|
4
CFR 21.8 (d): Payment of Protester's Costs |
|
Comptroller General - Key Excerpts |
As a general rule, we consider a successful protester entitled
to be reimbursed costs incurred with respect to all issues
pursued, not merely those upon which it prevails. AAR Aircraft
Servs.--Costs, B-291670.6, May 12, 2003, 2003 CPD para. 100 at
9. In our view, limiting recovery of protest costs in all cases
to only those issues on which the protester prevailed would be
inconsistent with the broad, remedial congressional purpose
behind the cost reimbursement provisions of the Competition in
Contracting Act of 1984, 31 U.S.C. sect. 3554 (c)(1)(a) (2006).
AAR Aircraft Servs.--Costs, supra; TRESP Assocs., Inc.--Costs,
B-258322.8, Nov. 3, 1998, 98-2 CPD para. 108 at 2. Nevertheless,
failing to limit the recovery of protest costs in all instances
of partial or limited success by a protester may also result in
an unjust award determination. Accordingly, in appropriate
cases, we have limited our recommendation for the award of
protest costs where a part of those costs is allocable to an
unsuccessful protest issue that is so clearly severable from the
successful issues as to essentially constitute a separate
protest. See, e.g., BAE Tech. Servs., Inc.--Costs, B-296699.3,
Aug. 11, 2006, 2006 CPD para. 122 at 3; Interface Floorings
Sys., Inc.--Claim for Attorneys’ Fees, B‑225439.5, July 29,
1987, 87‑2 CPD para. 106 at 2-3. In determining whether protest
issues are so clearly severable as to essentially constitute
separate protests, we consider, among other things, the extent
to which the issues are interrelated or intertwined--i.e., the
successful and unsuccessful arguments share a common core set of
facts, are based on related legal theories, or are otherwise not
readily severable. See Sodexho Mgmt., Inc.--Costs, B‑289605.3,
Aug. 6, 2003, 2003 CPD para.136 at 29. We previously have
found that the three issue areas raised by BRSC in its
protest--misevaluation of proposals, failure to hold meaningful
discussions, and treating offerors unequally--involve the same
core facts, and thus are intertwined for purposes of considering
whether protest costs should be reimbursed. BAE Tech. Servs.
Inc.--Costs, B-296699.3 Aug. 11, 2006 , 2006 CPD para. 122 at 3.
The agency has presented no argument or evidence that persuades
us that our view in this regard should be changed under the
facts of this case. Under these circumstances, we conclude that
the evaluation, discussions, and equal treatment issues raised
in BRSC’s protest are not severable, and that BRSC therefore
should be reimbursed its reasonable costs related to all of
these issues. BRSC is not required to separate the costs
associated with its arguments relating to the agency’s failure
to conduct meaningful discussions from the costs associated with
the other arguments raised in its protest. BRSC should submit
its claim to the agency. (Burns
and Roe Services Corporation--B-310828.2, Costs, April 28,
2008) (pdf)
We
decline to recommend that TACOM reimburse ALF for any costs. We
will recommend the amount that the agency should pay only where,
prior to coming to our Office, the protester timely pursued a
claim to the agency; that is, where the protester filed an
adequately documented claim with the agency within 60 days after
receiving our recommendation that costs be paid. See 4 C.F.R.
sect. 21.8(f)(1). The 60‑day timeframe was specifically designed
to avoid the piecemeal presentation of claims (which necessarily
results in unduly delaying their resolution), while at the same
time affording protesters an ample opportunity to submit
adequately substantiated certified claims. REEP, Inc.--Costs,
B-290665.2, July 29, 2003, 2003 CPD para. 131 at 4. To be
considered adequately documented, a claim for reimbursement of
employee compensation must include documentation establishing
the number of hours worked and the purposes of the employees’
efforts; in addition, it must demonstrate that the claimed
hourly rates reflect the employees’ actual rates of compensation
plus reasonable overhead and fringe benefits. See W.S. Spotswood
& Sons, Inc.--Claim for Costs, B-236713.3, July 19, 1990, 90-2
CPD para. 50 at 3. While we do not believe that the 60-day
timeframe should be applied in so harsh a manner that a
protester receives no reimbursement merely because its initial,
timely claim required some supplementation or elaboration, where
the timely submission is of little or no value in supporting the
claim, we will consider the claim untimely and regard it as
forfeited. REEP, Inc.--Costs, supra. We note in this connection
that a protester’s failure to file an adequately documented
claim within the 60-day period may result in forfeiture of its
right to recover costs even where the parties have continued to
negotiate after the 60-day period expired. H. G. Prop. A, L.
P.--Costs, B‑277572.8, Sept. 9, 1998, 98-2 CPD para. 62 at 2-3.
Here, ALF’s initial, timely submission to the agency was so
deficient as to be of basically no value in supporting its
claim. As previously noted, the submission failed to furnish any
detail regarding the claimed employee hours or supporting the
claimed rates of compensation; in addition, it failed to include
any documentation demonstrating ALF’s obligation to compensate
the consultant. Moreover, even when given the opportunity to
supplement its submission to the agency, ALF never sought to
overcome the second deficiency; that is, it never furnished the
agency with documentation supporting its claimed rates of
employee compensation--and, indeed, ultimately submitted
documentation to our Office that clearly demonstrated that the
initially claimed rates were substantially overstated. In
addition, we are not persuaded that prior to seeking a
recommendation regarding cost recovery from our Office, the
protester made a reasonable attempt to reach an agreement with
the agency, as contemplated by our Regulations. As noted above,
it was not until the protester sought a recommendation from our
Office that it for the first time furnished documentation
substantiating its claimed rates of employee compensation. By
failing to furnish such documentation to the agency, ALF
effectively eliminated the possibility of the two parties
arriving at an agreement. We do not think that it is appropriate
to permit a protester to seek a recommendation regarding cost
recovery from our Office where it has not previously made a
reasonable effort to reach an agreement with the agency. (Al
Long Ford--Costs, B-297807.2, October 18, 2007) (pdf)
Under the Competition in Contracting Act (CICA), when our
Office finds that an agency’s procurement activities fail to
comply with the requirements of statute or regulation, we are
given discretionary authority to recommend the reimbursement of
proposal preparation costs. Specifically, CICA states: “If the
Comptroller General determines that . . . the award of a
contract does not comply with a statute or regulation, the
Comptroller General may recommend that the Federal agency
conducting the procurement pay to an appropriate interested
party the costs of . . . bid and proposal preparation.” 31.
U.S.C. sect. 3554(c)(1) (2000) (italics added). Here, as
discussed above, Lockheed Martin has already received the
agreed-upon compensation for its performance of the fixed-price
CAD contract, under which its technical solution for the SDD
contract was evaluated. Further, Lockheed Martin will have an
opportunity to compete for the phase II requirements that were
deleted from the solicitation. Finally, it is clear that,
following deletion of the phase II requirements, Lockheed Martin
continued to compete for the modified phase I requirements; its
protest, which we sustained, challenged the basis for the
changes to those requirements--not the source selection process
following the changes. Based on our consideration of the
record as a whole, we decline to exercise our discretionary
authority to recommend reimbursement of Lockheed Martin’s
proposal preparation costs. (Lockheed
Martin Corporation--Costs, B-295402.2, November 1, 2005) (pdf)
We have previously reasoned that the justification for an
upward fee adjustment is self-evident if the claimant alleges
that the cost of living has increased, as measured by the
Department of Labor’s Consumer Price Index (CPI). Sodexho Mgmt.,
Inc.--Costs, B-289605.3, Aug. 6, 2003, 2003 CPD para. 136 at
41. In this regard, we have declined to impose a requirement
that a claimant do more than request an adjustment and present a
basis upon which the adjustment should be calculated. Id.; see
Brickwood Contractors, Inc. v. United States, 49 Fed. Cl. 148,
164 (2001); California Marine Cleaning Servs., Inc. v. United
States, 43 Fed. Cl. 724 (1999). Where a claimant meets this
standard, and an agency does not articulate any objection, we
will grant a claimant’s request for a recommendation in favor of
a cost of living adjustment to the fee cap. Sodexho Mgmt.,
Inc.--Costs, supra. In support of its claim for attorneys’ fees
above the $150 level, Inter-Con provided a detailed explanation
of its calculation of the rates and included a printout of the
“All Urban Consumers” CPI for the San Francisco-Oakland-San
Jose, California area. Inter‑Con Claim Letters, dated April 8
and 26, 2005. Use of the “All Urban Consumers” CPI for a
specific area is consistent with our decision in Sodexho. See
Sodexho Mgmt., Inc.--Costs, supra, at 43 n.33. In requesting our
recommendation, DOS agrees that the protester’s “request appears
to be consistent with the standards followed in [Sodexho],” and
provides no specific objection to the higher fees. DOS Letter,
June 3, 2005. We have reviewed Inter-Con’s calculation in
support of the higher requested fees, and find that they appear
properly supported and reasonable. Accordingly, we recommend
that DOS pay the higher attorneys’ fees claimed. (Department
of State--Costs, B-295352.5, August 18, 2005) (pdf)
CourtSmart incurred $153,971.25 for its attorney's
services at an hourly rate of $475. SSA generally alleges that
the rate is above the reasonable rate charged for these
services. In response, CourtSmart submitted information from a
2002 national billing rate survey. Specifically, CourtSmart
identified the ranges of hourly billing rates for partners and
for associates from 19 firms in the Washington, D.C. area, as
published in the January 2003 edition of Legal Times. The hourly
rates for partners reported by these firms ranged from $185 to
$750. CourtSmart Submission (Oct. 1, 2004) at 2, encl. 4. The
highest rates for partners for all but two of these firms were
in excess of $500. CourtSmart states that a breakdown of billing
rates by specific practice area was not available. CourtSmart's
attorney states that he has 30 years of experience in federal
procurement law in the Washington, D.C. area, and has the
expertise, reputation and ability commensurate with partners at
the high end of the billing rate range. CourtSmart asserts that,
since the $475 rate billed by its attorney is within the range
billed by firms in the community, the hourly rate is reasonable.
SSA has not challenged the applicability of the survey for the
purpose of determining the reasonableness of the attorney's
hourly rate billed here. SSA has also not challenged the
asserted expertise, reputation and ability of the attorney.
Here, the work was performed by the attorney from November 2003
through February 2004, which is within approximately 1 year of
the billing rate survey. Although the survey does not provide
hourly rate information for attorneys practicing in federal
procurement law or related areas of practice, SSA does not
challenge the relevance of the information submitted. On this
record, we find the attorney's billed hourly rate of $475 was
reasonable. See KPMG Peat Marwick, LLP--Costs , supra, at 5-6;
Bay Tankers, Inc.--Costs , supra . Therefore, we find
$153,971.25 ( i.e. , 324.15 hours x $475 per hour) that
CourtSmart claims for attorney's fees is reasonable and
recoverable. (CourtSmart Digital
Systems, Inc.--Costs, B-292995.7, March 18, 2005) (pdf)
Furthermore, even if SBA were to issue a formal size
determination, that determination would not have any
retroactive effect on Brechan's size for purposes of its
initial protest, as the effect of such a determination
after the award of a contract is prospective. See , e.g. ,
FAR 19.302(j); Planned Sys. Int'l, Inc. , B-292319.7, Feb.
24, 2004, 2004 CPD 43 at 3 (adverse SBA decision issued
after award does not require cancellation of the award);
Dawkins Gen. Contractors & Supply, Inc , B243613,
B-243613.11, Sept. 21,1992, 92-2 CPD 190 at 3 (adverse SBA
size determinations apply prospectively only). Although
Brechan's request presents the somewhat unusual
circumstance of an agency's challenge to the size status
of an unsuccessful offeror after award has been made, in
the context of a recompetition in which the offeror is not
participating and solely for the purpose of challenging
entitlement to protest costs, we believe that our cases
and SBA regulations do not provide for a retroactive
challenge to Brechan's standing. Accordingly, we conclude
that there is no basis to challenge Brechan's status as a
small business for purposes of this request. Based on the
record, Brechan's request for a recommendation that it be
reimbursed the reasonable costs of filing and pursuing its
protest is granted. Further, in light of the discussion
above, we conclude that Brechan is a small business for
purposes of filing its claim for costs with the agency. (Brechan
Enterprises, Inc.--Costs, B-294046.2, November 4,
2004) (pdf)
We
find that reimbursement is warranted. The promptness
standard applicable to protests cannot be applied to the
agency's request for reconsideration because the request
itself caused the protester to expend unnecessary time and
resources to obtain relief, a key consideration in our
deciding whether reimbursement of a protester's costs is
appropriate. See AAR Aircraft Servs.--Costs , B-291670.6,
May 12, 2003, 2003 CPD 100 at 5. It is reasonable for a
firm whose protest has been sustained by our Office to
feel compelled to respond to the agency's request for
reconsideration. Here, the agency caused the protester to
incur costs opposing a request for reconsideration that
was devoid of merit. In this regard, parties filing
requests for reconsideration are required to submit a
detailed statement of the factual and legal grounds upon
which reversal or modification is deemed warranted,
specifying any errors of law made or information not
previously considered. Bid Protest Regulations, 4 C.F.R.
21.14(a). DHS's reconsideration request did not meet this
standard. (Security Consultants
Group, Inc.--Costs, B-293344.6, November 4, 2004) (pdf)
Neither our regulations nor our prior decisions recognize
an exception to the 60-day filing requirement based simply
on the fact of a request for reconsideration having been
filed. While our Office has indicated that we may consider
an untimely claim for good cause, we have construed the
term to mean that some compelling reason beyond the
control of the protester prevented the protester from
timely filing the claim. Continental Maritime of San
Diego, Inc.-Costs , B-249858.5, Dec. 17, 1993, 93-2 CPD 323
at 2; Test Sys. Assocs., Inc.-Costs , May 3, 1993, 93-1 CPD
351 at 2. Here, there is no evidence that Keeton could not
have filed within the required time period a documented,
substantiated claim for the costs of filing and pursuing
the protest that we had sustained. Not only did Keeton's
request for reconsideration not prevent the protester from
timely filing its claim, the request for reconsideration
did not even call into question the basis upon which we
sustained the protest and thus our recommendation of
protest costs. Moreover, we note that when Keeton received
our decision denying its request for reconsideration on
March 31, Keeton still had 33 days within which to file its
cost claim. Keeton has offered no explanation as to why it
did not have sufficient time after receiving our decision
denying its request for reconsideration to complete and
timely file its claim with the agency. In these
circumstances, we decline to recommend that the agency pay
the claimed costs. (Keeton
Corrections, Inc.—Costs, B-293348.3, October 25, 2004)
(pdf)
Based on our review of the record, we find no basis to
object to the reasonableness of the agency’s determination
that CAMS should be reimbursed $3,946.30 for its total
claimed costs of filing and pursuing its protest. However,
we do not recommend that CAMS be reimbursed for the costs
of pursuing its claim at the agency, because those costs
are not associated with proceedings before our Office. See
SKJ & Assocs.--Costs, B-291533.3, July 24, 2003, 2003 CPD
¶ 130 at 4. We also deny CAMS’s costs for pursuing this
claim before our Office. Our Bid Protest Regulations, 4
C.F.R. § 21.6(f)(2) (2003), provide that we may recommend
that a protester be reimbursed the costs of pursuing its
claim before our Office. Since we recommend that CAMS be
reimbursed the amount the agency determined is due,
however, we find no basis to recommend that CAMS be
reimbursed for the costs of pursuing the claim at our
Office. (CAMS, Inc.--Costs,
B-292546.2, March 22, 2004) (pdf)
Our Bid Protest Regulations, 4 C.F.R. § 21.8(f)(1) (2003),
require protesters to file claims for protest costs within
60 days of receiving our recommendation that such costs be
paid. This 60-day timeframe was specifically designed to
avoid the piecemeal presentation of claims (which
necessarily results in unduly delaying their resolution),
while at the same time affording protesters an ample
opportunity to submit adequately substantiated, certified
claims. HG Properties A, L.P.--Costs, B-277572.8, Sept. 9,
1998, 98-2 CPD ¶ 62 at 2. A protester's failure to file an
adequately documented claim within this 60-day period
results in forfeiture of its right to recover costs,
irrespective of whether the parties may have continued to
negotiate after the 60-day period expired. Id. at 2-3. In
this latter connection, a protester seeking to recover its
protest costs must submit evidence sufficient to support
its claim that those costs were incurred and are properly
attributable to filing and pursuing the protest. Stocker &
Yale, Inc.--Claim for Costs, B-242568.3, May 18, 1993,
93-1 CPD ¶ 387 at 4. Although we recognize that the
requirement for documentation may sometimes entail certain
practical difficulties, we do not consider it unreasonable
to require a protester to document in some detail the
amount and purposes of its employees' and attorneys'
efforts and to establish that the claimed hourly rates
reflect the employees' actual rates of compensation plus
reasonable overhead and fringe benefits. W.S. Spotswood &
Sons, Inc.--Claim for Costs, B-236713.3, July 19, 1990,
90-2 CPD ¶ 50 at 3. We do not believe that the 60-day
timeframe should be applied in so harsh a manner that a
protester receives no reimbursement merely because its
initial, timely, claim required some supplementation or
elaboration. Nonetheless, where the timely submission is
of little or no value in supporting the claim, we believe
that the claim should be rejected as untimely. (REEP,
Inc.--Costs, B-290665.2, July 29, 2003) (pdf)
Our review of the record confirms the reasonableness of
the agency's conclusion that the protester has not
adequately documented its protest costs. Despite the
passage of many months and several requests from the
agency to do so, the protester has not submitted any
documentation to show that the $425 hourly rate claimed by
TRS counsel is representative of that charged for similar
services in the Philadelphia area, where he practices law.
(TRS Research--Costs,
B-290644.2, June 10, 2003)
Our Bid Protest Regulations provide that where the
contracting agency decides to take corrective action in
response to a protest, we may recommend that the protester
be reimbursed the costs of filing and pursuing its
protest, including reasonable attorneys' fees. 4
C.F.R. §
21.8(e) (2003). This does not mean that costs should be
reimbursed in every case in which an agency decides to
take corrective action; rather, a protest should be
reimbursed its costs where an agency unduly delayed its
decision to take corrective action in the face of a
clearly meritorious protest. Griner's-A-One Pipeline Servs.,
Inc.--Entitlement to Costs, B-255078.3, July 22, 1994,
94-2 CPD ¶ 41. Thus, as a prerequisite to our
recommending that costs be reimbursed where a protest has
been settled by corrective action, not only must the
protest have been meritorious, but it also must have been
clearly meritorious, i.e., not a close question. J.F.
Taylor, Inc.--Entitlement to Costs, B-266039.3, July 5,
1996, 96-2 CPD ¶ 5 at 3; Baxter Healthcare
Corp.--Entitlement to Costs, B-259811.3, Oct. 16, 1995,
95-2 CPE ¶ 174 at 4-5; GVC Cos.--Entitlement to Costs,
B-254670.4, May 3, 1994, 94-1 CPD ¶ 292 at 3. A protest is
"clearly meritorious" when a reasonable agency inquiry
into the protester's allegations would show facts
disclosing the absence of a defensible legal position.
Department of the Army--Recon., B-270860.5, July 18, 1996,
96-2 CPD ¶ 23 at 3. The mere fact that an agency decides
to take corrective action does not establish that a
statute or regulation clearly has been violated. Spar
Applied Sys.--Declaration of Entitlement, B-276030.2,
Sept. 12, 1997, 97-2 CPD ¶ 70 at 5. Here, we
conclude that it is not appropriate to recommend that East
Penn recover its protest costs because East Penn's protest
was not clearly meritorious. (East
Penn Manufacturing Company, Inc.--Costs, B-291503.4,
April 10, 2003) (txt
version)
In view of
the cancellation of the RFP, which has deprived ATS of
an opportunity to compete for the scope of services
contemplated in the solicitation at issue in the
protest, ATS requests that we modify our earlier
recommendation to allow ATS to be reimbursed the costs
of preparing its proposal. The Army has no objections to
ATS's request. Under these circumstances, we modify our
recommendation to provide that ATS should be reimbursed
the costs of preparing its proposal under the canceled
solicitation. [1] 31 U.S.C. sect. 3554(c)(1), 4 C.F.R.
sect. 21.8(d)(2) (2001). (Aberdeen
Technical Services--Modification of Recommendation,
B-283727.3, August 22, 2001) (pdf)
Request for
recommendation that agency reimburse protester for the
costs it incurred in pursuing an administrative appeal
of the agency's initial cost comparison decision under
Office of Management and Budget Circular No. A-76 is
denied because GAO's authority to recommend
reimbursement of protest costs does not extend to costs
incurred by a protester in litigating in another forum.
(Rice
Services, Ltd.--Costs, B-284997.2, May 18, 2001)
Our Office generally
accepts the number of attorney hours claimed, unless the
agency identifies specific hours as excessive and
articulates a reasoned analysis as to why payment for
those hours should be disallowed. Data Based Decisions,
Inc.--Claim for Costs, B-232663.3, Dec. 11, 1989, 89-2
CPD para. 538 at 3. Simply concluding that the hours
claimed are excessive or suggest duplication of effort
is inadequate to justify denying a claim for protest
costs. Princeton Gamma-Tech, Inc.--Claim for Costs,
B-228052.5, Apr. 24, 1989, 89-1 CPD para. 401 at 4. We
will examine the reasonableness of the attorney hours
claimed to determine whether they exceed, in nature and
amount, what a prudent person would incur in pursuit of
his or her protest. Price Waterhouse--Claim for Costs,
B-254492.3, July 20, 1995, 95-2 CPD para. 38 at 5.
(Pulau
Electronics Corporation--Costs, B-280048.11, July
31, 2000) (pdf)
We next turn to the
Navy's contention that it should not be required to
reimburse DRS for its protest costs because the agency
acted in good faith in relying on GSA's representations.
As we stated in our prior decision, we have no basis to
conclude, nor do we think, that the Navy acted in less
than complete good faith in placing this order. DRS
Precision Echo, Inc., supra, at 3. In addition, our
prior decision did not intend to suggest that the Navy
acted in bad faith in defending DRS's protest. Instead,
the decision reflected only a limited concern about the
continued defense of this purchase given GSA's inability
over a period of several months to produce any evidence
that a contract slated to expire had not done so. Id.
Nonetheless, despite the Navy's claims of good faith,
and despite any concern by our Office that the Navy may
have unnecessarily prolonged the dispute, the decision
whether to recommend an award of costs bears no
relationship to whether the agency acted in good faith;
rather, as stated above, costs are awarded to relieve
protesters of the financial burden of the public service
they perform. General Servs. Admin.--Recon., B-239569.2,
Feb.13, 1991, 91-1 CPD para. 163 at 3. (Department
of the Navy--Modification of Remedy, B-284080.3, May
24, 2000)
As a general rule, we
recommend that a prevailing protester be reimbursed the
costs incurred with respect to all issues pursued, not
merely those upon which it prevails. Omni Analysis;
Department of the Navy--Recon., B-233372.2, B-233372.3,
July 24, 1989, 89-2 CPD para. 73 at 3-4. However, our
Office will limit its recommendation regarding a
successful protester's recovery of protest costs when a
part of the costs is allocable to a losing protest issue
that is so clearly severable as to constitute a separate
protest. Price Waterhouse--Claim for Costs, B-254492.3,
July 20, 1995, 95-2 CPD para. 38 at 3-4. (TRW,
Inc.--Costs, B-282459.3, August 4, 1999) (pdf)
We will not consider
requests for a recommendation for reimbursement of costs
where the protester fails to document its claim to the
contracting agency. See Custom Prod. Mfg., Inc.--Recon.,
B-235431.8, July 21, 1995, 95-2 CPD para. 40 at 3.
Where, as here, attorneys' fees are sought to be
recovered, evidence from the attorneys involved must be
submitted, including, for instance, copies of bills from
the attorneys listing the dates the services were
performed and the hours billed to the protester. Custom
Prod. Mfg., Inc.--Costs, B-235431.7, May 9, 1995, 95-1
CPD para. 236 at 3. We have reviewed the documentation
submitted by the protesters' attorneys here, which
consists of the abstracts of attorneys' fees and
expenses for each pleading or document that dealt with
the partial set-aside issue, and we find this evidence
insufficient to support the protesters' claim. (A-1
Movers of America, Inc. et al.--Costs, B-277241.31,
August 2, 1999) (pdf)
A protester seeking to
recover the costs of pursuing its protest must submit
sufficient evidence to support its monetary claim. The
amount claimed may be recovered to the extent that the
claim is adequately documented and is shown to be
reasonable; a claim is reasonable, if, in its nature and
amount, it does not exceed that which would be incurred
by a prudent person in the pursuit of a protest.
E&R, Inc.--Claim for Costs, B-255868.2, May 30,
1996, 96-1 CPD para. 264 at 2; Data Based Decisions,
Inc.--Claim for Costs, B-232663.3, Dec. 11, 1989, 89-2
CPD para. 538 at 2-3. (Chant
Engineering Co., Inc.--Costs, B-274871.4, April 28,
1999) (pdf)
|
|
|
Comptroller General - Listing of Decisions |
|
For
the Government |
For
the Protester |
|
Al Long Ford--Costs,
B-297807.2, October 18, 2007 (pdf) |
Burns and Roe Services Corporation--B-310828.2,
Costs, April 28, 2008) (pdf) |
|
Lockheed Martin
Corporation--Costs, B-295402.2, November 1, 2005 (pdf) |
CourtSmart Digital Systems,
Inc.--Costs, B-292995.7, March 18, 2005 (pdf) |
|
Department of State--Costs,
B-295352.5, August 18, 2005 (pdf) |
Security Consultants Group,
Inc.--Costs, B-293344.6, November 4, 2004 (pdf) |
|
Keeton Corrections, Inc.—Costs,
B-293348.3, October 25, 2004 (pdf) |
Brechan Enterprises, Inc.--Costs,
B-294046.2, November 4, 2004) (pdf) |
|
e-LYNXX Corporation--Costs,
B-292761.2, August 12, 2004 |
|
|
CAMS, Inc.--Costs,
B-292546.2, March 22, 2004 (pdf) |
|
|
REEP, Inc.--Costs,
B-290665.2, July 29, 2003 (pdf) |
|
|
SKJ & Associates, Inc.--Costs,
B-291533.3, July 24, 2003 (pdf) |
|
|
TRS Research--Costs,
B-290644.2, June 10, 2003 (pdf) |
|
|
East Penn Manufacturing Company, Inc.--Costs, B-291503.4,
April 10, 2003) (txt
version) |
|
|
M&S Farms, Inc.--Costs,
B-290599.3, April 8, 2003 (pdf) |
|
|
QuanTech, Inc.--Costs, B-291226.3, March 17, 2003 (pdf)
(txt
version) |
|
|
Priority
One Services, Inc.--Costs, B-288836.5, November 8, 2002
(pdf) |
|
|
Galen
Medical Associates, Inc. -- Costs, B-288661.6, July 22,
2002 (pdf) |
|
| Parmatic
Filter Corporation--Costs, B-285288.5, August 27, 2001 (pdf) |
|
| Aberdeen
Technical Services--Modification of Recommendation,
B-283727.3, August 22, 2001 (pdf) |
|
| Rice
Services, Ltd.--Costs, B-284997.2, May 18, 2001 (PDF
Version) |
|
| Pulau
Electronics Corporation--Costs, B-280048.11, July 31,
2000 (pdf) |
|
| Department
of the Navy--Modification of Remedy, B-284080.3, May 24,
2000 (pdf) |
|
| Dual
Inc.--Costs, B-280719.3, April 28, 2000 (pdf) |
|
| Aberdeen
Technical Services, B-283727.2, February 22, 2000 |
|
| TRW,
Inc.--Costs, B-282459.3, August 4, 1999 (pdf) |
|
| A-1
Movers of America, Inc. et al.--Costs, B-277241.31, August
2, 1999 (pdf) |
|
| Aalco
Forwarding, Inc., et al.--Costs, B-277241.30, July 30, 1999
(pdf) |
|
| Chant
Engineering Co., Inc.--Costs, B-274871.4, April 28, 1999 |
|
|
U. S. Court of Federal Claims
- Key Excerpts |
|
Under the EAJA, an award of reasonable attorneys’ fees may be
made to a qualifying
party who prevails in an action by or against the United States,
provided that certain criteria are
met. 28 U.S.C. § 2412(d)(1)(A).2 Eligibility for such an award
requires that: (1) the claimant be
a “prevailing party;” (2) the government’s position was not
“substantially justified;” (3) no
“special circumstances make an award unjust;” and (4) any fee
application be submitted to the
court within 30 days of final judgment in the action and be
supported by an itemized statement.
Id. § 2412(d)(1)(A), (B); see Commissioner, INS v. Jean, 496
U.S. 154, 158 (1990); Loomis v.
United States, 74 Fed. Cl. 350, 353 (2006); Lion Raisins, Inc.
v. United States, 57 Fed. Cl. 505
(2003); see also Knowledge Connections, Inc. v. United States,
76 Fed. Cl. 612, 614-15 (2007).
(sections deleted)
The burden of establishing substantial justification rests upon
the government. See White
v. Nicholson, 412 F.3d 1314, 1315 (Fed. Cir. 2005); Hillensbeck
v. United States, 74 Fed. Cl.
477, 479-80 (2006); Lion Raisins, 57 Fed. Cl. at 512. In
Pierce
v. Underwood, 487 U.S. 552,
565 (1998), the Supreme Court described substantial
justification as meaning “not ‘justified to a
high degree,’ but rather ‘justified in substance or in the
main’– that is, justified to a degree that
could satisfy a reasonable person.” In determining substantial
justification, the court must “look
at the entirety of the government’s conduct [both prior to and
during litigation] and make a
judgment call whether the government’s overall position had a
reasonable basis in both law and
fact.” Chiu v. United States, 948 F.2d 711, 715 (Fed. Cir.
1991); see also Doty v. United States,
71 F.3d 384, 386 (Fed. Cir. 1995) (“[T]he term ‘position of the
United States’ [in the EAJA]
refers to the government’s position throughout the dispute,
including not only its litigating
position but also the agency’s administrative position.”).
The key inquiry is “not what the law now is, but what the
government was substantially
justified in believing it to have been.” Loomis, 74 Fed. Cl. at
355 (quoting Underwood, 487 U.S.
at 561). The government’s position may therefore be found to be
substantially justified even
though the court previously overturned the government’s actions.
Id.; see also Scarborough v. Principi, 541 U.S. 401, 415 (2004) (“Congress did not . . . want
the ‘substantially justified’
standard to ‘be read to raise a presumption that the [g]overnment
position was not substantially
justified simply because it lost the case.’”); RAMCOR Servs.
Group, Inc. v. United States, 185
F.3d 1286, 1290 (Fed. Cir. 1999) (“Although INS had lost the
underlying action, that outcome
does not alone show that its position had no substantial
justification.”). Of course, “[t]o be
‘substantially justified’ means . . . more than merely
undeserving of sanctions for frivolousness.”
Underwood, 487 U.S. at 566.
The government argues that its position in the underlying
litigation was justified because
there was “significant GAO precedent” supporting the Contracting
Officer’s issuance of
Solicitation Amendments 9 and 12 to extend the closing dates for Presidential’s proposal
revisions nunc pro tunc. Def.’s Opp’n at 4 (citing Micromass,
Inc., B-278869, Mar. 24, 1998,
98-1 CPD ¶ 93; Ivey Mech. Co., Comp. Gen. Dec. B-272764, 96-2 CPD ¶ 83, Aug. 23, 1996;
Fort Biscuit Co., B-247319, May 12, 1992, 92-1 CPD ¶ 440;
Institute for Advanced Safety
Studies-Recon., B-221330.2, July 25, 1986, 86-2 CPD ¶ 110). The
government posits that its
reliance on these GAO opinions “was reasonable and substantially
justified” because the
Contracting Officer in the instant case was “faced with
circumstances essentially the same” as
those existing in the GAO cases and issued the amendments to
enhance competition, consistent
with those decisions. Id. The government also puts forward GAO’s
decision in Geo-Seis
Helicopters, Inc., B-299175, B-299175.2, Mar. 5, 2007, as a
basis for support. The government
argues that, having prevailed before GAO, ‘“the [g]overnment’s
defense of a case arising from an
administrative decision is reasonable where it is not clear that
the administrative decision was
erroneous.’” Def.’s Opp’n at 4-5 (quoting Trone v. United
States, 3 Cl. Ct. 690, 693 (1983), and
citing Engles v. United States, 2 Cl. Ct. 166 (1983), and Stolpe
v. United States, 36 Fed. Cl. 259,
266 (1996)).
The government’s reliance on the set of decisions by GAO is
problematic. The court
specifically disavowed and refused to follow those precedents.
See Geo-Seis, 77 Fed. Cl. at 645
n.28. More importantly, the government’s argument based on the
GAO precedents sidesteps the
basis for the court’s decision on the merits. The court looked
directly to the provisions of the
FAR that governed the procurement and held that “[t]he plain
language of FAR § 52.215-
1(c)(3)(ii)(A) precluded the Sealift Command’s consideration of
Presidential’s revised
proposals.” Geo-Seis, 77 Fed. Cl. at 645.3 After examining the
regulatory history of revisions
made to the FAR in 1997, id. at 642-45, the court concluded that
those revisions expressly
rejected the position taken by the Contracting Officer in the
challenged procurement, i.e., that she
could issue a post-deadline amendment to the solicitation
allowing a late proposal where doing
so was “in the best interest of the [g]overnment.” Id. at 637
(quoting AR 342 (Mem. to file from
Stangler and Kimm (Mar. 22, 2006))). Proposed revisions to the
FAR in 1996 would have
allowed just that sort of discretion on the part of a
contracting officer, id. at 642 (citing and
quoting Federal Acquisition Regulation; Part 15 Rewrite–Phase I,
61 Fed. Reg. 48,380, 48,380-
81 (Sept. 12, 1996)), but those proposed revisions were not
adopted on the ground that they gave
too much discretion to a contracting officer. Id. at 643 (citing
and quoting Federal Acquisition
Regulation; Part 15 Rewrite; Contracting by Negotiation and
Competitive Range Determination,
62 Fed. Reg. 51,224 (Sept. 30, 1997)). Thus, the FAR, not GAO
and not the court, established
the parameters for the Contracting Officer’s action. “[T]he FAR
Councils [the Civilian Agency
Acquisition Council and the Defense Acquisition Regulations
Council] specifically addressed th[e attendant] policy issues in the 1997 reconsideration of the
FAR, and th[e] court should not undercut that resolution by a
contrary decision in this case.” Id. at 646. In short,
even if the line of GAO decisions had some basis prior to the
1997 revisions to the FAR, which itself is a dubious
proposition, those decisions could not have retained any
vitality after those revisions.
The government’s position will not be found to be reasonable or
substantially justified
when explicit, unambiguous regulations directly contradict that
position. See Hillensbeck, 74
Fed. Cl. at 481 (government’s position conflicted with
unambiguous statutory definition and
regulations); Loomis, 74 Fed. Cl. at 355 (military failed to
comply with its own regulations). The
government argues that Hillensbeck is “readily distinguishable”
from the instant case because the
agency here did not “rel[y] upon an internal agency
interpretation of a statute,” but, rather, “[the]
M[ilitary] S[ealift] C[ommand] relied upon a line of protest
decisions from the GAO . . . [which
is] statutorily mandated to render such decisions.” Def.’s Opp’n
at 6. The proffered distinction
is not meaningful. The actions of the Sealift Command’s
Contracting Officer contravened the
FAR, and the GAO precedents could not excuse that deviation from
legal requirements. In short,
“there is no justification for the government’s position when
clear, unambiguous regulations
directly contradict that position.” Filtration Dev. Co. v.
United States, 63 Fed. Cl. 612, 621
(2005).
Accordingly, the government has not met its burden of proving
that its position was
substantially justified. Geo-Seis’ claim satisfies the
requirements of the EAJA.
(sections deleted)
The clerk shall enter judgment for plaintiff in the total amount
of
$101,915.26. (Geo-Seis
Helicopters, Inc., v. U. S. and Presidential Airways, Inc.,
07-155C, Reissued October 31, 2007) (pdf)
The Court of Claims recognized in Severin v. United States that
if a contractor proved that “in the performance of [its]
contract with the Government [it] became liable to [its]
subcontractor for the damages which the latter suffered, . . .
[this] might well constitute actual damages” recoverable by the
contractor, even though the contractor has not yet paid the
subcontractor. 99 Ct. Cl. 435, 443 (1943). In the absence of
such proof, however, the Court of Claims made clear that a
contractor is precluded from recovering in its claim for damages
those losses suffered by its subcontractor. Id. at 443-44.
Notwithstanding an opportunity to supplement its initially
submitted documentary evidence to support its claim for bid
proposal and preparation costs, plaintiff has declined even to
submit corroborating declarations from its subcontractors
regarding the respective payment obligations between plaintiff
and the subcontractors. The Court of Claims recognized in
Severin that, in the absence of proof of a contractor’s
liability to a subcontractor, a contractor is precluded from
recovering in its claim for damages those losses suffered by its
subcontractor. 99 Ct. Cl. at 443-44. The court finds that
plaintiff has failed to carry its burden of proof in this case
and DENIES, as part of plaintiff’s claim for bid proposal and
preparation costs, the recovery of those expenses incurred by
plaintiff’s subcontractors in connection with the bid
preparation at issue here.
In this case, plaintiff has submitted no evidence regarding its
directly incurred bid preparation costs. Notwithstanding the
court’s order directing plaintiff to provide specific
documentary evidence in support of its claim, plaintiff has
declined to expend the effort to prove its claim. Plaintiff
states that “to spend significant amounts of money on Italian
lawyers and accountants to verify and further substantiate it
case . . . [would] not be prudent from a business standpoint
considering the amount of time and energy and money already
spent in pursuing this case.” Pl.’s Claim Supp. at 3. The court,
however, fails to see why it would have been necessary to hire
“Italian lawyers and accountants” to provide such basic evidence
as tax or payroll records. In the absence of any evidence of the
bid preparation costs directly incurred by plaintiff,
plaintiff’s claim is wholly unsupported and legally
insufficient. Accordingly,the court DENIES plaintiff’s claim for
its directly incurred bid preparation and proposal costs. (Impressa
Construzioni Geom. Domenico Garufi v. U. S., No. 99-400C,
c/w 01-708C, June 30, 2004) (pdf)
Where, as here, a teaming agreement or subcontract “expressly
negates any liability of the prime contractor to the
subcontractor,” the prime may not recover those costs. Donovan
Constr. Co.v. United States, 138 Ct. Cl. 97, 99 (1957), cert.
denied, 355 U.S. 826 (construing United States v.Blair, 321 U.S.
730, 737 (1944)). As our appellate authority held:
Quite logically where the subcontract absolves the prime
contractor from liability to his subcontractor there can be no
derivative liability of the Government to the subcontractor
even where the Government would otherwise be culpable, for
actual damage to the prime is a prerequisite to recovery
either for himself or for those subordinate to him.
Gardner Displays Co. v. United States, 346 F.2d 585, 586-87 (Ct.
Cl. 1965).
Because Plaintiff’s teaming agreements with ILC Dover and CUBRC
clearly indicate that Plaintiff was under no obligation to
compensate its teammates for their B&P costs, Gentex may not
recover those costs on their behalf in this action. Gentex’s
post hoc agreement to reimburse their B&P costs if it recovers
them in this action does not create an obligation or liability
sufficient to imbue Gentex with the requisite actual injury
necessary for standing. Absent such obligation, the Court would
be allowing a plaintiff to raise another entity’s legal rights
and recover the damages of nonparties in disregard of
traditional threshold requirements of standing. Allen, 468 U.S.
at 751.
Plaintiff has asked that a 15% markup, or “profit,” be included
in its bid preparation and proposal costs. However, because
profit is not a cost incurred in the bid preparation and
proposal process, the Court denies recovery. (Gentex
Corporation v. U. S., No. 03-728C, June 10, 2004, June 18,
2004) (pdf)
Balancing the hardships between the government and WPS on the
one hand and PGBA on the other, the Court determines that
adequate justification does not exist to set aside the contract
and require a new round of solicitation. This procurement has
already lasted nearly one and one half years, from the issuance
of the RFP in September 2002 to the anticipated work
commencement date of April 1, 2004, and WPS avers that it has
expended significant resources preparing for implementation.
Interv.-Def.’s Opp. at 63; Interv.-Def.’s Reply at 24. Revoking
the contract and requiring a new solicitation would likely
engender an additional delay of at least the same length. In
light of these considerations, the Court determines that the
balance of 30 hardships weighs in favor of denying PGBA’s
request for declaratory relief. In a bid protest case, 28 U.S.C.
§ 1491(b)(2) provides that “[t]o afford relief in such an
action, the court[] may award any relief that the court
considers proper, including declaratory and injunctive relief
except that any monetary relief shall be limited to bid
preparation and proposal costs.” In the circumstances of this
case, the Court has determined that PGBA is entitled to recover
its reasonable costs incurred in preparing its proposal for the
TDEFIC solicitation. “[A]losing competitor may recover the costs
of preparing its unsuccessful proposal if it can establish that
the Government’s consideration of the proposal submitted was
arbitrary or capricious or in violation of applicable statute or
regulation.” Gentex Corp., 58 Fed. Cl. at 656 (citing CSE Constr.
Co. v. United States, 58 Fed. Cl. 230, 262- 3 (2003); 28 U.S.C.
§ 1491(b)(2)). In light of the errors discussed above and
because PGBA was prejudiced by such errors, PGBA may recover its
bid preparation and proposal costs. The amount of such recovery
shall be determined through further proceedings in this action.
(PGBA, LLC,v. U. S. (Defendant) and
Wisconsin Physicians Service Insurance Corporation
(Intervening-Defendant); No. 03-2773C, March 31, 2004,
Reissued April 22, 2004.) (pdf) |
|
|
U. S. Court of Federal Claims
-
Listing of Decisions |
|
For
the Government |
For
the Protester |
|
Impressa Construzioni Geom. Domenico
Garufi v. U. S., No. 99-400C, c/w 01-708C, June 30, 2004 (pdf) |
Geo-Seis Helicopters, Inc., v. U. S. and
Presidential Airways, Inc., 07-155C, Reissued October 31, 2007 (pdf) |
|
Gentex Corporation v. U. S., No.
03-728C, June 10, 2004, June 18, 2004 (pdf) |
PGBA, LLC,v. U. S. (Defendant) and
Wisconsin Physicians Service Insurance Corporation
(Intervening-Defendant); No. 03-2773C, March 31, 2004,
Reissued April 22, 2004 (pdf) |
| Lion
Raisins, Inc, Nos. 01-322C & 01-536C, March 20, 2002 |
Lion
Raisins, Inc, Nos. 01-322C & 01-536C, June 10, 2002 |
|
|