Contractor500 Posted October 28, 2024 Report Share Posted October 28, 2024 The Gov't customer is withholding payment of invoices due to a missing deliverable. This contract is about the resell of a software product. No services involved. Is there a way to resolve this issue so we may receive payment? Thank you. Quote Link to comment Share on other sites More sharing options...
Contractor500 Posted October 28, 2024 Author Report Share Posted October 28, 2024 Apologies, additional information: the resale of the products POP didn't match the Gov't contract POP which is an issue when it comes to a software product. The Gov't POP is 29 September 2023 to 28 September 2024. The software vendors didn't deliver products until Feb 2024, so we didn't receive payments until Feb 2024 Quote Link to comment Share on other sites More sharing options...
here_2_help Posted October 29, 2024 Report Share Posted October 29, 2024 18 hours ago, Contractor500 said: Apologies, additional information: the resale of the products POP didn't match the Gov't contract POP which is an issue when it comes to a software product. The Gov't POP is 29 September 2023 to 28 September 2024. The software vendors didn't deliver products until Feb 2024, so we didn't receive payments until Feb 2024 Are you sure your dates are correct because Feb 2024 is well within the Period of Performance you specified (29 Sept 2023 to 29 Sept 2024). Second, it's nearly impossible for anyone here to assist you without access to the contract and all the facts. In my opinion, you should hire an experienced government contracts attorney. Quote Link to comment Share on other sites More sharing options...
Retreadfed Posted October 29, 2024 Report Share Posted October 29, 2024 Contractor, is the contract one for commercial products with FAR 52.212-4? If it is not for commercial products, how is the contract priced, e.g., cost reimbursement, FFP etc.? Also, I agree with H2H your facts are unclear. Quote Link to comment Share on other sites More sharing options...
Neil Roberts Posted October 30, 2024 Report Share Posted October 30, 2024 (edited) On 10/28/2024 at 12:39 PM, Contractor500 said: he Gov't customer is withholding payment of invoices due to a missing deliverable. Fixed price Government contracts usually do not require the Government to pay for deliverables that are missing. Edited October 30, 2024 by Neil Roberts missing language. sent in error Quote Link to comment Share on other sites More sharing options...