I have been advised that an emergency construction contract for forest debris removal was awarded (>$150K) and the contractor began performance without providing bonds IAW the Miller Act. The contract did not contain a requirement to provide bonding and the work is currently in progress.
The Miller Act requires that payment and performance be submitted before receiving a notice to proceed with the work or being allowed to start work.
I believe this could be corrected by modifying the contr