Funding, Ceiling, and EVM???


jhoward99

Recommended Posts

I work for a large gov?t agency on a level I acquisition program as the gov't EVM lead. We have a $1B contract with a prime. Under one large task order with many CLINs and many Control Accounts (CAs), we have several CAs that have under-run their budget. This is a LOE on a CPFF contract. The PM would like to have the contractor continue performing LOE work until the funds are exhausted. The CO has issued a contract mod to extend the PoP and allow the contractor to continue working - but will not add ceiling. My contractor EVM team is telling me that in order to plan the additional work, they need additional budget (ie, ceiling) against which to plan the additional work. Note the distinction - they don't need funding - they need ceiling.

As an example, say we are funded for, and plan $1M worth of LOE work over 12 months. As we set up our EV system, we budget $1M worth of work over 12 mos (BCWS) at a planned value of $1M (BCWP). At the end of 12 months, we've only spent $800k (ACWP = $800k). In EV terms, we have a cost variance of +200k - not a bad thing! We have measured costs against the $1M. Now, we want to spend an additional 200k. We have to plan that against an additional 200k, as we've already planned and measured against the original $1M. To do this, we need additional budget authority (again, ceiling) so that we will have planned $1.2M worth of work - which should come in at the funded amount of $1M. At the end, the BCWS = 1.2M, BCWP - 1.2M, and ACWP - 1M. Without the additional ceiling against which to plan the additional work, we will have a situation where we plan $0 work, schedule $0 work, but have $200k of cost - kind of tough to tell the taxpayer that we spent $200k on nothing.

My CO tells me that the FAR doesn't allow him to add ceiling when funding is sufficient. I say that he is adding scope (additional time on LOE work is scope, isn't it?) I say his options are to 1) add ceiling, but manage the contractor not to exceed funded amount, OR 2) close out the CA, de-obligate the remaining funds, and issue a new task/CA/whatever you want to call it, for the additional work the PM would like to have performed.

Am I wrong here? Certainly, I could be... but would welcome any comments that let me know where/how I'm wrong. I've looked for FAR clauses but can't find anything concrete. I know that EVMS guidelines (the 32 ANSI guidelines) definitely don't allow you to perform work that hasn't been properly planned. Thanks!!

Link to comment
Share on other sites

I work for a large gov?t agency on a level I acquisition program as the gov't EVM lead. We have a $1B contract with a prime. Under one large task order with many CLINs and many Control Accounts (CAs), we have several CAs that have under-run their budget. This is a LOE on a CPFF contract. The PM would like to have the contractor continue performing LOE work until the funds are exhausted. The CO has issued a contract mod to extend the PoP and allow the contractor to continue working - but will not add ceiling. My contractor EVM team is telling me that in order to plan the additional work, they need additional budget (ie, ceiling) against which to plan the additional work. Note the distinction - they don't need funding - they need ceiling.

As an example, say we are funded for, and plan $1M worth of LOE work over 12 months. As we set up our EV system, we budget $1M worth of work over 12 mos (BCWS) at a planned value of $1M (BCWP). At the end of 12 months, we've only spent $800k (ACWP = $800k). In EV terms, we have a cost variance of +200k - not a bad thing! We have measured costs against the $1M. Now, we want to spend an additional 200k. We have to plan that against an additional 200k, as we've already planned and measured against the original $1M. To do this, we need additional budget authority (again, ceiling) so that we will have planned $1.2M worth of work - which should come in at the funded amount of $1M. At the end, the BCWS = 1.2M, BCWP - 1.2M, and ACWP - 1M. Without the additional ceiling against which to plan the additional work, we will have a situation where we plan $0 work, schedule $0 work, but have $200k of cost - kind of tough to tell the taxpayer that we spent $200k on nothing.

My CO tells me that the FAR doesn't allow him to add ceiling when funding is sufficient. I say that he is adding scope (additional time on LOE work is scope, isn't it?) I say his options are to 1) add ceiling, but manage the contractor not to exceed funded amount, OR 2) close out the CA, de-obligate the remaining funds, and issue a new task/CA/whatever you want to call it, for the additional work the PM would like to have performed.

Am I wrong here? Certainly, I could be... but would welcome any comments that let me know where/how I'm wrong. I've looked for FAR clauses but can't find anything concrete. I know that EVMS guidelines (the 32 ANSI guidelines) definitely don't allow you to perform work that hasn't been properly planned. Thanks!!

In EV terms, we have a cost variance of +200k - not a bad thing! Hmmmm! 20% CPI... And who managed that project?

Link to comment
Share on other sites

But your example leaves out the Schedule part of the equation. Was your ACWP lower than expected because all the work wasn't done?? Need to look at your ACWS and EAC as well for the originally scheduled work.

No - in a level of effort, ACWS always equals BCWS - as you get credit for work accomplishment as time passes. Regardless, that's not what I'm getting at. The question really involves whether to add ceiling when adding additional work - or not adding ceiling. I'd really like to see a FAR reference that prohibits COs from adding ceiling when there is remaining funding - if such a clause exists.

Link to comment
Share on other sites

Guest Vern Edwards
Under one large task order with many CLINs and many Control Accounts (CAs), we have several CAs that have under-run their budget. This is a LOE on a CPFF contract. The PM would like to have the contractor continue performing LOE work until the funds are exhausted.

***

My CO tells me that the FAR doesn't allow him to add ceiling when funding is sufficient. I say that he is adding scope (additional time on LOE work is scope, isn't it?) I say his options are to 1) add ceiling, but manage the contractor not to exceed funded amount, OR 2) close out the CA, de-obligate the remaining funds, and issue a new task/CA/whatever you want to call it, for the additional work the PM would like to have performed.

Am I wrong here? Certainly, I could be... but would welcome any comments that let me know where/how I'm wrong. I've looked for FAR clauses but can't find anything concrete. I know that EVMS guidelines (the 32 ANSI guidelines) definitely don't allow you to perform work that hasn't been properly planned. Thanks!!

Okay, so the work (LOE) has been completed with a $200,000 underrun, and the $200,000 remains obligated on the contract. Ordinarily, the CO would de-obligate the excess funds and close out the contract, But the program manager wants to use that money to buy additional level of effort. Adding level of effort would be increasing the scope of the contract, for which you either need competition or a justification and approval for other than full and open competition.

If the CO did decide to add level of effort, he should modify the contract and document the file to show what happened. The easiest thing to do that would be to create a new CLIN for the new work, with its own estimated cost and fee, de-obligate the excess funds from the completed CLIN and re-obligate those funds against the new CLIN. Voila! The thing is done.

Apparently, EVM is making life more complicated than it needs to be, no surprise. What is this "ceiling" that you keep referring to and that you want the CO to increase from $1M to $1.2M? Ceiling is not a term usually associated with CPFF contracts, so I assume it is some EVM term, although I do not recognize it as such. Do you mean the estimate at completion (EAC)? Do you mean the contract estimated cost? Do you want to handle the new work LOE as an addition to the completed LOE? What sense would that make?

Link to comment
Share on other sites

Okay, so the work (LOE) has been completed with a $200,000 underrun, and the $200,000 remains obligated on the contract. Ordinarily, the CO would de-obligate the excess funds and close out the contract, But the program manager wants to use that money to buy additional level of effort. Adding level of effort would be increasing the scope of the contract, for which you either need competition or a justification and approval for other than full and open competition.

If the CO did decide to add level of effort, he should modify the contract and document the file to show what happened. The easiest thing to do that would be to create a new CLIN for the new work, with its own estimated cost and fee, de-obligate the excess funds from the completed CLIN and re-obligate those funds against the new CLIN. Voila! The thing is done.

Apparently, EVM is making life more complicated than it needs to be, no surprise. What is this "ceiling" that you keep referring to and that you want the CO to increase from $1M to $1.2M? Ceiling is not a term usually associated with CPFF contracts, so I assume it is some EVM term, although I do not recognize it as such. Do you mean the estimate at completion (EAC)? Do you mean the contract estimated cost? Do you want to handle the new work LOE as an addition to the completed LOE? What sense would that make?

Yes, I think he should de-ob the excess funds and create a new CLIN/TO for the additional LOE work. Instead, he simply increased the PoP and said continue charging. He has no knowledge or concern about EVM. Ceiling is a contracting term that basically means the highest amount that the government is obligated to pay. If a contractor continues to accrue costs above and beyond the contract "ceiling", then they are working at risk and the gov't is not obligated to pay. That is the main reason the CO doesn't want to increase ceiling - because IF the contractor were to incur 400k in costs to do 200k worth of work, the gov't would be obligated to pay. Still, the CO could manage the contractor to ensure that doesn't happen - plus the fact that we have data that shows they performed work at a lower than expected cost.

Link to comment
Share on other sites

If the CO did decide to add level of effort, he should modify the contract and document the file to show what happened. The easiest thing to do that would be to create a new CLIN for the new work, with its own estimated cost and fee, de-obligate the excess funds from the completed CLIN and re-obligate those funds against the new CLIN. Voila! The thing is done.

jhoward99,

That's your solution. Forget about using the "ceiling" term. You're just confusing things. Have the CO do a mod and use the excess funds to fund a new CLIN. From an EVM perspective can either treat the new CLIN separtely as completely new work or as an addition. In that case you are facing the situation you earlier described when you said:

we will have planned $1.2M worth of work - which should come in at the funded amount of $1M. At the end, the BCWS = 1.2M, BCWP - 1.2M, and ACWP - 1M.
Link to comment
Share on other sites

Guest Vern Edwards
Have the CO do a mod and use the excess funds to fund a new CLIN. From an EVM perspective can either treat the new CLIN separtely as completely new work or as an addition.

Ah, formerfed--within two minutes of each other. Great minds think alike. (Or maybe just old minds.)

Link to comment
Share on other sites

Guest Vern Edwards
Yes, I think he should de-ob the excess funds and create a new CLIN/TO for the additional LOE work. Instead, he simply increased the PoP and said continue charging. He has no knowledge or concern about EVM. Ceiling is a contracting term that basically means the highest amount that the government is obligated to pay. If a contractor continues to accrue costs above and beyond the contract "ceiling", then they are working at risk and the gov't is not obligated to pay. That is the main reason the CO doesn't want to increase ceiling - because IF the contractor were to incur 400k in costs to do 200k worth of work, the gov't would be obligated to pay. Still, the CO could manage the contractor to ensure that doesn't happen - plus the fact that we have data that shows they performed work at a lower than expected cost.

Ceiling [price] is used in time-and-materials and labor hour contracts. The term in cost-reimbursement contracts is either "estimated cost" or "total amount (or funds) allotted," depending on whether the contract is fully or incrementally funded. See FAR 52.232-20 and 52.232-22. Your use of "ceiling" will confuse people who know and use the proper terminology.

Extending the period of performance and telling the contractor to keep working was the wrong thing to do if the contractor had already delivered the original LOE.