A&E Single award IDIQ w/ 52.217-8
Basically, you signed up to a contract with options and you're not sure how the options are to be priced. Am I correct? If so, call the contracting officer and work something out.
-
An Excellent Collection of Papers on Contracting
I wouldn't try any of them right before bed. 😂 (I think you meant the second one. The first one is only three and one-half pages.)
-
A&E Single award IDIQ w/ 52.217-8
If the option clause is in the contract, then the government does not need a J&A to exercise it. FAR 36.602-1(c) doesn't have anything to do with it.
-
An Excellent Collection of Papers on Contracting
For those who are interesting in contracts and contracting—as distinct from how to work one's way through the maze of bureaucratic rules and procedures in FAR and agency policy documents—I have found an excellent collection of nine papers. They were prepared for a symposium conducted by the Lean Construction Institute, https://leanconstruction.org/ , in 2005. The symposium focused on relational contracting. The titles of the papers are: Relational Contracting and Lean Construction Flexibility in Long-Term Contractual Relationships: The Role of Co-operation Relational Contracting: Creating Value Beyond the Project Integrated Project Delivery: An Example of Relational Contracting PPC 2000: Association of Consultant Architects Standard Form Of Project Partnering Contract Project Alliancing: A Relational Contracting Mechanism for Dynamic Projects Relational Contracts: NEC [New Engineering Contract] In Perspective The Application Of Lean Principles To In-Service Support: A Comparison Between Construction And The Aerospace And Defence Sectors Sutter Health: Developing a Contracting Model to Support Lean Project Delivery These papers should be of interest to those who want to learn more about contract planning, formation, and performance, especially those who buy long-term and complex services (construction is a service) in a project environment. They may not be of interest to those who are interested mainly in government acquisition rules and procedures. The collection is 112 pages long and is downloadable as a single pdf document at: https://leanconstruction.org/uploads/wp/media/docs/lcj/V2_N1/LCJ_05_V2N1.pdf
-
Is a J & A needed?
Adding some more work to a labor-hour contract is a new procurement. Adding more work is not "in scope." If you do it sole source you need a J&A.
-
Transfer an existing BPA to a new 20-year GSA MAS contract?
I don't know. To be honest, I haven't paid much attention to GSA and its FSS procedures and don't plan to in the future, because I don't think its "contracting" in any meaningful sense of the term. It's a bureaucratic madhouse. But if GSA's madhouse works for people, and it apparently does, then that's fine. Besides, FARWorld is a madhouse, too. Thanks, Retread. Thanks formerfed.
-
Use of DFARS 217.202(2) and 234.005-1 on other than a Major System Acquisition
@ebkacDid you notice that DFARS 234.005-1 cites 10 USC 2302e? That statute is now at 10 USC 4004. Go read it, then come back and ask your questions.
-
Transfer an existing BPA to a new 20-year GSA MAS contract?
@formerfed Go to https://www.gsa.gov/cdnstatic/PSS_Implementation_-_Customer_Presentation_July_2015.pdf Read pages 20 -25. GSA refers to the process of "migration" of BPAs.
-
Transfer an existing BPA to a new 20-year GSA MAS contract?
I think the promise of an opportunity to compete would be consideration. So the deal would go down like this: The contractor with the BPA contacts a GSA CO and say it has a BPA under another contract that is about to expire and offers to transfer it to the CO's contract and compete for orders, which would benefit the the government by increasing competition. The CO agrees to do it and promises to let the contractor compete, which serves as consideration in return for the contractor's offer. Is that it? Is that how it works?
-
Transfer an existing BPA to a new 20-year GSA MAS contract?
All contracts are presumably beneficial to both parties. You still need consideration in order to seal the deal. In the case of government bilateral contracts, such as a supplemental agreement, what usually happens is that one party makes an offer (a promise) and the other party accepts and makes a return promise. The return promise is the consideration.
-
Transfer an existing BPA to a new 20-year GSA MAS contract?
@formerfedI think that a mod to move a BPA from an expiring contract to a continuing contract affects the rights of the parties. If so, then it cannot be an administrative change. See FAR 43.101: If the mod is a supplemental agreement, then there must be consideration. I'm not sure what you meant by "mutual consideration."
-
Transfer an existing BPA to a new 20-year GSA MAS contract?
@formerfedWould the transfer of a BPA from one contract to another be a contract modification? If so, what kind of mod would it be, administrative change or supplemental agreement? If a supplemental agreement, what would be the consideration needed to make the mod binding? From which party should the consideration flow?
-
Mentor-Protege Joint Ventures, GSA Schedules, and Exemption from Affiliation
@contractor100 Thankyou.
-
Transfer an existing BPA to a new 20-year GSA MAS contract?
What if the new GSA contract includes contract clauses that were not in the old GSA contract, or different versions of the clauses that were in the old GSA contract?
-
Mentor-Protege Joint Ventures, GSA Schedules, and Exemption from Affiliation
Where does Kingdomware say that a "GSA schedule award" is not a contract? On what page? Provide a quote.
-
Transfer an existing BPA to a new 20-year GSA MAS contract?
Contracts end. That is part of the expected order of business. Businesses must plan for that and take the actions necessary to survive or they will die. The "transfer" of a BPA from a dying MAS contract to a living MAS contract in order to keep it "alive" is a strange idea to an old-timer like me. But the GSA MAS program is a madhouse of procedures and "vehicles", so I do not doubt that agencies do it. As for worries about survival, such worries are every businessperson's reality.
-
Transfer an existing BPA to a new 20-year GSA MAS contract?
Here's another option: Let the BPA under the expiring MAS contract expire and let the contractor seek a new MAS contract and a new BPA.
-
Exercising Options without funding
Maybe true professionals should study, know, and understand the what, how and why of the regulations, policies, and organizational norms that govern their routine tasks. Then, when determining a course of action, they should: (1) ascertain the facts of their situation, (2) consider their objective(s), (3) consider what the regulations, policies, and norms require and would permit, (4) consider their resources, (5) tentatively develop a preferred plan of action and an argument in support of it, (6) consider arguments against, and (7) develop a fallback plan in case they can't sell their preferred plan. And remember the maxim: People who know what and how work for the people who know why.
-
Does a Bidder on an Multiple Award IDIQ Umbrella Contract Need to be Responsible for all of the Supplies and Services to be Awarded
Excellent question.
-
Exercising Options without funding
The most often answer: Yes.
-
T&M Rates and Subcontractor Pricing
See the time-and-materials payment clause, FAR 52.232-7. Neither 52.216-29 nor 52.232-7 indicate that the hourly rate(s) proposed/negotiated for subcontractor work must be the amount that the prime will pay to the sub for its work. Offhand, I can't think of why what you describe would be illegal or necessarily improper, but I would strongly advise that you disclose to the government what you plan on doing. I also suggest that you have a good explanation for why you plan on doing it. I'm not sure what that means, but I think you have to identify each subcontractor and the rate(s) you will charge for its work.
-
T&M Rates and Subcontractor Pricing
In short, what you want to know is if you can propose/negotiate a rate of $150/hr for subcontractor senior engineers, then negotiate a lower rate from the subs, such as $100/hr, then bill the government at $150 and keep the extra $50 for yourself. Is that what you want to know?
-
Exercising Options without funding
No funds, no obligation. Think about it. See also 31 USC 1341. This is Contracting 101. The OP's question has been answered.
-
Exercising Options without funding
It would be okay between the parties, but a competitor who learns about it (unlikely) might protest that the parties changed the terms of the option. See FAR 17.207(f). I don't know what the outcome would be.
-
Exercising Options without funding
There are two possible issues. First, does the contractor object? Second, does FAR permit? As to contractor objections, there have been a number of board of contract appeals decisions based on a contractor's objection to the exercise of an option subject to the availability of funds. Contractually, an option must be exercised in strict accordance with its terms. It appears that the government cannot exercise an option subject to the availability of funds unless the contract permits it to do so. The boards have rejected attempts by the government to insert an availability of funds clause at the time of option exercise. See Grumman Technical Services, Inc., ASBCA 46040, Sept. 5, 1995. But if the Availability of Funds clause, FAR 52.232-18, is already in the contract, then the government may exercise an option subject to the availability of funds. See American Contract Services, Inc., ASBCA 46788, April 6, 1994: As to whether FAR permits, 32.703-2(a) applies to contract actions. See the definition of contract action in FAR 32.001: I don't think the exercise of an option is a contract action under that definition. Nevertheless, it is clear from cases that agencies apply the availability of funds clause when exercising options, so go figure. I have not done extensive research. The cases I cited are a little old, and your agency may have a policy about exercising an option subject to the availability of funds. So I suggest that you confirm the above in consultation with your CO and your attorney before attempting to exercise an option subject to the availability of funds.