  1. Another long time reader of this forum, I am very interested in this topic as well. I agree with what Vern said "an IDIQ contractor is obligated to perform any task order that is within the scope and ordering limits of the contract", as this how I understand the language in 52.216-22( b ) Indefinite Quantity. Regarding the CO not being obligated to issue orders off of an IDIQ, I have always been under the impression that if a contracting activity awards an IDIQ for a particular product or service, any contract or order issued from that contracting activity for the same product or service outside of that contract would be viewed as splitting a requirement unless the IDIQ either ended or was terminated first. Of course, this is a bit of a grey area, but I wanted to see what others thought.
×
×