I am working on my first Termination for Default on a construction contract. The Government incurred some damages due to the default, i.e. damages such as having to take emergency protection measures on our building that was being sided since the default occured in the winter on the rainy Oregon Coast, and the building would have sustained water damage. We also plan to reprocure against the Contractor's account. Do I send two seperate demands for payment - one for other damages, and one for reprocurement costs, or can it all be rolled into one demand?