Jump to content
  • Search By Tags

    Type tags separated by commas.
  • Search By Author

Content Type

Forums

  • Instructions, Terms of Use, Q&A, Commentary, Opinions & Debates
    • Terms Of Use
    • Before You Register, Before You Post, Instructions for Writing Your Question
    • Q&A
    • Commentary, Opinions & Debates
  • Contracting Forum
    • WIFCON PODCAST
    • What Happened?
    • Polls
    • For Beginners Only
    • About The Regulations
    • COVID-19 And Its Effect on Contracting
    • Contracting Workforce
    • The Good, The Bad, the Ugly
    • Recommended Reading
    • Contract Award Process
    • Contract Pricing Including CAS & Allowable Costs
    • Contract Administration
    • Schedules, GWACS, MACs, IDIQs
    • Subcontracts & Subcontract Management
    • Small Business, Socioeconomic Programs
    • Proposed Law & Regulations; Legal Decisions
  • Contest

Blogs

  • The Wifcon Blog
  • Don Mansfield's Blog
  • Emptor Cautus' Blog
  • SmallGovCon.com
  • NIH NITAAC Blog
  • The Contractor's Perspective
  • Government Contracts Legal Forum
  • Government Contracts Blog
  • Government Contracts Insights
  • NIH NITAAC Blog
  • High-Performance Track Systems | iAutomation

Calendars

  • Community Calendar

Product Groups

There are no results to display.

Categories

  • Rules & Tools
  • Legal Opinions
  • News

Find results in

Find results that contain...

Date Created

  • Start

    End

Last Updated

  • Start

    End


Filter by number of...

Found 1 result

  1. Background: My co-worker and I disagree on a matter and I am looking for clarification to see if I am missing something. I am processing a modification for said co-worker to extend the Period of Performance only. The award was made for services as a FFP PO inclusive of 52.212-4. No other changes clauses were included. My co-worker wants to pursue issuance of a unilateral change order citing FAR 43.202 as the authority. My inclination is it is not permissible to issue a unilateral change order to the contract as the changes clauses included specifically states “Changes in the terms and conditions of this contract may be made only by written agreement of the parties.” Based on 52.212-4, it seems to me that it would be a breach of contract terms on the Government’s part if the CO were to issue a unilateral change order on this contract. Questions: Does the FAR permit issuance of a unilateral change order extending the Period of Performance end date under a Firm-Fixed-Price Purchase Order for services containing 52.212-4 and no other changes clauses? Does FAR 43.202 give Contracting Officers the authority to issue a unilateral change order against any contract? Is it permissible to cite FAR 43.202 as the authority?