|
1. Plaintiff Lacks Standing to Challenge Its
Exclusion From the Competition
As a threshold matter, defendant argues that
plaintiff lacks standing to challenge its
exclusion from the competition. “[T]he question of standing is
whether the litigant is entitled to
have the court decide the merits of the dispute or of particular
issues.” Warth v. Seldin, 422 U.S.
490, 498 (1975). The standing inquiry involves both Article III
“case or controversy” limitations
on federal jurisdiction and “prudential limitations on its
exercise.” Id. The plaintiff bears the
burden of establishing its standing to protest. Lujan v.
Defenders of Wildlife, 504 U.S. 555, 561
(1992).
“The standing issue in this case is framed by 28 U.S.C. §
1491(b)(1), which . . . imposes
more stringent standing requirements than Article III.” Weeks
Marine, Inc. v. United States, 575
F.3d 1352, 1359 (Fed. Cir. 2009). Under section 1491(b)(1), bid
protests may only be brought by
“interested parties.” The term “interested party” is construed
in accordance with the Competition
in Contracting Act of 1984, and, accordingly, “standing under §
1491(b)(1) is limited to actual or
prospective bidders or offerors whose direct economic interest
would be affected by the award of
the contract or by failure to award the contract.” Am. Fed’n of
Gov’t Emps. v. United States, 258 F.3d 1294, 1302 (Fed. Cir.
2001) (citing 31 U.S.C. § 3551(2)(A) (2000)); see also Info.
Tech. & Applications Corp. v. United States, 316 F.3d 1312, 1319
(Fed. Cir. 2003) (interpreting
this standard as requiring a protester to show that it was an
interested party prejudiced by the
procuring agency’s action and holding that “because the question
of prejudice goes directly to the
question of standing, the prejudice issue must be reached before
addressing the merits”); Myers
Investigative & Sec. Servs., Inc. v. United States, 275 F.3d
1366, 1370 (Fed. Cir. 2002) (defining
“prejudice” as “injury”). Therefore, plaintiff must establish
that it “(1) is an actual or prospective
bidder, and (2) possesses the requisite direct economic
interest.” Rex Serv. Corp. v. United
States, 448 F.3d 1305, 1307 (Fed. Cir. 2006).
In this case, there is no dispute
that plaintiff is an actual bidder. Thus, the first prong of
the interested party test has been satisfied. With regard to the
second prong, however, defendant
contends that plaintiff does not possess the necessary direct
economic interest that would be
affected by award of the contract. The United States Court of
Appeals for the Federal Circuit
(“Federal Circuit”) has described two ways in which a protester
may demonstrate the requisite
direct economic interest, depending on the timing of the
protest. In postaward bid protests, a
protester must show that it had a “substantial chance” of
receiving the contract. Id. at 1307. In
other words, “[t]o have standing, the plaintiff need only
establish that it ‘could compete for the
contract’ . . . .” Myers Investigative & Sec. Servs., Inc., 275
F.3d at 1370 (quoting Impresa
Construzioni Geom. Domenico Garufi v. United States, 238 F.3d
1324, 1334 (Fed. Cir. 2001)).
And, in at least some preaward bid protests, a protester must
show “a ‘non-trivial competitive
injury which can be addressed by judicial relief.’” Weeks
Marine, Inc., 575 F.3d at 1361-63
(quoting WinStar Commc’ns, Inc. v. United States, 41 Fed. Cl.
748 (1998)). Defendant argues
that plaintiff’s direct economic interest should be analyzed
under the “substantial chance” test
applied in postaward bid protests. At oral argument, it
explained that although this protest was lodged before the Army
awarded any contracts, the fact that offerors had already
submitted proposals made this protest more analogous to a
postaward protest for purposes of determining standing.
The key issue presented here is
whether the test endorsed by the Federal Circuit in Weeks
Marine, Inc.–a nontrivial competitive injury that can be
addressed by judicial relief–applies in
this preaward bid protest. In Weeks Marine, Inc., the protester
objected to the contract vehicle
selected by the agency for a dredging procurement, and filed its
protest before proposals were
due. See Weeks Marine, Inc. v. United States, 79 Fed. Cl. 22,
23, 27-28 (2007) (indicating that
the solicitation was issued on June 4, 2007, that the
solicitation was amended ten times from
June to September 2007, that the protest was filed on September
28, 2007, and that the agency
agreed to extend the due date for proposals to November 1,
2007), aff’d in part, rev’d in part, 575
F.3d at 1352. The Federal Circuit remarked:
[W]here a prospective bidder/offeror
is challenging a solicitation in the pre-award
context[,] . . . it is difficult for a prospective bidder/offeror
to make the showing of
prejudice that we have required in post-award bid protest cases.
The reason of
course is that, in a case such as this, there have been neither
bids/offers, nor a
contract award. Hence, there is no factual foundation for a “but
for” prejudice
analysis. However, Article III considerations require a party
such as [the
protester] to make a showing of some prejudice.
575 F.3d at 1361 (citation
omitted). It therefore held: “[I]n a pre-award protest such as
the one
before us, [a] prospective bidder or offeror must establish ‘a
non-trivial competitive injury which
can be redressed by judicial relief’ to meet the standing
requirement of § 1491(b)(1).” Id. at
1363.
There is a lack of unanimity in
the Court of Federal Claims concerning whether the test
endorsed in Weeks Marine, Inc. applies in all preaward bid
protests, regardless of the stage of the
procurement. In most preaward bid protests decided after Weeks
Marine, Inc. where standing
was at issue, the court has analyzed a protester’s direct
economic interest under the Weeks
Marine, Inc. test. In some cases the protest was filed
before the deadline for proposals. See, e.g., CW Gov’t Travel,
Inc. v. United States, No. 11-298C, 2011 WL 4363087 (Fed. Cl.
Aug. 26,
2011) (applying the test in a challenge to certain terms in the
solicitation); Jacobs Tech. Inc. v.
United States, No. 11-180C, 2011 WL 2215018 (Fed. Cl. May 27,
2011) (applying the test in a
challenge to a reprocurement that occurred as part of an
agency’s corrective action). In other
cases, the protester submitted a proposal but the procuring
agency had not yet awarded a contract.
See, e.g., ICP Nw., LLC v. United States, 98 Fed. Cl. 29 (2011)
(applying the test where the
protester submitted bids on seven solicitations and then
challenged the terms of the solicitations);
Camden Shipping Corp. v. United States, 89 Fed. Cl. 433 (2009)
(applying the test where the
protester submitted a timely proposal but was later eliminated
from the competition after its offer
had expired, and holding that had the protester “successfully
proved the facts alleged, it would
have suffered a non-trivial competitive injury resulting from a
prejudicial error made by [the
agency]”).
In contrast to the decisions in
which the court has applied the test endorsed in Weeks
Marine, Inc., the court in CS-360, LLC suggested, albeit in
dicta, that the Weeks Marine, Inc. test
should not be applied in all preaward bid protests 94 Fed. Cl.
at 495 n.6. It distinguished the
posture of the procurement in the protest before it–where the
protester submitted an offer and
was declared the lowest bidder–from the posture of the
procurement in Weeks Marine, Inc., and concluded: “The
traditional ‘substantial chance’ test . . . seems more
appropriate given the facts
of this case. The standard applied by the Federal Circuit in
Weeks Marine is sui generis to that
case.” Id. Nevertheless, because the protester in its case was
ineligible to participate in the
procurement in the first instance, id. at 500, the court
recognized that its holding would be the
same regardless of which test was used, id. at 495 n.6. Although
the facts in CS-360, LLC are
distinguishable from those in this case the court reaches the
same conclusion: plaintiff lacks
standing regardless of which test the court applies.
Plaintiff contends that the Army
both could have, and should have, evaluated its
cost/price proposal as submitted; in other words, that the
cost/price data from five of its teaming
partners omitted from its proposal was unnecessary for the
Army’s evaluation. Plaintiff’s
contention is premised upon its interpretation of section L of
the solicitation, which, according to
plaintiff, contains only guidelines for preparing and submitting
proposals, and not proposal
requirements. It therefore argues that teaming partner
cost/price data was not a required part its
proposal. Plaintiff’s argument lacks merit.
As a preliminary matter, the court notes that although it is
generally required to assume
that allegations in a complaint are true and construe those
allegations in the plaintiff’s favor, it
need not do so when jurisdiction is at issue. Here, plaintiff’s
allegation that its proposal was
timely and complete because it “contained all the information
necessary for the Agency to
evaluate its proposed costs and prices,” Compl. ¶ 6, and its
allegation that section L of the
solicitation contained “guidelines,” not “requirements,” id. ¶
7, are central to the issue of
plaintiff’s standing. Thus, the court is entitled to look beyond
the complaint to ascertain whether
these allegations have a factual basis. As the court explains
more fully below, the evidence in the
administrative record and the relevant regulations belie
plaintiff’s allegations.
First, plaintiff’s general contention that the provisions of
section L of the solicitation are
mere guidelines and not requirements is clearly contradicted by
the plain language of the
solicitation. The solicitation contained explicit language
requiring offerors to comply with everysection of the
solicitation–in other words, sections A through M–including all
terms, conditions,
representations, certifications, and technical requirements. AR
131, 209, 213, 225. In fact, in
section M–the section describing the evaluation factors for
award–the Army noted that a
successful proposal would conform to all of the solicitation’s
requirements, specifically including
those set forth in section L. Id. at 225.
Second, plaintiff’s more specific
assertion that the submission of detailed cost/price data
for each teaming partner was not required is also contrary to
the plain language of the
solicitation. The solicitation contained an unambiguous
requirement that offerors either supply
their teaming partners’ price/cost data to the Army or ensure
that the Army received the data
directly from their teaming partners by the proposal deadline.
Id. at 223. Moreover, the Army
clearly indicated in the solicitation that it would use offerors’
teaming partner cost/price data to
perform a cost realism analysis. Id. at 231; see also FAR
15.403-3(a)(1)(ii) (noting that an
agency can “[r]equire submission of data . . . from the offeror
to the extent necessary to
determine a fair and reasonable price,” including “data from an offeror to support a cost realism
analysis”). Plaintiff’s attempt to cast the solicitation’s
language concerning teaming partner
cost/price data as permissive rather than mandatory cannot
succeed.
Plaintiff’s reliance on decisions
from the Comptroller General and the General Services
Board of Contract Appeals (“GSBCA”) cannot detract from the
solicitation’s plain language. In All Phase Environmental,
Inc., the Comptroller General remarked that “rather than
establishing minimum evaluation standards, the instructions of
section L generally provide
guidance to assist offerors in preparing and organizing
proposals.” B-292919.2 et al., 2004 CPD
¶ 62 (Comp. Gen. Feb. 4, 2004). There is no indication, however,
that the solicitation at issue in
that case contained the explicit language present in the
solicitation here requiring offerors to
comply with section L. Id. In Syntrex Inc., the protester
contended that section L language
indicating that proposed software be “described by giving the
‘date of release for general use’”
required that “all offered software must have been released for
general use at the time for
submission of proposals.” GSBCA No. 8696-P, 87-1 BCA ¶ 19497.
The GSBCA disagreed
with the protester’s interpretation of the quoted language,
finding it “was merely an instruction
regarding the format for proposals which required offerors to
identify the release date for
software,” but the GSBCA did not hold that all section L
language constituted instructions. Id.
Thus, neither decision provides support for plaintiff’s
position.
Given the plain language of the
solicitation, plaintiff cannot establish standing to protest
under any standard. Under the “substantial chance” standard,
plaintiff must show that it could
compete for the contract but for the Army’s alleged error in
disqualifying its proposal. Plaintiff
cannot make this showing because it failed to submit
information–complete cost/price data for all>
of its teaming partners–clearly required in the solicitation,
and plainly necessary for the Army to
conduct a cost realism analysis. Acceptance of plaintiff’s
argument that complete cost/price data
for all of its teaming partners was unnecessary to perform a
cost realism analysis would be akin
to shifting the burden of providing the information required for
a cost realism analysis from
plaintiff to the Army. If the burden shifted in that manner, the
Army would be forced to examine
a teaming partner’s total proposed cost for a particular
position and guess the amount of each
component of that cost, such as the hourly wage rate, the fringe
benefit amount, and the general
and administrative cost. The Army, however, is not responsible
for filling in missing data, much
less filling in missing data with its own guesses. Because
plaintiff failed to include critical
information in its proposal, it had no chance, much less a
substantial chance, of receiving a
contract award. Further, under the standard endorsed in Weeks
Marine, Inc., plaintiff must
demonstrate that it suffered a nontrivial competitive injury
that is within the court’s power to
remedy. Plaintiff has not made this showing. Because it failed
to submit all of the information
the Army required to evaluate its proposal, as specified in the
solicitation, plaintiff could not
have been injured by the Army’s failure to evaluate its
proposal.
In sum, regardless of which
standard the court employs, plaintiff has not established that
it has a direct economic interest in the competition. Therefore,
it is not an interested party.
Accordingly, plaintiff lacks standing to assert its first claim
for relief. (Orion Technology,
Inc. v. U. S. and Strategic Resources, Inc., No 11-573C,
December 1, 2011) (pdf)
Until January 1, 2012, in order to be awarded a
contract, an otherwise qualified
SDVOSB must be listed in the VIP database. See id. § 8127(e) (“A
small business concern
may be awarded a contract under this section only if the small
business concern and the
veteran owner of the small business concern are listed in the
database of veteran-owned
businesses maintained by the Secretary under subsection (f).”);
FAR 804.1102 (“Prior to
January 1, 2012, all . . . SDVOSBs must be listed in the VIP
database, available at http://www.vetbiz.gov , and also must be registered in the
Central Contractor Registration
(CCR) (see 48 CAR subpart 4.11) to receive contract awards under
VA’s Veteran-owned
Small Business prime contracting and subcontracting
opportunities program.”). Also until
December 31, 2011, an applicant can self-represent its status as
a SDVOSB in the VIP
database. See FAR 819.7003(b) (“At the time of submission of
offer, the offeror must represent to the contracting officer
that it is a—(1) SDVOSB concern . . . and (3) Verified
for eligibility in the VIP database.”).
After December 31, 2011, the
regulations require that an applicant be “listed as
verified” in the VIP database. FAR 804.1102 (“After December 31,
2011, all . . . SDVOSBs,
must be listed as verified in the VIP database, and also must be
registered in the CCR to be
eligible to participate in order to receive new contract awards
under this program.”). The VA
Center for Veterans Enterprise (the “CVE”) evaluates
applications for inclusion in the VIP
database to verify whether an applicant satisfies the
eligibility requirements to be listed as
a SDVOSB. See 38 C.F.R. § 74.11(a) (2011) (“The Director, Center
for Veterans Enterprise,
is authorized to approve or deny applications for VetBiz VIP
Verification. The CVE will
receive, review and evaluate all VetBiz VIP Verification
applications.”). “Once an
application, a request for reconsideration, or an appeal to a
cancellation notice, as applicable,
has been denied, the applicant or participant shall be required
to wait for a period of 6 months
before a new application will be processed by CVE.” 38 C.F.R. §
74.14.
38 C.F.R. Part 74 and FAR Part
819, when read together, establish a comprehensive
regulatory scheme to ensure verification of SDVOSB status in
order to prevent unscrupulous
offerors from misrepresenting their veteran or service-disabled
ownership status. In so
doing, the VA is fulfilling its verification obligation
according to congressional mandate, as
prescribed by 38 U.S.C. § 8127(f)(4) (“In maintaining the
database, the Secretary shall carry
out at least the following two verification functions: (A)
Verification that each small business
concern listed in the database is owned and controlled by
veterans. (B) In the case of a
veteran who indicates a service-connected disability,
verification of the service-disabled
status of such veteran.”). FAR 819.7003 sets forth the
eligibility requirements for SDVOSBs
and provides that such eligibility is governed by certain SBA
regulations, “except where
expressly directed otherwise by . . . 38 C.F.R. verification
regulations for SDVOSBs . . . .”
Id. § 819.7003(a). Moreover, this regulation also requires an
offeror bidding on a solicitation
to represent to the contracting officer that the offeror is
“[v]erified for eligibility in the VIP
database.” Id. § 819.7003(b)(3). 38 C.F.R. § 74.2, in turn,
lists “the eligibility requirements
for VIP verification.” VA Acquisition Regulation: Supporting
Veteran-Owned and
Service-Disabled Veteran-Owned Small Businesses, 74 Fed. Reg. at
64,619. 38 U.S.C.
§ 8127(e) conditions award of a SDVOSB contract upon inclusion
in the VIP database. If
plaintiff is ineligible to be listed therein, it cannot show a
substantial chance of securing the
contract and, therefore, cannot establish prejudice. Without
such a showing, plaintiff is not an interested party for Tucker
Act purposes and lacks standing to bring its claim in the Court
of Federal Claims.
In protesting both the GSA and DLA
Solicitations as improper, plaintiff alleged that
the agencies failed to make any attempts to encourage
participation by SDVOSBs in
contravention of Executive Order 13,360, Exec. Order No. 13,360,
69 Fed. Reg. 62,549 (Oct.
20, 2004), and 15 U.S.C. § 644(g)(1), which set minimum goals
for participation by small
businesses in procurement contracts. Additionally, in its
protest of the DLA Solicitation,
plaintiff alleged that the Solicitation was improper in that it
required all SDVOSBs and SBCs
to satisfy the NMR. According to plaintiff, these improprieties
rendered the Solicitations
unlawful, necessitating a rebidding.
On August 26, 2011, defendant
filed a notice to the effect that plaintiff is neither
certified as nor qualified to be a SDVOSB. Def.’s Br. filed Aug.
26, 2011, at 1. The actual
letter from the CVE denied plaintiff’s application for inclusion
in the VIP database. The
CVE letter explained that plaintiff is a wholly-owned subsidiary
of BSE Holdco, LLC, a
holding company that itself is a wholly-owned subsidiary of
BlueStar Energy Holdings, Inc.,
a corporation owned 75% by a service-disabled veteran. Given
this chain of ownership, the
entity owned by the service-disabled veteran is BlueStar Energy
Holdings, Inc., not plaintiff.
Plaintiff, therefore, is unable to satisfy the “direct
ownership” requirement for certification
as a SDVOSB.
The CVE letter also announced that
plaintiff is unable to satisfy the “control”
requirement even though the service-disabled veteran sits on
plaintiff’s Board of Directors.
Plaintiff’s bylaws provide that it is managed and governed by a
Board of Directors (the
“Board”) that can act when a quorum—a majority of directors—is
present. Given that
plaintiff’s Board consists of five directors, three must be
present to constitute a quorum.
Consequently, because the Board can act in the absence of the
service-disabled veteran, it
cannot be said that the service-disabled veteran has control of
the Board and/or plaintiff.
Failure to meet the control requirement for a SDVOSB therefore
prevented plaintiff from
qualifying as a SDVOSB.
Defendant takes the position that
plaintiff’s ineligibility for SDVOSB set-asides is
decisive that plaintiff lacks standing to pursue these protests.
To establish its standing,
plaintiff was required to prove both that it is an actual or
prospective bidder and that it had
a direct economic interest in the award of the contract. For the
reasons stated above, see
supra Part II.1-II.2, plaintiff has failed to show that it is an
actual or prospective bidder and
that it has a direct economic interest in the award of the
contract. Defendant reasons that
plaintiff was not prejudiced by any government action or
inaction as to SDVOSB set-asides
because, having failed to qualify as a SDVOSB, plaintiff was not
eligible to benefit from
these set-asides. Moreover, defendant contends that plaintiff’s
ineligibility for the set-asides precludes the court from
affording plaintiff the requested relief, thereby rendering
plaintiff’s
claims moot. Def.’s Br. filed Aug. 26, 2011, at 1.
Plaintiff’s counsel conceded
during oral argument that, because an offeror must be
certified as a SDVOSB to be eligible for a VA procurement like
that in the GSA Solicitation,
plaintiff’s failure to obtain such certification renders moot
its contention that GSA
improperly included a VA procurement in a contract bundle that
did not comply with the
procedures required for VA procurements (Count III of the GSA
Complaint). According to
plaintiff, its other claims were not mooted because plaintiff
could self-certify its status as a
SDVOSB.
As to the GSA Solicitation,
defendant’s position is correct. Plaintiff cannot
demonstrate the requisite prejudice because it was ineligible to
bid for the contract. It
ultimately is plaintiff’s own ineligibility, not GSA’s alleged
failure to encourage participation
by SDVOSBs and SBCs, that would bar plaintiff from availing
itself of the set-aside.
Defendant also is correct that plaintiff would be unable to
demonstrate the requisite prejudice
because plaintiff, given its ineligibility for SDVOSB status,
could not show that it had a
substantial chance of securing the contract. See Labatt, 577
F.3d at 1378. Moreover, by
plaintiff’s own admission, it cannot self-certify itself as a
SDVOSB for this Solicitation
because the Solicitation contains a VA procurement, and such
procurements can only be
awarded to an entity that is listed in the VIP as a verified
SDVOSB. 38 U.S.C. § 8127(e)
(requiring small business concern and veteran owner to be listed
in database in order to be
eligible for award of VA procurement); 38 C.F.R. pt. 74
(establishing verification procedures
for SDVOSBs). Because plaintiff did not qualify for inclusion in
the VIP, it was not eligible
for the GSA contract and cannot maintain suit for GSA’s alleged
failure to encourage
participation by SDVOSBs. Accordingly, Count II of the GSA
Complaint is mooted.
Regarding the DLA Solicitation, it
should be noted that DLA dissolved all set-asides>
after determining that none of the offerors qualified as a
SDVOSB or SBC; therefore,
plaintiff’s ineligibility to qualify as a SDVOSB does not
preclude it from being awarded the
contract as it does with respect to the GSA Solicitation.
Nonetheless, it does render
plaintiff’s claims moot. Specifically, plaintiff has prayed that
this court declare that the DLA
(1) failed to make any attempts to encourage participation by
SDVOSBs and SBCs (Count
II of the DLA Complaint) and (2) impermissibly incorporated the
NMR requirement into the
Solicitation (Count III of the DLA Complaint). Plaintiff has
also requested that this court
enter an injunction dissolving the portions of the RFP
designated as SBC and SDVOSB setasides
and requiring DLA to re-bid those portions without the NMR
requirement. These
claims are mooted in light of plaintiff’s inability to qualify
as a SDVOSB.
Plaintiff contends that it can
salvage these claims by self-certifying itself as a SDVOSB. Self-certification, it argues, is acceptable because the
DLA Solicitation does not contain a VA procurement and thus does
not require that an offeror be listed as a verified
SDVOSB in any database. Although self-certification may be
acceptable, it is not available
in this case. To be considered a SDVOSB, a small business
concern “must be at least 51
percent unconditionally and directly owned by one or more
veterans or service-disabled
veterans.” 38 C.F.R. § 74.3. Moreover, the service-disabled
owner must control the “day-today
management and long-term decisionmaking” of the entity. 38 C.F.R.
§ 74.4(a). As
explained in the CVE letter, the service-disabled veteran does
not directly own plaintiff;
rather, the service-disabled veteran owns BlueStar Energy
Holdings, Inc., which indirectly
owns plaintiff through one of its wholly-owned subsidiaries.
This does not satisfy the
requirement that the service-disabled veteran directly own the
small business concern. See
38 C.F.R. § 74.3(a) (“An applicant or participant owned
principally by another business
entity . . . that is in turn owned by one or more veterans or
service-disabled veterans does not
meet th[e] [direct ownership] requirement.”). The CVE letter
also indicated that plaintiff
does not satisfy the “control” requirement because plaintiff’s
Board of Directors could take
decisive action in the absence of the service-disabled veteran.
The CVE’s finding is accurate
and does prevent plaintiff from satisfying the control
requirement. See 38 C.F.R. § 74.4(b)
(“An applicant or participant’s management and daily business
operations must be conducted
by one or more veterans or service-disabled veterans.”). Because
these decisions can be
made without any involvement by the service-disabled veteran,
plaintiff cannot be deemed
to be controlled by the service-disabled veteran. Plaintiff,
therefore, cannot in good faith
certify that it qualifies as a SDVOSB. Consequently, Counts II
and III of the DLA
Complaint are dismissed as moot.
Plaintiff’s inability to qualify
as a SDVOSB also serves to deconstruct its futility
argument. Essentially, plaintiff contends that it qualified as a
prospective bidder for purposes
of determining whether or not it is an interested party despite
its failure to submit price
proposals in response to the Solicitations. Plaintiff explained
that it was futile to submit such
proposals because GSA and DLA had made no attempts to encourage
participation by
SDVOSBs, resulting in a diminished likelihood that plaintiff
would be awarded the contract.
Given this showing and its intention to submit offers in
response to any re-solicitations,
plaintiff deems itself to be a prospective bidder. Plaintiff,
however, is not a SDVOSB;
therefore, the agencies’ failure to encourage participation by
such entities would not have
rendered it futile for plaintiff to submit a bid. As such,
plaintiff cannot establish its standing
to bring these protests, and the remaining counts—Count I in
both the GSA and DLA
Complaints—are dismissed for lack of standing. (BlueStar
Energy Services, Inc. d/b/a BlueStar Energy Solutions, v. U. S.
Nos. 11-460C and 11-461C, September 22, 2011) (pdf)
1. The VIP database and SDVOSB contracts
The Veterans Benefits, Health Care, and Information Technology
Act of 2006, Pub. L. No. 109-461, §§ 502-03 (codified at 38
U.S.C. §§ 8127-28 (2006)), was enacted to increase contracting
opportunities for service-disabled veteran and veteran-owned
qualified small businesses. See 38 U.S.C. § 8127(a).
Accordingly, the [Department of Veterans Affairs] DVA sets aside certain contracts for SDVOSB
concerns. See id. §§ 8127-28. The DVA keeps an online database
of qualified SDVOSBs at its [Vendor Information Pages] VIP website, www.VetBiz.gov. See id.
§ 8127(f) ("[T]he Secretary shall maintain a database of small
business concerns owned and controlled by veterans and the
veteran owners of such business concerns.”); 48 C.F.R. 2/ §
804.1102 (2010) (providing VIP online database).
Until January 1, 2012, in order to
be awarded a contract, an otherwise qualified SDVOSB must be
listed in the VIP database. See id. § 8127(e) (“A small business
concern may be awarded a contract under this section only if the
small business concern and the veteran owner of the small
business concern are listed in the database of veteran-owned
businesses maintained by the Secretary under subsection (f).”);
48 C.F.R. § 804.1102 (“Prior to January 1, 2012, all VOSBs and
SDVOSBs must be listed in the VIP database, available at
http://www.VetBiz.gov ,
and also must be registered in the Central Contractor
Registration (CCR) (see 48 CAR subpart 4.11) to receive contract
awards under VA's Veteran-owned Small Business prime contracting
and subcontracting opportunities program.”). Also until December
31, 2011, an applicant can self-represent its status as an
SDVOSB in the VIP database. See 48 C.F.R. § 819.7003(b) (2010)
(“At the time of submission of offer, the offeror must represent
to the contracting officer that it is a–(1) SDVOSB concern or
VOSB concern; . . . and (3) Verified for eligibility in the VIP
database.”).
After December 31, 2011, the
regulations require that an applicant be “listed as verified” in
the VIP database. 48 C.F.R. § 804.1102 (“After December 31,
2011, all VOSBs, including SDVOSBs, must be listed as verified
in the VIP database, and also must be registered in the CCR to
be eligible to participate in order to receive new contract
awards under this program.”). The Center for Veterans Enterprise
(the “CVE”), a division of the DVA, evaluates applications for
inclusion in the VIP database to verify whether an applicant
satisfies the eligibility requirements to be listed as a SDVOSB.
See 38 C.F.R. § 74.11(a) (2010) (“The Director, Center for
Veterans Enterprise, is authorized to approve or deny
applications for VetBiz VIP Verification. The CVE will receive,
review and evaluate all VetBiz VIP Verification applications.”).
The CVE has authority to remove from the VIP database a firm
“found to be ineligible due to an SBA protest decision or other
negative finding,” and the firm will not be eligible to
participate in the 38 U.S.C. § 8127 program. 38 C.F.R. § 74.2(e)
(2010). “Once an application, a request for reconsideration, or
an appeal to a cancellation notice, as applicable, has been
denied, the applicant or participant shall be required to wait
for a period of 6 months before a new application will be
processed by CVE.” 38 C.F.R. § 74.14 (2010).
An interested offeror bidding on a
procurement may challenge another offeror’s listing
status as an SDVOSB in the VIP database by filing a protest with
the VA Office of Small and
Disadvantaged Business Utilization (the “OSDBU”). See 48 C.F.R.
§ 819.307(c) (2010). Pending an interagency agreement with
the Small Business Administration (the “SBA”), the
Executive Director of the OSDBU decides protests of SDVOSB
status raised by either
another offeror or the contracting officer. Id. His decision is
final. Id.
(sections deleted)
2) Analysis
Defendant bases its claim that
plaintiff has no standing on two regulations, 48 C.F.R.
§ 819.307(c)(3) and 38 C.F.R. § 74.2(e), which, respectively,
acts to bar a purported
SDVOSB from bidding on a future procurement if a status protest
has been sustained against
that bidder and grants the CVE authority to remove the bidder
from the VIP database.
Defendant argues that the two regulations “go hand in hand” and
accuses plaintiff of
“parsing” the regulatory scheme by differentiating between being
listed on the VIP database,
48 C.F.R. § 804.1102, from the VIP verification application
process, 38 C.F.R. § 74.11, in
12 order to misrepresent its status as an SDVOSB. 8/ Def.’s Br.
filed Aug. 19, 2010, at 4-5
(citing Pl.’s Br. filed Aug. 6, 2010, at 8).
“The rules of statutory
construction apply when interpreting an agency regulation.”
Roberto v. Dep’t of the Navy, 440 F.3d 1341, 1350 (Fed. Cir.
2006). The court begins its
analysis of the regulations by “reviewing its language to
ascertain its plain meaning.” Am.
Airlines, Inc. v. United States, 551 F.3d 1294, 1299 (Fed. Cir.
2008). The court may
consider the language of other, related regulations to guide its
analysis. Roberto, 440 F.3d
at 1350. The court will defer to the relevant agency’s
interpretation of a statute or regulation
that is “not clear on its face or does not speak directly to an
issue.” Am. Airlines, 551 F.3d
at 1299-1300 (citing Chevron, U.S.A., Inc. v. Natural Res. Def.
Council, Inc., 467 U.S. 837,
842-45 (1984)); see also Roberto, 440 F.3d at 1350 (“[I]f the
regulation is silent or
ambiguous, the court then gives deference to the agency’s own
interpretations.”). However,
when the regulation’s text is clear, the court’s inquiry ends
with the plain meaning. Roberto,
440 F.3d at 1350.
The court agrees in part with
plaintiff’s construction of 48 C.F.R. § 819.307(c)(3).
Defendant argues that plaintiff’s interpretation of the
regulation “fails to include a situation,
such as the one at issue here, where a status protest has
already been sustained against an
offeror.” Def.’s Br. filed Aug. 19, 2010, at 5. Section
819.307(c)(3) provides:
If the Executive Director sustains a service-disabled
veteran-owned or
veteran-owned small business status protest and the contract has
already been
awarded, then the contracting officer cannot count the award as
an award to
a VOSB or SDVOSB and the concern cannot submit another offer as
a VOSB or SDVOSB on a future VOSB or SDVOSB procurement under
this part, as
applicable, unless it demonstrates to VA that it has overcome
the reasons for
the determination of ineligibility.
48 C.F.R. § 819.307(c)(3). This
regulation applies to status protests of successful bidders
to whom “the contract has already been awarded,” not merely
protests sustained against an
unsuccessful bidder. Id. Nothing in the text suggests a broader
application. Indeed, the
VA’s own final rule confirms this construction: “Lastly, 819.307
is clarified to explain that
if a SDVOSB or VOSB status protest is granted, if contract award
has already been made,
VA will not be required to terminate the award . . . .” VA
Acquisition Regulation:
Supporting Veteran-Owned and Service-Disabled Veteran-Owned
Small Businesses, 74 Fed.
Reg. 64,619, 64,627 (Dec. 8, 2009) (emphasis added). Defendant’s
construction of the
regulation to encompass unsuccessful bidders ignores the
conjunctive clause “and the
contract has already been awarded,” 48 C.F.R. § 819.307(c)(3),
which would render
meaningless the immediately succeeding clause, “then the
contracting officer cannot count
the award as an award to a VOSB or SDVOSB,” id. This result the
court cannot sanction,
as it “would contravene the ‘longstanding canon of statutory
construction that terms in a
statute should not be construed so as to render any provision of
that statute meaningless or
superfluous.’” Roche v. Merit Sys. Prot. Bd., 596 F.3d 1375,
1380 (Fed. Cir. 2010) (quoting
Beck v. Prupis, 529 U.S. 494, 506 (2000)). The court must also
follow the “cardinal rule that
statutory language must be read in context since a phrase
gathers meaning from the words
around it.” Hawkins v. United States, 469 F.3d 993, 1001 (Fed.
Cir. 2006) (citation omitted)
(internal quotation marks omitted). The court concludes that, by
its plain terms, 48 C.F.R.
§ 819.307(c)(3) only applies to status protests sustained
against firms that already have been
awarded a contract.
Applying this construction to the
facts of this case, it becomes clear that the regulation
is inapplicable. When the OSDBU sustained the status protest
against plaintiff on April 30,
2010, by plaintiff’s own admission, see Pl.’s Br. filed Aug. 6,
2010, at 4, the protested
procurement had not been awarded to plaintiff. Nothing in the
regulation’s text supports
applying its penalty clause—barring sustained protested firms
from future bids—to an
anomalous situation where, as here, the sustained protested firm
was an unsuccessful bidder.
Therefore, 48 C.F.R. § 819.307 does not bar plaintiff from
bidding on the Solicitation.
For the same reason, however,
plaintiff cannot take refuge in the regulation’s safe
harbor provision, “unless it demonstrates to VA that it has
overcome the reasons for the
determination of ineligibility.” 48 C.F.R. § 819.307(c)(3). The
regulation simply does not
apply to a sustained status protest regarding an offeror’s
prior, unsuccessful bid. Even
though the regulation does not bar plaintiff from bidding, that
does not mean that, by
negative implication, the regulation permits plaintiff to bid on
future procurements after the CVE’s determination of
ineligibility for SDVOSB status. In other words, § 819.307(c)(3)
does not apply to this case.
Defendant argues that the DVA’s
amendment to the pre-solicitation notice to conform
it to 38 U.S.C. § 8127(e) and the DVA’s own interpretation of
that statute in Corners
Construction confirm that plaintiff has until the actual award
of the contract to be listed in
the VIP database. Plaintiff insists that, in light of the CVE’s
acknowledgment that plaintiff
cured the defects identified in the OSDBU’s April 30 letter,
nothing prevents it from being
placed back on the VIP database prior to the contract’s award.
The court concludes,
however, that notwithstanding the CVE’s observations pertinent
to the OSDBU’s status
protest, plaintiff is ineligible to bid by virtue of 48 C.F.R. §
819.7003(a) and 38 C.F.R. §
74.2(e).
38 C.F.R. Part 74 and 48 C.F.R.
Part 819, when read together, establish a
comprehensive regulatory scheme to ensure verification of SDVOSB
status in order to
prevent unscrupulous bidders from misrepresenting their veteran-
or service-disabled
ownership status. In so doing, DVA is fulfilling its
verification obligation according to
congressional mandate, as prescribed by 38 U.S.C. § 8127(f)(4)
(“In maintaining the
database, the Secretary shall carry out at least the following
two verification functions: (A)
Verification that each small business concern listed in the
database is owned and controlled
by veterans. (B) In the case of a veteran who indicates a
service-connected disability,
verification of the service-disabled status of such veteran.”).
Defendant correctly contends
that these two provisions cannot be considered in isolation.
Each provision is examined in
turn.
48 C.F.R. § 819.7003 sets forth
the eligibility requirements for SDVOSBs and
provides that such eligibility is governed by certain SBA
regulations, “except where
expressly directed otherwise by . . . 38 C.F.R. verification
regulations for SDVOSBs and
VOSBs.” Id. § 819.7003(a). Moreover, this regulation also
requires an offeror bidding on
a solicitation to represent to the contracting officer that the
offeror is “[v]erified for eligibility
in the VIP database.” Id. § 819.7003(b)(3) (emphasis added). 38
C.F.R. § 74.2, in turn, lists
“the eligibility requirements for VIP verification.” VA
Acquisition Regulation: Supporting
Veteran-Owned and Service-Disabled Veteran-Owned Small
Businesses, 74 Fed. Reg. at
64,619. Section 74.2(e) provides:
U.S. Small Business Administration
(SBA) Protest Decisions. Any firm
registered in the VetBiz VIP database that is found to be
ineligible due to an
SBA protest decision or other negative finding will be
immediately removed
from the VetBiz VIP database. Until such time as CVE receives
official
notification that the firm has proven that it has successfully
overcome the
grounds for the determination or that the SBA decision is
overturned on
appeal, the firm will not be eligible to participate in the 38
U.S.C. [§] 8127
program.
38 C.F.R. § 74.2(e) (emphasis
added). Plaintiff disputes the applicability of 38 C.F.R.
§ 74.2(e) on the ground that it is specific to SBA decisions.
See Pl.’s Br. filed Aug. 6, 2010,
at 5 (“The title of the clause alone speaks to its
inapplicability . . . .”). However, a regulation
is not interpreted merely according to its title. See Fla. Dep’t
of Revenue v. Piccadilly
Cafeterias, Inc., 554 U.S. 33, __, 128 S. Ct. 2326, 2336 (2008)
(“To be sure, a subchapter
heading cannot substitute for the operative text of the
statute.”); Pa. Dep’t of Corrections v.
Yeskey, 524 U.S. 206, 212 (1998) (explaining that title of
statute does not limit plain
meaning of its text). As the text of the regulation explicitly
provides, a firm will be removed
from the VIP database if it is found to be ineligible due to
“[an]other negative finding,” not
only an SBA decision. Moreover, the CVE’s authority to remove a
bidder upon a negative
finding by the DVA and bar that bidder from bidding on future
procurements is not so readily
discounted, and the court declines to do so now. 48 C.F.R. §
819.7003 expressly conditions
eligibility for SDVOSB status on satisfying the verification
requirements of 38 C.F.R. Part
72. Upon plaintiff’s application, which proceeded in tandem with
the Solicitation, the CVE
removed plaintiff from the VIP database on April 30, 2010,
thereby rendering plaintiff
ineligible to participate in the Solicitation. Nothing in the
regulatory scheme permits a firm
to represent itself as an SDVOSB once it has been removed from
the VIP database. To do
so would turn the DVA’s verification process on it head. 38
U.S.C. § 8127(e) conditions
award of an SDVOSB contract upon inclusion in the VIP database.
Because plaintiff is
ineligible to be listed therein, it cannot show a substantial
chance of securing the contract
and, therefore, cannot establish prejudice. Without such a
showing, plaintiff is not an interested party for Tucker Act
purposes and lacks standing to bring its claim in the Court
of Federal Claims. (CS-360,
LLC, v. U. S., No 10-457C, September 16, 2010) (pdf)
I. Standing
Standing is a
threshold jurisdictional issue. Myers
Investigative & Sec.
Servs., Inc., v. United States, 275 F.3d 1366,
1369 (Fed. Cir. 2002) (citing
Steel Co. v. Citizens for a Better Env’t, 523
U.S. 83, 102-04 (1998)). The
doctrine of standing ensures that the party
seeking redress is properly entitled
to have the court decide the dispute or issue.
Warth v. Seldin, 422 U.S. 490,
498 (1975). It is an outgrowth of the
Constitution’s “case or controversy”
requirement, and, although we are an Article I
court, we generally apply the
same standard as the federal courts created
under Article III. Anderson v.
United States, 344 F.3d 1343, 1350 n.1 (Fed.
Cir. 2003). This standard
requires that, to have standing, a litigant must
have suffered a concrete and
particular injury that is fairly traceable to
the defendant’s action and which is
likely to be redressed by a favorable decision.
Lujan v. Defenders of Wildlife,
504 U.S. 555, 560-61 (1992).
In the bid protest context, the standing issue
is framed by 28 U.S.C. § 1491(b)(1), which
grants jurisdiction over a protest brought by an
“interested party”:
Both the Unites
[sic] States Court of Federal Claims and the
district courts of the United States shall have
jurisdiction to render judgment on an action by
an interested party objecting to a solicitation
by a Federal agency for bids or proposals for a
proposed contract or to a proposed award or the
award of a contract or any alleged violation of
statute or regulation in connection with a
procurement or a proposed procurement. . . .
28 U.S.C. §
1491(b)(1) (2006). Though the statute does not
speak of standing,
its requirement of an interested party has been
interpreted as “impos[ing] more
stringent standing requirements than Article
III.” Weeks Marine, Inc. v. United
States, 575 F.3d 1352, 1359 (Fed. Cir. 2009)
(citing Am. Fed’n of Gov.
Employees v. United States, 258 F.3d 1294, 1302
(Fed. Cir. 2001)). Here, the
crux of the standing argument is whether Navarro
is an interested party.
At first blush,
Navarro—the incumbent contractor and a
disappointed
bidder—seems the very model of an interested
party, having failed in its bid
to receive a contract valued at nearly $30
million. The government, however,
argues that Navarro does not qualify as an
interested party and thus lacks
standing. The government’s argument, discussed
in more detail below, is
drawn from decisions in which the plaintiff was
challenging the merits of an
award. We believe that Navarro’s situation is
sufficiently different from the
typical bid protest that a different standing
requirement should apply here.
The government’s
argument begins by noting that, although 28
U.S.C.
§ 1491 does not define an interested party, past
cases have applied the
definition found in the Competition In
Contracting Act, 31 U.S.C. § 3551(2)
(2006). Def. Resp. 4 (citing Rex Serv. Corp. v.
United States, 448 F.3d 1305,
1307 (Fed. Cir. 1996)). Under this definition,
interested parties are those
“actual or prospective bidders or offerors whose
direct economic interest
would be affected by the award of the contract
or by failure to award the
contract.” 31 U.S.C. § 3551(2)(A); Rex Serv.
Corp., 448 F.3d at 1307. While
plaintiff would obviously meet that requirement,
the government next draws
from decisions holding that a protestor has a
“direct economic interest” only
if it could be put in a position for award as a
result of prevailing in its bid
protest. Def. Resp. 5 (citing United States v.
Int’l Bus. Machs. Corp., 892 F.2d
1006, 1011 (Fed. Cir. 1989)). In other words,
the contractor “must show that
there was a ‘substantial chance’ it would have
received the contract award but
for the alleged error in the procurement
process.” Info. Tech. & Applications
v. United States, 316 F.3d 1312, 1319 (Fed. Cir.
2003); see also Myers, 275
F.3d at 1369-70 (“[P]rejudice (or injury) is a
necessary element of standing.”).
In the present
action, Navarro is not challenging the
procurement
decision itself but rather seeks to enforce a
post-award procedural remedy—an
allegedly mandatory debriefing. In other words,
even if Navarro were to
prevail here, it would not be awarded the
contract. It would still have to obtain
review of the merits of the award and succeed.
Thus, the government argues,
Navarro has no direct economic interest, is not
an interested party, and therefore lacks
standing. Although the precise question
presented is one of
first impression,6 we believe that the relevant
statutes and related case law
mean that the government is incorrect.
The government’s
argument relies on standing doctrine developed
in
typical bid protests, in which the winner of the
competition has been
announced or even awarded the contract. In such
a “substantive” challenge to
a procurement, it makes sense to insist that the
protestor has a substantial
chance at the award. Otherwise, the court’s
ruling would serve no purpose,
neither changing the award nor redressing the
protestor’s real grievance.
In Weeks Marine,
Inc. v. United States, 575 F.3d 1352 (Fed. Cir.
2009),
the Federal Circuit confronted a challenge to
standing in a pre-award protest,
in which the plaintiff challenged the agency’s
decision to use task order
contracts rather than sealed bidding procedures.
Id. at 1354-58. The
challenge, in other words, was not unique to the
plaintiff’s circumstances. It
went to the validity of the entire solicitation
process. The Court of Federal
Claims had ruled in favor of the contractor and
enjoined the agency from
moving forward with the solicitation. On appeal,
the government, relying on
standing decisions developed in post-award
contexts, made the same challenge
to standing which it makes here—that plaintiff’s
injury was too speculative
because there was no assurance that, if
successful with the protest, plaintiff
would receive the award.
The Federal
Circuit rejected the government’s argument. It
began with
the proposition that determining bid protest
standing is a two-prong test
requiring the protestor “to establish that it
‘(1) is an actual or prospective
bidder and (2) possess[es] the requisite direct
economic interest.’” Id. at 1359
(quoting Rex Serv. Corp., 448 F.3d at 1308). The
first prong was not disputed.
Id. at 1359-60. As to the second prong, the
Weeks Marine court held that the
unique context of pre-award bid protests merited
a modification of the usual
standing requirement. It rejected the
“substantial chance” definition of direct
economic interest in favor of a more inclusive
test. Id. at 1361-62. The court
adopted the standard used by the trial court, in
which “standing is established by alleging a
‘non-trivial competitive injury which can be
redressed by judicial
relief.’” Id. at 1361 (quoting unattributed
source). This standard “strikes the
appropriate balance between the language of §
1491(b)(1) . . . and Article III’s
standing requirements.” Id. at 1362. The court
noted that a different result
would lead to the anomalous outcome that the
protestor had no standing, but
if it subsequently challenged an actual award at
a later point in the process, it
would be confronted with the argument that, by
not protesting, it had waived
the right to challenge the terms of the
solicitation.
The court also
reasoned that a different result would be at
odds with
prior decisions recognizing the broad terms of
28 U.S.C. § 1491’s
jurisdictional grant to this court. See RAMCOR
Serv. Group, Inc. v. United
States, 185 F.3d 1286, 1289 (Fed. Cir. 1999)
(noting that language in
§ 1491(b)(1) “is very sweeping in scope”). This
court has been given
jurisdiction to hear challenges to “any alleged
violation of statute or regulation
in connection with a procurement or a proposed
procurement.” 28 U.S.C.
§ 1491(b)(1). Denying standing to a protestor
attempting to enforce one of the
statutory requirements related to a procurement
would be tantamount to
making the procedure illusory.
We therefore
conclude that the Weeks Marine standard strikes
the
appropriate balance in a bid protest seeking an
allegedly mandatory post-award
debriefing. An interested party is an actual or
prospective bidder alleging a
non-trivial competitive injury related to the
procurement which can be
redressed by judicial relief. Here, Navarro
satisfies this standard and therefore
has standing.
Navarro satisfied
the first prong of the test—an actual or
prospective
bidder—when it submitted a bid on the RFQ. We
also believe Navarro has
satisfied the second prong by alleging a
non-trivial competitive injury capable
of judicial redress. If Navarro were to prevail
here and receive the debriefing
it seeks, it would then have the ability,
assuming it refiled a protest at GAO,
to trigger a stay of the transition to the new
contractor. In such situations, it
is not uncommon for the incumbent contractor to
continue performance during
the pendency of the stay. The ability to perform
during this interim period is
not a trivial benefit. Furthermore, the
information gleaned from the debriefing
could be helpful to Navarro in its protest at
GAO and in shaping its future
bidding strategies. Finally, a stay in place
during the pendency of a protest
allows the court, in the event the protest is
well founded in fact and law, to
award injunctive relief without the extraneous
concern that too much work has been performed by
the putative awardee to prevent undue harm to it
or the
government.
In sum, Congress
created a mechanism that gives a bidder the
presumptive right to a stay during the pendency
of a bid protest at GAO. We
need not second guess why Congress believed it
important to the competitive
process to create such a possibility. Nor do we
second guess the assignment
to this court of the responsibility to hear
protests involving a statute or
regulation connected with that same procurement.
It is sufficient to say that
our obligation to hear the latter type claim
would be meaningless if the
protestor here had to persuade us that it would
succeed at GAO. Plaintiff has
standing. (Navarro
Research and Engineering, Inc. v. U. S., and
Portage, Inc., No. 10-481C, August 16, 2010)
(pdf)
Standing
The Government contends that L-3 does not have standing and that
this Court lacks jurisdiction because L-3 is not an interested party under the
ADRA. The Federal Circuit has construed the term “interested party” in the ADRA to have the
same meaning that it has under the Competition and Contracting Act, 31 USC § 3551-56 (“CICA”).
E.g., Rex Service Corp. v. United States, 448 F.3d 1305, 1307 (Fed. Cir. 2006);
American
Federation of Government Employees v. United States, 258 F.3d 1294, 1302 (Fed. Cir. 2001). CICA
defines the term “interested party” to mean “an actual or prospective bidder or offeror whose direct
economic interest would be affected by the award of the contract or by failure to award the
contract.” 31 U.S.C. § 3551(2)(A). Defendant contends that L-3 fails to qualify as an interested party
because it was not an actual or prospective offeror and did not submit a proposal -- indeed it did not even
exist when its predecessor submitted its offer. While this is true, this argument ignores the reality
that L-3 is the complete successor-in-interest to the actual offeror, Raytheon Company, and embraces the
identical business unit which submitted Raytheon Company’s bid in the C-5 AMP procurement. As
such, L-3 stands in the shoes of Raytheon Company in the instant case and has standing to
pursue this claim. See Alabama Aircraft Industries, Inc. v. United States, 83 Fed. Cl. 666, 682
(2008) (holding that successor-ininterest to the original offeror, was in effect, the same legal entity
which had submitted its proposal and was an interested party under ADRA); accord,
Coggeshall Dev.
Corp. v. United States, 23 Cl. Ct. 739, 743 (1991) (holding that successor-in-interest under
Government deed had a contractual relationship with the United States and could maintain a breach
of contract action); Harnischfeger Corp., B-224371, 86-2 CPD ¶ 296. As such, L-3 is an interested
party under ADRA and has standing to pursue this protest.
(L-3 Communications Integrated
Systems, L. P., v. U. S. and Lockheed Martin Aeronautics Company,
No. 06-396C-Costs, Filed November 26, 2008, Reissued December 5,
2008) (pdf)
The Air Force and Boeing contend that
Alabama Aircraft does not have standing, and thus that this court has no jurisdiction over Alabama Aircraft’s
claims, because it is not an “interested party” under the ADRA. The Federal Circuit has
construed the term “interested party” in the ADRA to have the same meaning as it does under the
Competition in Contracting Act, 31 U.S.C. §§ 3551-56. Rex Service, 448 F.3d at 1307;
American Fed’n of Gov’t Employees v. United States, 258 F.3d 1294, 1302 (Fed. Cir. 2001).35
Standing to bring a protest under the ADRA is “limited to actual or prospective bidders or offerors
whose direct economic interest would be affected by the award of the contract or by failure to
award the contract.” American Federation, 258 F.3d at 1302. The Federal Circuit has refined
its definition of interested party to require a protestor to have a “greater than an insubstantial
chance of securing the contract if successful on the merits of the bid protest.”
Information Tech.
& Applications Corp. v. United States, 316 F.3d 1312, 1319 (Fed. Cir. 2003).
The Air Force and Boeing claim that Alabama Aircraft fails to
qualify as an “interested party” because “it is not the same entity that submitted a
proposal” and because it lacks adequate financial resources to perform the KC-135 contract. Intervening Def.’s Reply to Pl.’s Opp’n to Def.’s and Intervening Def.’s Mot. to Dismiss at 1-2
(“Intervening Def.’s Reply on Standing”); see also Def.’s Mot. to Dismiss at 10. The Air Force further
argues that “[i]f Pemco actually wished to change its name, or declare [Alabama Aircraft] a
successor in interest to the bid, as [Alabama Aircraft] appears to allege, Pemco should have done so
formally so that the Government could determine if its interests are protected.”
Def.’s Mot. to Dismiss at 11. Alabama Aircraft resists these contentions on the grounds that
it is the same corporate entity as Pemco Aeroplex, that the Air Force had notice of the sale of
Pemco World Air and the resulting name change, and that it has the financial capability to perform
the contract, as evidenced by an audit report prepared in June 2008 by the Defense Contract Audit
Agency. Pl.’s Opp’n to Def.’s and Intervening Def.’s Mot. to Dismiss at 10, 19-20 (“Pl.’s
Opp’n). Whether Alabama Aircraft qualifies as an “interested party” and has standing to protest
must be addressed as a threshold issue in this case. (p.
19)
(sections deleted)
Alabama Aircraft has
standing to challenge the Air Force’s award of the KC-135 PDM
contract because it satisfies the definition of “interested
party.” Despite its name change and the sale of a sister subsidiary, Alabama Aircraft is the same legal
entity as the company that submitted its second final proposal revision in June 2007.
Alabama Aircraft has the same operational capabilities as its predecessor and due to the sale
to the sister company it is in a stronger financial position to perform the instant contract.
Furthermore, the Air Force had ample notice of the sale of the sister company and failed to initiate
any inquiries about whether the sale called into question Alabama Aircraft’s capabilities to perform
the contract. The DCAA audit report completed in June 2008, while not the equivalent of a
responsibility determination, confirms that for the near future Alabama Aircraft has
sufficient financial resources to perform under the contract. For these reasons, Alabama Aircraft
continues to be an interested party with standing to pursue this bid protest.
(p. 24) (Alabama Aircraft
Industries, Inc. - Birmingham v. U. S., and The Boeing Company,
No. 08-470C, October 7, 2008) (pdf)
1. Standing as a function of relative responsiveness
Plaintiff argues that it has standing to pursue this action (1)
because it was an actual offeror in this Solicitation and (2) because its direct economic
interest would be affected adversely by the award to CSC, the successful bidder. Plaintiff
contends that the MCC arbitrarily excluded plaintiff’s proposal from the competitive
range because plaintiff’s final proposal still contained open-market items (plaintiff argues
that this nonconformity was illusory), whereas CSC’s final proposal manifested the same type
of noncompliance for a similar requirement.
Defendant had argued in its two briefs that the MCC’s exclusion
of plaintiff’s final proposal as noncompliant defeats its claim to standing. See
Def.’s Br. filed Aug. 8, 2008, at 1; Def.’s Br. filed July 31, 2008, at 19. During oral
argument, however, defendant conceded that plaintiff has
standing to challenge the MCC’s determinations that plaintiff’s proposal was noncompliant and that CSC’s proposal was compliant.
See Transcript of Proceedings, at 36, Dyonyx, L.P. v. United States, No. 08-458C
(Fed. Cl. Aug. 19, 2008) (“Tr.”). (“Our view is that Dyonyx has standing to address two
issues here. First, whether or not their proposal was in fact compliant, which goes to the
open-market issue, and, secondly, whether or not CSC’s proposal was in fact compliant.”)
Defendant nonetheless would limit the court’s consideration to these issues.
Although jurisdiction cannot be established by a litigant’s
concession, see Industrial Addition Ass’n v. Comm’r, 323 U.S. 310, 313 (1945) (stating that
parties cannot confer jurisdiction by mutual consent), accord Grantham v. Brown, 114
F.3d 1156, 1158 (Fed. Cir. 1997); Gould v. Control Laser Corp., 866 F.2d 1391, 1393 (Fed.
Cir. 1989); Glasstech, Inc. v. AB Kyro OY, 769 F.2d 1574, 1577 (Fed. Cir. 1985), defendant,
in effect, acknowledged that using the acceptability of a proposal to determine standing
could produce an inane result. Thus, defendant would be arguing that, even if CSC’s proposal
was materially noncompliant, plaintiff lacked standing to question the award because
plaintiff’s proposal was materially noncompliant. Ultimately, defendant argued that plaintiff’s
final proposal failed a mandatory requirement that pertained to compliance, whereas CSC’s proposal
manifested a weakness in staffing, a non-mandatory technical subfactor that the MCC
considered in weighing the minimum qualifications of the staff proposed by both plaintiff
and CSC. This argument is not an issue of standing.
The caselaw has confused the legal issue whether a noncompliant
proposal forfeits the offeror’s status as an actual offeror. This confusion arises
within the Court of Federal Claims and not in the binding precedent of the Federal Circuit.
The confusion traces to the Federal Acquisition Regulation, which attaches the concept of
responsiveness to eligibility “[t]o be considered for award.”
PART 14 – SEALED BIDDING
SUBPART 14.3 – SUBMISSION OF BIDS
14.301 Responsiveness of bids.
(a) To be considered for award, a bid must comply in all
material respects with the invitation for bids [IFB]. Such compliance
enables bidders to stand on an equal footing and maintain the integrity of the
sealed bidding system.
The FAR confines the concept of responsiveness to sealed
bidding. FAR Part 15 Contracting by Negotiation, governing competitive procurements,
neither employs the term nor the concept of “responsiveness.”
This distinction is significant. As the Federal
Circuit held in AFGE, 258 F.3d at 1302, “the term ‘interested
party’ in [28 U.S.C.]
§ 1491(b)(1), . . . [as related to standing] is limited to
actual or prospective bidders or
offerors whose direct economic interest would be affected by the
award of the contract or by
failure to award the contract.”
Subsequently, the Court of Federal Claims in A&D Fire
Protection, Inc. v. United
States, 72 Fed. Cl. 126, 139 (2006), involving a negotiated
procurement (an RFP) held that,
by failing to prove that it submitted a bid bond, the offeror
has failed to show that it was a
“qualified bidder” and therefore lacked standing. The court also
held that the solicitation’s
prohibition of submission of a bid bond via facsimile
transmission rendered the proposal
nonresponsive. See id. at 138-40. The court in Dismas Charities,
Inc. v. United States, 75
Fed. Cl. 59 (2007), another negotiated procurement, cited and
quoted A&D for the
proposition that a bidder submitting a nonresponsive bid lacks
standing and continued:
Although responsiveness is generally used to describe sealed
bids, the same
concept applies to final offers submitted after negotiations.
Just as a sealed bid
that does not meet the minimum solicitation requirements is
non-responsive
and cannot be considered for contract award, FAR § 14.301(a), a
Final Proposal Revision that does not conform to the solicitation
requirements is technically unacceptable and cannot be considered for award
unless the agency reopens negotiations for all offerors or modifies the
solicitation. See FAR § 15.307(b); cf. Labat-Anderson, Inc. v. United States, 42 Fed. Cl.
806, 841 (1999) (contrasting technically unacceptable initial proposals
with technically unacceptable Best and Final Offers).
Dismas Charities, 75 Fed. Cl. at 61.
FAR § 15.307(b) addresses proposal revisions in negotiated
procurements. Although Labat-Anderson states that generally a technically unacceptable
proposal must be excluded from the competitive range, neither FAR § 15.307(b) nor
Labat-Anderson
purports to address standing as a function of technical acceptability. Nor does
Burroughs Corp. v. United States, 617 F.2d 590 (Ct. Cl. 1980), 3/ cited by Labat-Anderson for the
proposition that a technically unacceptable proposal cannot be
considered for award. Id. at 596 (cited in Labat-Anderson, 42 Fed. Cl. at 841).
Defendant’s opening brief seized on Dismas as authority for its
argument that plaintiff’s proposal was “non-responsive” and “non-compliant”
and thereby forfeited plaintiff any standing to protest. Def.’s Br. filed July 31, 2008, at 19.
However, Dismas cited a regulation and case, FAR § 15.307(b) and
Labet-Anderson, that
apply to consideration of
evaluation of negotiated proposals after discussions.
While defendant drew support from Dismas, it was also inspired
by Eracent, Inc. v.
United States, 79 Fed. Cl. 427 (2007), also cited in defendant’s
opening brief. This case
involved a GSA FSS acquisition for which a non-FSS contractor
had standing to challenge
whether a FSS order included non-FSS items which, by regulation,
were prohibited from
inclusion in a task order. The court ruled on the merits. To the
extent that the non-FSS
contractor/protestor was challenging a potential violation of 31
U.S.C. § 3324 (2000)
(dealing with advances of public money), the court alternatively
ruled that plaintiff lacked
standing. 79 Fed. Cl. at 433. Judgment, however, was entered on
the merits.
Given that Dismas cannot stand for the broad proposition argued
in defendant’s
opening brief, the court reiterates that it is the Federal
Circuit, not the Court of Federal
Claims, that issues the decisions defendant should cite as law.
As Judge Bush pointed out
in her recent decision Tip Top Construction Inc. v. United
States, 2008 WL 3153607 (Fed.
Cl. Aug. 1, 2008), Rex is the law of the Circuit. The
Government’s efforts to whittle away
the jurisdiction of the Court of Federal Claims by circular
arguments attacking standing, such
as in Tip Top, 2008 WL 3153607 at *11 (characterizing as
“circular” defendant’s argument that protestor could not show
that it was responsible and therefore could not show that it had
a substantial chance of winning award), or in the case at bar
(arguing that offeror had no
standing based on noncompliant sources of items proposed), are
transparent and misleading
attempts to change binding law. (Dyonyx,
L. P., v. United States, No. 08-458C, September 15, 2008) (pdf)
The Tucker Act permits postaward bid protests to be brought by
“interested parties.” 28
U.S.C. § 1491(b)(1). The United States Court of Appeals for the
Federal Circuit (“Federal
Circuit”) has held that the term “interested party” should be
construed in accordance with the
Competition in Contracting Act of 1984, and that, accordingly,
“standing under § 1491(b)(1) is
limited to actual or prospective bidders or offerors whose
direct economic interest would be
affected by the award of the contract or by failure to award the
contract.” Am. Fed’n of Gov’t
Employees v. United States, 258 F.3d 1294, 1302 (Fed. Cir. 2001)
(citing 31 U.S.C.
§ 3551(2)(A)). Accordingly, plaintiff must establish that it
“(1) is an actual or prospective
bidder, and (2) possesses the requisite direct economic
interest.” Rex Serv. Corp. v. United
States, 448 F.3d 1305, 1307 (Fed. Cir. 2006).
To prove that it possesses a “direct economic interest,”
plaintiff must show that it had a
“substantial chance” of receiving the contract. Id. at 1307. In
other words, “[t]o have standing,
the plaintiff need only establish that it ‘could compete for the
contract’ . . . .” Myers
Investigative & Sec. Servs., Inc. v. United States, 275 F.3d
1366, 1370 (Fed. Cir. 2002) (citing
Impresa Construzioni Geom. Domenico Garufi v. United States, 238
F.3d 1324, 1334 (Fed. Cir.
2001)).
(sections
deleted)
As the court reads the complaint, plaintiff seeks two forms of
relief. First, plaintiff
requests that the court set aside the contract award to
defendant-intervenor. In support of this
request, plaintiff contends in Counts I and II that the Army and
the SBA knowingly failed to
consider defendant-intervenor’s ostensible subcontractor during
the procurement process.
However, plaintiff is not an “interested party” entitled to
pursue either claim because under the
facts of this case, there is no chance, much less a substantial
chance, that plaintiff could be
awarded the contract in the event that the Army’s contract with
defendant-intervenor is set aside.
Assuming, arguendo, that the SBA and the Army improperly
considered defendant-intervenor to
be a small business, plaintiff itself is not a small business
and there remains a small business in
the competitive range–Torres–that would be awarded the contract
if the award to defendantintervenor
is set aside. Plaintiff’s argument that Torres is not a small
business, id. at 2, 12-17,
20, lacks merit because neither the contracting officer nor the
SBA has determined that Torres is
not a small business, and this court lacks any authority to
entertain a size protest. See 13 C.F.R.
§ 121.1002 (providing that the SBA “makes all formal size
determinations”); see also Compl.
¶¶ 25, 29 (alleging that plaintiff lodged a size protest of
Torres with the SBA as part of its size
protest of defendant-intervenor but that the SBA dismissed its
size protest of defendantintervenor
for lack of standing, without addressing the size protest of
Torres). Thus, without any
The second, and more general, form of relief requested by
plaintiff is the full and open
recompetition of the contract. However, to obtain such relief,
the court would first be required to
set aside the contract award to defendant-intervenor, relief
that the court has already determined
that plaintiff is foreclosed from pursuing because it lacks
standing. Thus, it follows that
plaintiff lacks standing to seek recompetition of the contract.
As noted by defendant, Def.’s
Reply Support Def.’s Mot. Dismiss Lack Standing & Non-Justiciability
7-10, the cases cited by
plaintiff in support of its standing argument are unpersuasive.
For example, plaintiff’s reliance
upon Impresa Construzioni is unavailing because even though the
Federal Circuit held that
sustaining the bid protest would require the contract to be
rebid, 238 F.3d at 1334, its holding
was undoubtably based on the fact that after setting aside the
award, there were no other offerors
in the competitive range to which the award could be made, see
id. at 1329. This is not true in
the instant case, where Torres remains a qualified bidder in the
competitive range. (International
Management Services, Inc., v. U. S. and Aegis, Mission Essential
Personnel LLC, No. 07-831C, Reissued January 9, 2008) (pdf)
In this bid protest action, Plaintiff, Ezenia!, Inc. (Ezenia),
as well as the Defendant-
Intervenor Carahsoft Technology Corp. (Carahsoft), are vendors
on the Army’s Federal Supply Schedule that provide commercial
software to the military. The military, and in particular the
Army,
use different types of software for command and control of
soldiers, especially those who are
engaged in combat operations. These products allow
video-teleconferencing on a computer via the
internet in a secure environment, while at the same time
allowing the computer screen to show the
windows from other computer programs such as PowerPoint
presentations or battle plan diagrams.
Two such products are Adobe Breeze (now called Adobe Connect)
and Ezenia’s InfoWorkspace
(IWS). Because of the need for interoperability, the Army
standardized the software through an
evaluation technique called “Best of Breed” and chose Adobe
Breeze as its computer software.
Ezenia clearly states in its papers that it is not protesting
the actual decision of the Army to
standardize, but rather is challenging the award of sole-source
contracts for the brand name Adobe
Connect product. Ezenia alleges that three contracts were
procured in violation of the proper
statutory and regulatory guidelines governing those awards. As
such, Ezenia asserts that it is an
interested party protesting the Army’s actions in connection
with these procurements.
Defendant and Defendant-Intervenor move this Court to dismiss
Plaintiff’s action pursuant
to Rule 12(b)(1) for want of subject-matter jurisdiction. Both
Defendant and Defendant-Intervenor
argue that the matter must be dismissed because Plaintiff fails
to identify a procurement action
within this Court’s jurisdiction, and/or that Plaintiff is not
an “interested party” with standing to
bring this action. Both assert that Ezenia is not an
“interested party” because Ezenia is not a
qualified bidder. Both further contend that Ezenia is really
protesting the standardization decision
of the Army to use the Adobe product and that this Court is
without jurisdiction to entertain such
a protest.
After briefing, oral argument and careful consideration, the
Court finds that it must dismiss
this matter. It is clear to the Court that even though Ezenia
states clearly that it is not challenging
the Army’s decision to standardize, that is exactly what Ezenia
is challenging. The procurements
that have been identified by both Plaintiff and Defendant are
purchases that were properly done
within the statutory and regulatory guidelines. Although not
necessary, the Court also finds that
Plaintiff is not an interested party. The Court, therefore,
GRANTS Defendant’s and Defendant-
Intervenor’s Motions to Dismiss. (Ezenia!,
Inc. v. U. S. and Carahsoft Technology Corporation, No.
07-759C, Reissued after seal on January 4, 2007)
Even assuming, arguendo, that
plaintiff could establish his financial wherewithal,
technical and/or other necessary specialized expertise, and
prior experience in contracting
on similar projects suited to the Solicitation, plaintiff
nonetheless would be unable to
establish that he had a substantial chance of contract award.
Because plaintiff did not submit
a bid prior to the close of the period for submission of
proposals, even if he could prevail on
his challenge to the terms of the solicitation and the court
were to order a reevaluation of the
proposals with the allegedly illegal provisions removed,
plaintiff would have no chance of
securing award of the contract, as he has formulated it. Rex
Serv. Corp., 448 F.3d at 1308
(holding that plaintiff-protestor alleging violations in
solicitation process did not have
“substantial chance” of receiving contract because plaintiff
never bid on contract prior to
close of solicitation); see also AFGE, 258 F.3d at 1302
(“Congress intended standing under
the [ADRA] to be limited to disappointed bidders.”)
Plaintiff does not qualify as an interested party with standing
under the ADRA
because he does not establish a substantial chance of award and
thus does not show a direct
economic interest in the award or failure to award the contract.
Nonetheless, in the interest
of giving full consideration to the issue of standing, the court
examines the issue of plaintiff’s
status as an actual or prospective bidder. (Brian
X. Scott, v. U. S., No. 07-216C, August 23, 2007) (pdf)
This Court has held that "[a] bidder submitting a nonresponsive
bid has no standing to
protest an award, because it has no chance of receiving the
award." A & D Fire Protection, 72 Fed.
Cl. at 138. Although responsiveness is generally used to
describe sealed bids, the same concept
applies to final offers submitted after negotiations. Just as a
sealed bid that does not meet the
minimum solicitation requirements is non-responsive and cannot
be considered for contract award,
FAR § 14.301(a), a Final Proposal Revision that does not conform
to the solicitation requirements is
technically unacceptable and cannot be considered for award
unless the agency reopens negotiations
for all offerors or modifies the solicitation. See FAR §
15.307(b); cf. Labat-Anderson, Inc. v.
United States, 42 Fed. Cl. 806, 841 (1999) (contrasting
technically unacceptable initial proposals
with technically unacceptable Best and Final Offers).
The Government and Bannum claim that Dismas submitted a
non-compliant proposal by
including the 240-day development schedule. However, Bureau of
Prisons decisionmakers
evaluated Dismas's Final Proposal Revision on its merits in its
Source Selection Decision (“SSD”)
dated February 6, 2006, and never explicitly stated that it did
not comply with the solicitation. The
SSD elsewhere declared that "[a]ll of the offerors' responses to
‘Request for Final Proposal
Revisions' have been reviewed and determined to be acceptable,"
AR 1307, that "Dismas received a
color rating of Blue/Very Good" for the Site Location factor
under Technical/Management, which
included the comments about the 240-day start-up period, AR
1315, and that "Dismas met the
minimum requirements" for Technical/Management and "was rated
higher than the other offerors"
for that category. AR 1319. Even the post-award debriefing
letter, dated May 31, 2006, declared
that "Dismas' proposal also met the requirements of the
solicitation in every factor of the solicitation
and had a very good solution for meeting the needs and
objectives of the program.” AR 923.
In a similar case, the Court determined that a plaintiff whose
potentially non-responsive bid
was treated as an alternative proposal by the agency, which then
evaluated the bid on the merits, did
have a substantial chance of receiving the award, and therefore,
was an interested party for the
purposes of this Court's bid protest jurisdiction. Galen Medical
Assoc., Inc. v. United States, 56
Fed. Cl. 104, 108 (2003), aff'd 369 F.3d 1324 (Fed. Cir. 2004).
Despite Dismas's current argument
that, like the Galen bid, its 240-day proposal was "an
alternative, additional option," the Final
Proposal Revision never described it as such. AR 859-60. In
fact, Plaintiff’s counsel admitted at
the hearing that no language in the record itself supported
Dismas’s argument that the 240-day startup
plan was an alternative proposal. Transcript at 30-31. Instead,
Dismas used the words "revise"
or “revised” at least five times in the Final Proposal Revision
in referring to its new plans. AR
859-60. These contemporaneous descriptors point to a replacement
of the original 120-day plan
with a 240-day plan, rather than a possible alternative. The
fact that the Bureau of Prisons personnel
evaluated Dismas based on the increased costs associated with
the 240-day plan, compare AR 860
with AR 1319, demonstrates that they also considered it a
substitute rather than an option. In
addition, there was no evidence in Galen that the contracting
officials "found plaintiff's proposal
technically unacceptable." 56 Fed. Cl. at 108. In contrast, the
Bureau of Prisons officials in this
case noted in the final SSD that Dismas's 240-day start-up
period "would extend beyond the
required performance date." AR 1315.
Because Dismas's 240-day proposal was not "an alternative,
additional option," A & D Fire
Protection provides more useful guidance. In that case, the
Court held that a protestor was not an
“interested party” because its bid had not included a required
bid bond and was therefore
non-responsive. 72 Fed. Cl. at 140. The Court concluded that the
protestor did not have
standing–even though its bid had been evaluated twice by the
agency, and it had not been declared
non-responsive. Id. Similarly, Dismas did not meet a fundamental
requirement of the solicitation,
and it "cannot excuse its failure to properly submit a
[requirement] by the agency's lack of diligence
in removing a nonresponsive bid from consideration." See id.
Dismas submitted a Final Proposal
Revision that did not conform to the solicitation requirements.
As a result, it did not have a
substantial chance of contract award and cannot be an
"interested party" for purposes of this Court's
bid protest jurisdiction. (Dismas
Charities, Inc., v. U. S. and Bannum, Inc., 06-825C,
February 7, 2007) (pdf)
Because we conclude that Fire-Trol has not shown itself to be an
“interested party” within
the meaning of 28 U.S.C. § 1491(b)(1), we do not reach the
question whether the statutory and
regulatory violations Fire-Trol alleges are “in connection with
a procurement or a proposed
procurement,” id., even though the USFS has not yet issued a
solicitation. Nor do we reach the
question whether plaintiff’s claim based on alleged violation of
the APA would be within the
Court’s jurisdiction if the Court were to hold that the alleged
APA violation was “in connection
with a procurement or proposed procurement.” Id.
Though Fire-Trol has expressed its intention to bid in response
to solicitations to be
issued during the USFS’s 2005 procurement for wildland fire
retardant, it concedes that no such
solicitation has yet been issued. Given that fact, Fire-Trol is
not now “an actual or prospective
bidder or offeror” within the meaning of 31 U.S.C. § 3551(2).
Therefore, Fire-Trol is not now an
“interested party” within the meaning of 28 U.S.C. § 1491(b)(1).
(Fire-Trol Holdings, LLC v.
U. S., No. 04-1389C, October 12, 2004) (pdf)
Although the United States Court of Appeals for the
Federal Circuit has not explicitly addressed the
standard of review for a plaintiff’s standing in a
pre-award context, the court is persuaded that a
plaintiff would not be required to establish that, but
for the alleged error, “there was a substantial chance
it would have received the contract award[.]” Alfa
Laval, 175 F.3d at 1367. At the pre-award juncture, a
plaintiff usually will not know who the other offerors
are and may not know their bona fides. Indeed, if the
plaintiff had knowledge of these facts, certainly a
factual question of how that information was ascertained
would raise an issue under the Sherman Act, 15 U.S.C. §§
1 and perhaps the Procurement Integrity Act, 41 U.S.C.
§§ 401-36, as well. Without at least some of this
information, however, a plaintiff would have no idea
whether its offer would be within the “zone of active
consideration.” Statistica,102 F.3d at 1581. Of course,
a rule could be fashioned that would require a plaintiff
to have prior comparable industry experience or
experience as a government contractor, but such a rule
would preclude a new entrant from being able to assert a
bid protest. For these reasons, the court declines to
require the plaintiff in this case to satisfy the
“substantial chance” standing test pre-award, but rather
will rely on the “interested party” test until the
United States Court of Appeals for the Federal Circuit
directs otherwise. (Red
River Service Corp., v. U. S., No. 03-2747C, April
30, 2004) (pdf)
MCI Telecomm. Corp. v. United States, 878 F.2d 362 (Fed. Cir. 1989),
presented the nearly identical question of “whether a would-be protestor wishing to
bring about a resolicitation on which it says it intends to bid has the necessary status,
even though it failed to either bid in response to the original solicitation or to protest
before the close of the proposal period...” 878 F.2d at 364.1 In MCI, as here, plaintiff
charged that the government waived mandatory contract requirements and that a
resolicitation should occur. The Court reasoned that the use of the word “prospective”
indicated that, “in order to be eligible to protest, one who has not actually submitted
an offer must be expecting to submit an offer prior to the closing date of the
solicitation...the opportunity to qualify either as an actual or a prospective bidder ends
when the proposal period ends.” MCI, 878 F.2d at 365. See also Fed. Data Corp. v.
United States, 911 F.2d 699, 704 (Fed. Cir. 1990); United States v. IBM, 892 F.2d
1006, 1010-11 (Fed. Cir. 1989); Ryan Co. v. United States, 43 Fed.
Cl. 646, 657 (1999). Therefore, because McRae decided not to submit a bid for this contract or
protest the RFP requirements prior to the close of bidding, McRae is not a
“prospective bidder” and does not have standing to challenge the award.
(McRae
Industries, Inc. v. U. S.. No.
01-460C, August 14, 2002) (pdf) |