Posted October 16, 201311 yr comment_19474 I am attempting to validate as to whether or not a Prime, if awarded a FFP contract, may issue a FFP-LOE SubK knowing the work that is to be performed by the subcontractor will exceed the $150k limitation per FAR 16.207.3 (Limitations of firm-fixed-price, level-of-effort term contracts)? Thank you in advance for your time.
October 17, 201311 yr comment_19476 The limitation in FAR does not apply to contractors and to the award of subcontracts. It limits the Government's use of FFP-LOE contracts, not a contractor's use.