Moderator Posted August 27, 2022 Report Share Posted August 27, 2022 Quote The "'measured mile' approach compares the productivity of an impacted period of the project with the productivity of an unimpacted period," Advanced Engineering & Planning Corp., ASBCA Nos. 53366, 54044, 05-1 BCA ,i 32,806 at 162,325. Here are examples of how is it used. See Lockheed Martin Aeronautics Company v. U. S., ASBCA No. 62209, August 3, 2022. Also see King Aerospace, Inc., ASBCA No. 60933, 19- 1 BCA ¶ 37,316. Link to comment Share on other sites More sharing options...