Skip to content
View in the app

A better way to browse. Learn more.

The Wifcon Forums and Blogs - 27 Years Online

A full-screen app on your home screen with push notifications, badges and more.

To install this app on iOS and iPadOS
  1. Tap the Share icon in Safari
  2. Scroll the menu and tap Add to Home Screen.
  3. Tap Add in the top-right corner.
To install this app on Android
  1. Tap the 3-dot menu (⋮) in the top-right corner of the browser.
  2. Tap Add to Home screen or Install app.
  3. Confirm by tapping Install.

Vern Edwards

Members
  • Joined

  • Last visited

Everything posted by Vern Edwards

  1. Standard Form 30, block 13, says to use 43.103(b) as authority for an administrative change. But if you issued a task order that stated an erroneous period of performance you should prepare a supplemental (bilateral) agreement rather than an administrative change, state in the mod that the change was made to correct an error, and get the contractor to sign it.
  2. @formerfedInteresting. You conduct a competition to select contractors to do various task order work, award a contract to specific contractors to do specific work, then let everybody compete to do everything, regardless of what they were awarded a contract to do.
  3. Let's talk about standards. Standards for being competent. Competent to do what? Here's an excerpt from FAR 1.602, which specifies the authority and responsibility of contracting officers: There is a lot more to that than preparing, processing, and signing paperwork. Now suppose your office procures construction under contracts that average $1.5 million each. What do have to know and how much experience should you have in order to do what FAR requires? Suppose that your office is engaged in the acquisition of major systems. (See the definition at FAR 2.101.) What do you have to know and how much experience should you have in order to do it? What do you have to know and how much experience should you have in order to consider the advice you are given by specialists in audit, law, engineering, information security, transportation, and other fields? Consider advice, not do as you're told. Think about it. In another thread, someone posted this: Now, what does "2-3 year's experience" mean? What happens in two to three years? Is it the same for everyone in that shop? Is there a standard experience in a year? What do you know and how many of the duties described in FAR 1.602 are you competent to perform after working in a contracting office for two to three years? "Years" is an absurd measure of experience. Does doing something once make you "experienced" in the ordinary sense of that word? In my opinion, passing written exams and "boards" and having three years of experience in no way qualifies a person to do all the things required of a contracting officer with an unlimited warrant. I wasn't qualified when I got mine after four years. You need extensive and deep knowledge and experience to be competent at doing the things required by FAR 1.602. You need the ability to explain contracting concepts, principles, and rules to program managers, and to devise contracting solutions that meet their needs without having to convoke a synod. On the other hand, if in your shop all COs do is prepare documents, assemble files, ask their boss what to do next and how to do it, go to the lawyer to ask what is okay and what is not, and ask questions at Wifcon, well maybe two to three "years" experience is enough for an unlimited warrant. Why not, since COs in your shop don't do professional work. They're clerks, and the only reason they have a warrant is so they can sign things after someone else does the professional work, if anybody does it at all. And after two or three years you should know what to put in Standard Form 30 block 13C.
  4. @louistm In your opening post you said: Then you said you got your answer, and C Culham said: To which you replied: In your opening you referred to the standards of responsibility in FAR 9.104-1. The FAR passage that C Culham wrote about is a different matter than the standards of responsibility in FAR 9.104-1. It referred to standards of comparison with other contractors. The standards of responsibility are pass/fail standards, not standards of comparison with other contractors. How much of what you are reading and saying in this thread do you understand?
  5. You have to look at more than the matrix. See FAR 12.301, Solicitation provisions and contract clauses for the acquisition of commercial products and commercial services. Note paragraph (a), which says: Then see paragraphs (b) through (f). Does FAR 12.301 answer your question? As for the folks at DAU being smarter than you... Don't be so sure. 😆
  6. @formerfed How did that work? Did it work like this? Suppose that an RFP for a MATOC specifies four "subject areas", each described by a CLIN. The RFP says that offerors can submit proposals for one or any combination of the four subject areas. Offeror A submits a proposal for Subject Area 1, CLIN 0001, but not for CLINs 0002, 0003, or 0004, and is awarded a contract. It is now a contractor for CLIN 0001, Subject Area 1, and is designated Contractor 1A. But when the agency issues a fair opportunity notice for CLIN 0003, Subject Area 3, Contractor 1A may submit a proposal and be awarded the order, even though it did not submit a proposal on CLIN 0003 and its award included only CLIN 0001. Is that how it worked?
  7. T&M is a pricing arrangement, not an ordering arrangement. The government hires a contractor to do a job, the cost or which is uncertain. The parties agree that the contractor will make its best effort to complete the job within a ceiling price, and the government will pay an hourly labor rate and reimburse the cost of materials. If the parties combine a time-and-materials contract with an indefinite-quantity contract, then the government must promise to buy a minimum amount of work.
  8. During the 1970s and 1980s there was a lot of interest in the "role of the contracting officer." I came across copies of these publications while going through some boxes of old documents: The Contracting Officer: His Authority to Act and His Duty to Act Independently, Hanes and Smith, Dickinson Law Review (1966), available via Heinonline The Judicial Role of the Contracting Officer in U.S. Government Contracting, Spriggs, Washburn Law Journal (1972), available via Heinonline The Advocacy of a Systems Contracting Officer for Major Weapon Systems Acquisition, Young, Defense Systems Management College (1973), available via Defense Technical Information Center (DTIC) The Contracting Officer and the System Manager: An Analysis of Authorities and Responsibilities within the Department of Defense, Defense Systems Management School (Feb 1974), available from National Technical Information Service (NTIS), AD780693 Role and Mission of the Contracting Officer, Logistics Management Institute (May 1974), available from NTIS, AD780793 The Navy Program Manager and the Contracting Officer, Defense Systems Management School (Nov 1974), available from NTIS, ADA028656 Government Contracts in Public Administration: The Role and Environment of the Contracting Officer, Cooper, Public Administration Review (1980), available via JSTOR or Heinonline Handbook for Entry-Level System Buyers: The Role-Relationship of the Contracting Officer and Program Manager and the System Program Office Interfaces (April 1985), available from NTIS, ADA156313 The DOD Contracting Officer: A Study of the Past, An Assessment of the Present, Recommendations for the Future, American Bar Association, Section of Public Contract Law (1987) Identification of Critical Roles of Program Managers and Contracting Officers, Shingledecker, Air Force Institute of Technology (2001), available via DTIC Characteristics and Effects of Relationships involving Federal Government Contracting Officers, Lawl The Incredible Shrinking Contracting Officer, Pachter, Public Contract Law Journal (2010), available via JSTOR, Heinonline, or Westlaw Contracting officer workload, incomplete contracting, and contractual terms, Warren, RAND Journal of Economics (2014), available via JSTOR The Future Role of the Contracting Officer, Maldonado, Defense Acquisition University (2020), available via DTIC Characteristics and Effects of Relationships involving Federal Government Contracting Officers, Lawless, Naval Postgraduate School (1988), available via DTIC There was a high level of interest in the role of the contracting officer in DOD during the 1970s because of the emergence of the concept of the "program office" and the "program manager" during the 1960s and 1970s raised questions about the relative authority of the program manager and the contracting officer. There was not as much interest in the civilian agencies, where the contracting officer's role during that period was still mainly that of a purchasing agent. Within the legal community, interest was high because of the procedures for settling claims were somewhat unsettled. Lawyers wanted the contracting officer to play the role of an impartial, independent judge when settling disputes. Specific interest in the role of the contracting officer seems to have peaked during the 1980s and waned over the course of the last two decades. I suspect it is because the position is diminished relative to those of program management officials, but there may be other reasons. The Clinton Administration's "reforms" did great damage to the contracting workforce.
  9. Yes. The contract should be written so that there is a contract line item for each product or service for which orders can be placed. See FAR Subpart 4.10. Offerors may then be permitted to qualify as responsible for the purposes of competing for future orders for all or only some of the line items. If, after contract award, you want to allow contractors to qualify as being responsible with respect to additional line items and thereby become eligible to compete for orders for those items, you can write a clause that reserves the government's right to let additional contractors apply to be determined responsible for additional line items at a later date. I do not know of any standard clause for that, but there may be one in some agency FAR supplement.
  10. Welcome back, Jon. I got your email and will respond soon. Rather than say what kind of self-study is best (I'll do that later), I thought I'd show what kinds of stuff I've studied. I'm doing that because it's spring cleaning time and my wife has ordered be to get rid of some of my 50 file boxes of old stuff that I couldn't bear to throw away. So I started going through it and tossing some stuff. Here's a short, random, eclectic list of some of the stuff I found in one box. This is stuff I'm keeping. Some of this is stuff I copied from a book or journal in my local public library, and I don't have all the source information. BOX # 30 Contract Negotiations and Results in Aircraft Procurement: Case Studies of the B-52 and B-58, Preston, Rand Corp, 1962 Decisionmaking Among Multiple-Attribute Alternatives: A Survey and Consolidated Approach, MacCrimmon, Rand Corp, 1968 SMARTS and SMARTER: Improved Simple Methods for Multiattribute Utility Measurement, Edwards (not me) and Barron, 1994 Toward a Definition of Organizational Incompetence: A Neglected Variable in Organizational Theory, Orr and Shafritz, 1994 The Role of Questions in Teaching, Thinking and Learning (webpage download) Three Categories of Questions: Crucial Distinctions (webpage download) The Critical Mind is A Questioning Mind: Learning How to Ask Powerful, Probing Questions (webpage download) What Should We Teach About Questions? Harrah, 1982 The Nature of Questions (webpage discussion) How to Ask a Smart Question, Snyder (webpage article) 7 Must-Ask Questions in Any Negotiation, Lewis-Fernandez, businessknowhow.com Karrass Effective Negotiating Tip: What Questions Do You Ask, webpage download Use Clever Questions in Your Negotiations (webpage download) How to Ask a Question, Johnson, Review of General Semantics, 1983 What Is A Question? Cohen, The Monist, 1929 The Iliad, or the Poem of Force, Weil (1945) Slow Reading - the affirmation of authorial intent, Fletcher (webpage download) 2013 A Theory of Questions and Question Asking, Ram, Georgia Institute of Technology, 1991 A Lesson from Michelangelo, Fenton, NY Review of Books, 1995 Alternate Fighter Engine Competition: Source Selection Advisory Council Proposal Analysis Report, 1983 Military Aircraft and Aircraft Procurement: The Case of the C-5A, Knaack, USAF History & Museums Program The Dismissal of A. Ernest Fitzgerald by the Department of Defense, congressional hearings, 1969 The Source Selection Decision Process in Aeronautical Systems Division, Barclay and Nido, AFIT-LSSR 12-81 (1982) Legislative History of the Armed Services Procurement Act of 1947, congressional hearings, 1948 A Comparison of DOD and Commercial Airline Purchasing Practices, GAO/NSIAD-00-22 (1999) Presolicitation Discussions and the "Unfair" Competitive Advantage, Femino, Army Lawyer, 1990 Legal Theories of Profit, Foreman, Columbia Law Review, 1918 Competitive Bidding: A Comprehensive Bibliography, Stark and Rothkopf, Operations Research, 1979 The Nature of the Firm, Coase, Economica, 1937 Paperwork: The State of the Discipline, Kafka (not THAT Kafka(, Book History, 2009 One box down. Twenty-nine to go. I'll cut a deal with my wife about keeping some stuff. Jon, I know one guy (you know him, too, from Ruth's Chris in Crystal City), who might have more stuff than me. John Krieger of DAU. That guy has a lot of stuff. When I don't have something I call him. Pack rats of the world, Unite!
  11. What!!! We're not going to stop the rockfall from Coyote Wall onto Highway 14 that killed a driver in January? I'm shocked! SHOCKED!
  12. @LoulWhatever the reason(s) for your (presumably short-term) inability to comply with the telework restriction, you must demonstrate that the problem is beyond your fault or negligence. If your main problem is that some employees have quit rather than commute to the office, be sure to document, in detail, all of your efforts to find and recruit replacements.
  13. 😁 @PATRICK3 You have hit upon one of the longest-standing issues in government contract administration—What do you insert in Standard Form 30, block 13c, when you change the contract by mutual agreement? Contract specialists and file reviewers have argued about that since I was a GS-05 novice. I have never heard or given an answer that everyone agreed upon. Can you enter "mutual agreement of the parties" or do you have to cite some statute, regulation, or contract clause? I like "mutual agreement", but I have known plenty of competent people who would say that's dead wrong. They would want to cite some statute or regulation. I know people who would cite the U.S. Constitution. I've seen "United States Code" without reference to a specific section; "48 CFR"; and "FAR Part 43". I'd go along with ji20874's idea of leaving it blank, but I know that many, perhaps a majority, would object to that. The block's there—gotta be filled, right? Great trivia question at the club over beers.
  14. @PATRICK3If I were your CO I would allow you to write one modification that both adds the clause and issues the change order. You have to write it carefully. You (1) add the clause and then (2) issue the change, both via one supplemental agreement, and state that an equitable adjustment, if required, will be made by subsequent agreement. Now some COs might object, stating that adding the clause must be done bilaterally and issuing the change order must be done unilaterally and that those must be done under separate modifications. I don't think that's necessary, but different COs do some things differently. If you can, (1) add the clause, (2) issue the order, and (3) make the equitable adjustment all in one mod. I don't know what type of contract you have, but, arguably, you could assert that the changes clause is in the contract by operation of law (Christian Doctrine) and that you don't need to add it by modification. But it might just be easier to add it by mod. Finally, you don't really need the changes clause if the contractor agrees to the change. But if you think you might make other changes the clause might be needed.
  15. @LoulYou have not said what the contract pricing arrangement is, so I'll choose the most challenging—firm-fixed-price. Look at the Default clause, FAR 52.249-8. Read paragraph (a). It states three bases for T for D, which are failure to: (i) Deliver the supplies or to perform the services within the time specified in this contract or any extension; (ii) Make progress, so as to endanger performance of this contract (but see paragraph (a)(2) of this clause); or (iii) Perform any of the other provisions of this contract (but see paragraph (a)(2) of this clause). Let's say that failure to comply with the telework restriction falls under (iii). The courts and boards have excused a contractor's duty to proceed where it would be unfair or illogical to require it to do so. Having waived the telework restriction, and probably forbidden you to come in to work, I don't think the Government can dictate an arbitrary and unreasonable date for resumption of normal operations unless you agreed to some term to that effect. A knowledgeable and reasonable CO should know that, and should be willing to work with you to reach an agreement. It is not a matter of you wanting the Government "to be nicer" to your company. And unless the contract requires you to resume normal operations within a specified period of time, you probably don't need a contract change or to provide consideration. It is a matter of the time that you are reasonably entitled to in light of the facts of your case, the terms of your contract, and the law of government contracts. That kind of response to you is why I told you to get off Wifcon and call a lawyer. Neither party need be "nice." Both must be reasonable. What is reasonable depends on the facts of your case and the law of contracts. See paragraph (h) of the default clause: The issue before you and the government is what would be a reasonable time for you be able to resume normal operations. Meet with your lawyer, assemble your facts, and negotiate a reasonable resolution. You might need to phase-in resumption of normal operations and the performance of certain tasks while you reassemble and, perhaps, reconstitute your workforce. May I suggest that your company buy a copy of Administration of Government Contracts, 5th edition, by Cibinic, Nash, and Nagle. See p. 828, "Exceptions to the Duty to Proceed," page 830, "Impractical to proceed."
  16. I don't think it will settle the issue for Don, but it might shed some light.
  17. The government could not impose a "fine." But if you could not perform within the contract telework restrictions they might (1) withhold payment on grounds of nonperformance, (2) pay something, but with a deduction for nonperformance, (3) seek a no-cost termination of the contract for convenience, or in the extreme, (4) terminate your contract for default (breach). Much depends on the type of service(s) you provide, the type(s) of employees involved, the types of contracts involved (firm-fixed-price, cost-reimbursement, time-and-materials, etc.), and the terms pertaining to the telework restriction. An attorney will want to know the facts about the contracts, the history and terms of the telework restriction and waiver, their importance to performance, how long the waiver has been in place, the content and date of the notification that the waiver is being withdrawn, and the nature and circumstances of your employee losses and what it will take to replace them. The attorney will be concerned to assess the reasonableness of the government's withdrawal of the waiver in light of all the facts.
  18. @PATRICK3 So you want to (1) add the changes clause, then (2) issue a change order under the clause, and then (3) make an equitable adjustment for the change in a subsequent mod at a later date. And you want to know if you can do (1) and (2) in the same mod. Is that right?
  19. I just realized that, but he hasn't responded to me.
  20. @Don Mansfield@Lionel HutzSee Eyester, "NAFTA and the Barriers to Federal Procurement Opportunities in the United States," 31 Pub. Cont. L.J. 695, the section entitled, "Small Business Set-Aside Exemption," pp. 714 - 718. It might shed some light on your debate, esp. with regard to the interpretation of FAR 25.401(a)(1).
  21. So you want to (1) add the changes clause, then (2) issue a change order under the clause, and then (3) make an equitable adjustment for the change in a subsequent mod at a later date. Is that right?
  22. @here_2_helpThat's kind, but it's demonstrably untrue, and I really am old and intemperate. I'm embarrassed. Sitting here answering a few questions won't fix what's wrong with contracting today. I've tried to contribute by writing, but it has done little good. One of my last surviving mentors feels the same way. I honestly don't know what to do. The greatest book ever written about government contracting will go into its last edition this year. The three finest and most productive writers of government contracting reference works will produce no more. One has passed. One is ancient. And one is seriously ill. The last periodical publication devoted to practical matters will likely cease publication within a year or two, because it's very difficult to find knowledgeable, capable writers. I have tried to encourage some younger people to write, but to no avail. It's verging on impossible to find quality textbook materials suitable for novice and working level practitioners. The books still in print are prohibitively costly for individuals. I have been giving some away as gifts at my own expense in the one class I still teach occasionally. Agencies generally provide poor in-house training. The same is true of the official training institutions, and managerial devotion to their proper maintenance is weak if judged by more than words. There are some centers of excellence, but they are islands. We have a contracted-out government, so contracting and competence in its execution is extremely important to our nation's well-being. But our leaders are too short-sighted to invest in the kind of education and training we need to field a workforce that can interact effectively with an ever-increasingly complex environment. The FAR is over 2,000 pages. The DFARS is another 1,000. And they are just the tip of the iceberg. We are into the second year of a new presidency and still don't have an OFPP administrator (as far as I know). But even if we did the position has been so undermined as to be practically powerless. I have long known that things were bad, but, still, I was shocked when I read that NCMA contract management standard that Don posted and realized that it is now the basis for DOD and civilian agency contracting certification. I have been in something of a state of shock ever since. My own peers in terms of age and experience feel much the same. Thanks for the slap, H2H. I deserved and needed it. It was a sign. Again, apologies to all.
  23. I apologize for being intemperate. If you are looking for answers, begin by admitting that you are ignorant, and teach yourself to write coherent questions. All learning and knowledge begins with questions. Questions that you ask yourself. Questions that you ask of others. If you are trying to learn, the most powerful tool in your "toolkit" is the ability to write a good question. And when you write one, don't bury it under a speculative preface. Again, I apologize. I'm frustrated at the state of our business. It's getting ever worse, and at great cost. Nothing seems to work to fix it, and for some of us old-timers, time is running out. Maybe it's time for me to check out of here again and check into chat room rehab. I'm getting too old and cranky for this.

Account

Navigation

Search

Search

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.