Jump to content

Vkpitts

Members
  • Posts

    1
  • Joined

  • Last visited

Reputation

0 Neutral
  1. Greetings all! I have an Air Force PM who indicates reluctance to sign as approval authority in Block I. of the DD 1423 Contract Data Requirements List. The PM feels the Contracting Officer is the approval authority. I reviewed DoD 5010.12 but couldn't find a break down of CDRL approval authorities. The contract is for R&D, the data requirements are for progress reports, technical and scientific reports, computer software and prototype hardware. Thanks in advance to anyone who can come up with written direction!
×
×
  • Create New...