Construction MATOC Task Orders


dkubis

Recommended Posts

To issue a TO off of a Construction MATOC, is it really necessary to issue a 1442? It just seems like that's extra work and defeats the purpose. To me if it's already on an IDIQ it would be enough to just issue a Task Order, assuming all the terms and conditions are met. Am I wrong or what?

Link to comment
Share on other sites

  • 2 weeks later...

Vern, I believe you mean 53.216-1 and 53.236-1(d). I also suggest reviewing FAR Part 36.7 in conjunction with 36.101.

If you follow the interpretation that a task order is a "contract" for policy purposes (i.e. for interpreting and applying the regulations), then you should be using the SF 1442 if the orders are above the SAT (you can use OF-347 if below the SAT). If you believe that a task order is not a "contract" for policy purposes, then you can use the OF-347.

Link to comment