

dsmith101abn
-
Posts
65 -
Joined
-
Last visited
Content Type
Profiles
Forums
Blogs
Events
Store
Breaking News
Posts posted by dsmith101abn
-
-
I think it’s a great idea but would be super hard to implement. Maybe scale it down as a phased approach. By that I mean start with a no GAO protests against things the Government isn’t great at, like IT procurements first and then move on from there. I don’t have a roadmap but that would be the idea. Final phase would be eliminate GAO protests.
Also, since GAO recommends the Government cover the protesters costs if the Government loses a protest, maybe GAO also recommends the denied protester covers the Governments cost, inclusive of delay costs, etc. maybe that’s already a thing or just makes further litigation costs I dono just typing outload loud if you will as an alternative.
-
7 minutes ago, dsmith101abn said:
I'm told by my finance/fiscal office there's not a mechanism to pay other federal/state/county/city organizations if there is no SAM registration. System limitation. Whether that applies to other executive agencies I do not know. Whether that is a requirement of any regulation i do not know that ether.
-
20 minutes ago, Oyster said:
Federal agencies don't register in Sam.gov,
Some do. I don't exactly know why but assume there is a reason. My civilian sub agency does. Perhaps I should ask.
-
i dont know what you're doing and i'm not into 20 questions, but did you look through 2 CFR and see if there's something there applicable to your situation? Is checking SAM registration a burden? arbitrary questions.
-
13 CFR 121.404. There might be a FAR reference but i didn't look for it. Always can go to the SBA and let them make that determination. I'm not certain.
-
yeah, my new T-11R didn't deploy. It's been known to happen.
I shouldn't have said what i said. but lol on some of the responses.
-
10 minutes ago, Retreadfed said:
See FAR 33.104 (Procedures for protests to GAO are found at 4 CFR Part 21 (GAO Bid Protest Regulations). In the event guidance concerning GAO procedure in this section conflicts with 4 CFR Part 21, 4 CFR Part 21 governs.) This should answer your other question.
^^^ Thanks.
-
On 3/8/2023 at 7:11 AM, Vern Edwards said:
In such cases, with respect to any protest basis which is known or should have been known either before or as a result of the debriefing, and which does not involve an alleged solicitation impropriety covered by paragraph (a)(1) of this section, the initial protest shall not be filed before the debriefing date offered to the protester, but shall be filed not later than 10 days after the date on which the debriefing is held.
I couldn't get acquisition.gov to open and didn't try any other avenues, but isn't 5 days prescribed in FAR 33, not 10 days?
so if 4 and 48 CFR conflict which one do you follow? I'd gather with a degree of certainty this has happened before.
Another question, since the regulations use the word offered, i could potentially offer a post award debrief 5 days after a written request for one, and if 5 days is the time limitation to protest, the contractor would be untimely in their protest since i didn't give it until day 5? that seems shady but that's what i took away.
-
54 minutes ago, Vern Edwards said:
Don Mansfield and I recently had a conversation about innovation in acquisition and I pointed out that we know very little about whether innovations, such as incentive contracts and performance-based acquisition, word as advertised. Basically, what happens in our business is that when an innovation has been described and adopted it is almost immediately declared to be a success and accepted as such by noncritical thinkers. Rarely do we collect information that would enable us to reach an informed conclusion in that regard. We design, but we don't test.
I took a innovation in contracting class recently. there were about 30 of us. There were more procurement attorneys then 1102's. one of the opening questions was why we wanted to take this class. almost all of the attorneys said they wanted to know where the innovation training was coming from because they had been seeing more garbage (my term) then they where historically used to.
-
Thanks everyone. I'm not going to respond to all the what if's and questions, but I'll leave some final words just to close up the thread.
17 hours ago, joel hoffman said:2-3 months for discussions , revisions, reviews??
Edit: Hard for me to comprehend taking that long.
↓
18 hours ago, dsmith101abn said:8-12 weeks, majority of which is internal Leadtime (a different discussion).
17 hours ago, joel hoffman said:You say you want to award 8-10 ID/IQ’s. But the current universe is seven proposals…
yup, we didn't get enough proposals to make the number of awards we planned on.
I appreciate you trying to flush out the thoughts and details, but in the end with leaving all the gaps in what i haven't explained, i don't think we're at a cardinal change.
14 hours ago, C Culham said:The other thought I had, and again it may be too late, is to seek an individual deviation from FAR 16.505(b)(2) that is stopping your idea.
Overall GSA does it so it seems to me that it can be done even at the point your are now at.
I don't know how long deviations take in most of the Government, but for the few agencies I've worked for, it's not quick. the quicker option had we not planned on a deviation at the beginning would be to resolicited.
GSA is the Tom Brady of federal agencies, GSA gets away with a lot of stuff.
6 hours ago, Vern Edwards said:I do not know of any law or regulation requiring that you award all MATOCs resulting from a single solicitation on the same date with the same period of performance. And see FAR 52.215-1(f)(5).
But, what you do must be consistent with the terms of the solicitation itself.
Off hand, I do not see why you cannot award four contracts now, without discussions, and three more later, after discussions and final proposal revisions. While negotiating with the three, I don't see why you cannot provide fair opportunities to the four.
But check what your solicitation says and the terms of the proposals.
This is the conclusion i gathered and i believe the solicitation allows for some awards now and more after discussions.
I appreciate everyone's time and input. I have nothing further. Dsmith out.
-
Correct.
2 hours ago, Vern Edwards said:So you want to make the PM happy by awarding four contracts now, with three more to follow after discussions and final proposal revisions. Right?
How long do you think discussions and final proposal revisions will take?
I guess a piece of information that would have helped, we're using seed projects to evaluate price, which were solicited with the IDIQs. so not necessarily for just the PM but for the project schedules.
The evaluation criteria, i think, wasn't that complex or hard to understand. I think with discussions, revisions, reviews, 8-12 weeks, majority of which is internal Leadtime (a different discussion).
-
from a project manager standpoint, over a certain $ threshold you have to go to a board, which is one day a month, usually towards the end of the month, and the approval comes a few weeks later, so it's schedule. PM's tend to think their projects are the most important thing in the world.
Our office gets a periodical about contracting stuff, and i disagree with it. what prompted my question was the below, and i don't agree with it.
Nothing Magic about 5 Years, other then prices have changed dramatically over 5 years, and in this particular area, we dont want to limit the experience of other contractors.
-
I have a question where I thought there was a simple answer, and there still may be. I was talking through what I wanted to do with a peer and now I’m not sure on the answer. I know what I can get away with, but looking at the right answer.
I want to award 8-10 IDIQ’s. A solicitation was advertised LPTA and we received 7 proposals, 4 of which were acceptable; however the capacity of 4 contractors most likely would not fulfil our 5 year planned requirements, so I want to negotiate with 3 of the unacceptable offerors and try to give the offerors a chance to cure the deficiencies. I want to award at least one IDIQ now so work can start on a TO and then negotiate with the contractors that had deficiencies in their IDIQ proposals, award those IDIQ’s later, and have different POP among the IDIQ awardees.
So Question, can you have a MATOC with multiple IDIQ contract awardees with different POP’s?
How, if anything, would that affect the fair opportunity requirement?
is that still considered a MATOC?
Do you have different POP for an agency MATOC’s or do you modify the IDIQ’s to have the same POP after negotiations?
What am I not thinking about? Am I making this too hard?
I have an idea what I’m gonna do, but thought I’d ask hoping for non-hostile input.
* I’m not spelling out acronyms. Interpret acronyms as used in common practice.
-
I don't know what GovCons or M&A mean.
-
23 minutes ago, joel hoffman said:
for construction, numerous agencies use the UCF. Many of my non-DoD students in my D-B class over a period of 20 years confirmed that.
Understood, do attachments have a different contract meaning vs being included as part of a contract full text? I know we're talking about C vs H but what about J?
Reason for my quote, I'm non-DOD and i'd like to take a D-B class sometime. If you can let me know what you teach (if you still do) or otherwise recommend I'd appreciate it. I don't do a lot of D/B stuff but once in a while it presents itself.
-
7 hours ago, joel hoffman said:
completely familiar with the CSI format for construction contracts
Some construction industries use this format. others use modified formats, some use the AASHTO format. Maybe unrelated to this forum.
-
O and the survey was focused on our industry specifically.
-
I got an agency protest. First one in a long while. I looked back 6 years and found 3 size standard protests and one agency. We did an informal survey and found most contractors don’t protest because they think we treat them in good faith (my industry is very specific to a certain kind of work).
Weren’t evaluated right, unfair advantage, etc. etc. but if we were more transparent and not so scared to talk to the contractor community would protests chill out?
-
-
On 10/15/2022 at 2:26 PM, ji20874 said:
I have never used these labels in my exchanges with offerors. I regret that some DHS contracting officers think they must.
I'll go even further -- it is not necessary to use these labels even in the internal technical evaluation report. I have led evaluations where we scrupulously avoided using those labels.
On 10/15/2022 at 6:52 PM, Vern Edwards said:Agree.
I'm not saying I disagree, just wanted to clarify if y'all are suggesting labels shouldn't be used or just that labels are not required to be used?
-
o and it wouldn't have to be a prize or award for ever exercise.
-
I'm not a noob but i still looked for the answer and i liked the exercise. would anyone have interest in doing this regularly? i'm thinking exercise of the week like what's the limitation on contractors fee under an A/E contract. i'd guess some people know it but couldn't find the citation.
-
59 minutes ago, C Culham said:
Hope I have helped no matter the approach you and your team decide to take. . Best of luck moving forward.
Thanks Carl.
I especially appreciate the leeway comment. When I had my first kid i was overwhelmed by parent advice, some of people who had young kids, some older kids, some had kids 40 years ago and some with never having kids. To this advice I would say good idea, turn around and do whatever the F i wanted. I appreciate the idea that not one way is correct and the other is wrong and there are options. I feel HQ might be out of touch with the field here! or I'm an idiot, that's a possibility.
That's not to downplay the value of the feedback I've received on this form. It is much appreciated. hopefully nobody's offended.
-
perhaps nothing.
6.305 Availability of the justification.
(a) The agency shall make publicly available the justification required by 6.303-1 as required by 10 U. S.C. 2304(l) and 41 U.S.C. 3304(f). Except for the circumstances in paragraphs (b) and (c) of this section, the justification shall be made publicly available within 14 days after contract award.
(b) In the case of a contract award permitted under 6.302-2, the justification shall be posted within 30 days after contract award.
(c) In the case of a brand name justification under 6.302-1(c), the justification shall be posted with the solicitation (see 5.102(a)(6)).
(d) The justifications shall be made publicly available-
(1) At the Government Point of Entry (GPE) https://www.sam.gov.
(2) On the website of the agency, which may provide access to the justifications by linking to the GPE; and
(3) Must remain posted for a minimum of 30 days.
Rationale for CO not providing conformed copy of contract?
in For Beginners Only
Posted
If I understand your question, and I don’t know I fully do, if you have the original contract and all the mods, is there a reason you can’t keep your contract up to date and the Government should do it for you?