  1. When exercising an option, would there be a "Change in Price" or would there only be a change in obligation? or Both?
  2. I am trying to remove a CDRL requirement after contract award to determine the equitable adjustment. Since the data is not separately priced (NSP), I am having difficulty determining the value of the CDRL I want to remove. The Basis of Estimates (BOEs) from the original proposal are not clear on the hours that were bid for the task specific to this data. Does anyone have any experience with this or suggestions? I am considering removing the requirement for the Program Unique Specification Document (PIDS), but need to know what equitable adjustment to request. Any help you can offer would be greatly appreciated. Thanks in advance.
×
×