_KB_ Posted August 9, 2022 Report Share Posted August 9, 2022 Is there any hard restriction in the FAR or other govt regulation restricting weekend work? We have a CO who is questioning why work was done on the weekend, although there is no language in our contract that expressly restricts it. Link to comment Share on other sites More sharing options...
ji20874 Posted August 9, 2022 Report Share Posted August 9, 2022 Fixed-price, cost-reimbursement, or T&M/LH? What is the nature of the work? Link to comment Share on other sites More sharing options...
here_2_help Posted August 9, 2022 Report Share Posted August 9, 2022 There is no restriction on contractor work hours. However, there may be a restriction on reimbursing the cost of those hours. For example, 52.222-2 may limit payment of overtime premiums. There may also be concerns with uncompensated overtime worked by salaried, exempt, personnel (see 52.237-10). Generally speaking, the government should not want to manage how the contractor performs its efforts. Link to comment Share on other sites More sharing options...
Vern Edwards Posted August 9, 2022 Report Share Posted August 9, 2022 What do you mean by "weekend work"? Is the worker being paid at overtime rates? Link to comment Share on other sites More sharing options...
C Culham Posted August 10, 2022 Report Share Posted August 10, 2022 19 hours ago, _KB_ said: FAR or other govt regulation restricting weekend work? 15 hours ago, here_2_help said: For example, 52.222-2 may limit payment of overtime premiums. Since OT has come into the discussion a visit to FAR subpart 22.103 in total might help. Note that a normal workweek is defined as a 40 hour period not specific days of the week. Link to comment Share on other sites More sharing options...
_KB_ Posted August 15, 2022 Author Report Share Posted August 15, 2022 Thanks for all the feedback. We were surprised the CO wanted to manage how we are performing that closely as well. If anything, we thought it showed dedication on the part of the employee. The employee took PTO earlier in the week and they wanted to catch up, so they worked a few contract billable hours on Saturday and Sunday so deliverables didn't slip. This is under a cost reimbursement contract type so we are solely invoicing the government for an employee's actual costs regardless of when they perform the work. We don't apply any premiums to these costs. Additionally, our accounting system uses dilution, so even if he were to have worked over 40 hours in a given week to this contract, his effective/adjusted hourly rate would have been calculated lower, and our invoiced amount to the Govt would have been the same as if he had worked 40 hours. Link to comment Share on other sites More sharing options...
here_2_help Posted August 15, 2022 Report Share Posted August 15, 2022 1 hour ago, _KB_ said: Thanks for all the feedback. Seems like you have an opportunity to ask the CO what their concerns are. If the CO doesn't want your company to let its employees work weekends get that direction in writing. Link to comment Share on other sites More sharing options...
ji20874 Posted August 15, 2022 Report Share Posted August 15, 2022 _KB_, a salaried employee, or an hourly-rate employee? Link to comment Share on other sites More sharing options...