I have a FPAF construction contract where performance is going to be delayed by the Gov't. The prime contractor uses the percentage method to recover field overhead costs, while some of the subcontractors use the daily rate method. FAR 31.105(d)(3) requires consistency with established accounting practices in treating field overhead costs as direct or indirect. My question is: Does the prime contractor's established practice of treating field overhead costs as indirect costs preclude the subc