Jump to content
View in the app

A better way to browse. Learn more.

The Wifcon Forums and Blogs - 27 Years Online

A full-screen app on your home screen with push notifications, badges and more.

To install this app on iOS and iPadOS
  1. Tap the Share icon in Safari
  2. Scroll the menu and tap Add to Home Screen.
  3. Tap Add in the top-right corner.
To install this app on Android
  1. Tap the 3-dot menu (⋮) in the top-right corner of the browser.
  2. Tap Add to Home screen or Install app.
  3. Confirm by tapping Install.

Featured Replies

Posted

Hello, 

I am having a disagreement with people in my office regarding BPA orders off of a BPA off of a GSA contract. So we established a BPA off of a GSA  contract (Using Part 8). The orders placed against that BPA are sometimes for services for a 3 year period. Like a report that takes 3 years to compile. In accordance with FAR Part 17 do you have to have options on a BPA order? Or have approval for a multi-year contract?

Thank you! 

It depends on what kind services you're buying, severable or nonseverable, and what kind of funds you have, annual or multiple year..

  • Author

Mr. Edwards. The legend himself. This is using multiple year money and the service is nonseverable. With those attributes does that mean you don't have to do options or get multiyear approval? 

If the services are nonseverable, then whether you have annual funds or multiple year, if you have enough money for the three year period of performance you do not need options or multiyear approval.

Because multiyear contracting is a procedure in which the government makes a contractual commitment in advance of appropriations. See FAR 17.104(a):

Quote

Multi-year contracting is a special contracting method to acquire known requirements in quantities and total cost not over planned requirements for up to 5 years unless otherwise authorized by statute, even though the total funds ultimately to be obligated may not be available at the time of contract award.

See also the definition in FAR 17.103.

No, that's not correct. You are buying a nonseverable service, which is a single job with a beginning and an ending. If the job is the bona fide need of FY2016, and begins in FY2016 but ends three years later, in FY2019, and if you have enough one-year FY2016 (annual) money to pay for the entire job, then you could obligate FY2016 funds to cover the entire job, all three years of performance. You would not be conducting a multiyear procurement.

Now, listen, CPH, I'm no genius. This is all fairly basic fiscal law, covered in the GAO's Principles of Federal Appropriations Law, Vol. I, Ch. 5. I suggest that you and your colleagues study that material. If you're in DOD the topic is covered in the Financial Management Regulation.

  • Author

Thank you Mr. Edwards. I hope you have a great Holiday. Thank you for your continued input into this forum and I will bring up the cited reading to my colleagues. 


All the best,

CPH 

The issues are discussed extensively in the DOD FMR Vol. 11A, Ch. 18.

Edited by Vern Edwards
Corrected chapter number.

Guest
This topic is now closed to further replies.

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.