Posted for lkinser:

"Would like to know if a RFQ goes out Open Market and the quotes all reference a GSA Contract for services but Open Market for equipment how should this be handled? The RFQ went out GSA with no quotes to start with."

#2 woops85

woops85

    Bronze Member

  • Members
  • PipPipPip
  • 237 posts
  • Gender:Female
  • Location:DC area

Posted 10 September 2010 - 12:27 PM

Intent is probably that labor services must be on the referenced GSA contract (assume a schedule) but that the proposed equipment does not have to be. What did the issuing KO say when asked?

#3 napolik

napolik

    Silver Member

  • Members
  • PipPipPipPip
  • 480 posts
  • Gender:Male
  • Location:Alexandria, Virginia

Posted 10 September 2010 - 02:15 PM

Posted for lkinser:

"Would like to know if a RFQ goes out Open Market and the quotes all reference a GSA Contract for services but Open Market for equipment how should this be handled? The RFQ went out GSA with no quotes to start with."


Did you send out a second RFQ for services using other than FAR Part 8 procedures after failing to receive any quotes against a solicitation issued under FAR Part 8? Or, are you speculating about doing so?

If you did, how many quotes did you receive? Did the quotes cite the same GSA Schedule and SIN?