Here, we find reasonable the Army's
determination that the inclusion of these Fort Lee employees on
the SSEB did not create a conflict or apparent conflict of
interest. The protester has not shown that these employees will
be directly affected by the outcome of the procurement; that is,
none of these employees' positions are subject to being
contracted out. (IT
Facility Services-Joint Venture, B-285841, October 17, 2000)
In a cost comparison study
pursuant to Office of Management and Budget Circular No. A-76,
where 14 of 16 agency evaluators held positions under the study
and thus subject to being contracted out, a conflict of interest
that could not be mitigated was created, and protests
challenging the evaluators' conclusion that all private-sector
offers were unacceptable are therefore sustained. (DZS/Baker
LLC; Morrison Knudsen Corporation, B-281224; B- 281224.2;
B-281224.3; B-281224.4; B-281224.5; B-281224.6, January 12,
1999) |
|
Comptroller
General - Listing of Decisions |
For
the Government |
For
the Protester |
IT
Facility Services-Joint Venture, B-285841, October 17, 2000 |
DZS/Baker
LLC; Morrison Knudsen Corporation, B-281224; B- 281224.2;