Posted June 13, 20196 yr comment_47212 Is there a time limit for the duration of a follow-on task order under a GSA schedule contract for information technology (IT) services and supplies under FAR Subpart 8.4?
June 13, 20196 yr comment_47217 The exception states “in the interests of economy and efficiency...” so it boils down to discretion and deciding are you wasting government’s and industry’s time with competing knowing which source will likely win? No, there’s no absolute time limit and you have to use judgement. It all depends on the exact nature of the requirement and what the incumbent possesses in terms of techniques, skills, methodologies , expertise, and approaches.