Jump to content
View in the app

A better way to browse. Learn more.

The Wifcon Forums and Blogs - 27 Years Online

A full-screen app on your home screen with push notifications, badges and more.

To install this app on iOS and iPadOS
  1. Tap the Share icon in Safari
  2. Scroll the menu and tap Add to Home Screen.
  3. Tap Add in the top-right corner.
To install this app on Android
  1. Tap the 3-dot menu (⋮) in the top-right corner of the browser.
  2. Tap Add to Home screen or Install app.
  3. Confirm by tapping Install.

Featured Replies

Posted

Scenario:

You have a Contract that requires over and above (O&A) effort to be administered IAW DFARs 217.77.

Question:

Once the ceiling amount of the O&A effort is established and the contract is awarded, what type of funds commitment, as it relates to O&A, does the government have to make at time of award? Furthermore, will the price the O&A CLIN be the ceiling amount, with the obligation amount being zero?

Observation:

I believe O&A is often being misused to accomplish, what should have been, ?known requirements? at the time of award and is justified by SOW statements and the tailoring of DFARs 252.217-7028. Also, please feel free to provide any advice or lessons learned when administering O&A effort.

I'll take a stab at this:

What type of funds: Don't know, what type of funds are on the contract? Is the change fiscally in scope?

Will the price the O&A CLIN be the ceiling amount, with the obligation amount being zero: That is how I would process it; however you may want to fund some of it (much like a UCA).

  • Author
I'll take a stab at this:

What type of funds: Don't know, what type of funds are on the contract? Is the change fiscally in scope?

Will the price the O&A CLIN be the ceiling amount, with the obligation amount being zero: That is how I would process it; however you may want to fund some of it (much like a UCA).

3600 Funds

Yes, effort is in scope - not sure what fiscally in scope means "bonifide need"?

Why would I fund some of it? O&A is for effort unknow at time of award.

What I meant by fiscally in scope: Does the work to be performed fall within the purpose of the funding. If you are doing repair work that is part of the T&E, then you probably are ok; assuming those funds are still available for new obligations (i.e. year 1 or 2). If you are doing repair work that isn't part of the T&E, then you probably should be using O&M or possibly procurement funds.

Why fund part of it: If it is going to take a while to definitize the action, then your contractor may want to receive payment for some of the work that has been performed.

Guest
This topic is now closed to further replies.

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.