4
CFR 21.8:
Corrective
Action Taken by Agency |
|
Comptroller
General - Key Excerpts |
|
NGTS challenges
the extent of the proposed corrective action. NGTS asserts that
the corrective action is unduly limited, and that the agency
instead should reopen discussions with all offerors followed by
the opportunity to generally revise proposals.
Contracting officers in negotiated procurements have broad
discretion to take corrective action where the agency determines
that such action is necessary to ensure a fair and impartial
competition. Domain Name Alliance Registry, B-310803.2, Aug. 18,
2008, 2008 CPD para. 168 at 8. As a general matter, the details
of a corrective action are within the sound discretion and
judgment of the contracting agency. Rockwell Elec. Commerce
Corp., B‑286201.6, Aug. 30, 2001, 2001 CPD para. 162 at 4. In
this regard, an agency's discretion when taking corrective
action extends to a decision on the scope of proposal revisions,
and there are circumstances where an agency may reasonably
decide to limit the revisions offerors may make to their
proposals. See, e.g., Honeywell Tech. Solutions, Inc.,
B‑400771.6, Nov. 23, 2009, 2009 CPD para. 240 at 4; Domain Name
Alliance Registry, supra; Rel-Tek Sys. & Design,
Inc.-Modification of Remedy, B‑280463.7, July 1, 1999, 99-2 CPD
para. 1 at 3. We generally will not object to the specific
corrective action, so long as it is appropriate to remedy the
concern that caused the agency to take corrective action.
Networks Elec. Corp., B‑290666.3, Sept. 30, 2002, 2002 CPD para.
173 at 3.
Here, the Army's intended corrective action focused not only on
the very procurement deficiency (an unreasonable past
performance evaluation) that led to GAO's ADR prediction that
L‑3's protest would be sustained, but also on the concerns
expressed by GAO regarding the adequacy of the evaluation of the
performance of the EO/IR sensors as part of the offerors'
proposed EMARSS systems. Since the agency's corrective action
responded to the areas of concern identified by GAO, and nothing
in NGTS's protest demonstrates that the agency's approach was an
abuse of discretion, we deny NGTS's protest regarding the scope
of the corrective action. Intermarkets Global, B-400660.10;
B-400660.11, Feb. 2, 2011, 2011 CPD para. 30 at 3; cf., Lockheed
Martin Sys. Integration‑‑Owego; Sikorsky Aircraft Co.,
B‑299145.5; B‑299145.6, Aug. 30, 2007, 2007 CPD para. 155 at 6
(change in evaluation methodology required opportunity to
respond to revised scheme).
NGTS asserts that in reexamining the performance validations for
the offerors' EMARSS systems, including considering information
learned as a result of the protest process, it is likely that
the agency essentially will conduct unequal discussions. We need
not now resolve this dispute, since we view NGTS's assertion of
unequal discussions as premature, given that an award decision
has not yet been made. If NGTS is not selected for award, it may
raise whatever evaluation errors it deems appropriate, including
unequal discussions, at that time. See Intermarkets Global,
supra, at 4-5; American K-9 Detection Servs., Inc., B-400464.6,
May 5, 2009, 2009 CPD para. 107 at 5. (Northrop
Grumman Technical Services, Inc., B-404636.11, June 15,
2011) (pdf)
Northrop requests
that we recommend that the agency reinstate the task order
previously issued to it. In the alternative, Northrop requests
that we recommend that the agency tailor its corrective action
and limit it to only that which is necessary to remedy any
demonstrable errors in the earlier acquisition. In this regard,
Northrop proposes various graduated levels of corrective action,
including, for example, a limited reevaluation of the proposals,
limited discussions with the offerors, or the issuance of a
separate solicitation for some of the agency's requirements
while leaving the remainder of the requirement under Northrop's
previously issued task order.
As a general rule, agencies have broad discretion to take
corrective action where the agency has determined that such
action is necessary to ensure fair and impartial competition.
Greentree Transp. Co., Inc., B-403556.2, Dec. 10, 2010, 2010 CPD
para. 293 at 2. The details of implementing the corrective
action are within the sound discretion and judgment of the
contracting agency, and we will not object to any particular
corrective action, so long as it is appropriate to remedy the
concern that caused the agency to take corrective action.
Partnership for Response and Recovery, B-298443.4, Dec. 18,
2006, 2007 CPD para. 3 at 3. Additionally, we have recognized
that the possibility that a contract may not have been awarded
based on a fair determination of the most advantageous proposal
has a more harmful effect on the integrity of the competitive
procurement system than does the possibility that the original
awardee will be at a disadvantage in a reopened procurement
because its price has been exposed. Id. at 4.
We have recognized a limited exception under which we will
object to an agency's corrective action if the record
establishes either that there was no impropriety in the original
evaluation and award decision, or where there was an actual
impropriety, but it was not prejudicial to any of the offerors.
Security Consultants Group, Inc., B-293344.2, Mar. 19, 2004,
2004 CPD para. 53 at 2-3. In comparison, where, for example, an
agency's proposed corrective action goes beyond what our Office
originally may have recommended in connection with sustaining a
protest, the agency's decision to pursue such a course of action
does not, by itself, provide a basis for protest, absent some
showing that the agency's actions are contrary to procurement
law or regulation, or otherwise are improper. See C2C Solutions,
Inc.; Trust Solutions, LLC, B-401106.6, B-401106.7, June 21,
2010, 2010 CPD para. 145 at 3; see also NavCom Defense Elec.,
Inc., B-276163.3, Oct. 31, 1997, 97-2 CPD para. 126 at 3.
On the record here, we have no basis to object to GSA's proposed
corrective action. The agency explains that it determined from
the results of the original competition that its requirements
may not have been adequately defined. In this regard, after it
issued the original TOR, the agency amended the solicitation to
add a significant requirement for optional operations and
maintenance (O&M) work to be performed outside of the St.
Elizabeth's campus. Specifically, section B of the solicitation
was amended to add optional CLINs 004B, 1004B and 2004B (each of
these CLINS has several sub-CLINs representing annual
requirements for each year of the multi-year periods of
performance). While the CLINs included ceiling dollar value
amounts (totaling $1,080,000,000), there was no further
narrative description of the requirement in this section of the
TOR. TOR, at B-4, B-6 and B-8.
Elsewhere in the TOR, there were two brief narrative references
to the added services. First, the overview section of the
statement of work provided, in relevant part, as follows:
"Operations and Maintenance for DHS Headquarters personnel that
do not move onto the campus are within the scope of this task
order." TOR, at C-3. Second, the service desk section of the
statement of work provided:
In addition, on an optional basis the Government may have the
contractor support approximately 7,000 DHS HQ employees
operating outside of the St. Elizabeth's campus in the
National Capitol Region.
TOR, at C-11. The TOR included an additional reference to this
added requirement; firms were instructed to submit a performance
work statement that was structured around seven broad tasks, and
task 4 included a reference to the optional O&M requirement. TOR,
at C-15. Aside from these references to the optional O&M
requirement, the TOR did not include any specific details
concerning the nature of the services, the location where they
would be performed, or any other details relating to the
operating environments where the services were to be provided.
The lack of detail in this regard resulted in two bidder
questions and answers, but the agency's answers did not provide
any further specific elaboration concerning the agency's
substantive requirements. The first question provided:
Q. The government in amendment 1 added the optional
requirements of providing Operations and Maintenance (O&M)
support to the residents of DHS that would not be moving to
the St. Elizabeth's campus. By doing so they added an
additional $1B[illion] in contract ceiling to the TOR. However
the government didn't provide any information that would be
needed to support those customers such as the locations and
number of employees by facility. What their current O&M
environments are; additional systems requirements analysis and
design for those off campus; installation and testing
requirements for those off campus.
A. Government will evaluate the proposed concept of how the
O&M requirement will be handled. The ceiling (plug) number to
bid to ($1B[illion]) is provided, so that won't affect
pricing.
TOR, amend. 6, May 25, 2010, question No. 257. The second
question related to how the offerors should bid what the agency
described as the $1B ceiling value (and specifically was
concerned with what would be required during performance should
the ceiling amount be exceeded), but this second question
provided no additional discussion concerning the substantive
details of the agency's requirements, and again directed firms
simply to "bid to the plug number." Id., question No. 261.
The record shows that the offerors diverged widely in their
responses to the O&M requirement, and that the agency viewed the
responses from three of the five competitors in this area as so
deficient as to render their proposals technically unacceptable
and, thus, ineligible for further evaluation or award
consideration. Specifically, the agency had developed an
independent government cost estimate (IGCE) for the O&M
requirement which was based on an agency staffing estimate of
22,530,909 labor hours. Using the IGCE staffing estimate as a
standard against which to evaluate the offerors' proposals, the
agency found three of the proposals unacceptable for having
offered inadequate staffing to perform the requirement. One of
the three offerors proposed to perform the O&M requirement using
[deleted] labor hours; a second offeror proposed [deleted] labor
hours; and a third offeror proposed [deleted] labor hours. (In
comparison, [deleted]; Northrop proposed [deleted] hours and the
other firm proposed [deleted] hours. AR, exh. 5, at 63, 120.)
The record shows that, once the agency found the proposals
technically unacceptable for failing to offer adequate staffing,
it discontinued its evaluation, and did not give consideration
to the price proposals of the unacceptable offerors. AR, exh. 7,
at 38.
Having found that four of the five competitors submitted
technically unacceptable proposals, the agency made award on the
basis of initial proposals to Northrop, notwithstanding the fact
that its proposed price was [deleted] among the competitors (and
exceeded the low price by more than $[deleted] million). In
making its award decision, the agency did not perform a
cost/technical tradeoff because it had eliminated the other
offers from consideration. AR, exh. 7, at 38. The record also
shows that, although these four proposals were found technically
unacceptable for offering inadequate staffing, they otherwise
received relatively high, closely ranked, scores under the
evaluation criteria not related to adequacy of proposed
staffing. AR, exh. 7, at 17.
We find the agency's decision to take corrective action in these
circumstances reasonable. As noted, the proposed levels of
effort for the O&M requirement varied significantly from one
another, with a low proposed level of effort of [deleted] labor
hours ([deleted] percent fewer hours than used for the IGCE); a
second proposal of [deleted] labor hours ([deleted] percent
fewer hours than used for the IGCE); and a third proposal of
[deleted] labor hours ([deleted] percent fewer hours than used
for the IGCE). Given the wide divergence in proposed levels of
effort for the O&M requirement, as well as the relative lack of
detail in the solicitation regarding this work, the agency
reasonably concluded that it had failed adequately to convey its
requirements to the offerors in a manner that would allow them
to compete intelligently, and on a relatively equal basis.
Northrop suggests that it was the offerors' business judgment,
rather than a lack of information relating to the agency's
requirements, that led them to deviate so dramatically in their
proposed staffing for the optional O&M requirement. Northrop
maintains that, because the agency included in the solicitation
a $1 billion "plug" price for purposes of preparing their
proposals, firms were on notice of how the agency wanted to have
this requirement staffed. We disagree.
The TOR characterized this and the other pricing information
included in section B as ceiling prices, rather than as "plug"
prices. TOR, section B. (Each of the CLINs included a ceiling
price, not just the optional O&M requirements CLINS). There is
nothing in the solicitation that indicated that the agency
expected the offerors to submit technical responses based on the
maximum level of effort possible under the ceiling prices, or
that the ceiling prices were anything other than an upper,
not-to-exceed limit on contractor compensation. In fact, the
agency specifically described the ceiling prices in a bidder
question and answer as follows: "The ceiling price is the
maximum that may be paid to the contractor except for any
adjustment under other contract clauses providing for equitable
adjustment or other revision of the contract price under stated
circumstances." TOR, amend. 6, May 25, 2010, question No. 19.
In contrast, insofar as the relationship of the ceiling prices
to the optional O&M requirements were concerned, the agency
advised offerors (in its answer to a bidders' question) that the
"Government will evaluate the proposed concept of how the O&M
requirement will be handled." TOR, amend. 6, May 25, 2010,
question No. 257. Such an evaluation approach presupposes that
different concepts or approaches (including different staffing
approaches and levels of effort) to meeting the O&M requirement
were anticipated by the agency and would be evaluated. Simply
stated, the agency's inclusion of the ceiling prices provided no
meaningful information or guidance relating to the agency's
desired staffing levels.
In summary, we find that the record provides an adequate basis
for the agency to have taken corrective action. As discussed,
the record supports the agency's conclusion that three of five
competitors may have been eliminated from the competition
because the offerors did not have adequate information to
compete intelligently and on a relatively equal basis. (Northrop
Grumman Information Technology, Inc., B-404263.6, March 1,
2011) (pdf)
As an initial
matter, IMG asserts that the corrective action is unduly
limited, and that the offerors instead should be given the
opportunity to generally revise their proposal.
Contracting officers in negotiated procurements have broad
discretion to take corrective action where the agency determines
that such action is necessary to ensure a fair and impartial
competition. Domain Name Alliance Registry, B-310803.2, Aug. 18,
2008, 2008 CPD para. 168 at 8. As a general matter, the details
of a corrective action are within the sound discretion and
judgment of the contracting agency. Rockwell Elec. Commerce
Corp., B‑286201.6, Aug. 30, 2001, 2001 CPD para. 162 at 4. In
this regard, an agency's discretion when taking corrective
action extends to a decision on the scope of proposal revisions,
and there are circumstances where an agency may reasonably
decide to limit the revisions offerors may make to their
proposals. See, e.g., Honeywell Technology Solutions, Inc.,
B‑400771.6, Nov. 23, 2009, 2009 CPD para. 240 at 4; Domain Name
Alliance Registry; Computer Assocs. Int'l, supra; Rel-Tek Sys. &
Design, Inc.-Modification of Remedy, B‑280463.7, July 1, 1999,
99-2 CPD para. 1 at 3. We generally will not object to the
specific corrective action, so long as it is appropriate to
remedy the concern that caused the agency to take corrective
action. Networks Elec. Corp., B‑290666.3, Sept. 30, 2002, 2002
CPD para. 173 at 3.
Here, DLA's corrective action first focused on the very
procurement deficiency (an unreasonable price realism
evaluation) that led to GAO's ADR prediction that the protests
would be sustained, and then turned to the other areas of
concern identified during the ADR. In this regard, the agency
amended the solicitation to clarify the assumed size of the
required warehouse pallets and the force protection
requirements, Amend. 26, and then advised offerors that they
could submit a final technical proposal revision addressing
either or both of these areas, as well as make any price
revisions for which the offeror could provide documented
evidence showing a direct link between changes in the proposal
resulting from the two clarifications and the proposed pricing.
DLA Letters to Offerors, Oct. 20, 2010. Since the agency's
corrective action responded to the areas of concern identified
by GAO, and nothing in IMG's protest demonstrates that the
agency's approach was an abuse of discretion, we deny IMG's
protest regarding the scope of the corrective action. Cf.,
Lockheed Martin Sys. Integration‑‑Owego; Sikorsky Aircraft Co.,
B‑299145.5; B‑299145.6, Aug. 30, 2007, 2007 CPD para. 155 at 6
(change in evaluation methodology required opportunity to
respond to revised scheme). (Intermarkets
Global, B-400660.10; B-400660.11, February 2, 2011) (pdf)
McKean argues
that the Navy's proposed corrective action goes beyond what is
required to address any concern with the cost evaluation, and is
therefore unreasonable.[3] Since McKean has hired many of the
incumbent personnel at the direction of the Navy, McKean argues
that requiring it to submit a revised proposal will harm its
chances of award.
Our Office requested that McKean further explain why it is
necessary to restrict the Navy's discretion in taking corrective
action here. McKean responded that BCI was not prejudiced by any
error in the cost realism analysis because McKean's evaluated
cost was significantly lower than BCI's. Thus, in McKean's view,
the error in the cost realism analysis did not prejudice BCI,
while the reopening of discussions will cause significant harm
to McKean's competitive position. Accordingly, McKean argues
that the Navy must limit its corrective action to a reevaluation
of the proposals submitted previously. McKean Response to GAO,
Nov. 3, 2009, at 5 (citing Security Consultants Group, Inc.,
B-293344.2, Mar. 19, 2004, 2004 CPD para. 53). We disagree.
In negotiated procurements, agencies have broad discretion to
take corrective action where they determine that such action is
necessary to ensure fair and impartial competition. MayaTech
Corp., B-400491.4, B‑400491.5, Feb. 25, 2009, 2009 CPD para. 55
at 3. Where the corrective action taken by an agency is
otherwise unobjectionable, a request for revised price proposals
is not improper merely because the awardee's price has been
exposed. Strand Hunt Constr., Inc., B-292415, Sept. 9, 2003,
2003 CPD para. 167 at 6. We have recognized a limited exception
to that rule where the record establishes that there was no
impropriety in the original evaluation and award, or that an
actual impropriety did not result in any prejudice to offerors;
where this is the case, reopening the competition after prices
have been disclosed does not provide any benefit to the
procurement system that would justify compromising the offerors'
competitive positions. Security Consultants Group, supra, at
2-3; Hawaii Int'l Movers, Inc., B‑248131, Aug. 3, 1992, 92-2 CPD
para. 67 at 6, recon. denied, Gunn Van Lines; Dept. of the
Navy--Recon., B-248131.2, B-248131.4, Nov. 10, 1992, 92-2 CPD
para. 336.
The Navy advises that it needs to reopen discussions to address
potentially significant changes, due to the passage of time, in
how the offerors will meet the agency's requirements. In our
view, this is a matter where the agency has considerable
discretion and we will not substitute our views for the Navy's
on how the agency should proceed, absent a showing that this
discretion is being abused. We see no such showing here.
Rather than being inconsistent with the rationale of our
decision in Security Consultants Group, we view that decision as
involving a critical difference. There, after identifying a flaw
(the solicitation did not disclose that the past performance
factor was nearly three times more significant than either of
the other non-price factors), it appeared that none of the
offerors had been competitively prejudiced by the incorrect
weighting described in the solicitation. Nevertheless, the
agency proposed to request revised proposals, but presented no
reason to reopen the competition. In contrast, here, the Navy
has presented both a flaw requiring corrective action (an error
in the cost realism evaluation) and a reasonable basis why
reopening the competition is appropriate to achieve a fair
competition--i.e., the likelihood that one or both offerors
would need to make significant personnel/ resume changes in
their initial proposals.
In our view the Navy has shown a reasonable basis for conducting
discussions and requesting revised proposals. Doing so is within
the discretion of the Navy to determine the scope of corrective
action, and therefore we will not substitute our judgment for
the agency's. (McKean Defense
Group--Information Technology, B-401702.2, LLC, January 11,
2010) (pdf)
The original RFP
contained three technical evaluation factors--technical
approach, management and staffing, and past performance. When
combined, those factors were significantly more important than
cost/price. Original RFP at 41. Three offerors, including the
awardee and the protester, submitted proposals. The earlier
protest followed contract award.
In response to that protest, the agency announced it would take
the following corrective action: amend the solicitation to
reflect that the combination of the technical factors is
approximately equal to (not significantly more important than)
price; accept revised proposals; reevaluate; and make a new
award decision. The contracting officer asserts that the protest
warranted corrective action for two main reasons. The protester
complained that it had not been accorded the opportunity to
respond to negative past performance information, as required by
Federal Acquisition Regulation sect. 15.306. The contracting
officer saw reopening the competition to allow the protester to
respond as "the only way to remedy the agency error in
evaluating adverse past performance information." Contracting
Officer's Statement of Facts at 2. The contracting officer also
discovered an error in section M of the RFP; contrary to the
terms of the original RFP, the agency did not intend for the
technical factors to be significantly more important than
cost/price. Accordingly, the RFP was amended to state that all
evaluation factors other than cost/price, when combined, are
approximately equal to cost/price. Id. at 3.
We see no basis to object to the agency's corrective action. The
contracting officer states that the original RFP was in error
when it identified the combined technical factors as
significantly more important than cost/price. Contracting
Officer's Statement of Facts at 3. A contracting agency properly
may take corrective action in order to rectify an error in the
solicitation concerning the basis for award, where there is no
evidence that the agency acted in other than good faith. Alfa
Consult S.A., B-298164.2, B-298288, Aug. 3, 2006, 2006 CPD para.
127 at 2. Here, the agency reasonably remedied the misstatement
of the relative weight of the evaluation factors by amending the
solicitation and requesting revised proposals.
The protester argues that the agency in fact acted in bad faith
and that its corrective action intentionally favored the prior
awardee. See Comments, Sept. 12, 2010 at 7. The protester offers
no evidence to support its assertion of agency bias, other than
its own bare allegation that the agency's actions improperly
favored the awardee. Government procurement officials are
presumed to act in good faith, and we will not attribute unfair
or prejudicial motives to them on the basis of inference or
supposition. Triton Marine Constr. Corp., B-250856, Feb. 23,
1993, 93-1 CPD para. 171 at 6. In the absence of any evidence of
bias in the record, we see no merit to this protest allegation.
The protester also asserts, correctly, that the agency's
corrective action does not address certain of the protester's
original protest grounds. For example, the protester asserted in
the underlying protest that the awardee had an unmitigated
conflict of interest. There is currently no contract award and,
therefore, no alleged violation of procurement regulation or
statute to protest. The protester's allegations are premised on
the agency making award to the same firm again, and, because
they anticipate allegedly improper agency action, they are
speculative and premature. Paramount Group, Inc., B-298082, June
15, 2006, 2006 CPD para. 98 at 6-7. Our Office will not assume
in advance that an agency will conduct its procurements
improperly. (Training
Management Solutions, Inc., B-403461.2, September 29, 2010)
(pdf)
Contracting
officers in negotiated procurements have broad discretion to
take corrective action where the agency determines that such
action is necessary to ensure a fair and impartial competition.
Domain Name Alliance Registry, B-310803.2, Aug. 18, 2008, 2008
CPD para. 168 at 8; Computer Assocs. Int'l, B-292077.2, Sept. 4,
2003, 2003 CPD para. 157 at 5. An agency's discretion when
taking corrective action also extends to a decision on the scope
of proposal revisions, and there are circumstances where an
agency may reasonably decide to limit the revisions offerors may
make to their proposals. See, e.g., Computer Assocs. Int'l,
supra; Rel-Tek Sys. & Design, Inc.--Modification of Remedy,
B-280463.7, July 1, 1999, 99-2 CPD para. 1 at 3. In instances
where the corrective action does not also include amending the
solicitation, we will not question an agency's decision to
restrict proposal revisions when taking corrective action so
long as it is reasonable in nature and remedies the established
or suspected procurement impropriety. See Consolidated Eng'g
Servs., Inc., B-293864.2, Oct. 25, 2004, 2004 CPD para. 214 at
3-4; Computer Assocs. Int'l, supra.
As a preliminary matter, the parties agree that NASA's
corrective action here does not include amending either the
solicitation's substantive requirements or evaluation scheme.
Additionally, Honeywell does not dispute that NASA's corrective
action remedies the established or suspected procurement
impropriety (i.e., the agency's evaluation of ITT's past
performance). Rather, the crux of Honeywell's objections is that
the agency's corrective action does not go far enough, insofar
as offerors should be permitted to submit unlimited proposal
revisions.
The agency's decision to limit the scope of its corrective
action was reasonable. As noted above, our January 27 decision
found that NASA's evaluation of ITT's past performance was
improper, but that Honeywell's remaining challenges to the
evaluation of offerors' proposals were without merit: in light
thereof, our recommendation was limited to remedying the
identified problem regarding the past performance evaluation.
Further, after the June 25 outcome prediction ADR conference,
NASA took corrective action to remedy the problem identified
regarding the past performance evaluation and, at the same time,
decided to obtain updated information from both offerors in that
area. In our view, NASA's decision to update the past
performance information from each offeror was a reasonable way
to remedy the identified procurement impropriety while not
affecting other portions of offerors' proposals and the
evaluation thereof. This approach has the added benefit of
reducing further cost and delay in the procurement. See Computer
Assocs. Int'l, Inc., supra; Serv-Air, Inc., B-258243.4, Mar. 3,
1995, 95-1 CPD para. 125 at 2-3. We therefore conclude that the
agency acted within its discretion in limiting the revisions
offerors may make to their proposals. (Honeywell
Technology Solutions, Inc., B-400771.6, November 23, 2009) (pdf)
First,
Pemco asserts that the agency was obligated to reopen
discussions with the offerors in order to obtain additional
information prior to performing the price realism and risk
analysis required by the solicitation and recommended by our
Office, and that its failure to do so rendered the subsequent
source selection decision improper.
As a general rule, the details of implementing recommendations
of our Office are within the sound discretion and judgment of
the contracting agency, and we will not question an agency’s
ultimate manner of compliance, so long as it remedies the
procurement impropriety that was the basis for our
recommendation. See, e. g., Partnership for Response and
Recovery, B-298443.4, Dec. 18, 2006, 2006 CPD para. 3 at 3;
ST Aerospace Engines Pte, Ltd., B-275725.3, Oct. 17, 1997, 97-2
CPD para. 106 at 5. In this regard, an agency’s discretion
generally extends to determining whether it is necessary to
reopen discussions and obtain proposal revisions. See SDS
Int’l, Inc. B‑291183.4, Apr. 28, 2003, 2003 CPD para. 127 at
6; Computer Assocs. Int’l, B‑292077.2, Sept. 4, 2003,
2003 CPD para. 157 at 5.
Here, our decision sustaining Pemco’s prior protest was based on
the absence of any agency documentation reflecting the agency’s
judgments regarding price realism and proposal risk in the
context of Boeing’s final proposal revisions. Pemco’s assertion
that the agency was required to reopen discussions appears to be
based on a perception that our Office found Boeing’s proposal to
be informationally deficient; we did not. In this regard, it is
not the function of our Office to evaluate proposals; rather, we
will examine the procurement record created by the agency to
determine whether the agency’s evaluation was consistent with
the solicitation requirements and applicable statutes and
regulations. E.g. Pacific Ship Repair and Fabrications,
B‑279793, July 23, 1998, 98-2 CPD para. 29 at 3‑4.
Since our prior decision was based on an informational
deficiency in the agency’s evaluation record, it was not
unreasonable for the agency to correct that deficiency by
performing, and documenting, the required analyses based on the
information that was already available. Pemco’s assertion that
the agency was obligated to reopen discussions with all of the
offerors is without merit. (Pemco
Aeroplex, Inc., B-310372.3, June 13, 2008) (pdf) (See
prior decision,
Pemco Aeroplex, Inc., B-310372,
December 27, 2007)
An agency’s discretion in the area of corrective action
extends to deciding the scope of proposal revisions, and there
are circumstances where an agency reasonably may decide to limit
revisions offerors make to their proposals. See, e.g., Computer
Assocs. Int’l, B-292077.2, Sept. 4, 2003, 2003 CPD para. 157 at
5. Where, as here, an agency decides to amend a solicitation
after closing and permit offerors to revise their proposals in
response, however, we think that offerors should be permitted to
revise any aspect of their proposals, including those that were
not the subject of the amendment, unless the agency offers
evidence that the amendment could not reasonably have any effect
on other aspects of proposals, or that allowing such revisions
would have a detrimental impact on the competitive process.
Unlike in prior cases where we found that agencies could limit
the extent to which proposals may be revised, see, e.g., Rel-Tek
Sys. & Design, Inc.--Modification of Remedy, supra; ST Aerospace
Engines Pte. Ltd., B-275725.3, Oct. 17, 1997, 97-2 CPD para. 106
at 4; System Planning Corp., B-244697.2, June 15, 1992, 92-1 CPD
para. 516 at 4, the agency has not made such a showing here. The
record does not contain any argument from the Navy that allowing
offerors to submit revised proposals would impair the
competitive process in any way. With respect to the effect of
the amendment on proposals, the Navy argues that it made no
revisions to the RFP that would have an impact on scheduling,
and thus there is no reason for it to permit offerors to revise
their proposed schedules. We disagree. Clearly, amending the
solicitation to permit exercise of the options for line items
0003-0007 for up to 365 days after notice to proceed for line
item 0001 could have an impact on offerors’ schedules, which
were based on exercise of these options 8 months after contract
award. Even to the extent that the delay in the performance
period could not reasonably be expected to have an impact on the
sequencing and duration of the various construction tasks, we
agree with the protester that it could be expected to have an
impact on schedule-related matters such as the availability of
subcontractors and, depending on the time of year at which
notice to proceed is issued, accounting for holiday periods. We
are also persuaded that where, as here, price revisions are
permitted, offerors should be allowed to revise any portions of
their technical proposals that could have an impact on their
pricing, which clearly would include schedule. In sum, without
some rational basis for denying offerors the ability to make
revisions to all portions of their proposals, we think the
Navy’s decision to limit the scope of revisions to technical
proposals was unreasonable. Accordingly, we sustain CMR’s
protest against the agency’s failure to permit it to revise its
schedule in its final offer. (Cooperativa
Muratori Riuniti, B-294980.5, July 27, 2005) (pdf)
As a preliminary matter, although it characterizes its
current filing as a request for reconsideration, Envirosolve does
not argue that we should not have dismissed its earlier protest
because the agencys proposed corrective action did not, in fact,
render the protest academic. Compare Saltwater Inc.--Recon. and
Costs , B-294121.3, B-294121.4, Feb.8, 2005, 2005 CPD 33. Instead,
Envirosolve argues that DEA has failed to take the corrective
action promised within the time period promised. A protest, like
the one here, that was once academic is not revived by subsequent
agency action or inaction. Rather, the subsequent agency conduct
gives rise to a new basis for protest even if some of the issues
raised by the subsequent action are the same as the issues raised
under the earlier protest. See Lackland 21st Century Servs.
Consol.--Protest and Costs , B-285938.6, July 13, 2001, 2001 CPD
124 at 4. (Envirosolve LLC,
B-294974.4, June 8, 2005) (pdf)
Four vendors, including CMC and SSG, submitted
quotations, which were evaluated by the then-cognizant contracting
officer, who alone evaluated their technical qualifications. The
contracting officer summarized her adjectival ratings in matrix
form and, without identifying the vendors by name, furnished them
to the three member technical evaluation panel (TEP) for review.
Based on this review, bidder 1 (SSG) was rated technically lower,
and had a lower price, than bidder 2 (CMC); the TEP thus
recommended award to CMC. After awarding the contract to CMC, the
contracting officer left federal service and was replaced by
another individual. Thereafter, SSG requested a debriefing, but
when the replacement contracting officer reviewed the contracting
file, she determined that the evaluation was so flawed that it had
to be redone. She notified the vendors and had the TEP review each
vendor's quotation, individually score them, and then complete a
consensus evaluation. The TEP's consensus evaluation rated CMC's
quotation as good under the technical factor and unsatisfactory
under the past performance factor, while rating SSG's quotation as
outstanding under both factors. Based on SSG's technical ratings
and low price, the contracting officer terminated CMC's contract
and made award to SSG. Upon learning of the termination of its
contract and the new award, CMC filed this protest. Here, the
replacement contracting officer's decision to take corrective
action was both reasonable and appropriate because the original
evaluation and its record were significantly flawed. Specifically,
even though the quotations were to be evaluated on the basis of
technical qualifications and past performance, there was
nothing--no strengths or weaknesses--listed in the evaluation
record to support the original contracting officer's adjectival
ratings for the vendors. Further, the evaluation matrix was
inconsistent with SSG's past performance information.
Specifically, one of SSG's past performance questionnaire
respondents had indicated that he would do business with SSG
again, and the other had indicated that he "maybe" would do
business with SSG again. However, the original evaluation matrix
indicated that these respondents had answered "maybe" and "no," a
significant difference. Moreover, the TEP members, charged with
responsibility for evaluating the proposals, had not reviewed
either proposal before making their initial award recommendation.
Given the agency's reliance on erroneous information, the lack of
supporting narrative, and the absence from the record of any
information supporting the TEP's award recommendation, the award
determination was unsupportable and potentially subject to a
successful protest challenge. U.S. Defense Sys., Inc. , supra .
Under these circumstances it was within the agency's discretion to
reevaluate the quotations and make a new award determination based
on a fully documented evaluation record. Since following this
course resulted in a determination that SSG's proposal, rather
than CMC's, represented the best value, the termination of CMC's
contract and issuance of a new contract to SSG were
unobjectionable. (CMC &
Maintenance, Inc., B-293803.2, December 2, 2004) (pdf)
Under the circumstances here, it was reasonable for the
agency to limit the vendors’ submissions to revised price quotes.
As noted above, USDA determined that its evaluation of CA’s price
quote may have been improper, and that the subsequent source
selection decision had not been adequately documented. By
contrast, the agency found nothing improper in its evaluation of
the vendors’ technical quotes and found no merit to CA’s
allegation concerning an unstated minimum requirement for an
integrated multiple platform software product. The agency also
determined that the cost of conducting the initial technical
evaluation of quotes--and presumably, the approximate cost for
conducting a second technical evaluation of quotes--was more than
$42,000. Contracting Officer’s Statement, June 18, 2003, at 1; AR,
Tab F, TET Leader Statement, June 20, 2003, at 2-3. In our view,
USDA’s limited request for price information from each vendor was
a reasonable way to remedy the suspected procurement impropriety
while not affecting other portions of vendors’ quotes and the
evaluation thereof. This approach has the added benefit of
reducing further cost and delay in the procurement. We therefore
conclude that the agency acted within its discretion in limiting
the revisions vendors may make to their quotes. (Computer
Associates International, Inc., B-292077.2, September 4, 2003)
(pdf)
To the extent HTI contends that the corrective action
had no effect on the competition and merely “glosses over”
improprieties in the solicitation, Comments at 3-7, its
disagreement with the scope of the corrective action--that the
agency’s corrective action did not remedy HTI’s challenge to the
agency’s evaluation of PCCI’s proposal and the award
decision--does not provide a basis to question the agency’s
actions. We think the VA’s decision to solicit and evaluate
revised proposals and to make a new best-value determination based
on that reevaluation renders academic HTI’s protest of the initial
evaluation and award decision. In short, the other alleged
deficiencies or improprieties identified in HTI’s earlier protest
became moot where the agency’s decision to reopen the competition
and make a new best value determination afforded the protester
another opportunity to be considered for award. (Hyperbaric
Technologies, Inc., B-293047.2; B-293047.3, February 11, 2004)
The Air Force determined that, despite amendment No.
0001 and the FedBizOpps posting, some offerors had been
confused regarding the pricing instructions, and that
corrective action was appropriate. On October 23, the Air
Force notified PCA of its intended corrective action, and
on November 3 the agency rescinded the award. PCA contends
that corrective action was unwarranted and “not supported
by any credible evidence.” Supplemental Comments at 2. The
protester argues that the corrective action would be
proper only if AIM “was in fact misled” by the
solicitation or by the agency’s letters and amendments
aimed at clarifying the pricing. Id. In this regard, PCA
argues that “no one was disadvantaged by the omission (on
some [September 15] letters) of the ‘critical sentence’,”
because all letters advised offerors to refer to amendment
No. 0001 and to the FedBizOpps memo, receipt of which AIM
acknowledged in its protest. Comments at 2. In negotiated
procurements, agencies have broad discretion to take
corrective action where they determine that such action is
necessary to ensure fair and impartial competition.
Patriot Contract Servs., LLC et al., B-278276.11 et al.,
Sept. 22, 1998, 98‑2 CPD ¶ 77 at 4. Where an agency has
reasonable concerns that there were errors in a
procurement, the agency may take corrective action, even
if it is not certain that a protest of the procurement
would be sustained. Main Bldg. Maint., Inc., B‑279191.3,
Aug. 5, 1998, 98-2 CPD ¶ 47 at 3. We will not object to
proposed corrective action, so long as it is appropriate
to remedy the concern that caused the agency to take
corrective action. Network Elec. Corp., B-290666.3, Sept.
30, 2002 CPD ¶ 173 at 3. The corrective action here is
unobjectionable. The prices received varied
dramatically--as noted above, from approximately [DELETED]
to [DELETED] for all offerors and from [DELETED] to
[DELETED] for competitive range offerors--and the agency
concluded that the offerors’ approaches to pricing
titanium was the likely cause of the disparity,
notwithstanding its efforts to clarify the CAP line item.
We have recognized that such dramatic price differentials
may reasonably be interpreted to suggest that offerors had
dissimilar understandings of the requirements. See Federal
Sec. Sys., Inc., B-281745.2, Apr. 29, 1999, 99-1 CPD ¶ 86
at 5. In these circumstances, agencies are not required to
ignore the reasonable possibility that the disparate
prices received do not accurately reflect the competitive
marketplace, and that the award based on those prices may
not reflect the most advantageous proposal. Thus,
notwithstanding the protester’s arguments to the
contrary--to the effect that all offerors should have
understood titanium pricing under the CAP line item--there
was nothing unreasonable in the agency’s determination
that corrective action was necessary to ensure both that
the competition was fair and that the award would be based
on the most advantageous proposal. (PCA
Aerospace, Inc., B-293042.3, February 17, 2004)
(pdf)
The agency’s acceptance of Strand’s noncompliant
proposal meant that the agency waived these design
criteria for Strand, which resulted in an unfair and
unequal evaluation. It is a fundamental principle of
federal procurement that competition must be conducted on
an equal basis; that is, offerors must be treated equally
and be provided with a common basis for the preparation of
their proposals. SWR, Inc., B-284075, B-284075.2, Feb. 16,
2000, 2000 CPD ¶ 43 at 3. Accordingly, the Corps
reasonably determined that it was necessary to terminate
Strand’s contract in order to correct the improper award.
(Strand Hunt Construction, Inc.,
B-292415, September 9, 2003) (pdf)
While, as the protester suggests, a more comprehensive
method of implementing our recommendation could have been
chosen by the Air Force, including reopening discussions
and obtaining revised proposals and reevaluating past
performance, the agency has stated a reasonable basis for
not performing these actions. Specifically, the record
does not show any weaknesses or deficiencies in SDS's
proposal that required discussions. Moreover, SDS
has offered no new evidence, not considered in our prior
decision, that would indicate that the past performance
ratings of SDS and CBD were not reasonable. Finally, it
was within the discretion of the agency to consider the
mission capability factor as a whole, since our prior
decision did not preclude this evaluation and it has
offered a reasonable explanation (set forth above) as to
why it was necessary. (SDS
International, Inc., B-291183.4; B-291183.5, April 28,
2003)
Considering the actual staffing included in SMI's FPR
pricing was consistent with the scope of the reopened
discussions. SMI's explanation that its FPR pricing
included an additional risk mitigation allowance of
[DELETED] FTEs was responsive to the goal established for
the reopened discussions--that SMI demonstrate the realism
of its proposed pricing, including demonstrating that it
was offering adequate staffing. Indeed, the agency would
have failed in its obligation to evaluate the
reasonableness of the proposed pricing had it not
considered the actual staffing included in SMI's pricing.
Also consistent with the limitations established in the
reopened solicitation is the fact that the additional
staffing was not used to alter the evaluation of SMI's
organization and management plans, small business
subcontracting plan, and past performance. RFP § M.3.4.2.
We conclude that USMC reasonably evaluated SMI's second
FPR based on a staffing level of [DELETED] FTEs. J.W. (Holding
Group & Associates, Inc., B-285882.11; B-285882.12,
October 23, 2002) (pdf)
Where, as here, an agency has improperly conducted
discussions with only one offeror after receipt of
proposals, reopening the competition and seeking another
round of amended proposals is an appropriate way to
remedy the underlying deficiency and permit offerors a
fair opportunity to compete. International Res.
Group, B-286683, Jan. 31, 2001, 2001 CPD ¶ 35.
The disclosure of pricing and other information in
another offeror's proposal, as here, is permissible
because the possibility that the contract may not have
been awarded based on a true determination of the most
advantageous proposal has a more harmful effect on the
integrity of the competitive procurement system than the
fear of an auction; the statutory requirements for
competition take priority over any possible constraints
on auction techniques. Federal Sec. Sys., Inc.,
supra, at 4. Accordingly, the agency's
corrective action of disclosure and placing the offerors
on an even footing, and providing them with an equal
opportunity to compete by submitting new proposals is
unobjectionable here. (Networks
Electronic Corporation, B-290666.3, September 30,
2002) (pdf)
Where agency took corrective action
in response to an earlier protest by amending the solicitation
and reopening discussions, the prior disclosure of protester's
prices and the request for final proposal revisions did not
create an improper auction. (Clearwater
Instrumentation, Inc., B-286454.2, September 12, 2001)
As a general matter, the
details of implementing our recommendations for
corrective action are within the sound discretion and
judgment of the contracting agency. Rel-Tek Sys. &
Design, Inc.--Modification of Remedy, B-280463.7, July
1, 1999, 99-2 CPD para. 1 at 3. Such discretion must be
exercised reasonably and in a fashion that remedies the
procurement impropriety that was the basis for our
protest recommendation. The Futures Group Int'l,
B-281274.5 et al., Mar. 10, 2000, 2000 CPD para. 148 at
8; CitiWest Properties, Inc., B-274689.4, Nov. 26, 1997,
98-1 CPD para. 3 at 6. Here, the agency did not act
reasonably in reopening discussions only with MCI, nor
did the agency's remedy resolve all the improprieties
that were the basis for our decision sustaining the
prior protest. (Rockwell
Electronic Commerce Corporation, B-286201.6, August
30, 2001) (pdf)
A protest,
like the one here, that was once academic is not
"revived" by subsequent agency action.
Instead, the subsequent action gives rise to a new basis
for protest, even if some of the issues raised by the
subsequent action are the same as the issues raised
under the earlier protest. See Pemco Aeroplex,
Inc.-Recon. and Costs, B-275587.5, B-275587.6, Oct. 14,
1997, 97-2 CPD para. 102 at 4-5. With respect to the
specific request here, on December 13, the Air Force
conceded that its initial decision that it would be more
economical to perform base operations support at
Lackland in-house, rather than contract out this effort,
was improper. Thus, the decision that L-21 would have us
consider no longer exists, and any dispute about that
decision has been rendered academic by the concession in
the Air Force's letter of December 13. QuanTech,
Inc.--Costs, B-278380.3, June 17, 1998, 98-1 CPD para.
165 at 2. (A-76 issue) (Lackland
21st Century Services Consolidated--Protest and Costs,
B-285938.6, July 13, 2001)
Generally, we decline to
review the termination of contracts for the convenience
of the government because such actions are matters of
contract administration. We will review the propriety of
the termination where the termination flows from a
defect the contracting agency perceived in the award
process. In such cases, we examine the award procedures
that underlie the termination action for the limited
purpose of determining whether the initial award may
have been improper and, if so, whether the corrective
action taken was appropriate to protect the integrity of
the competitive procurement system. GAI, Inc., B-247962,
B-247971, July 8, 1992, 92-2 CPD para. 10 at 3. We will
not object to an agency's proposed corrective action
where the agency concludes that the award, because of
perceived flaws in the procurement process, was not
necessarily made on the basis most advantageous to the
government, so long as the corrective action taken is
appropriate to remedy the impropriety. Rockville Mailing
Serv., Inc., B-270161.2, Apr. 10, 1996, 96-1 CPD para.
184 at 4. The record contains abundant evidence that
this was a flawed procurement resulting in an award not
necessarily made on the basis most advantageous to the
government, and that the agency's corrective action is
appropriate. (Fisher-Cal
Industries, Inc., B-285150.2, July 6, 2000)
Where award of
indefinite-delivery, indefinite-quantity contract
improperly was made to large business, proposed
corrective action is reasonable, and warrants dismissing
protest as academic, where agency will (1) allow
improperly awarded contract to expire, (2) place no new
delivery orders under the contract, but allow delivery
orders already issued to be performed pending
recompetition and new award, and (3) promptly conduct
recompetition, with award to be made within 6 months.
(Landmark
Construction Corporation, B-281957.3, October 22,
1999)
Contracting officials in
negotiated procurements have broad discretion to take
corrective action where the agency determines that such
action is necessary to ensure fair and impartial
competition. Patriot Contract Servs., LLC et al.,
B-278276.11 et al., Sept. 22, 1998, 98-2 CPD para. 77 at
4; Rockville Mailing Serv., Inc., B-270161.2, Apr. 10,
1996, 96-1 CPD para. 184 at 4. It is not necessary for
an agency to conclude that the protest is certain to be
sustained before it may take corrective action; where
the agency has reasonable concern that there were errors
in the procurement, even if the protest could be denied,
we view it as within the agency's discretion to take
corrective action. Patriot Contract Servs., LLC et al.,
supra. An agency may amend a solicitation, and request
and evaluate another round of BAFOs where the record
shows that the agency made the decision to take this
action in good faith, without the specific intent of
changing a particular offeror's technical ranking or
avoiding an award to a particular offeror. See PRC,
Inc., B-233561.8, B-233561.9, Sept. 29, 1992, 92-2 CPD
para. 215 at 3-4. (Federal
Security Systems, Inc., B-281745.2, April 29, 1999)
|
|
|
Comptroller
General - Listing of Decisions |
|
For
the Government |
For
the Protester |
|
Northrop Grumman Technical Services,
Inc., B-404636.11, June 15, 2011 (pdf) |
Cooperativa Muratori Riuniti,
B-294980.5, July 27, 2005 (pdf) |
|
Northrop Grumman Information
Technology, Inc., B-404263.6, March 1, 2011 (pdf) |
Envirosolve LLC, B-294974.4, June
8, 2005 (pdf) |
|
Intermarkets Global,
B-400660.10; B-400660.11, February 2, 2011 (pdf) |
Rockwell Electronic Commerce Corporation, B-286201.6, August
30, 2001 (pdf) |
|
McKean Defense Group--Information
Technology, B-401702.2, LLC, January 11, 2010 |
|
|
Training Management Solutions, Inc.,
B-403461.2, September 29, 2010 (pdf) |
|
|
Honeywell Technology Solutions, Inc.,
B-400771.6, November 23, 2009 (pdf) |
|
|
Pemco Aeroplex, Inc., B-310372.3,
June 13, 2008 (pdf) |
|
|
CMC & Maintenance, Inc.,
B-293803.2, December 2, 2004 (pdf) |
|
|
Computer Associates
International, Inc., B-292077.2, September 4, 2003 (pdf) |
|
|
Hyperbaric Technologies, Inc.,
B-293047.2; B-293047.3, February 11, 2004 (pdf) |
|
|
PCA Aerospace, Inc.,
B-293042.3, February 17, 2004 (pdf) |
|
|
Strand Hunt Construction, Inc.,
B-292415, September 9, 2003) (pdf) |
|
|
SDS International, Inc.,
B-291183.4; B-291183.5, April 28, 2003 (pdf) |
|
|
Holding Group & Associates,
Inc., B-285882.11; B-285882.12, October 23, 2002 (pdf) |
|
|
Networks
Electronic Corporation, B-290666.3, September 30, 2002 (pdf)
|
|
|
Omega
World Travel, Inc.; SatoTravel, Inc., B-288861.5;
B-288861.6; B-288861.7, August 21, 2002 (pdf)
|
|
|
Alatech
Healthcare, LLC--Protest; Custom Services International,
Inc.--Costs,
B-289134.3; B-289134.4, April 29, 2002 (PDF
Version) |
|
|
TyeCom, Inc., B-287321.3; B-287321.4,
April 29, 2002 |
|
|
Royal
Hawaiian Movers, Inc., B-288653, October 31, 2001 (Reverse
auction issue) (PDF
Version) |
|
|
Clearwater
Instrumentation, Inc., B-286454.2, September 12, 2001 |
|
|
Johnson
Controls World Services, Inc., B-286714.3, August 20, 2001
(A-76 issue) (PDF
Version) |
|
|
Lackland
21st Century Services Consolidated--Protest and Costs,
B-285938.6, July 13, 2001 (A-76 issue) (PDF
Version) |
|
|
Fisher-Cal
Industries, Inc., B-285150.2, July 6, 2000 (PDF
Version) |
|
|
Landmark
Construction Corporation, B-281957.3, October 22, 1999
(PDF
Version) |
|
|
Rel-Tek
Systems & Design, Inc. -- Modification of Remedy,
B-280463.7, July 1, 1999 (pdf) |
|
|
Federal
Security Systems, Inc., B-281745.2, April 29, 1999 (PDF
Version) |
|
|
U.
S. Court of Federal Claims - Key Excerpts |
|
1.
The Army’s Reliance on the GAO Attorney’s April 20, 2011
Electronic-Mail Message
Renders Its Decision to Take Corrective Action Irrational
The first protest ground asserted by plaintiff–that the Army’s
decision to take corrective
action is arbitrary, capricious, and unreasonable because the
decision is based on an electronicmail
message from a GAO attorney that is itself unreasonable–raises
two threshold issues: was
the Army’s decision to take corrective action premised on the
GAO attorney’s April 20, 2011
electronic-mail message and, to the extent that it was, is the
court empowered to review the
electronic-mail message for rationality in the same way it can
review a formal decision by the
GAO recommending corrective action?
To answer the first question, the court
looks to the timeline of events reflected in the
administrative record. Kratos lodged its supplemental protest on
April 4, 2011. On April 7,
2011, the GAO attorney informed the parties that in light of the
supplemental protest, he was
interested in whether the Army would continue to oppose the
protest or take corrective action.
Then, on April 11, 2011, the GAO attorney invited the Army to
respond to comments made by
Kratos about its initial protest, but specifically requested
that the Army not respond to Kratos’s
supplemental protest. The Army complied with the request; its
response did not address Kratos’s
supplemental protest. On April 20, 2011, in the electronic-mail
message at issue, the GAO
attorney conveyed his impressions of Kratos’s supplemental
protest. In a response sent that same
day, the Army indicated that it understood the GAO attorney’s
position. Then, on April 22,
2011, the Army informed the GAO and the other parties that,
after reviewing the supplemental protest, it had decided to take
corrective action. The Army’s April 22, 2011 letter constituted
its
first formal response to Kratos’s supplemental protest.
The timeline suggests two possible
scenarios. One possibility is that the Army had been
considering how to respond to the supplemental protest for more
than two weeks, i.e., from the
time that it was first advanced by Kratos, and that its April
22, 2011 letter was the culmination of
its deliberations. The fact that the Army did not address the
merits of the supplemental protest
before April 22, 2011, supports this scenario, as does the
Army’s failure to mention the GAO
attorney’s electronic-mail message in its letter. The other
possibility is that the position taken by
the Army in its April 22, 2011 letter was prompted by the GAO
attorney’s April 20, 2011
electronic-mail message. The brief period of time—two
days—between the message and the
letter supports this scenario. Given the ambiguity regarding the
true basis of the Army’s decision
to take corrective action, the court finds it reasonable to
assume that the decision was based, at
least in part, on the GAO attorney’s April 20, 2011
electronic-mail message.
Assuming that the Army based its decision
to take corrective action on the impressions
conveyed by the GAO attorney in his electronic-mail message, the
court must next determine
whether it can review the message in the same way it reviews a
formal GAO decision
recommending corrective action. This appears to be an issue of
first impression.
There is no question that a court, in
deciding the propriety of a procuring agency’s
implementation of corrective action recommended by the GAO, may
review whether the GAO’s
recommendation was itself rational. See Honeywell, Inc. v.
United States, 870 F.2d 644, 648
(Fed. Cir. 1989) (“[A] procurement agency’s decision to follow
the Comptroller General’s
recommendation, even though that recommendation differed from
the contracting officer’s initial
decision, was proper unless the Comptroller General’s decision
itself was irrational.”); Centech
Grp., Inc., 79 Fed. Cl. at 563 n.2 (“[I]t is appropriate for
this Court to consider the rationality of
GAO’s determination where the agency relied upon such
determination in taking the corrective
action at issue.”). The decisional law reflects, however, that
as a general rule, courts have
reviewed GAO recommendations only when they were included as
part of a formal GAO
decision. See John Reiner & Co. v. United States, 325 F.2d 438,
442 (Ct. Cl. 1963) (“[I]t is the
usual policy, if not the obligation, of the procuring
departments to accommodate themselves to
positions formally taken by the [GAO] with respect to
competitive bidding.” (emphasis added));
see also Interstate Rock Prods., Inc. v. United States, 50 Fed.
Cl. 349, 363 (2001) (citing
Honeywell for the proposition that “to the extent that an agency
chooses to follow the advice of
the GAO, courts should only intervene if the advice the agency
receives is ‘irrational,’” and
concluding that the prior GAO decisions relied upon by the
procuring agency in rejecting a bid as
unresponsive were “eminently rational”); see also ManTech
Telecomms. & Info. Sys. Corp., 49
Fed. Cl. at 62, 73-80 (analyzing, in a case where the procuring
agency’s proposed corrective
action was based on the GAO’s suggestion during the alternative
dispute resolution process that
it would sustain the protest before it, only whether the
proposed corrective action was reasonable,
and not whether the GAO’s suggestion was rational).
In the present case, there is no formal GAO
decision sustaining Kratos’s protest and
recommending corrective action. Rather, there are only the
informal and nonfinal impressions of
the GAO attorney, expressed in an electronic-mail message,
indicating that the GAO would
likely sustain Kratos’s supplemental protest. Nevertheless, the
court has a broad mandate to
entertain bid protests and review government procurement
decisions. If a procuring agency takes
an action that is challenged in this court, this court has the
responsibility to examine the basis for
the agency’s action, regardless of what that basis might be. In
other words, when determining the
propriety of a procuring agency’s decision to take corrective
action, the court may review the
rationality of, as appropriate, the underlying formal GAO
decision containing a recommendation
that the agency take such action or the underlying informal
suggestion by the GAO, or any other
entity or individual, that such action might be proper. Thus,
the court concludes that because the
Army relied upon the GAO attorney’s electronic-mail message in
deciding to take corrective
action, and only because the Army relied upon the message, it
may review the message to
determine whether it was rational.
The threshold issues thus resolved, the
court turns to the substance of the GAO attorney’s
electronic-mail message. In his message, the GAO attorney
reaches two conclusions. First, he
opines that the GAO “need not resolve the issue of whether . . .
the protester timely challenged”
the Army’s evaluation of proposals. Second, he indicates that
the GAO would likely sustain
Kratos’s protest due to deficiencies in the source selection
decision. Both of these conclusions
are irrational.
The GAO is empowered to entertain protests
“concerning an alleged violation of a
procurement statute or regulation” so long as the protests are
filed in accordance with the
governing statutes. 31 U.S.C. § 3552(a) (2006). These statutes
require the GAO to establish
procedures for the “expeditious” resolution of the protests. Id.
§ 3555(a). Under this authority,
the GAO adopted a regulation providing that the GAO “shall”
dismiss a protest that is not timely
filed, 4 C.F.R. § 21.5(e) (2011), unless it determines that the
protest “raises issues significant to
the procurement system” or finds that “good cause” exists to
consider the protest, id. § 21.2(c).
In other words, except under limited circumstances, the GAO may
not entertain untimely protests
because they are not filed in accordance with the governing
statutes. The GAO’s own decisions
support this conclusion. See, e.g., Patricia A. Thompson-Agency
Tender Official, B-310910.4,
2009 CPD ¶ 24 (Comp. Gen. Jan. 22, 2009) (“Our Bid Protest
Regulations contain strict rules
requiring timely submission of protests. . . . [T]he protest is
untimely and, therefore, must be
dismissed.”); Goel Servs., Inc., B-310822.2, 2008 CPD ¶ 99
(Comp. Gen. May 23, 2008) (“Our
timeliness rules reflect the dual requirements of giving parties
a fair opportunity to present their
cases and resolving protests expeditiously without unduly
disrupting or delaying the procurement
process. In order to prevent these rules from becoming
meaningless, exceptions are strictly
construed and rarely used. The ‘good cause’ exception is limited
to circumstances where some
compelling reason beyond the protester’s control prevents the
protester from filing a timely
protest. The significant issue exception is limited to untimely
protests that raise issues of
widespread interest to the procurement community, and which have
not been considered on the
merits in a prior decision.” (citations omitted)); Cornet, Inc.,
B-270330 et al., 96-1 CPD ¶ 189 (Comp. Gen. Feb. 28, 1996)
(noting that the protest regulations require the dismissal of
untimely
protests and dismissing supplemental protest grounds as
untimely).
Here, the GAO attorney asserted that the
GAO “need not” consider the timeliness of
Kratos’s supplemental protest, and, although the court cannot
completely discount the possibility
that the GAO attorney was impliedly invoking one of the
exceptions allowing the GAO to
consider an untimely protest, there is no indication in the
electronic-mail message that an
exception to the timeliness rule applied. Thus, the GAO
attorney’s statement that the timeliness
of Kratos’s protest was irrelevant clearly contravenes the
statutory mandate that the GAO not
entertain untimely protests. When the GAO acts in violation of
the law, the act lacks a rational
basis. See SP Sys., Inc. v. United States, 86 Fed. Cl. 1, 13
(2009) (“If the GAO recommendation
is . . . plainly contrary to a statutory requirement, that
decision is irrational and an agency action
is not justifiably based upon it.” (citing Grunley Walsh Int’l,
LLC v. United States, 78 Fed. Cl.
35, 44 (2007))); Cal. Marine Cleaning, Inc., 42 Fed. Cl. at
295-96 (holding that the GAO’s
misapplication of late bid rule set forth in the FAR was
irrational, and therefore the agency’s
reliance on the GAO’s decision was improper); see also United
States v. Amdahl Corp., 786 F.2d
387, 392-93 (Fed. Cir. 1986) (“Administrative actions taken in
violation of statutory
authorization or requirement are of no effect.”). The GAO
attorney’s statement on timeliness is
therefore irrational.
The GAO attorney’s analysis of the Army’s
evaluation of proposals suffers the same fate.
In the Source Selection Decision Memorandum, the Source
Selection Authority reported the
findings from the Army’s evaluation and concluded that there
were “no meaningful distinctions”
among the noncost elements of the proposals. AR 2013. The Source
Selection Authority
acknowledged, however, that the proposals submitted by Kratos
and SA-TECH were not
identical: “[T]he main difference between the two offerors is
that, as the incumbent, Kratos/WSS
has the personnel with the specific TMO experience in their
current employment and has
proposed these employees for the follow-on ATFS requirement.”
Id. at 2014. She then
explained how SA-TECH’s proposal mitigated those differences.
[. . .]
Id. In other words, she most assuredly compared the ability of Kratos, as the incumbent
contractor, to supply personnel with specific experience with
SA-TECH’s proposal to supply
personnel with general experience coupled with a plan to
mitigate its failure to propose personnel
with specific experience. She then concluded that the
“price/cost advantages of SA-TECH’s
proposal outweigh[ed] the possibility of a learning curve
impact.” Id. at 2013. It is readily
apparent that the Source Selection Authority, upon comparing the
proposals of Kratos and SATECH,
clearly determined that the two proposals were not meaningfully
distinct in the area of
personnel experience and concluded that the benefit to the Army
of SA-TECH’s lower price was
worth the possibility that some of SA-TECH’s employees would
lack specific experience. Her conclusion is entitled to
deference.20 See Lockheed Missiles & Space Co. v. Bentsen, 4
F.3d
955, 958-59 (Fed. Cir. 1993) (“Effective contracting demands
broad discretion. Accordingly,
agencies ‘are entrusted with a good deal of discretion in
determining which bid is the most
advantageous to the Government.’” (citations omitted) (quoting
Tidewater Mgmt. Servs., Inc. v.
United States, 573 F.2d 65, 73 (Ct. Cl. 1978))); Gen. Offshore
Corp., B-251969 et al., 94-1 CPD
¶ 248 (Comp. Gen. Apr. 8, 1994) (“Where an evaluation is
challenged, we will examine the
agency’s evaluation to ensure that it was reasonable and
consistent with the evaluation criteria
and applicable statutes and regulations, since the relative
merit of competing proposals is
primarily a matter of administrative discretion.”), quoted in
E.W. Bliss Co. v. United States, 77
F.3d 445, 449 (Fed. Cir. 1996).
The GAO attorney did not afford the proper
deference to the Army’s source selection
decision. In fact, his electronic-mail message demonstrates that
he completely misread the
decision. He wrote:
The source selection fails to acknowledge
and appreciate the concerns expressed
in the evaluation of the Labor element, which serves as a key
discriminator
between the proposals. That the two proposals were rated the
same for this
element is highly irrelevant; regardless of ratings, the source
selection must look
behind those ratings to consider the distinctions uncovered in
the evaluation. This
source selection document fails to do that.
Had the agency said,
we recognize the value of incumbency and the
advantage of the reduced risk in the incumbent’s proposal, but
that advantage is
not worth the premium over the awardee’s proposal, we would in
all likelihood
deny a challenge to the best value trade-off. Those are not the
facts here. Here,
the agency denied that there were proposal
discriminators–documented in its
evaluation–and there was a trade-off to be made between, on the
one hand, an
incumbent who guaranteed to deliver an experienced work force,
and, on the
other, a lower-priced offeror who did not and about whom the
agency expressed
reservations.
AR 1995. First, contrary to the GAO
attorney’s observations, the Source Selection Authority did
“acknowledge and appreciate the concerns” of the Technical
Evaluation Committee regarding the
experience of SA-TECH’s proposed workforce; she set forth those
concerns in her decision and
explained that SA-TECH had sufficiently mitigated those
concerns. The Source Selection
Authority also “look[ed] behind [the] ratings to consider the
distinctions” identified by the Technical Evaluation Committee;
she both described the distinctions and explained why those
distinctions were not meaningful. Third, despite the GAO
attorney’s representations, the Source
Selection Authority “recognize[d] the value of incumbency” and
concluded that the value of
incumbency was not worth the price premium–in the Source
Selection Decision Memorandum
she acknowledged that Kratos, as the incumbent contractor, had
personnel with specific
experience and explained that the cost advantage of SA-TECH’s
proposal outweighed the lack of
specific experience of its proposed personnel. Fourth, the
Source Selection Authority
acknowledged the distinctions between the proposals of Kratos
and SA-TECH, finding them not
to be meaningful; she did not, as the GAO attorney stated,
“den[y] that there were proposal
discriminators[.]” Finally, contrary to the GAO attorney’s
assertion, the Source Selection
Authority described both a tradeoff between Kratos’s incumbency
and SA-TECH’s mitigation
efforts and a tradeoff between the proposed prices and the
relative experience levels of the
proposed personnel. All of these errors suggest that instead of
applying the necessary amount of
deference, the GAO attorney was substituting his judgment for
that of the Army. He may not do
so. Turner Constr. Co., 2011 WL 2714137, at *5 (“When an
officer’s decision is reasonable,
neither a court nor the GAO may substitute its judgment for that
of the agency.”). Accordingly,
his analysis of the source selection decision is irrational.
Because the GAO attorney improperly
declared that the timeliness of Kratos’s protest was
irrelevant and completely misconstrued the Source Selection
Decision Memorandum, the
contents of the GAO attorney’s April 20, 2011 electronic-mail
message are irrational. As a
result, to the extent that the Army’s decision to take
corrective action is based upon the message,
it lacks a rational basis and is therefore arbitrary,
capricious, and an abuse of discretion. (Systems
Application & Technologies, Inc. v. U. S. and Madison Research
Corporation, No. 11-280C, August 25, 2011) (pdf)
II. The Agency’s Planned Corrective
Action is Unlawful and Irrational.
The Court now turns to whether the
agency’s proposed corrective action was improper or otherwise
contrary to law. The Court’s limited review of agency decisions
is set forth in the Administrative Procedures Act (“APA”). 5
U.S.C. § 706(2)(A). The APA provides that an agency decision may
be set aside only if it is “arbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with law.” 5 U.S.C. §
706(2)(A) (incorporated by reference in 28 U.S.C. § 1491(b)(4));
Bannum, Inc. v. United States, 404 F.3d 1346, 1351 (Fed. Cir.
2005). Therefore, an agency’s procurement decision may be set
aside if it lacked a rational basis or involved a violation of
statute or regulation. Impresa Construzioni Geom. Domenico
Garufi v. United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001).
This standard of review is highly deferential to the agency’s
decision. Advanced Data Concepts, Inc. v. United States, 216
F.3d 1054, 1057-58 (Fed. Cir. 2000).
In applying this standard to an agency’s
corrective action, contracting officers are provided “broad
discretion to take corrective action where the agency determines
that such action is necessary to ensure fair and impartial
competition.” DGS Contract Serv., Inc. v. United States, 43 Fed.
Cl. 227, 238 (1999) (quoting Rockville Mailing Serv., Inc.,
B-270161.2, 96-1 CPD ¶ 184 (Comp. Gen. Apr. 10, 1996)).
Nevertheless, the chosen corrective action must be “reasonable
under the circumstances.” Id. To be reasonable, the agency’s
corrective action must be rationally related to the defect to be
corrected. MCII Generator & Elec., 2002 WL 32126244.
Furthermore, the reason for the corrective action must be
supported by the evidence in the record. Id.
Despite the wide latitude afforded to an
agency’s corrective action, the Court finds the evidence lacking
in this case. The record is devoid of any justification for the
agency’s decision to solicit revised proposals. Defendant
asserts that corrective action was necessary to address defects
in the procurement raised by JCN in its bid protest.
Specifically, Defendant contends that, because of an incorrectly
established competitive range, the agency improperly provided
Sheridan with disparate treatment. Although the Court will
analyze the appropriateness of the corrective action, the issue
of whether Sheridan received any disparate treatment is not
currently before the Court and will not be addressed in this
Opinion.
Defendant contends that the corrective
action is necessary because the contracting officer committed an
error by not establishing “a competitive range comprised of all
of the most highly rated proposals” as required by FAR
15.306(c)(1). Defendant alleges that this error occurred because
the contracting officer, in setting the competitive range,
incorrectly attributed to Sheridan a past performance rating of
“very low risk,” instead of the actual assigned factor of “low
risk.” In making this assertion, Defendant cites the April 20,
2010 Memorandum for the Record – Analysis of Proposal Summary,
which states “[o]n 12 Mar 10 a Competitive Range was established
which consisted of all offerors that were considered to have
reasonable and realistic pricing, and received a rating of Very
Low Risk.” (AR 519.) Defendant suggests that, had the
contracting officer correctly evaluated Sheridan’s risk factor
in setting the competitive range, the range would have consisted
of the top three offerors instead of only Sheridan. Defendant’s
argument is flawed for two reasons: (1) the competitive range
was an unnecessary procedural step; and (2) it is unclear from
the record that the agency evaluated Sheridan’s past performance
risk rating incorrectly.
First, the competitive range described
in FAR 15.306(c)(1) is inapplicable where, as here, the agency
awards the contract without conducting any offeror discussions.
The only error in this case was the agency’s use of the term
“competitive range” in the first place. Defendant cites the
second sentence of FAR 15.306(c)(1) for the proposition that the
competitive range should have consisted of more than just one
proposal. The second sentence of FAR 15.306(c)(1) states: “the
contracting officer shall establish a competitive range
comprised of all of the most highly rated proposals . . . .”
However, Defendant consistently ignores the first sentence of
FAR 15.306(c)(1) which provides: “[a]gencies shall evaluate all
proposals in accordance with 15.305(a), and, if discussions are
to be conducted, establish the competitive range.” (emphasis
added). The first sentence of FAR 15.306(c)(1) instructs on
when to create a competitive range, and the second sentence
instructs on how to establish a competitive range.
In this case, the agency did not conduct
any discussions with offerors, and stated in the RFP that it did
not intend to conduct discussions. (AR 78.) Because of the lack
of any discussions with offerors, the agency should not have
created a competitive range and should have simply awarded the
contract to the highest rated proposal. The concept of a
competitive range in this case was entirely meaningless and
unnecessary. Accordingly, because the concept of a competitive
range was inapplicable to this solicitation, any issue relating
to the size of the competitive range was not a defect in need of
correction, but simply an unnecessary step that the agency
should have ignored in the first place.
Second, Defendant cites an error that
caused the contracting officer to limit the “competitive range”
only to Sheridan. Allegedly, the contracting officer incorrectly
believed that Sheridan was the only proposal to receive a “very
low risk” rating. The administrative record at best is ambiguous
on whether this error actually occurred as Defendant suggests.
Defendant asserts that this error is based on a statement in the
agency’s April 20, 2010 memorandum summarizing the procurement
that Sheridan was assessed as “very low risk.” (AR 519.)
However, it is impossible to conclude that the addition of the
word “very” in the April 20, 2010 memorandum was not simply the
result of a typographical error or an improper recollection. The
record suggests that, at the time the agency selected Sheridan
as the best value proposal, it had evaluated Sheridan’s proposal
as “low risk.” The Source Selection Document, dated March 19,
2010, states that “the proposal presented by The Sheridan
Corporation, which revealed the highest rated Past Performance
assessment of all offerors and the only Low-Risk offeror
assessed, combined with the second lowest price provides the
best overall value to the Government.” (AR 516.) Defendant thus
cites a memorandum written over a month after source selection
as proof that somehow the agency incorrectly evaluated Sheridan
as “very low risk.” The Court, however, finds the
contemporaneous statements from the Source Selection Document to
be the more persuasive evidence of the agency’s evaluation of
Sheridan’s proposal.
A careful review of the administrative
record does not reveal any errors that required corrective
action. Even if the Court accepts JCN’s assertion that Sheridan
received disparate treatment requiring corrective action, the
chosen corrective action to resolicit proposals was improper.
Defendant has never suggested that Sheridan did not submit the
best proposal. Defendant’s counsel has agreed that the actual
proposals received by the agency had no flaws. (Oral Arg., Oct.
13, 2010, Tr. 20.) The only potential error acknowledged by the
agency is in the evaluation of the proposals. Although the APA
grants the Government wide latitude in its decision-making
process, this Court has rejected corrective action to resolicit
proposals because of a perceived evaluation error. See, e.g.,
Delaney Constr. Corp., 56 Fed. Cl. at 476; MCII Generator &
Elec., 2002 WL 32126244. Simply put, the corrective action must
target the identified defect. Here, the agency’s concern related
to the evaluation of the proposals. Any corrective action should
have been targeted to that issue. Resoliciting new proposals was
not a rational corrective action.
The Court finds the circumstances here
analogous to Delaney. 56 Fed. Cl. 470. In that case, Delaney, a
self-certified small business, submitted the lowest priced,
technically acceptable offer. Id. at 472. Tug Hill, a
self-certified HUBZone small business contractor, submitted the
second lowest priced, technically acceptable proposal. Id.
During the debriefing following the agency’s decision to award
the contract to Delaney, the agency informed Tug Hill that the
agency initially considered applying a ten percent HUBZone price
preference required by 15 U.S.C. § 657a to Tug Hill’s price,
which would have made Tug Hill’s bid the lowest technically
acceptable offeror. However, the agency determined that the
preference did not apply when a HUBZone small business competed
against another small business, and therefore, the agency
awarded the contract to Delaney. Id. Tug Hill initiated a size
protest contending that Delaney did not meet the required small
business size standards. Id. Shortly thereafter, Delaney
notified the contracting officer that it had failed to consider
revenues from affiliated companies, and conceded that it no
longer met the small business standards. Id. at 473.
Following an unsuccessful agency level
protest, Tug Hill submitted a protest to the GAO. Id. Ten days
later, the agency requested GAO to dismiss the protest because
it intended to take corrective action. Id. As part of the
corrective action, the agency elected to reopen the competition
and insert a clause regarding the HUBZone ten percent
preference. Id. Both Delaney and Tug Hill objected to the
proposed corrective action to reopen the competition. Id. at
473-74. The Court held that, because the prices had been
disclosed,7
the proposed corrective action to obtain new price proposals
“would comprise arbitrary action.” Id. at 476. The Court
explained that “[n]o public interest purpose has been
established which would support trashing the disclosed proposed
prices, obtained on the basis of full and open competition, in
favor of obtaining new prices as a result of adding a contract
clause which only provides notice of a statutory requirement
that existed at all relevant times.” Id.
Similarly, in MCII Generator & Electric,
an unsuccessful offeror filed a bid protest with the GAO
alleging that the Army had improperly evaluated its price and
the awardee’s risk in making its selection. 2002 WL 32126244.
The Army proposed to take corrective action by resoliciting
proposals. Id. The awardee brought suit seeking injunctive
relief to stop the resolicitation because the proposed
corrective action lacked a rational connection to any identified
defect. Id. The Court in MCII Generator struggled, as this Court
does here, to find any defect in the initial procurement
selection, let alone a defect that warranted reopening the
competition. Id. The Court enjoined the Army’s proposed
corrective action finding that “the integrity of the procurement
system requires that award decisions not be overturned for no
reason or for insubstantial reason.” Id.
The Court finds the MCII Generator case
particularly relevant to the present case. In both situations,
the “defect” identified by the Government had no relation to the
proposed corrective action. The record in both cases suggests
that the respective agencies made the correct award decisions,
and that if any flaws in the process existed, such flaws
occurred during the evaluation of the properly submitted
proposals. In such circumstances, a reevaluation of the
proposals may be warranted, but a resolicitation of the
proposals compromises the integrity of the procurement system,
especially where the winning price has been disclosed to the
public.
Defendant argues that this case can be
distinguished from Delaney, MCII Generator, and other cases
because here, the resolicitation is on identical terms. The
Court finds this position entirely illogical. Instead, the fact
that the agency conducted the resolicitation on identical terms
further strengthens Plaintiff’s argument that a resolicitation
was improper and unnecessary. Where the terms of the RFP remain
unchanged and the initial proposals were properly submitted,
there is no rational basis for the agency to resolicit proposals
that it already received under a properly conducted
solicitation. The only conceivable reason to permit
resolicitation would be to allow the unsuccessful offerors an
opportunity to beat the now disclosed price of the winning
proposal. Such a result is impermissible and would severely
damage the integrity of the procurement process.
Finally, Defendant argues that, because
of the passage of time in this case, a resolicitation is
necessary to ensure that all the proposals are accurate and
up-to-date. This argument is unsupported by the administrative
record and was raised for the first time during oral argument.
See Oral Arg., Oct. 13, 2010, Tr. 25. Any issues resulting from
the passage of time were of the Government’s own creation and
cannot support the agency’s attempt to resolicit proposals.
Furthermore, there are mechanisms in the RFP to adjust the price
as necessary to take into account fluctuations in the price of
materials as a result of the delay. Therefore, the Court
concludes that the proposed corrective action of resoliciting
proposals lacks a rational basis and is not supported by the
administrative record. (The
Sheridan Corporation v. U. S. and JCN Construction Company, Inc.,
10-547C, November 5, 2010) (pdf)
3. Was GAO’s Corrective Action Reasonable and Lawful?
Having decided that corrective action was necessary, the court
must now consider whether the
corrective actions GAO took were reasonable and lawful.
Following the “outcome prediction” in
which the PLCG1 informed GAO that it intended to sustain
plaintiff’s protest with regard to the
indemnification clause, GAO reopened the solicitation and
requested another round of FPRs. AR
1777–81, 1917, 1921. GAO permitted the offerors unlimited
discretion in revising their price
proposals, but did not allow them to change their technical
proposals. In addition, GAO forced
Monster to either remove the unacceptable indemnification clause
or face elimination. AR 1918,
1922. GAO’s stated purpose in taking these corrective actions
was “to eliminate the indemnification
provision in Monster’s proposal and allow the offerors to
compete on price alone.” AR 1779.
Plaintiff asserts in its complaint that “[w]hen a negotiated
procurement is reopened by an
agency for revised offers, it must allow any revision to those
offers the offeror may care to make.”
Compl. ¶ 26. For this proposition, plaintiff cites FAR 15.206
and FAR 15.307 without any preceding
signal. However, these citations do not support plaintiff’s
proposition either directly or indirectly.
FAR 15.206, titled “Amending the [S]olicitation,” outlines when
a contracting officer may
amend a solicitation and how such an amendment is issued. FAR
15.307, titled “Proposal
[R]evisions,” provides:
(a) If an offeror’s proposal is eliminated or otherwise removed
from
the competitive range, no further revisions to that offeror’s
proposal
shall be accepted or considered.
(b) The contracting officer may request or allow proposal
revisions to
clarify and document understandings reached during negotiations.
At
the conclusion of discussions, each offeror still in the
competitive
range shall be given an opportunity to submit a final proposal
revision.
The contracting officer is required to establish a common
cut-off date
only for receipt of final proposal revisions. Requests for final
proposal
revisions shall advise offerors that the final proposal
revisions shall be
in writing and that the Government intends to make award without
obtaining further revisions.
The court finds nothing in these regulations to support
plaintiff’s cited proposition. Indeed, this court
has recognized that subsequent to an “outcome prediction,” an
agency may re-open a solicitation and
allow offerors to make only limited revisions to their
proposals. See Consol. Eng’g Servs., Inc. v.
United States, 64 Fed. Cl. 617, 627–29 (2005) (“[T]he agency’s
decision to expand the scope of the corrective action to permit
revisions to key personnel and subcontractors was reasonable, as
was its
decision to limit revisions to those aforementioned areas.”).
This ability to limit proposal revisions derives, in part, from
contracting officials’ “broad
discretion to take corrective action where the agency determines
that such action is necessary to
ensure fair and impartial competition.” DGS Contract Serv., Inc.
v. United States, 43 Fed. Cl. 227,
238 (1999) (quoting Rockville Mailing Serv., Inc., B-270161.2,
Apr. 10, 1996, 96-1 CPD ¶ 184 at *4);
see also FAR 1.602-2(b) (“Contracting officers shall [e]nsure
that contractors receive impartial, fair,
and equitable treatment.”). Here, GAO’s corrective action was
aimed at ensuring fair and impartial
treatment for both plaintiff and Monster. Plaintiff was assured
that its competitor would not be
advantaged via an unlawful indemnification clause, while Monster
was granted the same meaningful
discussions that plaintiff enjoyed.
Moreover, this approach recognizes the agency’s interest in
preserving its resources and the
resources of the parties. Thus, the agency may salvage those
portions of the procurement untainted
by the problems identified in the protest. See Serv-Air, Inc.,
B-258243, et al., March 3, 1995, 95-1 CPD ¶ 125 at *2 (holding that agency may take corrective action
by limiting offerors’ proposal
revisions to cost proposals where PLCG’s prior decision found
nothing improper in the agency’s
previous evaluation of technical proposals). The only problem
that the PLCG recognized in the
procurement was the indemnification clause in Monster’s initial
FPR. AR 1777–81. Despite
plaintiff’s assertions to the contrary, GAO should not be
required to scrap its previously upheld
technical evaluations, nor should the parties be required to
resubmit technical proposals, when a more
limited corrective action will remedy the impropriety. Every
problem identified in a procurement
does not necessitate an entirely new competition. See id. According to plaintiff, GAO’s corrective action was unfair
because Monster’s indemnification
clause was a “non-pricing term,” and thus, “Monster was allowed
to alter both price and non-price
factors while [plaintiff] was limited to price-only changes.”
Pl.’s Am. Mem. 33–34; Pl.’s Reply
25–28. However, plaintiff’s counsel appeared to abandon this
position at oral argument where he
stated, “[W]e would also add that the indemnification clause has
a cost aspect to it.” Tr. 75.
Regardless of whether the indemnification clause is a pricing
term or not, GAO explained in its
proposed corrective action that it would permit Monster to
remove the indemnification clause. AR
1779. Indeed, the whole purpose of the corrective action was to
resolve the indemnification clause
problem, thus, it is irrelevant how the clause is characterized.
AR 1779. When GAO allowed
Monster to remove the indemnification clause, it was simply
acting in conformity with the corrective
action plan as proposed to the PLCG.
(sections deleted)
After reviewing the record, the court finds
that plaintiff enjoyed meaningful discussions prior
to the submission of initial FPRs, while Monster did not. Thus,
GAO’s corrective action—allowing
Monster to remove the offending indemnification clause while
limiting any other revisions to price
only—was a reasonable and lawful means of ensuring fair and
impartial treatment for both
competitors.20 This corrective action provided Monster with the
benefit of meaningful discussions and
remedied the impropriety identified by the PLCG. (Carahsoft
Technology Corporation, v. U. S. and Monster Government
Solutions, No 08-646C, Reissued February 12, 2009)
------------------------------------
1 This is GAO's Procurement Law
Contracting Group. |
|
|
U.
S. Court of Federal Claims - Listing of Decisions
|
|
For
the Government |
For
the Protester |
|
Carahsoft Technology Corporation, v. U.
S. and Monster Government Solutions, No 08-646C, Reissued
February 12, 2009
(pdf) |
Systems Application & Technologies, Inc.
v. U. S. and Madison Research Corporation, No. 11-280C, August
25, 2011 (pdf) |
|
Omega World Travel, Inc. v. The U. S., No. 02, 1199C, November
26, 2002 (pdf) |
The Sheridan Corporation v. U. S. and
JCN Construction Company, Inc., 10-547C, November 5, 2010
(pdf) |
|
|