Jump to content






Those Pesky IDIQ Contracts Again

Posted by Vern Edwards, 22 June 2009 · 9,326 views

In a recent thread in the Wifcon discussion forum, a member asked if a task order issued under an Indefinite-Delivery Indefinite-Quantity (IDIQ) contract can contain an option that permits extension of the order beyond the contract expiration date. Here is the question:

QUOTE
[T]he requiring activity wants to put a task order in place that has a base year and 2, one-year options. The ID/IQ contract expires half way through the first one-year option. What authority allows you to exercise the second option year?

At about the same time as that post, I received a telephone call from a former student asking virtually the same question.

Those questions come after the decision by the Armed Services Board of Contract Appeals? decision in General Dynamics C4 Systems, Inc., ASBCA No. 54988, May 8, 2009, http://docs.law.gwu....f2009/54988.pdf. We work in a time in which people do not read the Federal Acquisition Regulation and the standard clauses in their contracts. The General Dynamics decision shows the latent potency of those clauses. So I thought it might be useful to review the standard terms of IDIQ contracts to see how we can answer the questions.

In this piece, when I write ?task order? I?m including delivery orders.

Key Terms of IDIQ Contracts

FAR 16.504, which describes Indefinite-Delivery contracts, prescribes their content and establishes rules for their use. FAR 16.504(a)(4)(i) provides, without further explanation, that an IDIQ contract must:

QUOTE
Specify the period of the contract, including the number of options and the period for which the Government may extend the contract under each option? .

What is ?the period? of an IDIQ contract? In order to answer that question we must look first to the standard FAR clauses. FAR 16.506 prescribes two such clauses for use in IDIQ contracts: FAR 52.216-18, Ordering (OCT 1995) and FAR 52.216-22, Indefinite Quantity (OCT 1995). The Indefinite Quantity clause provides as follows:

QUOTE
Indefinite Quantity (Oct 1995)

(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.

(B) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the ?maximum.? The Government shall order at least the quantity of supplies or services designated in the Schedule as the ?minimum.?

? Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor?s and Government?s rights and obligations with respect to that order to the same extent as if the order were completed during the contract?s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after _______________ [insert date].

(End of clause)

Note that paragraphs (a) and (d) of the Indefinite Quantity clause refer to a period within which the contract is ?effective,? and which I?ll call the effective period. The clause provides no space in which to insert the start and end dates of the effective period, but indicates that the dates are ?in the Schedule.? When using the Uniform Contract Format described in FAR 14.201-1 and 15.204-1, the Schedule includes contract sections A through H.

Paragraph (d) of the Indefinite Quantity clause provides a space in which the contracting officer is supposed to insert the last date on which the government can require the contractor to perform or deliver, which I?ll call the last date of required performance. (See FAR 52.104(d) and (e) about making insertions in clauses.)

Note three things about paragraph (d): first, it implies that the contracting officer can issue an order requiring performance or delivery after the expiration of the effective period; second, it says that if the order is not to be completed within the effective period the terms of the contract will be extended ?with respect to that order?; and third, it indicates that the last date of required performance can also be later than the expiration of the effective period.

The Ordering clause provides as follows:

QUOTE
Ordering (Oct 1995)

(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from __________ through ____________ [insert dates].

(B) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

? If mailed, a delivery order or task order is considered ?issued? when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the Schedule.

(End of clause)

Note that the Ordering clause provides for the establishment of a period within which the government may issue task orders, which I will call the ordering period. The government may not issue task orders after expiration of the ordering period. The contracting officer is supposed to specify the ordering period by inserting dates in the space provided in paragraph (a). (This clause was central to the ASBCA?s General Dynamics decision.)

The Five Dates In An IDIQ Contract

Let?s review: Based exclusively on the texts of the Indefinite Quantity clause and the Ordering clause, an IDIQ contract is supposed to contain the following five dates:

1. somewhere in the Schedule, the date on which the effective period begins;

2. also in the Schedule, the date on which the effective period ends;

3. in paragraph (d) of the Indefinite Quantity clause, in Section I, the last date of performance;

4. in paragraph (a) of the Ordering clause, in Section I, the date of which the ordering period begins; and

5. also in paragraph (a) of the Ordering clause, the date on which the ordering period ends.

The contracting officer is supposed to insert the dates in the contract, but it is my impression that contracts are often awarded without the insertion of one or more of those sets of dates.

In addition to the five dates listed above, there will be the dates associated with each task order, such as the period of performance of services or the delivery dates for supplies.

If the contract contains the clause at FAR 52.217-9, Option to Extend the Term of the Contract (MAR 2000), then in addition to the above dates there will be the period within which the contracting officer may exercise each such option, the deadline for giving the contractor preliminary notice of the government?s intent to exercise the option, and the dates of the option period(s). The boards of contract appeals and the Court of Federal Claims strictly enforce dates associated with the power to exercise options, and they may treat the issuance of a task order as the exercise of an option in that regard. See the General Dynamics decision:

QUOTE
In Dynamics Corp. of America v. United States, 389 F.2d 424, 430-33 (Ct. Cl. 1968), the Court of Claims established that the government?s issuance of orders under an indefinite quantity contract is like its exercise of options and must be accomplished in strict accordance with the contract?s terms. The court found that the orders in question were not issued within the time period specified in the contract and granted summary judgment to the contractor for the reasonable value of goods it had delivered under protest when the government required it to perform. Indeed, it is settled that, ?[f]or an option order to be effective, the Government must exercise the option in exact accord with the terms of the contract.? Freightliner Corp. v. Caldera, 225 F.3d 1361, 1366 (Fed. Cir. 2000).

Thus, the interplay among all of the dates discussed above might in some cases become problematical.

The Effective Period And The Ordering Period: One And The Same?

It is possible that the author(s) of the Indefinite Quantity clause and the Ordering clause meant for the effective period and the ordering period to be one and the same. But the Indefinite Quantity clause puts the effective period in the Schedule and the FAR clause matrix puts the Ordering clause in Section I of the Uniform Contract Format, which is not part of the Schedule. If we assume that the author(s) of the two clauses knew what they were doing and meant to put the effective period and the ordering period in different sections of the contract, it seems likely that they did not mean for them to be one and the same. Thus, the ordering period might start after the first date of the effective period and end before the expiration date of that period.

The Mysterious ?Effective Period?

What is the contractual significance of the effective period mentioned in the Indefinite Quantity clause? In what sense is an IDIQ contract ?effective?? What is the operative relationship between the effective period and the ordering period, between the effective period and the performance period or delivery date(s) of an order, and between the effective period and option-related dates? The answers to those questions are not immediately apparent to me.

Presumably, the effective period is the time within which the rights and obligations of the parties are in effect. Do those rights and obligations expire with the effective period? For example, does the contractor?s obligation to take affirmative action in the employment of disabled workers end when the effective period expires? What about the contractor?s obligation to pay Service Contract Act wages or to comply with change orders? Are contract prices no longer in effect after expiration of the effective date? Remember that paragraph (d) of the Indefinite Quantity clause says:

QUOTE
Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor?s and Government?s rights and obligations with respect to that order to the same extent as if the order were completed during the contract?s effective period? .

Emphasis added. However, the paragraph goes on to say:

QUOTE
provided, that the Contractor shall not be required to make any deliveries under this contract after _______________ [insert date].

Thus, the contract terms and the rights and obligations of the parties with respect to a ?not completed? order do not expire with the effective period, but continue in effect until the order is completed, provided that completion is not later than the last date of performance.

When is an order ?completed?? Does ?completed? refer to the contractor?s work or to something else? Is an order ?completed? when the contractor delivers or finishes the work, i.e., when the contractor?s performance is completed? The phrase ?shall be completed by the contractor? seems to suggest so. Or does ?completed? mean when the government has accepted performance, or when the government has made final payment? Does it mean ?physically completed,? as described in FAR 4.804-4 with reference to the closeout of contract files:

QUOTE
(a) Except as provided in paragraph (B) of this section, a contract is considered to be physically completed when?

(1)(i) The contractor has completed the required deliveries and the Government has inspected and accepted the supplies;

(ii) The contractor has performed all services and the Government has accepted these services; and

(iii) All option provisions, if any, have expired; or

(2) The Government has given the contractor a notice of complete contract termination.

(B) Rental, use, and storage agreements are considered to be physically completed when?

(1) The Government has given the contractor a notice of complete contract termination; or

(2) The contract period has expired.

Absent some express definition of when an order is ?completed,? the meaning will depend on a reading of the contract as a whole, including the order, so that no term is rendered meaningless and without effect, which means that it cannot be defined in any abstract sense.

The Indefinite Quantity clause says that the terms of the contract continue to apply to uncompleted orders after expiration of the effective period, but what about orders completed within the effective period? Suppose that a fixed-price order requires the contractor to deliver supplies on a date prior to the expiration date of the effective period and that the contractor delivers accordingly. Suppose further that the government does not inspect the supplies before the expiration of the effective period. Finally, suppose that after expiration of the effective period the government discovers a patent defect in the delivered supplies. If the order was ?completed? upon the delivery of the supplies and the contract effective date has expired, can the government still invoke the terms of the fixed-price inspection clause, FAR 52.246-2, Inspection of Supplies⎯Fixed-Price (AUG 1996), and demand that the contractor correct the defects at no additional cost?

What if the contractor has completed an order and is still performing under another order when the effective period expires? Does the fact that one order remains uncompleted mean that the terms of the contract continue in effect with respect to ?completed? orders? The Indefinite Quantity clause says that the terms of the contract remain in effect ?with respect to that order,? not all orders.

Of course, these questions are of less concern when a clause expressly provides for the survival of rights and obligations after completion or final payment, such as in the clause at FAR 52.215-2, Audit and Records (JUN 1999), or a warranty clause. Note in that regard that the inspection clause for cost-reimbursement contracts requires the contractor to take corrective action for up to six months ?after acceptance.?

There are likely many other such possibilities as to the contractual significance of the effective period of an IDIQ contract. I have not tried to think them through and I have done no legal research, so I encourage readers of this blog to speculate or inform the rest of us of anything they may know or learn in that regard. In any case, contracting officers should be thoughtful when establishing the myriad dates in an IDIQ contract and be especially thoughtful about the potential effect of the effective date. It might be wise to ensure that timely administrative action is taken with respect to orders completed prior to the expiration of the contract effective period. It might not hurt to write special clauses to state the significance of the effective period and to define order ?completion? for purposes of the Indefinite Quantity clause.

One way to cope with the effective period problem would be to write a clause like the following and put it in Section H:

The effective period of this contract begins on the date of contract award and ends on the date following the date of final payment under this contract.

Options In IDIQ Contracts

The government may put options in IDIQ contracts to extend the effective period, the ordering period, and the last day of required performance. Note, however, that the standard clause at FAR 52.217-9, Option to Extend the Term of the Contract (MAR 2000), makes no express mention of ?effective period,? ?ordering period,? or last date of required performance. Thus, contracting officers should modify the clause when using it in an IDIQ contract to make express mention of those dates. (The preface to the standard option clause permits the use of a clause that is ?substantially the same.? See FAR 52.104 (a) through ? about modifying clauses.) Presumably, when establishing option line items, the contracting officer will want to stipulate the new effective period, new ordering period, and new last date of required performance associated with each option.

If an order is valued at less than $10,000,000 at the time of issuance, but an option in the order would increase the cumulative value of the order to in excess of $10,000,000, would the GAO consider a protest against the award of the order under FAR 16.505(a)(9)(i)(B), which does not say ?including options?? Probably. Keep in mind that FAR 1.108? says that options are to be included when applying dollar thresholds. Again, I know of no case law that directly answers the question.

Options in Task Orders

What about options in task orders? I know of no rule in FAR that prohibits the use of options is task orders. Presumably, the policies in FAR Subpart 17.2 apply to such options. Agencies may have policies of their own, as well. See, e.g., GSA?s policy with respect to Federal Supply Schedule contracts:

QUOTE
Options may be included on orders placed against GSA Multiple Award Schedule (MAS) contracts, provided that the options are clearly stated in the requirement and are evaluated as part of the ordering activity's best value determination. Such options may be exercised on GSA Schedule contract orders, provided that:

? Funds are available;

? The requirement covered by the option fulfills an existing government need;

? Prior to exercising an option, the ordering activity ensures that it is still in the government's best interest; i.e., that the option is the most advantageous method of fulfilling the government's need, price and other factors considered; and

? The options do not extend beyond the period of the Schedule contract, including option year periods.

There are questions about the use of options in task orders:

1. Can you put an option in a task order that is to be exercised before the expiration of the effective period and that would extend performance beyond that period?

2. If so, can such an option require performance after the last day of required performance stipulated in paragraph (d) of the Indefinite Quantity clause?

3. Can you put an option in a task order that can be exercised after the expiration of the effective period?

4. If so, can the option require performance after the last date of required performance?

The answer to the first question appears to be yes, since the Indefinite Quantity clause makes express provision for orders that require performance after the expiration of the effective period.

The answer to the second question should be yes if the option is written so as to extend the last date of required performance for the purposes of the order in question. Otherwise, there might be an issue. An agency should state its intent to use such options in the solicitation for the contract, and the contract should make express provision for the issuance of orders that include such options, otherwise, the use of such an option might be an expansion of the scope of the contract and subject to protest.

The answer to the third question is problematical. It would be best to extend the contract effective period prior to exercising such an option in a task order, just to avoid any issues about the viability of the option. Since extension of the effective period would expand the scope of the contract, the intention to do so in connection with such task order options should be stated in the solicitation for the contract and provided for in the contract.

The answer to the fourth question is also problematical. There might be an issue, unless the task order option expressly requires the contractor to work after the last date of required performance, thereby effectively extending that date for the task order in question. The contract should make provision for extension of the last date of contract performance in connection with such task order options.

What happens if the contracting officer issues an order containing an option that would permit its extension beyond the effective date or the last date of required performance? Can the contractor object and refuse to accept such an order? I think the contractor would have grounds to object and reject if, at the time of award, the contract did not expressly permit the issuance of such an order, such that the contractor was not or could not have been aware that it could happen. If the contractor did not object when the order was issued, can it later object to the exercise of the option? Again, I think so, if the contract or the order did not expressly permit such an extension, such that the contractor was not and could not have been aware. It seems likely that a court would require the contractor to perform if it knowingly accepts the order without objection.

What if, at the time of award, the contract did not expressly permit the issuance of such an order, but the contractor is willing to accept it? Would that make it okay? Probably not, because the exercise of such an option would enlarge the scope of the contract by effectively extending the effective period and the last date of contract performance, thus opening the way to a protest. Would it be okay to add such an option to a task order after its issuance? Again, doing so would enlarge the scope of the contract and open the way to a protest.

Is exercising an option to extend a task order tantamount to issuing a new order? I don?t know, but I think it is possible that a court, a board of contract appeals, or the Government Accountability Office (GAO) might consider it so. If so, can a contracting officer exercise such an option after the expiration of the ordering period or the last day of required performance? I think it?s possible that a court a board or the GAO would say no. I am aware of no case law that directly answers those questions.

Coordinate Those Dates!

Contracting officers should carefully coordinate all contract dates and task order dates in order to avoid potential conflicts and disputes. If a contracting officer wants to use options in task orders to permit their extension, then he or she should include options in the basic contract to extend the contract effective period and to change the last date of required performance. If such options are not included in the contract at the time of award, later changes in those dates will be outside the scope of the contract and open to protest.

Anyone who thinks that these matters are mere technicalities had better read the ASBCA?s General Dynamics decision, cited above. The board rejected that notion.

I have not attempted to make a detailed or comprehensive, much less exhaustive, analysis of these questions. My objective here is to raise questions that smart people will consider when writing IDIQ contracts and task orders.

Just a little word to the wise.





Vern,

As a matter of course, my Department of the Navy contracting office writes IDIQ contracts with a one year ordering/effective period, but no one can explain "why". Is there some specific problem with having a five year IDIQ (note that I've read your previous paper on the 5 year limitation and saw no specific prohibition identified therein)? Keeping in mind that we principally obligate O&M,N funds which are 1-year funds, I still see no problem as long as the ORDER'S performance period doesn't extend one year. Along these lines, could I write a service task order using FY2010 O&M,N funds with a performance period from 01 Oct 2010 thru 30 September 2010 and then, find that all of my services will not be performed (or effort expended) by 30 September and then deobligate the likely unused effort/funds before 30 September and then re-obligate them, thereby extending the life of my funds?

If I'm unclear, I'd be delighted to explain further.

Tx,

NavyKGuy
  • Report

Recent Comments

Tags

    October 2014

    S M T W T F S
       1234
    567891011
    12131415161718
    19202122232425
    26272829 30 31 

    3 user(s) viewing

    0 members, 2 guests, 0 anonymous users


    Bing (1)

    3 user(s) viewing

    0 members, 2 guests, 0 anonymous users


    Bing (1)