Rachel_CO Posted June 11, 2021 Report Share Posted June 11, 2021 In what circumstances would a CO use a CPFF task order with CPFF option line items instead of incrementally funding a CPFF task order for a two-year systems engineering requirement when funding is allotted for only one year at a time? I am unfamiliar with the use of cost-type options and what advantage they offer. Link to comment Share on other sites More sharing options...
Vern Edwards Posted June 12, 2021 Report Share Posted June 12, 2021 Is the work for a capital project or is it severable support? Link to comment Share on other sites More sharing options...
Rachel_CO Posted December 2, 2021 Author Report Share Posted December 2, 2021 Let's assume for the purpose of this question that the requirement is for severable services. Link to comment Share on other sites More sharing options...
ji20874 Posted December 2, 2021 Report Share Posted December 2, 2021 Severable services? My first thought would be to use an option for the second year. Link to comment Share on other sites More sharing options...
Recommended Posts