original procurement,” “[s]ignificant addition or subtraction of the quantity of work,” and
“[a]dditional time spent on performance of a contract . . . when such time is extended in
order to add significantly more quantity or new requirements to the contract.”).
“Because every situation in which parties enter into a contractual relationship is
unique, there is no definitive test for determining whether a change is beyond the scope
of a particular contract.” Keeter Trading Co. v. United States, 79 Fed. Cl. 243, 260
(2007) (citation omitted); see also Rumsfeld v. Freedom NY, Inc., 329 F.3d 1320, 1332
(Fed. Cir.), reh’g and reh’g en banc denied, 346 F.3d 1359 (Fed. Cir. 2003), cert.
denied, 541 U.S. 987 (2004) (“The finding of a cardinal change is ‘principally a question
of fact’” (quoting Allied Materials & Equip. Co. v. United States, 215 Ct. Cl. at 411, 569
F.2d at 565)); Golden Mfg. Co., Inc. v. United States, 2012 WL 4479422, at *10 (“In
emphasizing that there is no mechanical or arithmetical answer, we have repeated that
(t)he number of changes is not, in and of itself, the test[.]” (alterations in original)
(quoting Air-A-Plane Corp. v. United States, 187 Ct. Cl. 269, 276, 408 F.2d 1030, 1033
(1969))); ThermoCor, Inc. v. United States, 35 Fed. Cl. 480, 490 (1996) (“‘Each case
must be analyzed on its own facts and in light of its own circumstances, giving just
consideration to the magnitude and quality of the changes ordered and their cumulative
effect upon the project as a whole.’” (quoting Wunderlich Contracting Co. v. United
States, 173 Ct. Cl. 180, 194, 351 F.2d 956, 966 (1965))).
In addition, as indicated by the Federal Circuit, a factor to consider when
determining the scope of the original competition is “‘whether the solicitation for the
original contract adequately advised offerors of the potential for the type of changes
during the course of the contract that in fact occurred, or whether the modification is of a
nature which potential offerors would reasonably have anticipated.’” AT & T Commc’ns,
Inc. v. Wiltel, Inc., 1 F.3d at 1207 (quoting Neil R. Gross & Co., Inc., B-237434, 90-1
CPD ¶ 212, 1990 WL 269546, at *294 (Comp. Gen. Feb. 23, 1990) (citation omitted));
see also RN Expertise, Inc. v. United States, 97 Fed. Cl. at 474; Chapman Law Firm
Co. v. United States, 81 Fed. Cl. 323, 327 (2008). “A modification generally falls within
the scope of the original procurement if potential bidders would have expected it to fall
within the contract’s changes clause.” AT & T Commc’ns, Inc. v. Wiltel, Inc., 1 F.3d at
1205. Whether potential bidders would have anticipated a particular modification is
judged under an objective standard, see Global Computer Enters., Inc. v. United States,
88 Fed. Cl. 52, 56 (2009); CESC Plaza Ltd. P’ship v. United States, 52 Fed. Cl. at 93
(citing CCL, Inc. v. United States, 39 Fed. Cl. at 791), and “depends heavily on the
language of the solicitation.” See Northrop Grumman Corp. v. United States, 50 Fed.
Cl. at 466 (citing John Cibinic, Jr. & Ralph C. Nash, Jr., Administration of Government
Contracts 389 (3d ed. 1995)). If a court ultimately finds a modification “to be outside the
reasonable expectations of the bidders, the government must show that it adequately
advised the bidders that such a change might occur.” Id. at 465 (citation omitted).
(sections deleted)
Although plaintiff argues that the September 22, 2011 request for additional items
was a “competitive negotiated procurement,” the administrative record does not support
plaintiff’s position. The title of the September 22, 2011 request for additional items
stated that it was intended to add items to the September 10, 2009 solicitation, and
specifically identified that solicitation by number: “Addition of Items to Solicitation
SPM1C1-08-R-0153 for Coats, All-Weather, Various, Men and Women, Indefinite
Delivery Type Contract.” Furthermore, the September 22, 2011 request invoked the
Add/Delete Clause included in the 2009 solicitation as the basis for the manner of
procurement of the new items, and explained that DLA intended to add Items 0006 and
0007 to either Bluewater’s or American Apparel’s contract. Using the procedures
described in the referenced Add/Delete Clause, “bilateral modification with negotiated
prices,” the agency asked both contractors to submit price proposals for the additional
items. The defendant explained at the oral argument, “the United States had a
contractual right to modify this contract without using nonprice factors or CICA
requirements,” because “competition requirements were addressed in 2009 when these
contracts were originally awarded.” Both Bluewater and American Apparel were
selected after the 2009 and 2010 full and open competition, with the agency considering
the technical evaluations of the factors described above in addition to price for the allweather
coats for each of the offerors, including American Apparel and Bluewater. The
all-weather coat contracts awarded to Bluewater and American Apparel on December
22, 2010 were “similar in kind and complexity” to the items to be added to the
procurement “on a post-award basis via Add/Delete Clause” to contractors able to
supply additional coats.
The objective of the September 10, 2009 solicitation was defined as the
procurement of “Coats, All Weather, Various, Mens and Womens.” The items solicited,
at the time, were Item 0001, “PGC 02850 Coat, All Weather, Marine Corp Men’s,” Item
0002, “PGC 02851 Coat, All Weather, Marine Corp Women’s,” Item 0003, “PGC 02110
Coat, All Weather, Army Women’s,” Item 0004, “PCG 01940 Coat, All Weather, Navy
Men’s,” and Item 0005, “PGC 01908 Coat, All Weather, Navy Women’s.” The agency
also indicated, in its August 10, 2009 pre-solicitation Initial Procurement Synopsis that
three additional all-weather coats “may be added on a post-award basis via Add/Delete
Clause,” listing them specifically as “PGC 02111 Army, Men’s, Coat, All Weather,” “PGC
01958 Air Force Men’s, Coat, All Weather,” and “PGC 01959 Air Force Womens, Coat,
All Weather.”
The Add/Delete Clause included in the September 10, 2009 solicitation and
incorporated by reference into Bluewater’s contract stated, in pertinent part:
(b) New items may be added to the contract through bilateral modification
with negotiated prices. All new requirements are subject to synopsis prior
to addition to the contract.
The Add/Delete Clause appears on page 56 of the original September 10, 2009
solicitation, under the section “52.216-9006 Addition/Deletion of Items,” including the
following:
As prescribed in 16.506(90), insert the following clause:
ADDITION/DELETIONS OF ITEMS (AUG 2005) – DLAD.
* * *
b) New items may be added to the contract
through bilateral modification with negotiated prices. All new
requirements are subject to synopsis prior to addition to the
contract.
Plaintiff argues that in the context of the entire solicitation, including the terms of
the September 10, 2009 solicitation for the Items 0001 through 0005, as well as DLAD
16.506(90), application of the Add/Delete Clause, the process of addition or deletion of
“items covered by the contract,” must comply with competition requirements. Plaintiff
maintains that the phrase contained in DLAD 16.506(90)(1) “[c]ompetition requirements
must be addressed before new items may be added to a contract” supports its case.
Defendant, on the other hand, asserts that “to the extent the language [of the DLAD
16.506(90)] applied to the Addition / Deletion clause,” in-scope modifications are not
subject to CICA requirements.
The Add/Delete Clause was invoked in the context of the August 10, 2009, presolicitation
Initial Procurement Synopsis, issued by the agency, which announced the
agency’s intention to issue the solicitation and indicated that three more coats
potentially could be added to the procurement “on a post award basis:” Army Men’s, Air
Force Men’s and Air Force Women’s all-weather coats.
The Clause includes the following language:
In accordance with DLAD Clause 52.216-9006, Addition/Deletion of Items,
found on page 56 of the subject Solicitation SPM1C1-08-R-0153, the
attached Items 0006 and 0007 for the Air Force/Coast Guard Men and
Women All-Weather Coats are being solicited for addition to either the
Universal All Weather Coat Contract SPM1C1-10-D-1099 or SPM1C1-10-
D-1100.
Offers will be evaluated based on price only . . . . All other terms and
conditions of the offeror’s contract, Contract SPM1C1-10-D-1009 [sic]
and/or SPM1C1-10-D-1100 remain in effect and apply to the addition of
items.
The September 22, 2011 corrected request for additional items not only
referenced the Add/Delete clause in the 2009 solicitation, but also indicated that “[a]ll
other terms and conditions of the offeror’s contract . . . remain in effect and apply to the
additional items.” The September 22, 2011 request included technical data for the new
coats and stated that the coats were “considered to be within the scope of the universe
of all-weather coats as they [were] similar in kind and complexity to all weather coat(s)
under the Universal All-Weather Coat Contracts.” Price offers for the new coats were
requested from American Apparel and Bluewater. The May 13, 2011 DLA-FQCB Memo
for Record stated “price will be the determining facts to the addition of items.”
To determine whether the addition of Items 0006 and 0007 for Air Force/Coast
Guard Men’s and Women’s All-Weather Coats were modifications or should have
resulted in new competitive procurements requires a comparison of what occurred in
this case in 2009 and 2011. Although the competition goals of CICA are a critical part
of the government procurement framework, so is the modification process, if the
procurement system is to function efficiently. See AT & T Commc’ns, Inc. v. Wiltel, Inc.,
1 F.3d at 1205, 1205 n.1 (noting, with respect to CICA, that “Congress did not intend to
prevent contract modification”). This is why “only modifications outside the scope of the
original competed contract fall under the statutory competition requirement[s]” of CICA.
Id. at 1205.
Based on the language of the Add/Delete Clause, in addition to the earlier
indication in the August 10, 2009 pre-solicitation Initial Procurement Synopsis that three
additional items could be included in the contracts ultimately awarded to Bluewater and
American Apparel, later identified as all-weather coats Items 0006 and 0007 for
additional branches of the United States military, the court determines that what
occurred in this case in 2011 was a modification to Bluewater’s contract, No. SPM1C1-
10-D-1100, that was within the scope of the original procurement. The original
September 10, 2009 solicitation, listed five different coats as “items:” Marine Corp coats
for men and women, Navy coats for men and women, and Army coats for women. The
February 18, 2011 and September 22, 2011 requests for additional items added the
same type of coats, with somewhat different specifications, but only slightly varying
types of functionally similar all-weather military coats. Moreover, Item 0006, “PGC
01958 Coat, All Weather, Air Force/Coast Guard Men’s” and Item 0007, “PGC 01959
Coat, All Weather, Air Force/Coast Guard Women’s,” were “items” contemplated by the
agency at the time of original September 10, 2009 solicitation SPM1C1-08-R-0153, as
evidenced by the August 10, 2009 pre-solicitation Initial Procurement Synopsis.
The line items solicited pursuant to the original procurement, and awarded to Bluewater and American Apparel on December 22, 2010, and the items added to
Bluewater’s contract on April 18, 2012, after reviewing price offers from American
Apparel and Bluewater, were, as described by DLA, “similar in kind and complexity:” allweather
coats for the various branches of the United States military. See The May 13,
2011 DLA-FQCB Memo for Record; Combined Pre-Negotiation Briefing Memorandum
(PBM)/Price Negotiation Memorandum (PNM)/Price Analysis. The fact that the agency
designated Items 0006 and 0007 as all-weather coats for “Air Force/Coast Guard,”
indicating that they could be used by either of the two branches, confirms the similarity
of the coats, and reinforces that the “items” procured by the agency pursuant to the
September 10, 2009 solicitation and September 22, 2011 notice are of similar kind and
complexity. In fact, the government decided that there was no need to change any of
the contracts terms upon the addition of the new items. “[T]he scope of the entire
original procurement in comparison to the scope of the contract as modified,” therefore,
indicates that Bluewater’s contract, as modified, did not “materially depart[] from the
scope of the original procurement.” AT & T Commc’ns, Inc. v. Wiltel, Inc., 1 F.3d at
1205.
As stated in AT & T Communications, Inc. v. Wiltel, Inc.:
An important factor in determining the scope of the original competition is
“whether the solicitation for the original contract adequately advised offerors of the potential for the type of changes during the course of the
contract that in fact occurred, or whether the modification is of a nature
which potential offerors would reasonably have anticipated.”
Id. at 1207 (quoting Neil R. Gross & Co., 90–1 CPD ¶ 212, 1990 WL 269546, at *3
(citation omitted)). Because the Add/Delete Clause, in conjunction with the presolicitation
Initial Procurement Synopsis, envisioned the addition of similar items, and
both existing contractors were offered the same opportunity to submit price quotes to
add one or both of the additional items to their existing contracts, American Apparel
“‘would reasonably have anticipated’” the addition of Items 0006 and 0007 to either
contract awarded under the original September 10, 2009 solicitation. See id. at 1207
(quoting Neil R. Gross & Co., 90–1 CPD ¶ 212, 1990 WL 269546, at *3 (citation
omitted)). The pre-solicitation Initial Procurement Synopsis “adequately advised”
American Apparel that items, such as Items 006 and 007, may be added to a contract
awarded under the original September 10, 2009 solicitation. See Northrop Grumman
Corp. v. United States, 50 Fed. Cl. at 465.
The most difficult part of the assessment in the instant case is that, in addition to
a comparison of the type of work contemplated by the original procurement and the type
of work contemplated by a contract modification, or a comparison between services or
products procured under the original procurement and those added by a contract
modification, courts also consider whether a contract modification significantly increases
the costs of the contract, as compared to the original procurement. See Cardinal Maint.
Serv., Inc. v. United States, 63 Fed. Cl. at 106; CESC Plaza Ltd. P’ship v. United
States, 52 Fed. Cl. at 93. Some price increase certainly is to be anticipated with the
addition of new items for production. By addition of Items 0006 and 0007, the total
annual estimated amount of Bluewater’s contract for Item 0001 was increased by
“$17,187,887.08 from $20,016,708.00 to $37,204,592.08 [sic].”23 Although Bluewater’s
estimated contract price increased by approximately $17,187,887.08, the nature of the
items procured under Bluewater’s contract remained the same. The Weighted Average
Price per unit for Items 0006 and 0007 was, respectively, [deleted] and [deleted], which
was near the average of the Weighted Average Price per unit for Items 0001 through
0005, demonstrating that Items 0006 and 0007 were similar in price, and presumably
quality, to Items 0001 through 0005. This is consistent with DLA’s statement that Items
0006 and 0007 were “considered to be within the scope of the universe of all-weather
coats as they are similar in kind and complexity to the all-weather coat(s) under the
Universal All-Weather Coat Contracts.”
As indicated in Golden Manufacturing Co., Inc. v. United States, 2012 WL
4479422, at *14, it is not simply a matter of arithmetic calculations. In cases that apply
the cardinal change doctrine, even a substantial price increase alone is not enough to
establish that modifications are beyond the scope of a contract, as long as the nature
and purpose of the contract has not changed. See, e.g., S. J. Groves & Sons Co. v.
United States, 228 Ct. Cl. 598, 602, 661 F.2d 170, 173 (1981); Def. Sys. Grp., B-
240295, 1990 WL 293536 (Comp. Gen. Nov. 6, 1990) (a 120 percent increase in price
was not a cardinal change because the nature and purpose of the contract had not
changed). In contrast, in circumstances where a large price increase is accompanied
by a substantial change in the nature of work contemplated by a contract, courts have
deemed a contract modification to be a cardinal change. See Golden Mfg. Co., Inc. v.
United States, 2012 WL 4479422, at *14 (quoting Cardinal Maint. Serv., Inc. v. United
States, 63 Fed. Cl. at 109) (“Where, as here, the amount of additional work nearly
doubles the price of the contract that was awarded, and the nature of the work was so
substantially increased that the change provision of the contract had to be deleted to
accomplish the modifications, the originally awarded contract has been materially
changed.”).
In the case currently before the court, the nature and purpose of the work
contemplated by the original September 10, 2009 solicitation, to provide servicemember
coats, remained unchanged. The agency consistently announced the
contract’s intended purpose, once in the September 10, 2009 solicitation, and again in
the February 18, 2011 request for additional items, which remained constant in the
September 22, 2011 request for additional items. The December 22, 2010 awards of
contract Item 0001 to Bluewater, and contract Items 0002-0005 to American Apparel
were made after evaluation of the product demonstration model (PDM), past
performance/experience, and socioeconomic considerations. Both Bluewater and
American Apparel, therefore, had gone through the entire evaluation process, and had
been vetted and approved after a full and open competition prior to receiving the
December 22, 2010 awards. The time to challenge those evaluations conducted by the
agency is long past due.
The all-weather coats added to Bluewater’s contract in 2012 are in the nature of
modifications forecast in the 2010 contract between the defendant and Bluewater, and
within the scope of the September 10, 2009 solicitation. Specifically, the items added to
the Bluewater contract by DLA following the September 22, 2011 request did not differ
materially from the other all-weather coats procured as a result of the September 10,
2009 solicitation. As stated by the agency in the May 13, 2011 DLA-FQCB Memo for
Record; Combined Pre-Negotiation Briefing Memorandum (PBM)/Price Negotiation
Memorandum (PNM)/Price Analysis:
The Air Force Man and Woman All-Weather Coats are considered to be
within the scope of the universe of all-weather coats as they are similar in
kind and complexity to the all-weather coat(s) under the Universal All-
Weather Coat Contracts. These additional items were also included in the
synopsis of subject Universal AWC solicitation.
The addition of Item 0006, “PGC 01958 Coat, All Weather, Air Force/Coast Guard
Men’s” and Item 0007, “PGC 01959 Coat, All Weather, Air Force/Coast Guard
Women’s,” to the existing Bluewater’s Contract No. SPM1C1-10-D-1100, was an inscope
modification pursuant to the Add/Delete Clause also included as part of the 2009
solicitation and, therefore, not a material departure from the original procurement.
(American Apparel, Inc., v. U. S. and
Bluewater Defense Inc., No. 12-293C, December 14, 2012)
(pdf)
In determining whether a modification is outside the scope of
the original government
contract, the Court applies the “cardinal change doctrine.”
Wiltel, 1 F.3d at 1205 (noting that
CICA sets forth no standard for determining when a modification
is within the scope of the
original contract). “[A] cardinal change . . . occurs when the
government effects an alteration
in the work so drastic that it effectively requires the
contractor to perform duties materially
different from those originally bargained for.” Id. If the
contract as modified materially
departs from the scope of the original procurement, then CICA’s
competition requirements
will apply. See, e.g., CWT/Alexander Travel, Ltd. v. United
States, 78 Fed. Cl. 486, 494
(2007); HDM Corp. v. United States, 69 Fed. Cl. 243, 254 (2005).
In its analysis, the Court
should look to whether the original offerors were adequately
advised of the potential for the
types of changes that in fact occurred, and “whether the
modification is of a nature which
potential offerors would reasonably have anticipated.” Wiltel, 1
F.3d at 1207 (quoting Neil
R. Gross & Co., B-237434, 90-1 CPD ¶ 212 at 3 (February 23,
1990)).
In the present
case, Chapman does not dispute that the nature of the work in
the proposed modifications would require incumbent contractors to
provide the same M&M
services in Ohio or Michigan as they currently provide under
their existing contracts in other regions. See AR 20-21. The only
changes at issue here are the geographic expansion of
service and the possibility of new pricing. Deft.’s Motion at
12-13. These two changes
clearly were contemplated in the M&M contracts. Clause H.2,
found in every M&M
contract, including the four contracts selected for
modification, expressly allows HUD to
“unilaterally increase the geographic service areas of this
contract, by contract modification.”
AR 6. Clause H.2 also provides that if the modification causes a
change in the price, the
contractor may assert its right to an equitable adjustment. Id.
All of the contractors,
including Chapman and the contractors selected for the
modification, reasonably should have
anticipated the potential for precisely the kind of modification
that HUD seeks to make.
In an attempt to avoid HUD’s
express contractual authority to make the proposed
modifications, Chapman argues that actions which would otherwise
constitute a modification
nevertheless become solicitations for new contracts when the
Government shops around for
the best incumbent contractor. Pltf.’s Brief at 6. However,
Chapman’s argument misses the
mark. When applying the cardinal change doctrine, the Court
focuses on the nature of the
work to be done and whether the modification is one which
existing contractors reasonably
should have anticipated. See Wiltel, 1 F.3d at 1205, 1207. If
the nature of the work under
the modified contracts is not materially different, and the
contractors were adequately
advised of the potential for the change that in fact occurred,
the modification is within the
scope of the original contract. The Court will not impose
additional restrictions on how an
agency chooses to modify existing contracts. HUD believed it
would be advantageous to
research potential pricing before issuing modifications, rather
than receiving requests for
equitable adjustments after the fact. Deft.’s Motion at 5, n.5.
It is not the business of this
Court to question the wisdom of that approach. Impresa
Construzioni Geom. Domenico
Garufi v. United States, 238 F.3d 1324, 1332-33 (Fed. Cir.
2001)(“[C]ontracting officers are
entitled to exercise discretion upon a broad range of issues
confronting them in the
procurement process”); Bender Shipbuilding & Repair Co. v.
United States, 297 F.3d 1358,
1362 (Fed. Cir. 2002) (deferring to “informed, complicated
business judgment” of
contracting officer).
In any case, HUD’s selection of
the limited pool of eligible firms was hardly random.
As is noted in the record, HUD compiled a list of all incumbent
contractors and narrowed the
field to four firms according to past performance ratings and
capacity. AR 14-19. It is
entirely sensible that, having a ready list of incumbent
contractors, HUD would seek to know
which of them could accommodate the additional work at the
lowest possible cost to the
Government. In this way, HUD assured itself of securing not only
a low price, but also a
contractor familiar with the work to be done. If HUD decided, as
it apparently has, that it
is in some way preferable to modify an existing contract than to
create a new one, the Court
must show deference to that determination as long as the
modification remains within the
scope of the original contract. See, e.g., R & W Flammann GmbH
v. United States, 339 F.3d1320, 1322 (Fed. Cir. 2003) (“[w]hen
an officer’s judgment is reasonable, a court may not
substitute its judgment for that of the agency.”). As discussed
above, the modifications were
within the scope of the original contracts.
Finally, Chapman argues that it
should have been included among the list of potential
contractors, and if it had been included and fairly evaluated,
it would have received the work
covered by the modifications. Unfortunately for Chapman, HUD
allowed its contract to
expire on December 31, 2007. Consequently, at the time HUD
developed its list of eligible
firms and requested price proposals from the four selected
contractors, Chapman was not an
incumbent contractor with a contract capable of being modified.
AR 5. (Chapman Law Firm Co., v.
U. S., No. 08-39C, April 2, 2008) (pdf)
The court finds that the delay to the start date and the alleged
price modifications do
not amount to a “cardinal change” or other violation of CICA.
The plaintiffs’ allegations
are most similar to those brought by the plaintiffs in CESC
Plaza, in which the protestors
argued that “the sum of the changes materially alter[ed] the
contract, not that the specific
changes themselves [were] out of scope modifications.” CESC
Plaza, 52 Fed. Cl. at 94.
In CESC Plaza, the court held that the plaintiffs would be
required to demonstrate that the
sum of the modifications were “materially outside the scope of
the [solicitation] and that
these modifications were not foreseeable to the bidders.” Id.
The court adopts the test
articulated in CESC Plaza and holds that the plaintiffs in this
case cannot prevail on their
CICA violation or cardinal change claims because they cannot
demonstrate that the delays
in commencement of the contracts or the possible price increases
are materially outside the
scope of the contracts and were not foreseeable to the offerors.
First, as the government notes, the solicitation did not specify
a definite start date
for commencement of performance or specific dates between which
the base performance
period had to be completed. Instead, the solicitation stated
that “the base ordering period
begins with the issuance of a contract modification for
commencement of services through
24 consecutive months” and that three additional one-year option
periods could be
exercised by the government. AR 5. Thus, the solicitation
contemplated only that the
contract would start at some time after the award date. In such
circumstances, the
plaintiffs’ reliance on the GAO decisions in Defense Sys. Group
and Ingersoll-Rand,
which involved the requirement for performance by specific
dates, is misplaced. In
addition, where as here, the solicitation did not confine the
base period of performance to a
set time period expiring on April 1, 2007, the court will not
read set dates into the
contracts. Where flexibility has been incorporated into the
solicitation, the court must
respect that determination. See AT&T, 1 F.3d at 1205.
Second, the proposed price modifications are not enough alone or
in combination
with the commencement date modifications to establish a cardinal
change or violation of
CICA. The solicitation contemplated price changes and authorized
price negotiations to
deal with changes in ticket volume requirements and technology.
Indeed, given the nature
of the travel services required under the contract, price
changes were viewed as inevitable.
The government has limited control over the number of recruits
or the location of recruits
needing travel services. Thus, authorization for price changes
in what was otherwise a
fixed-price contract was written into the solicitation to meet
the Army’s needs. Price
changes were therefore both authorized and foreseeable.
Moreover, plaintiffs’ contentions
regarding the size of any price change are unsubstantiated, as
no major price modifications
have been issued. The plaintiffs have failed to establish that
the delay will, in fact, result
in any significant cost increase to the government. (CWT/Alexander
Travel, LTD, and CWT/EL Sol Travel, Inc., v. U. S., No.
07-612C, Filed October 2, 2007) (pdf)
Tested by the standards set forth in the above-cited cases, the
court finds that the
addition to, and deletion of work from, the Navales contract
materially changed the original
competed contract. The changes to the Navales contract were not
changes of the type that
were specifically authorized or even foreseen in the original
contract. Rather, the modifications authorized substantial
changes, which the contracting officer identified as
“considerable” with costs that were potentially “extremely
excessive.” AR at 4871. The
Navales contract contemplated “minimal additions and deletions
of service” which would
be accomplished through application of the Add/Delete of Service
Cost Sheet, set forth in
Section 1.6 of the solicitation. The modifications to the
Navales contract were not,
however, made through this provision. Instead, the contracting
officer concluded that the
Air Force needed to remove the Add/Delete of Service Cost Sheet
from the Navales
contract to make the changes the Air Force wanted. Specifically,
the contracting officer
explained:
It was determined in the best interest of parties, the
government and contractor,
for this pricing structure [the Add/Delete of Service Cost
Sheet] to be deleted
by modification and all future modifications to be accomplished
through
negotiation. . . . Had the price sheet been used it would have
resulted in
extremely excessive costs bordering changes outside the scope of
the contract.
AR at 4871 (emphasis added).
In other words, the Air Force
deleted the Add/Delete of
Service Cost Sheet clause in the Navales contract, which
authorized only minor changes, in
order to make future major modifications. The Air Force feared
that if it did not do this,
then the excessive costs would “border[ on] changes outside the
scope of the contract.” AR
at 4871 (emphasis added).
The Air Force’s decision to modify the Add/Delete of Service
Cost Sheet of the
original contract, in order to avoid changing the “scope of the
contract” was not sufficient
to overcome CICA’s mandates. The government cannot circumvent
CICA by modifying a
contract to allow for modifications that were not originally
within the scope of the
contract. Northrop Grumman, 50 Fed. Cl. at 464. This would
defeat the language and
purpose of CICA. Accordingly, where, as here, the government
modified the contract to
allow for changes not contemplated in the original contract, the
government cardinally
changed the contract; by doing so without resoliciting the
contract, and by instead
eliminating the limitations on changes specifically set forth in
the original contract, the
government violated CICA. Because the government’s procurement
was not in accordance
with law, the court is authorized to overturn this illegal
action. See 5 U.S.C. § 706(2)(A);
28 U.S.C. § 1491(b)(4). (Cardinal
Maintenance Service, Inc., v. U. S. and Navales Enterprises,
Inc., 04-94C, November 22, 2004) (pdf)
In determining whether a modification falls within CICA's competition requirement, this court examines whether the contract as modified materially departs from the scope of the original procurement. . . . The analysis thus focuses on the scope of the entire original procurement in comparison to the scope of the contract as modified. Thus a broad original competition may validate a broader range of later modifications without further bid procedures.
Id. at 1205 (citations omitted).(15) The inquiry with respect to scope is an objective one viewed from the perspective of potential bidders for the original procurement. See id.; CCL, Inc. v. United States, 39 Fed. Cl. at
791.(16) (Phoenix Air Group, Inc. v.
U.S., No. 98-602C, February 18,
2000)
As we held in
CCL v. United States, 39 Fed. Cl. 780, 791 (1997), contract
modifications cannot materially depart from the scope of the original
procurement, otherwise the modification prevents potential bidders from
participating in what should be a new procurement. In this respect it is relevant
to inquire into whether potential bidders at the time of the original contract would
have been on notice that the later modification was within the reasonable scope
of the solicited material or services. (VMC Behavioral Healthcare Services, Division of Vasquez Group,
Inc. v. U.S.,
No. 01-473C, September 18, 2001) (.pdf)
|
|
U.
S. Court of Federal Claims - Listing of Decisions
|
For
the Government |
For
the Protester |
New
Electra-Med, et al., v. U. S.
and American Medical Depot, et al., No. 18-927C,
October 3, 2018. |
Chapman Law Firm Co., v. U. S.,
No. 08-39C, April 2, 2008 (pdf) |
Schott Government Services, LLC v. U.
S. and Oran Safety Glass, Nos. 15-616C, 15-617C, 15-618C,
15-619C, 15-620C, September 17, 2015 (pdf) |
Cardinal Maintenance Service, Inc., v.
U. S. and Navales Enterprises, Inc., 04-94C, November 22, 2004
(pdf) |
Aircraft Charter Solutions, Inc. v. U.
S. and DynCorp International LLC, No. 13-9C, March 8, 2013
(pdf) |
|
American Apparel, Inc., v. U. S. and
Bluewater Defense Inc., No. 12-293C, December 14, 2012
(pdf) |
|
CWT/Alexander Travel, LTD, and CWT/EL
Sol Travel, Inc., v. U. S., No. 07-612C, Filed October 2, 2007
(pdf) |
|
CESC
Plaza Limited Partnership, et al., v. U.S., No. 01-715C,
March 22, 2002 (pdf) |
|
Northrop
Grumman Corporation, v. U. S. and Raytheon; Lockheed Martin
Corporation Naval Electronics and Surveillance Systems, v. U. S.
and Raytheon, Nos. 00-306C and 00-367C, October 4,
2001 (pdf) |
|
Phoenix Air Group, Inc. v.
U.S., No. 98-602C, February 18,
2000 |
|
VMC Behavioral Healthcare Services, Division of Vasquez Group,
Inc. v. U.S.,
No. 01-473C, September 18, 2001 (.pdf) |
|
|
|