Upon award, a GAO protest was received and inevitably denied. In all, 94 days of performance were lost due to the stay imposed by GAO. Can the Govt mod the contract to get that time back? If so, would the period of performance simply change to a negotiated start date and all other performance periods (opt. 1-4) change with it?