Is a J & A needed?


DonDon

Recommended Posts

5 hours ago, DonDon said:

I know the contract can be modified as the additional work is in scope under the original SOW.

First, what do you mean by this? Why do you say the additional work is in scope under the original SOW?

Link to comment
Share on other sites

I agree that adding additional work is not "in scope." But we use terms sloppily sometimes.

DonDon, Is the government really adding additional work?  Or does the contractor need to do additional work in order to complete the work already contracted for?  These are very different, but sometimes people can't see the difference.

Link to comment
Share on other sites