Posted January 8Jan 8 comment_90641 Can a GC claim extended field overhead for an agreed upon delay where operations on the critical path were disrupted due to differing site conditions, but they continued to work on non-critical path activities? A suspension of work was not issued.
February 26Feb 26 comment_91131 On 1/8/2025 at 4:57 PM, It_Dependsss said: Can a GC claim extended field overhead for an agreed upon delay where operations on the critical path were disrupted due to differing site conditions, but they continued to work on non-critical path activities? A suspension of work was not issued. Just saw a notice of this new topic this morning in my Denali. In response, based upon the limited information in the original post: If the contract completion date has been extended due to delays to the critical path to completion due to a DSC, it would appear that some form of extended field office overhead would be allowable.